Anda di halaman 1dari 113

Progress Claim No.

07
PROJECT : CADANGAN PEMBANGUNAN 2 BLOK MENARA PERDAGANGAN BERCAMPUR 46 TINGKAT (BLOK A) DAN 45 TINGKAT (BLOK B)
YANG MENGANDUNGI:

A. FASA 1, 1. MENARA BLOK A: ii. 28 TINGKAT PANGSAPURI SERVIS (418 UNIT) DI TINGKAT 9 HINGGA TINGKAT 36
Iii. 2 TINGKAT PANGSAPURI SERVIS (12 UNIT) DAN PANGSAPURI DUPLEX (9 UNIT) DI TINGKAT 37 DAN TINGKAT 38
iv. 2 TINGKAT PANGSAPURI SERVIS DUPLEX (15 UNIT) DI TINGKAT 39 DAN TINGKAT 40
v. 1 TINGKAT RUANG MEKANIKAL DI TINGKAT 41 vi. 1 TINGKAT RUANG PERNIAGAAN DI TINGKAT 42 (1 UNIT)
Vii.2 TINGKAT PENTHOUSE (1 UNIT) DI TINGKAT 43 DAN 44 BESERTA RUANG PERNIAGAAN (1 UNIT) DI TINGKAT 43 DI ATAS 9

TINGKAT PODIUM YANG MENGANDUNGI: i. 3 TINGKAT RUANG PERNIAGAAN (1 UNIT) DI TINGKAT BAWAH, TINGKAT 1 DAN
TINGKAT 2
ii. 6 TINGKAT TEMPAT LETAK KERETA DI TINGKAT 1A & 2A (MEZANIN) DAN DI TINGKAT 3 HINGGA TINGKAT 6
DENGAN 1 TINGKAT BESMEN TEMPAT LETAK KERETA DAN RUANG-RUANG M&E. 2. 1 UNIT RUMAH PENGAWAL DI TINGKAT BAWAH

B. FASA 2, 1. MENARA BLOK B: i. 1 TINGKAT YANG MENGANDUNGI SEBAHAGIAN RUANG KEMUDAHAN DI TINGKAT 8 ii. 30
TINGKAT PANGSAPURI SERVIS (448 UNIT) DI TINGKAT 9 HINGGA TINGKAT 38 Iii. 2 TINGKAT PANGSAPURI SERVIS DUPLEX (15
UNIT) DI TINGKAT 39 DAN TINGKAT 40 iv. 1 TINGKAT RUANG MEKANIKAL DI TINGKAT 41 v. 2 TINGKAT RUANG PERNIAGAAN (1
UNIT) DI TINGKAT 42 DAN TINGKAT 43 DI ATAS SEBAHAGIAN LOT P.T. 76, SEKSYEN 47, JALAN TUN RAZAK, KUALA LUMPUR
UNTUK TETUAN QUANTUM DENSITY SDN. BHD

CONTRACT AMOUNT : Original Contract = $7,576,965.00


Variation Order is =
Total ALL Project Contract is = $7,576,965.00

COMMENCEMENT DATE : August 2022

COMPLETION DATE : 12th January 2026

JOB REF NO :

PROGRESS CLAIM NO : 07

DATE : 13st June 2023

SUMMARY OF CLAIMS – Progress Claim for The Month of June 2023

ITEM DESCRIPTION AMOUNT (RM)

A : Work Done To-date - Original Contract $49,806.31

B : Work Done To-date – Materials On-Site $0.00

C : Work Done To-date – Variation Order $0.00

(A + B + C) $49,806.31

Less:
Total Invoice Submitted $31,747.32
Total Payment Certificate by Consultant/CHT International Sdn Bhd $42,415.82
Total Payment Certificate by Maincon/PEMBANGUNAN YUEN SENG SDN. BHD. $31,747.32

TOTAL CLAIM FOR PROGRESSIVE CLAIM NO. 07 $2,677.62


- June 2023

D : Previous Payment
Record of payments until June 2023 $28,543.97

Payment Cert (for Approval by Consultant/CHT $7,390.49


Payment Cert (for Approval by Maincon/PYS) $18,058.99
Total Unpaid Invoice $3,203.35
PROGRESS CLAIM SUMMARY
Project Title : TR2
Progress Claim No. 07
Contract Breakdown – Progress Claim / Work Done To-date EKTech Claims
Contract Amount Previous Current Total To-Date
No Description
Amount (RM) Percentage Amount (RM) Percentage Amount (RM) Percentage Amount (RM)
1 PRELIMINARIES 83,550.00 12% 9,901.02 1% 875.00 13% 10,776.02
2 CCTV (Residence) 260,233.00 4% 9,353.18 0% 507.78 4% 9,860.96

3 CCTV (Commercial) 114,947.00 3% 3,936.00 0.16% 187.20 4% 4,123.20


4 Card Access (Residence) 679,017.00 1% 3,690.00 0% 820.00 1% 4,510.00
5 Card Access (Commercial) 95,273.00 0% 324.72 0% 59.04 0% 383.76

6 Barrier Gate (Residence) 44,597.00 0% - 0% - 0% -


7 Barrier Gate (Commercial) 141,090.00 0% - 0% - 0% -
8 Public Address (Residence) 463,498.00 3% 15,727.04 0% - 3% 15,727.04

9 Public Address (Commercial) 239,104.00 2% 4,137.93 0.09% 205.08 2% 4,343.01

10 Audio Visual (Residence) 20,836.00 0% - 0% - 0% -


11 Audio Visual (Commercial) 408,485.00 0% - 0% - 0% -

12 SMATV (Residence) 359,647.00 0% - 0% - 0% -


13 FTTH (Residence) 417,473.00 0% - 0% - 0% -
14 FTTH (Commercial) 185,645.00 0% 58.80 0% 23.52 0% 82.32
15 Smart Home & Digital Door Lock 4,063,570.00 0% - 0% - 0% -

FINAL TOTAL 7,576,965.00 1% 47,128.69 0% 2,677.62 1% 49,806.31


Project Title : TR2
Progress Claim No. 07
Contract Breakdown – Progress Claim / Work Done To-date EKTech Claims
Contract Amount Previous Current Total To-Date
No Description
Qty Rate Amount Percentage Amount (RM) Percentage Amount (RM) Percentage Amount (RM)

PRELIMINARIES
1.1 Bank Guarantee 1 1,250.00 1,250.00 38% 475.00 10% 125.00 48% 600.00

1.2 Mobilisation 1 5,000.00 5,000.00 15% 750.00 0% - 15% 750.00

1.3 Shop Drawing, Documentations, Catalogues and Sample Submission. 1 12,000.00 12,000.00 43% 5,160.00 0% - 43% 5,160.00

Painting with dark color for exposed services (trunking / cable tray) at
1.4 1 16,000.00 16,000.00 0% 0% - 0% -
typical floor corridor including brackets / support (L9 to L40).

Painting with dark color for exposed services (trunking / cable tray) at
1.5 1 7,500.00 7,500.00 0% - 0% - 0% -
mall corridor including brackets / support (P1 to P2.).

1.6 Cost full time Site Supervisor for the duration of the works. 1 12,500.00 12,500.00 22% 2,766.02 5% 625.00 27% 3,391.02

Site co-ordination with Main Contractor & other trades Sub-


1.7 1 2,500.00 2,500.00 30% 750.00 5% 125.00 35% 875.00
Contractors.

Cost of Maintenance of Equipment during the 28 months Defects


1.8 1 12,000.00 12,000.00 0% - 0% - 0% -
Liability Period.

Liasion with local authorities in obtaining relevant approval and ensure


1.9 1 5,000.00 5,000.00 0% - 0% - 0% -
the works compliance with their requirement and specification.

Fire stop barriers at all building penetrations and all floor slab
2.0 structural riser openings of approved make and Jabatan Bomba 1 4,800.00 4,800.00 0% - 0% - 0% -
approval.

As-built Drawings and Maintenance & Operation Manuals and training


2.1 1 5,000.00 5,000.00 0% - 0% - 0% -
(6 sets of A1 size and 6 sets of soft copies in CD).

2.2 Any other items


I)
ii)
iii)

83,550.00 9,901.02 875.00 10,776.02


Project Title : TR2
Progress Claim No. 07
Contract Breakdown – Progress Claim / Work Done To-date EKTech Claims
Contract Amount Previous Current Total To-Date
No Description
Qty Rate Amount Percentage Amount (RM) Percentage Amount (RM) Percentage Amount (RM)
A Service Apartment
2.0 CLOSED CIRCUIT TELEVISION (CCTV) SYSTEM

To supply, deliver, install, testing and commissioning the following


complete CCTV system as specified in the drawings and specifications.

4 Megapixel WER day/night Fided Dome Network cameras. c/w


2.1 Vandalproof Housing & Bracket, 12V DC/PoE power support (for lift 12 353.00 4,236.00 0% - 0% - 0% -
cars).

4 Megapixel WDR day/night HD Fixed Dome Network IR cameras. c/w


2.2 74 353.00 26,122.00 0% - 0% - 0% -
Indoor Housing & Bracket, 12V DC/PoE power support.

4 Megapixel WDR day/night HD Fixed Bullet Network IR cameras. c/w


2.3 66 350.00 23,100.00 0% - 0% - 0% -
Housing & Bracket, 12V DC/PoE power support, IP67.

64 Channel Network Video Recorder, 16 SATA interface c/w 30 days


2.4 1 45,334.00 45,334.00 0% - 0% - 0% -
harddisk storage, with motion detection funcion/settings.

Video Management Software with client/server based video


2.5 management system, alarm handling with alarm priorities selectable 1 4,320.00 4,320.00 0% - 0% - 0% -
user, Mobile video client for live and playback.

Workstation PC and 24” LED Monitor for Management Software with


2.6 minimum Windows 10 Ultimete Edition 64 bit, Intel Core i7 c/w 1TB 3 8,169.00 24,507.00 0% - 0% - 0% -
harddisk (at L8 management office, GH main fire control room)

Digital Surveillance Closed Circuit Television Monitoring system 42”


2.7 4 1,643.00 6,572.00 0% - 0% - 0% -
Full HD LED monitor c/w wall mount kit and all necessary accessories.

UPS for main ethernet switch, NVR and workstation PC c/w all
2.8 necessary accessories with duration 15 minute (at L8 management 1 840.00 840.00 0% - 0% - 0% -
office, GF main fire control room).

Data and AC mains surge arrestor for CCTV system at L8 management


2.9 1 969.00 969.00 0% - 0% - 0% -
office.

Fiber optic cable for cameras video signal cabling works run in
2.10 concealed uPVC or exposed G.I conduit/trunking clw all necessary 1 14,746.00 14,746.00 4% 589.84 0% - 4% 589.84
accessories.

Page 4
2.11 HDMI cabling between CCTV Monitors and Workstation. 1 378.00 378.00 0% - 0% - 0% -

UTP Cat6 data cable run in concealed uPVC or exposed G.I


2.12 1 50,778.00 50,778.00 17% 8,632.26 1% 507.78 18% 9,140.04
conduit/trunking (from Network Switch to Cameras).

UTP Cat6 data cable run in concealed uPVC or exposed G.I


conduit/trunking (from Network Switch to transciver at Lift Motor
2.13 Room + transciver to Camera in lift cars). 1 3,277.00 3,277.00 4% 131.08 0% - 4% 131.08
(from Network Switch to CCTV transciver at L7 + transciver to Camera
in lift cars).

Lift car camera transciver c/w power supply unit and other necessary
2.14 1 3,651.00 3,651.00 0% - 0% - 0% -
accessories.

Main Ethernet Switch (L3 Core Switch) c/w SFP module and necessary
2.15 1 4,892.00 4,892.00 0% - 0% - 0% -
accessories.

12 port PoE Ethernet Switch c/w SFP module and necessary


2.16 1 5,770.00 5,770.00 0% - 0% - 0% -
accessories.

24 port PoE Ethernet Switch c/w SFP module and necessary


2.17 8 1,385.00 11,080.00 0% - 0% - 0% -
accessories.

2.18 wall mounted 6U Equipment Rack c/w necessary accessories. 13 300.00 3,900.00 0% - 0% - 0% -

UPS for above Ethernet Switch in riser c/w necessary accessories with
2.19 13 430.00 5,590.00 0% - 0% - 0% -
duration 15 minute.

Testing & Commissioning c/w on-site training and Manufacturer’s


2.20 1 4,616.00 4,616.00 0% - 0% - 0% -
Support Letter.

Any other works not specifically mentioned but necessary to complete


2.21
the installation.
a) 42U equipment rack for CCTV System 1 2,419.00 2,419.00 0% - 0% - 0% -
b) 8 port PoE switch for CCTV system at Fire Control Room c/w 6U
1 702.00 702.00 0% - 0% - 0% -
rack.
c) System cabling using fiber optic cable c/w splicing and pigtails for
1 434.00 434.00 0% - 0% - 0% -
PoE switch in Fire Control Room.
d) Custom Made Table for CCTV system at Level 8 Management Office
2 6,000.00 12,000.00 0% - 0% - 0% -
and Ground floor Main Fire Control Room.

260,233.00 9,353.18 507.78 9,860.96

Page 5
Project Title : TR2
Progress Claim No. 07
Contract Breakdown – Progress Claim / Work Done To-date EKTech Claims
Contract Amount Previous Current Total To-Date
No Description
Qty Rate Amount Percentage Amount (RM) Percentage Amount (RM) Percentage Amount (RM)
B Commercial
2.0 CLOSED CIRCUIT TELEVISION (CCTV) SYSTEM

To supply, deliver, install, testing and commissioning the following


complete CCTV system as specified in the drawings and specifications.

4 Megapixel WER day/night Fided Dome Network cameras. c/w


2.1 Vandalproof Housing & Bracket, 12V DC/PoE power support (for lift 2 353.00 706.00 0% - 0% - 0% -
cars).

4 Megapixel WDR day/night HD Fixed Dome Network IR cameras. c/w


2.2 52 353.00 18,356.00 0% - 0% - 0% -
Indoor Housing & Bracket, 12V DC/PoE power support.

4 Megapixel WDR day/night HD Fixed Bullet Network IR cameras. c/w


2.3 2 350.00 700.00 0% - 0% - 0% -
Housing & Bracket, 12V DC/PoE power support, IP67.

64 Channel Network Video Recorder, 16 SATA interface c/w 30 days


2.4 1 15,111.00 15,111.00 0% - 0% - 0% -
harddisk storage, with motion detection funcion/settings.

Video Management Software with client/server based video


2.5 management system, alarm handling with alarm priorities selectable 1 4,320.00 4,320.00 0% - 0% - 0% -
user, Mobile video client for live and playback.

