NO Tanggal SPT MA Nama Area Unit Uraian Pekerjaan P/B Durasi Progress Terpasang Terbongkar Tambah No Reg
Pakai Titik
SPT LAMA
5 22-May-23 MA 4 Raga Ananta KPC KPC Untuk support pasang kanopi P 7 100% P P 267/MA4/V/23
10 22-May-23 MA 4 Pras W KPC 84 V 203 Untuk support fit stop P 9 100% P 272/MA2/V/23
21 23-May-23 MA 1 Irvan FOC 1 FOC 1 BL Ex piping B 100% P 283/MA1/V/23
22 23-May-23 MA 1 Irvan FOC 1 10. 12 Ex piping steam B 100% P 284/MA1/V/23
18 11-May-23 MA 2 David M LOC 2 023 PS 119,120,121 Untuk support isolasi dan cat P 100% P 165/MA2/V/23
19 22-May-23 MA 1 Tri Wurtanto LOC 1 21 F 1 Pasang scaffolding P 7 100% P 244/MA1/V/23
20 22-May-23 MA 5 M Syarifudin UTL 051 G 102 Ex outlet surface B 100% P 245/MA5/V/23
21 22-May-23 MA 5 M Syarifudin UTL 052 B 104 Ex bocoran line sot blower B 100% P 246/MA5/V/23
22 22-May-23 MA 5 M Syarifudin UTL 500 PS 18 Ex reinject OLLS B 100% P 247/MA5/V/23
23 22-May-23 MA 5 M Syarifudin UTL 057 E 102 Ex bocoran Cover HE B 100% P 248/MA5/V/23
24 22-May-23 MA 5 M Syarifudin UTL 05 PS 159 ex bocoran B 100% P 249/MA5/V/23
25 22-May-23 MA 5 M Syarifudin UTL 05 Ex line drine condensate B 100% P 250/MA5/V/23
26 22-May-23 MA 5 M Syarifudin UTL 500 PS 03 Ex bocoran flange HP B 100% P 251/MA5/V/23
27 22-May-23 MA 5 M Syarifudin UTL 051 G 101 Ex cleaning condensor B 100% P 252/MA5/V/23
28 22-May-23 MA 5 M Syarifudin UTL 051 G 102 Ex cleaning surface condensor B 100% P 253/MA5/V/23
16 18-May-23 MA 4 M Aji KPC 84 k 202 Untuk perbaikan isolasi P 7 100% P 235/MA4/V/23
14 18-May-23 MA 4 M Aji KPC 84 k 201 Untuk perbaikan isolasi P 7 100% 234/MA4/V/23
11 17-May-23 MA 4 Pras W LOC 3 200 PS 608 Untuk support perbaikan bocoran steam P 4 100% 221/MA4/V/23
12 17-May-23 MA 6 Zidnie Ilma RFCC 101 101 BL Untuk support isolasi P 7 100% P 222/MA6/V/23
9 17-May-23 MA 1 Aziz B LOC 1 24 C 5 Bongkar scaffolding B 100% P 215/MA1/V/23
1 23-May-23 MA 5 Agus W 63 063 P 301 M U/ Support bongkar motor P 7 100% P 285/MA5/V/23
2 23-May-23 MA 3 Widodo 70 73 U/ support perbaikan Leaking style P 7 100% P 286/MA3/V/23
3 23-May-23 MA 3 Widodo 70 72 Ex bongkar perbaikan Line bunker B 100% P 287/MA3/V/23
4 23-May-23 MA 3 Widodo 70 73 Ex bongkar perbaikan LA 73X104 B 100% P 288/MA3/V/23
5 23-May-23 MA 3 Widodo 70 75 Ex bongkar buka blind flange 30" B 100% P 289/MA3/V/23
6 23-May-23 MA 6 Ifanudin RFCC 104 104 Ex bongkar line MPC B 100% P 290/MA6/V/23
7 23-May-23 MA 6 Anugrah RFCC 101 101 FT 067 Ex perbaikan B 100% P 291/MA6/V/23
30 23-May-23 MA 4 Pras W LOC 3 200 PS 618 Bongkar scaffolding B 100% P 281/MA4/V/23
28 23-May-23 MA 2 Salis N FOC 2 01 PS 101 Ex bongkar akses line drain B 100% P 279/MA2/V/23
25 23-May-23 MA 2 Salis N FOC 2 01 PS 151 Ex bongkar akses line drain B 100% P 276/MA2/V/23
23 23-May-23 MA 2 Salis N FOC 2 011 F 101 A Ex chemical cleaning B 100% P 274/MA2/V/23
18 22-May-23 MA 4 Raga Ananta KPC KPC Ex kanopi B 100% P 268/MA4/V/23
19 23-May-23 MA 2 Depta FOC 2 FOC 2 A BL Untuk jumper line 6'' to 3 '' Line SWS P 7 100% P 269/MA2/V/23
20 23-May-23 MA 2 Hendro S LOC 2 002 V 102 Untuk support pipa steam P 7 100% P 270/MA2/V/23
21 23-May-23 MA 2 Depta FOC 2 019 BL Untuk reinjeck OLLS P 7 100% P 271/MA2/V/23
10 16-May-23 MA 3 Yulianto OM 30 31 Untuk support line tie in 12" premium sucti P 7 100% P 226/MA3/V/23
11 19-May-23 MA 6 Yusro RFCC 101 102/PS 005 Untuk perbaikab kabel tray P 100% 242/MA6/V/23
15 22-May-23 MA 4 M Aji KPC 84 PR V 5 perbaikan bocoran steam P 100% P 257/MA4/V/23
15 25-May-23 MA 4 M Aji KPC 87 F 201 Ex bongkar cleaning Box burner B 100% P 306/MA4/V/23
9 24-May-23 MA 3 Widodo 70 70 U/ support pekerjaan line pipa 10" P 10 100% 300/MA3/V/23
10 24-May-23 MA 3 Widodo 70 73 Ex bongkar perbaikan leaking style B 100% 301/MA3/V/23
4 23-May-23 MA 1 Wisnu FOC 1 16 PS 10.21 Ex bongkar perbaikan bocoran B 100% 295/MA1/V/23
5 23-May-23 MA 1 Wisnu FOC 1 12 E 1 Ex bongkar fasilitas test B 100% 296/MA1/V/23
6 23-May-23 MA 1 Wisnu FOC 1 16 V 4 Ex bongkar pasang level glass B 100% 297/MA1/V/23
15 23-May-23 MA 2 Salis N FOC 2 01 PS 106 Ex akses line drain B 100% 273/MA2/V/23
16 23-May-23 MA 2 Salis N FOC 2 01 PS 159 Ex akses valve B 100% P 275/MA2/V/23
17 23-May-23 MA 2 Salis N KPC 80 PR 1 Ex bongkar akses line drain B 100% P 277/MA2/V/23
18 23-May-23 MA 2 Salis N FOC 2 01 PS 122 Ex bongkar akses line drain B 100% 278/MA2/V/23
10 2-May-23 MA 1 Wisnu LOC 1 41 T 19 Untuk cleaning tanki P 14 100% P 16/MA1/V/23
11 22-May-23 MA 5 Aziz UTL 51 E 2/3 Utuk support reposisi P 14 100% P 254/MA5/V/23
24 25-May-23 MA 2 Candra FOC 2 011 PS 117 U/ support pekerjaan instrument P 7 100% P 307/MA2/V/23
25 25-May-23 MA 2 FOC 2 011 P 119 U/ support pekerjaan akses bordesk P 10 100% P 308/MA2/V/23
26 25-May-23 MA 4 Angga KPC 88 A 201 U/ support pembongkaran atap RL P 7 100% 309/MA4/V/23
27 25-May-23 MA 4 Kusnan KPC 48 LT 201 Ex bongkar substandart B 100% 310/MA4/V/23
28 24-May-23 MA 5 Wisnu Dermaga 68 Dermaga 68 U/ support LA Propylene dermaga 68 P 7 100% 311/MA5/V/23
29 22-May-23 MA 1 Aziz Bima FOC 1 10 PS 10 U/ support penggantian pipa P 7 100% 312/MA1/V/23
3 25-May-23 MA 5 Agus W Dermaga 63 60 SS 1 Untuk support perbaikan cable tray P 7 100% P 315/MA5/V/23
4 25-May-23 MA 5 Rachmat UTL RFCC UTL RFCC Ex cek valve B 100% P 316/MA5/V/23
5 25-May-23 MA 5 Endro UTL 50 054 E102/103 A/B Untuk support penggantian HE P 20 100% P 317/MA5/V/23
6 25-May-23 MA 5 Parikin 63 63 Untuk support penerangan lampu P 7 100% P 318/MA5/V/23
7 25-May-23 MA 5 Parikin 63 60 SS 1 Ex trafo B 100% P 319/MA5/V/23
11 26-May-23 MA 7 Ikkorianto KLBC 120 E 601 Untuk support tikcness P 7 100% P 323/MA7/V/23
12 22-May-23 MA 4 M Aji KPC 87 F 201 Ex bongkar perbaikan bocoran steam B 100% P 256/MA4/V/23
18 23-May-23 MA 1 Wisnu SRU 94 C 401 Ex bongkar di 94 C 401 B 100% P 298/MA1/V/23
19 23-May-23 MA 1 Wisnu SRU 93 A 401 Ex bongkar perbaikan sulfur pit B 100% P 299/MA1/V/23
20 25-May-23 MA 4 M Aji KPC 84 lorong Ex bongkar pengecatan pipa line flare B 100% P 302/MA4/V/23
21 25-May-23 MA 4 M Aji KPC 88 P 206 Ex bongkar perbaikan bocoran steam B 100% P 303/MA4/V/23
22 25-May-23 MA 4 M Aji KPC 80 PR 6 Ex bongkar perbaikan bocoran Heavy plat B 100% P 304/MA4/V/23
13 23-May-23 MA 4 Pras W LOC 3 240 K 101 Untuk support bocoran condensate P 7 100% P 280/MA4/V/23
1 25-May-23 MA 3 Fajri IK 70 73 U/ support perb. Leaking style 80 P 2 100% P 333/MA3/V/23
2 25-May-23 MA 3 Fajri IK 70 73 Ex bongkar perb. Leaking Style 80 B 100% P 334/MA3/V/23
3 15-May-23 MA 4 Tri Asmoro LOC 3 240 P 114 U/ support steaming out Line pompa P 7 100% P 335/MA4/V/23
25 25-May-23 MA 1 Roy A FOC 1 11 E 13 Pasang scaffolding P 7 100% P 326/MA4/V/23
26 26-May-23 MA 3 Widodo 70 73 U/ support perbaikan Leaking style 50 P 7 100% P 327/MA3/V/23
27 26-May-23 MA 3 Fauzi A 70 75 U/ support perbaikan MOV tanki 71 T 20 P 7 100% P 328/MA3/V/23
28 27-May-23 MA 2 Rachmat FOC 2 01 PS 154 U/ support perbaikan isolasi P 15 100% P 329/MA2/V/23
29 27-May-23 MA 2 Rachmat FOC 2 011 E 110 Box 2 U/ support open Cover Fin fan P 7 100% P 330/MA2/V/23
21 27-May-23 MA 2 Rachmat FOC 2 019 BL Ex pekerjaan isolasi B 100% P 321/MA2/V/23
22 26-May-23 MA 5 Luqmanul UTL 05 057 E 101 Ex bocoran cover HE B 100% P 322/MA3/V/23
23 26-May-23 MA 4 M Aji M KPC 84 K 202 A Untuk support bocoran steam P 7 100% P 324/MA4/V/23
15 24-May-23 MA 1 Wisnu FOC 1 11 K 401 U/ support penggantian pipa P 7 100% P 293/MA1/V/23
16 24-May-23 MA 1 Wisnu FOC 1 11 U/ support perbaikan Union P 10 100% P 294/MA1/V/23
17 25-May-23 MA 4 M Aji KPC 84 V 221 Ex bongkar pengecatan B 100% P 305/MA4/V/23
18 26-May-23 MA 1 Wisnu FOC 1 11 P 23 AB U/ support cleaning strainer P 7 100% P 320/MA1/V/23
10 17-May-23 MA 1 Aziz B FOC 1 11 F 1 Untuk support Isolasi P 7 100% P 218/MA1/V/23
11 17-May-23 MA 5 Aziz UTL 50 51 E 3 Ex perbaikan bocoran B 100% P 264/MA5/V/23
12 22-May-23 MA 3 Arif OM 30 38 T 103 Bongkar scaffolding B 100% P 265/MA3/V/23
8 17-May-23 MA 1 Zaenal SRU 91 K 401 Untuk support perbaikan P 7 100% P 208/MA1/V/23
4 22-May-23 MA 4 Raga Ananta KPC KPC Ex kanopi B 100% P 268/MA4/V/23
10 30-May-23 MA 6 Zidnie Ilma RFCC 104 K 501 Ex perbaikan atap B 100% P 364/MA6/V/23
8 29-May-23 MA 1 Roy A 25 F 1 25 F 1 Bongkar scaffolding B 100% P 361/MA1/V/23
20 29-May-23 MA 1 Wisnu FOC 1 11 P 23 Ex cleaning strainer B 100% P 340/MA1/V/23
18 29-May-23 MA 2 Depta FOC 2 19 BL Ex reinjeckt OLLS B 7 100% 338/MA2/V/23
11 26-May-23 MA 1 Awang LOC 1 20 SS 1 Untuk support painting trafo P 7 100% P 314/MA1/V/23
9 24-May-23 MA 1 Wisnu FOC 1 14 K 1 U/ support perbaikan pipa P 10 100% P 292/MA1/V/23
1 8-May-23 MA 7 Frans S GTO 106 Untuk support pengecatan structure P 17 100% P 102/MA7/V/23
41 30-May-23 MA 5 M Syarifudin UTL 05 05 PS 122 Untuk perbaikan line condensate P 7 100% P 380/MA5/V/23
42 31-May-23 MA 7 Ikkorianto PLBC 120 Untuk pekerjaan reinjeck OLLS P 7 100% P 381/MA5/V/23
35 31-May-23 MA 4 Tri Asmoro LOC 3 260 V 104 Ex line steam B 100% P 374/MA4/V/23
36 31-May-23 MA 4 Tri Asmoro LOC 3 200 PS 608 Ex bocoran line steam B 100% P 375/MA4/V/23
37 31-May-23 MA 1 Aziz B FOC 1 11 E 17 Bongkar scaffolding B 100% P 376/MA1/V/23
28 26-May-23 MA 3 Agusalim 70 71 T 20 untuk perbaikan MOV P 3 100% P 367/MA3/V/23
23 29-May-23 MA 1 Roy A FOC 1 11 E 13-11C8 Bongkar scaffolding B 100% P 360/MA1/V/23
24 30-May-23 MA 2 FOC 2 FOC 2 011 PS 123-124 Ex line CWS B 100% P 362/MA1/V/23
25 30-May-23 MA 2 FOC 2 LOC 2 021 C 103 Ex perbaikan isolasi B 100% P 363/MA1/V/23
20 29-May-23 MA 7 NF Asror GTO 106 Untuk pengecetan structure B 100% P 344/MA7/V/23
21 30-May-23 MA 4 Pras W LOC 3 240PS 143 Ex 240 PS 143/ 240 K 101 B 100% P 358/MA4/V/23
17 29-May-23 MA 5 Aziz 63 63 A 501 D Untuk cleaning strainer P 14 100% P 341/MA5/V/23
13 29-May-23 MA 1 Roy A FOC 1 14 F 5 Pasang scaffolding P 7 100% P 336/MA1/V/23
14 29-May-23 MA 4 Angga KPC 86 PL 8003 Untuk support pekerjaan P 7 100% P 337/MA4/V/23
15 29-May-23 MA 1 Wisnu FOC 1 11 F 1 Untuk perbaikan pipa air 1" P 7 100% P 339/MA1/V/23
10 27-May-23 MA 4 Davit LOC 3 260 K 102A U/ support perbaikan bocoran Tubing P 7 100% P 331/MA4/V/23
11 27-May-23 MA 1 Wiisnu FOC 1 11 PS 10 90 Untuk bocoran pipa P 7 100% P 332/MA1/V/23
25 5-Jun-23 MA 1 Irvan FOC 1 12 K 1 C Ex cleaning strainer B 100% P 19/MA1/VI/23
26 5-Jun-23 MA 1 Irvan FOC 1 11 F 1 Ex bocoran pipa air B 100% P 20/MA1/VI/23
21 5-Jun-23 MA 1 Irvan SRU 90 V 404 Bongkar scaffolding B 100% P 15/MA1/VI/23
22 5-Jun-23 MA 1 Irvan SRU 94 E 401 Ex hot bolting B 100% P 16/MA1/VI/23
8 29-May-23 MA 3 Eko N 70 75 Ex selter solar B 100% P 389/MA3/V/23
9 29-May-23 MA 3 Agusalim 70 73 Ex MOV Tanki B 100% P 390/MA3/V/23
1 29-May-23 MA 5 Kevin UTL RFCC 152 FD 009-010 Ex flange detektor B 100% P 382/MA5/V/23
24 31-May-23 MA 1 Aziz B FOC 1 93 A 404 Bongkar scaffolding B 100% P 378/MA1/V/23
25 31-May-23 MA 1 Aziz B FOC 1 94 C 401 Bongkar scaffolding B 100% P 379/MA1/V/23
21 31-May-23 MA 4 Tri Asmoro LOC 3 220 Ex steaming OUT (oprate valve) B 100% P 372/MA4/V/23
22 31-May-23 MA 4 Tri Asmoro LOC 3 260 Ex line discharge B 100% P 373/MA4/V/23
19 31-May-23 MA 4 Angga KPC 86 PL 8097 Untuk fasilitas Cui P 10 100% P 370/MA4/V/23
11 25-May-23 MA 5 Parikin 63 Dermaga Untuk support penerangan lampu P 7 100% P 318/MA5/V/23
12 29-May-23 MA 1 Zaenal LOC 1 25 LT 004-005 Untuk perbaikan level trasmiter P 7 100% P 342/MA1/V/23
13 29-May-23 MA 7 NF Asror GTO 106 Untuk pengecetan structure tangga P 7 100% P 343/MA7/V/23
14 29-May-23 MA 5 Aziz UTL 50 54 WS 2 Untuk support bocoran pipa prodact P 7 100% P 359/MA5/V/23
15 30-May-23 MA 6 Imron M RFCC 102 E 520 A 2 Untuk perbaikan fin fan P 7 100% P 365/MA6/V/23
8 25-May-23 MA 5 Endro UTL 50 TG 50 Ex painting beam troling B 100% P 313/MA5/V/23
9 25-May-23 MA 1 Roy A FOC 1 48 Flare Pasang scaffolding P 7 100% P 325/MA4/V/23
13 31-May-23 MA 1 Aziz B FOC 1 11 E 7 Bongkar scaffolding B 100% P 377/MA1/V/23
14 29-May-23 MA 3 Widodo 70 71 T 11 Ex sorokan 24" B 100% P 383/MA3/V/23
15 29-May-23 MA 3 Widodo 70 71 T 12 Ex sorokan 24" B 100% P 384/MA3/V/23
16 29-May-23 MA 3 Widodo 70 71 T 15 Ex sorokan 24" B 100% P 385/MA3/V/23
17 29-May-23 MA 3 Widodo 70 71 T 17 Ex sorokan 24" B 100% P 386/MA3/V/23
18 29-May-23 MA 3 Widodo 70 71 T 16 Ex sorokan 24" B 100% P 387/MA3/V/23
