RENCANA ANGGARAN BIAYA

PEMBANGUNAN SARANA IBADAH (MUSHALLA)


SDN 1 PEKANTINGAN
No PEKERJAAN Qty Sat HARGA SATUAN JUMLAH
I. Pekerjaan Tanah
1 Galian tanah pondasi Lajur step batas suci 2.8 m³ Rp 75,000.00 Rp 210,000.00
2 Urugan & Pemadatan manual ruang dalam 14 m³ Rp 107,142.85 Rp 1,499,999.90
3 Urugan pasir 1.8 m³ Rp 217,200.00 Rp 390,960.00
Rp 2,100,959.90
II. Pekerjaan Pasangan
1 Pasangan rollag bata merah 1.6 m³ Rp 926,532.00 Rp 1,482,451.20
2 Pas. Lantai Keramik 40.40 45 m² Rp 142,000.00 Rp 6,390,000.00
Rp 7,872,451.20
III. Pekerjaan Kusen
1 Kusen Alumunium 3" Pintu Kaca 5mm 1 Unit Rp 3,500,000.00 Rp 3,500,000.00
2 Kusen Alumunium 3" Jendela Kaca 5mm 7 Unit Rp 650,000.00 Rp 4,550,000.00
Rp 8,050,000.00
IV. Pekerjaan Atap
1 Pem Kuda-Kuda Baja ringan 57.9 m² Rp 175,000.00 Rp 10,132,500.00
2 Pas Atap Metalroof 57.9 m² Rp 95,000.00 Rp 5,500,500.00
3 Pas Wuwungan 14 m¹ Rp 65,000.00 Rp 910,000.00
4 List plank GRC 20 m¹ Rp 32,500.00 Rp 650,000.00
5 Pas Rangka Plafound Holow Wafer 34.435 m² Rp 78,000.00 Rp 2,685,930.00
6 Pas Plafound Gypsum 34.435 m² Rp 36,400.00 Rp 1,253,434.00
Rp 21,132,364.00
V. Pekerjaan Elektrikal
1 Box MCB 1.00 Ttk Rp 105,000.00 Rp 105,000.00
2 Titik Instalasi Penerangan 4.00 Ttk Rp 90,000.00 Rp 360,000.00
3 Titik Instalasi Daya 4.00 Ttk Rp 80,000.00 Rp 320,000.00
4 Pas. Lamp tunggal 8 / 12 watt 4.00 Set Rp 35,000.00 Rp 140,000.00
5 Stop Kontak 2.00 Bh Rp 22,500.00 Rp 45,000.00
6 Saklar Ganda 2.00 Bh Rp 22,500.00 Rp 45,000.00
Rp 1,015,000.00
VI. Pekerjaan Pengecatan
1 Pengecatan Luar 72.60 m² Rp 30,000.00 Rp 2,178,000.00
2 Pengecatan Dalam Ruang 72.60 m² Rp 25,000.00 Rp 1,815,000.00
3 Pengecatan Plafound 34.43 m² Rp 30,000.00 Rp 1,033,050.00
Rp 5,026,050.00

REKAPITULASI
No PEKERJAAN JUMLAH HARGA
1 I. Pekerjaan Tanah Rp 2,100,959.90
2 II. Pekerjaan Pasangan Rp 7,872,451.20
3 III. Pekerjaan Kusen Rp 8,050,000.00
4 IV. Pekerjaan Atap Rp 21,132,364.00
5 V. Pekerjaan Elektrikal Rp 1,015,000.00
6 VI. Pekerjaan Pengecatan Rp 5,026,050.00
TOTAL BIAYA Rp 45,196,825.10
DIBULATKAN Rp 45,197,000.00
Terbilang :
Kusen jendela mati
M 3" 4 btg
Ambang Z 2 btg
tutup Z 2 btg
Kaca 5mm 140x55 7 lbr
C 3"
Skoneng kcl 1 btg
C 3" 1 btg
Karet skoneng 6m
Daun pintu
B besar 1 btg
Engsel 2 set
Kaca 5mm 195x85 1 lbr
Alexsindo Alko
stoper cassemen 0502B 0502C
frame / daun 0501B 0501C
Bead/ tutup casemen 0503 0503C

Open Back
4" 0402A 0402B
3" 0302A 0302B
Kaca mati
4" 0401A 0401B
3" 0301A 0301B
Tutup kaca mati
4" 0405A 0405B
3" 0305A 0305B
Tutup openback
4" 0406A 0406B
3" 0306A 0306B

Jendela sleding
Rel atas sleding 0601A 0601B
Rel bawah sleding 0604A 0604B
Tatapan samping 0605A 0605B
Tihang kait 0607A 0607B
Tihang sleding 0606A 0606B
Ambang bawah 0603A 0603B