Workstation PC and 24” LED Monitor for Management Software with


2.6 minimum Windows 10 Ultimete Edition 64 bit, Intel Core i7 c/w 1TB 2 8,169.00 16,338.00 0% - 0% - 0% -
harddisk (at L8 management office, GH main fire control room)

2.7 24” LED Monitor 1 600.00 600.00 0% - 0% - 0% -

Digital Surveillance Closed Circuit Television Monitoring system 42”


2.8 2 1,643.00 3,286.00 0% - 0% - 0% -
Full HD LED monitor c/w wall mount kit and all necessary accessories.

Page 6
Project Title : TR2
Progress Claim No. 07
Contract Breakdown – Progress Claim / Work Done To-date EKTech Claims
Contract Amount Previous Current Total To-Date
No Description
Qty Rate Amount Percentage Amount (RM) Percentage Amount (RM) Percentage Amount (RM)
UPS for main ethernet switch, NVR and workstation PC c/w all
2.9 necessary accessories with duration 15 minute (at L8 management 1 840.00 840.00 0% - 0% - 0% -
office, GF main fire control room).

Data and AC mains surge arrestor for CCTV system at L8 management


2.10 1 969.00 969.00 0% - 0% - 0% -
office.

Fiber optic cable for cameras video signal cabling works run in
2.11 concealed uPVC or exposed G.I conduit/trunking clw all necessary 1 7,080.00 7,080.00 8% 566.40 0% - 8% 566.40
accessories.

2.12 HDMI cabling between CCTV Monitors and Workstation. 1 171.00 171.00 0% - 0% - 0% -

UTP Cat6 data cable run in concealed uPVC or exposed G.I


2.13 1 18,720.00 18,720.00 18% 3,369.60 1% 187.20 19% 3,556.80
conduit/trunking (from Network Switch to Cameras).

UTP Cat6 data cable run in concealed uPVC or exposed G.I


2.14 conduit/trunking (from Network Switch to CCTV transciver at Lift 1 674.00 674.00 0% - 0% - 0% -
Motor Room + transciver to Camera in lift cars).

Lift car camera transciver c/w power supply unit and other necessary
2.15 1 2,908.00 2,908.00 0% - 0% - 0% -
accessories.

Main Ethernet Switch (L3 Core Switch) c/w SFP module and necessary
2.16 1 3,637.00 3,637.00 0% - 0% - 0% -
accessories.

24 port PoE Ethernet Switch c/w SFP module and necessary


2.17 4 1,154.00 4,616.00 0% - 0% - 0% -
accessories.

2.18 wall mounted 6U Equipment Rack c/w necessary accessories. 4 300.00 1,200.00 0% - 0% - 0% -

UPS for above Ethernet Switch in riser c/w necessary accessories with
2.19 4 420.00 1,680.00 0% - 0% - 0% -
duration 15 minute.

Page 7
Project Title : TR2
Progress Claim No. 07
Contract Breakdown – Progress Claim / Work Done To-date EKTech Claims
Contract Amount Previous Current Total To-Date
No Description
Qty Rate Amount Percentage Amount (RM) Percentage Amount (RM) Percentage Amount (RM)
Testing & Commissioning c/w on-site training and Manufacturer’s
2.20 1 4,616.00 4,616.00 0% - 0% - 0% -
Support Letter.

Any other works not specifically mentioned but necessary to complete


2.21
the installation.
a) 42U equipment rack for CCTV System 1 2,419.00 2,419.00 0% - 0% - 0% -
b) Custom Made Table for CCTV system at Level 8 Management Office
1 6,000.00 6,000.00 0% - 0% - 0% -
and Ground floor Main Fire Control Room.

114,947.00 3,936.00 187.20 4,123.20

Page 8
4. BLOCK A - HD SMATV SYSTEM INSTALLATION (FASA 1)

Project Title : TR2


Progress Claim No. 07
Contract Breakdown – Progress Claim / Work Done To-date EKTech Claims
Contract Amount Previous Current Total To-Date
No Description
Qty Rate Amount Percentage Amount (RM) Percentage Amount (RM) Percentage Amount (RM)
A SERVICE APARTMENT
3.0 CARD ACCESS SYSTEM

To supply, deliver, install, testing and commissioning the following


complete card access system as specified in the drawings and
specifications.
DCSS LNB to MEASAT Std. Complete with bracket stand

For List Access Control


3.1 Network Lift Access Controller c/w I/O boards and necessary 4 14,408.00 57,632.00 0% - 0% - 0% -
accessories.

Weigand Converter (to convert RS485) at lift car top c/w all necessary
3.2 14 432.00 6,048.00 0% - 0% - 0% -
accessories.

Mobile access reader/bluetooth reader (able to used as contactless


3.3 Smart Card Reader) without keypad, LCD and biometric sensor c/w 14 500.00 7,000.00 0% - 0% - 0% -
witing works (for lift car only).
connections

3.4 QR Code reader c/w wiring works (for lift car only) 14 460.00 6,440.00 0% - 0% - 0% -

UTP Cat6 data cable (from Access Switch to lift access controller) run
3.5 in concealed uPVC or exposed G.I conduit/trunking c/w all necessary 4 378.00 1,512.00 0% - 0% - 0% -
accessories.
Connectors and lead cable fittings

Active Network Door Controller with 2 nos Readers interface, input &
3.6 125 1,012.00 126,500.00 0% - 0% - 0% -
output channels, and power supply unit with 12VDC backup battery.

Mobile access reader/bluetooth reader (able to used as contactless


3.7 Smart Card Reader) without keypad, LCD and biometric sensor c/w 125 500.00 62,500.00 0% - 0% - 0% -
witing works (for lift car only).

Page 9
4. BLOCK A - HD SMATV SYSTEM INSTALLATION (FASA 1)

Project Title : TR2


Progress Claim No. 07
Contract Breakdown – Progress Claim / Work Done To-date EKTech Claims
Contract Amount Previous Current Total To-Date
No Description
Qty Rate Amount Percentage Amount (RM) Percentage Amount (RM) Percentage Amount (RM)

3.8 QR Code reader c/w wiring works. 22 460.00 10,120.00 0% - 0% - 0% -

3.9 Facial recognition reader c/w wiring works. 31 1,696.00 52,576.00 0% - 0% - 0% -

3.10 Facial recognition reader c/w wiring works. 31 360.00 11,160.00 0% - 0% - 0% -

3.11 600lbs electromagnet lock c/w bracket and wiring works. 210 105.00 22,050.00 0% - 0% - 0% -

3.12 Magnetic Door Sensor c/w wiring works. 214 6.00 1,284.00 0% - 0% - 0% -

3.13 Emergency Breakglass Unit c/w wiring works. 125 17.00 2,125.00 0% - 0% - 0% -

3.14 Contactless “Request to Exit” Button c/w wiring works. 94 46.00 4,324.00 0% - 0% - 0% -

3.15 Override Key Switch c/w wiring works. 125 36.00 4,500.00 0% - 0% - 0% -

UTP Cat6 data cable (from Access Switch to Door controller) run in
3.16 concealed uPVC or exposed G.I conduit/trunking c/w all necessary 125 328.00 41,000.00 9% 3,690.00 2% 820.00 11% 4,510.00
accessories.

Panic button (red color) c/w 2 way communication with fire control
3.17 4 1,836.00 7,344.00 0% - 0% - 0% -
room, siren unit, stroble light c/w wiring works.

OKU type Panic button c/w pull cord, siren unit, strobe light c/w
3.18 1 1,662.00 1,662.00 0% - 0% - 0% -
wiring.

UTP Cat6 data cable (from Access Switch to Panic Button) run in
3.19 concealed uPVC or exposed G.I conduit/trunking c/w all necessary 5 672.00 3,360.00 0% - 0% - 0% -
accessories.

Page 10
4. BLOCK A - HD SMATV SYSTEM INSTALLATION (FASA 1)

Project Title : TR2


Progress Claim No. 07
Contract Breakdown – Progress Claim / Work Done To-date EKTech Claims
Contract Amount Previous Current Total To-Date
No Description
Qty Rate Amount Percentage Amount (RM) Percentage Amount (RM) Percentage Amount (RM)
2C indoor multimode fiber optics cable (from main access switch to
3.20 access switch) run in concealed uPVC or exposed G.I conduit/trunking 1 18,000.00 18,000.00 0% - 0% - 0% -
c/w all necessary accessories.

3.21 Main Access Switch 1 4,320.00 4,320.00 0% - 0% - 0% -

3.22 12 port Access Switch 5 1,283.00 6,415.00 0% - 0% - 0% -

3.23 24 port Access Switch 6 1,440.00 8,640.00 0% - 0% - 0% -

3.24 wall mounted 6U Equipment Rack c/w necessary accessories. 1 360.00 360.00 0% - 0% - 0% -

Workstation PC and 24” LED Monitor for Access Control system


3.25 Software with minimum Windows 10 Ultimete Edition 64 bit, Intel Core 1 15,995.00 15,995.00 0% - 0% - 0% -
i7-6700k c/w 12TB harddisk (at L8 management office.)

3.26 card enrolment reader c/w wiring works and all necessary accessories. 1 840.00 840.00 0% - 0% - 0% -

Workstation PC and 24” LED Monitor for Access Control system


(repeater) Software with minimum Windows 10 Ultimete Edition 64
3.27 1 7,860.00 7,860.00 0% - 0% - 0% -
bit, Intel Core i7-6700k c/w 12TB harddisk (for Main Fire Control Room
at Ground Floor)

3.28 Intergration with 3rd party property management apps. 1 15,240.00 15,240.00 0% - 0% - 0% -

UPS for above workstations c/w all necessary accessories with


3.29 3 420.00 1,260.00 0% - 0% - 0% -
duration 15 minute.

UTP Cat6 data cable (from Access Switch to Workstation) run in


3.30 concealed uPVC or exposed G.I conduit/trunking c/w all necessary 2 372.00 744.00 0% - 0% - 0% -
accessories.

3.31 Access Card (Desfire EV 1 or iClass Seos or equivalent). 2020 20.00 40,400.00 0% - 0% - 0% -

Page 11
4. BLOCK A - HD SMATV SYSTEM INSTALLATION (FASA 1)

Project Title : TR2


Progress Claim No. 07
Contract Breakdown – Progress Claim / Work Done To-date EKTech Claims
Contract Amount Previous Current Total To-Date
No Description
Qty Rate Amount Percentage Amount (RM) Percentage Amount (RM) Percentage Amount (RM)

3.32 Installation, Programming and Configuration works. 1 31,200.00 31,200.00 0% - 0% - 0% -

Testing & Commissioning c/w on-site training and Manufacturer’s


3.33 1 930.00 930.00 0% - 0% - 0% -
Support Letter.

Any other works not specifically mentooned but necessary to complete


3.33
the installation.

a) credential (or license) for mobile access reader (or bluetooth


reader) where 1 credential allow for 5 device; included subscription 918 102.00 93,636.00 0% - 0% - 0% -
fee during the DLP.
b) 2020 2.00 4,040.00 0% - 0% - 0% -

679,017.00 3,690.00 820.00 4,510.00

Page 12
5. BLOCK A - IP CCTV + CARD ACCESS CONTROL SYSTEM INSTALLATION (FASA 1)

Project Title : TR2


Progress Claim No. 07
Contract Breakdown – Progress Claim / Work Done To-date EKTech Claims
Contract Amount Previous Current Total To-Date
No Description
Qty Rate Amount Percentage Amount (RM) Percentage Amount (RM) Percentage Amount (RM)
B COMMERCIAL
3.0 ACCESS CONTROL SYSTEM

To supply, deliver, install, testing and commissioning the following


complete card access system as specified in the drawings and
specifications.
DCSS LNB to MEASAT Std. Complete with bracket stand

For List Access Control


3.1 Network Lift Access Controller c/w I/O boards and necessary 2 12,169.00 24,338.00 0% - 0% - 0% -
accessories.

Weigand Converter (to convert RS485) at lift car top c/w all necessary
3.2 6 432.00 2,592.00 0% - 0% - 0% -
accessories.

Mobile access reader/bluetooth reader (able to used as contactless


3.3 Smart Card Reader) without keypad, LCD and biometric sensor c/w 6 500.00 3,000.00 0% - 0% - 0% -
witing works (for lift car only).
connections

UTP Cat6 data cable (from Access Switch to lift access controller) run
3.4 in concealed uPVC or exposed G.I conduit/trunking c/w all necessary 2 378.00 756.00 0% - 0% - 0% -
accessories.
Connectors and lead cable fittings

For Door Access Control


3.5 Active Network Door Controller with 2 nos Readers interface, input & 9 1,012.00 9,108.00 0% - 0% - 0% -
output channels, and power supply unit with 12VDC backup battery.

Mobile access reader/bluetooth reader (able to used as contactless


3.6 Smart Card Reader) without keypad, LCD and biometric sensor c/w 9 500.00 4,500.00 0% - 0% - 0% -
witing works (for lift car only).

Page 13
5. BLOCK A - IP CCTV + CARD ACCESS CONTROL SYSTEM INSTALLATION (FASA 1)

Project Title : TR2


Progress Claim No. 07
Contract Breakdown – Progress Claim / Work Done To-date EKTech Claims
Contract Amount Previous Current Total To-Date
No Description
Qty Rate Amount Percentage Amount (RM) Percentage Amount (RM) Percentage Amount (RM)
3.7 600lbs electromagnet lock c/w bracket and wiring works. 12 104.00 1,248.00 0% - 0% - 0% -

3.8 Magnetic Door Sensor c/w wiring works. 12 6.00 72.00 0% - 0% - 0% -

3.9 Emergency Breakglass Unit c/w wiring works. 9 17.00 153.00 0% - 0% - 0% -

3.10 Contactless “Request to Exit” Button c/w wiring works. 9 144.00 1,296.00 0% - 0% - 0% -

3.11 Override Key Switch c/w wiring works. 9 36.00 324.00 0% - 0% - 0% -

UTP Cat6 data cable (from Access Switch to Door controller) run in
3.12 concealed uPVC or exposed G.I conduit/trunking c/w all necessary 9 328.00 2,952.00 11% 324.72 2% 59.04 13% 383.76
accessories.

OKU type Panic button c/w pull cord, siren unit, strobe light c/w
3.13 5 1,366.00 6,830.00 0% - 0% - 0% -
wiring.

UTP Cat6 data cable (from Access Switch to Panic Button) run in
3.14 concealed uPVC or exposed G.I conduit/trunking c/w all necessary 5 372.00 1,860.00 0% - 0% - 0% -
accessories.

2C indoor multimode fiber optics cable (from main access switch to


3.15 access switch) run in concealed uPVC or exposed G.I conduit/trunking 1 7,200.00 7,200.00 0% - 0% - 0% -
c/w all necessary accessories.

3.16 Main Access Switch 1 4,320.00 4,320.00 0% - 0% - 0% -

3.17 12 port Access Switch 3 1,283.00 3,849.00 0% - 0% - 0% -

Workstation PC and 24” LED Monitor for Access Control system


Software with minimum Windows 10 Ultimete Edition 64 bit, Intel Core
3.18 1 8,890.00 8,890.00 0% - 0% - 0% -
i7-6700k c/w 12TB harddisk (for Sub Fire Control Room @ Ground
Floor).

