BIDANG INSFRASTRUKTUR
KOTA : Samarinda KEGIATAN : Semenisasi di Gang 1 B
KECAMATAN : Samarinda Ulu VOLUME : 52,5 m
KELURAHAN : Sidodadi LOKASI RT : 04
HARGA TOTAL
NO URAIAN SATUAN VOLUME
SATUAN BIAYA
a b c d e f= ( d x e )
UPAH PEKERJA
I 1) Tukang (1 org x 4 hari) HOK 4,00 170.000,00 680.000,00
2) Pekerja (2 org x 4 hari) HOK 8,00 130.000,00 1.040.000,00
SUB TOTAL UPAH PEKERJA (I) 1.720.000,00
BAHAN
1) Semen Zak 28,00 70.000,00 1.960.000,00
2) Pasir M3 2,97 198.000,00 588.015,45
II 3) Kerikil M3 3,77 346.500,00 1.305.871,88
4) Begisting M3 0,23 750.000,00 168.750,00
GG 1B
SEGMENT 1
SEGMENT 2
SEGMENT 3
SEGMENT 4
I
AJ
M
PROGRAM PEMBANGUNAN DAN PEMBERDAYAAN MASYARAKAT
OE
.S
PROBEBAYA
.H
GG
JL. MAWAR
KARA
AYANG
JL. BH
GG.
1B
ST
A
0+
05
2
LOKASI SEMENISASI
ST
A
0+
00
0
CL Beton Mutu Sedang k 175
Tb. 5 cm PEMERINTAH KOTA SAMARINDA
190
TYPICAL JALAN
SEGMENT 1
STA 0 + 000 S/D 0 + 020
CL Beton Mutu Sedang k 175
Tb. 5 cm
EKSISTING JALAN
250
TYPICAL JALAN
SEGMENT 2
STA 0 + 000 S/D 0 + 015
200
TYPICAL JALAN
SEGMENT 3 CL Beton Mutu Sedang k 175
Tb. 5 cm
STA 0 + 000 S/D 0 + 005
EKSISTING JALAN
120
TYPICAL JALAN
SEGMENT4
STA 0 + 000 S/D 0 + 012.5