19 30-May-23 MA 5 Rachmat UTL 50 51 G 3 Untuk support generan cleaning P 7 100% P 388/MA5/V/23
11 31-May-23 MA 4 Angga KPC 82 PL 8085 Untuk fasilitas Cui P 10 100% 369/MA4/V/23
21 31-May-23 MA 2 Salis N LOC 2 023 V 103 Ex Bocoran steam B 100% P 392/MA2/V/23
22 31-May-23 MA 2 Salis N LOC 2 024 PS 140 Ex line propane B 100% P 393/MA2/V/23
23 31-May-23 MA 2 Salis N LOC 2 021 STR 101 Ex Bocoran steam B 100% P 394/MA2/V/23
24 31-May-23 MA 2 Salis N LOC 2 024 P 103 Ex akses buka cover B 100% P 395/MA2/V/23
25 31-May-23 MA 2 Salis N LOC 2 01 PS 105 Ex Bocoran steam B 100% P 396/MA2/V/23
26 31-May-23 MA 2 Salis N LOC 2 024 E 127 Ex bocoran hidro carbon B 100% P 397/MA2/V/23
27 31-May-23 MA 2 Salis N LOC 2 022 V 102 Ex Bocoran steam B 100% P 398/MA2/V/23
28 5-Jun-23 MA 1 Irvan FOC 1 12 E 1 A Ex hot bolting B 100% P 12/MA1/VI/23
29 5-Jun-23 MA 1 Irvan FOC 1 11 E 7 Ex hot bolting B 100% P 13/MA1/VI/23
30 5-Jun-23 MA 1 Irvan FOC 1 11 E 7 Ex sorokan B 100% P 14/MA1/VI/23
31 5-Jun-23 MA 1 Irvan FOC 1 11 E 25 Ex hot bolting B 100% P 17/MA1/VI/23
32 5-Jun-23 MA 1 Irvan FOC 1 12 K 1 C Untuk piping P 7 100% 18/MA1/VI/23
33 5-Jun-23 MA 5 Aziz UTL 50 051 E 101 Untuk support bocorn flexible hose P 14 100% P 21/MA5/VI/23
34 5-Jun-23 MA 5 Aziz UTL 50 53 T 1 Bongkar scaffolding B 100% P 22/MA5/VI/23
35 5-Jun-23 MA 5 Wisnu 64 Dermaga 64 Untuk perbaikan valve 12" P 7 100% P 23/MA5/VI/23
1 2-Jun-23 MA 2 Depta FOC 2 011 PS 134,135 Untuk support fire proofing P 7 100% P 1/MA2/VI/23
2 2-Jun-23 MA 2 Depta FOC 2 011 PS 131,132 Untuk support fire proofing P 7 100% P 2/MA2/VI/23
3 2-Jun-23 MA 2 Depta FOC 2 011 PS 133,134 Untuk support fire proofing P 7 100% P 3/MA2/VI/23
4 2-Jun-23 MA 2 Besar SP FOC 2 011 PS 117 Ex support instrument B 100% P 4/MA2/VI/23
5 2-Jun-23 MA 2 Besar SP FOC 2 011 E 103 Untuk support instrument P 7 100% P 5/MA2/VI/23
6 2-Jun-23 MA 2 Salis N LOC 2 022 E 109 Ex bocoran HE B 100% P 6/MA2/VI/23
8 2-Jun-23 MA 2 Depta FOC 2 013 C 101 Untuk support CUF P 10 100% P 8/MA2/VI/23
9 2-Jun-23 MA 2 Depta FOC 2 018 R 101 Untuk support CUF P 10 100% P 9/MA2/VI/23
10 2-Jun-23 MA 2 Ilyas FOC 2 013 E 107 MO 7 Ex brearing fin fan B 100% P 10/MA2/VI/23
11 2-Jun-23 MA 2 Ilyas FOC 2 018 E 105 K1 Untuk support perbaikan bearinf fin fan P 5 100% P 11/MA2/VI/23
12 1-Jun-23 MA 5 Rachmat UTL 50 54 P 202 A,B,C Untuk penggantian ARC Valve P 7 100% P 24/MA5/V/23
13 1-Jun-23 MA 5 Rachmat UTL 50 51 G 3 Ex cleaning 51 3 B 100% P 25/MA5/V/23
14 1-Jun-23 MA 5 Rachmat UTL 50 51 E 3 Ex penggantian lo cooler & air cooler B 100% P 26/MA5/V/23
20 6-Jun-23 MA 1 Irvan FOC 1 11 C 1 Untuk support taping point line LGO P 10 100% P 32/MA5/VI/23
15 6-Jun-23 MA 4 M Aji M KPC 84 K 202 A Ex perbaikan isolasi B 100% P 27/MA4/VI/23
16 6-Jun-23 MA 4 M Aji M KPC 84 K 202 A Selatan Ex bocoran steam B 100% P 28/MA4/VI/23
7 17-May-23 MA 3 Ikhan OM 30 30 E 0012 Ex akses jembatan B 100% P 282/MA5/V/23
4 23-May-23 MA 1 Adimas LOC 1 21 PS 20/22 Untuk kabel tray instrument P 7 100% P 399/MA1/V/23
4 31 mei 23 MA 4 Pras W LOC 3 220 V 103 Bongkar scaffolding B 100% P 400/MA4/V/23
17 5-Jun-23 MA 3 Widodo 70 71 Untuk selter sub jalan Z P 30 100% P 42/MA3/VI/23
17 5-Jun-23 MA 3 Widodo 70 70 P 9 B Untuk mobilisasi diesel enggine P 7 100% P 43/MA3/VI/23
17 6-Jun-23 MA 3 Fajri IK 70 71 T 19 Ex sorokan 24" B 100% P 44/MA3/VI/23
17 6-Jun-23 MA 3 Fajri IK 70 70 P 9 Ex mobilisasi diesel enggine B 100% P 45/MA3/VI/23
18 6-Jun-23 MA 1 Jordan LOC 1 20 SS 1 Bongkar scaffolding B 100% P 46/MA1/VI/23
9 6-Jun-23 MA 6 Yusro RFCC 102 102 PS 005 Ex kabel tray instrument B 100% P 40/MA6/VI/23
5 6-Jun-23 MA 1 Adimas LOC 1 25 LT 004-005 25 V 1 Pasang scaffolding P 7 100% P 37/MA1/VI/23
9 6-Jun-23 MA 6 Anas AF RFCC 101 101 K 501 Ex painting stuckture B 100% P 38/MA6/VI/23
15 6-Jun-23 MA 2 Depta FOC 2 13 PS 121 Untuk support line steam 1" P 100% P 31/MA2/VI/23
18 7-Jun-23 MA 1 Aziz B FOC 1 11 P 4 Untuk support hot bolting P 7 100% 48/MA1/VI/23
4 7-Jun-23 MA 7 Ikkorianto GTO 106 Untuk line injeksi AO dan ASA P 100% P 52/MA7/VI/23
16 7-Jun-23 MA 4 Tri Yulianto KPC 39 T 212 Untuk tempat berteduh P 100% P P 47/MA4/VI/23
1 6-Jun-23 MA 5 Aziz UTL 50 UTL 50 Untuk bocoran MPS temporary P 14 100% 49/MA5/VI/23
2 8-Jun-23 MA 6 Zidnie Ilma RFCC 101 V 502 Untuk bocoran line katalise lantai 10 P 7 100% P 50/MA6/VI/23
3 6-Jun-23 MA 1 Roy A LOC 1 24 Untuk line steam P 14 100% 35/MA1/VI/23
14 6-Jun-23 MA 2 Depta LOC 2 41 T 119 Untuk support akses selter P 100% P 30/MA2/VI/23
1 6-Jun-23 MA 1 Roy A LOC 1 24 Coling water Untuk line coolong water P 7 100% 33/MA1/VI/23
2 10-May-23 MA 5 Endro UTL 05 05 PS 139-142 Ex pengecatan structure B 100% P 133/MA5/V/23
3 11-May-23 MA 5 Iryan B UTL RFCC Dermaga 63 U/ support cover pile dermaga area 63 P 7 continue P 157/MA5/V/23
7 26-May-23 MA 7 Ikkorianto KLBC 120 E 601 Untuk support tikcness P 7 100% P 323/MA7/V/23
18 8-Jun-23 MA 6 Zidnie Ilma RFCC 101 BL Ex bongkar isolasi B 100% P 51/MA6/VI/23
19 5-Jun-23 MA 5 Iryan B UTL 50 54 T 2/T1 Ex selter perbaikan tanki B 100% P 53/MA5/VI/23
11 30-May-23 MA 5 M Syarifudin UTL 500 530 S 301/302 Ex beam Trasmiter P 7 100% P 391/MA5/V/23
9 8-Jun-23 MA 7 Asror LNHT 120E 607 Untuk pekerjaan tikness P 7 100% P 69/MA1/VI/23
10 9-Jun-23 MA 7 Asror PLBC 100 E 611 B Untuk pekerjaan tikness P 7 100% P 70/MA1/VI/23
5 9-Jun-23 MA 1 Wisnu FOC 1 16 R1 Untuk support Hottap P 7 100% P 65/MA1/VI/23
6 9-Jun-23 MA 1 Wisnu FOC 1 11 P 4 Ex hot bolting B 100% P 66/MA1/VI/23
7 9-Jun-23 MA 1 Wisnu FOC 1 11 C 6 Ex re inject OLLS B 100% P 67/MA1/VI/23
1 8-Jun-23 MA 5 Aziz UTL 05 05 PS 123 U/ support bocoran pipa P 14 100% P 61/SP/P/VI/23
2 7-Jun-23 MA 5 Aziz UTL 05 05 PS 122 U/ support bocoran pipa P 14 100% P 62/SP/P/VI/23
4 8-Jun-23 MA 7 Ikkorianto KLBC 120 E 604 B Untuk support tikcness P 7 100% P 74/MA7/VI/23
23 9-Jun-23 MA 4 Tri Asmoro KPC Bongkar scaffolding B 100% P 64/MA4/VI/23
22 9-Jun-23 MA 4 Fangky KPC 86 C 201 Ex bongkar wrapping dan isolasi B 100% P 63/MA4/VI/23
1 11-Jun-23 MA 2 Salis N LOC 2 022 K 101 Perbaikan line propare P 7 100% P 90/MA2/VI/23
10 6-Jun-23 MA 1 Roy A LOC 1 21 C 1 Untuk steaming out line wash gas P 7 xx 34/MA1/VI/23
10 12-Jun-23 MA 7 NF Asror KLBC 140 R 601 B Untuk support LRUT P 7 100% P 88/MA7/VI/23
7 12-Jun-23 MA 7 NF Asror KLBC 140 V 604 Untuk modivikasi line N2 P 7 100% P 85/MA7/VI/23
4 12-Jun-23 MA 1 Aziz B FOC 1 12 K 1 Bongkar perbaikan pipa B 100% P 82/MA1/VI/23
5 12-Jun-23 MA 1 Aziz B FOC 1 16 PS 21 Untuk support operate valve P 7 100% P 83/MA1/VI/23
24 12-Jun-23 MA 5 Iryan B UTL 500 510 E 601 Untuk support condensore P 7 100% P 76/MA5/VI/23
25 9-Jun-23 MA 6 Anas AF RFCC 101 101 P 502 B Untuk tambahan line by pass check P 7 100% P 77/MA6/VI/23
19 8-Jun-23 MA 1 Irvan FOC 1 12 E 1 F Untuk painting beam P 7 100% P 60/MA1/VI/23
20 9-Jun-23 MA 1 Wisnu FOC 1 19 E 1B,1D Untuk verifikasi P 7 100% P 68/MA1/VI/23
21 9-Jun-23 MA 7 Ikkorianto KLBC 140 Untuksupport modifikasi line P 7 100% P 72/MA7/VI/23
17 8-Jun-23 MA 1 Irvan FOC 1 FOC 1 Untuk MOV GAS P 10 100% P 58/MA1/VI/23
10 6-Jun-23 MA 1 Roy A LOC 1 CPI Pasang scaffolding P 30 100% 36/MA1/VI/23
8 2-Jun-23 MA 2 Depta FOC 2 011 V 107 Untuk support CUF P 10 100% P 7/MA2/VI/23
15 8-Jun-23 MA 1 Irvan SRU 93 P 402 Untuk piping P 14 100% P 59/MA1/VI/23
16 9-Jun-23 MA 7 Ikkorianto KLBC 140 D 601 Untuk support adsorben P 7 100% P 73/MA7/VI/23
17 8-Jun-23 MA 7 Ikkorianto KLBC 140 D 601 A Untuk support tikcness P 7 100% P 75/MA7/VI/23
18 11-Jun-23 MA 4 Tri Yulianto KPC 84 E 202 Bongkar scaffolding B 100% P 79/MA4/VI/23
19 9-Jun-23 MA 3 Agusalim 70 70 SS 1 Pasang scaffolding P 7 100% P 80/MA3/VI/23
20 9-Jun-23 MA 3 Agusalim 70 LA 72 X 201 Untuk perbaikan leaking style P 7 100% P 81/MA3/VI/23
21 12-Jun-23 MA 7 NF Asror KLBC 120 E 601 Ex tikness B 100% P P 84/MA7/VI/23
3 13-Jun-23 MA 7 Wahyu GTO 106 Ex line injeksi AO dan ASA B 100% P 93/MA7/VI/23
4 13-Jun-23 MA 7 Wahyu 140 140 E 602 Untuk support bocoran HE P 7 100% P 94/MA7/VI/23
8 13-Jun-23 MA 1 Aziz B SRU 93 Ex bongkar N2 B 100% P 98/MA1/VI/23
11 13-Jun-23 MA 4 M Aji KPC 84 PR 7-8 Untuk painting pipa P 7 100% P 101/MA4/VI/23
9 14-Jun-23 GMT Mafrio Gd Surplus Gd surplus Pinjam material P 270 100% P 122/MA2/VI/23
10 14-Jun-23 MA 1 Irvan LOC 1 41 T 19 Ex cleaning 41 T 19 B 100% P 123/MA1/VI/23
1 10-Jun-23 MA 3 Widodo 70 72 Ex perbaikan leaking style 50 72 X 201 B 100% P 114/MA3/VI/23
2 10-Jun-23 MA 3 Widodo 70 70 Ex pekerjaan line pipa 10 " B 100% P 115/MA3/VI/23
3 10-Jun-23 MA 3 Widodo 70 72 X 203 Ex perbaikan telescopic B 100% P 116/MA3/VI/23
4 10-Jun-23 MA 3 Widodo 70 71 T 1 Ex perbaikan MOV Tanki B 100% P 117/MA3/VI/23
5 10-Jun-23 MA 3 Widodo 70 70 SS 1 Bongkar scaffolding B 100% P 118/MA3/VI/23
30 13-Jun-23 MA 2 Salis N LOC 2 022 PS 115 U/ support CCTV P 7 100% P 107/MA2/VI/23
21 31-May-23 MA 5 Agus W UTL 500 500 PS 16 Untuk support perbaikan lampu P 5 100% P 96/MA5/VI/23
22 13-Jun-23 MA 1 Tri Wurtanto SRU 93 FV 032 Pasang scaffolding P 7 100% P 97/MA1/VI/23
16 12-Jun-23 MA 6 Zidnie Ilma RFCC 101 R 502 Untuk tiknes P 7 100% P 87/MA6/VI/23
17 12-Jun-23 MA 7 NF Asror KLBC 140 R RGDI Untuk support LRUT P 7 100% P 89/MA7/VI/23
10 6-Jun-23 MA 7 Ikkorianto GTO 106 Ex bocoran out let B 100% P 41/MA7/VI/23
11 8-Jun-23 GMT Alfian Ghani Lapangan HO Lapangan HO Untuk support shoting club P 7 100% P 54/GMT/VI/23
16 31-May-23 MA 5 Agus W 63 P 102 A 63 A 501 D Ex bongkar cleaning clarifier B 100% P 95/MA5/VI/23
18 13-Jun-23 MA 1 Roy A SRU 22 E 9 Untuk perbaikan line CWR P 7 100% P 100/MA1/VI/23
19 13-Jun-23 MA 2 Depta FOC 2 017 P 106 A Untuk isolasi line 14 P 7 100% P 102/MA2/VI/23
20 13-Jun-23 MA 2 Depta FOC 2 011 E 118 Untukisolasi line 18" P 7 100% P 103/MA2/VI/23
22 11-Jun-23 MA 4 Kusnan KPC 84 Untuk substandar instrument P 7 100% P 105/MA4/VI/23
23 13-Jun-23 MA 2 Depta FOC 2 015 E 101 Untuk isolasi line 4" P 7 100% P 106/MA2/VI/23
24 13-Jun-23 MA 4 M Aji KPC 88-89 Untuk perbaikan sub standar area C P 7 100% P 108/MA4/VI/23
25 13-Jun-23 MA 2 David FOC 2 012 F 102 Untuk inpeksi cui P 7 100% P 109/MA2/VI/23
26 13-Jun-23 MA 2 M khoirudin FOC 2 012 E 103 1/2 Untuk inpeksi cui P 7 100% P 110/MA2/VI/23
27 13-Jun-23 MA 2 Salis N FOC 2 012 P 103 AB Untuk inpeksi cui P 7 100% P 111/MA2/VI/23
28 13-Jun-23 MA 4 M Aji KPC 49 Untuk pasang BA loading tank cor P 7 100% P 112/MA4/VI/23
30 14-Jun-23 MA 2 Prasetyo FOC 2 015 E 107 KG Untuk perbaikan bearing fin fan P 10 100% P 120/MA2/VI/23
31 13-Jun-23 MA 4 Fangky KPC 84 E202 C Untuk support perbaikan plenum P 5 100% P 121/MA4/VI/23
35 14-Jun-23 MA 1 Wisnu FOC 1 11 V 8 Untuk penggantian pipa P 7 100% P 127/MA1/VI/23
36 14-Jun-23 MA 3 Yulianto OM 40 49 Untuk penggantian pipa P 7 100% P 128/MA3/VI/23
37 14-Jun-23 MA 5 Iryan B UTL 500 520 B 401 Untuk support bocoran steam flange P 14 100% P 129/MA5/VI/23
38 14-Jun-23 MA 5 Aziz B UTL 50 54 T 3 Ex cleaning tanki B 100% P 130/MA5/VI/23
39 13-Jun-23 MA 5 Iryan B UTL 50 54 WS 201 ex perbaikan OLLS line fuel oil B 7 100% P 113/MA5/VI/23
18 15-Jun-23 MA 6 Guntani RFFC 101 P 522 C Untuk akses hottap P 100% P 148/MA6/VI/23
1 13-Jun-23 MA 3 Widodo 70 73 U/ Support Fix drip sampler LA 73X02 P 7 100% P 131/MA3/VI/23
2 13-Jun-23 MA 3 Fajri IK 70 73 U/ support perb pedestal Crane 73X8 P 15 100% P 132/MA3/VI/23
3 13-Jun-23 MA 3 Widodo 70 73 U/ Support Fix drip sampler LA 73X01 P 7 100% P 133/MA3/VI/23
4 13-Jun-23 MA 3 Widodo 70 73 U/ Support Fix drip sampler LA 73X04 P 7 100% P 134/MA3/VI/23
5 13-Jun-23 MA 3 Widodo 70 73 U/ Support Fix drip sampler LA 73X03 P 7 100% P 135/MA3/VI/23
6 14-Jun-23 MA 3 Widodo 70 73 U/ Support perb Leaking style LA 73X102 P 30 100% P 136/MA3/VI/23
7 14-Jun-23 MA 3 Widodo 70 73 Ex bongkar Leaking style 73X102 B 100% P 137/MA3/VI/23
8 15-Jun-23 MA 1 Roy A LOC 1 24 PS 65 Untuk support cooling water 1" P 7 100% P 138/MA1/VI/23
17 13-Jun-23 MA 2 M Anwar FOC 2 013 E 111 K02 Untuk perbaikan fin fan P 7 100% P 104/MA2/VI/23
18 14-Jun-23 MA 2 Prasetyo FOC 2 011 E 110 K 26 Untuk perbaikan bearing fin fan P 7 100% P 119/MA2/VI/23
19 15-Jun-23 MA 1 Hafidh LOC 1 25 V 1 Pasang scaffolding P 10 100% P 124/MA1/VI/23
