Anda di halaman 1dari 1

PEMILIK : Subaru Indonesia

PROYEK : Dudukan Mobil Subaru


ALAMAT : Pondok Indah
TANGGAL : 30 Mei 2023

MATERIAL UPAH
NO. URAIAN PEKERJAAN SPESIFIKASI VOL SAT RP SATUAN JUMLAH
RP TOTAL RP TOTAL
PEKERJAAN PERSIAPAN
I Mobilisasi dan Langsir material Pick-up/Mobil Box 1.0 Rit Rp - Rp - Rp 1,200,000 Rp 1,200,000 Rp 1,200,000 Rp 1,200,000
II Survey, Marking & Lot Area Benang, Bandul, Meteran 1.0 Ls Rp - Rp - Rp 150,000 Rp 150,000 Rp 150,000 Rp 150,000
III Proteksi Area Kerja Plastik Cover Finish 1.0 Ls Rp - Rp - Rp 500,000 Rp 500,000 Rp 500,000 Rp 500,000
IV Kebersihan 1.0 Ls Rp - Rp - Rp 150,000 Rp 150,000 Rp 150,000 Rp 150,000
TOTAL PEKERJAAN PERSIAPAN Rp 2,000,000
PEKERJAAN UTAMA
I PEKERJAAN DUDUKAN MOBIL
1 Finishing Wood Vinyl Taco Vinyl Plank TV-3014 3mm (3,34 m2) 18.0 m2 Rp 185,000 Rp 3,330,000 Rp 100,000 Rp 1,800,000 Rp 285,000 Rp 5,130,000
2 Base floor multplek 18 mm multiplek 18mm (1,22 x 2,44 m) 18.0 m2 Rp 130,000 Rp 2,340,000 Rp 150,000 Rp 2,700,000 Rp 280,000 Rp 5,040,000
3 Finishing List Strip Plank Silver Hairline- 100mm, 3,05m 18.0 mL Rp - Rp - Rp 75,000 Rp 1,350,000 Rp 75,000 Rp 1,350,000
4 Pijakan Rumput Sintetis Sakura Grass tipe Swiss - 3mm (1 x 2m) 18.0 m2 Rp 120,000 Rp 2,160,000 Rp 75,000 Rp 1,350,000 Rp 195,000 Rp 3,510,000
SUB TOTAL PEKERJAAN UTAMA Rp 15,030,000
TOTAL PEKERJAAN Rp 17,030,000
MANAGEMENT FEE 10% Rp 18,733,000
Ppn 11% Rp 2,060,630
GRAND TOTAL Rp 20,793,630
PEMBULATAN Rp 20,700,000
NOTES :
1. Harga sewaktu waktu bisa berubah menyesuaikan harga pasaran
2. Penawaran berlaku selama 30 hari kerja
3. Pekerjaan dilaksanakan setelah ada DP/Termin 1
4. Jika ada penambahan item pekerjaan maka ke dua belah pihak sepakat untuk adendum/addcost
5. Termin pekerjaan :
- 80% (DP/Termin 1)
- 20% (Pelunasan/Termin 2, setelah progress 80%)
Bintaro, 30 Mei 2023

Kevin Y. Maringka S. Ars


Kontraktor

Anda mungkin juga menyukai