REKAPITULASI RAB

PROGRAM : PEMBANGUNAN GEDUNG KESEHATAN


KEGIATAN : PEMBANGUNAN RUMAH SAKIT "INTERNATIONAL SMART HOSPITAL"
PEKERJAAN : PEMBANGUNAN RUMAH SINGGAH
LOKASI : DESA PRINGGABAYA KEC. PRINGGABAYA KAB. LOMBOK TIMUR
TAHUN ANGGARAN : 2021

NO JENIS PEKERJAAN JUMLAH TOTAL

1 2 3
I PEKERJAAN PERSIAPAN 6,812,784.00
II PEKERJAAN TANAH DAN URUGAN 30,929,844.00
III PEKERJAAN PASANGAN DAN PLESTERAN 321,535,534.61
IV PEKERJAAN BETON LANTAI I DAN LANTAI II 716,544,251.43
V PEKERJAAN KAYU ATAP DAN PLAFOND 197,220,568.47
VI PEKERJAAN LANTAI 155,483,113.17
VII PEKERJAAN KUSEN PINTU/JENDELA 124,718,074.61
VIII. PEKERJAAAN INSTALASI LISTRIK 21,975,690.00
IX. PEKERJAAN INSTALASI AIR BERSIH DAN AIR KOTOR 117,086,614.74
X. PEKERJAAN BESI DAN PENGUNCI 7,839,648.00
XI. PEKERJAAN PENGECATAN LANTAI I & LANTAI II 60,780,954.26
REAL COST 1 UNIT Rp. 1,760,927,077.29
PAJAK / PPN 10 % Rp. 176,092,707.73
TOTAL JUMLAH BIAYA Rp. 1,937,019,785.02
PEMBULATAN Rp. 1,937,019,000.00
TERBILANG : SATU MILIAR SEMBILAN RATUS TIGA PULUH TUJUH JUTA SEMBILAN BELAS RIBU RUPIAH

Lombok Timur, Januari 2021


Disetujui Oleh : Dibuat Oleh :
PT. NABIL SURYA PERSADA/INVESTMEN Konsultan Nemo Partner
PERWAKILAN REGIONAL 7 PROVINSI NTB CV. ADIJAYA KONSULTAN

KUSAIBAH RURROZIKI SUHARDI, ST


Kepala Perwakilan Direktur
Nip. 19631231 199103 1 148
RENCANA ANGGARAN BIAYA (RAB)
PROGRAM : PEMBANGUNAN GEDUNG KESEHATAN
KEGIATAN : PEMBANGUNAN RUMAH SAKIT "INTERNATIONAL SMART HOSPITAL"
PEKERJAAN : PEMBANGUNAN RUMAH SINGGAH
LOKASI : DESA PRINGGABAYA KEC. PRINGGABAYA KAB. LOMBOK TIMUR
TAHUN : 2021

HARGA
KODE JUMLAH HARGA
NO URAIAN PEKERJAAN VOLUME SAT. SATUAN
ANALISA
(Rp.) (Rp.)
1 2 3 4 5 6 7
I. PEKERJAAN PERSIAPAN
1 Pek. Uitzet & Bouplank 68.00 m¹ A.2.2.1.4. 52,668.00 3,581,424.00
2 Pek. Pembersihan awal sampai akhir 204.00 m² A.2.2.1.9. 15,840.00 3,231,360.00

