A.4.1.

1 HARGA SATUAN PEKERJAAN BETON


1. A.4.1.1.4. Membuat 1m3 Lantai Kerja Beton Mutu f'c = 7,4 Mpa
(SNI-Permen PUPR No 28 2016, Hal. 605)
Harga Jumlah
Satuan Harga
No Uraian Kode Satuan Koefisien (Rp) (Rp)

A TENAGA
Pekerja L.01 OH 1.650 135,000 222,750.00
Tukang L.02 OH 0.275 150,000 41,250.00
Kepala tukang L.03 OH 0.028 175,000 4,900.00
Mandor L.04 OH 0.083 200,000 16,600.00
JUMLAH TENAGA KERJA 285,500.00
B BAHAN
Semen Portland kg 230.000 1,200.00 276,000.00
Pasir Beton kg 1920.000 357.89 687,157.89
Kerikil (Maks 30 mm) kg 1027.000 - -
Air Litter 200.000 50.00 10,000.00
JUMLAH HARGA BAHAN 973,157.89
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 1,258,657.89


F Harga Satuan Pekerjaan (D+E) 1,258,657.89
DAFTAR HARGA SATUAN DASAR (HSD) BAHAN/ MATERIAL

NO. BAHAN Kode SAT. HARGA

I BAHAN PEREKAT
1 Semen Portland BP-01 kg 1,200
2 Air BP-05 Litter 50
VIII BATA, BATU, PASIR DAN BETON
1 Kerikil (Maks 30 mm) kg 358
2 Pasir Beton kg 328
DAFTAR HARGA SATUAN DASAR (HSD) UPAH

NO. URAIAN KODE SATUAN HARGA UPAH KET.


(Rp.)

1 Pekerja L.01 OH 135,000 1 OH = 7 OJ

2 Tukang L.02 OH 150,000 1 OH = 7 OJ

3 Kepala tukang L.03 OH 175,000 1 OH = 7 OJ

4 Mandor L.04 OH 200,000 1 OH = 7 OJ

5 Sopir L.06 OH 250,000 1 OH = 7 OJ

6 Kernet / pembantu sopir L.07 OH 100,000 1 OH = 7 OJ

7 Mekanik L.08 OH 200,000 1 OH = 7 OJ

8 Pembantu mekanik L.09 OH 100,000 1 OH = 7 OJ

9 Operator L.10 OH 350,000 1 OH = 7 OJ

10 Pembantu operator L.11 OH 200,000 1 OH = 7 OJ

11 Juru ukur L.12 OH 175,000 1 OH = 7 OJ

12 Pembantu juru ukur L.13 OH 85,000 1 OH = 7 OJ


DAFTAR HARGA SATUAN DASAR (HSD) SEWA PERALATAN

HARGA HARGA
No. POWER (HP) KAPASITAS ALAT SEWA ALAT PER JAM
(Rp.) (Rp.)

1 BAR BENDER 3 - 32,000,000.00 95,000.00


2 BAR CUTTER 3 - 40,000,000.00 100,000.00
3 CONCRETE PUMP 100 8 M3 1,950,000,000.00 705,000.00
4 CONCRETE VIBRATOR 5.5 25 - 8,250,000.00 100,000.00
5 CRANE 10-15 TON 173 12 Ton 4,350,000,000.00 1,450,000.00
6 DROP HAMMER 48 1 Ton 225,000,000.00 320,000.00
7 DUMP TRUCK 10 - 15 TON 190 10 Ton 1,200,000,000.00 795,000.00
8 DUMP TRUCK 3.5 TON 100 3.5 Ton 275,000,000.00 370,000.00
9 TRAILER 20 TON 175 20 Ton 2,000,000,000.00 900,000.00
10 WELDING SET 40 250 Amp 8,000,000.00 135,000.00