A. TENAGA
Pekerja OH 0.1500 100,000.00
Tukang cat OH 0.0950 100,000.00
Mandor OH 0.0080 120,000.00
JUMLAH TENAGA KERJA
B. BAHAN
MU-200 KG 2.0000 3,750.00
Peralatan(steger dll) LS 0.1000 21,500.00
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT
D. Jumlah (A + B + C)
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E)
JUMLAH HARGA
(Rp.)
15,000.00
9,500.00
960.00
25,460.00
7,500.00 150,000.00
2,150.00 3750
9,650.00
35,110.00
35,110.00