Page 14
5. BLOCK A - IP CCTV + CARD ACCESS CONTROL SYSTEM INSTALLATION (FASA 1)

Project Title : TR2


Progress Claim No. 07
Contract Breakdown – Progress Claim / Work Done To-date EKTech Claims
Contract Amount Previous Current Total To-Date
No Description
Qty Rate Amount Percentage Amount (RM) Percentage Amount (RM) Percentage Amount (RM)

3.19 card enrolment reader c/w wiring works and all necessary accessories. 1 840.00 840.00 0% - 0% - 0% -

UPS for above workstations c/w all necessary accessories with


3.20 1 420.00 420.00 0% - 0% - 0% -
duration 15 minute.

3.21 Access Card (Desfire EV 1 or iClass Seos or equivalent). 100 23.00 2,300.00 0% - 0% - 0% -

3.22 Installation, Programming and Configuration works. 1 5,965.00 5,965.00 0% - 0% - 0% -

Testing & Commissioning c/w on-site training and Manufacturer’s


3.23 1 240.00 240.00 0% - 0% - 0% -
Support Letter.

Any other works not specifically mentooned but necessary to complete


3.24
the installation.
a) credential (or license) for the mobile accress reader (or bluetooth
reader) where 1 credential allow for 5 device; included subscription
fee during the DLP; [subscription fee : RM_________ per year per 20 101.00 2,020.00 0% - 0% - 0% -
credential]

b) sticker (building name / logo) on the access card 100 2.00 200.00 0% - 0% - 0% -
c) 0 0.00

95,273.00 324.72 59.04 383.76

Page 15
6. BLOCK B - TELECOM DISTRIBUTION INSTALLATION (FASA 1)

Project Title : TR2


Progress Claim No. 07
Contract Breakdown – Progress Claim / Work Done To-date EKTech Claims
Contract Amount Previous Current Total To-Date
No Description
Qty Rate Amount Percentage Amount (RM) Percentage Amount (RM) Percentage Amount (RM)

A SERVICE APARTMENT
4.0 VEHICLE ACCESS SYSTEM

Barrier gate c/w enclosure, 3m folding arm, open/close time 1.8sec.


4.1 4 2,700.00 10,800.00 0% - 0% - 0% -
LED indicator light and necessary accessories.

Safety loop and open loop for passenger car c/w wiring in concealed
4.2 4 600.00 2,400.00 0% - 0% - 0% -
GI and necesasry accessories

Safety loop and open loop for motorcycle c/w wiring in concealed GI
4.3 4 600.00 2,400.00 0% - 0% - 0% -
and necesasry accessories

4.4 Vehicle access software 1 4,199.00 4,199.00 0% - 0% - 0% -

4.5 Push button 4 74.00 296.00 0% - 0% - 0% -

4.6 Wiring work


a. Cat6 cable in concealed pvc conduit 1 1,385.00 1,385.00 0% - 0% - 0% -
b. Jelly filled Cat6 cable in concealed pvc conduit 1 2,308.00 2,308.00 0% - 0% - 0% -

4.7 Controller for vehicle access system 1 5,304.00 5,304.00 0% - 0% - 0% -

Mobile access reader/bluetooth reader (able to use as contactless


4.8 smart card reader) without keypad, LCD and biometric sensor c/w 4 646.00 2,584.00 0% - 0% - 0% -
wiring works.

4.9 QR code reader c/w wiring works 2 535.00 1,070.00 0% - 0% - 0% -

4.10 Epoxy coated pole/stand for readers & cctv 8 465.00 3,720.00 0% - 0% - 0% -

4.11 Data and ac surge arrestor 1 947.00 947.00 0% - 0% - 0% -

Page 16
6. BLOCK B - TELECOM DISTRIBUTION INSTALLATION (FASA 1)

Project Title : TR2


Progress Claim No. 07
Contract Breakdown – Progress Claim / Work Done To-date EKTech Claims
Contract Amount Previous Current Total To-Date
No Description
Qty Rate Amount Percentage Amount (RM) Percentage Amount (RM) Percentage Amount (RM)
4.12 Installtion, programming and configuration works 1 5,538.00 5,538.00 0% - 0% - 0% -

Testing & commissioning c/w on-site training and manufacturer’s


4.13 1 1,646.00 1,646.00 0% - 0% - 0% -
support letter.

44,597.00 - - -

Page 17
7. BLOCK B - HD SMATV SYSTEM INSTALLATION (FASA 1)

Project Title : TR2


Progress Claim No. 07
Contract Breakdown – Progress Claim / Work Done To-date EKTech Claims
Contract Amount Previous Current Total To-Date
No Description
Qty Rate Amount Percentage Amount (RM) Percentage Amount (RM) Percentage Amount (RM)

B COMMERCIAL
4.0 VEHICLE ACCESS SYSTEM

Entry station c/w short range reader for season parking, intercom, t&g
4.1 1 8,970.00 8,970.00 0% - 0% - 0% -
payment, credit card payment, led display and necessary accessories

Exit station c/w short range reader for season parking, intercom, t&g
4.2 1 8,970.00 8,970.00 0% - 0% - 0% -
payment, credit card payment, led display and necessary accessories

Barrier gate c/w enclosure, 3m folding arm, open/close time 1.5sec.


4.3 2 13,800.00 27,600.00 0% - 0% - 0% -
LED indicator light and necessary accessories.

Safety loop and open loop for passenger car c/w wiring in concealed
4.4 2 1,150.00 2,300.00 0% - 0% - 0% -
GI and necesasry accessories

Safety loop and open loop for motorcycle c/w wiring in concealed GI
4.5 2 580.00 1,160.00 0% - 0% - 0% -
and necesasry accessories

4.6 License plate recognition (LPR) camera (1 for in and 1 for out) 2 14,380.00 28,760.00 0% - 0% - 0% -

Local server, software and all necessary accessories for LPR system
4.7 1 41,400.00 41,400.00 0% - 0% - 0% -
(able to QR code and make payment via mobile online)

4.8 8 port network switch for vehicle access system 1 210.00 210.00 0% - 0% - 0% -
0% - 0% - 0% -
4.9 Intercom panel 1 2,300.00 2,300.00 0% - 0% - 0% -

4.10 Epoxy coated pole/stand for readers cctv 2 580.00 1,160.00 0% - 0% - 0% -

Page 18
7. BLOCK B - HD SMATV SYSTEM INSTALLATION (FASA 1)

Project Title : TR2


Progress Claim No. 07
Contract Breakdown – Progress Claim / Work Done To-date EKTech Claims
Contract Amount Previous Current Total To-Date
No Description
Qty Rate Amount Percentage Amount (RM) Percentage Amount (RM) Percentage Amount (RM)
Workstation pc and 24” led monitor for vehicle access software,
4.11 window 10 ultimate edition, Intel i7, 4 display output graphic card, 12 1 5,590.00 5,590.00 0% - 0% - 0% -
tb harddisk

4.12 Wiring works with below


2 pair 0.63mm telephone cable in concealed
a GI conduit 1 1,730.00 1,730.00 0% - 0% - 0% -
Cat 6 cable in concealed GI conduit b 1 4,030.00 4,030.00 0% - 0% - 0% -

4.13 Installation, Programming and Configuration. 1 1,150.00 1,150.00 0% - 0% - 0% -

Testing & commissioning c/w on-site training and manufacturer’s


4.14 1 580.00 580.00 0% - 0% - 0% -
support letter.

Any other works not specifically mentioned but necessary to complete


4.15 1 5,180.00 5,180.00 0% - 0% - 0% -
installations
a) License plate intergration
b) Credit/debit card system
c) _________________________________________

141,090.00 - - -

Page 19
Project Title : TR2
Progress Claim No. 07
Contract Breakdown – Progress Claim / Work Done To-date EKTech Claims
Contract Amount Previous Current Total To-Date
No Description
Qty Rate Amount Percentage Amount (RM) Percentage Amount (RM) Percentage Amount (RM)

SERVICE APARTMENT
A
PUBLIC ADDRESS SYSTEM

Emergency paging panel c/w handheld paging microphone and siren


tone generator, remote siren trigger and other necessary accessories.
5.1 1 869.00 869.00 0% - 0% - 0% -
All other paging in progress, music streaming would be directly cut off
upon activation of the unit

Message recorder/player, support micro sd up to 16gb, auto firmware


5.2 1 1,674.00 1,674.00 0% - 0% - 0% -
update/detection upon power up and other necessary accessories

AM-FM Tuner/dvd/cd/mp3 player with usb / sd card and other


5.3 1 952.00 952.00 0% - 0% - 0% -
necessary accessories

Dual channel media player


5.4 1
- inclusive

Digital desktop paging mic up to 256 zone with lcd display, 9


5.5 1 1,769.00 1,769.00 0% - 0% - 0% -
programmable grouping and all call, built in selectable chime.

5.6 24 zone rack mounted data decorder and other necessary accessories. 1 945.00 945.00 0% - 0% - 0% -

Mixed pre-amplifier with 12 inputs ( 6 mics, 4bgm sources, aux, ext


5.7 line) for PA with dual output, bgm source and mixed audio, with 2 mic 1 983.00 983.00 0% - 0% - 0% -
priority input.

2 input 8 output distribution amplifier for audio line signal and other
5.8 1 983.00 983.00 0% - 0% - 0% -
necessary accessories

250w 100v line power amplifier amplifiers with auto fault sensor, built
5.9 1 4,112.00 4,112.00 0% - 0% - 0% -
in changeover, digital display and other accessories.

Page 20
Project Title : TR2
Progress Claim No. 07
Contract Breakdown – Progress Claim / Work Done To-date EKTech Claims
Contract Amount Previous Current Total To-Date
No Description
Qty Rate Amount Percentage Amount (RM) Percentage Amount (RM) Percentage Amount (RM)
375w 100v line power amplifier amplifiers with auto fault sensor, built
5.10 1 4,611.00 4,611.00 0% - 0% - 0% -
in changeover, digital display and other accessories.

500w 100v line power amplifier amplifiers with auto fault sensor, built
5.11 1 38,772.00 38,772.00 0% - 0% - 0% -
in changeover, digital display and other accessories.

500w 100v line power amplifier amplifiers with auto fault sensor, built
5.12 1 7,755.00 7,755.00 0% - 0% - 0% -
in changeover, digital display (standby) and other accessories.

Regulated 24vdc power supply, automatic battery charger, 4 nos 12v


5.13 1 7,164.00 7,164.00 0% - 0% - 0% -
100ah sla battery and other necessary accessories

12 channel selector c/w all call, priority contact and remote selection
5.14 1 3,447.00 3,447.00 0% - 0% - 0% -
and other necessary accessories

16 channel speaker line surveillance with impendance measurement &


5.15 1 6,394.00 6,394.00 0% - 0% - 0% -
timer trigger and other necessary accessories

100v auto-trans volume controller with overriding indicator and other


5.16 1
necessary accessories – omitted

6w 5” 100v line dual cone speaker with matching transformer, back


5.17
enclosure and abs grille, power tapping and other accessories
a surface mount 487 44.00 21,428.00 0% - 0% - 0% -
b ceiling mount 136 39.00 5,304.00 0% - 0% - 0% -

6w 5” 100v line dual cone ceiling speaker with matching transformer,


5.18 back enclosure and abs grille, 1/3/6/ 10w power tapping and other
accessories
a surface mount 5 41.00 205.00 0% - 0% - 0% -
b ceiling mount 35 140.00 4,900.00 0% - 0% - 0% -

Page 21
Project Title : TR2
Progress Claim No. 07
Contract Breakdown – Progress Claim / Work Done To-date EKTech Claims
Contract Amount Previous Current Total To-Date
No Description
Qty Rate Amount Percentage Amount (RM) Percentage Amount (RM) Percentage Amount (RM)
6w 4” 100v line surface mount dual cone box speaker with matching
5.19 transformer, back enclosure and abs grille, power tapping and other 1280 47.00 60,160.00 0% - 0% - 0% -
accessories

30w 100v line horn speaker with 8” aluminium flare and other
5.20 98 179.00 17,542.00 0% - 0% - 0% -
accessories

20w 100v line column speaker and other accessories


5.21 13 215.00 2,795.00 0% - 0% - 0% -
(Level 8 only)

5.22 42u equipment rack and other necessary accessories 1 7,200.00 7,200.00 0% - 0% - 0% -

2x1.55mm pvc cabling run in concealed upvc conduit from PA


5.23 1 53,680.00 53,680.00 8% 4,294.40 0% - 8% 4,294.40
equipment rack/patch panel to speaker

4x1.55mm pvc cabling run in concealed upvc conduit from PA


5.24 1 194.00 194.00 0% - 0% - 0% -
equipment rack/patch panel

2x2.5mm pvc cabling run in concealed upvc conduit from PA


5.25 1 194.00 190,544.00 6% 11,432.64 0% - 6% 11,432.64
equipment rack/patch panel speaker

twisted screen cabling c/w upvc conduit run in conceal from paging
5.26 1 1,383.00 1,383.00 0% - 0% - 0% -
mic to main fire control room

5.27 100v line patch panel 1 2,585.00 2,585.00 0% - 0% - 0% -

connection link between PA system in main fire control room and sub
5.28 1 4,800.00 4,800.00 0% - 0% - 0% -
fire control room

5.29 Installation, programming and configuration works 1 3,902.00 3,902.00 0% - 0% - 0% -

Testing and commissioning c/.w on-site training and manufacturer’s


5.30 1 4,200.00 4,200.00 0% - 0% - 0% -
support letter

Page 22
Project Title : TR2
Progress Claim No. 07
Contract Breakdown – Progress Claim / Work Done To-date EKTech Claims
Contract Amount Previous Current Total To-Date
No Description
Qty Rate Amount Percentage Amount (RM) Percentage Amount (RM) Percentage Amount (RM)
Any other works not specifically mentioned but necessary to complete
5.31
installations
a) Amplifier monitor panel 1 1,028.00 1,028.00 0% - 0% - 0% -
b) 1 1,218.00 1,218.00 0% - 0% - 0% -
c) _________________________________________ 1

463,498.00 15,727.04 - 15,727.04

Page 23
Project Title : TR2
Progress Claim No. 07
Contract Breakdown – Progress Claim / Work Done To-date EKTech Claims
Contract Amount Previous Current Total To-Date
No Description
Qty Rate Amount Percentage Amount (RM) Percentage Amount (RM) Percentage Amount (RM)

COMMERCIAL
B
PUBLIC ADDRESS SYSTEM

Emergency paging panel c/w handheld paging microphone and siren


tone generator, remote siren trigger and other necessary accessories.
5.1 1 869.00 869.00 0% - 0% - 0% -
All other paging in progress, music streaming would be directly cut off
upon activation of the unit

Message recorder/player, support micro sd up to 16gb, auto firmware


5.2 1 1,674.00 1,674.00 0% - 0% - 0% -
update/detection upon power up and other necessary accessories

AM-FM Tuner/dvd/cd/mp3 player with usb / sd card and other


5.3 1 952.00 952.00 0% - 0% - 0% -
necessary accessories

5.4 Dual channel media player 1 771.00 771.00 0% - 0% - 0% -

Touch screen desktop paging mic with grouping and all call, built in
5.5 1 3,538.00 3,538.00 0% - 0% - 0% -
selectable chime and other necessary accessories

5.6 24 zone rack mounted data decorder and other necessary accessories. 1 945.00 945.00 0% - 0% - 0% -

Mixed pre-amplifier with 12 inputs ( 6 mics, 4bgm sources, aux, ext


5.7 line) for PA with dual output, bgm source and mixed audio, with 2 mic 1 983.00 983.00 0% - 0% - 0% -
priority input.

