Medan datar
FAKTOR JAM/
ITEM KONDISI UNIT KAP BUCKET PROD/HM
ISI BUCKET
STANDART PRODUKSI 0.83 0.65 0.90 0.55 53
KEMAMPUAN EXCA 01 BBP 0.67 0.65 0.90 0.55 43
TARGET PRODUKSI BP21EXCA01 409
NOTE :
1. Terpakai untuk P2H Isi solar & Pemanasan unit
2. Terpakai untuk pembersihan area quary
3. Terpakai untuk pembuatan stockpile material
4. Servise rutin ganti oli dll
5. Perbaikan ringan seperti Kencangin baut traclink dll
PERHITUNGAN EXCAVATOR PC 200
FAKTOR PENGISIAN
MUDAH = 0.8 - 1
KETERANGAN SEDANG = 0.6 - 0.8
M3/Bucket
M3/Bucket
TARGET PANJANG JALAN 254 MTR TARGET PANJANG JALAN 318 MTR TARGET PANJANG JALAN 586 MTR
JARAK RATA-RATA 4 KM JARAK RAT-RATA 1.7 KM JARAK TEMPUH RAT-RATA 3 KM
PENGERJAAN 4 HARI PENGERJAAN 3 HARI PENGERJAAN 7 HARI
JUMLAH RITASE TIMBUN TANAH DIV 2 TLSE JUMLAH RITASE TIMBUN TANAH DIV 1 TLSE GRANDTOTAL RITASE & RATA-RATA PRODUKSI / UNIT/HARI
PRODUKSI HARIAN PRODUKSI HARIAN AVARAGE/HK/UNIT
NAMA UNIT RIT m3/rit TOTAL M3 NAMA UNIT RIT m3/rit TOTAL M3 NAMA UNIT RIT m3/rit TOTAL M3 KETERANGAN
RIT/HK M3/HK RIT/HK M3/HK RIT/HK M3/HK
BP21TRUK01 8 4 32 2 8 BP21TRUK01 27 4 108 7 27 BP21TRUK01 35 4 140 18 70 Unit produksi sifatnya hanya bantu
BP21TRUK03 10 4 40 3 10 BP21TRUK05 27 4 108 7 27 BP21TRUK03 10 4 40 10 40 Unit produksi sifatnya bantu
BP21TRUK04 4 4 16 1 4 BP21TRUK06 56 4 224 14 56 BP21TRUK04 4 4 16 4 16 Unit umum sifatnya bantu
BP21TRUK05 46 4 184 12 46 BP21TRUK07 49 4 196 12 49 BP21TRUK05 73 4 292 12 49 Full terpakai penimbunan
BP21TRUK06 24 4 96 6 24 BP21TRUK08 81 4 324 20 81 BP21TRUK06 80 4 320 16 64 Full terpakai penimbunan
BP21TRUK07 26 4 104 7 26 BP21TRUK10 80 4 320 20 80 BP21TRUK07 75 4 300 15 60 Full terpakai penimbunan
BP21TRUK08 15 4 60 4 15 BP21TRUK11 59 4 236 15 59 BP21TRUK08 96 4 384 16 64 Full terpakai penimbunan
BP21TRUK09 8 4 32 2 8 TOTAL 379 4 1516 14 54 BP21TRUK09 8 4 32 8 32 Unit hanya 1 hari kerja karna berangkat ke MJIM
BP21TRUK10 30 4 120 8 30 BP21TRUK10 110 4 440 16 63 Full terpakai penimbunan
BP21TRUK11 36 4 144 9 36 BP21TRUK11 95 4 380 14 54 Full terpakai penimbunan
TOTAL 207 4 828 5 21 TOTAL 586 4 2344 13 51 Actual produksi unit full kerja per hari diluar unit bantu 15 Rit/Unit/Hari
