PERHITUNGAN BIAYA PEKERJAAN PONDASI PLAT SETEMPAT

HARGA SATUAN JUMLAH HARGA


NO URAIAN PEKERJAAN SATUAN VOLUME
(Rp.) (Rp.)

A PEKERJAAN PONDASI PLAT SETEMPAT (1 TITIK)


1 Pek. Galian Tanah Biasa M3 1.00 80,888.13 80,888.13
2 Pek. Pasir Urug Tbl. 5 Cm M3 0.05 184,707.25 9,235.36
3 Pek. Lantai Kerja Beton K-100 Tbl. 5 Cm M3 0.05 730,681.96 36,534.10
4 Pek. Pondasi Plat Setempat Uk. 80 x 80 x 25 Cm -
a. Bekisting Pondasi M2 1.32 218,135.45 287,938.79
b. Pembesian Kg 35.35 14,394.55 508,850.35
c. Beton Mutu K-200 M3 0.19 940,852.46 174,998.56
5 Pek. Urugan Tanah Kembali M3 0.71 59,426.25 42,430.34

JUMLAH A 1,140,875.63

B PEKERJAAN PONDASI PLAT SETEMPAT (27 TITIK)


1 Pek. Galian Tanah Biasa M3 27.00 80,888.13 2,183,979.38
2 Pek. Pasir Urug Tbl. 5 Cm M3 1.35 184,707.25 249,354.79
3 Pek. Lantai Kerja Beton K-100 Tbl. 5 Cm M3 1.35 730,681.96 986,420.65
4 Pek. Pondasi Plat Setempat Uk. 80 x 80 x 25 Cm
a. Bekisting Pondasi M2 35.64 218,135.45 7,774,347.44
b. Pembesian Kg 954.46 14,394.55 13,738,959.34
c. Beton Mutu K-200 M3 5.02 940,852.46 4,724,961.05
5 Pek. Urugan Tanah Kembali M3 19.28 59,426.25 1,145,619.25

JUMLAH B 30,803,641.88
ANALISA HARGA SATUAN PEKERJAAN Lamp.04 Permen PUPR No. 28 Tahun 2016 - Bidang Cipta Karya

A.2.3.1.1 Penggalian 1 m3 tanah biasa sedalam 1 meter


Harga Satuan
Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.7500 89,000.00 66,750.00
Mandor L.04 OH 0.0250 143,500.00 3,587.50
JUMLAH HARGA TENAGA 70,337.50
B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN

JUMLAH HARGA PERALATAN -


D Jumlah (A+B+C) 70,337.50
E Overhead & Profit 15% x D 10,550.63
F Harga Satuan Pekerjaan (D+E) 80,888.13

A.2.3.1.11 Pengurugan 1 m3 dengan pasir urug


Harga Satuan
Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.3000 89,000.00 26,700.00
Mandor L.04 OH 0.0100 143,500.00 1,435.00
JUMLAH HARGA TENAGA 28,135.00
B BAHAN
Pasir urug m3 1.2000 110,400.00 132,480.00
JUMLAH HARGA BAHAN 132,480.00
C PERALATAN

JUMLAH HARGA PERALATAN -


D Jumlah (A+B+C) 160,615.00
E Overhead & Profit 15% x D 24,092.25
F Harga Satuan Pekerjaan (D+E) 184,707.25

A.2.3.1.9 Pengurugan kembali 1 m3 galian tanah


Harga Satuan
Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.5000 89,000.00 44,500.00
Mandor L.04 OH 0.0500 143,500.00 7,175.00
JUMLAH HARGA TENAGA 51,675.00
B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN

JUMLAH HARGA PERALATAN -


D Jumlah (A+B+C) 51,675.00
E Overhead & Profit 15% x D 7,751.25
F Harga Satuan Pekerjaan (D+E) 59,426.25
A.4.1.1.4 Membuat 1 m3 lantai kerja beton mutu f’c = 7,4 MPa slump (3-6) cm, w/c = 0,87
Harga Satuan
Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.2000 89,000.00 106,800.00
Tukang batu L.02 OH 0.2000 124,950.00 24,990.00
Kepala tukang L.03 OH 0.0200 143,500.00 2,870.00
Mandor L.04 OH 0.0600 143,500.00 8,610.00
JUMLAH HARGA TENAGA 143,270.00
B BAHAN
Semen Portland Kg 230.00 1,202.00 276,460.00
Pasir beton Kg 893.00 113.93 101,738.21
Kerikil (Maks 30 mm) Kg 1,027.00 107.41 110,307.41
Air Ltr 200.00 18.00 3,600.00
JUMLAH HARGA BAHAN 492,105.62
C PERALATAN