20 14-Jun-23 MA 1 Aziz B SRU 94 E 402 Untuk perbaikan expansion joint P 7 100% P 125/MA1/VI/23
22 15-Jun-23 MA 1 Roy A LOC 1 24 PS 63 Untuk support cooling water 1" P 7 100% P 139/MA1/VI/23
23 15-Jan-23 MA 2 Depta FOC 2 011 E 132 M1,M2 Ex dudukan blower B 100% P 140/MA2/VI/23
24 15-Jan-23 MA 2 Depta FOC 2 018 R 101 Ex fire proofing ( CUF) B 100% P 141/MA2/VI/23
26 15-Jan-23 MA 2 Depta FOC 2 011 V 107 Ex CUF B 100% P 143/MA2/VI/23
27 15-Jan-23 MA 2 Depta FOC 1 011 E 125 KS Ex perbaikan fin fan B 100% P 144/MA2/VI/23
28 15-Jan-23 MA 2 David LOC 2 024 PS 130 Untuk isolasi P 7 100% P 145/MA2/VI/23
29 15-Jan-23 MA 2 David LOC 2 21 Untuk sproket valve P 7 100% P 146/MA2/VI/23
30 15-Jun-23 MA 6 Guntani RFFC 101 Untuk reinject OLLS P 100% P 147/MA6/VI/23
31 15-Jun-23 MA 7 Ega Yusuf K GTO 108 K 502 AM Untuk penggantian valve P 100% P 149/MA7/VI/23
11 16-Jun-23 MA 6 Guntani RFCC 101 FT 087 Untuk reinjeck OLLS P 100% P 160/MA6/VI/23
8 16-Jun-23 MA 4 Fanky KPC 84 PR 7.8 Ex pengecatan B 100% P 157/MA4/VI/23
4 16-Jun-23 MA 1 Aziz B SRU 91 K 402 Untuk perbaikan plenum P 7 100% P 153/MA1/VI/23
17 14-Jun-23 MA 1 Wisnu FOC 1 11 F 1 Ex isolasi B 100% P 126/MA1/VI/23
18 15-Jan-23 MA 2 Depta FOC 2 014 BL Ex bongkar painting B 100% P 142/MA2/VI/23
1 16-Jun-23 MA 6 Guntani RFCC 101 101 HV 026 Pasang scaffolding P 7 100% P 162/MA6/VI/23
1 16-Jun-23 MA 6 Anas AF RFCC 101 101 E 523 Untuk lepas pasang HE P 7 100% P 163/MA6/VI/23
3 16-Jun-23 MA 5 Luqmanul UTL RFCC UTL RFCC Untuk perbaikan AUX Boiler A P 7 100% P 164/MA5/VI/23
4 16-Jun-23 MA 7 NF Asror KLBC 120 E 601 A Untuk support LRUT P 7 100% P 165/MA7/VI/23
4 16-Jun-23 MA 7 NF Asror KLBC 140 R 601 A/B Untuk support LRUT P 7 100% P 166/MA7/VI/23
4 16-Jun-23 MA 7 NF Asror KLBC 140 E 602 Untuk support LRUT P 7 100% P 167/MA7/VI/23
1 16-Jun-23 MA 7 NF Asror KLBC 140 R 601 A/B Untuk support LRUT P 7 100% P 166/MA7/VI/23
2 17-Jun-23 MA 7 NF Asror KLBC 140 C 601 Untuk pekerjaan LRUT line H2 P 14 100% P 168/MA7/VI/23
3 18-Jun-23 MA 5 Iryan B UTL RFCC 151 B 501 A Pasang scaffolding P 7 100% P 169/MA7/VI/23
28 1-Mar-23 MA 5 Iryan B Dermaga 63 63 RWI Untuk pekerjaan line drain pipa RWI P 14 100% P 301/MA2/III/23
1 8-May-23 MA 3 Yulianto OM 30 38 T 101 Ex bongkar scaffolding di 38 T 101 B 104/MA3/V/23
2 15-May-23 Gmnt Raga Ananta 30 SS 13 30 SS 13 Untuk perbaikan bocoran dac P 7 Continue P 176/GMT/V/23
3 15-May-23 Gmnt Raga Ananta SS GIS 150 SS GIS 150 KV Untuk perbaikan dac P 7 Continue P 177/GMT/V/23
4 17-May-23 MA 1 Aziz B SRU 47 S 505 Untuk support kabel tray P 7 212/MA1/V/23
5 30-May-23 MA 6 Zidnie Ilma RFCC 104 V 504 A/B Untuk pengecetan P 7 366/MA6/V/23
6 31-May-23 MA 4 Angga KPC 84 PL 8537 Untuk fasilitas Cui P 10 Continue P 368/MA4/V/23
7 30-May-23 MA 4 Tri Asmoro LOC 3 All Area Untuk cleaning sower P 7 Continue P 371/MA4/V/23
8 6-Jun-23 MA 2 Depta LOC 2 41 T 111 Ex akses dan selter B continue P 29/MA2/VI/23
9 6-Jun-23 MA 6 Yusro RFCC 101 Untuk kabel tray P 7 39/MA6/VI/23
10 19-Jun-23 GMT Alfian Ghani Lapangan HO Lapangan HO Bongkar scaffolding B 55/GMT/VI/23
11 8-Jun-23 MA 1 Irvan FOC 1 11 Untuk isolasi pengecekan CUI TA P 10 Continue P 57/MA1/VI/23
12 8-Jun-23 MA 1 Irvan FOC 1 FOC 1 Untuk LRUT P 30 Continue P 56/MA1/VI/23
13 12-Jun-23 MA 6 Zidnie Ilma RFCC 101 Untuk parameter CEMS P 7 86/MA6/VI/23
14 31-May-23 MA 5 Agus W 63 P 102 A 63 P 102 A Untuk perbaikan penerangan lampu dermag P 7 Continue P 91/MA5/VI/23
15 13-Jun-23 MA 7 NF Asror GTO 106 Ex painting strcture B Continue P 92/MA7/VI/23
16 13-Jun-23 MA 1 Roy A SRU 21 C 2 Untuk support cleaning flame arrester P 7 99/MA1/VI/23
17 14-Jun-23 MA 4 M Aji KPC 80 PR G-H Ex perbaikan pipa B 150/MA3/VI/23
18 16-Jun-23 MA 1 Roy A LOC 1 23 E 9 Bongkar scaffolding B 151/MA1/VI/23
19 16-Jun-23 MA 4 Pras W LOC 3 240 P 154 A/B Ex perbaikan Isolasi B 152/MA4/VI/23
20 16-Jun-23 MA 4 Pras W LOC 3 260 V 160 Untuk pengecatan P 14 154/MA4/VI/23
21 16-Jun-23 MA 1 Imam FOC 1 011 FT 046/011 E 130 Ex pekerjaan instrument B 155/MA4/VI/23
22 16-Jun-23 MA 4 Fanky KPC 84 F 201 Ex pver plat B 156/MA4/VI/23
23 16-Jun-23 MA 1 Imam FOC 1 014 E 110 Ex pressure garage B 158/MA4/VI/23
24 16-Jun-23 MA 2 Salis N FOC 2 01 PS 115 Untuk bocoran steam P 7 159/MA2/VI/23
25 16-Jun-23 MA 6 Guntani RFCC 101 Ex flushing line Oil HGO B 161/MA6/VI/23
SPT BARU
1 19-Jan-23 MA 6 Fuad FOC 2 018 / OB Untuk perbaikan lampu sorot P 7 168/MA2/VI/23
2 19-Jan-23 MA 1 Aziz B FOC 1 12 Ex bongkar pengecatan beam B 169/MA2/VI/23
2 19-Jan-23 MA 5 Agus UTL 500 PS 16-19 Ex perbaikan lampu sekitar B 170/MA2/VI/23
2 19-Jan-23 MA 5 Endro UTL 50 54 WS 201 Untuk perbaikan line steam P 4 171/MA2/VI/23
DAILY ACTIVITY
11 57/MA1/VI/23
12 56/MA1/VI/23
7 7-Jul-23 MA 2 David LOC 2 023 PS 121-124 Untuk penggantian isolasi pipa P 15 100% P 67/MA2/VII/23
15 Spt Menyusul MA 4 - KPC 82 New line pertamak turbo P Continue P -
11 20-Jul-23 MA 2 Salis N FOC 2 011 P 122 Untuk bongkar sproket P 100% P 222/MA 2/VII/23
11 20-Jul-23 MA 2 Salis N FOC 2 019 P 118 A Untuk bongkar sproket P 100% P 221/MA 2/VII/23
24 19-Jul-23 WS Fandi D WS WS Untuk perbaikan crane valve P 7 100% P 199/MA1/VII/23
11 13-Jul-23 MA 1 Irvan FOC 1 FOC 1 Ex pengecekan LRUT ( 2 titik ) B 100% P 124/MA1/VII/23
3 20-Jul-23 MA 1 Yudi FOC 1 11 E 52 F C Bongkar scaffolding ( 2 titik ) B 100% P 213/MA1/VII/23
3 20-Jul-23 MA 1 Yudi FOC 1 11 E 54 A,B Pasang scaffonding ( 2 titik ) P 7 100% P 214/MA1/VII/23
3 13-Jul-23 MA 1 Roy A LOC 1 22 E 9 U/ support pemasangan scaff pengecatan P 14 Continue P 138/MA1/VII/23
12 22-Jun-23 MA 3 Ikhsan OM 30 38 T 101 Untuk penyangga tangga roling P 14 100% P 203/MA7/VI/23
3 20-Jul-23 MA 5 Wisnu Dermaga 64 Dermaga 64 Ex perbaikan valve 12" ( 2 titik ) B 100% P 211/MA5/VII/23
3 20-Jul-23 MA 5 Iryan B Dermaga Dermaga Untuk chain block gantungan P 7 100% P 210/MA5/VII/23
10 17-Jul-23 MA 6 M Faidi 102 102 E 520 A2 Ex perbaikan fin fan B 100% P 166/MA6/VII/23
15 Spt Menyusul MA 3 - 70 pangkal dermaga Untuk pekerjaan fasilitas painting pipa P Continue P -
LAPORAN HARIAN SPT PASANG DAN BONGKAR SCAFFOLDING UNIT PRICE
PT TRIAGUNG JAYA ABADI
SELASA, 25 JULI 2023
Durasi Tambah
NO Tanggal SPT MA Nama Area Unit Uraian Pekerjaan P/B Progress Terpasang Terbongkar No Reg
Pakai Titik
SPT LAMA
5 22-May-23 MA 4 Raga Ananta KPC KPC Untuk support pasang kanopi P 7 100% P P 267/MA4/V/23
10 22-May-23 MA 4 Pras W KPC 84 V 203 Untuk support fit stop P 9 100% P 272/MA2/V/23
21 23-May-23 MA 1 Irvan FOC 1 FOC 1 BL Ex piping B 100% P 283/MA1/V/23
22 23-May-23 MA 1 Irvan FOC 1 10. 12 Ex piping steam B 100% P 284/MA1/V/23
18 11-May-23 MA 2 David M LOC 2 023 PS 119,120,121 Untuk support isolasi dan cat P 100% P 165/MA2/V/23
19 22-May-23 MA 1 Tri Wurtanto LOC 1 21 F 1 Pasang scaffolding P 7 100% P 244/MA1/V/23
20 22-May-23 MA 5 M Syarifudin UTL 051 G 102 Ex outlet surface B 100% P 245/MA5/V/23
21 22-May-23 MA 5 M Syarifudin UTL 052 B 104 Ex bocoran line sot blower B 100% P 246/MA5/V/23
22 22-May-23 MA 5 M Syarifudin UTL 500 PS 18 Ex reinject OLLS B 100% P 247/MA5/V/23
23 22-May-23 MA 5 M Syarifudin UTL 057 E 102 Ex bocoran Cover HE B 100% P 248/MA5/V/23
24 22-May-23 MA 5 M Syarifudin UTL 05 PS 159 ex bocoran B 100% P 249/MA5/V/23
25 22-May-23 MA 5 M Syarifudin UTL 05 Ex line drine condensate B 100% P 250/MA5/V/23
26 22-May-23 MA 5 M Syarifudin UTL 500 PS 03 Ex bocoran flange HP B 100% P 251/MA5/V/23
27 22-May-23 MA 5 M Syarifudin UTL 051 G 101 Ex cleaning condensor B 100% P 252/MA5/V/23
28 22-May-23 MA 5 M Syarifudin UTL 051 G 102 Ex cleaning surface condensor B 100% P 253/MA5/V/23
16 18-May-23 MA 4 M Aji KPC 84 k 202 Untuk perbaikan isolasi P 7 100% P 235/MA4/V/23
14 18-May-23 MA 4 M Aji KPC 84 k 201 Untuk perbaikan isolasi P 7 100% 234/MA4/V/23
11 17-May-23 MA 4 Pras W LOC 3 200 PS 608 Untuk support perbaikan bocoran steam P 4 100% 221/MA4/V/23
12 17-May-23 MA 6 Zidnie Ilma RFCC 101 101 BL Untuk support isolasi P 7 100% P 222/MA6/V/23
9 17-May-23 MA 1 Aziz B LOC 1 24 C 5 Bongkar scaffolding B 100% P 215/MA1/V/23
1 23-May-23 MA 5 Agus W 63 063 P 301 M U/ Support bongkar motor P 7 100% P 285/MA5/V/23
2 23-May-23 MA 3 Widodo 70 73 U/ support perbaikan Leaking style P 7 100% P 286/MA3/V/23
3 23-May-23 MA 3 Widodo 70 72 Ex bongkar perbaikan Line bunker B 100% P 287/MA3/V/23
4 23-May-23 MA 3 Widodo 70 73 Ex bongkar perbaikan LA 73X104 B 100% P 288/MA3/V/23
5 23-May-23 MA 3 Widodo 70 75 Ex bongkar buka blind flange 30" B 100% P 289/MA3/V/23
6 23-May-23 MA 6 Ifanudin RFCC 104 104 Ex bongkar line MPC B 100% P 290/MA6/V/23
7 23-May-23 MA 6 Anugrah RFCC 101 101 FT 067 Ex perbaikan B 100% P 291/MA6/V/23
30 23-May-23 MA 4 Pras W LOC 3 200 PS 618 Bongkar scaffolding B 100% P 281/MA4/V/23
28 23-May-23 MA 2 Salis N FOC 2 01 PS 101 Ex bongkar akses line drain B 100% P 279/MA2/V/23
25 23-May-23 MA 2 Salis N FOC 2 01 PS 151 Ex bongkar akses line drain B 100% P 276/MA2/V/23
23 23-May-23 MA 2 Salis N FOC 2 011 F 101 A Ex chemical cleaning B 100% P 274/MA2/V/23
18 22-May-23 MA 4 Raga Ananta KPC KPC Ex kanopi B 100% P 268/MA4/V/23
19 23-May-23 MA 2 Depta FOC 2 FOC 2 A BL Untuk jumper line 6'' to 3 '' Line SWS P 7 100% P 269/MA2/V/23
20 23-May-23 MA 2 Hendro S LOC 2 002 V 102 Untuk support pipa steam P 7 100% P 270/MA2/V/23
21 23-May-23 MA 2 Depta FOC 2 019 BL Untuk reinjeck OLLS P 7 100% P 271/MA2/V/23
10 16-May-23 MA 3 Yulianto OM 30 31 Untuk support line tie in 12" premium suction P 7 100% P 226/MA3/V/23
11 19-May-23 MA 6 Yusro RFCC 101 102/PS 005 Untuk perbaikab kabel tray P 100% 242/MA6/V/23
15 22-May-23 MA 4 M Aji KPC 84 PR V 5 perbaikan bocoran steam P 100% P 257/MA4/V/23
15 25-May-23 MA 4 M Aji KPC 87 F 201 Ex bongkar cleaning Box burner B 100% P 306/MA4/V/23
9 24-May-23 MA 3 Widodo 70 70 U/ support pekerjaan line pipa 10" P 10 100% 300/MA3/V/23
10 24-May-23 MA 3 Widodo 70 73 Ex bongkar perbaikan leaking style B 100% 301/MA3/V/23
4 23-May-23 MA 1 Wisnu FOC 1 16 PS 10.21 Ex bongkar perbaikan bocoran B 100% 295/MA1/V/23
5 23-May-23 MA 1 Wisnu FOC 1 12 E 1 Ex bongkar fasilitas test B 100% 296/MA1/V/23
6 23-May-23 MA 1 Wisnu FOC 1 16 V 4 Ex bongkar pasang level glass B 100% 297/MA1/V/23
15 23-May-23 MA 2 Salis N FOC 2 01 PS 106 Ex akses line drain B 100% 273/MA2/V/23
16 23-May-23 MA 2 Salis N FOC 2 01 PS 159 Ex akses valve B 100% P 275/MA2/V/23
17 23-May-23 MA 2 Salis N KPC 80 PR 1 Ex bongkar akses line drain B 100% P 277/MA2/V/23
18 23-May-23 MA 2 Salis N FOC 2 01 PS 122 Ex bongkar akses line drain B 100% 278/MA2/V/23
10 2-May-23 MA 1 Wisnu LOC 1 41 T 19 Untuk cleaning tanki P 14 100% P 16/MA1/V/23
11 22-May-23 MA 5 Aziz UTL 51 E 2/3 Utuk support reposisi P 14 100% P 254/MA5/V/23
24 25-May-23 MA 2 Candra FOC 2 011 PS 117 U/ support pekerjaan instrument P 7 100% P 307/MA2/V/23
25 25-May-23 MA 2 FOC 2 011 P 119 U/ support pekerjaan akses bordesk P 10 100% P 308/MA2/V/23
26 25-May-23 MA 4 Angga KPC 88 A 201 U/ support pembongkaran atap RL P 7 100% 309/MA4/V/23
27 25-May-23 MA 4 Kusnan KPC 48 LT 201 Ex bongkar substandart B 100% 310/MA4/V/23
28 24-May-23 MA 5 Wisnu Dermaga 68 Dermaga 68 U/ support LA Propylene dermaga 68 P 7 100% 311/MA5/V/23
29 22-May-23 MA 1 Aziz Bima FOC 1 10 PS 10 U/ support penggantian pipa P 7 100% 312/MA1/V/23
3 25-May-23 MA 5 Agus W Dermaga 63 60 SS 1 Untuk support perbaikan cable tray P 7 100% P 315/MA5/V/23
4 25-May-23 MA 5 Rachmat UTL RFCC UTL RFCC Ex cek valve B 100% P 316/MA5/V/23
5 25-May-23 MA 5 Endro UTL 50 054 E102/103 A/B Untuk support penggantian HE P 20 100% P 317/MA5/V/23
6 25-May-23 MA 5 Parikin 63 63 Untuk support penerangan lampu P 7 100% P 318/MA5/V/23
7 25-May-23 MA 5 Parikin 63 60 SS 1 Ex trafo B 100% P 319/MA5/V/23
11 26-May-23 MA 7 Ikkorianto KLBC 120 E 601 Untuk support tikcness P 7 100% P 323/MA7/V/23
12 22-May-23 MA 4 M Aji KPC 87 F 201 Ex bongkar perbaikan bocoran steam B 100% P 256/MA4/V/23
18 23-May-23 MA 1 Wisnu SRU 94 C 401 Ex bongkar di 94 C 401 B 100% P 298/MA1/V/23
19 23-May-23 MA 1 Wisnu SRU 93 A 401 Ex bongkar perbaikan sulfur pit B 100% P 299/MA1/V/23
20 25-May-23 MA 4 M Aji KPC 84 lorong Ex bongkar pengecatan pipa line flare B 100% P 302/MA4/V/23
21 25-May-23 MA 4 M Aji KPC 88 P 206 Ex bongkar perbaikan bocoran steam B 100% P 303/MA4/V/23
