Anda di halaman 1dari 5

PEKERJAAN : JASA KONSTRUKSI TERINTEGRASI RANCANG BANGUN (DESIGN AND BUILD)

JALAN TOL SOLO - YOGYAKARTA - NYIA KULON PROGO


PAKET : PAKET 1.2A
RUAS : KLATEN - PURWOMARTANI
STA : STA 32+300 - STA 33+000

Harga Satuan Jumlah Harga


No Item Item Pekerjaan Satuan Volume
(Rp.) (Rp.)

A PEKERJAAN PELAKSANAAN
BAB 1 UMUM
JUMLAH BAB 1 -

BAB 2 PEMBERSIHAN TEMPAT KERJA


2.01 (1) Pembersihan Tempat Kerja m2 2,500.00 3,798.00 9,495,000.00
2.01 (3) Penebangan Pohon bh -
-
JUMLAH BAB 2 9,495,000.00

BAB 3 PEMBONGKARAN
3.01(1b) Pembongkaran Beton (Perkerasan) m3 500.00 176,000.00 88,000,000.00
3.01 (5) Pembongkaran Rumah m2 -
JUMLAH BAB 3 88,000,000.00

BAB 4 PEKERJAAN TANAH


4.03 (1) Galian Biasa untuk Timbunan m3 -
4.03 (3) Galian Dibuang m3 -
4.05 (1) Common Borrow Material m3 -
4.05 (2) Selected Borrow Material (Urugan Pasir) m3 1,750.00 121,000.00 211,750,000.00
4.09 Urugan Material Berbutir (Granular Backfill) m3 -
4.11 (2) Geotextile Seprator (Kelas 1) m2 1.00 9,500.00 9,500.00
JUMLAH BAB 4 211,759,500.00
Harga Satuan Jumlah Harga
No Item Item Pekerjaan Satuan Volume
(Rp.) (Rp.)

BAB 5 GALIAN STRUKTUR


5.01 (1) Galian Struktur Kedalaman < 2m m3 875.00 37,171.00 32,524,625.00
5.01 (2) Galian Struktur Kedalaman 2 - 4 m m3 1.00 41,109.00 41,109.00

JUMLAH BAB 5 32,565,734.00

BAB 10 STRUKTUR BETON


10.01(4a) Beton Kelas B-1-1a (Lantai Beton Bertulang dari Gelagar Beton Pratekan U/I) m3 -
10.01(4a). Beton Kelas B-1-1a (Struktur Lantai Elevated) m3 - -
10.01(3c) Beton Kelas B-1-3 (Kepala Pier Beton Bertulang) m3 -
10.01(3c). Beton Kelas B-1-3 (Struktur Pierhead Elevated) m3 - -
10.01(7f) Beton Kelas B-1-4f (Kolom Beton Bertulang dari Pier) m3 -
10.01(7f). Beton Kelas B-1-4f (Kolom Beton Bertulang dari Pier,Elevated) m3 - -
SS. 10.01(7f1) Fasade Elevated Pilar - -
10.01(10) Beton Kelas C-1 (Abutment, Telapak Pier, Box, Wingwall) m3 -
10.01(10). Beton Kelas C-1 (Struktur Telapak Pier Elevated) m3 - -
10.01(11) Beton Kelas C-2 (Box Culvert, Plat Injak) m3 4,541.00 1,889,300.00 8,579,311,300.00

10.01(14) Beton Kelas E m3 89.00 1,051,771.00 93,607,619.00

10.02 (3) Batang Baja Tulangan Sirip BjTS 420A kg 618,000.00 12,350.00 7,632,300,000.00
10.03 (13c1) Gelagar PCI bentang nominal 15,10m to 17m H=1,4m, penyediaan unit -
10.03 (13c2) Gelagar PCI bentang nominal 15,10m to 17m H=1,4m, pemasangan unit -
10.03 (14a) Gelagar PCI bentang nominal 25,0m to 27m H=1,6m, penyediaan unit - -
10.03 (14b) Gelagar PCI bentang nominal 25,0m to 27m H=1,6m, pemasangan unit - -
10.03 (15a) Gelagar PCI bentang nominal 30,0m to 32m H=1,7m, penyediaan unit - -
10.03 (15b) Gelagar PCI bentang nominal 30,0m to 32m H=1,7m, pemasangan unit - -
10.03 (16a1) Gelagar PCI bentang nominal 20,0m to 22m H=2,1m, penyediaan unit - -
10.03 (16a2) Gelagar PCI bentang nominal 20,0m to 22m H=2,1m, pemasangan unit - -
10.03 (16b1) Gelagar PCI bentang nominal 39,0m to 41m H=2,1m, penyediaan unit -
10.03 (16b2) Gelagar PCI bentang nominal 39,0m to 41m H=2,1m, pemasangan unit -
10.03 (16b1). Gelagar PCI bentang nominal 39,0m to 41m H=2,1m, penyediaan (Elevated) unit - -
10.03 (16b2). Gelagar PCI bentang nominal 39,0m to 41m H=2,1m, pemasangan (Elevated) unit - -
SS.10.03 (17b1) Gelagar PCI bentang nominal 50m H=2,3m, penyediaan unit - -
SS.10.03 (17b2) Gelagar PCI bentang nominal 50m H=2,3m, pemasangan unit - -
SS.10.03 (17b7) Precast Diafragma Girder unit -
Ss 10.03.(19) Galvanized Metal Formwork (Bondek) m2 -
SS. 10.05 (4a) Penyediaan Minipile Triangel 32 x 32 m' - -
SS.10.05 (4b) Pemancangan Minipile Triangel 32 x 32 m' - -
10.07 (1a) Tiang Cor Beton Cast-in-Place D=100cm dengan pemantauan ultrasonik m' -
SS.10.07 (4 b) Tiang Cor Beton Cast-in-Place D=200cm m' - -
Harga Satuan Jumlah Harga
No Item Item Pekerjaan Satuan Volume
(Rp.) (Rp.)

10.10 (2) Sambungan Siar Muai Tipe B (Adhesive Sealant Joint) m' -
SS 10.11 (7A) Elastomeric Bearing Pad 500 x 400 bh -
Harga Satuan Jumlah Harga
No Item Item Pekerjaan Satuan Volume
(Rp.) (Rp.)

SS 10.11 (7B) Elastomeric Bearing Pad 500 x 400 (Lead Rubber Bearing) bh - -
SS.10.11 (27a) Angkur dan Aksesoris (Fix/Move) unit -
10.12 (1) Pipa Drainase D=20cm dengan fitting dan penompang m' -
10.12 (3) Deck Drain Tipe 1 dengan pelengkapan unit -
JUMLAH BAB 10 16,305,218,919.00
TOTAL 16,647,039,153.00
PPN 11% 1,831,174,306.83
JUMLAH TOTAL 18,478,213,459.83
PEMBULATAN 18,478,213,000.00
Harga Beton JKB (diluar Ppn)

Klas P (FS-45) = 905,900.00


Klas B2 (FC-30) = 925,600.00
Klas B1 (FC-30) = 914,800.00
Klas C1 (FC-25) = 846,000.00
Klas C2 (FC-25) = 867,600.00
Klas D = 781,600.00
Klas E = 744,800.00
Klas B0 (Lean Concrete) = 675,900.00