Jumlah I 6,812,784.00
II. PEKERJAAN TANAH DAN URUGAN
1 Pek. Galian tanah pondasi keliling 174.35 m³ A.2.3.1.1. 72,600.00 12,657,810.00
2 Pek. Urugan tanah kembali 13.14 m³ A.2.3.1.9. 52,800.00 693,792.00
3 Pek. Urugan tanah dalam bangunan 61.20 m³ A.2.3.1.14. 171,600.00 10,501,920.00
4 Pek. Urugan pasir bawah pondasi dan bawah lantai 31.35 m³ A.2.3.1.11. 225,720.00 7,076,322.00
Jumlah II 30,929,844.00
III. PEKERJAAN PASANGAN DAN PLESTERAN
a. PEKERJAAN PASANGAN LANTAI I
1 Pek. Batu kosong 21.90 m³ A.3.2.1.9. 435,223.80 9,531,401.22
2 Pek. Pasangan pondasi batu kali 1:5 48.18 m³ A.3.2.1.3. 783,147.20 37,732,032.10
3 Pek. Pas. Trasraam 1/2 bata 1:3 48.00 m³ A.4.4.1.8. 139,098.52 6,676,728.96
4 Pek. Pas. Trasraam 1 bata 1:3 teras 1.60 m³ A.4.4.1.2. 284,680.00 455,488.00
5 Pek. Pasangan dinding 1/2 bata 1pc:5psr 399.12 m² A.4.4.1.10. 132,082.28 52,716,679.59
6 Pek. Plesteran trasraam 1pc:3psr 96.00 m² A.4.4.2.3. 63,898.30 6,134,236.42
7 Pek. Plesteran dinding 798.24 m² A.4.4.2.5. 60,575.06 48,353,439.09
8 Pek. Acian dinding bata merah 798.24 m² A.4.4.2.27. 36,872.00 29,432,705.28
a. PEKERJAAN PASANGAN LANTAI I
1 Pek. Pasangan dinding 1/2 bata 1pc:5psr 399.12 m² A.4.4.1.10. 132,082.28 52,716,679.59
2 Pek. Plesteran trasraam 1pc:3psr - m² 0 - -
3 Pek. Plesteran dinding 798.24 m² A.4.4.2.5. 60,575.06 48,353,439.09
4 Pek. Acian dinding bata merah 798.24 m² A.4.4.2.27. 36,872.00 29,432,705.28
Jumlah III 321,535,534.61
IV. PEKERJAAN BETON LANTAI I DAN LANTAI II -
a. PEKERJAAN BETON LANTAI I
1 Pek. Beton Lantai Kerja t. 10 cm 0.40 m³
-Beton mutu (K 100) 0.40 m³ A.4.1.1.1. 982,369.93 392,947.97

2 Pek. Poot Plat 125 x 125, P1 = 30 bh 12.89 m³


-Beton mutu (K 225) 12.89 m³ A.4.1.1.7. 1,155,342.92 14,893,092.34
- Begisting 24.00 m² A.4.1.1.20. 180,906.00 4,341,744.00
- Besi Polos dia 12mm 585.92 kg A.4.1.1.17.a. 15,199.80 8,905,891.14
- Besi Polos dia 10mm 406.89 kg A.4.1.1.17.a. 15,199.80 6,184,646.62

3 Pek. Poot Plat 80 x 80, P2 = 28 bh 4.93 m³


-Beton mutu (K 225) 4.93 m³ A.4.1.1.7. 1,155,342.92 5,693,529.91
- Begisting 22.40 m² A.4.1.1.20. 180,906.00 4,052,294.40
- Besi Polos dia 12mm 348.00 kg A.4.1.1.17.a. 15,199.80 5,289,559.58
- Besi Polos dia 10mm 241.67 kg A.4.1.1.17.a. 15,199.80 3,673,305.27

4 Pek. Sloof = 13/25 3.59 m³


-Beton mutu (K 225) 3.59 m³ A.4.1.1.7. 1,155,342.92 4,141,904.37
- Begisting sloof 38.24 m² A.4.1.1.17. 16,354.80 625,407.55
- Besi Polos Ø 12mm 509.22 kg A.4.1.1.17.a. 15,199.80 7,740,029.02
- Besi beugel Polos Ø 8mm 176.03 kg A.4.1.1.17.a. 15,199.80 2,675,565.59

5 Pek. Sloof = 13/20 2.00 m³


-Beton mutu (K 225) 2.00 m³ A.4.1.1.7. 1,155,342.92 2,312,996.53
- Begisting sloof 24.64 m² A.4.1.1.17. 16,354.80 402,982.27
- Besi Polos Ø 12mm 328.12 kg A.4.1.1.17.a. 15,199.80 4,987,299.04
- Besi beugel Polos Ø 8mm 113.42 kg A.4.1.1.17.a. 15,199.80 1,724,004.61
6 Pek. Kolom 25/25 4.70 m³
-Beton mutu (K 225) 4.70 m³ A.4.1.1.7. 1,155,342.92 5,430,111.73
- Begisting kolom 75.20 m² A.4.1.1.22. 204,963.00 15,413,217.60
- Besi Polos Ø 16mm 1,424.20 kg A.4.1.1.17.a. 15,199.80 21,647,612.55
- Besi beugel Polos Ø 8mm 178.03 kg A.4.1.1.17.a. 15,199.80 2,705,951.57

