REKAPITULASI RAB

PROGRAM : PEMBANGUNAN GEDUNG KESEHATAN


KEGIATAN : PEMBANGUNAN INTERNATIONAL SMART HOSPITAL
PEKERJAAN : PEMBANGUNAN RUMAH PERAWAT TYPE 45 ( 1 unit )
LOKASI : PRINGGABAYA KEC. PRINGGABAYA KAB. LOMBOK TIMUR
TAHUN ANGGARAN : 2021

NO JENIS PEKERJAAN JUMLAH TOTAL

1 2 3
I PEKERJAAN PERSIAPAN 2,129,688.00
II PEKERJAAN TANAH DAN URUGAN 8,381,934.00
III PEKERJAAN PASANGAN DAN PLESTERAN 72,315,219.61
IV PEKERJAAN BETON 52,407,131.16
V PEKERJAAN KAYU ATAP DAN PLAFOND 44,966,648.06
VI PEKERJAAN LANTAI 15,794,604.76
VII PEKERJAAN KUSEN PINTU/JENDELA 17,429,225.28
VIII. PEKERJAAAN INSTALASI LISTRIK 3,742,150.50
IX. PEKERJAAN INSTALASI AIR BERSIH DAN AIR KOTOR 14,391,704.73
X. PEKERJAAN BESI DAN PENGUNCI 4,054,824.00
XI. PEKERJAAN PENGECATAN 12,872,532.54
REAL COST 1 UNIT Rp. 248,485,662.65
PAJAK / PPN 10 % Rp. 24,848,566.27
TOTAL JUMLAH BIAYA Rp. 273,334,228.92
PEMBULATAN Rp. 273,334,000.00
TERBILANG : DUA RATUS TUJUH PULUH TIGA JUTA TIGA RATUS TIGA PULUH EMPAT RIBU RUPIAH

Lombok Timur, Maret 2021


Disetujui Oleh : Dibuat Oleh :
PT. NABIL SURYA PERSADA/INVESTMEN Konsultan Nemo Partner
PERWAKILAN REGIONAL 7 PROVINSI NTB CV. ADIJAYA KONSULTAN

KUSAIBAH RURROZIKI SUHARDI, ST


Kepala Perwakilan Direktur
Mengetahui :
RENCANA ANGGARAN BIAYA (RAB)
PROGRAM : PEMBANGUNAN GEDUNG KESEHATAN
KEGIATAN : PEMBANGUNAN INTERNATIONAL SMART HOSPITAL
PEKERJAAN : PEMBANGUNAN RUMAH PERAWAT TYPE 45 ( 1 unit )
LOKASI : PRINGGABAYA KEC. PRINGGABAYA KAB. LOMBOK TIMUR
TAHUN : 2021

HARGA
KODE JUMLAH HARGA
NO URAIAN PEKERJAAN VOLUME SAT. SATUAN
ANALISA
(Rp.) (Rp.)
1 2 3 4 5 6 7
I. PEKERJAAN PERSIAPAN
1 Pek. Uitzet & Bouplank 26.00 m¹ A.2.2.1.4. 52,668.00 1,369,368.00
2 Pek. Pembersihan awal sampai akhir 48.00 m² A.2.2.1.9. 15,840.00 760,320.00

Jumlah I 2,129,688.00
II. PEKERJAAN TANAH DAN URUGAN
1 Pek. Galian tanah pondasi keliling 46.20 m³ A.2.3.1.1. 72,600.00 3,354,120.00
2 Pek. Urugan tanah kembali 5.04 m³ A.2.3.1.9. 52,800.00 266,112.00
3 Pek. Urugan tanah dalam bangunan 15.45 m³ A.2.3.1.14. 171,600.00 2,651,220.00
4 Pek. Urugan pasir bawah pondasi dan bawah lantai 9.35 m³ A.2.3.1.11. 225,720.00 2,110,482.00
Jumlah II 8,381,934.00
III. PEKERJAAN PASANGAN DAN PLESTERAN
1 Pek. Batu kosong 8.40 m³ A.3.2.1.9. 435,223.80 3,655,879.92
2 Pek. Pasangan pondasi batu kali 1:5 18.48 m³ A.3.2.1.3. 783,147.20 14,472,560.26
3 Pek. Pas. Trasraam 1/2 bata 1:3 16.72 m³ A.4.4.1.8. 139,098.52 2,325,727.25
4 Pek. Pas. Trasraam 1 bata 1:3 teras 1.60 m³ A.4.4.1.2. 284,680.00 455,488.00
5 Pek. Pasangan dinding 1/2 bata 1pc:5psr 150.68 m² A.4.4.1.10. 132,082.28 19,902,157.95
6 Pek. Plesteran trasraam 1pc:3psr 33.44 m² A.4.4.2.3. 63,898.30 2,136,759.02
7 Pek. Plesteran dinding 301.36 m² A.4.4.2.5. 60,575.06 18,254,901.29
8 Pek. Acian dinding bata merah 301.36 m² A.4.4.2.27. 36,872.00 11,111,745.92
Jumlah III 72,315,219.61
IV. PEKERJAAN BETON -
1 Pek. Beton Lantai Kerja t. 10 cm 0.40 m³
-Beton mutu (K 100) 0.40 m³ A.4.1.1.1. 982,369.93 392,947.97