2 input 8 output distribution amplifier for audio line signal and other
5.8 1 983.00 983.00 0% - 0% - 0% -
necessary accessories

Ethernet transciver for digital paging mic, convert ra485 data to ip


5.9 1 1,512.00 1,512.00 0% - 0% - 0% -
communication

Ethernet transciver for digital paging and music streaming, convert


5.10 1 876.00 876.00 0% - 0% - 0% -
ra485 data/music to ip communication

Page 24
Project Title : TR2
Progress Claim No. 07
Contract Breakdown – Progress Claim / Work Done To-date EKTech Claims
Contract Amount Previous Current Total To-Date
No Description
Qty Rate Amount Percentage Amount (RM) Percentage Amount (RM) Percentage Amount (RM)
250w 100v line power amplifier amplifiers with auto fault sensor, built
5.11 1 8,223.00 8,223.00 0% - 0% - 0% -
in changeover, digital display and other accessories.

375w 100v line power amplifier amplifiers with auto fault sensor, built
5.12 1 2,308.00 2,308.00 0% - 0% - 0% -
in changeover, digital display and other accessories.

500w 100v line power amplifier amplifiers with auto fault sensor, built
5.13 1 7,755.00 7,755.00 0% - 0% - 0% -
in changeover, digital display and other accessories.

500w 100v line power amplifier amplifiers with auto fault sensor, built
5.14 1 2,585.00 2,585.00 0% - 0% - 0% -
in changeover, digital display (standby) and other accessories.

5.15 12 channel amplifier monitor panel and other accessories 1 514.00 514.00 0% - 0% - 0% -

Regulated 24vdc power supply, automatic battery charger, 2 nos 12v


5.16 1 3,742.00 3,742.00 0% - 0% - 0% -
100ah sla battery and other accessories

12 channel selector c/w all call, priority contact and remote selection
5.17 1 1,724.00 1,724.00 0% - 0% - 0% -
and other necessary accessories

16 channel speaker line surveillance with impendance measurement &


5.18 1 2,132.00 2,132.00 0% - 0% - 0% -
timer trigger and other necessary accessories

100v auto-trans volume controller with overriding indicator and other


5.19 1
necessary accessories – omitted

6w 5” 100v line dual cone speaker with matching transformer, back


5.20
enclosure and abs grille, power tapping and other accessories
a ceiling recessed 27 50.00 1,350.00 0% - 0% - 0% -

10w 5” 100v line dual cone ceiling speaker with matching transformer,
5.21
back enclosure and abs grille, power tapping and other accessories

a ceiling recessed 223 39.00 8,697.00 0% - 0% - 0% -

Page 25
Project Title : TR2
Progress Claim No. 07
Contract Breakdown – Progress Claim / Work Done To-date EKTech Claims
Contract Amount Previous Current Total To-Date
No Description
Qty Rate Amount Percentage Amount (RM) Percentage Amount (RM) Percentage Amount (RM)
6w 4” 100v line surface mount dual cone box speaker with matching
5.22 transformer, back enclosure and abs grille, power tapping and other 19 50.00 950.00 0% - 0% - 0% -
accessories

30w 100v line horn speaker with 8” aluminium flare and other
5.23 2 189.00 378.00 0% - 0% - 0% -
accessories

5.24 42u equipment rack and other necessary accessories 1 2,400.00 2,400.00 0% - 0% - 0% -

2x1.5mm pvc cabling run in concealed upvc conduit from PA


5.25 1 36,450.00 36,450.00 9% 3,280.50 0% - 9% 3,280.50
equipment rack/patch panel to speaker

4x1.5mm pvc cabling run in concealed upvc conduit from PA


5.26 1 19,800.00 19,800.00 2% 396.00 0% - 2% 396.00
equipment rack/patch panel

twisted screen cabling c/w upvc conduit run in conceal from paging
5.27 1 1,383.00 1,383.00 0% - 0% - 0% -
mic to main fire control room

5.28 100v line patch panel 110 60.00 6,600.00 0% - 0% - 0% -

5.29 Installation, programming and configuration works 1 3,900.00 3,900.00 0% - 0% - 0% -

Testing and commissioning c/.w on-site training and manufacturer’s


5.30 1 1,200.00 1,200.00 0% - 0% - 0% -
support letter

For Tower A Level 42 & Level 43


network switch 10/100/1000 c/w 4 port uplink/combo port and other
5.31 1 1,656.00 1,656.00 0% - 0% - 0% -
necessary accessories

Ethernet transciver for paging and music streaming, convert ra485


5.32 1 876.00 876.00 0% - 0% - 0% -
data/music to ip communication

5.33 8 channel data decoder/zone selector and other necessary accessories 1 1,247.00 1,247.00 0% - 0% - 0% -

Page 26
Project Title : TR2
Progress Claim No. 07
Contract Breakdown – Progress Claim / Work Done To-date EKTech Claims
Contract Amount Previous Current Total To-Date
No Description
Qty Rate Amount Percentage Amount (RM) Percentage Amount (RM) Percentage Amount (RM)
250w 100v line power amplifier amplifiers with auto fault sensor, built
5.34 in changeover, digital display and RS485 data control (on duty) and 1 2,056.00 2,056.00 0% - 0% - 0% -
any other accessories.

250w 100v line power amplifier amplifiers with auto fault sensor, built
5.35 in changeover, digital display and RS485 data control (standby) and 1 2,056.00 2,056.00 0% - 0% - 0% -
any other accessories.

5.36 12 channel amplifier monitor panel and other accessories 1 514.00 514.00 0% - 0% - 0% -

Regulated 24vdc power supply, automatic battery charger, 2 nos 12v


5.37 1 3,582.00 3,582.00 0% - 0% - 0% -
100ah sla battery and other accessories

100v auto-trans volume controller with overriding indicator and other


5.38
necessary accessories – omitted

6w 5” 100v line dual cone speaker with matching transformer, back


5.39
enclosure and abs grille, power tapping and other accessories
a ceiling recessed 11 38.00 418.00 0% - 0% - 0% -

30w 100v line horn speaker with 8” aluminium flare and other
5.40 2 179.00 358.00 0% - 0% - 0% -
accessories

5.41 42u equipment rack and other necessary accessories 1 2,400.00 2,400.00 0% - 0% - 0% -

2x2.5mm pvc cabling run in concealed upvc conduit from PA


5.42 1 1,070.00 1,070.00 0% - 0% - 0% -
equipment rack to patch panel to speaker

4x2.5mm pvc cabling or above AWG cabling c/w upvc conduit run in
5.43 1 389.00 389.00 0% - 0% - 0% -
concealed from PA equipment rack/patch panel

4C single mode indoor fiber optic from sub fire control room to PA
5.44 1 3,000.00 3,000.00 0% - 0% - 0% -
equipment rach in tower A level 42 riser

5.45 Patch panel 2 300.00 600.00 0% - 0% - 0% -

Page 27
Project Title : TR2
Progress Claim No. 07
Contract Breakdown – Progress Claim / Work Done To-date EKTech Claims
Contract Amount Previous Current Total To-Date
No Description
Qty Rate Amount Percentage Amount (RM) Percentage Amount (RM) Percentage Amount (RM)

5.46 Installation, programming and configuration works 1 1,800.00 1,800.00 0% - 0% - 0% -

Testing and commissioning c/.w on-site training and manufacturer’s


5.47 1 600.00 600.00 0% - 0% - 0% -
support letter

network switch 10/100/1000 c/w 4 port uplink/combo port and other


5.48 1 315.00 315.00 0% - 0% - 0% -
necessary accessories

5.49 8 x 8 network matrix controller and other necessary accessories 1 4,173.00 4,173.00 0% - 0% - 0% -

AM-FM Tuner/dvd/cd/mp3 player with usb / sd card and other


5.50 1 952.00 952.00 0% - 0% - 0% -
necessary accessories

Touch screen desktop paging mic with grouping and all call, built in
5.51 1 1,769.00 1,769.00 0% - 0% - 0% -
selectable chime and other necessary accessories

5.52 8 channel data decoder/zone selector and other necessary accessories 1 1,247.00 1,247.00 0% - 0% - 0% -

Ethernet transciver for paging and music streaming, convert ra485


5.53 1 876.00 876.00 0% - 0% - 0% -
data/music to ip communication

500w 100v line power amplifier amplifiers with auto fault sensor, built
5.54 1 5,170.00 5,170.00 0% - 0% - 0% -
in changeover, digital display (on duty) and other accessories.

500w 100v line power amplifier amplifiers with auto fault sensor, built
5.55 1 2,585.00 2,585.00 0% - 0% - 0% -
in changeover, digital display (standby) and other accessories.

5.56 12 channel amplifier monitor panel and other accessories 1 514.00 514.00 0% - 0% - 0% -

Regulated 24vdc power supply, automatic battery charger, 2 nos 12v


5.57 1 3,582.00 3,582.00 0% - 0% - 0% -
100ah sla battery and other accessories

100v auto-trans volume controller with overriding indicator and other


5.58 1 60.00 60.00 0% - 0% - 0% -
necessary accessories

Page 28
Project Title : TR2
Progress Claim No. 07
Contract Breakdown – Progress Claim / Work Done To-date EKTech Claims
Contract Amount Previous Current Total To-Date
No Description
Qty Rate Amount Percentage Amount (RM) Percentage Amount (RM) Percentage Amount (RM)

6w 5” 100v line dual cone box speaker with matching transformer,


5.59
back enclosure and abs grille, power tapping and other accessories
a ceiling recessed 2 39.00 78.00 0% - 0% - 0% -

20w 6” 100v line coaxial ceiling speaker with matching transformer,


5.60 bank enclosure and abs grille, power tapping and other necessary
accessories
a ceiling recessed 35 130.00 4,550.00 0% - 0% - 0% -

5.61 6w 4” 100v line surface mount box and other accessories 2 47.00 94.00 0% - 0% - 0% -

5.62 42u equipment rack and other necessary accessories 1 2,400.00 2,400.00 0% - 0% - 0% -

2x2.5mm pvc cabling or above AWG run in concealed upvc conduit


5.63 1 3,402.00 3,402.00 0% - 0% - 0% -
from PA equipment rack to patch panel to volume control speaker

4x2.5mm pvc cabling or above AWG cabling c/w upvc conduit run in
5.64 1 584.00 584.00 0% - 0% - 0% -
concealed from PA equipment rack to volume control

4C single mode indoor fiber optic from sub fire control room to PA
5.65 1 2,400.00 2,400.00 0% - 0% - 0% -
equipment rack in tower B level 42 AV room

5.66 Volume control 1 480.00 480.00 0% - 0% - 0% -

5.67 Installation, programming and configuration works 1 3,000.00 3,000.00 0% - 0% - 0% -

Testing and commissioning c/.w on-site training and manufacturer’s


5.68 1 1,200.00 1,200.00 0% - 0% - 0% -
support letter

For Tower B Level 43


network switch 10/100/1000 c/w 4 port uplink/combo port and other
5.69 1 315.00 315.00 0% - 0% - 0% -
necessary accessories

5.70 8 x 8 network matrix controller and other necessary accessories 1 4,173.00 4,173.00 0% - 0% - 0% -

Page 29
Project Title : TR2
Progress Claim No. 07
Contract Breakdown – Progress Claim / Work Done To-date EKTech Claims
Contract Amount Previous Current Total To-Date
No Description
Qty Rate Amount Percentage Amount (RM) Percentage Amount (RM) Percentage Amount (RM)

AM-FM Tuner/dvd/cd/mp3 player with usb / sd card and other


5.71 1 952.00 952.00 0% - 0% - 0% -
necessary accessories

Touch screen desktop paging mic with grouping and all call, built in
5.72 1 1,769.00 1,769.00 0% - 0% - 0% -
selectable chime and other necessary accessories

5.73 8 channel data decoder/zone selector and other necessary accessories 1 1,247.00 1,247.00 0% - 0% - 0% -

Ethernet transciver for paging and music streaming, convert ra485


5.74 1 876.00 876.00 0% - 0% - 0% -
data/music to ip communication

500w 100v line power amplifier amplifiers with auto fault sensor, built
5.75 1 5,170.00 5,170.00 0% - 0% - 0% -
in changeover, digital display (on duty) and other accessories.

500w 100v line power amplifier amplifiers with auto fault sensor, built
5.76 1 2,585.00 2,585.00 0% - 0% - 0% -
in changeover, digital display (standby) and other accessories.