7 Pek. Kolom 20/20 4.51 m³


-Beton mutu (K 225) 4.51 m³ A.4.1.1.7. 1,155,342.92 5,212,907.26
- Begisting kolom 112.80 m² A.4.1.1.22. 204,963.00 23,119,826.40
- Besi Polos Ø 13mm 940.20 kg A.4.1.1.17.a. 15,199.80 14,290,806.73
- Besi beugel Polos Ø 8mm 267.04 kg A.4.1.1.17.a. 15,199.80 4,058,927.35

8 Pek. Kolom Praktis = 11 x 11 80.00 m' A.4.1.1.35. 93,878.40 7,510,272.00

9 Pek. Ringbalk dan balok Lisplank = 10/20 0.89 m³


-Beton mutu (K 225) 0.89 m³ A.4.1.1.7. 1,155,342.92 1,028,255.20
- Begisting balok 26.70 m² A.4.1.1.23. 463,353.00 12,371,525.10
- Besi Polos Ø 12mm 158.02 kg A.4.1.1.17.a. 15,199.80 2,401,891.85
- Besi beugel Polos Ø 6mm 158.02 kg A.4.1.1.17.a. 15,199.80 2,401,891.85

10 Pek. Beton Balok Plat = 15/40 6.60 m³


-Beton mutu (K 225) 6.60 m³ A.4.1.1.7. 1,155,342.92 7,625,263.28
- Begisting balok 121.00 m² A.4.1.1.23. 463,353.00 56,065,713.00
- Besi Polos D 13mm 1,146.07 kg A.4.1.1.17. 16,354.80 18,743,802.88
- Besi beugel Polos Ø 10mm 452.10 kg A.4.1.1.17.a. 15,199.80 6,871,829.58

11 Pek. Beton Balok Plat = 15/30 5.11 m³


-Beton mutu (K 225) 5.11 m³ A.4.1.1.7. 1,155,342.92 5,900,913.97
- Begisting balok 79.45 m² A.4.1.1.23. 463,353.00 36,813,395.85
- Besi Polos D 13mm 1,064.29 kg A.4.1.1.17. 16,354.80 17,406,176.95
- Besi beugel Polos Ø 10mm 373.19 kg A.4.1.1.17.a. 15,199.80 5,672,382.96

12 Pek. Beton balok Latei = 10/15 0.45 m³


-Beton mutu (K 225) 0.45 m³ A.4.1.1.7. 1,155,342.92 519,904.31
- Begisting balok 15.00 m² A.4.1.1.23. 463,353.00 6,950,295.00
- Besi Polos Ø 10mm 73.98 kg A.4.1.1.17.a. 15,199.80 1,124,481.20
- Besi beugel Polos Ø 6mm 19.53 kg A.4.1.1.17.a. 15,199.80 296,863.04

13 Pek. Plat Lantai beton t. 12 cm 25.56 m³


-Beton mutu (K 225) 25.56 m³ A.4.1.1.7. 1,155,342.92 29,530,565.05
- Begisting lantai 213.00 m² A.4.1.1.24. 269,203.00 57,340,239.00
- Besi Polos Ø 10mm 2,386.46 kg A.4.1.1.17.a. 15,199.80 36,273,754.99

14 Pek. Plat Level beton t. 9 cm 0.81 m³


-Beton mutu (K 225) 0.81 m³ A.4.1.1.7. 1,155,342.92 935,827.77
- Begisting lantai 10.13 m² A.4.1.1.24. 269,203.00 2,725,680.38
- Besi Polos Ø 8mm 72.60 kg A.4.1.1.17.a. 15,199.80 1,103,539.59

b. PEKERJAAN BETON LANTAI II


15 Pek. Kolom 25/25 4.70 m³
-Beton mutu (K 225) 4.70 m³ A.4.1.1.7. 1,155,342.92 5,430,111.73
- Begisting kolom 75.20 m² A.4.1.1.22. 204,963.00 15,413,217.60
- Besi Polos Ø 16mm 1,186.84 kg A.4.1.1.17.a. 15,199.80 18,039,677.13
- Besi beugel Polos Ø 8mm 178.03 kg A.4.1.1.17.a. 15,199.80 2,705,951.57