JUMLAH PEMAKAIAN HM ALAT BERAT EXCAVATOR DI TLSE DIV 2 JUMLAH PEMAKAIAN HM ALAT BERAT EXCAVATOR DI TLSE DIV 1 JUMLAH PEMAKAIAN HM ALAT BERAT EXCAVATOR DI TLSE DIV 1
KETERANGAN
NAMA UNIT HM AWAL HM AKHIR HM HM/HK MTR/HM M3/HM NAMA UNIT HM AWAL HM AKHIR HM HM/HK MTR/HM M3/HM NAMA UNIT HM AWAL HM AKHIR HM HM/HK MTR/HM M3/HM
BP21EXCA01 12685 12,712 27 7 9 30.67 BP21EXCA01 12720 12752 32 10.67 10 47.38 BP21EXCA01 12685 12752 67 9.57 9 35 Actual rata-rata 35 m3/Hm tanah yang terangkut
JUMLAH PEMAKAIAN HM ALAT BERAT GRADER DI TLSE JUMLAH PEMAKAIAN HM ALAT BERAT GRADER DI TLSE JUMLAH PEMAKAIAN HM ALAT BERAT GRADER DI TLSE
NAMA UNIT HM AWAL HM AKHIR HM HM/HK MTR/HM M3/HM NAMA UNIT HM AWAL HM AKHIR HM HM/HK MTR/HM M3/HM NAMA UNIT HM AWAL HM AKHIR HM HM/HK MTR/HM M3/HM
BP21GRAD01 4839 4,864 24 6.05 10 34.21 BP21GRAD01 4870.4 4894.8 24 8.13 13 62.13 BP21GRAD01 4839 4894.8 56 7.93 11 42 Actual rata-rata 42 m3/Hm tanah yang terangkut
JUMLAH PEMAKAIAN HM ALAT BERAT VBRA DI TLSE JUMLAH PEMAKAIAN HM ALAT BERAT VBRA DI TLSE JUMLAH PEMAKAIAN HM ALAT BERAT VBRA DI TLSE
NAMA UNIT HM AWAL HM AKHIR HM HM/HK MTR/HM M3/HM NAMA UNIT HM AWAL HM AKHIR HM HM/HK MTR/HM M3/HM NAMA UNIT HM AWAL HM AKHIR HM HM/HK MTR/HM M3/HM
BP21VBRA01 3401 3,417 16 4.00 16 51.75 BP21VBRA01 3422 3443 21 7 15 72.19 BP21VBRA01 3401 3443 42 6 14 56 Actual rata-rata 56 m3/Hm tanah yang terangkut
PENIMBUNAN JALAN DIV 1 RY1 & DIV 2 RY2
TANGGAL BULAN DIV ESTATE RANGE NAMA UNIT JUMLAH RIT
31.05.2021 MEI 2 TLSE R2 ALBINUS BP21TRUK04 4
31.05.2021 MEI 2 TLSE R2 KURNIAWAN BP21TRUK05 8
31.05.2021 MEI 2 TLSE R2 HERYONO BP21TRUK08 6
31.05.2021 MEI 2 TLSE R2 FAUZAN BP21TRUK09 8
31.05.2021 MEI 2 TLSE R2 SAHRUL BP21TRUK10 5
31.05.2021 MEI 2 TLSE R2 FAJAR BP21TRUK11 9
02.06.2021 JUNI 2 TLSE R2 ENDANG BP21TRUK01 8
02.06.2021 JUNI 2 TLSE R2 LONGINUS BP21TRUK03 10
02.06.2021 JUNI 2 TLSE R2 KURNIAWAN BP21TRUK05 13
02.06.2021 JUNI 2 TLSE R2 ALBINUS BP21TRUK06 3
02.06.2021 JUNI 2 TLSE R2 ASRUL BP21TRUK07 2
02.06.2021 JUNI 2 TLSE R2 HERYONO BP21TRUK08 3
02.06.2021 JUNI 2 TLSE R2 SAHRUL BP21TRUK10 4
02.06.2021 JUNI 2 TLSE R2 FAJAR BP21TRUK11 7
03.06.2021 JUNI 2 TLSE R2 KURNIAWAN BP21TRUK05 16
03.06.2021 JUNI 2 TLSE R2 ALBINUS BP21TRUK06 13