22 25-May-23 MA 4 M Aji KPC 80 PR 6 Ex bongkar perbaikan bocoran Heavy plat B 100% P 304/MA4/V/23
13 23-May-23 MA 4 Pras W LOC 3 240 K 101 Untuk support bocoran condensate P 7 100% P 280/MA4/V/23
1 25-May-23 MA 3 Fajri IK 70 73 U/ support perb. Leaking style 80 P 2 100% P 333/MA3/V/23
2 25-May-23 MA 3 Fajri IK 70 73 Ex bongkar perb. Leaking Style 80 B 100% P 334/MA3/V/23
3 15-May-23 MA 4 Tri Asmoro LOC 3 240 P 114 U/ support steaming out Line pompa P 7 100% P 335/MA4/V/23
25 25-May-23 MA 1 Roy A FOC 1 11 E 13 Pasang scaffolding P 7 100% P 326/MA4/V/23
26 26-May-23 MA 3 Widodo 70 73 U/ support perbaikan Leaking style 50 P 7 100% P 327/MA3/V/23
27 26-May-23 MA 3 Fauzi A 70 75 U/ support perbaikan MOV tanki 71 T 20 P 7 100% P 328/MA3/V/23
28 27-May-23 MA 2 Rachmat FOC 2 01 PS 154 U/ support perbaikan isolasi P 15 100% P 329/MA2/V/23
29 27-May-23 MA 2 Rachmat FOC 2 011 E 110 Box 2 U/ support open Cover Fin fan P 7 100% P 330/MA2/V/23
21 27-May-23 MA 2 Rachmat FOC 2 019 BL Ex pekerjaan isolasi B 100% P 321/MA2/V/23
22 26-May-23 MA 5 Luqmanul UTL 05 057 E 101 Ex bocoran cover HE B 100% P 322/MA3/V/23
23 26-May-23 MA 4 M Aji M KPC 84 K 202 A Untuk support bocoran steam P 7 100% P 324/MA4/V/23
15 24-May-23 MA 1 Wisnu FOC 1 11 K 401 U/ support penggantian pipa P 7 100% P 293/MA1/V/23
16 24-May-23 MA 1 Wisnu FOC 1 11 U/ support perbaikan Union P 10 100% P 294/MA1/V/23
17 25-May-23 MA 4 M Aji KPC 84 V 221 Ex bongkar pengecatan B 100% P 305/MA4/V/23
18 26-May-23 MA 1 Wisnu FOC 1 11 P 23 AB U/ support cleaning strainer P 7 100% P 320/MA1/V/23
10 17-May-23 MA 1 Aziz B FOC 1 11 F 1 Untuk support Isolasi P 7 100% P 218/MA1/V/23
11 17-May-23 MA 5 Aziz UTL 50 51 E 3 Ex perbaikan bocoran B 100% P 264/MA5/V/23
12 22-May-23 MA 3 Arif OM 30 38 T 103 Bongkar scaffolding B 100% P 265/MA3/V/23
8 17-May-23 MA 1 Zaenal SRU 91 K 401 Untuk support perbaikan P 7 100% P 208/MA1/V/23
4 22-May-23 MA 4 Raga Ananta KPC KPC Ex kanopi B 100% P 268/MA4/V/23
10 30-May-23 MA 6 Zidnie Ilma RFCC 104 K 501 Ex perbaikan atap B 100% P 364/MA6/V/23
8 29-May-23 MA 1 Roy A 25 F 1 25 F 1 Bongkar scaffolding B 100% P 361/MA1/V/23
20 29-May-23 MA 1 Wisnu FOC 1 11 P 23 Ex cleaning strainer B 100% P 340/MA1/V/23
18 29-May-23 MA 2 Depta FOC 2 19 BL Ex reinjeckt OLLS B 7 100% 338/MA2/V/23
11 26-May-23 MA 1 Awang LOC 1 20 SS 1 Untuk support painting trafo P 7 100% P 314/MA1/V/23
9 24-May-23 MA 1 Wisnu FOC 1 14 K 1 U/ support perbaikan pipa P 10 100% P 292/MA1/V/23
1 8-May-23 MA 7 Frans S GTO 106 Untuk support pengecatan structure P 17 100% P 102/MA7/V/23
41 30-May-23 MA 5 M Syarifudin UTL 05 05 PS 122 Untuk perbaikan line condensate P 7 100% P 380/MA5/V/23
42 31-May-23 MA 7 Ikkorianto PLBC 120 Untuk pekerjaan reinjeck OLLS P 7 100% P 381/MA5/V/23
35 31-May-23 MA 4 Tri Asmoro LOC 3 260 V 104 Ex line steam B 100% P 374/MA4/V/23
36 31-May-23 MA 4 Tri Asmoro LOC 3 200 PS 608 Ex bocoran line steam B 100% P 375/MA4/V/23
37 31-May-23 MA 1 Aziz B FOC 1 11 E 17 Bongkar scaffolding B 100% P 376/MA1/V/23
28 26-May-23 MA 3 Agusalim 70 71 T 20 untuk perbaikan MOV P 3 100% P 367/MA3/V/23
23 29-May-23 MA 1 Roy A FOC 1 11 E 13-11C8 Bongkar scaffolding B 100% P 360/MA1/V/23
24 30-May-23 MA 2 FOC 2 FOC 2 011 PS 123-124 Ex line CWS B 100% P 362/MA1/V/23
25 30-May-23 MA 2 FOC 2 LOC 2 021 C 103 Ex perbaikan isolasi B 100% P 363/MA1/V/23
20 29-May-23 MA 7 NF Asror GTO 106 Untuk pengecetan structure B 100% P 344/MA7/V/23
21 30-May-23 MA 4 Pras W LOC 3 240PS 143 Ex 240 PS 143/ 240 K 101 B 100% P 358/MA4/V/23
17 29-May-23 MA 5 Aziz 63 63 A 501 D Untuk cleaning strainer P 14 100% P 341/MA5/V/23
13 29-May-23 MA 1 Roy A FOC 1 14 F 5 Pasang scaffolding P 7 100% P 336/MA1/V/23
14 29-May-23 MA 4 Angga KPC 86 PL 8003 Untuk support pekerjaan P 7 100% P 337/MA4/V/23
15 29-May-23 MA 1 Wisnu FOC 1 11 F 1 Untuk perbaikan pipa air 1" P 7 100% P 339/MA1/V/23
10 27-May-23 MA 4 Davit LOC 3 260 K 102A U/ support perbaikan bocoran Tubing P 7 100% P 331/MA4/V/23
11 27-May-23 MA 1 Wiisnu FOC 1 11 PS 10 90 Untuk bocoran pipa P 7 100% P 332/MA1/V/23
25 5-Jun-23 MA 1 Irvan FOC 1 12 K 1 C Ex cleaning strainer B 100% P 19/MA1/VI/23
26 5-Jun-23 MA 1 Irvan FOC 1 11 F 1 Ex bocoran pipa air B 100% P 20/MA1/VI/23
21 5-Jun-23 MA 1 Irvan SRU 90 V 404 Bongkar scaffolding B 100% P 15/MA1/VI/23
22 5-Jun-23 MA 1 Irvan SRU 94 E 401 Ex hot bolting B 100% P 16/MA1/VI/23
8 29-May-23 MA 3 Eko N 70 75 Ex selter solar B 100% P 389/MA3/V/23
9 29-May-23 MA 3 Agusalim 70 73 Ex MOV Tanki B 100% P 390/MA3/V/23
1 29-May-23 MA 5 Kevin UTL RFCC 152 FD 009-010 Ex flange detektor B 100% P 382/MA5/V/23
24 31-May-23 MA 1 Aziz B FOC 1 93 A 404 Bongkar scaffolding B 100% P 378/MA1/V/23
25 31-May-23 MA 1 Aziz B FOC 1 94 C 401 Bongkar scaffolding B 100% P 379/MA1/V/23
21 31-May-23 MA 4 Tri Asmoro LOC 3 220 Ex steaming OUT (oprate valve) B 100% P 372/MA4/V/23
22 31-May-23 MA 4 Tri Asmoro LOC 3 260 Ex line discharge B 100% P 373/MA4/V/23
19 31-May-23 MA 4 Angga KPC 86 PL 8097 Untuk fasilitas Cui P 10 100% P 370/MA4/V/23
11 25-May-23 MA 5 Parikin 63 Dermaga Untuk support penerangan lampu P 7 100% P 318/MA5/V/23
12 29-May-23 MA 1 Zaenal LOC 1 25 LT 004-005 Untuk perbaikan level trasmiter P 7 100% P 342/MA1/V/23
13 29-May-23 MA 7 NF Asror GTO 106 Untuk pengecetan structure tangga P 7 100% P 343/MA7/V/23
14 29-May-23 MA 5 Aziz UTL 50 54 WS 2 Untuk support bocoran pipa prodact P 7 100% P 359/MA5/V/23
15 30-May-23 MA 6 Imron M RFCC 102 E 520 A 2 Untuk perbaikan fin fan P 7 100% P 365/MA6/V/23
8 25-May-23 MA 5 Endro UTL 50 TG 50 Ex painting beam troling B 100% P 313/MA5/V/23
9 25-May-23 MA 1 Roy A FOC 1 48 Flare Pasang scaffolding P 7 100% P 325/MA4/V/23
13 31-May-23 MA 1 Aziz B FOC 1 11 E 7 Bongkar scaffolding B 100% P 377/MA1/V/23
14 29-May-23 MA 3 Widodo 70 71 T 11 Ex sorokan 24" B 100% P 383/MA3/V/23
15 29-May-23 MA 3 Widodo 70 71 T 12 Ex sorokan 24" B 100% P 384/MA3/V/23
16 29-May-23 MA 3 Widodo 70 71 T 15 Ex sorokan 24" B 100% P 385/MA3/V/23
17 29-May-23 MA 3 Widodo 70 71 T 17 Ex sorokan 24" B 100% P 386/MA3/V/23
18 29-May-23 MA 3 Widodo 70 71 T 16 Ex sorokan 24" B 100% P 387/MA3/V/23
19 30-May-23 MA 5 Rachmat UTL 50 51 G 3 Untuk support generan cleaning P 7 100% P 388/MA5/V/23
11 31-May-23 MA 4 Angga KPC 82 PL 8085 Untuk fasilitas Cui P 10 100% 369/MA4/V/23
21 31-May-23 MA 2 Salis N LOC 2 023 V 103 Ex Bocoran steam B 100% P 392/MA2/V/23
22 31-May-23 MA 2 Salis N LOC 2 024 PS 140 Ex line propane B 100% P 393/MA2/V/23
23 31-May-23 MA 2 Salis N LOC 2 021 STR 101 Ex Bocoran steam B 100% P 394/MA2/V/23
24 31-May-23 MA 2 Salis N LOC 2 024 P 103 Ex akses buka cover B 100% P 395/MA2/V/23
25 31-May-23 MA 2 Salis N LOC 2 01 PS 105 Ex Bocoran steam B 100% P 396/MA2/V/23
26 31-May-23 MA 2 Salis N LOC 2 024 E 127 Ex bocoran hidro carbon B 100% P 397/MA2/V/23
27 31-May-23 MA 2 Salis N LOC 2 022 V 102 Ex Bocoran steam B 100% P 398/MA2/V/23
28 5-Jun-23 MA 1 Irvan FOC 1 12 E 1 A Ex hot bolting B 100% P 12/MA1/VI/23
29 5-Jun-23 MA 1 Irvan FOC 1 11 E 7 Ex hot bolting B 100% P 13/MA1/VI/23
30 5-Jun-23 MA 1 Irvan FOC 1 11 E 7 Ex sorokan B 100% P 14/MA1/VI/23
31 5-Jun-23 MA 1 Irvan FOC 1 11 E 25 Ex hot bolting B 100% P 17/MA1/VI/23
32 5-Jun-23 MA 1 Irvan FOC 1 12 K 1 C Untuk piping P 7 100% 18/MA1/VI/23
33 5-Jun-23 MA 5 Aziz UTL 50 051 E 101 Untuk support bocorn flexible hose P 14 100% P 21/MA5/VI/23
34 5-Jun-23 MA 5 Aziz UTL 50 53 T 1 Bongkar scaffolding B 100% P 22/MA5/VI/23
35 5-Jun-23 MA 5 Wisnu 64 Dermaga 64 Untuk perbaikan valve 12" P 7 100% P 23/MA5/VI/23
1 2-Jun-23 MA 2 Depta FOC 2 011 PS 134,135 Untuk support fire proofing P 7 100% P 1/MA2/VI/23
2 2-Jun-23 MA 2 Depta FOC 2 011 PS 131,132 Untuk support fire proofing P 7 100% P 2/MA2/VI/23
3 2-Jun-23 MA 2 Depta FOC 2 011 PS 133,134 Untuk support fire proofing P 7 100% P 3/MA2/VI/23
4 2-Jun-23 MA 2 Besar SP FOC 2 011 PS 117 Ex support instrument B 100% P 4/MA2/VI/23
5 2-Jun-23 MA 2 Besar SP FOC 2 011 E 103 Untuk support instrument P 7 100% P 5/MA2/VI/23
6 2-Jun-23 MA 2 Salis N LOC 2 022 E 109 Ex bocoran HE B 100% P 6/MA2/VI/23
8 2-Jun-23 MA 2 Depta FOC 2 013 C 101 Untuk support CUF P 10 100% P 8/MA2/VI/23
9 2-Jun-23 MA 2 Depta FOC 2 018 R 101 Untuk support CUF P 10 100% P 9/MA2/VI/23
10 2-Jun-23 MA 2 Ilyas FOC 2 013 E 107 MO 7 Ex brearing fin fan B 100% P 10/MA2/VI/23
11 2-Jun-23 MA 2 Ilyas FOC 2 018 E 105 K1 Untuk support perbaikan bearinf fin fan P 5 100% P 11/MA2/VI/23
12 1-Jun-23 MA 5 Rachmat UTL 50 54 P 202 A,B,C Untuk penggantian ARC Valve P 7 100% P 24/MA5/V/23
13 1-Jun-23 MA 5 Rachmat UTL 50 51 G 3 Ex cleaning 51 3 B 100% P 25/MA5/V/23
14 1-Jun-23 MA 5 Rachmat UTL 50 51 E 3 Ex penggantian lo cooler & air cooler B 100% P 26/MA5/V/23
20 6-Jun-23 MA 1 Irvan FOC 1 11 C 1 Untuk support taping point line LGO P 10 100% P 32/MA5/VI/23
15 6-Jun-23 MA 4 M Aji M KPC 84 K 202 A Ex perbaikan isolasi B 100% P 27/MA4/VI/23
16 6-Jun-23 MA 4 M Aji M KPC 84 K 202 A Selatan Ex bocoran steam B 100% P 28/MA4/VI/23
7 17-May-23 MA 3 Ikhan OM 30 30 E 0012 Ex akses jembatan B 100% P 282/MA5/V/23
4 23-May-23 MA 1 Adimas LOC 1 21 PS 20/22 Untuk kabel tray instrument P 7 100% P 399/MA1/V/23
4 31 mei 23 MA 4 Pras W LOC 3 220 V 103 Bongkar scaffolding B 100% P 400/MA4/V/23
17 5-Jun-23 MA 3 Widodo 70 71 Untuk selter sub jalan Z P 30 100% P 42/MA3/VI/23
17 5-Jun-23 MA 3 Widodo 70 70 P 9 B Untuk mobilisasi diesel enggine P 7 100% P 43/MA3/VI/23
17 6-Jun-23 MA 3 Fajri IK 70 71 T 19 Ex sorokan 24" B 100% P 44/MA3/VI/23
17 6-Jun-23 MA 3 Fajri IK 70 70 P 9 Ex mobilisasi diesel enggine B 100% P 45/MA3/VI/23
18 6-Jun-23 MA 1 Jordan LOC 1 20 SS 1 Bongkar scaffolding B 100% P 46/MA1/VI/23
9 6-Jun-23 MA 6 Yusro RFCC 102 102 PS 005 Ex kabel tray instrument B 100% P 40/MA6/VI/23
5 6-Jun-23 MA 1 Adimas LOC 1 25 LT 004-005 25 V 1 Pasang scaffolding P 7 100% P 37/MA1/VI/23
9 6-Jun-23 MA 6 Anas AF RFCC 101 101 K 501 Ex painting stuckture B 100% P 38/MA6/VI/23
15 6-Jun-23 MA 2 Depta FOC 2 13 PS 121 Untuk support line steam 1" P 100% P 31/MA2/VI/23
18 7-Jun-23 MA 1 Aziz B FOC 1 11 P 4 Untuk support hot bolting P 7 100% 48/MA1/VI/23
4 7-Jun-23 MA 7 Ikkorianto GTO 106 Untuk line injeksi AO dan ASA P 100% P 52/MA7/VI/23
16 7-Jun-23 MA 4 Tri Yulianto KPC 39 T 212 Untuk tempat berteduh P 100% P P 47/MA4/VI/23
1 6-Jun-23 MA 5 Aziz UTL 50 UTL 50 Untuk bocoran MPS temporary P 14 100% 49/MA5/VI/23
2 8-Jun-23 MA 6 Zidnie Ilma RFCC 101 V 502 Untuk bocoran line katalise lantai 10 P 7 100% P 50/MA6/VI/23
3 6-Jun-23 MA 1 Roy A LOC 1 24 Untuk line steam P 14 100% 35/MA1/VI/23
14 6-Jun-23 MA 2 Depta LOC 2 41 T 119 Untuk support akses selter P 100% P 30/MA2/VI/23
1 6-Jun-23 MA 1 Roy A LOC 1 24 Coling water Untuk line coolong water P 7 100% 33/MA1/VI/23
2 10-May-23 MA 5 Endro UTL 05 05 PS 139-142 Ex pengecatan structure B 100% P 133/MA5/V/23
3 11-May-23 MA 5 Iryan B UTL RFCC Dermaga 63 U/ support cover pile dermaga area 63 P 7 continue P 157/MA5/V/23
7 26-May-23 MA 7 Ikkorianto KLBC 120 E 601 Untuk support tikcness P 7 100% P 323/MA7/V/23
18 8-Jun-23 MA 6 Zidnie Ilma RFCC 101 BL Ex bongkar isolasi B 100% P 51/MA6/VI/23
19 5-Jun-23 MA 5 Iryan B UTL 50 54 T 2/T1 Ex selter perbaikan tanki B 100% P 53/MA5/VI/23
11 30-May-23 MA 5 M Syarifudin UTL 500 530 S 301/302 Ex beam Trasmiter P 7 100% P 391/MA5/V/23
9 8-Jun-23 MA 7 Asror LNHT 120E 607 Untuk pekerjaan tikness P 7 100% P 69/MA1/VI/23
10 9-Jun-23 MA 7 Asror PLBC 100 E 611 B Untuk pekerjaan tikness P 7 100% P 70/MA1/VI/23
5 9-Jun-23 MA 1 Wisnu FOC 1 16 R1 Untuk support Hottap P 7 100% P 65/MA1/VI/23
6 9-Jun-23 MA 1 Wisnu FOC 1 11 P 4 Ex hot bolting B 100% P 66/MA1/VI/23
7 9-Jun-23 MA 1 Wisnu FOC 1 11 C 6 Ex re inject OLLS B 100% P 67/MA1/VI/23
1 8-Jun-23 MA 5 Aziz UTL 05 05 PS 123 U/ support bocoran pipa P 14 100% P 61/SP/P/VI/23
2 7-Jun-23 MA 5 Aziz UTL 05 05 PS 122 U/ support bocoran pipa P 14 100% P 62/SP/P/VI/23
4 8-Jun-23 MA 7 Ikkorianto KLBC 120 E 604 B Untuk support tikcness P 7 100% P 74/MA7/VI/23
23 9-Jun-23 MA 4 Tri Asmoro KPC Bongkar scaffolding B 100% P 64/MA4/VI/23
22 9-Jun-23 MA 4 Fangky KPC 86 C 201 Ex bongkar wrapping dan isolasi B 100% P 63/MA4/VI/23
1 11-Jun-23 MA 2 Salis N LOC 2 022 K 101 Perbaikan line propare P 7 100% P 90/MA2/VI/23