16 Pek. Kolom 20/20 4.51 m³


-Beton mutu (K 225) 4.51 m³ A.4.1.1.7. 1,155,342.92 5,212,907.26
- Begisting kolom 112.80 m² A.4.1.1.22. 204,963.00 23,119,826.40
- Besi Polos Ø 13mm 940.20 kg A.4.1.1.17.a. 15,199.80 14,290,806.73
- Besi beugel Polos Ø 8mm 267.04 kg A.4.1.1.17.a. 15,199.80 4,058,927.35

17 Pek. Kolom Praktis = 11 x 11 18.33 m' A.4.1.1.35. 93,878.40 1,721,104.00

18 Pek. Beton Balok Plat = 15/30 3.06 m³


-Beton mutu (K 225) 3.06 m³ A.4.1.1.7. 1,155,342.92 3,535,349.34
- Begisting balok 61.20 m² A.4.1.1.23. 463,353.00 28,357,203.60
- Besi Polos D 13mm 566.79 kg A.4.1.1.17. 16,354.80 9,269,662.51
- Besi beugel Polos Ø 10mm 223.58 kg A.4.1.1.17.a. 15,199.80 3,398,432.08
19 Pek. Beton Balok Plat = 13/30 0.95 m³
-Beton mutu (K 225) 0.95 m³ A.4.1.1.7. 1,155,342.92 1,091,799.06
- Begisting balok 18.90 m² A.4.1.1.23. 463,353.00 8,757,371.70
- Besi Polos D 13mm 175.04 kg A.4.1.1.17. 16,354.80 2,862,689.89
- Besi beugel Polos Ø 10mm 65.60 kg A.4.1.1.17.a. 15,199.80 997,040.00

20 Pek. Plat Level beton t. 10 cm 7.80 m³


-Beton mutu (K 225) 7.80 m³ A.4.1.1.7. 1,155,342.92 9,011,674.78
- Begisting lantai 78.00 m² A.4.1.1.24. 269,203.00 20,997,834.00
- Besi Polos Ø 8mm 873.92 kg A.4.1.1.17.a. 15,199.80 13,283,346.90