03.06.2021 JUNI 2 TLSE R2 ASRUL BP21TRUK07 15
03.06.2021 JUNI 2 TLSE R2 HERYONO BP21TRUK08 6
03.06.2021 JUNI 2 TLSE R2 SAHRUL BP21TRUK10 13
03.06.2021 JUNI 2 TLSE R2 FAJAR BP21TRUK11 11
04.06.2021 JUNI 2 TLSE R2 KURNIAWAN BP21TRUK05 9
04.06.2021 JUNI 2 TLSE R2 ALBINUS BP21TRUK06 8
04.06.2021 JUNI 2 TLSE R2 ASRUL BP21TRUK07 9
04.06.2021 JUNI 2 TLSE R2 SAHRUL BP21TRUK10 8
04.06.2021 JUNI 2 TLSE R2 FAJAR BP21TRUK11 9
06.06.2021 JUNI 1 TLSE R1 ALBINUS BP21TRUK06 37
06.06.2021 JUNI 1 TLSE R1 ASRUL BP21TRUK07 38
06.06.2021 JUNI 1 TLSE R1 HERYONO BP21TRUK08 38
06.06.2021 JUNI 1 TLSE R1 SAHRUL BP21TRUK10 39
06.06.2021 JUNI 1 TLSE R1 FAJAR BP21TRUK11 34
07.06.2021 JUNI 1 TLSE R1 KURNIAWAN BP21TRUK05 4
07.06.2021 JUNI 1 TLSE R1 ALBINUS BP21TRUK06 19
07.06.2021 JUNI 1 TLSE R1 ASRUL BP21TRUK07 11
07.06.2021 JUNI 1 TLSE R1 HERYONO BP21TRUK08 25
07.06.2021 JUNI 1 TLSE R1 SAHRUL BP21TRUK10 24
07.06.2021 JUNI 1 TLSE R1 FAJAR BP21TRUK11 5
08.06.2021 JUNI 1 TLSE R1 ENDANG BP21TRUK01 27
08.06.2021 JUNI 1 TLSE R1 KURNIAWAN BP21TRUK05 23
08.06.2021 JUNI 1 TLSE R1 HERYONO BP21TRUK08 18
08.06.2021 JUNI 1 TLSE R1 SAHRUL BP21TRUK10 17
08.06.2021 JUNI 1 TLSE R1 FAJAR BP21TRUK11 20
TOTAL RITASE 586
JENIS UNIT H.KERJA TOTAL RIT RIT/HK TOTAL M3
DT 01 2 35 18 140
DT 03 1 10 10 40
DT 04 1 4 4 16
DT 05 6 73 12 292
DT 06 5 80 16 320
DT 07 5 75 15 300
DT 08 6 96 16 384
DT 09 1 8 8 32
DT 10 7 110 16 440
DT 11 7 95 14 380
TOTAL 586 2,344
MONITORING PEMAKAIAN HM EXCA01 DI TLSE
Tanggal Bulan Jenis pekerjaan Estate HM awal
31.05.2021 Mei KUMPULKAN DAN LOADING TANAH TIMBUNAN TLSE 12685
02.06.2021 Juni KUMPULKAN DAN LOADING TANAH TIMBUNAN TLSE 12694
03.06.2021 Juni KUMPULKAN DAN LOADING TANAH TIMBUNAN TLSE 12704
04.06.2021 Juni KUMPULKAN DAN LOADING TANAH TIMBUNAN TLSE 12704
06.06.2021 Juni KUMPULKAN DAN LOADING TANAH TIMBUNAN TLSE 12720
07.06.2021 Juni KUMPULKAN DAN LOADING TANAH TIMBUNAN TLSE 12732
08.06.2021 Juni KUMPULKAN DAN LOADING TANAH TIMBUNAN TLSE 12744
AVARAGE
HM akhir HM Hi Total HM sd HI
4846 6 6
4852 7 13
4859 6 19
4864 5 24
4881 10 10
4888 8 18
4895 7 24
6.94 HM/HARI
HM akhir HM Hi Total HM sd HI
3405 4 4
3409 4 8
3413 4 12
3417 4 16
3430 8 8
3436 6 14
3443 7 21
5.29 HM/HARI