PT BPP

MONITORING KONDISI UNIT BREAK DOWN REGION BENGALON


MINGGU KE III MARET 2023

TAHUN
NO CODE UNIT JENIS UNIT UMUR UNIT
PEROLEHAN

PT BBP

1 DT 04 MITSHUBHIS CANTER 125 PS 2014 9

2 DT 11 MITSHUBHIS CANTER 125 PS 2015 8

3 Exa 01 PC 200-8M0 2013 10

STATUS BREAK DOWN B1


B1x Proses Created PR kebun
B1a Proses Release Strategy
B1b PR Full Release Belum Created PO
B1c PR Full Release sudah ada PO
B0 Proese perbaikan
2022
ENGALON
4/1/2023

HM / KM BD TANGGAL BD BD ( HARI )

139160 3/1/2023 31

207921 3/1/2023 31

16423 3/14/2023 18

PRIORITAS
P1 = 1 - 6 HARI
P2 = 7 - 12 HARI
P3 = 13 - 18 HARI
DESCRIPTION

suri propeler shaft aus


pompa solar tidak fungsi dan rem parkir rusak
rem parkir

ban aus

unit cannot run (tidak ada pembakaran dan presure C.rail


tidak tercapai)
STATUS
PERBAIKAN DAN KEBUTUHAN PARTS NORMA LIFE TIME
BD

Order part B1c


B1b
B1a

Order Part B1b

10000km

tunggu mekanik electrik TLSE B0


PRO
PRIORITAS
NO PR TGL PR ASKEP TEK LT

P3 1652001239, '10/1/2023
1652001289, , 02/24/2023
1652001317 3/19/2023

1652001297 3/8/2023

P2

PR to Askep #DIV/0!
PROSES PURCHASING REQUEST
RPH LT MGR TEK LT BUDGET LT DIR.OPS

proses

AT to RPH #DIV/0! AT to MT #DIV/0! MT to BD #DIV/0!


PURCHASING ORDER
STATUS PR TGL FR
LT DIR KEU LT NO PO

full release 1/20/2023 1672001458


full release 3/15/2023 belum PO

3/23/2023

full release
PO

dari FR to PO ( Hari )
PURCHASING ORDER PARTS TERSUPPLY
ESTIMASI PLAN
TANGGAL PO LT dari FR TERSUPPLY TANGGAL LT dari PO RFU

3/2/2023

M Ke II april
3/6/2023

R to PO ( Hari ) #DIV/0! PO > Supply #DIV/0!


ACTUAL RFU KETERANGAN

Part tersedia di gudang BBP

injektor cyl 1 open circuit, dan diakukan perbaikan selesai (03/15/2023) CA 322
error NE sensor, selesai, 03/15/2023
error prerseure oil (03/15/2023)
unit can't run, (starter bisa mutar, tp mesin tidak hidup karena tidak ada pembakaran)
selesai, unit beroperasi normal setelah ganti injektor bekas dar GKAE
22

akaran)
PR PART UNIT YG BEROPERASI

NO CODE UNIT JENIS UNIT TAHUN UMUR UNIT


PEROLEHAN

PT BBP

BP21VBRA01 COMPACTOR 2014 9


1

2 BP21EXA01 EXAVATOR PC 200-8M0 2014 9

3 BP21FORD FORD RANGER 2013 10

4 BP21EXA02 EXAVATOR PC200-8 2013 10

5 BP21EXA05 EXAVATOR PC300-8 M0 2019 9

6 DT 01 Mistubhisi Canter 2013 10

7 DT 03 Mistubhisi Canter 2013 10


7 DT 03 Mistubhisi Canter 2013 10

8 DT 05 Mistubhisi Canter 2014 9

9 DT 06 Mistubhisi Canter 2014 9

10 DT 07 Mistubhisi Canter 2015 8

11 DT 08 Mistubhisi Canter 2015 8

12 DT 09 Mistubhisi Canter 2015 8

12 DT 10 Mistubhisi Canter 2015 8

13 Greder 01 Cat 120K 2015 8

14 Whelloader WA 180-3 2013 10

STATUS BREAK DOWN B1


B1x Proses Created PR kebun
B1a Proses Release Strategy
B1b PR Full Release Belum Created PO
B1c PR Full Release sudah ada PO
4/6/2023
HM / KM TANGGAL BD ( HARI ) DESCRIPTION
BD BD