10 6-Jun-23 MA 1 Roy A LOC 1 21 C 1 Untuk steaming out line wash gas P 7 xx 34/MA1/VI/23
10 12-Jun-23 MA 7 NF Asror KLBC 140 R 601 B Untuk support LRUT P 7 100% P 88/MA7/VI/23
7 12-Jun-23 MA 7 NF Asror KLBC 140 V 604 Untuk modivikasi line N2 P 7 100% P P 85/MA7/VI/23
4 12-Jun-23 MA 1 Aziz B FOC 1 12 K 1 Bongkar perbaikan pipa B 100% P 82/MA1/VI/23
5 12-Jun-23 MA 1 Aziz B FOC 1 16 PS 21 Untuk support operate valve P 7 100% P 83/MA1/VI/23
24 12-Jun-23 MA 5 Iryan B UTL 500 510 E 601 Untuk support condensore P 7 100% P 76/MA5/VI/23
25 9-Jun-23 MA 6 Anas AF RFCC 101 101 P 502 B Untuk tambahan line by pass check P 7 100% P 77/MA6/VI/23
19 8-Jun-23 MA 1 Irvan FOC 1 12 E 1 F Untuk painting beam P 7 100% P 60/MA1/VI/23
20 9-Jun-23 MA 1 Wisnu FOC 1 19 E 1B,1D Untuk verifikasi P 7 100% P 68/MA1/VI/23
21 9-Jun-23 MA 7 Ikkorianto KLBC 140 Untuksupport modifikasi line P 7 100% P 72/MA7/VI/23
17 8-Jun-23 MA 1 Irvan FOC 1 FOC 1 Untuk MOV GAS P 10 100% P 58/MA1/VI/23
10 6-Jun-23 MA 1 Roy A LOC 1 CPI Pasang scaffolding P 30 100% 36/MA1/VI/23
8 2-Jun-23 MA 2 Depta FOC 2 011 V 107 Untuk support CUF P 10 100% P 7/MA2/VI/23
15 8-Jun-23 MA 1 Irvan SRU 93 P 402 Untuk piping P 14 100% P 59/MA1/VI/23
16 9-Jun-23 MA 7 Ikkorianto KLBC 140 D 601 Untuk support adsorben P 7 100% P 73/MA7/VI/23
17 8-Jun-23 MA 7 Ikkorianto KLBC 140 D 601 A Untuk support tikcness P 7 100% P 75/MA7/VI/23
18 11-Jun-23 MA 4 Tri Yulianto KPC 84 E 202 Bongkar scaffolding B 100% P 79/MA4/VI/23
19 9-Jun-23 MA 3 Agusalim 70 70 SS 1 Pasang scaffolding P 7 100% P 80/MA3/VI/23
20 9-Jun-23 MA 3 Agusalim 70 LA 72 X 201 Untuk perbaikan leaking style P 7 100% P 81/MA3/VI/23
21 12-Jun-23 MA 7 NF Asror KLBC 120 E 601 Ex tikness B 100% P P 84/MA7/VI/23
3 13-Jun-23 MA 7 Wahyu GTO 106 Ex line injeksi AO dan ASA B 100% P 93/MA7/VI/23
4 13-Jun-23 MA 7 Wahyu 140 140 E 602 Untuk support bocoran HE P 7 100% P 94/MA7/VI/23
8 13-Jun-23 MA 1 Aziz B SRU 93 Ex bongkar N2 B 100% P 98/MA1/VI/23
11 13-Jun-23 MA 4 M Aji KPC 84 PR 7-8 Untuk painting pipa P 7 100% P 101/MA4/VI/23
9 14-Jun-23 GMT Mafrio Gd Surplus Gd surplus Pinjam material P 270 100% P 122/MA2/VI/23
10 14-Jun-23 MA 1 Irvan LOC 1 41 T 19 Ex cleaning 41 T 19 B 100% P 123/MA1/VI/23
1 10-Jun-23 MA 3 Widodo 70 72 Ex perbaikan leaking style 50 72 X 201 B 100% P 114/MA3/VI/23
2 10-Jun-23 MA 3 Widodo 70 70 Ex pekerjaan line pipa 10 " B 100% P 115/MA3/VI/23
3 10-Jun-23 MA 3 Widodo 70 72 X 203 Ex perbaikan telescopic B 100% P 116/MA3/VI/23
4 10-Jun-23 MA 3 Widodo 70 71 T 1 Ex perbaikan MOV Tanki B 100% P 117/MA3/VI/23
5 10-Jun-23 MA 3 Widodo 70 70 SS 1 Bongkar scaffolding B 100% P 118/MA3/VI/23
30 13-Jun-23 MA 2 Salis N LOC 2 022 PS 115 U/ support CCTV P 7 100% P P 107/MA2/VI/23
21 31-May-23 MA 5 Agus W UTL 500 500 PS 16 Untuk support perbaikan lampu P 5 100% P 96/MA5/VI/23
22 13-Jun-23 MA 1 Tri Wurtanto SRU 93 FV 032 Pasang scaffolding P 7 100% P 97/MA1/VI/23
16 12-Jun-23 MA 6 Zidnie Ilma RFCC 101 R 502 Untuk tiknes P 7 100% P 87/MA6/VI/23
17 12-Jun-23 MA 7 NF Asror KLBC 140 R RGDI Untuk support LRUT P 7 100% P 89/MA7/VI/23
10 6-Jun-23 MA 7 Ikkorianto GTO 106 Ex bocoran out let B 100% P 41/MA7/VI/23
11 8-Jun-23 GMT Alfian Ghani Lapangan HO Lapangan HO Untuk support shoting club P 7 100% P 54/GMT/VI/23
16 31-May-23 MA 5 Agus W 63 P 102 A 63 A 501 D Ex bongkar cleaning clarifier B 100% P 95/MA5/VI/23
18 13-Jun-23 MA 1 Roy A SRU 22 E 9 Untuk perbaikan line CWR P 7 100% P 100/MA1/VI/23
19 13-Jun-23 MA 2 Depta FOC 2 017 P 106 A Untuk isolasi line 14 P 7 100% P 102/MA2/VI/23
20 13-Jun-23 MA 2 Depta FOC 2 011 E 118 Untukisolasi line 18" P 7 100% P 103/MA2/VI/23
22 11-Jun-23 MA 4 Kusnan KPC 84 Untuk substandar instrument P 7 100% P 105/MA4/VI/23
23 13-Jun-23 MA 2 Depta FOC 2 015 E 101 Untuk isolasi line 4" P 7 100% P 106/MA2/VI/23
24 13-Jun-23 MA 4 M Aji KPC 88-89 Untuk perbaikan sub standar area C P 7 100% P 108/MA4/VI/23
25 13-Jun-23 MA 2 David FOC 2 012 F 102 Untuk inpeksi cui P 7 100% P 109/MA2/VI/23
26 13-Jun-23 MA 2 M khoirudin FOC 2 012 E 103 1/2 Untuk inpeksi cui P 7 100% P 110/MA2/VI/23
27 13-Jun-23 MA 2 Salis N FOC 2 012 P 103 AB Untuk inpeksi cui P 7 100% P 111/MA2/VI/23
28 13-Jun-23 MA 4 M Aji KPC 49 Untuk pasang BA loading tank cor P 7 100% P 112/MA4/VI/23
30 14-Jun-23 MA 2 Prasetyo FOC 2 015 E 107 KG Untuk perbaikan bearing fin fan P 10 100% P P 120/MA2/VI/23
31 13-Jun-23 MA 4 Fangky KPC 84 E202 C Untuk support perbaikan plenum P 5 100% P 121/MA4/VI/23
35 14-Jun-23 MA 1 Wisnu FOC 1 11 V 8 Untuk penggantian pipa P 7 100% P 127/MA1/VI/23
36 14-Jun-23 MA 3 Yulianto OM 40 49 Untuk penggantian pipa P 7 100% P 128/MA3/VI/23
37 14-Jun-23 MA 5 Iryan B UTL 500 520 B 401 Untuk support bocoran steam flange P 14 100% P 129/MA5/VI/23
38 14-Jun-23 MA 5 Aziz B UTL 50 54 T 3 Ex cleaning tanki B 100% P 130/MA5/VI/23
39 13-Jun-23 MA 5 Iryan B UTL 50 54 WS 201 ex perbaikan OLLS line fuel oil B 7 100% P 113/MA5/VI/23
18 15-Jun-23 MA 6 Guntani RFFC 101 P 522 C Untuk akses hottap P 100% P 148/MA6/VI/23
1 13-Jun-23 MA 3 Widodo 70 73 U/ Support Fix drip sampler LA 73X02 P 7 100% P 131/MA3/VI/23
2 13-Jun-23 MA 3 Fajri IK 70 73 U/ support perb pedestal Crane 73X8 P 15 100% P 132/MA3/VI/23
3 13-Jun-23 MA 3 Widodo 70 73 U/ Support Fix drip sampler LA 73X01 P 7 100% P 133/MA3/VI/23
4 13-Jun-23 MA 3 Widodo 70 73 U/ Support Fix drip sampler LA 73X04 P 7 100% P 134/MA3/VI/23
5 13-Jun-23 MA 3 Widodo 70 73 U/ Support Fix drip sampler LA 73X03 P 7 100% P 135/MA3/VI/23
6 14-Jun-23 MA 3 Widodo 70 73 U/ Support perb Leaking style LA 73X102 P 30 100% P 136/MA3/VI/23
7 14-Jun-23 MA 3 Widodo 70 73 Ex bongkar Leaking style 73X102 B 100% P 137/MA3/VI/23
8 15-Jun-23 MA 1 Roy A LOC 1 24 PS 65 Untuk support cooling water 1" P 7 100% P 138/MA1/VI/23
17 13-Jun-23 MA 2 M Anwar FOC 2 013 E 111 K02 Untuk perbaikan fin fan P 7 100% P 104/MA2/VI/23
18 14-Jun-23 MA 2 Prasetyo FOC 2 011 E 110 K 26 Untuk perbaikan bearing fin fan P 7 100% P 119/MA2/VI/23
19 15-Jun-23 MA 1 Hafidh LOC 1 25 V 1 Pasang scaffolding P 10 100% P 124/MA1/VI/23
20 14-Jun-23 MA 1 Aziz B SRU 94 E 402 Untuk perbaikan expansion joint P 7 100% P 125/MA1/VI/23
22 15-Jun-23 MA 1 Roy A LOC 1 24 PS 63 Untuk support cooling water 1" P 7 100% P 139/MA1/VI/23
23 15-Jan-23 MA 2 Depta FOC 2 011 E 132 M1,M2 Ex dudukan blower B 100% P 140/MA2/VI/23
24 15-Jan-23 MA 2 Depta FOC 2 018 R 101 Ex fire proofing ( CUF) B 100% P 141/MA2/VI/23
26 15-Jan-23 MA 2 Depta FOC 2 011 V 107 Ex CUF B 100% P 143/MA2/VI/23
27 15-Jan-23 MA 2 Depta FOC 1 011 E 125 KS Ex perbaikan fin fan B 100% P 144/MA2/VI/23
28 15-Jan-23 MA 2 David LOC 2 024 PS 130 Untuk isolasi P 7 100% P 145/MA2/VI/23
29 15-Jan-23 MA 2 David LOC 2 21 Untuk sproket valve P 7 100% P 146/MA2/VI/23
30 15-Jun-23 MA 6 Guntani RFFC 101 Untuk reinject OLLS P 100% P 147/MA6/VI/23
31 15-Jun-23 MA 7 Ega Yusuf K GTO 108 K 502 AM Untuk penggantian valve P 100% P 149/MA7/VI/23
11 16-Jun-23 MA 6 Guntani RFCC 101 FT 087 Untuk reinjeck OLLS P 100% P 160/MA6/VI/23
8 16-Jun-23 MA 4 Fanky KPC 84 PR 7.8 Ex pengecatan B 100% P 157/MA4/VI/23
4 16-Jun-23 MA 1 Aziz B SRU 91 K 402 Untuk perbaikan plenum P 7 100% P 153/MA1/VI/23
17 14-Jun-23 MA 1 Wisnu FOC 1 11 F 1 Ex isolasi B 100% P 126/MA1/VI/23
18 15-Jan-23 MA 2 Depta FOC 2 014 BL Ex bongkar painting B 100% P 142/MA2/VI/23
1 16-Jun-23 MA 6 Guntani RFCC 101 101 HV 026 Pasang scaffolding P 7 100% P 162/MA6/VI/23
1 16-Jun-23 MA 6 Anas AF RFCC 101 101 E 523 Untuk lepas pasang HE P 7 100% P 163/MA6/VI/23
3 16-Jun-23 MA 5 Luqmanul UTL RFCC UTL RFCC Untuk perbaikan AUX Boiler A P 7 100% P 164/MA5/VI/23
4 16-Jun-23 MA 7 NF Asror KLBC 120 E 601 A Untuk support LRUT P 7 100% P 165/MA7/VI/23
4 16-Jun-23 MA 7 NF Asror KLBC 140 R 601 A/B Untuk support LRUT P 7 100% P 166/MA7/VI/23
4 16-Jun-23 MA 7 NF Asror KLBC 140 E 602 Untuk support LRUT P 7 100% P 167/MA7/VI/23
1 16-Jun-23 MA 7 NF Asror KLBC 140 R 601 A/B Untuk support LRUT P 7 100% P 166/MA7/VI/23
2 17-Jun-23 MA 7 NF Asror KLBC 140 C 601 Untuk pekerjaan LRUT line H2 P 14 100% P 168/MA7/VI/23
3 18-Jun-23 MA 5 Iryan B UTL RFCC 151 B 501 A Pasang scaffolding P 7 100% P 169/MA7/VI/23
21 16-Jun-23 MA 1 Imam FOC 1 011 FT 046/011 E 130 Ex pekerjaan instrument B 100% P 155/MA4/VI/23
22 16-Jun-23 MA 4 Fanky KPC 84 F 201 Ex pver plat B 100% P 156/MA4/VI/23
17 14-Jun-23 MA 4 M Aji KPC 80 PR G-H Ex perbaikan pipa B 100% P 150/MA3/VI/23
18 16-Jun-23 MA 1 Roy A LOC 1 23 E 9 Bongkar scaffolding B 100% P 151/MA1/VI/23
19 16-Jun-23 MA 4 Pras W LOC 3 240 P 154 A/B Ex perbaikan Isolasi B 100% P 152/MA4/VI/23
24 16-Jun-23 MA 2 Salis N FOC 2 01 PS 115 Untuk bocoran steam P 7 100% P 159/MA2/VI/23
25 16-Jun-23 MA 6 Guntani RFCC 101 Ex flushing line Oil HGO B 100% P 161/MA6/VI/23
18 16-Jun-23 MA 4 Pras W LOC 3 260 V 160 Untuk pengecatan P 14 Continue P 154/MA4/VI/23
19 16-Jun-23 MA 1 Imam FOC 1 014 E 110 Ex pressure garage B 100% P 158/MA4/VI/23
20 19-Jan-23 MA 6 Fuad FOC 2 018 / OB Untuk perbaikan lampu sorot P 7 100% P 168/MA2/VI/23
21 19-Jun-23 MA 1 Aziz B FOC 1 12 Ex bongkar pengecatan beam B 100% P 169/MA2/VI/23
22 19-Jan-23 MA 5 Agus UTL 500 PS 16-19 Ex perbaikan lampu sekitar B 100% P 170/MA2/VI/23
23 19-Jun-23 MA 5 Endro UTL 50 54 WS 201 Untuk perbaikan line steam P 4 100% P 171/MA2/VI/23
14 12-Jun-23 MA 6 Zidnie Ilma RFCC 101 Untuk parameter CEMS P 7 100% P 86/MA6/VI/23
10 6-Jun-23 MA 6 Yusro RFCC 101 Untuk kabel tray P 7 100% P 39/MA6/VI/23
8 20-Jan-23 MA 4 Fanky KPC 85 PR 15 Untuk pekerjaan cui P 4 100% P 179/MA4/VI/23
6 20-Jan-23 MA 4 Tri Asmoro LOC 3 200 PS 127 Untuk bocoran steam line condensateheater P 7 100% P 177/MA4/VI/23
4 20-Jun-23 MA 1 Awang M FOC 1 14 Untuk angkat kabel power termoheater P 14 100% P 175/MA1/VI/23
1 13-Jun-23 MA 3 OM 30 31 T 7 Untuk pasang scaffolding P 7 100% P 172/MA3/VI/23
2 19-Jun-23 MA 3 Widodo 70 73 Untuk line pipa solar 2" jocky pump P 10 100% P 173/MA3/VI/23
18 19-Jun-23 MA 4 Kusnan KPC 88 Untuk perbaikan sub stabdar instrument P 7 100% P 178/MA4/VI/23
19 20-Jan-23 MA 4 Fanky KPC 84 F 201 Untuk pekerjaan CUI dan Assesment P 5 100% P 180/MA4/VI/23
20 20-Jan-23 MA 2 Salis N FOC 2 012 P 103 Ex pekerjaan isolasi B 100% P 181/MA2/VI/23
1 20-Jun-23 MA 7 NF Asror KLBC 140 V 603 Untuk inpeksi internal absorben P 2 100% P 182/MA7/VI/23
2 19-Jun-23 MA 2 Salis N FOC 2 018 PS 101 Untu bocoran steam P 7 100% P 183/MA2/VI/23
4 20-Jun-23 MA 2 Candra FOC 2 018 FT 105 Pasang scaffolding P 7 100% P 185/MA2/VI/23
5 8-Jun-23 MA 4 Rifki K KPC 88 Untuk perbaikan kabel tray P 7 100% P 186/MA2/VI/23
8 30-May-23 MA 4 Tri Asmoro LOC 3 All Area Untuk cleaning sower P 7 100% P 371/MA4/V/23
25 21-Jun-23 MA 5 M Syarifudin UTL 500 530 S 301/302 Ex perbaikan beam di strainer B 100% P 212/MA5/VI/23
26 21-Jun-23 MA 5 M Syarifudin UTL 05 054 WS 105 Bongkat scaffolding B 100% P 213/MA5/VI/23
27 21-Jun-23 MA 5 M Syarifudin UTL 500 520 B 401 ex bocoran steam flange boiler B 100% P 214/MA5/VI/23
28 21-Jun-23 MA 5 M Syarifudin UTL 500 54 P 202 A,B,D Ex penggantian ARC valve B 100% P 215/MA5/VI/23
23 22-Jun-23 MA 4 Fangky KPC 89 K 201 Ex isolasi B 7 100% P 210/MA4/VI/23
21 22-Jun-23 MA 4 Agus L KPC 84 PL 80 20 Untuk pekerjaan cui P 7 100% P 208/MA4/VI/23
13 21-Jun-23 MA 6 Bahron RFCC 101 K 501 MAB Untuk pengecatan structure P 7 Continue P 200/MA2/VI/23
14 20-Jun-23 MA 3 Fajri IK 70 73 Untuk fasilitas perbaikan leaking pd clam 18" P 10 100% P 201/MA1/VI/23
11 21-Jun-23 MA 5 Endro UTL RFCC 151 B 501 A Ex perbaikan boiler ( internal combuston) B 100% P 198/MA5/VI/23
9 21-Jun-23 MA 5 Endro UTL RFCC 156 A 501 A/B Untuk pemasangan boardes dan atap P 14 100% P 196/MA5/VI/23
5 21-Jun-23 MA 4 Tri Asmono KPC 80 Untuk suvice water belakang control room P 7 100% P 192/MA4/VI/23
6 21-Jun-23 MA 2 Salis N FOC 2 011 PS 10.36 Ex perbaikan pipa steam P 7 100% P 193/MA2/VI/23
7 21-Jun-23 MA 2 Salis N FOC 2 018 PS 103 Untuk perbaikan union P 7 100% P 194/MA2/VI/23
3 20-Jun-23 MA 4 Tri Asmono LOC 3 200 PS 141 Untuk bocoran steam condensate P 7 100% P 190/MA4/VI/23
17 15-Jun-23 MA 5 Aziz UTL 50 52 B 3 Untuk oprate out let valve P 14 100% P 184/MA5/VI/23
9 19-Jun-23 GMT Alfian Ghani Lapangan HO Lapangan HO Bongkar scaffolding B 100% P 55/GMT/VI/23
