Material Balance Sump Pit II

SIMULASI PERHITUNGAN Material Balance Sump Pit II DENGAN HUJAN RANCANGAN Q5TH

Jenis Pompa Jumlah Flow Rate Vol. Pump Rate Cathment Area 0.09 km2
CAT 3412DI KUD SS 1 765000 Lt/Hrs 2601 m3/day Intensitas CH renc.Q5th 26.86 mm/jam
Pump WP 200 PT SLN 1 620000 Lt/Hrs 2108 m3/day CH rencana Q5th 107 mm
0 Lt/Hrs 0 m3/day Q.Air Tanah 5% . Qair (prediction)
0 Lt/Hrs 0 m3/day L.Pit 0.043 km2
0 Lt/Hrs 0 m3/day L.Limpasan 0.045 km2
0 Lt/Hrs 0 m3/day Volume Air Up Date 20,000 M3

Avr. Pump Rate 2355 m3/day Volume Air Hujan 2,119.68 M3


Efisiensi 85% Volume Air Tanah 105.98 M3
Jumlah Pump 2 Unit Total Vol Penambah 2,225.66 M3
Jam Kerja Pompa/hari 4 Jam

ESTIMASI KOLAM KERING 22-Aug-23 ELEVASI Lama Pengeringan 1 hari


Vol.Air Vol. Air Hujan Vol. Air Tanah Vol.Total Vol.Pump Rate Vol.Remind
TANGGAL Elevasi
m3 m3 m3 m3 m3 m3
8/22/2023 20,000 6,359 318 26,677 57,638 KERING -1790.04
8/23/2023 KERING
8/24/2023
8/25/2023
8/26/2023 Schedule Pompa :
8/27/2023
8/28/2023 1. standar unit pompa beroperasi minimal 4 jam/hari
8/29/2023 2. pengoperasian pompa berdasarkan acuan banyaknya air
8/30/2023 pada sump. Bila melebihi standar kapasitas sump, curah hujan
8/31/2023 tinggi, maka jam kerja pompa akan di naikkan setelah
9/1/2023
dilakukan perhitungan. (Instruksi dari Pengawas Pompa).