2 Pek. Poot Plat 100 x 100, P1 = 4 bh 1.10 m³


-Beton mutu (K 225) 1.10 m³ A.4.1.1.7. 1,155,342.92 1,270,877.21
- Begisting 3.20 m² A.4.1.1.20. 180,906.00 578,899.20
- Besi Polos dia 10mm 78.91 kg A.4.1.1.17.a. 15,199.80 1,199,446.62

3 Pek. Sloof = 15/20 1.25 m³


-Beton mutu (K 225) 1.25 m³ A.4.1.1.7. 1,155,342.92 1,448,800.02
- Begisting sloof 16.72 m² A.4.1.1.17. 16,354.80 273,452.26
- Besi Polos Ø 10mm 103.08 kg A.4.1.1.17.a. 15,199.80 1,566,777.14
- Besi beugel Polos Ø 6mm 37.11 kg A.4.1.1.17.a. 15,199.80 564,039.77

4 Pek. Kolom 13/20 0.49 m³


-Beton mutu (K 225) 0.49 m³ A.4.1.1.7. 1,155,342.92 564,731.62
- Begisting kolom 12.41 m² A.4.1.1.22. 204,963.00 2,543,180.90
- Besi Polos Ø 12mm 66.76 kg A.4.1.1.17.a. 15,199.80 1,014,731.84
- Besi beugel Polos Ø 8mm 29.67 kg A.4.1.1.17.a. 15,199.80 450,991.93

5 Pek. Kolom Praktis = 11 x 11 96.00 m' A.4.1.1.35. 93,878.40 9,012,326.40

6 Pek. Beton balok Sunscren = 10/20 0.18 m³


-Beton mutu (K 225) 0.18 m³ A.4.1.1.7. 1,155,342.92 207,961.73
- Begisting balok 5.40 m² A.4.1.1.23. 463,353.00 2,502,106.20
- Besi Polos Ø 10mm 22.19 kg A.4.1.1.17.a. 15,199.80 337,344.36
- Besi beugel Polos Ø 6mm 22.19 kg A.4.1.1.17.a. 15,199.80 337,344.36

7 Pek. Beton Balok Plat = 15/20 0.45 m³


-Beton mutu (K 225) 0.45 m³ A.4.1.1.7. 1,155,342.92 519,904.31
- Begisting balok 10.50 m² A.4.1.1.23. 463,353.00 4,865,206.50
- Besi Polos Ø 12mm 53.27 kg A.4.1.1.17.a. 15,199.80 809,626.47
- Besi beugel Polos Ø 6mm 13.32 kg A.4.1.1.17.a. 15,199.80 202,406.62
8 Pek. Beton ringbalk = 10/15 0.99 m³
-Beton mutu (K 225) 0.99 m³ A.4.1.1.7. 1,155,342.92 1,143,789.49
- Begisting balok 19.80 m² A.4.1.1.23. 463,353.00 9,174,389.40
- Besi Polos Ø 10mm 122.07 kg A.4.1.1.17.a. 15,199.80 1,855,393.99
- Besi beugel Polos Ø 6mm 39.55 kg A.4.1.1.17.a. 15,199.80 601,147.65

9 Pek. Beton balok Latei = 10/15 0.23 m³


-Beton mutu (K 225) 0.23 m³ A.4.1.1.7. 1,155,342.92 259,952.16
- Begisting balok 7.50 m² A.4.1.1.23. 463,353.00 3,475,147.50
- Besi Polos Ø 10mm 36.99 kg A.4.1.1.17.a. 15,199.80 562,240.60
- Besi beugel Polos Ø 6mm 9.77 kg A.4.1.1.17.a. 15,199.80 148,431.52