21 23-Jan-23 MA 1 Roy A LOC 1 24 PS 64 Ex perbaikan line cw B 100% P 232/MA1/VI/23
22 23-Jan-23 MA 1 Roy A LOC 1 24 PS 62 Ex perbaikan line Cw B 100% P 233/MA1/VI/23
23 23-Jan-23 MA 1 Roy A LOC 1 24 PS 49 Ex perbaikan line CW B 100% 234/MA1/VI/23
24 23-Jan-23 MA 1 Wisnu FOC 1 14 V 6 Untuk bocoran pipa 6" line H2 P 10 100% P 235/MA1/VI/23
25 23-Jun-23 MA 1 Roy A FOC 1 16 FT 019 Pasang scaffolding P 7 100% P 236/MA1/VI/23
26 22-Jun-23 MA 7 Frans S GTO 108 K 501/502 u/ support LRUT/Tikness P 7 100% P 237/MA7/VI/23
27 22-Jun-23 MA 7 Frans S GTO 105 E 501 Untuk support LRUT P 7 100% P 238/MA7/VI/23
28 22-Jun-23 MA 7 Frans S GTO 105 E 502 Untuk support LRUT P 7 100% P 239/MA7/VI/23
29 23-Jun-23 MA 7 Ikkorianto GTO 140 V 603 Ex penggantian absorben B 100% P 240/MA7/VI/23
18 23-Jan-23 MA 1 Aziz FOC 1 16 Untukpasang sorokan P 7 100% P 229/MA1/VI/23
10 22-Jun-23 MA 5 Endro UTL 05 054 E 102/103 AB Ex penggantian HE B 100% P 221/MA5/VI/23
11 22-Jun-23 MA 5 M Syarifudin UTL 05 05 PS 123 Ex perbaikan bocoran pipa B 100% P 222/MA5/VI/23
12 22-Jun-23 MA 5 M Syarifudin UTL 05 05 PS 122 Ex perbaikan bocoran pipa B 100% P 223/MA5/VI/23
13 22-Jun-23 MA 5 M Syarifudin UTL 05 05 PS 122 Ex perbaikan line condensate B 100% P 224/MA5/VI/23
14 22-Jun-23 MA 5 M Syarifudin UTL 05 05 PS 109 Ex bocoran gland paking B 100% P 225/MA5/VI/23
2 21-Jun-23 MA 5 M Syarifudin UTL 05 054 WS 105 Bongkar scaffolding B 100% P 213/MA5/VI/23
3 21-Jun-23 MA 5 M Syarifudin UTL 500 520 B 401 Ex bocoran steam flange B 100% P 214/MA5/VI/23
4 21-Jun-23 MA 5 M Syarifudin UTL 500 530 S 301 Ex penggantian ARC valve B 100% P 215/MA5/VI/23
5 22-Jun-23 MA 2 Endro FOC 2 019 E 105 Pasang scaffolding P 14 100% P 216/MA2/VI/23
6 22-Jun-23 MA 5 M Syarifudin UTL 05 05 PS 164 Untuk perbaikan bocoran P 14 100% P 217/MA5/VI/23
7 22-Jun-23 MA 5 Endro UTL 50 54 WS 210 Perbaikan line blow down P 14 100% P 218/MA5/VI/23
8 21-Jun-23 MA 5 Ikhsan 68 Dermaga 68 EX LA propylene B 100% P 219/MA5/VI/23
25 21-Jun-23 MA 2 Salis N FOC 2 011 PS 134-135 Ex perbaikan fire proofing B 100% P 204/MA2/V/23
26 22-Jun-23 MA 2 Salis N FOC 2 014 V 103 Untuk perbaikan isolasi P 5 100% P 205/MA2/VI/23
27 19 juni 23 MA 4 Fandi KPC 84 V 205/84 E 207 Untuk perbaikan lampu penerangan P 7 100% P 206/MA4/VI/23
28 22-Jun-23 MA 4 Angga KPC 86 F 201 Untuk perbaikan bocoran steam P 7 100% P 207/MA4/VI/23
29 22-Jun-23 MA 4 Fangky KPC 84 F 202 Ex isolasi B 100% P 209/MA4/VI/23
23 22-Jun-23 MA 2 Salis N FOC 2 014 E 105 Untuk perbaikan fire profing P 7 100% P 202/MA4/VI/23
14 19-Jun-23 MA 3 Reno OM 30 31 M 7A Ex bongkar tanki 31 T 7 B 100% 174/MA3/VI/23
15 20 juni 23 MA 3 Ikhsan OM 40 49 T 2 Untuk akses jembatan P 7 100% P 176/MA2/VI/23
8 20-Jun-23 WS Itok A WS WS All Area Untuk penulisan WS P 7 100% P 248/WS/VI/23
9 20-Jun-23 WS Irvani WS WS Untuk akses stranjing pipa P 7 100% P 249/WS/VI/23
14 21-Jun-23 MA 4 Tri Asmono LOC 3 260 Untuk pekerjaan cui dan LRUT P 14 100% P 187/MA4/VI/23
6 23-Jun-23 MA 7 Ikkorianto GTO 105 K 501 Untuk pekerjaan LRUT / THICNESS P 7 100% P 246/MA7/VI/23
7 20-Jun-23 WS Fandy D WS WS All Area Untuk support crane demag P 7 100% P 247/WS/VI/23
1 25-Jun-23 MA 4 Angga KPC 86 PR 11 Untuk perbaikan bocoran steam P 7 100% P 252/MA4/VI/23
31 23 juni 23 MA 4 Agus L KPC 80 5. 210 A Untuk perbaikan bocoran pipa P 7 100% P 243/MA4/VI/23
32 23-Jan-23 MA 1 Irvan FOC 1 13 K 1,12 K 1 Untuk assesment Cui P 7 100% P 244/MA1/VI/23
33 23-Jun-23 MA 7 Ikkorianto KLBC 120 K 601 B Untuk pekerjaan LRUT / THICNESS p 7 100% P 245/MA7/VI/23
12 8-Jun-23 LOC 1 Roy A LOC 1 CPI Sewa material untuk clening CPI P 30 100% P 264/MA1/VI/23
13 26-Jun-23 MA 6 Irfan RFCC 101 101 P 501 A Untuk bocoran steam trace P 7 100% P 265/MA6/VI/23
14 26-Jun-23 MA 7 Ikkorianto GTO 108 K 502 AM Ex penggantian valve B 100% P 266/MA7/VI/23
15 26-Jun-23 MA 7 Ikkorianto GTO 105 V 503 Untuk pekerjaan LRUT P 7 100% P 267/MA7/VI/23
16 26-Jun-23 MA 6 Irfan RFCC 101 101 COB Ex perbaikan lggo RFCC B 100% P 268/MA6/VI/23
17 26-Jun-23 MA 6 Irfan RFCC 101 101 R 502 Untuk stand pipa P 7 100% P 269/MA6/VI/23
9 26-Jun-23 MA 1 Wisnu SRU 94 E 402 Ex expansion joint B 100% P 261/MA1/VI/23
10 26-Jun-23 MA 1 Wisnu SRU 94 R 401 Untuk Hot bolting P 10 100% P 262/MA1/VI/23
7 26-Jun-23 MA 1 Irvan FOC 1 11 Untuk bocoran CW( depan 12 P 1) P 7 100% 259/MA1/VI/23
5 26-Jun-23 MA 2 Depta FOC 2 014 CCR LT 1 Untuk bongkar isolasi P 7 100% P 257/MA2/VI/23
12 8-Jun-23 LOC 1 Roy A LOC 1 CPI Sewa material untuk clening CPI P 30 100% P 264/MA1/VI/23
13 26-Jun-23 MA 6 Irfan RFCC 101 101 P 501 A Untuk bocoran steam trace P 7 100% P 265/MA6/VI/23
14 26-Jun-23 MA 7 Ikkorianto GTO 108 K 502 AM Ex penggantian valve B 100% P 266/MA7/VI/23
15 26-Jun-23 MA 7 Ikkorianto GTO 105 V 503 Untuk pekerjaan LRUT P 7 100% P 267/MA7/VI/23
16 26-Jun-23 MA 6 Irfan RFCC 101 101 COB Ex perbaikan lggo RFCC B 100% P 268/MA6/VI/23
17 26-Jun-23 MA 6 Irfan RFCC 101 101 R 502 Untuk stand pipa P 7 100% P 269/MA6/VI/23
1 26-Jun-23 MA 2 Raga Ananta FOC 2 018 Ex lampu tiang B 100% P 253/MA2/VI/23
2 26-Jun-23 MA 2 Depta FOC 2 015 C 102 perbaikan bocoran steam P 10 100% P 254/MA2/VI/23
9 26-Jun-23 MA 1 Wisnu SRU 94 E 402 Ex expansion joint B 100% P 261/MA1/VI/23
10 26-Jun-23 MA 1 Wisnu SRU 94 R 401 Untuk Hot bolting P 10 100% P 262/MA1/VI/23
7 26-Jun-23 MA 1 Irvan FOC 1 11 Untuk bocoran CW( depan 12 P 1) P 7 100% 259/MA1/VI/23
5 26-Jun-23 MA 2 Depta FOC 2 014 CCR LT 1 Untuk bongkar isolasi P 7 100% P 257/MA2/VI/23
32 24-Jun-23 MA 4 Angga KPC 86 PL 8003 Ex CUI B 100% P 251/MA4/VI/23
1 26-Jun-23 MA 2 Raga Ananta FOC 2 018 Ex lampu tiang B 100% P 253/MA2/VI/23
2 26-Jun-23 MA 2 Depta FOC 2 015 C 102 perbaikan bocoran steam P 10 100% P 254/MA2/VI/23
28 23-Jan-23 MA 1 Roy A LOC 1 41 T19 Untuk perbaikan bocoran steam P 7 100% P 231/MA1/VI/23
23 22-Jun-23 MA 5 M Syarifudin UTL 500 510 E 601 Ex perbaikan condensor B 100% P 220/MA5/VI/23
24 23-Jun-23 MA 4 Agus L KPC 84 E 214 A/B/C/D Ex plenum fin fan B 100% P 226/MA4/VI/23
21 22-Jun-23 MA 3 Reno OM 30 36 T 101 Untuk lepas motor gawangan P 7 100% P 211/MA4/VI/23
18 21-Jun-23 MA 5 Endro UTL RFCC 151 B 501 A Ex penggantian air intake B 100% P 197/MA5/VI/23
25 21-Jun-23 MA 7 Ega Yusuf K WWT WWT 166 Untuk cleaning 166 PIT SRU P 7 100% P 242/MA7/VI/23
24 23-Jun-23 MA 7 Ikkorianto KLBC 140 E 604 B Ex perbaikan tiknes B 100% P 241/MA7/VI/23
26 24-Jun-23 MA 4 Angga KPC 80 E 202 G Ex plenum B 100% P 250/MA4/VI/23
27 26-Jun-23 MA 2 Depta FOC 2 011 BL Ex jumper line 3" B 100% P 255/MA2/VI/23
32 26-Jun-23 MA 4 David KPC 88 Ex perbaikan sub standar B 100% P 256/MA4/VI/23
33 26-Jun-23 MA 4 Angga KPC 85 E 202 Ex hot bolting B 100% P 258/MA4/VI/23
20 21-Jun-23 MA 5 M Syarifudin UTL 500 530 S 301 Ex beam strainer B 100% P 212/MA5/VI/23
15 21-Jun-23 MA 1 Wisnu P FOC 1 14 F 5 Untuk bocoran pipa WHP P 10 100% P 189/MA1/VI/23
16 21-Jun-23 MA 1 Wisnu P FOC 1 14 E 611/612 Pasang pipa back wash P 14 100% P 191/MA1/VI/23
17 19-Jun-23 MA 6 Lubis RFCC 101 FT 207 Untuk perbaikan P 7 100% P 195/MA6/V/23
18 21-Jun-23 MA 7 Ega Yusuf K KLBC 140 Ex modifikasi line drane B 100% P 199/MA7/VI/23
1 26-Jun-23 MA 6 Ifan RFCC 101 101 P 501 A Untuk bocoran steam trace P 7 100% P 270/MA6/VI/23
3 26-Jun-23 MA 6 Fendi Ardi MA 4 84 K 202 BM Untuk exhaust fin fan P 7 100% P 272/MA4/VI/23
4 26-Jun-23 MA 6 Mahardika RFCC 101 101 HV 026 Bongkar scaffolding B 100% P 273/MA6/VI/23
5 27-Jun-23 MA 6 Mahardika RFCC 101 101 LT 7 Untuk perbaikan bocoran steam lt 7 P 7 100% P 274/MA6/VI/23
3 23-Jun-23 MA 4 Tri Yulianto LOC 3 260 F 101-V155 Untuk penggatia pipa P 7 100% P 276/MA4/VI/23
3 27-Jun-23 MA 4 Yudi 14 E 6 B 14 E 6 B Pasang scaffolding P 7 100% P 277/MA4/VI/23
6 30-May-23 MA 6 Zidnie Ilma RFCC 104 V 504 A/B Untuk pengecetan P 7 100% P 366/MA6/V/23
2 12-Jun-23 MA 7 NF Asror KLBC 140 V 604 Untuk modivikasi line N2 P 7 100% P P 85/MA7/VI/23
3 15-May-23 Gmnt Raga Ananta 30 SS 13 30 SS 13 Untuk perbaikan bocoran dac P 7 100% P 176/GMT/V/23
4 15-May-23 Gmnt Raga Ananta SS GIS 150 SS GIS 150 KV Untuk perbaikan dac P 7 100% P 177/GMT/V/23
7 31-May-23 MA 4 Angga KPC 84 PL 8537 Untuk fasilitas Cui P 10 100% P 368/MA4/V/23
8 6-Jun-23 MA 2 Depta LOC 2 41 T 111 Ex akses dan selter B 100% P 29/MA2/VI/23
9 8-Jun-23 MA 1 Irvan FOC 1 11 Untuk isolasi pengecekan CUI TA P 10 100% P 57/MA1/VI/23
10 8-Jun-23 MA 1 Irvan FOC 1 FOC 1 Untuk LRUT P 30 100% P 56/MA1/VI/23
11 31-May-23 MA 5 Agus W 63 P 102 A 63 P 102 A Untuk perbaikan penerangan lampu dermaga P 7 100% P 91/MA5/VI/23
13 27-Jun-23 MA 5 Luqmanul UTL RFCC 154 A 501 A Ex penggantian brine Heater SWD B 100% 275/MA5/VI/23
9 23-Jan-23 MA 3 Arif OM 40 43 T 4 Untuk perbaikan water springkle P 7 100% P 230/MA3/VI/23
1 30-Jun-23 MA 3 Yulianto OM 30 35 T 3 Ex akses perbaikan springkle tanki B 100% P 278/MA3/VI/23
5 13-Jun-23 MA 1 Roy A SRU 21 C 2 Untuk support cleaning flame arrester P 7 100% P 99/MA1/VI/23
8 23-Jun-23 MA 2 Prasetyo FOC 2 017 E 105 K1 Untuk perbaikan bearing fin fan P 7 100% P 227/MA2/VI/23
9 23-Jun-23 MA 2 Prasetyo FOC 2 011 E 110 K 26 Ex perbaikan bearing fin fan B 100% P P 228/MA2/VI/23
1 30-Jun-23 MA 3 Yulianto OM 30 35 T 3 Ex akses perbaikan water springkle B 100% 278/MA3/VI/23
3 3-Jul-23 GMT Mafrio WS Riger WS Riger Bongkar scaffolding B 100% P 1/GMT/VI/23
8 3-Jul-23 MA 2 Salis N FOC 2 011 V 108 Ex perbaikan pipa B 100% 6/MA2/VI/23
10 3-Jul-23 MA 2 Prasetyo FOC 2 015 E 107 KG Ex perbaikan fin fan B 100% P P 8/MA2/VI/23
14 2-Jul-23 MA 1 Irvan SRU 91 K 402 Untuk prbaikan bocoran P 10 100% P 12/MA1/VI/23
1 30-Jun-23 MA 5 M Syarifudin UTL RFCC 151 B 501 Penggantian air intake FD fan Boiler( Tambah Titik ) P 7 100% 273/MA3/VI/23
13 3-Jul-23 MA 2 Salis N FOC 2 01 PS 113 Ex pekerjaan HOT TAP B 100% P 5/MA2/VII/23
7 26-Jun-23 LOC 1 Roy A LOC 1 24 C 6 Untuk fire profing P 14 100% P 263/MA1/VI/23
8 26-Jun-23 MA 3 Arif OM 30 34 T 1 Untuk pasang bordesk utara P 7 100% 271/MA3/VI/23
9 26-Jun-23 WS Aditya N WS Valve WS valve Ex perbaikan Overhead Crane B 100% P 279/WS/VI/23
15 3-Jul-23 MA 2 M Anwar FOC 2 01 PS 158 erbaikan bocoran pipa P 7 100% P 9/MA2/VII/23
16 3-Jul-23 MA 2 M Anwar FOC 2 01 PS 154 Ex perkerjaan isolasi B 100% P 10/MA2/VII/23
2 4-Jul-23 MA 7 Ikkorianto KLBC 140 D 601 Ex ganti absorben B 100% P 20/MA7/VII/23
2 4-Jul-23 MA 5 Parikin UTL 500 500 Untuk support scaffolding mobail P 7 100% P 14/MA5/VII/23
21 5-Jul-23 MA 6 Zidnie Ilma RFCC 101 101 P 501 A Ex perbaikan steam trace B 100% P 42/MA6/VII/23
22 5-Jul-23 MA 6 Zidnie Ilma RFCC 101 101 HV 026 U tuk pekerjaan clam OLLS P 7 100% P 43/MA6/VII/23
23 5-Jul-23 MA 6 Hendra M RFCC 101 101 Ex kabel tray barat elevator B 100% P 44/MA6/VII/23
11 3-Jul-23 MA 4 Fangky KPC 89 E 201 Untuk pekerjaan CUI P 7 100% 11/MA4/VII/23
13 11-Jul-23 WS Alfian Ghani WS WS Ex perbaikan OHC WS B 100% P 13/WS/VII/23
15 4-Jul-23 MA 4 M Aji KPC 80 PR G Ex line flare/ Line service water B 100% 16/MA4/VII/23
16 4-Jul-23 MA 2 Salis N FOC 2 012 PS 104 Untuk perbaikan isolasi P 7 100% 17/MA2/VII/23
18 4-Jul-23 MA 4 M Aji KPC 85 E 212 Untuk perbaikan bocoran steam P 100% P 19/MA4/VII/23
5 5-Jul-23 MA 4 Fangky KPC 84 PL 80.20 Ex pekerjaan CUI B 100% P 26/MA4/VII/23
6 5-Jul-23 MA 2 Hendro S FOC 2 01 PS 158 Ex bocoran pipa B 100% P 27/MA2/VII/23
7 5-Jul-23 MA 2 Hendro S FOC 2 01 PS 159 Untuk perbaikan bocoran pipa P 7 100% P 28/MA2/VII/23
8 5-Jul-23 MA 4 M Aji KPC 84 K 202 A Untuk perbaikan bocoran steam P 7 100% P 29/MA4/VII/23
16 5-Jul-23 MA 1 Wisnu FOC 1 12 E 1F Untuk pekerjaan operate valve P 10 100% P 37/MA1/VII/23
12 5-Jul-23 MA 5 Parikin Dermaga 63 63 Ex penerangan B 100% P 33/MA 5/VII/23
19 5-Jul-23 MA 7 Ikkorianto GD MA 6/7 Gedung Untuk perbaaikan plafon PVC P P 8 XX 40/MA7/VII/23
12 4-Jul-23 MA 4 M Aji KPC 84 PL 8020 Exassesment CUI B 100% P 15/MA4/VII/23
16 5-Jul-23 MA 4 M Aji KPC 48 Flare perbaikan bocoran steam P 7 100% 23/MA4/VII/23
17 4-Jul-23 MA 4 Kusnan KPC 48 Flare Ex substandar instrument B 100% 24/MA4/VII/23
18 5-Jul-23 MA 4 Fangky KPC 84 PR 15 Ex bocoran steam B 100% 25/MA4/VII/23
19 5-Jul-23 MA 5 Iryan B UTL 50 052 B 102 Untuk perbaikan bocoran steam 3.4 P 7 100% P 30/MA 5/VII/23
20 5-Jul-23 MA 5 Syarufudin UTL 500 510 G 601 Untuk perbaikan bocoran pipa B 100% P 31/MA 5/VII/23