5.77 12 channel amplifier monitor panel and other accessories 1 514.00 514.00 0% - 0% - 0% -

Regulated 24vdc power supply, automatic battery charger, 2 nos 12v


5.78 1 3,582.00 3,582.00 0% - 0% - 0% -
100ah sla battery and other accessories

100v auto-trans volume controller with overriding indicator and other


5.79 1 240.00 240.00 0% - 0% - 0% -
necessary accessories

6w 5” 100v line dual cone speaker with matching transformer, back


5.80
enclosure and abs grille, power tapping and other accessories
ceiling recessed 4 39.00 156.00 0% - 0% - 0% -

20w 6” 100v line coaxial ceiling speaker with matching transformer,


5.81 bank enclosure and abs grille, power tapping and other necessary
accessories
a ceiling recessed 33 130.00 4,290.00 0% - 0% - 0% -

Page 30
Project Title : TR2
Progress Claim No. 07
Contract Breakdown – Progress Claim / Work Done To-date EKTech Claims
Contract Amount Previous Current Total To-Date
No Description
Qty Rate Amount Percentage Amount (RM) Percentage Amount (RM) Percentage Amount (RM)
6w 4” 100v line surface mount dual cone box speaker with matching
transformer, back enclosure and abs grille, power tapping and other 2 39.00 78.00 0% - 0% - 0% -
accessories

42u equipment rack and other necessary accessories 1 2,400.00 2,400.00 0% - 0% - 0% -

2x2.5mm pvc cabling or above AWG run in concealed upvc conduit


1 3,960.00 3,960.00 9% 356.40 4% 158.40 13% 514.80
from PA equipment rack to patch panel to volume control speaker

4x2.5mm pvc cabling or above AWG cabling c/w upvc conduit run in
1 1,167.00 1,167.00 9% 105.03 4% 46.68 13% 151.71
concealed from PA equipment rack to volume control

4C single mode indoor fiber optic from sub fire control room to PA
1 3,000.00 3,000.00 0% - 0% - 0% -
equipment rack in tower B level 44 AV room

Volume control 2 77.00 154.00 0% - 0% - 0% -

Installation, programming and configuration works 1 4,950.00 4,950.00 0% - 0% - 0% -

Testing and commissioning c/.w on-site training and manufacturer’s


1 4,200.00 4,200.00 0% - 0% - 0% -
support letter

Any other works not specifically mentioned but necessary to complete


installations
a) 1 2,238.00 2,238.00 0% - 0% - 0% -
b) 1 2,299.00 2,299.00 0% - 0% - 0% -
c) _________________________________________ 1 771.00 771.00 0% - 0% - 0% -
d) 1 771.00 771.00 0% - 0% - 0% -
239,104.00 4,137.93 205.08 4,343.01

Page 31
10. PUSAT KOMUNITI - TELECOMMUNICATION DISTRIBUTION INSTALLATION (FASA 1)

Project Title : TR2


Progress Claim No. 07
Contract Breakdown – Progress Claim / Work Done To-date EKTech Claims
Contract Amount Previous Current Total To-Date
No Description
Qty Rate Amount Percentage Amount (RM) Percentage Amount (RM) Percentage Amount (RM)

A Service Apartment
6.0 Audio Visual System

6.1 3 way speaker karaoke speaker (1 pair) 1 4,224.00 4,224.00 0% - 0% - 0% -

6.2 karaoke amplifier 1 5,376.00 5,376.00 0% - 0% - 0% -

6.3 dynamic handheld wired karaoke mic c/w extension cable (5m) 2 228.00 456.00 0% - 0% - 0% -

6.4 UHF dual channel handheld wireless karaoke mic system 1 2,784.00 2,784.00 0% - 0% - 0% -

6.5 60” smart LED UHD TV c/w wall bracket 1 3,960.00 3,960.00 0% - 0% - 0% -

6.6 HDMI panel 1 30.00 30.00 0% - 0% - 0% -

6.7 Cabling work (HDMI) in pvc conduit 1 1,680.00 1,680.00 0% - 0% - 0% -

6.8 Cabling work (twisted pair cable) in pvc conduit 1 1,680.00 1,680.00 0% - 0% - 0% -

System configurations, installations & termination c/w necessary


6.9 1 461.00 461.00 0% - 0% - 0% -
accessories

6.10 Testing and commissioning 1 185.00 185.00 0% - 0% - 0% -

Any other works not specifically mentioned but necessary to complete


6.11
installations
I)
ii)
iii) _________________________________________

20,836.00 - - -

Page 32
11. PUSAT KOMUNITI - IP CCTV + CARD ACCESS CONTROL SYSTEM INSTALLATION (FASA 1)

Project Title : TR2


Progress Claim No. 07
Contract Breakdown – Progress Claim / Work Done To-date EKTech Claims
Contract Amount Previous Current Total To-Date
No Description
Qty Rate Amount Percentage Amount (RM) Percentage Amount (RM) Percentage Amount (RM)
B Commercial
6.0 Audio Visual System
Level 42
6.1 5500 ansi lumens projector c/w lens 4 5,865.00 23,460.00 0% - 0% - 0% -

Motorized bracket for projector (able to have multi stop) c/w other
6.2 4 2,415.00 9,660.00
accessories

Motorized front projection screen (12ft x 9ft) with black border, limit
6.3 stop, up/stop/down switch, matte white surface and other necessary 4 1,921.00 7,684.00
accessories

Fixed mounting bracket for projection screen c/w other necessary


6.4 4 334.00 1,336.00
accessories

6.5 8 input 8 output HDMI matrix switch c/w other necessary accessories 1 7,993.00 7,993.00

6.6 HDMI transmitter (extended HDMI connection via CAT cable) 4 656.00 2,624.00

6.7 HDMI receiver (extended HDMI connection via CAT cable) 8 656.00 5,248.00

HDMI transmitter (extended HDMI connection via CAT cable) c/w wall
6.8 4 1,058.00 4,232.00
plate

6.9 HDMI extension cable c/w connector (3m length) for PC guest 3 58.00 174.00

6.10 Server rack with 24 port jack panel 1 2,875.00 2,875.00

Workstation PC and 24” LED monitor for audio visual system software
with minimum windows ultimate Edition 64 bit, intel core i7-6700k @
6.11 1 7,533.00 7,533.00
4ghz, 16gb ram, 4 display outputs graphic careds, 100/1000 base-t
network card, storage of 1tb harddisk complete with mouse, keyboard.

Page 33
11. PUSAT KOMUNITI - IP CCTV + CARD ACCESS CONTROL SYSTEM INSTALLATION (FASA 1)

Project Title : TR2


Progress Claim No. 07
Contract Breakdown – Progress Claim / Work Done To-date EKTech Claims
Contract Amount Previous Current Total To-Date
No Description
Qty Rate Amount Percentage Amount (RM) Percentage Amount (RM) Percentage Amount (RM)

6.12 16 input 8 output digital mixer 3 19,895.00 59,685.00

6.13 500 watts, 8 ohms 15” 2-way full range loudspeaker 8 2,806.00 22,448.00

6.14 2 x 550 watts, 8 ohms power amplifier 4 2,103.00 8,412.00

UHF dual channel handheld wireless microphone system consist of UHF


6.15 3 1,375.00 4,125.00
receiver and handheld transmitter

6.16 Dynamic handheld voval microphone 6 110.00 660.00

6.17 Microphone extension cable c/w connectors (10m length) 6 69.00 414.00

6.18 Floor microphone stand c/w boom arm 6 115.00 690.00

6.19 DVD / CD Pplayer c/w usb port 3 403.00 1,209.00

6.20 Mocrophone receptacle panel 6 35.00 210.00

6.21 Powered control room monitor speaker 3 754.00 2,262.00

6.22 Preset panel 3 690.00 2,070.00

6.23 Source selector 3 978.00 2,934.00

6.24 Equipment rack 3 2,875.00 8,625.00

6.25 Cabling works with cat5e cable concealed in upvc conduit or gi conduit 1 1,553.00 1,553.00

6.26 Cabling works with HDMI cable concealed in upvc conduit or gi conduit 1 920.00 920.00

Page 34
11. PUSAT KOMUNITI - IP CCTV + CARD ACCESS CONTROL SYSTEM INSTALLATION (FASA 1)

Project Title : TR2


Progress Claim No. 07
Contract Breakdown – Progress Claim / Work Done To-date EKTech Claims
Contract Amount Previous Current Total To-Date
No Description
Qty Rate Amount Percentage Amount (RM) Percentage Amount (RM) Percentage Amount (RM)
Cabling works with 4 x 2.5mmsq pvc cable in concealed upvc or gi
6.27 1 2,415.00 2,415.00
conduit

Cabling works with 2 core screen audio cable in concealed upvc or gi


6.28 1 3,450.00 3,450.00
conduit

Cabling works with twisted pair speaker cable in concealed upvc


6.29 1 1,150.00 1,150.00
conduit or gi conduit

System configuration, installation & termination c/w necessary


6.30 1 1,150.00 1,150.00
assessories

6.31 Testing & commissioning, one time on-site training 1 667.00 667.00

Level 43
6.32 5500 ansi lumens projector c/w lens 4 5,865.00 23,460.00

Motorized bracket for projector (able to have multi stop) c/w other
6.33 4 2,415.00 9,660.00
accessories

Motorized front projection screen (12ft x 9ft) with black border, limit
6.34 stop, up/stop/down switch, matte white surface and other necessary 4 1,921.00 7,684.00
accessories

Fixed mounting bracket for projection screen c/w other necessary


6.35 4 334.00 1,336.00
accessories

6.36 8 input 8 output HDMI matrix switch c/w other necessary accessories 1 7,993.00 7,993.00

6.37 HDMI transmitter (extended HDMI connection via CAT cable) 4 1,058.00 4,232.00

6.38 HDMI receiver (extended HDMI connection via CAT cable) 6 656.00 3,936.00

Page 35
11. PUSAT KOMUNITI - IP CCTV + CARD ACCESS CONTROL SYSTEM INSTALLATION (FASA 1)

Project Title : TR2


Progress Claim No. 07
Contract Breakdown – Progress Claim / Work Done To-date EKTech Claims
Contract Amount Previous Current Total To-Date
No Description
Qty Rate Amount Percentage Amount (RM) Percentage Amount (RM) Percentage Amount (RM)
6.39 HDMI receiver (extended HDMI connection via CAT cable) 2 656.00 1,312.00

6.40 HDMI extension cable c/w connectgor (3m length) for PC guest 1 58.00 58.00

6.41 Server rack with 24 port jack panel 1 2,875.00 2,875.00

Workstation PC and 24” LED monitor for audio visual system software
with minimum windows 10 ultimate Edition 64 bit, intel core i7-6700k
6.42 1 7,533.00 7,533.00
@ 4ghz, 16gb ram, 4 display outputs graphic careds, 100/1000 base-t
network card, storage of 1tb harddisk complete with mouse, keyboard.

6.43 16 input 8 output digital mixer 1 19,895.00 19,895.00

6.44 500 watts, 8 ohms 15” 2-way full range loudspeaker 8 2,806.00 22,448.00

6.45 2 x 550 watts, 8 ohms power amplifier 4 2,103.00 8,412.00

6.46 12” 2 way powered stage monitor loudspeaker 2 3,565.00 7,130.00

B Commercial
6.0 Audio Visual System

UHF dual channel handheld wireless mic system consist of UHF


6.47 3 1,375.00 4,125.00 0% - 0% - 0% -
receiver and handheld transmitter

6.48 Dynamic handheld voval mic 3 110.00 330.00 0% - 0% - 0% -

6.49 Mic extension cable c/w connectors (10m) 3 69.00 207.00 0% - 0% - 0% -

6.50 Floor mic stand c/w boom arm 3 115.00 345.00 0% - 0% - 0% -

6.51 DVD/CD Player c/w USB port 1 403.00 403.00 0% - 0% - 0% -

Page 36
11. PUSAT KOMUNITI - IP CCTV + CARD ACCESS CONTROL SYSTEM INSTALLATION (FASA 1)

Project Title : TR2


Progress Claim No. 07
Contract Breakdown – Progress Claim / Work Done To-date EKTech Claims
Contract Amount Previous Current Total To-Date
No Description
Qty Rate Amount Percentage Amount (RM) Percentage Amount (RM) Percentage Amount (RM)

6.52 Mic receptacle panel 3 35.00 105.00 0% - 0% - 0% -

6.53 Powered control room monitor speaker 1 754.00 754.00 0% - 0% - 0% -

6.54 Preset panel 1 690.00 690.00 0% - 0% - 0% -

6.55 Source selector 1 978.00 978.00 0% - 0% - 0% -

6.56 Equipment rack 1 2,875.00 2,875.00 0% - 0% - 0% -

4MP 26x ptz ip fast dome camera c/w PC control software, joystick
6.57 1 2,134.00 2,134.00 0% - 0% - 0% -
and other necessary accessories

6.58 8 channel NVR c/w 4tb harddsik 1 1,086.00 1,086.00 0% - 0% - 0% -

Stage lighting controller able to link to iOS, iphome, ipa, android,


6.59 1 644.00 644.00 0% - 0% - 0% -
MAC, PC, ethernet interface

12 x 4w quad-colour (rgba) LED par sportlight c/w barrel clamp, safety


6.60 12 943.00 11,316.00 0% - 0% - 0% -
cable and other necessary accessories

150w moving head LED spor light c/w barrel clamp, safety and other
6.61 4 5,463.00 21,852.00 0% - 0% - 0% -
necessary accessories

6.62 fixed lighting panel 1 1,321.00 1,321.00 0% - 0% - 0% -

6.63 Cabling works with cat5e cable in concealed pvc confuit or GI conduit 1 1,553.00 1,553.00 0% - 0% - 0% -

6.64 Cabling works with HDMI cable in concealed pvc confuit or GI conduit 1 1,725.00 1,725.00 0% - 0% - 0% -

Cabling works with 4 X 2.5mm pcv cable in concealed pvc confuit or GI


6.65 1 6,900.00 6,900.00 0% - 0% - 0% -
conduit

Page 37
11. PUSAT KOMUNITI - IP CCTV + CARD ACCESS CONTROL SYSTEM INSTALLATION (FASA 1)

Project Title : TR2


Progress Claim No. 07
Contract Breakdown – Progress Claim / Work Done To-date EKTech Claims
Contract Amount Previous Current Total To-Date
No Description
Qty Rate Amount Percentage Amount (RM) Percentage Amount (RM) Percentage Amount (RM)

Cabling works with 2 core screen audio cable in concealed pvc confuit
6.66 1 3,450.00 3,450.00 0% - 0% - 0% -
or GI conduit

System configuration, installation & terminations c/w necessary


6.67 1 10,616.00 10,616.00 0% - 0% - 0% -
accessories

6.68 Testing and commissioning c/w one time on-site training 1 5,378.00 5,378.00 0% - 0% - 0% -

Any other works not specifically mentioned but necessary to complete


6.69
installations
a) 1 1,106.00 1,106.00 0% - 0% - 0% -
b) 1 2,760.00 2,760.00 0% - 0% - 0% -
c) _________________________________________

408,485.00 - - -

Page 38
12. PONDOK PENGAWAL - VEHICLE ACCESS CONTROL SYSTEM INSTALLATION (FASA 1)

Project Title : TR2


Progress Claim No. 07
Contract Breakdown – Progress Claim / Work Done To-date EKTech Claims
Contract Amount Previous Current Total To-Date
No Description
Qty Rate Amount Percentage Amount (RM) Percentage Amount (RM) Percentage Amount (RM)

A Service Apartment
7.0 High Definition MATV System

To supply, deliver, install, testing and commissioning the following


7.1 complete HD MATV system as specified in the drawings and 2 4,390.00 8,780.00 0% - 0% - 0% -
specifications

Digital type metal headend cabinet to house 1310nm optic transmitter


(4-IF & 1RF, 87-2150Mhz), programmable headend amplifier (5inputs
7.2 2 6,798.00 13,596.00 0% - 0% - 0% -
50 cluster), surge protector device, optical splitter sc/apc and optical
antenuator sc/apc

7.3 Optical receiver and converter c/w other necessary accessories 4 863.00 3,452.00 0% - 0% - 0% -

distribution amplifier c/w power supply unit and other necessary


7.4 16 1,260.00 20,160.00 0% - 0% - 0% -
accessories

7.5 2 way coaxial splitter 61 35.00 2,135.00 0% - 0% - 0% -

7.6 4 way coaxial splitter 20 54.00 1,080.00 0% - 0% - 0% -

7.7 6 way coaxial splitter 1 82.00 82.00 0% - 0% - 0% -

7.8 8 way coaxial splitter 122 90.00 10,980.00 0% - 0% - 0% -

Fiber optic works from digital type headend cabinet to optical receiver
7.9 1 4,200.00 4,200.00 0% - 0% - 0% -
in trunking

7.10 Cabling work with 2 C singlemode 1 1,512.00 1,512.00 0% - 0% - 0% -

Cabling works woth RG6 coaxial cable works in trunking / in concealed


7.11 1 181,734.00 181,734.00 0% - 0% - 0% -
conduit.