JUMLAH HARGA PERALATAN -


D Jumlah (A+B+C) 635,375.62
E Overhead & Profit 15% x D 95,306.34
F Harga Satuan Pekerjaan (D+E) 730,681.96

A.4.1.1.6 Membuat 1 m3 beton mutu f’c = 16,9 MPa


Harga Satuan
Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 1.6500 89,000.00 146,850.00
Tukang batu L.02 OH 0.2750 124,950.00 34,361.25
Kepala tukang L.03 OH 0.0280 143,500.00 4,018.00
Mandor L.04 OH 0.0830 143,500.00 11,910.50
JUMLAH HARGA TENAGA 197,139.75
B BAHAN
Semen Portland Kg 352.00 1,202.00 423,104.00
Pasir beton Kg 731.00 113.93 83,281.79
Kerikil (Maks 30 mm) Kg 1,031.00 107.41 110,737.04
Air Ltr 215.00 18.00 3,870.00
JUMLAH HARGA BAHAN 620,992.82
C PERALATAN

JUMLAH HARGA PERALATAN -


D Jumlah (A+B+C) 818,132.57
E Overhead & Profit 15% x D 122,719.89
F Harga Satuan Pekerjaan (D+E) 940,852.46
Catatan : Bobot isi pasir = 1.400 kg/m3, Bobot isi kerikil = 1.350 kg/m3, Buckling factor pasir = 20%

A.4.1.1.17 Pembesian 10 kg dengan besi polos atau besi ulir


Harga Satuan
Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.0700 89,000.00 6,230.00
Tukang besi L.02 OH 0.0700 124,950.00 8,746.50
Kepala tukang L.03 OH 0.0070 143,500.00 1,004.50
Mandor L.04 OH 0.0040 143,500.00 574.00
JUMLAH HARGA TENAGA 16,555.00
B BAHAN
Besi beton (polos/ulir) Kg 10.5000 10,100.00 106,050.00
Kawat beton Kg 0.1500 17,100.00 2,565.00
JUMLAH HARGA BAHAN 108,615.00
C PERALATAN

JUMLAH HARGA PERALATAN -


D Jumlah (A+B+C) 125,170.00
E Overhead & Profit 15% x D 18,775.50
F Harga Satuan Pekerjaan (D+E) 143,945.50
A.4.1.1.20 (K3) Pemasangan 1 m2 bekisting untuk pondasi
Harga Satuan
Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp)
(Rp)
A TENAGA
Pekerja L.01 OH 0.5200 89,000.00 46,280.00
Tukang kayu L.02 OH 0.2600 124,950.00 32,487.00
Kepala tukang L.03 OH 0.0260 143,500.00 3,731.00
Mandor L.04 OH 0.0260 143,500.00 3,731.00
JUMLAH HARGA TENAGA 86,229.00
B BAHAN
Kayu kelas III m3 0.0400 2,426,600.00 97,064.00
Paku 5 – 10 cm Kg 0.3000 16,700.00 5,010.00
Minyak bekisting Ltr 0.1000 13,800.00 1,380.00
JUMLAH HARGA BAHAN 103,454.00
C PERALATAN

JUMLAH HARGA PERALATAN -


D Jumlah (A+B+C) 189,683.00
E Overhead & Profit 15% x D 28,452.45
F Harga Satuan Pekerjaan (D+E) 218,135.45
DAFTAR HARGA SATUAN UPAH DAN BAHAN

HARGA SATUAN
NO URAIAN KODE SATUAN
(Rp)

