A TENAGA
Pekerja L.01 OH 1.650 135,000 222,750.00
Tukang L.02 OH 0.275 150,000 41,250.00
Kepala tukang L.03 OH 0.028 175,000 4,900.00
Mandor L.04 OH 0.083 200,000 16,600.00
JUMLAH TENAGA KERJA 285,500.00
B BAHAN
Semen Portland kg 230.000 1,200.00 276,000.00
Pasir Beton kg 1920.000 357.89 687,157.89
Kerikil (Maks 30 mm) kg 1027.000 - -
Air Litter 200.000 50.00 10,000.00
JUMLAH HARGA BAHAN 973,157.89
C PERALATAN
I BAHAN PEREKAT
1 Semen Portland BP-01 kg 1,200
2 Air BP-05 Litter 50
VIII BATA, BATU, PASIR DAN BETON
1 Kerikil (Maks 30 mm) kg 358
2 Pasir Beton kg 328
DAFTAR HARGA SATUAN DASAR (HSD) UPAH
HARGA HARGA
No. POWER (HP) KAPASITAS ALAT SEWA ALAT PER JAM
(Rp.) (Rp.)