Page 39
12. PONDOK PENGAWAL - VEHICLE ACCESS CONTROL SYSTEM INSTALLATION (FASA 1)

Project Title : TR2


Progress Claim No. 07
Contract Breakdown – Progress Claim / Work Done To-date EKTech Claims
Contract Amount Previous Current Total To-Date
No Description
Qty Rate Amount Percentage Amount (RM) Percentage Amount (RM) Percentage Amount (RM)

7.12 SMATV outlet with 1 gang F connection outlet 918 72.00 66,096.00 0% - 0% - 0% -

System configuration, installation & terminations c/w necessary


7.13 1 24,000.00 24,000.00 0% - 0% - 0% -
accessories

7.14 Testing & commissioning 1 21,840.00 21,840.00 0% - 0% - 0% -

Any other works not specifically mentioned but necessary to complete


7.15
installations
a)
b)
c) _________________________________________

359,647.00 - - -

Page 40
13. PONDOK PENGAWAL - CCTV SYSTEM INSTALLATION (FASA 1)

Project Title : TR2


Progress Claim No. 07
Contract Breakdown – Progress Claim / Work Done To-date EKTech Claims
Contract Amount Previous Current Total To-Date
No Description
Qty Rate Amount Percentage Amount (RM) Percentage Amount (RM) Percentage Amount (RM)

A Service Apartment
8.0 Telephone System (FTTH)

Indoor fiber distribution hub, HSSB 19”x42” floor rack for out to riser
c/w fiber panel c/w UPC/SC connector, adaptor, pigtail, c/w surge
8.1 1 43,860.00 43,860.00 0% - 0% - 0% -
arrestor and all necessary accessories to Telekom requiremnets and
approval

8.2 Fiber tie from telekom MDF room to SDF room c/w termination 1 4,800.00 4,800.00 0% - 0% - 0% -

8 core single mode indoor fiber optic cable from indoor fiber
8.3 distribution hub at SDF room to telephone riser and inside telephone 1 1,968.00 1,968.00 0% - 0% - 0% -
riser

24 core single mode indoor fiber optic cable from indoor fiber
8.4 distribution hub at SDF room to telephone riser and inside telephone 1 44,856.00 44,856.00 0% - 0% - 0% -
riser

24 port wall splice box / fiber terminal box (FTB) with accessories at
8.5 1 12,444.00 12,444.00 0% - 0% - 0% -
each floor to authority requirements

8 port wall splice box / fiber terminal box (FTB) with accessories at
8.6 1 432.00 432.00 0% - 0% - 0% -
each floor to authority requirements

2C fiber drop cables from telephone riser FTB to apartment unit fiber
8.7 1 165,600.00 165,600.00 0% - 0% - 0% -
wall socket (FWS) in concealed conduit

4C fiber drop cables from telephone riser FTB to kindergarten unit


8.8 1 1,176.00 1,176.00 0% - 0% - 0% -
fiber wall socket (FWS) in concealed conduit

Fiber wall socket (FWS) at each apartment unit, mgmt office, retail
8.9 etc as shown in drawings and schematic diagram to authority 920 24.00 22,080.00 0% - 0% - 0% -
requirements

Data point using Cat6 cable in concealed conduit c/w RJ45 socket
8.10 6 600.00 3,600.00 0% - 0% - 0% -
outlet c/w terminations

Wifi point using UTP cat 6 cable in concealed conduit c/w rg45 socket
8.11 7 600.00 4,200.00 0% - 0% - 0% -
outlet.

Termination of fiber optic cables c/w necessary connector and


8.12 1 55,200.00 55,200.00 0% - 0% - 0% -
accessories

24 port network switch, cable management panel and other necessary


8.13 accessories in 15U wall mounted 19” equipment rack c/w 13A SSO 1 3,000.00 3,000.00 0% - 0% - 0% -
power rail in level 8 management office.

8.14 2 pair cat 6 cable from optical network unit to network switch 1 2,400.00 2,400.00 0% - 0% - 0% -

8 port network switch, cable management panel in 15U wall mounted


8.15 19” equipment rack c/w 13A SSO powerr rail in ground floor guard 1 1,800.00 1,800.00 0% - 0% - 0% -
house

Access point fitting (indoor type, 802.11 ac wave 2, tri-band c/w


8.16 7 918.00 6,426.00 0% - 0% - 0% -
necessary accessories

8.17 Smart access gateway 1 1,074.00 1,074.00 0% - 0% - 0% -

8.18 Earthing, Testing & Commissioning 1 12,144.00 12,144.00 0% - 0% - 0% -

Telekom Infra
600mm wide preforated galvanised steel cable tray run at MDF and
8.19 1 4,800.00 4,800.00 0% - 0% - 0% -
SDF room high level c/w bracket, fire seal (TM approved type)

600mm wide preforated galvanised steel cable tray run at MDF and
8.20 1 3,720.00 3,720.00 0% - 0% - 0% -
SDF room high level c/w bracket, fire seal (TM approved type)

2 layers of 2 nos 100mm upvc pipe laid underground from new jc9c
8.21 1 989.00 989.00 0% - 0% - 0% -
manhole to basement wall

2 layers of 2 nos 100mm GI pipes laid underground from new jc9c


8.22 1 8,304.00 8,304.00 0% - 0% - 0% -
manhole cross the drain and connect to telekom manhole.

8.23 Telekom manhole jc9c c/w fittings, covers, accessories. 1 4,800.00 4,800.00 0% - 0% - 0% -

8.24 600mm cable tray from pipe sleece at basement wall to MDF room. 1 1,200.00 1,200.00 0% - 0% - 0% -

Make good on the affected road above infra works and removal of
8.25 1 3,000.00 3,000.00 0% - 0% - 0% -
debris

8.26 Inspection with authorities to handover MDF and infra 1 1,200.00 1,200.00 0% - 0% - 0% -

8.27 Testing and commissioning 1 2,400.00 2,400.00 0% - 0% - 0% -

Any other works not specifically mentioned but necessary to complete


8.28 1
installations
a)
b)
c) _________________________________________

417,473.00 - - -

Page 41
14. PONDOK PENGAWAL - TELECOMMUNICATION DISTRIBUTION INSTALLATION (FASA 1)

Project Title : TR2


Progress Claim No. 07
Contract Breakdown – Progress Claim / Work Done To-date EKTech Claims
Contract Amount Previous Current Total To-Date
No Description
Qty Rate Amount Percentage Amount (RM) Percentage Amount (RM) Percentage Amount (RM)

B Commercial
8.0 Telephone System

Indoor fiber distribution hub, HSBB 19” X 42” floor rack for out to riser
c/w fiber panel c/w UPC/SC connector, adapter, pigtail c/w surge
8.1 1 21,060.00 21,060.00 0% - 0% - 0% -
arrestor and all necessary accessories to Telekom requirements and
approval.

600 mm wide perforated galvanised steel cable tray run at high level
from SDF room to telephone riser and inside each telephone riser at
8.2 1 13,800.00 13,800.00 0% - 0% - 0% -
all levels (vertical tray) c/w supporting brackets, hangers, fire seal
(TM appoved).

8.3 Fiber tie from telekom MDF room to SDF room c/w termination works. 1 7,800.00 7,800.00 0% - 0% - 0% -

8 Core single mode indoor fiber optic cable from indoor fiber
8.4 distribution hub at SDF room to telephone riser and inside telephone 1 1,200.00 1,200.00 0% - 0% - 0% -
riser

24 Core single mode indoor fiber optic cable from indoor fiber
8.5 distribution hub at SDF room to telephone riser and inside telephone 1 22,628.00 22,628.00 0% - 0% - 0% -
riser

48 Core single mode fiber optic cable from indoor fiber distribution
8.6 1 32,085.00 32,085.00 0% - 0% - 0% -
hub at SDF room to telephone riser and inside telephone riser

8 ports wall splice box / FTB with accessories at each floor to


8.7 1 432.00 432.00 0% - 0% - 0% -
authority requirements

24 ports wall splice box / FTB with accessories at each floor to


8.8 1 816.00 816.00 0% - 0% - 0% -
authority requirements

48 ports wall splice box / FTB with accessories at each floor to


8.9 1 204.00 204.00 0% - 0% - 0% -
authority requirements

4C fiber drop cables from telephone riser FTB to retail unit FWS in
8.10 1 1,176.00 1,176.00 5% 58.80 2% 23.52 7% 82.32
concealed heavy duty uPVC conduit

Fiber wall socket (FWS) at each retail units as shown in drawings and
8.11 160 24.00 3,840.00 0% - 0% - 0% -
schematic diagram to authority requirements

Telephone using 1 pair 0.63mm2 telephone cable in concealed conduit


8.12 12 300.00 3,600.00 0% - 0% - 0% -
c/w RJ11 socket outlet c/w terminations

Data point using Cat6 cable in concealed conduit c/w RJ45 sccket
8.13 18 420.00 7,560.00 0% - 0% - 0% -
outlet c/w terminations

Data point using Cat6 cable in concealed conduit c/w RJ45 sccket
8.14 34 858.00 29,172.00 0% - 0% - 0% -
outlet c/w terminations

8.15 Terminations of fiber optic c/w necessary connectors and accessories 1 9,600.00 9,600.00 0% - 0% - 0% -

48 ports networks switch, cable management panel and other


8.16 necessary accessories in 15U wall mounted 19” equipment rack c/w 1 5,340.00 5,340.00 0% - 0% - 0% -
13A S/S/O power rail in Level 2

24 ports networks switch, cable management panel and other


8.17 necessary accessories in 15U wall mounted 19” equipment rack c/w 2 3,000.00 6,000.00 0% - 0% - 0% -
13A S/S/O power rail in Level 42 and Level 43

8.18 2 core incoming / 20 pair outgoing IDF with surge arrestor 2 6,600.00 13,200.00 0% - 0% - 0% -

8.19 2 pair Cat 6 cable from optical network unit to network switch & IDF 1 2,400.00 2,400.00 0% - 0% - 0% -

8.20 Earthing, Testing and Commissioning 1 2,112.00 2,112.00 0% - 0% - 0% -

GI conduit, GI flexible couduit and other necessary accessories for


8.21 1 1,620.00 1,620.00 0% - 0% - 0% -
fiber wall socket at kiosk area

Any other works not specifically mentioned but necessary to complete


8.28 1
installations
a)
b)
c) _________________________________________

185,645.00 58.80 23.52 82.32

Page 42
15. OTHER ASSOCIATED WORKS (FASA 1)

Project Title : TR2


Progress Claim No. 07
Contract Breakdown – Progress Claim / Work Done To-date EKTech Claims
Contract Amount Previous Current Total To-Date
No Description
Qty Rate Amount Percentage Amount (RM) Percentage Amount (RM) Percentage Amount (RM)

A Service Apartment
9.0 SMART HOME & DIGITAL DOOR LOCK

9.1 Smart Home System


Wireless hub with Z wave, support wifi with built in motion detector
a 918 720.00 660,960.00 0% - 0% - 0% -
and IR extender
b Wireless magnetic contact 1844 110.00 202,840.00 0% - 0% - 0% -
c Wireless indoor siren 919 210.00 192,990.00 0% - 0% - 0% -
d Wifi IP camera 918 240.00 220,320.00 0% - 0% - 0% -
e Smart switching support 2 gang 1836 220.00 403,920.00 0% - 0% - 0% -
f Smart plug 918 130.00 119,340.00 0% - 0% - 0% -

Digital door lock c/w wireless digital door lock module, pull/push
handle, fingerprint reader, password & emergency key and support
9.2 918 2,400.00 2,203,200.00 0% - 0% - 0% -
apps for remote monitorng (PC supply rate: RM2,240.00/no.
Installation, Testing & Commissioning :RM160.00/job)

To include the cost on required bomba fire testing on “fire rated door
9.3 installed with above digital door lock” until obtain the bomba 0%
certificate. - inclusive

Testing & commissioning and handover in approved working order of


9.4 the complete system (for smart plug. T&C done with instaled 1 50,000.00 50,000.00 0%
downlight)

Training, customization as per users requirement and ensure the


9.5 1 10,000.00 10,000.00 0%
system full functioning to meet user satisfaction

Any other works not specifically mentioned but necessary to complete


9.6
installations
I)
ii)
iii) _________________________________________

4,063,570.00 - - -

Page 43
FTTH

Project Title : Skylake Service Apartment


Progress Claim No. 07
Contract Breakdown – Progress Claim / Work Done To-date
Contract Amount
No Description
Qty

Telecommunication Services

Supply and install the


telephone services
c/w all accessories
deemed necessary for
the satisfactory
completion of the
works in accordance
with the specification,
drawings and to
SKMM/MTFSB and
Telekom/service
provider requirements

EXTERNAL TELEPHONE
1
RETICULATION

Telephone manholes
c/w all necessary
accessories comply
with the
Telekom/service
1.1 provider requirement 0
inclusive of
excavation, making
good and reinstate to
original condition of
existing manholes.

Page 44
FTTH

Underground ducts
encased in concrete,
duct seal at entries of
manholes & trenches,
draw wires and all
1.2 0
necessary accessories
to the
Telekom/service
provider’s
requirement

Telekom’s Main Indoor


Fiber Distribution
Hub/Optical
Distribution Frame
2.1 (ODF) at MDF room for 0
Telekom’s incoming
cable c/w surge
arrestor and all
necessary

Subscriber’s Main
Fiber Termination Box
(MFTB) at MDF Room
2.2 0
c/w surge arrestor
and all necessary
accessories

Page 45
FTTH

Fiber patch cord


between Telekom’s
Main Indoor Fiber
Distribution
Hub/Optical
Distribution Fibre
(ODF) and Subscriber’s
2.3 0
Main Fiber
Termination Box
(MFTB) c/w
connectors/adaptors,
splicing, termination
and all necessary
Distribution horizontal
accessories
& vertical backbone
telephone cabling
from Main Fibre
Distribution Frame
(MFTB) at MDF room
to respective (FTB)
2.4 0
inside risers including
cable trays,
trunkings, cable
termination,
connectors, adapters
Fiber termination box
2.5 & all necessary
(FTB) inside telephone 54
accessories.
risers

Fiber optic drop cable


from fiber termination
box (FTB) inside risers
2.6
to respective fiber
wall socket (FWS) or
Utility Box c/w FWS :

Block A (Total 373


i) 15
Units)
Block A – Completed
120
120 Units
Block A – Completed
60
60 Units

Block A – Completed
90 Units (As at 90
december 2019 claim)

Page 46
FTTH

Block A – Completed
88 Units (As at july 88
2020 claim)

Block B (Total 373


ii) 13
Units)
Block B – Completed
270
270 Units

Block B – Completed
90 Units (as at dec 90
2019 claim)

Common area, facility


iii) area, offices, shops, 7
tadika, etc.