A. UPAH
1 Pekerja OH 89,000.00
2 Tukang OH 124,950.00
3 Kepala tukang OH 143,500.00
4 Mandor OH 143,500.00

B. BAHAN
1 Air Ltr 18.00
2 Pasir Beton (Kasar) m3 159,500.00
3 Pasir Urug m3 110,400.00
4 Kerikil (Maks 30 mm) m3 145,000.00
5 Semen / PC (50kg) Zak 60,100.00
6 Semen / PC (kg) Kg 1,202.00
7 Besi beton (polos/ulir) Kg 10,100.00
8 Kawat beton Kg 17,100.00
9 Kayu kelas III m3 2,426,600.00
10 Paku 5 – 10 cm Kg 16,700.00
11 Minyak bekisting Ltr 13,800.00
TABEL REKAP VOLUME PEKERJAAN PONDASI PLAT SETEMPAT
VOLUME
NO URAIAN SATUAN
1 TITIK 27 TITIK
1. Pek. Galian Tanah Biasa M3 1.00 27.00
2. Pek. Pasir Urug Tbl. 5 Cm M3 0.05 1.35
3. Pek. Lantai Kerja Beton K-100 Tbl. 5 Cm M3 0.05 1.35
4. Pek. Pondasi Plat Setempat Uk. 80 x 80 x 25 Cm
a. Bekisting Pondasi M2 1.32 35.64
b. Pembesian Kg 35.35 954.46
c. Beton Mutu K-200 M3 0.19 5.02
5. Pek. Urugan Tanah Kembali M3 0.71 19.28
PERHITUNGAN VOLUME PEKERJAAN

PROGRAM : -
KEGIATAN : -
PEKERJAAN : -
LOKASI : -
TAHUN : -

NO LINGKUP PEKERJAAN BESERTA GAMBAR SKET URAIAN PERHITUNGAN VOLUME PEKERJAAN VOLUME

II PEKERJAAN PONDASI PLAT SETEMPAT


Gambar Pondasi Plat Setempat : 1. Pek. Galian Tanah Biasa 27.00 M3
- Untuk 1 (Satu) Titik Pondasi
Luas penampang = 1.00 x 1.00 = 1.00 m2
Volume = 1.00 x 1.00 = 1.00 m3
- Untuk Seluruh Rencana Titik Pondasi
4 Ø 12 Volume = 27.00 x 1.00 = 27.00 m3
Ø 12 - 100

Ø 8 - 150 0.20 0.80 1.00


2. Pek. Pasir Urug Tbl. 5 Cm 1.35 M3
Ø 12 - 100 - Untuk 1 (Satu) Titik Pondasi
Luas penampang = 1.00 x 0.05 = 0.05 m2
Volume = 0.05 x 1.00 = 0.05 m3
0.20
- Untuk Seluruh Rencana Titik Pondasi
0.80
Volume = 27.00 x 0.05 = 1.35 m3
1.00

3. Pek. Lantai Kerja Beton K-100 Tbl. 5 Cm 1.35 M3


TAMPAK ATAS - Untuk 1 (Satu) Titik Pondasi
R
SKALA 1 : 25
Luas penampang = 1.00 x 0.05 = 0.05 m2
Volume = 0.05 x 1.00 = 0.05 m3
- Untuk Seluruh Rencana Titik Pondasi
Volume = 27.00 x 0.05 = 1.35 m3

Muka Tanah 4. Pek. Pondasi Plat Setempat Uk. 80 x 80 x 25 Cm


Tul. Pokok, 4 Ø 12 mm 4.a. Bekisting Pondasi 35.64 M2
Tul. Sengkang, Ø 8 - 150 mm - Untuk 1 (Satu) Titik Pondasi
0.65 Kolom Pondasi Uk. 20 x 20 x 65 cm
Beton K-200; Selimut Beton 2.5 cm Tapak pondasi = 3.20 x 0.25 = 0.80 m2
1.00 1.00
Urugan Tanah Kembali Kolom pondasi = 0.80 x 0.65 = 0.52 m2 +
Tul. Arah X, Ø 12 - 100 mm Jumlah = 1.32 m2
0.25 Tul. Arah Y, Ø 12 - 100 mm