Pintu swing
Tihang engsel 0105A 0105B
Tihang polos 0104A 0104B
Ambang bawah 0102A 0102B
Tutup Ambang bawah 0110A 0110B
Ambang atas
Kusen Pintu+jendela CA
Skoneng kcl 1 btg 58,000 58,000
C 3" 1 btg 143,000 143,000
Karet skoneng pintu 6m 2,000 12,000
Silikon 1 btl 25,000 25,000
M 3" 2m 57,667 115,333
Tutup eM 2m 40,333 80,667
Z 3" 2m 52,333 104,667
Tutup profil Z 2m 21,333 42,667
Karet kaca 12 m 2,000 24,000
Fischer 12 pcs 500 6,000
Rivet 550 4mm 24 pcs 180 4,320
Skrup 6x3/8 12 pcs 180 2,160
Skrup 8x11/2 12 pcs 250 3,000
Kaca 5mm 197,5x95 1 lbr 337,725 337,725
958,538

Daun Pintu CA
B besar 1 btg 287,000 287,000
Rel slidding 1 set 235,000 235,000
Kaca 5mm 195x90 1 lbr 315,900 315,900
Kunci tanam red orchad 1 set 155,000 155,000
Karet kaca 12 m 2,000 24,000
Rivet 550 4mm 16 pcs 180 2,880
Skrup 6x3/8 8 pcs 180 1,440
Skrup 8x11/2 8 pcs 250 2,000
Baut pintu m10 x 1mtr 2 pcs 24,500 49,000
Handle stainless 30cm 1 set 75,000 75,000
1,147,220

2,105,758
2,855,758
4
732,246
6 2 4
2 2 6.5 5 32.5
2 0 6.5 3 19.5
6 2 4 52
1.2 2.8
1.2 1.6
1 0.6
6 1 5
0.5 4.5
0.5 4
6 6 106.95
6 6 Luas 123.4988
2.3 1.7 cnp 82.33256
6 8.25 -2.25 reng 98.79908
6 3.75 skrup 2469.977
paku 96
reng bt m
14 6 0.4 6 2.4 2 2.8 9.55
13.5 6 0.4 6 1.9 2 2.3 9.25
13.2 6 0.4 6 1.7 2 2.1 8.86
12.7 6 0.4 6 1.3 2 1.7 8.46
12.3 6 0.4 6 0.7 2 1.1 8.06
12 6 0.4 6 0 2 0.4 7.66
11.5 6 6 2 0 7.26
11.1 6 6 2 0 6.86
10.7 6 0.4 4.7 1 5.1 6.46
10.3 6 0.4 4.3 1 4.7 6.06
10 6 0.4 4 1 4.4 5.67
9.52 6 0.4 3.52 1 3.92 5.27
9.12 6 0.4 3.12 1 3.52 4.87
8.72 6 0.4 2.72 1 3.12 4.47
8.32 6 0.4 2.32 1 2.72 4.07
7.92 6 0.4 1.92 1 2.32 3.67
7.53 6 0.4 1.53 1 1.93 3.28
7.13 6 0.4 1.13 1 1.53 2.88
6.73 6 0.4 0.73 1 1.13 2.48
6.33 6 0.4 0.33 1 0.73 2.08
5.93 6 1 0 1.68
5.53 5.53 5.53 1.28
5.13 5.13 5.13 0.89
4.74 4.74 4.74 0.49
4.34 4.34 4.34 0.09
65.26
29 12 41 82
6 0.4 3.55 1 3.95
6 0.4 3.25 1 3.65
6 0.4 2.86 1 3.26
6 0.4 2.46 1 2.86
6 0.4 2.06 1 2.46
6 0.4 1.66 1 2.06
6 0.4 1.26 1 1.66
6 0.4 0.86 1 1.26
6 0.4 0.46 1 0.86
6 0.4 0.06 1 0.46
6 1 0
6 1 0
5 1 5
4.5 1 4.5
4.2 1 4.2
4 1 4
3.5 1 3.5
3 1 3
2.5 1 2.5
2.1 1 2.1
2 1 2
1.5 1 1.5
1 1 1
0.5 1 0.5
0.2 1 0.2
56.48
25 10 35 70
RENCANA ANGGARAN BIAYA
RENOVASI ATAP RUMAH TINGGAL 160M2
KARANG ASEM - PEKANTINGAN
No PEKERJAAN Qty Sat HARGA SATUAN JUMLAH
I. Pekerjaan Bongkaran & Finish
1 Bongkar atap lama 14 Hok Rp 135,000.00 Rp 1,890,000.00
2 Pembersihan sisa pekerjaan 7 Hok Rp 135,000.00 Rp 945,000.00
Rp 2,835,000.00
II. Pekerjaan Pasangan
1 Pasangan bata merah 20 m' Rp 82,000.00 Rp 1,640,000.00
Rp 1,640,000.00
III. Pekerjaan Atap
1 Pem Kuda-Kuda Baja ringan 160 m² Rp 120,000.00 Rp 19,200,000.00
2 Pas Atap Metalroof 160 m² Rp 90,000.00 Rp 14,400,000.00
3 Pas Wuwungan 34 m¹ Rp 42,500.00 Rp 1,445,000.00
4 List plank GRC 28 m¹ Rp 32,500.00 Rp 910,000.00
Rp 35,955,000.00

REKAPITULASI
No PEKERJAAN JUMLAH HARGA
1 I. Pekerjaan Bongkaran & Finish Rp 2,835,000.00
2 II. Pekerjaan Pasangan Rp 1,640,000.00
4 III. Pekerjaan Atap Rp 35,955,000.00
TOTAL BIAYA Rp 40,430,000.00