Utility Box/Soho Box


c/w Fiber Wall Socket
with 2 core single
2.7 mode fibre cable,
patch panel and all
necessary accessories
for :

Common area, facility


i) area, offices, shops, 2
tadika, etc.

Fiber Wal Socket


(FWS) c/w 2 core
single mode fibre
2.8
cable and all
necessary accessories
for :
i) Block A 373
ii) Block B 373
Common area, facility
iii) area, offices, shops, 5
tadika, etc.

3 MISCELLANEOUS
3.1 Earthing System 1

Page 47
Testing and
FTTH commissioning
including liasion with
Telekom/service
3.2 1
provider for
inspection, approval
and handing over of
MDF Room

Page 48
FTTH

EKTech Claims
Contract Amount Current Previous
Rate Amount Percentage Amount (RM) Percentage Amount (RM)

0.00 - 0% - 90% -

Page 49
FTTH

33,500.00 - 0% - 70% -

- 0% - 0% -

40,000.00 - 0% - 0% -

Page 50
FTTH

24,500.00 - 0% - 0% -

74,300.00 - 0% - 55% -

1,023.50 55,269.00 0% - 90% 49,742.10

50.00 750.00 0% - 95% 712.50

50.00 6,000.00 0% - 100% 6,000.00

50.00 3,000.00 0% - 100% 3,000.00

50.00 4,500.00 0% - 100% 4,500.00

Page 51
FTTH

50.00 4,400.00 0% - 100% 4,400.00

50.00 650.00 0% - 100% 650.00

50.00 13,500.00 0% - 100% 13,500.00

50.00 4,500.00 0% - 100% 4,500.00

50.00 350.00 0% - 80% 280.00

660.00 1,320.00 0% - 90% 1,188.00

40.00 14,920.00 0% - 60% 8,952.00


40.00 14,920.00 0% - 85% 12,682.00

40.00 200.00 0% - 65% 130.00

840.00 840.00 0% - 0% -

Page 52
FTTH

153,408.00 153,408.00 0% - 55% 84,374.40

278,527.00 - 194,611.00

Page 53
FTTH

Claims
Total To-Date
Percentage Amount (RM)

90% -

Page 54
FTTH

70% -

0% -

0% -

Page 55
FTTH

0% -

55% -

90% 49,742.10

95% 712.50

100% 6,000.00

100% 3,000.00

100% 4,500.00

Page 56
FTTH

100% 4,400.00

100% 650.00

100% 13,500.00

100% 4,500.00

80% 280.00

90% 1,188.00

60% 8,952.00
85% 12,682.00

65% 130.00

0% -

Page 57
FTTH

55% 84,374.40

194,611.00

Page 58
Fireman

Project Title : Skylake Service Apartment


Progress Claim No. 07
Contract Breakdown – Progress Claim / Work Done To-date
Contract Amount
No Description
Qty

Fireman Intercom System

Supply, delivery,
installation, testing,
setting, commissioning
and maintenance
during the defect
liability period for the
Fireman Intercom
System all in
accordance with the
specification and
drawings. All
materials, labour etc.
Required for the
complete installation,
whether or not
specified or
separately itemised
shall be deemed to be
included.

Master handset panel


with high impact red
ABS plastic, solidstate
1 high impedance 1
speaker, coiled cord,
condenser microphone
240

Page 59
Fireman

Project Title : Skylake Service Apartment


Progress Claim No. 07
Contract Breakdown – Progress Claim / Work Done To-date
Contract Amount
No Description
Qty

Trouble indicator
panel with power
supply & charger
2 1
panel momentary
action push button
and LED indicators

Push button handset


zone selector panel
with built-in Green
3 Call LED, Red Fault 1
LED indicator and
press to call push
button

24V DC sealed lead


acid battery with
battery charger and
4 1
compartment in
compliance with
Bomba requirement

Digital Sub-panel
RTTUs (Remote
5
Telephone Terminal
Unit)

a. Block A 9
b. Block B 9
c. Podium Area 14

Page 60
Fireman

Project Title : Skylake Service Apartment


Progress Claim No. 07
Contract Breakdown – Progress Claim / Work Done To-date
Contract Amount
No Description
Qty

Remote handset with


supervisory module,
electronic buzzer, Red
flashing LED indicator,
6
metal enclosure, key
lock and master key
system with a break-
glass window access

a. Block A 81
b. Block B 81
c. Podium Area 77

Wiring in G.I conduit


and installation
complete with
cabling, conduits,
trunking and all
7 1
necessary accessories
- Conceal Piping using
PVC Piping ; Visible
Piping using G.I.
where possible

Testing and
8 1
Commissioning

Page 61
Fireman

EKTech Claims
Contract Amount Current Previous
Rate Amount Percentage Amount (RM) Percentage Amount (RM)

836.00 836.00 0% - 0% -

Page 62
Fireman

EKTech Claims
Contract Amount Current Previous
Rate Amount Percentage Amount (RM) Percentage Amount (RM)

3,630.00 3,630.00 0% - 0% -

14,655.00 14,655.00 0% - 0% -

3,146.00 3,146.00 0% - 0% -

1,573.00 14,157.00 0% - 80% 11,325.60


1,573.00 14,157.00 0% - 80% 11,325.60
1,573.00 22,022.00 0% - 80% 17,617.60

Page 63
Fireman

EKTech Claims
Contract Amount Current Previous
Rate Amount Percentage Amount (RM) Percentage Amount (RM)

418.00 33,858.00 0% - 55% 18,621.90


418.00 33,858.00 0% - 55% 18,621.90
418.00 32,186.00 0% - 55% 17,702.30

120,160.00 120,160.00 0% - 90% 108,144.00

2,000.00 2,000.00 0% - 0% -

294,665.00 - 203,358.90

Page 64
Fireman

Claims
Total To-Date
Percentage Amount (RM)

0% -

Page 65
Fireman

Claims
Total To-Date
Percentage Amount (RM)

0% -

0% -

0% -

80% 11,325.60
80% 11,325.60
80% 17,617.60

Page 66
Fireman

Claims
Total To-Date
Percentage Amount (RM)

55% 18,621.90
55% 18,621.90
55% 17,702.30

90% 108,144.00

0% -

203,358.90

Page 67
CCTV

Project Title : Skylake Service Apartment


Progress Claim No. 07
Contract Breakdown – Progress Claim / Work Done To-date
No Description Contract Amount
Supply, delivery, Qty
installation, testing,
setting, commissioning
and maintenance
Closed Circuit Television System
during the defect
liability period for the
CCTV System all in
accordance with the
specification and
drawings. All
materials, labour etc.
Required for the
complete installation,
whether or not
IR DOME Camera
specified or c/w
1 38
Power Adapter
separately itemised
shall be deemed to be
included.
- 2 Mega Pixels
- 1/3” B22 SONY
Exmor CMOS Sensor
- f=2.8~12mm lens
- 24pcs led
- WDR, 3D-NR, DSS
Supported
- 0 Lux (ir on)
- Support HD-SDI Video
out
- Degree of Protection
: IP66

IR Bullet Camera c/w


2 36
Power Adapter

Page 68
CCTV

Project Title : Skylake Service Apartment


Progress Claim No. 07
Contract Breakdown – Progress Claim / Work Done To-date
No Description Contract Amount
Qty

- 2 Mega Pixels
- 1/3” B22/B34 SONY
Exmor CMOS Sensor
- f=2.8~12mm lens
- 42pcs led
- WDR, 3D-NR, DSS
Supported
- 0 Lux (ir on)
- Support HD-SDI Video
out
- Degree of Protection
: IP66

IR Wide Angle Camera


3 8
c/w Power Adapter

- 2 Mega Pixels
- 1/3” SONY Exmor
CMOS Sensor
- f=2.8~8mm lens
- viewing angle
minimal 114 degree
- 24pcs led
- WDR, 3D-NR, DSS
Supported
- 0 Lux (ir on)
- Support TCP/IP out
- Degree of Protection
: IP66
Note : CCTV software
system to allow for
recording only, while
access of footage to
be limited to
authorised personnel
only.

Page 69
CCTV

Project Title : Skylake Service Apartment


Progress Claim No. 07
Contract Breakdown – Progress Claim / Work Done To-date
No Description Contract Amount
Qty

H.264 16-channel HD-


SDI, IP Hybrid digital
video recorder (DVR)
c/w 14 days, 24-hours
4 7
continuous recording
storage capacity and
etc.
- Control room

- 16 composite loop
through
- 1 composite video
output
- 1 VGA video output
- 1 Spot monitor video
output
- H.264 video
compression
- Recording Mode :
400fps @ Full HD
1080P
- Line Display : 400fps
@ Full HD 1080P
- 16 alarm sensor
input
- 4 alarm relay output
- Motion Detection
- 4 (Up to 16TB SATA
HDD) + 1 x DVD-RW
- 1 x RJ45 10/100
Base-T Port
- 1 x RS232 Port
- 2 x RS485 Port
- 4 x USB Port
- Front panel control
- I.R remote control
- CMS Support up to 6
monitor

Page 70
CCTV

Project Title : Skylake Service Apartment


Progress Claim No. 07
Contract Breakdown – Progress Claim / Work Done To-date
No Description Contract Amount
Qty

32” Professional
CCTV LED color
monitor c/w 2 x
composite video, 1 x
SVGA and 1 x S-Video,
Audio input, 1920 x
5 1080 pixel resolution, 7
1000 : 1 Contrast
Ratio, wall/ceiling
mount brackett and
other necessary
accessories
- Control room

Keyboard and mouse


6 7
switch

POE switch c/w all


7 1
necessary accessories

Fibre Patch Panel c/w


8 1
Patch cord

Fibre Converter c/w


9 all necessary 0
accessories

All CCTV cabling with


Full Copper Low Loss
Coaxial Cable and UTP
cable in concealed
10 conduit/G.I 1
conduit/M.S. trunking
c/w termination and
all necessary
accessories

Page 71
CCTV

Project Title : Skylake Service Apartment


Progress Claim No. 07
Contract Breakdown – Progress Claim / Work Done To-date
No Description Contract Amount
Qty

Single Mode Fibre


Cable c/w accessories
in concealed conduit/
11 G.I conduit / m.s. 1
trunking c/w
termination and all
necessary accessories

All power cabling in


concealed conduit/G.I
conduit from nearest
12 1
electrical distribution
board in electrical
riser

Surge protective
device for power,
13 data and video 1
- Guard House
- Control room

Uninterruptible Power
14 Supply (UPS) backup 1
Central
for mainMonitoring
equipment
System consisting of
PC Workstation with
Intel Core i5
processor, 4GB RAM, 6
15 2
nos. VGA output card,
32” LED monitor,
2KVA UPS and CMS
Software capable for 6
monitor output
15 SWG Mild Steel
Free Standing CCTV
16 Rack/Console to house 1
all CCTV equipment
- Control room

Page 72
CCTV

Project Title : Skylake Service Apartment


Progress Claim No. 07
Contract Breakdown – Progress Claim / Work Done To-date
No Description Contract Amount
Qty

System configuration,
17 1
Programming

Testing and
18 1
Commissioning

Page 73
CCTV

EKTech Claims
Contract Amount Current Previous
Rate Amount Percentage Amount (RM) Percentage Amount (RM)

555.00 21,090.00 0% - 0% -

555.00 19,980.00 0% - 0% -

Page 74
CCTV

EKTech Claims
Contract Amount Current Previous
Rate Amount Percentage Amount (RM) Percentage Amount (RM)

555.00 4,440.00 0% - 0% -

Page 75
CCTV

EKTech Claims
Contract Amount Current Previous
Rate Amount Percentage Amount (RM) Percentage Amount (RM)

3,200.00 22,400.00 0% - 0% -

Page 76
CCTV

EKTech Claims
Contract Amount Current Previous
Rate Amount Percentage Amount (RM) Percentage Amount (RM)

2,350.00 16,450.00 0% - 0% -

118.00 826.00 0% - 0% -

13,500.00 13,500.00 0% - 0% -

12,300.00 12,300.00 0% - 0% -

0.00

100,573.00 100,573.00 0% - 90% 90,515.70

Page 77
CCTV

EKTech Claims
Contract Amount Current Previous
Rate Amount Percentage Amount (RM) Percentage Amount (RM)

20,955.00 20,955.00 0% - 50% 10,477.50

0.00

17,000.00 17,000.00 0% - 0% -

8,900.00 8,900.00 0% - 0% -

7,500.00 15,000.00 0% - 0% -

4,200.00 4,200.00 0% - 0% -

Page 78
CCTV

EKTech Claims
Contract Amount Current Previous
Rate Amount Percentage Amount (RM) Percentage Amount (RM)

2,950.00 2,950.00 0% - 0% -

1,000.00 1,000.00 0% - 0% -

281,564.00 - 100,993.20

Page 79
CCTV

Claims
Total To-Date
Percentage Amount (RM)

0% -

0% -

Page 80
CCTV

Claims
Total To-Date
Percentage Amount (RM)

0% -

Page 81
CCTV

Claims
Total To-Date
Percentage Amount (RM)

0% -

Page 82
CCTV

Claims
Total To-Date
Percentage Amount (RM)

0% -

0% -

0% -

0% -

90% 90,515.70

Page 83
CCTV

Claims
Total To-Date
Percentage Amount (RM)

50% 10,477.50

0% -

0% -

0% -

0% -

Page 84
CCTV

Claims
Total To-Date
Percentage Amount (RM)

0% -

0% -

100,993.20

Page 85
Project Title : Skylake Service Apartment
Progress Claim No. 07
Contract Breakdown – Progress Claim / Work Done To-date EKTech Claims
No Description Contract Amount Current Previous Total To-Date
Qty Rate Amount Percentage Amount (RM) Percentage Amount (RM) Percentage Amount (RM)

Access Control System

Supply, delivery,
installation, testing,
setting, commissioning
and maintenance
during the defect
liability period for the
Access Control System
all in accordance with
the specification and
drawings. All
materials, labour etc.
Required for the
complete installation,
whether or not
specified or
separately itemised
shall be deemed to be
included.