10 Pek. Beton balok gevel = 10/13 27.60 m' A.4.1.1.35. 93,878.40 2,591,043.84

11 Pek. Plat Level beton t. 9 cm 0.33 m³


-Beton mutu (K 225) 0.33 m³ A.4.1.1.7. 1,155,342.92 379,530.15
- Begisting lantai 4.11 m² A.4.1.1.24. 269,203.00 1,105,414.82
- Besi Polos Ø 8mm 29.44 kg A.4.1.1.17.a. 15,199.80 447,546.61
Jumlah IV 52,407,131.16
V. PEKERJAAN KAYU ATAP DAN PLAFOND
1 Pek. Rangka Kap Gording 6/12 0.19 m³ A.4.6.1.15. 10,997,085.00 2,090,325.92
2 Pas. Rangka atap Usuk 5/7 dan reng 3/4 84.73 m² A.4.6.1.16 121,000.00 10,252,814.00
3 Pas. Atap genteng Plat 84.73 m² A.4.5.2.30. 128,117.00 10,855,865.88
4 Bubungan Atap genteng Plat 9.00 m' A.4.5.2.34. 152,805.40 1,375,248.60
5 Pas. Calsiplank 1/20 53.06 m' A.4.6.1.5b 56,358.50 2,990,382.01
5 Pas. Plafond Gifsum t.9mm Rangka besi Hollow 74.42 m² A.4.5.1.10.b 210,683.00 15,679,028.86
6 Pas. List plafond gipsum C10 69.60 m¹ A.4.5.1.9.a. 24,755.50 1,722,982.80
Jumlah V 44,966,648.06
VI. PEKERJAAN LANTAI
1 Pas. Lantai keramik 40x40cm 51.50 m² A.4.4.3.35.b 238,848.50 12,300,697.75
2 Pas. Lantai keramik 25x25cm km/wc 2.25 m² A.4.4.3.35.a 282,161.00 634,862.25
3 Pas. Dinding keramik 25x40cm km/wc 7.80 m¹ A.4.4.3.54.b 366,544.20 2,859,044.76
Jumlah VI 15,794,604.76
VII PEKERJAAN KUSEN PINTU/JENDELA
1 Pek. Kusen Pintu/Jendela kayu klas I 0.44 m³ A.4.6.1.1. 17,014,525.00 7,409,825.64
2 Pek. Daun Pintu Panil 8.61 m² A.4.6.1.5. 773,987.50 6,664,032.38
3 Pek. Daun Jendela kaca 3mm 5.28 m² A.4.6.1.6. 632,335.00 3,338,728.80
4 Pek. kaca 3mm 0.09 m² A.4.6.2.16 189,073.55 16,638.47
Jumlah VII 17,429,225.28
VIII. PEKERJAAAN INSTALASI LISTRIK
1 Panel Box + MCB 1.000 unit ME.8 633,105.00 633,105.00
2 Titik Lampu 9.000 unit Ls.Inst.1 184,387.50 1,659,487.50
3 Lampu SL14 watt 9.000 bh ME.5 64,570.00 581,130.00
4 Stop kontak tanam engkle 3.000 bh ME.1 100,870.00 302,610.00
5 Saklar Tunggal 5.400 bh ME.2 75,570.00 408,078.00
6 Saklar Ganda 2.000 bh ME.3 78,870.00 157,740.00
Jumlah VIII 3,742,150.50
IX. PEKERJAAN INSTALASI AIR BERSIH DAN AIR KOTOR
1 Pas. Pipa PVC Ø 3'' (dari km/wc ke peresapan) 12.000 m' A.5.1.1.31. 97,810.90 1,173,730.80
2 Pas. Pipa PVC Ø 4'' (ke septiktank) 12.000 m' A.5.1.1.32. 139,583.40 1,675,000.80
3 Pek. Pipa air bersih 3/4" 14.000 m' A.5.1.1.20. 36,592.60 512,296.40
4 Pekerjaan Septiktank konsruksi beton plat t. 10cm 1.000 unit A.5.1.1.38. 5,319,174.69 5,319,174.69
5 Pekerjaan Peresapan 1.000 unit A.5.1.1.39. 3,741,319.54 3,741,319.54
6 Closed Jongkok Porselin 1.000 unit A.5.1.1.2. 527,494.00 527,494.00
7 Bak Mandi Fibre 1.000 unit A.5.1.1.7. 1,262,954.00 1,262,954.00
8 Pek. Kran Air dia 1/2" 2.000 bh A.5.1.1.19. 71,420.25 142,840.50
9 Pek. Flor drain 1.000 bh A.5.1.1.14. 36,894.00 36,894.00
Jumlah X 14,391,704.73
X. PEKERJAAN BESI DAN PENGUNCI
1 Memasang Engsel Pintu 15.000 bh A.6.6.2.5. 63,806.60 957,099.00
2 Memasang kunci tanam ( 2 slaag ) 5.000 bh A.6.6.2.2. 199,801.00 999,005.00
3 Memasang engsel jendela 20.000 bh A.6.6.2.6. 32,450.00 649,000.00
4 Memasang Grendel jendela 10.000 bh A.6.6.2.11. 23,320.00 233,200.00
5 Memasang kait angin 20.000 bh A.6.6.2.7. 54,076.00 1,081,520.00
6 Memasang grendel pintu expenolet 5.000 bh Ls 27,000.00 135,000.00
Jumlah XI 4,054,824.00
XI. PEKERJAAN PENGECATAN
1 Pek. Cat Tembok mutu Menengah 301.360 m² A.4.7.1.10. 32,984.05 9,940,073.31
5 Pek. Cat Plafond mutu Menengah 74.420 m² A.4.7.1.10. 32,984.05 2,454,673.00
6 Pek. Cat Kayu kusen dan Listplank 12.627 m² A.4.7.1.4. 37,838.46 477,786.23
Jumlah XI 12,872,532.54