0.05
Tapak Pondasi Uk. 80 x 80 x 25 cm - Untuk Seluruh Rencana Titik Pondasi
0.05 Beton K-200; Selimut Beton 3 cm
Bekisting pondasi = 27.00 x 1.32 = 35.64 m2
0.20 Lantai Kerja Beton K-100, Tbl. 5 cm
Pasir Urug Tbl. 5 cm
0.80 4.b. Pembesian 954.46 Kg
1.00
- Untuk 1 (Satu) Titik Pondasi
Tapak Pondasi
DETAIL POTONGAN - Tulangan Arah = Arah X Arah Y
R
SKALA 1 : 25 - Diameter tulangan (Ø) = 12.00 12.00 mm
- Panjang besi per-batang = 12.00 12.00 m
- Berat besi per-batang = 10.65 10.65 kg/btg
- Berat besi per-1 m' = 0.89 0.89 kg/m
- Selimut beton = 0.030 0.030 m
Tul. Sengkang Ø 8 - 150
- Lebar tulangan = 0.74 0.74 m
Tul. Pokok 4 Ø 12

- Tinggi tulangan = 0.19 0.19 m


0.15 - Pembengkokan 135° (6d) = 0.072 0.072 m
1.25 1.25
0.15
- Panjang 1 bh tulangan = 2.00 2.00 m
- Spasi tulangan = 0.10 0.10 m
Tul. Tapak Pondasi
- Jumlah tulangan = 8.00 8.00 bh
0.19 Ø 12 - 100 - Volume tulangan = 14.23 14.23 kg
0.20 0.20
- Total pembesian = 28.47 kg
0.74

Kolom Pondasi
DETAIL PENULANGAN - Tulangan Pokok
R
SKALA 1 : 25 - Diameter tulangan (Ø) = 12.00 mm
- Panjang besi per-batang = 12.00 m
- Berat besi per-batang = 10.65 kg/btg
Jumlah Rencana Pondasi : 27.00 Titik - Berat besi per-1 m' = 0.89 kg/m
- Jumlah tulangan pokok = 4.00 bh
- Panjang 1 bh tulangan pokok = 1.55 m
- Panjang total tulangan pokok = 6.20 m
- Volume tulangan = 5.50 kg

- Tulangan Sengkang / Begol


- Diameter tulangan (Ø) = 8.00 mm
- Panjang besi per-batang = 12.00 m
- Berat besi per-batang = 4.73 kg/btg
- Berat besi per-1 m' = 0.39 kg/m
- Selimut beton = 0.025 m
- Lebar tulangan = 0.15 m
- Tinggi tulangan = 0.15 m
- Pembengkokan 135° (6d) = 0.050 m
- Panjang 1 bh tulangan = 0.70 m
- Spasi tulangan = 0.15 m
- Jumlah tulangan = 5.00 bh
- Volume tulangan = 1.38 kg

Jumlah Pembesian Untuk 1 Titik Pondasi


Tapak pondasi = 28.47 kg
Kolom pondasi (Tul. Pokok) = 5.50 kg
Kolom pondasi (Tul. Sengkang) = 1.38 kg +
Jumlah = 35.35 kg
- Untuk Seluruh Rencana Titik Pondasi
Pembesian pondasi = 27.00 x 35.35 = 954.46 kg

4.c. Beton Mutu K-200 5.02 M3


- Untuk 1 (Satu) Titik Pondasi
Tapak pondasi = 0.80 x 0.80 x 0.25 = 0.16 m3
Kolom pondasi = 0.20 x 0.20 x 0.65 = 0.03 m3 +
Jumlah = 0.19 m3
- Untuk Seluruh Rencana Titik Pondasi
Cor Beton pondasi = 27.00 x 0.19 = 5.02 m3

5. Pek. Urugan Tanah Kembali 19.28 M3


- Untuk 1 (Satu) Titik Pondasi
Urugan 01 = 3.60 x 0.10 x 0.25 = 0.09 m3
Urugan 02 = 2.40 x 0.40 x 0.65 = 0.62 m3 +
Jumlah = 0.71 m3
- Untuk Seluruh Rencana Titik Pondasi
Urugan kembali = 27.00 x 0.71 = 19.28 m3