Vehicle Access Control


1 System for
Guardhouse

Two-door TCP/IP
1.1 2 3,300.00 6,600.00 0% - 0% - 0% -
access controller

- Memory back-up
- Support up to
minimum 10,000 user
- Support up to
minimum 50,000
event transaction
- 10/100Mbits
communication

- 0% - 0% - 0% -
Power supply unit c/w
1.2 1 3,256.00 3,256.00 0% - 0% - 0% -
battery backup

Long Range Reader


Gate c/w mounting
1.3 2 6,050.00 12,100.00 0% - 0% - 0% -
pole & surge
protection

3” x 3” Push Button
1.4 - Barrier Access 2 330.00 660.00 0% - 0% - 0% -
Industrial Push Button

Heavy Duty Barrier


Gate c/w 3.0 meter
1.5 4 3,800.00 15,200.00 0% - 0% - 0% -
arm (arm speed <
1.8sec)

1.6 Vehicle Loop Detector 4 640.00 2,560.00 0% - 0% - 0% -

1.7 Intercom System x 4 1 4,800.00 4,800.00 0% - 0% - 0% -

10/100Mbps network
1.8 switches, accessories 1 1,137.00 1,137.00 0% - 0% - 0% -
and etc

1.9 Wall mount rack 1 858.00 858.00 0% - 0% - 0% -


System cabling and
installation c/w
1.10 concealed conduit/G.I 1 11,000.00 11,000.00 0% - 100% 11,000.00 100% 11,000.00
conduit
All power
- Using PVCcabling in
Conduit
concealed conduit/G.I
conduit from nearest
1.11 1 By Others
electrical distribution
board in electrical
riser
Surge protective
1.12 device for power, 1 990.00 990.00 0% - 0% - 0% -
signal and data
990.00
System configuration,
1.13 1 1,500.00 1,500.00 0% - 0% - 0% -
Programming

Testing and
1.14 1 2,350.00 2,350.00 0% - 0% - 0% -
Commissioning
Vehicle Access
Control System for
Internal Parking

Two-door TCP/IP
1.15 6 3,300.00 19,800.00 0% - 0% - 0% -
access controller

- Memory back-up
- Support up to
minimum 10,000 user
- Support up to
minimum 50,000
event transaction
- 10/100Mbits
communication

Power supply unit c/w


1.16 1 4,884.00 4,884.00 0% - 0% - 0% -
battery backup

Medium range card


reader ( detection
1.17 6 1,025.00 6,150.00 0% - 0% - 0% -
range of above 100cm)
c/w goose neck stand

3” x 3” Push Button
1.18 - Barrier Access 6 330.00 1,980.00 0% - 0% - 0% -
Industrial Push Button

Heavy Duty Barrier


Gate c/w 3.0 meter
1.19 6 3,800.00 22,800.00 0% - 0% - 0% -
arm (arm speed <
1.8sec)

1.20 Vehicle Loop Detector 6 640.00 3,840.00 0% - 0% - 0% -

Intercom System – 2 +
4=6
1.21 1 25,000.00 25,000.00 0% - 0% - 0% -
- All Link to Guard
House

10/100Mbps network
1.22 switches, accessories 1 2,273.00 2,273.00 0% - 0% - 0% -
and etc
Wall mount rack
1.23 1 1,716.00 1,716.00 0% - 0% - 0% -
- 9U Wall Mount Rack

System cabling and


installation c/w
1.24 concealed conduit/G.I 1 35,500.00 35,500.00 0% - 95% 33,725.00 95% 33,725.00
conduit
- PVC Piping

All power cabling in


concealed conduit/G.I
conduit from nearest
1.25 1 By Others
electrical distribution
board in electrical
riser

Surge protective
1.26 device for power, 1 1,320.00 1,320.00 0% - 0% - 0% -
signal and data

System configuration,
1.27 1 1,500.00 1,500.00 0% - 0% - 0% -
Programming

Testing and
1.28 1 2,350.00 2,350.00 0% - 0% - 0% -
Commissioning

Common Area – Door


2
Access System

Computer workstation
c/w Genuine Windows
OS & application
2.1 software, report 1 8,250.00 8,250.00 0% - 0% - 0% -
printing laser printer,
UPS and all necessary
accessories

- Intel Core i5
processor, 4GB RAM,
1TB Sata harddisk
drive, 21" LED
monitor, graphic card,
optical drive,
proprietary software
and etc
- Control room

2.2 Application softwares


Access control
a) 1 5,000.00 5,000.00 0% - 0% - 0% -
management software

Visitor management
b) 1 12,980.00 12,980.00 0% - 0% - 0% -
software

One-door TCP/IP
2.3 108 1,355.00 146,340.00 0% - 53% 77,560.20 53% 77,560.20
access controller

- Memory back-up
- Support up to
minimum 5,000 user
- Support up to
minimum 15,000
event transaction
- 10/100Mbits
communication

Power supply unit c/w


2.4 battery backup (Total 70 72.00 5,040.00 0% - 0% - 0% -
108 Units)

Power supply unit –


Completed as at/until 70 72.00 5,040.00 0% - 0% - 0% -
10/09/2019 = 70

Proximity card reader Bundle With


2.5 108
with LED indicator Item 2.3

- 1 no Green, 1 no Red
LED indicator
- 5cm reader reading
range

12V DC 600lbs electro-


magnetic lock,
magnetic contact,
Bundle With
2.6 switch, emergency 108
Item 2.3
breakglass, 3” x 3”
push button,
accessories

Proximity
(Note card –access
: Vehicle 3000
2.7 3000 28.00 84,000.00 0% - 0% - 0% -
nos
control system, lift
card access system
and door card access
system shall use one
proximity card
solution)
10/100Mbps network
2.8 1 22,000.00 22,000.00 0% - 0% - 0% -
switches
System cabling and
installation c/w
2.9 concealed conduit/G.I 1 65,500.00 65,500.00 0% - 90% 58,950.00 90% 58,950.00
conduit
- PVC Piping

All power cabling in


concealed conduit/G.I
conduit from nearest
2.10 1 By Others
electrical distribution
board in electrical
riser

Allow for wiring and


interfacing with fire
alarm panel at control
2.11 room to release 1 4,620.00 4,620.00 0% - 0% - 0% -
electromagnetic lock
in the event of fire
emergency

Surge protective
2.12 device for power, 108 250.00 27,000.00 0% - 0% - 0% -
data and signal

2.13 Wall mount rack 40 858.00 34,320.00 0% - 0% - 0% -

System configuration,
2.14 1 3,000.00 3,000.00 0% - 0% - 0% -
Programming

Testing and
2.15 1 5,500.00 5,500.00 0% - 0% - 0% -
Commissioning

All other works not


mentioned above but
necessary for the
2.16 complete
installations.
(to be clearly stated
by the Tenderers)

a) Lift Access System


1 32,750.00 32,750.00 0% - 0% - 0% -
Block A (4Lift)
b) Lift Access System
1 32,750.00 32,750.00 0% - 0% - 0% -
Block B (4Lift)
686,214.00 - 181,235.20 181,235.20
Panic Button

Project Title : Skylake Service Apartment


Progress Claim No. 07
Contract Breakdown – Progress Claim / Work Done To-date
No Description Contract Amount
Qty

Emergency Panic Button System

Supply, delivery,
installation, testing,
setting, commissioning
and maintenance
during the defect
liability period for the
Emergency Panic
Button System in
accordance with the
specification and
drawings. All
materials, labour etc.
Required for the
complete installation,
whether or not
specified or
separately itemised
shall be deemed to be
included.

Emergency Panic
1
Button System

Emergency Panic
1.1 Button system 1
controller

Power supply unit c/w


1.2 1
battery backup

230V AC surge
1.3 1
protector

Page 93
Panic Button

8 channel input and


1.4 3
output module

16 channel input and


1.5 2
output module

Emergency push
1.6 button c/w reset key, 33
accessories and etc

External siren box


1.7 33
(vandalproof type)

1.8 Strobe light 33

10/100Mbps network
1.9 1
switches

1.10 Wall mount rack 1

Computer workstation
c/w Genuine Windows
OS & application
1.11 software, report 1
printing laser printer,
UPS and all necessary
accessories

- Intel Core i5
processor, 4GB RAM,
1TB Sata harddisk
drive, 21" LED
monitor, graphic card,
optical drive,
proprietary software
and etc

Page 94
Panic Button

Panic alarm
1.12 managemant software 1
with mapping

System cabling and


installation c/w
1.13 1
concealed conduit/G.I
conduit

All power cabling in


concealed conduit/G.I
conduit from nearest
1.14 1
electrical distribution
board in electrical
riser

System configuration,
1.15 1
Programming

Testing and
1.16 1
Commissioning

Page 95
Panic Button

EKTech Claims
Contract Amount Current Previous
Rate Amount Percentage Amount (RM) Percentage Amount (RM)

19,000.00 19,000.00 0% - 0% -

2,145.00 2,145.00 0% - 0% -

4,125.00 4,125.00 0% - 0% -

Page 96
Panic Button

Not
Applicable to
our system

Not
Applicable to
our system

220.00 7,260.00 0% - 0% -

60.00 1,980.00 0% - 0% -

Bundle with
Item 1.6

7,300.00 7,300.00 0% - 0% -

11,500.00 11,500.00 0% - 0% -

7,000.00 7,000.00 0% - 0% -

Page 97
Panic Button

7,000.00 7,000.00 0% - 0% -

39,248.00 39,248.00 0% - 95% 37,285.60

By Others

3,000.00 3,000.00 0% - 0% -

1,600.00 1,600.00 0% - 0% -

111,158.00 - 37,285.60

Page 98
Panic Button

Claims
Total To-Date
Percentage Amount (RM)

0% -

0% -

0% -

Page 99
Panic Button

0% -

0% -

0% -

0% -

0% -

Page 100
Panic Button

0% -

95% 37,285.60

0% -

0% -

37,285.60

Page 101
HD SMATV

Project Title : Skylake Service Apartment


Progress Claim No. 07
Contract Breakdown – Progress Claim / Work Done To-date
No Description Contract Amount
Qty

HD SMATV

Supply, delivery,
installation, testing,
setting, commissioning
and maintenance
during the defect
liability period for the
Emergency Panic
Button System in
accordance with the
specification and
drawings. All
materials, labour etc.
Required for the
complete installation,
whether or not
specified or
separately itemised
shall be deemed to be
included.

FM antenna
constructed from
heavy gauge
1 2
aluminium or anodized
metal to avoid
corrosion and rusting

Page 102
HD SMATV

UHF antenna
constructed from
heavy gauge
2 6
aluminium or anodized
metal to avoid
corrosion and rusting

Hot dipped galvanized


steel Antenna
3 mounting pole and 8
bracket & mounting
accessories

Satellite dish (Astro


Beyond HD
4 compatible) c/w 2
optical LNB, bracket
and accessories

Lightning surge
5
arrestor for :

a) RF (terrestrial
antennas, satellite & 18
others)
b) Power 40

Programmable digital
6 (DVB-T2) headend 2
amplifier

Virtual fiber optical


7 1
converter

19” rack mounted 4 IF


(1 Sat) + 1 RF input, 1
8 optical output 1
SC/APC, 2 mW optical
transmitter

Page 103
HD SMATV

19” rack mounted SC-


9 APC fibre optic 2
splitter unit

wall mount rack to


10 house Headend 2
equipment

Optical multiswitch
with one core fiber
optical input
11 (SC/APC), (4 IF + 1 RF) 1
10 output 1 Sat + 1
terestrial out
multiswitch

4 IF + 1 RF final
12 multiswitch amplifier 1
with 8 output

SAT/TV/FM wall
13
outlet – Total 751

SAT/TV/FM wall
13a outlet (Block A Total 103
373 Units))

SAT/TV/FM wall
outlet – Block A 195
Completed 195 Units)

SAT/TV/FM wall
outlet – Block A 30
Completed 30 Units)

SAT/TV/FM wall
outlet – Block A 45
Completed 45 Units)

SAT/TV/FM wall
13b outlet (Block B Total 13
373 Units)

SAT/TV/FM wall
outlet – Block B 300
Completed 300 Units)

Page 104
HD SMATV

SAT/TV/FM wall
outlet – Block B 60
Completed 60 Units)

SAT/TV/FM wall
13c outlet (Other 5
Locations)

Supply and lay 3GHz


6/U satellite coaxial
14 cable in 1
conduit/trunking/cabl
e tray

Supply and lay fiber


optic cable in
15 1
conduit/trunking/cabl
e tray

System Installation
and termination c/w
16 1
connector and
accessories
System configuration,
17 1
Programming

Testing and
18 1
Commissioning

All other works not


mentioned above but
necessary for the
19 complete
installations.
(to be clearly stated
by the Tenderers)

a) VHF Antenna 4
b) SMATV Fiber Optic
1
Equipment
c) SMATV Switchline
1
MSW Switches

Page 105
HD SMATV

EKTech Claims
Contract Amount Current Previous
Rate Amount Percentage Amount (RM) Percentage Amount (RM)

260.00 520.00 0% - 0% -

Page 106
HD SMATV

260.00 1,560.00 0% - 0% -

60.00 480.00 0% - 0% -

1,030.00 2,060.00 0% - 0% -

60.00 1,080.00 0% - 0% -

125.00 5,000.00 0% - 0% -

3,200.00 6,400.00 0% - 0% -

Proposed
Different
Design

Proposed
Different
Design

Page 107
HD SMATV

Proposed
Different
Design

590.00 1,180.00 0% - 0% -

Proposed
Different
Design

Proposed
Different
Design

42.00 4,326.00 0% - 60% 2,595.60

42.00 8,190.00 0% - 100% 8,190.00

42.00 1,260.00 0% - 100% 1,260.00

42.00 1,890.00 0% - 100% 1,890.00

42.00 546.00 0% - 35% 191.10

42.00 12,600.00 0% - 100% 12,600.00

Page 108
HD SMATV

42.00 2,520.00 0% - 100% 2,520.00

42.00 210.00 0% - 90% 189.00

240,000.00 240,000.00 0% - 0% -

13,335.00 13,335.00 0% - 90% 12,001.50

20,000.00 20,000.00 0% - 0% -

6,000.00 6,000.00 0% - 0% -

22,000.00 22,000.00 0% - 0% -

330.00 1,320.00 0% - 0% -

18,000.00 18,000.00 0% - 0% -

111,500.00 111,500.00 0% - 0% -

481,977.00 - 41,437.20

Page 109
HD SMATV

Claims
Total To-Date
Percentage Amount (RM)

0% -

Page 110
HD SMATV

0% -

0% -

0% -

0% -

0% -

0% -

Page 111
HD SMATV

0% -

60% 2,595.60

100% 8,190.00

100% 1,260.00

100% 1,890.00

35% 191.10

100% 12,600.00

Page 112
HD SMATV

100% 2,520.00

90% 189.00

0% -

90% 12,001.50

0% -

0% -

0% -

0% -

0% -

0% -

41,437.20

Page 113

Anda mungkin juga menyukai