21 5-Jul-23 MA 5 Syarufudin UTL RFCC 151 B 501 C Untuk perbaikan bocoran line soot blower P 7 100% P 32/MA 5/VII/23
22 5-Jul-23 MA 5 M Syarifudin UTL 05 05 PS 164 Ex perbaikan bocoran pipa B 100% P 34/MA 5/VII/23
23 5-Jul-23 MA 5 M Syarifudin UTL 50 51 G 2 Untuk pekerjaan lube OIL COOLER & gland condensor P 7 100% P 35/MA 5/VII/23
24 5-Jul-23 MA 5 M Syarifudin Dermaga 63 54 WS 201 EX perbaikan line Steam B 100% P 36/MA 5/VII/23
25 6-Jul-23 MA 3 Arif 49 49 Untuk pekerjaan loading aspal P 7 100% P 38/MA3/VII/23
26 6-Jul-23 MA 3 Arif 49 49 Ex pekerjaan loading aspal B 100% P 39/MA3/VII/23
14 4-Jul-23 MA 4 Fangky KPC 82 E 203 C/D Untuk pengecatan HE dan piping P 6 100% P 21/MA4/VII/23
3 6-Jun-23 MA 4 Angga KPC 85 PR 14/15 Bongkar scaffolding B 100% P 46/MA4/VII/23
3 6-Jun-23 MA 4 Angga KPC 82 PR 8085 Ex pekerjaan CUI B 100% P 47/MA4/VII/23
3 6-Jun-23 MA 4 Angga KPC 85 E 212 Ex bocoran steam B 100% P 48/MA4/VII/23
10 6-Jul-23 MA 5 Iryan B UTL 50 54 WS 201 Ex pekerjaan blow drain SWD B 100% P 53/MA 5/VII/23
2 7-Jul-23 MA 2 Salis N FOC 2 018 PS 102 Ex operate valve B 100% P 55/MA2/VII/23
18 6-Jul-23 MA 4 M Aji KPC 84 F 201 Untuk bocoran ruf permanent P 7 100% P 50/MA4/VII/23
15 5-Jul-23 MA 4 Fendi Ardi KPC 84 E 207 Bongkar scaffolding B 100% 44/MA4/VII/23
16 6-Jul-23 MA 3 Reno OM 30 30 SS 2 Pasang scaffolding trafo P 7 100% P 45/MA3/VII/23
10 3-Jul-23 MA 2 Salis N FOC 2 011 V 104 Untuk pengecatan vessel P 14 100% P P 7/MA2/VII/23
6 26-Jun-23 MA 1 Roy A LOC 1 23 PS 47 Untuk support fire proofing P 14 100% P 260/MA1/VI/23
7 3-Jul-23 GMT Mafrio GMT SS GIS 150 KV Bongkar scaffolding B 100% P 2/GMT/VII/23
4 21-Jun-23 MA 1 Mafrio SRU Gedung Untuk pengecatan gedung P 7 100% P 188/MA1/VI/23
10 7-Jul-23 MA 2 Salis N LOC 2 021 STR 101 Untuk perbaikan structure P 7 100% P 69/MA2/VII/23
11 7-Jul-23 MA 2 Salis N FOC 2 011 V 111 Untuk pemasangan operate valve P 7 100% P 70/MA2/VII/23
18 7-Jul-23 MA 5 Rahmat UTL RFCC 151 B 501 C Untuk perbaikan bocoran tube boiler P 7 100% P 59/MA5/VII/23
1 8-Jul-23 MA 3 Eko N 70 73 Untuk akses jalan crew kapal P 7 100% P 60/MA3/VII/23
2 7-Jul-23 MA 3 Eko N 70 73 Ex fix drip sampler B 100% P 61/MA3/VII/23
3 5-Jul-23 MA 3 Widodo 70 73 Ex clam 18" line avture B 100% P 62/MA3/VII/23
4 5-Jul-23 MA 3 Widodo 70 73 Ex line pipa solar 2" B 100% P 63/MA3/VII/23
5 7-Jul-23 MA 1 Irvan FOC 1 19 Untuk pengecetan vessel dan colom P 100% P 64/MA6/VII/23
6 5-Jul-23 MA 3 Widodo 70 73 Ex line pipa hidrant B 100% P 65/MA3/VII/23
11 6-Jun-23 MA 1 Aziz B SRU 91 E 409 Untuk perbaikan plug ring P 7 100% P 49/MA1/VII/23
12 6-Jul-23 MA 4 M Aji KPC 84 F 201 ( Barat) Untuk perbaikan bocoran steam P 7 100% P 51/MA4/VII/23
13 6-Jun-23 MA 4 Angga KPC 87 F 201 Untuk bocoran steam P 7 100% P 52/MA4/VII/23
14 7-Jul-23 MA 4 M Aji KPC 89 E 209 Ex kabel tray B 100% P 54/MA4/VII/23
20 7-Jul-23 MA 2 Salis N FOC 2 011 E 114 Untuk pasang operate valve P 7 100% P 68/MA2/VII/23
21 7-Jul-23 MA 2 Salis N FOC 2 012 C 101 Untuk perbaikan isolasi P 7 100% P 71/MA2/VII/23
22 7-Jul-23 MA 2 Salis N FOC 2 011 E 114 Ex pekerjaan CUF B 100% P 72/MA2/VII/23
16 10-Jul-23 MA 6 Anas AF RFCC 101 104 V 504 A/B Ex pengecatan B 100% P 88/MA6/VII/23
16 6-Jul-23 MA 6 Anas AF RFCC 104 104 V 504 A/B Untuk support COA dan perbaikan P 10 100% P 57/MA6/VII/23
13 10-Jul-23 MA 5 Dalu UTL RFCC UTL RFCC Ex perbaikan atap rumah chemical B 100% P 85/MA5/VII/23
8 4-Jul-23 MA 4 M Aji KPC 88 A 201 Ex perbaikan atap rotary valve B 100% P 18/MA4/VII/23
11 7-Jul-23 MA 3 Resky OM 30 38 T 104 Untuk perbaikan level indikator P 7 100% P 56/MA3/VII/23
14 7-Jul-23 MA 2 David LOC 2 023 PS 121-124 Untuk penggantian isolasi pipa P 15 100% P 67/MA2/VII/23
18 10-Jul-23 MA 1 Aziz SRU 93 P402 Untuk bocoran P 7 100% P 75/MA1/VII/23
19 10-Jul-23 MA 1 Wisnu FOC 1 13 Ex ganti pipa 6" line H2 B 100% P 76/MA1/VII/23
20 10-Jul-23 MA 1 Wisnu FOC 1 11 Ex perbaikan pipa CW B 100% P 77/MA1/VII/23
16 10-Jul-23 MA 2 Candra FOC 2 011 F 101 A Untuk pekerjaan tangga dorong instrument P 100% P 73/MA2/VII/23
23 10-Jul-23 MA 2 Hendro S FOC 2 01 PS 159 Ex perbaikan bocoran pipa B 100% P 80/MA2/VII/23
25 10-Jul-23 MA 4 M Aji KPC 84 K 202 A Ex perbaikan bocoran steam B 100% P 82/MA4/VII/23
27 10-Jul-23 MA 5 Dalu 63 RWI 63 Untuk support chain block electrical P 7 100% P 84/MA5/VII/23
28 10-Jul-23 MA 6 Anugrah RFCC 101 101 PS 016 Untuk perbaikan kabel tray P 7 100% P 86/MA6/VII/23
29 10-Jul-23 MA 6 Anas AF RFCC 101 101 LT 7 Perbaikan isolasi LT 7 P 7 100% P 87/MA6/VII/23
30 10-Jul-23 MA 6 Anas AF RFCC 101 101 LT 7 Ex perbaikan steam trace B 100% P 89/MA6/VII/23
31 10-Jul-23 MA 6 Anas AF RFCC 101 101 SN 502 Untuk support semple korosif P 7 100% P 90/MA6/VII/23
4 10-Jul-23 MA 1 Wisnu FOC 1 11 E 52 F Pasang di Fin Fan P 7 100% P 95/MA1/VII/23
5 10-Jul-23 MA 2 Depta FOC 2 011 E 120 A/B Pasang perbaikan Hot Bolting P 7 100% P 96/MA2/VII/23
8 11-Jul-23 MA 1 Aziz Bima SRU 93 A 401 Untuk pekerjaan cleaning dan bocoran steam P 7 100% P 99/MA1/VII/23
9 11-Jul-23 MA 1 Aziz Bima SRU 93 A 401 Untuk pernggantian gasket P 7 100% P 100/MA1/VII/23
8 12-Jul-23 MA 6 Anas AF RFCC 101 BL Untuk perbaikan isolasi P 7 100% P 113/MA6/VII/23
9 12-Jul-23 MA 5 Endro S 63 Dermaga 63 Ex perbaikan cover file B 100% P 114/MA5/VII/23
10 12-Jul-23 MA 5 Iryan B UTL 50 50 Untuk bongkar enclosured/ rumah diesel generator P 14 100% P 115/MA5/VII/23
11 11 juli 23 MA 7 Asror GTO 108 K 502 AM Untuk perbaikan valve P 7 100% P 116/MA7/VII/23
6 12-Jul-23 MA 2 Depta FOC 2 011 E 106 Untuk pekerjaan HOT bolting HE P 5 100% P 111/MA2/VII/23
4 12-Jul-23 MA 2 Depta FOC 2 011 C 102 Untuk pekerjaan HOT bolting P 5 100% P 109/MA2/VII/23
28 11-Jul-23 MA 4 M Aji KPC 84 K 201 Untuk pekerjaan pengecatan H Beam P 7 100% P 105/MA4/VII/23
1 12-Jul-23 MA 1 Irvan SRU 93 E 402 Untuk ganti gasket inlet 16'' P 7 100% P 106/MA1/VII/23
24 11-Jul-23 MA 2 Depta LOC 2 022 E 109 A/B Untuk perbaikan bocoran HE P 7 100% P 101/MA2/VII/23
22 10-Jul-23 MA 2 Depta FOC 2 011 P 113 A/B/C Pasang untuk pekerjaan cleaning strainer P 7 100% P 97/MA2/VII/23
10 7-Jul-23 MA 5 Parikin 63 63 Ex kabel tray B 100% P 58/MA5/VII/23
20 11-Jul-23 MA 1 Hafidh LOC 1 23 LT 002 Pasang scaffolding P 7 100% P 93/MA1/VII/23
9 14-Jul-23 MA 2 Depta FOC 2 011 K 101 C Untuk perbaikan kjacket water P 100% P 125/MA2/VII/23
1 10-Jul-23 MA 3 Fauzi A 70 71 P. 7B Untuk fasilitas lepas motor B 100% P 117/MA3/VII/23
2 11-Jul-23 MA 3 Eko N 70 73 Untuk pekerjaan line Avture 18" P 2 100% P 118/MA3/VII/23
24 12-Jul-23 MA 3 Aufa Mirza OM 30 30 SS1 pasang di trafo P 7 100% P 107/MA3/VII/23
25 12-Jul-23 WS Andi WS WS Instrument Untuk perbaikan Atap P 14 100% P 108/WS/VII/23
26 12-Jul-23 MA 2 Depta FOC 2 011 E 131 Untuk pekerjaan HOT bolting HE P 5 100% P 110/MA2/VII/23
22 11-Jul-23 MA 4 M Aji KPC 84 F 201 Barat Untuk pengecatan P 7 100% P 103/MA4/VII/23
13 10-Jul-23 MA 1 Wisnu FOC 1 14 F V1 Ex bocoran pipa 3/4'' B 100% P 78/MA1/VII/23
16 10-Jul-23 MA 4 M Aji KPC 87 V 202 Ex perbaikan bordesk B 100% P 83/MA4/VII/23
5 3-Jul-23 MA 2 M Anwar FOC 2 018 E 105 k 01 Bongkar scaffolding B 100% P 3/MA2/VII/23
6 3-Jul-23 MA 2 M Anwar FOC 2 013 E 111 K02 Bongkar scaffolding B 100% P 4/MA2/VII/23
7 16-Jun-23 MA 4 Pras W LOC 3 260 V 160 Untuk pengecatan P 14 100% P P 154/MA4/VI/23
10 7-Jul-23 MA 1 Prasetyo FOC 1 17 E 105 K01 Ex bearing fin fan B 100% P 66/MA1/VII/23
18 11-Jul-23 MA 1 Hafidh SRU 93 FV 032 Pasang scaffolding P 7 100% 92/MA1/VII/23
19 10-Jul-23 MA 1 Hafidh SRU 91 LT 377 Pasang scaffolding P 7 100% 94/MA1/VII/23
6 13-Jul-23 MA 4 Angga LOC 3 220 PS 127 Ex bocoran pipa steam B 100% P 122/MA4/VII/23
2 14-Jul-23 MA 3 Ikhsan OM 30 36 T 105 Bongkar scaffolding B 100% P 127/MA3/VII/23
3 14-Jul-23 MA 2 Salis N FOC 2 011 V 111 Ex operate valve B 100% P 128/MA 2/VII/23
9 14-Jul-23 MA 2 Salis N FOC 2 012 PS 104 Ex pekerjaan isolasi B 100% P 134/MA 2/VII/23
10 14-Jul-23 MA 2 Salis N FOC 2 011 PS 131-132 Ex pekerjaan fire proofing B 100% P 135/MA 2/VII/23
11 14-Jul-23 MA 2 Salis N FOC 2 011 PS 125-126 Ex pekerjaan fire proofing B 100% P 136/MA 2/VII/23
12 14-Jul-23 MA 3 Rezky P OM 40 Timbangan NBM Pasang scaff u/ perbaikan timbangan 50 Ton P 14 100% P P 137/MA3/VII/23
14 13-Jul-23 MA 2 Depta FOC 2 012 PS 110-111 Ex pek isolasi B 100% P 139/MA2/VII//23
18 14-Jul-23 MA 6 Ikkorianto KLBC 120 E 601 F U/ support bocoran HE P 7 100% P 143/MA6/VII/23
30 10-Jul-23 MA 6 Anas AF RFCC 101 101 LT 7 Ex perbaikan steam trace B 100% P 89/MA6/VII/23
1 14-Jul-23 MA 3 Widodo 70 72 Untuk pasang fixdrip sampler 72 X 102 P 7 100% P 150/MA3/VII/23
1 14-Jul-23 MA 3 Widodo 70 72 Untuk pasang fixdrip sampler 72 X 101 P 7 100% P 151/MA3/VII/23
1 15-Jul-23 MA 3 Widodo 70 72 Untuk pasang fixdrip sampler 72 X 104 P 7 100% P 152/MA3/VII/23
1 15-Jul-12 MA 3 Widodo 70 72 Untuk pasang fixdrip sampler 72 X 103 P 7 100% P 153/MA3/VII/23
4 12 juli 23 MA 3 Eko N 70 73 Ex bongkar tickness line avture B 100% P 147/MA3/VII/23
5 13 juli 23 MA 3 Ery G 70 73 Untuk perbaikan MOV metering black produck P 10 100% P 148/MA3/VII/23
6 13-Jul-23 MA 3 Eko N 70 73 Untuk line pipa hydrand 6" P 7 100% P 149/MA3/VII/23
7 15-Jul-23 MA 3 Eko N 70 71 P 8 B Untuk akses perbaikan pompa P 5 100% P 154/MA3/VII/23
13 11-Jul-23 MA 4 M Aji KPC 85 E 106 Untuk pekerjaan penggantian bordesk P 7 100% P 102/MA4/VII/23
14 11-Jul-23 MA 4 M Aji KPC 85 E 205 Untuk pekerjaan penggantian bordesk P 7 100% P 104/MA4/VII/23
16 13-Jul-23 GMT Mafrio PHC PCH Untuk perbaikan atap ATG P 7 100% P 119/MA 5/VII/23
9 14-Jul-23 MA 1 Irvan 21 V 2 21 V 2 Untuk penggantian bordesk P 10 100% P 156/MA1/VII/23
10 15-Jul-23 KPC M Aji M KPC 84 F 203 Untuk pasang isolasi P 7 100% P 157/MA4/VII//23
11 15-Jul-23 KPC M Aji M KPC 85 C 206 -85 E 211 Ex penggantian line out let B 100% P 158/MA4/VII//23
12 15-Jul-23 KPC M Aji M KPC 82 F 202 Untuk perbaikan isolasi P 7 100% P 159/MA4/VII//23
13 15-Jul-23 KPC M Aji M KPC 84 F 201 Untuk perbaikan isolasi P 7 100% P 160/MA4/VII//23
25 14-Jul-23 MA 2 Salis N LOC 2 024 PS 130 Ex pekerjaan isolasi B 100% 132/MA 2/VII/23
26 14-Jul-23 MA 2 Salis N FOC 2 021 PS 115 Ex perbaikan support CCTV B 100% 133/MA 2/VII/23
5 5-Jul-23 MA 5 Parikin Dermaga 63 63 Ex lampu penerangan B 100% P 22/MA 5/VII/23
10 10-Jul-23 MA 2 Hendro S LOC 2 023 PS 119 Ex painting dan isolasi B 100% P 81/MA2/VII/23
15 12-Jul-23 MA 2 Depta FOC 2 012 P 103 Untuk pekerjaan fire proofing P 5 100% 112/MA2/VII/23
18 13-Jul-23 MA 5 Agus W UTL 05 051 G 101 Untuk perbaikan lampu di 05 ps 161 dan 05 PS 164 P 5 100% 121/MA 5/VII/23
28 13-Jul-23 MA 2 Depta FOC 2 012 PS 104 Ex pek isolasi B 100% P 140/MA2/VII/23
29 14-Jul-23 MA 4 Pras W LOC 3 200 Ex Cleaning Sewer AOC & COC B 100% 141/MA4/VII/23
30 14-Jul-23 MA 5 Aziz UTL 50 51 G 2 Ex perbaikan bocoran Valve B 100% 142/MA5/VII/23
1 15-Jul-23 MA 4 KPC KPC 84 CCR U/ support perb. Bocoran Steam P 7 100% P 161/MA4/VII/23
2 14-Jul-23 MA 2 Salis N FOC 2 013 PS 112 U/ suppport Line cooling water 1" P 7 100% P 162/MA2/VII/23
3 17-Jul-23 MA 6 Bahron M RFCC 101 101 K 501 MAB Ex Bongkar pengecatan structure B 100% P 163/MA6/VII/23
5 17-Jul-23 MA 6 M Faidi 102 102 E 520 B2 U/ support lepas pasang Fin Fan P 7 100% P 165/MA6/VII/23
9 17-Jul-23 MA 2 M khoirudin FOC 2 014 PS 104 U/ support perb. Block Valve 1" P 7 100% P 169/MA 2/VII/23
22 15-Jul-23 MA 2 Salis N FOC 2 01 PS 113-114 U/ support perb. Bocoran minyak P 7 100% P 170/MA 2/VII/23
23 17-Jul-23 MA 6 Anas AF RFCC 101 101 FT 237 U/ support perbaikan bocoran P 7 100% P 171/MA6/VII/23
14 14-Jul-23 MA 2 Salis N FOC 2 013 PS 121 EX perbaikan line Steam B 100% P 129/MA 2/VII/23
15 14-Jul-23 MA 2 Salis N FOC 2 011 E 114 Ex operate valve B 100% P 130/MA 2/VII/23
3 22-Jun-23 MA 3 Ikhsan OM 30 38 T 101 Untuk penyangga tangga roling P 14 100% 203/MA7/VI/23
1 8-May-23 MA 3 Yulianto OM 30 38 T 101 Ex bongkar scaffolding di 38 T 101 B 100% 104/MA3/V/23
1 16-Jul-23 MA 3 Eko N 70 72 Untuk fix drip sampler LA 72X 204 P 10 100% P 172/MA3/VII/23
2 16-Jul-23 MA 3 Eko N 70 72 Untuk fix drip sampler LA 72X 203 P 10 100% P 173/MA3/VII/23
3 16-Jul-23 MA 3 Eko N 70 73 Ex drip sampler LA 73 X 02 B 100% P 174/MA3/VII/23