21 Pek. Ringbalk = 10/20 2.04 m³


-Beton mutu (K 225) 2.04 m³ A.4.1.1.7. 1,155,342.92 2,356,899.56
- Begisting balok 61.20 m² A.4.1.1.23. 463,353.00 28,357,203.60
- Besi Polos Ø 12mm 362.21 kg A.4.1.1.17.a. 15,199.80 5,505,459.97
- Besi beugel Polos Ø 6mm 81.50 kg A.4.1.1.17.a. 15,199.80 1,238,728.49
Jumlah IV 716,544,251.43
V. PEKERJAAN KAYU ATAP DAN PLAFOND
1 Pek. Rangka Kap Gording 6/12 1.04 m³ A.4.6.1.15. 10,997,085.00 11,401,777.73
2 Pas. Rangka atap Usuk 5/7 dan reng 3/4 648.00 m² A.4.6.1.16 121,000.00 78,408,000.00
3 Pas. Atap genteng Plat 648.00 m² A.4.5.2.30. 128,117.00 83,019,816.00
4 Bubungan Atap genteng Plat 10.60 m' A.4.5.2.34. 152,805.40 1,619,737.24
5 Pas. Calsiplank 1/20 69.00 m' A.4.6.1.5b 56,358.50 3,888,736.50
5 Pas. Plafond Gifsum t.9mm Rangka besi Hollow 72.00 m² A.4.5.1.10.b 210,683.00 15,169,176.00
6 Pas. List plafond gipsum C10 150.00 m¹ A.4.5.1.9.a. 24,755.50 3,713,325.00
Jumlah V 197,220,568.47
VI. PEKERJAAN LANTAI
a. Pekerjaan Keramik Lantai I
1 Pas. Lantai keramik 40x40cm 175.50 m² A.4.4.3.35.b 238,848.50 41,917,911.75
2 Pas. Lantai keramik 25x25cm km/wc 22.50 m² A.4.4.3.35.a 282,161.00 6,348,622.50
3 Pas. Dinding keramik 25x40cm km/wc 78.00 m¹ A.4.4.3.54.b 366,544.20 28,590,447.60
4 Pas. Lantai keramik tangga 30x30cm 6.27 m² A.4.4.3.35.a 282,161.00 1,769,149.47
b. Pekerjaan Keramik Lantai II
4 Pas. Lantai keramik 40x40cm 175.50 m² A.4.4.3.35.b 238,848.50 41,917,911.75
5 Pas. Lantai keramik 25x25cm km/wc 22.50 m² A.4.4.3.35.a 282,161.00 6,348,622.50
6 Pas. Dinding keramik 25x40cm km/wc 78.00 m¹ A.4.4.3.54.b 366,544.20 28,590,447.60
Jumlah VI 155,483,113.17
VII PEKERJAAN KUSEN PINTU/JENDELA
a. Pekerjaan Kusan/Pintu Lantai I
1 Pek. Kusen Pintu/Jendela kayu klas I 1.24 m³ A.4.6.1.1. 17,014,525.00 21,026,209.70
2 Pek. Daun Pintu Panil 17.22 m² A.4.6.1.5. 773,987.50 13,328,064.75
3 Pek. Daun Pintu PVC km/wc 10.00 bh Ls 1,500,000.00 15,000,000.00
4 Pek. Daun Jendela kaca 3mm 20.04 m² A.4.6.1.6. 632,335.00 12,671,993.40
5 Pek. kaca 3mm 1.76 m² A.4.6.2.16 189,073.55 332,769.45
b. Pekerjaan Kusan/Pintu Lantai II
1 Pek. Kusen Pintu/Jendela kayu klas I 1.24 m³ A.4.6.1.1. 17,014,525.00 21,026,209.70
2 Pek. Daun Pintu Panil 17.22 m² A.4.6.1.5. 773,987.50 13,328,064.75
3 Pek. Daun Pintu PVC km/wc 10.00 bh Ls 1,500,000.00 15,000,000.00
4 Pek. Daun Jendela kaca 3mm 20.04 m² A.4.6.1.6. 632,335.00 12,671,993.40
5 Pek. kaca 3mm 1.76 m² A.4.6.2.16 189,073.55 332,769.45
Jumlah VII 124,718,074.61
VIII. PEKERJAAAN INSTALASI LISTRIK
a. Instalasi Listrik Lt. I
1 Panel Box + MCB 1.000 unit ME.8 633,105.00 633,105.00
2 Titik Lampu 32.000 unit Ls.Inst.1 184,387.50 5,900,400.00
3 Lampu SL14 watt 22.000 bh ME.5 64,570.00 1,420,540.00
4 Lampu pijar 15 watt 10.000 bh ME.5 48,070.00 480,700.00
5 Stop kontak tanam engkle 10.000 bh ME.1 100,870.00 1,008,700.00
6 Saklar Tunggal 10.000 bh ME.2 75,570.00 755,700.00
7 Saklar Ganda 10.000 bh ME.3 78,870.00 788,700.00
b. Instalasi Listrik Lt. II