HOSE VIBRATING SISTEM IN


HOSE VIBRATING SISTEM OUT

OPERASI

TRACKLINK ASSEMBLY
HOSE TURBO AIR CLEANER
OPERASI
SPROCKET
SHAFT IDLER
MOTOR STARTING
WIRING HARNESS INJECTOR

LOWER ARM
UPPER ARM
SHCOKABSORBER ASSY
OPERASI
DRIVE SHAFT
BALLJOINT
STABLIZER LINK

CUP RADIATOR
OPERASI CUP HIDROLIK TANK

KUKU BUCKET
OPERASI ADAPTOR
PEN KUKU BUCKET

Knucke arm RH dan LH


Operasi Crossjoint Propeler
Ban luar

Knucke arm RH dan LH


Operasi
Operasi Crossjoint
Ban luar

Knucke arm RH dan LH


Operasi Crossjoint
Ban luar

Knucke arm RH dan LH


Operasi Munting engine
Master kopling bawah

Knucke arm RH dan LH


Operasi Crosjoint
Rem angin

Knucke arm RH dan LH


Operasi Crossjoint

Knucke arm RH dan LH


Operasi Master kopling bawah
Ban luar

Knucke arm RH dan LH


Operasi Crossjoint

GP MTRG 222-3769 (Orbitol)


Operasi

Blade bucket
Operasi Ban loader
Oring kit

PRIORITAS
P1 = 1 - 6 HARI
P2 = 7 - 12 HARI
P3 = 13 - 18 HARI
P/N PERBAIKAN DAN KEBUTUHAN PARTS

1418-49005-0
1418-49005-0

PPBP
Order Part
Order Part
Order Part
PSA
Order Part

CREATE MATERIAL

CREATE MATERIAL

Order part
Order part
Order part

Order part
Order part

Order part
Order part

Order part
Order part
Order Part

Order part
Order part
Order part

Order part

Order part

Order part
Order part

Order part

Order part
Order part

PPBP dan create material

Orderpart
Orderpart
Creater Material
NORMA LIFE TIME STATUS PRIORITAS
BD NO PR TGL PR

1652001256 24.01.2023
1652001256 24.01.2023

1652001205 25.10.2022
1652001270 03.02.2023
1652001268 03.02.2023
1652001267 30.01.2023
1652001253 23.01.2023
1652001252 21.01.2023

1652001257 25.01.2023

1652001203 22.10.2022
1652001203 22.10.2022
1652001283 2/17/2023

1652001323 4/3/2023
1652001298 3/9/2023

1652001323 4/3/2023
1652001323 4/3/2023
1652001298 3/9/2023
1652001327 3/6/2023

1652001323 4/3/2023
1652001328 4/6/2023
1652001328 3/6/2023

1652001323 4/3/2023
165200298 3/9/2023
1652001328 4/3/2023

1652001323 4/3/2023
1652001298 3/9/2023

1652001323 4/3/2023
1652001328 4/6/2023

1652001323 4/3/2023
1652001298 3/9/2023

10000Hm

1652001254 1/23/2023
1652001299 3/9/2023
PROSES PURCHASING REQUEST
ASKEP TEK LT RPH LT MGR TEK LT

25.01.2023 Proses
25.01.2023 Proses

27.12.2022 29.12.2022
03.02.2023

Proses BA
25.01.2023 25.01.2023
25.01.2023 25.01.2023

28.01.2023 31.01.2023

27.10.2022 29.10.2022
27.10.2022

4/3/2023 Proses relase

4/3/2023
4/3/2023

belum release

4/3/2023

4/3/2023

4/3/2023

4/3/2023

4/3/2023
4/3/2023

4/3/2023

PR to Askep #DIV/0! AT to RPH #DIV/0! AT to MT #DIV/0!


EQUEST
BUDGET LT DIR.OPS LT DIR KEU LT

30.12.2022 23.12.2022 15.01.2023

07.11.2022 10.11.2022
MT to BD #DIV/0!
PURCHASING ORDER
STATUS PR TGL FR
NO PO TANGGAL PO

1672001525

1672002490

1672001438 30.01.2023
full relase 1672001438 30.01.2023
1672001517 28.11.2022
fullrelease 3/28/2023 Belum PO

Full relaseer 2/3/2023 1672001531


Full relaseer 3/20/2023 1672001518

dari FR to PO ( Hari )
RDER PARTS TERSUPPLY PLAN
ESTIMASI TERSUPPLY
LT dari FR TANGGAL LT dari PO RFU

3/6/2023 M ke II

Est bulan may

3/1/2023

3/7/2023

3/23/2023
3/23/2023

3/6/2023
3/6/2023

3/6/2023

#DIV/0! PO > Supply #DIV/0!


ACTUAL RFU KETERANGAN

Belum PO, Proses penawaran vendor sesuai arahan P.budi menggunakan merek UNO KOERA,

Part tersuply
Proses BA
Part tersuply sebagai cadangan stock

CREATE MATERIAL

CREATE MATERIAL

Part tersuply di gudang BBP


Part tersuply di gudang BBP

Part tersuply di gudang BBP


Part ban tersuply di gudang BBP

di gudang BPP

Create material tgl 03/27/2023

estimasi 2 mingu terhitung dari tgl 03/25/2023


merek UNO KOERA,