4 17-Jul-23 MA 3 Eko N 70 71 P 8 B Ex perbaikan pompa B 100% P 175/MA3/VII/23
5 17-Jul-23 MA 3 Agusalim 70 73 Untuk support scaffolding crane P 7 100% P 176/MA3/VII/23
9 15-Jul-23 MA 4 Angga KPC 84 CCR Untuk perbaikan bocoran steam P 7 100% P 180/MA6/VII/23
12 18-Jul-23 MA 4 Angga KPC 80 S 201 Ex perbaikan strainer B 100% P 183/MA4/VII/23
15 17-Jul-23 MA 2 Depta FOC 2 011 E 106 Ex hot bolting B 100% P 186/MA 2/VII/23
17 17-Jul-23 MA 2 Salis N FOC 2 011 E 106 Ex hot bolting B 100% P 188/MA 2/VII/23
18 17-Jul-23 MA 5 Rahmat UTL 50 56 K 1 Untuk perbaikan bocoran cooling water Air cooler P 7 100% P 189/MA5/VII/23
20 18-Jul-23 MA 6 Mahardika RFCC 101 SN 502 Ex pengecatan line sample korosif B 100% P 191/MA6/VII/23
5 18-Jul-23 MA 1 Wisnu P FOC 1 12 E 1 F Untuk bongkar pasang HE P 14 100% P 196/MA1/VII/23
6 19-Jul-23 MA 1 Wisnu P FOC 1 13 P 4 Untuk pasang bongkar isolasi pipa P 14 100% P 197/MA1/VII/23
10 19-Jul-23 MA 1 Wisnu FOC 1 13 Untuk pekerjaan CUI P 14 100% P 201/MA1/VII/23
18 17-Jul-23 MA 2 Depta FOC 2 011 C 102 Ex hot bolting B 100% P 168/MA 2/VII/23
19 18-Jul-23 MA 6 Mahardika RFCC 101 BL Ex perbaikan Isolasi ( 2 titik ) B 100% P 192/MA6/VII/23
20 18-Jul-23 MA 5 Iryan B UTL RFCC 151 B 501 C Untuk perbaikan bocoran soot blower B 100% P 193/MA5/VII/23
21 18-Jul-23 MA 5 Iryan B UTL RFCC 151 B 501 C Untuk perbaikan bocoran tube boiler B 100% P 194/MA5/VII/23
22 18-Jul-23 MA 5 Iryan B UTL RFCC 151 B 501 C Untuk perbaikan Aux boiller B 100% P 195/MA5/VII/23
23 19-Jul-23 WS Andi A WS WS Instrument Untuk perbaikan atap WS Instrument P 14 100% P 198/MA1/VII/23
24 19-Jul-23 WS Fandi D WS WS Untuk perbaikan crane valve P 7 100% P 199/MA1/VII/23
25 18-Jul-23 WS Andi A WS WS Untuk perbaikan atap WS Instrument B 100% P 200/MA1/VII/23
1 18-Jul-23 MA 3 Yulianto OM 30 35 Untuk pengelasan line vacum distilate P 7 100% P 202/MA6/VII/23
2 18-Jul-23 MA 3 Eko N 70 73 Untuk lepas pasang sorok 10" P 25 100% P 202/MA6/VII/23
15 17-Jul-23 MA 7 A Zidnie GTO 104 104 PipeRack U/ support perb. Steam Trace P 7 100% P 164/MA7/VII/23
11 13-Jul-23 MA 1 Irvan FOC 1 FOC 1 Ex pengecekan LRUT B 100% P 124/MA1/VII/23
12 14-Jul-23 MA 3 S.Arif OM 40 43 T 4 Bongkar scaffolding B Continue P 126/MA3/VII/23
13 14-Jul-23 MA 2 Salis N FOC 2 011 P 112 A/B Ex cleaning strainer B 100% 131/MA 2/VII/23
8 10-Jul-23 GMT Mafrio OM 30 30 SS13 Bongkar scaffolding B 100% P 98/GMT/VII/23
9 13-Jul-23 MA 5 Endro S Dermaga 63 63 Untuk perbaikan pile di dermaga 63 P 30 100% P 120/MA 5/VII/23
13 21-Jul-23 MA 5 Rachmat UTL 50 56 K 1 Ex perbaikan bocoran pipa cooling water B 100% P 218/MA5/VII/23
14 20-Jul-23 MA 5 Iryan B UTL 50 51 G 2 Untuk perbaikan cooling water oil cooler B 100% P 219/MA5/VII/23
15 20-Jul-23 MA 2 Salis N FOC 2 013 PS 112 Ex perbaikan cooling water B 100% P 220/MA 2/VII/23
16 20-Jul-23 MA 2 Salis N FOC 2 019 P 118 A Untuk bongkar sproket P 100% P 221/MA 2/VII/23
17 20-Jul-23 MA 2 Salis N FOC 2 011 P 122 Untuk bongkar sproket P 100% P 222/MA 2/VII/23
3 20-Jul-23 MA 5 M Syarifudin UTL 500 500 PS 09 Untuk perbaikan valve LP P 7 100% P 208/MA5/VII/23
4 20-Jul-23 MA 5 M Aziz RWI 63 Ex chain block Electrical B 100% P 209/MA5/VII/23
5 20-Jul-23 MA 5 Iryan B Dermaga Dermaga Untuk chain block gantungan P 7 100% P 210/MA5/VII/23
6 20-Jul-23 MA 5 Wisnu Dermaga 64 Dermaga 64 Ex perbaikan valve 12" B 100% P 211/MA5/VII/23
7 20-Jul-23 MA 1 Wisnu FOC 1 11 C 8 Untuk pekerjaan handrill P 7 100% P 212/MA1/VII/23
8 20-Jul-23 MA 1 Yudi FOC 1 11 E 52 F C Bongkar scaffolding B 100% P 213/MA1/VII/23
9 20-Jul-23 MA 1 Yudi FOC 1 11 E 54 A,B Pasang scaffonding P 7 100% P 214/MA1/VII/23
17 18-Jul-23 MA 3 Reno OM 30 30 EE 1211 A/B U/ pekerjaan trafo P 100% P 179/MA3/VII/23
1 20-Jul-23 MA 6 Ifanudin 104 104 V 504 A/B Ex perbaikan COA B 100% P 206/MA6/VII/23
15 18-Jul-23 MA 3 Reno OM 30 30 EE 201 A/B Ex pekerjaan trafo B 100% P 177/MA3/VII/23
10 17-Jul-23 MA 6 M Faidi 102 102 E 520 A2 Ex perbaikan fin fan B 100% P 166/MA6/VII/23
11 17-Jul-23 MA 2 Depta FOC 2 011 C 101 Ex bongkar bocoran steam B 100% P 167/MA 2/VII/23
3 3-Jul-23 MA 6 Mahardika RFCC 104 PS 007 Untuk pekerjaan perbaikan MPC P 14 100% P 225/MA6/VII/23
4 11 juli 23 MA 7 NF Asror GTO 108 K 502 AM Untuk perbaikan valve P 7 100% P 226/MA7/VII/23
5 12-Jul-23 MA 7 NF Asror GTO 105 F 501 Untuk perbaikan internal tube P 7 100% P 227/MA7/VII/23
15 21-Jul-23 GMT Mafrio PHC ATG Ex tower ATG PHC B 100% P 237/GMT/VII/23
16 20-Jul-23 MA 3 Fajri IK 70 73 Dermaga 1 Ex ekses jalan crew kapal B 100% P 238/MA3/VII/23
17 20-Jul-23 MA 3 Agusalim 70 Dermaga 1 Ex perbaikan crane B 100% P 239/MA3/VII/23
18 20-Jul-23 MA 3 Fajri IK 70 pangkal dermaga untuk fasilitas pengecatan d pangkal dermaga P 30 100% P 240/MA3/VII/23
19 20-Jul-23 MA 3 Fajri IK 70 Dermaga 3 Untuk penggantian valve 14" P 3 100% P 241/MA3/VII/23
10 21-Jul-23 MA 4 Fangky KPC 85 C 207 Untuk pekerjaan CUI P 7 232/MA4/VII/23
11 21-Jul-23 MA 4 Fangky KPC 86 V 201 Untuk pekerjaan CUI P 5 233/MA4/VII/23
12 21-Jul-23 MA 4 Fangky KPC 85 E 202 Untuk perbaikan Cui dan pengecatan P 5 234/MA4/VII/23
13 21-Jul-23 MA 4 Fangky KPC 85 C 201 Untuk perbaikan Cui idolsi dan pengecatan P 4 235/MA4/VII/23
14 21-Jul-23 MA 4 Fangky KPC 85 C 201 Untuk pekerjaan CUI P 7 236/MA4/VII/23
9 20 juli 23 MA 4 Septian Nanda KPC 84 lorong Ex support instrument B 100% 203/MA4/VII/23
10 20 juli 23 MA 4 Septian Nanda KPC 85-88 Ex support instruent B 100% 204/MA4/VII/23
11 20-Jul-23 MA 4 Fangky KPC 82 E 203 C/D Ex pengecatan HE B 100% 205/MA4/VII/23
1 17-May-23 MA 1 Aziz B SRU 47 S 505 Untuk support kabel tray P 7 ON HOLD 212/MA1/V/23
16 20-Jul-23 MA 1 Wisnu FOC 1 PS 10.22 Untuk pekerjaan tickness 3" Line LPG P 7 100% P 217/MA1/VII/23
13 20-Jul-23 MA 7 Heru WWT 106 Untuk flow meter holding basin RFCC P 7 100% P 207/MA7/VII/23
7 21-Jul-23 MA 4 Tri Yulianto KPC 85 F 201 Barat Ex perbaikan bocoran steam B 100% P 229/MA4/VII/23
8 21-Jul-23 MA 4 Tri Yulianto KPC 86 F 201 Barat Ex perbaikan bocoran steam B 100% P 230/MA4/VII/23
5 20-Jul-23 MA 4 M Aji KPC 82 U/ pek. New pipe Line Pertamax Turbo P 7 100% P 242/MA4/VII/23
6 24-Jul-23 MA 1 Tri Wurtanto SRU 91 K 402 B U/ support Scaffolding P 7 100% P 243/MA1/VII/23
1 21-Jul-23 MA 5 Iryan B UTL 50 054 WS 101 Untuk penggantian modul SWD P 7 100% P 223/MA5/VII/23
5 24-Jul-23 MA 3 Durrotul OM NBM Timbangan NBM Ex Perbaikan Timbangan B 100% P 244/MA3/VII/23
6 24-Jul-23 MA 1 Wisnu FOC 1 12.13 Ex Pekerjaan CUI B 100% 245/MA1/VII/23
6 10-Jul-23 MA 2 Hendro S FOC 2 011 PS 117-119 Untuk isolasi dan painting P 15 100% P 79/MA2/VII/23
28 1-Mar-23 MA 5 Iryan B Dermaga 63 63 RWI Untuk pekerjaan line drain pipa RWI P 14 100% P 301/MA2/III/23
1 21-Jul-23 MA 5 Iryan B UTL 50 154 A 501 A Untuk retubing modul SWD P 7 P 224/MA5/VII/23
2 20-Jul-23 MA 2 Depta FOC 2 011 E 125 M 5 Untuk pasang greting fin fan P 7 P 228/MA2/VII/23
3 21-Jul-23 MA 4 Tri Yulianto KPC 85 E 211 Ex opetare valve B P 231/MA4/VII/23
4 13-Jun-23 MA 7 NF Asror GTO 106 Ex painting strcture B Continue P 92/MA7/VI/23
5 5-Jul-23 MA 6 Hendra M RFCC 101 101 FG 001 Ex perbaikan LAR HVAC B 41/MA6/VII/23
6 7-Jul-23 MA 2 Salis N LOC 2 021 STR 101 Untuk perbaikan structure P 7 55% P P 69/MA2/VII/23
7 10-Jul-23 MA 3 Rezky P IPAL HVI 160-650 Ex pekerjaan motor d metering B 74/MA3/VII/23
8 10-Jul-23 MA 6 Anas AF RFCC 101 101 PS 21 G Untuk pengecatan line silincer HP Setam P 10 60% P 91/MA6/VII/23
9 13-Jul-23 MA 4 Angga LOC 3 260 Ex ELRUT All Area B Continue P 123/MA4/VII/23
10 13-Jul-23 MA 1 Roy A LOC 1 22 E 9 U/ support pemasangan scaff pengecatan P 14 Continue P 138/MA1/VII/23
11 18-Jul-23 MA 3 Reno OM 30 30 EE 111 B U/ pekerjaan trafo P 178/MA3/VII/23
12 20-Jul-23 MA 4 Septian Nanda LOC 3 260 Untuk perbaikan level trasmiter P 7 215/MA4/VII/23
13 20-Jul-23 MA 1 Roy A OM 40 41 T 16 Untuk akses jalan P 30 216/MA1/VII/23
SPT BARU
1 24-Jul-23 MA 1 Roy A LOC 1 22 PS 1 U/ support perbaikan bocoran pipa P 14 100% P 246/MA1/VII/23
2 24-Jul-23 MA 6 Yusro 101 101 ps 016 Ex perb. Kabel tray B 100% P 247/MA6/VII/23
3 24-Jul-23 MA 7 NF Asror 108 108 U/ support perbaikan atap & pengecatan P 7 P 248/MA7/VII/23
4 24-Jul-23 MA 6 Bahron M 104 104 PS 007 Ex perbaikan steam trace B 100% P 249/MA6/VII/23
5 24-Jul-23 MA 5 Aziz UTL 05 54 DA 201 U/ support Re Inject Flange MPS P 14 100% P 250/MA5/VII/23
6 24-Jul-23 MA 5 Aziz UTL 05 05 PS 158 U/ support perbaikan bocoran P 14 100% P 251/MA5/VII/23
7 24-Jul-23 MA 5 Aziz UTL 05 51 G2 Ex bongkar ganti lube oil air cooler B P 252/MA5/VII/23
8 21-Jul-23 MA 5 Dalu UTL 50 UTL 50 U/ support perb. Bocoran Elbow(STG) P 14 P 253/MA5/VII/23
9 25-Jul-23 MA 4 Angga KPC 88 U/ perb. Bocoran steam P 7 P 254/MA4/VII/23
10 25-Jul-23 MA 3 Rezky P OM NBM Timbangan NBM U/ support kabel power dan data timbangan P 14 P 255/MA3/VII/23
11 25-Jul-23 MA 5 Arif UTL RFCC 153 A 501 D U/ support Alignment P 7 P 256/MA5/VII/23
12 24-Jul-23 WS RIO WS WS valve Ex bongkar OH Crane , ws valve B 100% P 257/WS/VII/23
13 24-Jul-23 WS Aditya N WS WS Ex bongkar perb. Hoist Crane B 100% P 258/WS/VII/23
14 24-Jul-23 MA 2 Salis N FOC 2 019 P 118 A Ex perbaikan sprocket B P 259/MA2/VII/23
15 24-Jul-23 MA 2 Salis N FOC 2 011 P 122 Ex perbaikan sprocket B P 260/MA2/VII/23
16 25-Jul-23 MA 2 Candra FOC 2 011 E 108 A/B U/ support pasang Termo couple P 3 P 261/MA2/VII/23
17 26-Jul-23 MA 4 Angga KPC 84 C 203 lt 3-5 U/ support pek bordesk P 10 P 262/MA4/VII/23
18 24-Jul-23 MA 2 Salis N LOC 2 021 Batre Limit Ex Operate valve B P 263/MA2/VII/23
19 25-Jul-23 MA 1 Wisnu FOC 1 13 C 1/2 Ex perb. Fire proofing P 14 P 264/MA1/VII/23
20 24-Jul-23 MA 1 Aziz B FOC 1 FOC 1 Ex bongkar CUI TA B P 265/MA1/VII/23
21 25-Jul-23 MA 5 Endro S UTL 50 51 E 2 Ex perb. Air cooler lube oil B P 266/MA5/VII/23
22 25-Jul-23 MA 5 Endro S UTL 50 54 E 201 U/ support perb. Cover fin fan P 30 P 267/MA5/VII/23
23 25-Jul-23 MA 5 Endro S UTL 50 56 U/ support bocoran pipa P 7 P 268/MA5/VII/23
24 24-Jul-23 MA 4 Pras w LOC 3 260 Ex bongkar CUI B P 269/MA4/VII/23
25 25-Jul-23 MA 5 Dhanang 63 63 A 1 U/ support perb. Over head crane P 7 P 270/MA5/VII/23
26 25-Jul-23 MA 5 Dhanang 63 063 P 201 U/ support perb. Flange lube oil P 7 P 271/MA5/VII/23
27 24-Jul-23 MA 6 Lubis RFCC 102 FT 028 U/ support perbaikan transmitter P 7 P 272/MA6/VII/23
28 25-Jul-23 MA 6 Ifan RFCC 101 E 525 A B U/ support perb. HE P 7 P 273/MA6/VII/23
29 24-Jul-23 MA 5 Aziz UTL 05 52 P 202 A/B/C/D Ex bongkar pasang valve ARC B P 274/MA5/VII/23
DAILY ACTIVITY
1 24-Jul-23 MA 5 Aziz UTL 05 05 PS 158 U/ support perbaikan bocoran P 14 100% P 251/MA5/VII/23
2 5-Jul-23 MA 5 Iryan B UTL 50 052 B 102 Untuk perbaikan bocoran steam 3.4 P 7 100% P 30/MA 5/VII/23
3 10-Jul-23 GMT Mafrio OM 30 30 SS13 Bongkar scaffolding B Continue P 98/GMT/VII/23
4 18-Jul-23 MA 3 Reno OM 30 30 EE 111 B U/ pekerjaan trafo P 7 100% P 178/MA3/VII/23
5 24-Jul-23 MA 1 Roy A LOC 1 22 PS 1 U/ support perbaikan bocoran pipa P 14 100% P 246/MA1/VII/23
6 10-Jul-23 MA 2 Hendro S FOC 2 011 PS 117-119 Untuk isolasi dan painting P 15 100% P 79/MA2/VII/23
7 10-Jul-23 MA 2 Hendro S LOC 2 023 PS 119 Ex painting dan isolasi B 100% P 81/MA2/VII/23
8 20-Jul-23 MA 2 Salis N FOC 2 013 PS 112 Ex perbaikan cooling water B 100% P 220/MA 2/VII/23
9 25-Jul-23 MA 4 Angga KPC 88 U/ perb. Bocoran steam P 7 100% P 254/MA4/VII/23
10 20-Jul-23 MA 4 M Aji KPC 82 U/ pek. New pipe Line Pertamax Turbo P 7 100% P 242/MA4/VII/23
11 20-Jul-23 MA 4 Septian Nanda LOC 3 260 Untuk perbaikan level trasmiter P 7 100% 215/MA4/VII/23
12 21-Jul-23 MA 5 Iryan B UTL 50 054 WS 101 Untuk penggantian modul SWD P 7 Continue P 223/MA5/VII/23
13 24-Jul-23 MA 6 Bahron M 104 104 PS 007 Ex perbaikan steam trace B 100% P 249/MA6/VII/23
14 25-Jul-23 MA 6 Ifan RFCC 101 E 525 A B U/ support perb. He P 7 100% P 273/MA6/VII/23
SPT menyusul MA 1 - FOC 1 11 PS 93 Ex pekerjaan Isolasi B 100% P -
SPT menyusul MA 3 - OM 40 Drumplant Ex Perb. Timbangan B 100% P -
SPT menyusul MA 4 - LOC 3 260 PS 626 Ex pekerjaan CUI B 100% P -
SPT menyusul WS - Gen maint Gen maint Ex penerangan lampu Workshop B 100% P -
SPT menyusul MA 7 - 105 105 E 502 Ex pekerjaan LRUT & Thickness B 100% P -
SPT menyusul MA 6 - 101 101 PS 24 U/ support cleaning strainer P 100% P -
= Planing