1 Panel Box + MCB 1.000 unit ME.8 633,105.00 633,105.00
2 Titik Lampu 32.000 unit Ls.Inst.1 184,387.50 5,900,400.00
3 Lampu SL14 watt 22.000 bh ME.5 64,570.00 1,420,540.00
4 Lampu pijar 15 watt 10.000 bh ME.7 48,070.00 480,700.00
5 Stop kontak tanam engkle 10.000 bh ME.1 100,870.00 1,008,700.00
6 Saklar Tunggal 10.000 bh ME.2 75,570.00 755,700.00
7 Saklar Ganda 10.000 bh ME.3 78,870.00 788,700.00
Jumlah VIII 21,975,690.00
IX. PEKERJAAN INSTALASI AIR BERSIH DAN AIR KOTOR
a. Instalasi Air Bersih dan Air Kotor KM/WC
1 Pas. Pipa PVC Ø 3'' (dari km/wc ke peresapan) 32.000 m' A.5.1.1.31. 97,810.90 3,129,948.80
2 Pas. Pipa PVC Ø 4'' (ke septiktank) 32.000 m' A.5.1.1.32. 139,583.40 4,466,668.80
3 Pek. Pipa air bersih 3/4" 101.000 m' A.5.1.1.20. 36,592.60 3,695,852.60
4 Pekerjaan Septiktank konsruksi beton plat t. 10cm 4.000 unit A.5.1.1.38. 5,319,174.69 21,276,698.75
5 Pekerjaan Peresapan 4.000 unit A.5.1.1.39. 3,741,319.54 14,965,278.18
6 Closed Duduk 10.000 unit A.5.1.1.1. 2,838,550.00 28,385,500.00
7 Bak Mandi Fibre 10.000 unit A.5.1.1.7. 1,262,954.00 12,629,540.00
8 Wastapel 10.000 unit A.5.1.1.5. 1,251,074.00 12,510,740.00
9 Pek. Kran Air dia 1/2" 10.000 bh A.5.1.1.19. 71,420.25 714,202.50
10 Pek. Flor drain 10.000 bh A.5.1.1.14. 36,894.00 368,940.00
b. Instalasi Air Bersih, Grountank dan bak Penampung Air
11 Pekerjaan Grountank kapasitas 1,2 m3 1.000 unit A.5.1.1.40. 4,765,689.19 4,765,689.19
12 Pas. Water tank Steinles 1000 liter (merk Penguin) 1.000 unit A.8.4.4.12.d 4,939,045.10 4,939,045.10
13 Pompa Air Jet Pump Simizu - Pc 260 BIT - 250 Watt 1.000 unit A.8.4.4.12.c 2,464,045.10 2,464,045.10
Merk Shimizu - PC 260 BIT - 250 watt (otomatis)
Daya Output Listrik = 250 Watt
Daya Infut Star = 500 Watt
Daya Hisap = 30 m (15 m dr permukaan air)
Debit Air = 75 liter/menit
Inlet = 1 1/2 dan 1 Inch
Outlet = 1 Inch
14 Pek. Pipa inlet pvc 1 1/2" 12.000 m' A.5.1.1.20.a 77,512.60 930,151.20
15 Pek. Pipa outlet pvc 1" 8.000 m' A.5.1.1.20.b 41,707.60 333,660.80
16 Pek. Pipa overplow pvc 1 1/2" 12.200 m' A.5.1.1.20.a 77,512.60 945,653.72
17 Pas. Stop kran 1 1/2" 1.000 unit Ls 350,000.00 350,000.00
18 Radar Air otomatis 1.000 unit Ls 215,000.00 215,000.00
Jumlah X 117,086,614.74
X. PEKERJAAN BESI DAN PENGUNCI
1 Memasang Engsel Pintu 30.000 bh A.6.6.2.5. 63,806.60 1,914,198.00
2 Memasang kunci tanam ( 2 slaag ) 10.000 bh A.6.6.2.2. 199,801.00 1,998,010.00
3 Memasang engsel jendela 40.000 bh A.6.6.2.6. 32,450.00 1,298,000.00
4 Memasang Grendel jendela 20.000 bh A.6.6.2.11. 23,320.00 466,400.00
5 Memasang kait angin 40.000 bh A.6.6.2.7. 54,076.00 2,163,040.00
6 Memasang grendel pintu expenolet bh Ls 27,000.00 -
Jumlah XI 7,839,648.00
XI. PEKERJAAN PENGECATAN LANTAI I & LANTAI II
1 Pek. Cat Tembok mutu Menengah 1,596.480 m² A.4.7.1.10. 32,984.05 52,658,376.14
5 Pek. Cat Plafond mutu Menengah 144.000 m² A.4.7.1.10. 32,984.05 4,749,703.20
6 Pek. Cat Kayu kusen dan Listplank 89.139 m² A.4.7.1.4. 37,838.46 3,372,874.92
Jumlah XI 60,780,954.26