GAMBARAN UMUM PROYEK CUT AND FILL

xxxxxxxxxxxxxxxxxxxxxxx

OWNER : PT. xxxxxxxxxxxxxx

MAIN KONTRAKTOR : PT. xxxxxxxxxxxxxx


PT. xxxxxxxxxxxxxx

PEMBAYARAN : : PER 500.000 M3. (SKBDN / BANK GARANSI)

VOLUME KONTRAK : 1,000,000 M3 ATAU 50,000 DUMP

HARGA KONTRAK : Rp. 17,000.00 / M3. PADAT

WAKTU PELAKSANAAN : 6 Bulan / 180 hari

RENCANA ANGGARAN PELAKSANAAN ( PER M3. )

BIAYA RITASI DT & QUARRY :


1. SEWA DUMP TRUCK = Rp. 2,500
2. BIAYA BBM DT = Rp. 348
3. BIAYA SUPIR DT = Rp. 550
4. SEWA EXCAVATOR = Rp. 1,267
5. BIAYA BBM ALAT = Rp. 387
6. BIAYA OPERATOR ALAT = Rp. 147
BIAYA PEMADATAN :
1. SEWA VIBRO & BULDOZER = Rp. 1,699
2. BIAYA BBM ALAT = Rp. 1,476
3. BIAYA OPERATOR ALAT = Rp. 564
BIAYA UMUM & ADMIN. :
1. PEMOTONGAN OLEH MAIN KONTRAKTOR 7,000
( UNTUK BIAYA PAJAK & ADMINISTRASI ) = Rp.
2. BIAYA PERSIAPAN/PENDAHULUAN = Rp. 1,325
JUMLAH = Rp. 17,261
PROFIT = Rp. (261)
JUMLAH = Rp. 17,000

CATATAN : DEFISIT Rp (261.46) /M3. Minus

ASUMSI - ASUMSI :

WAKTU PELAKSANAAN :
VOLUME KONTRAK : 1,000,000 M3.
1. EXCAVATOR (BEKO)
KEMAMPUAN ALAT (EXCAVATOR) 60 M3./JAM
GALI/MUAT PER HARI = 10 JAM 600 M3.
JML PEMAKAIAN ALAT 10 UNIT
GALI/MUAT PER HARI = 10 JAM 6,000 M3.

JML WAKTU PELAKSANAAN 167 HARI


6 BULAN
2. DUMP TRUCK :
Kapasitas Dump truk 20 m3/DT
Frequensi Dump Truk 300 trip/hari
Jumlah armada 9 DT
Frequensi tiap 1 DT 33 trip

WAKTU SIKLUS ALAT/DT :


1. EXCAVATOR (BEKO)
Kapasitas Bucket 1.2 M3.
Kapasitas Produksi Per Jam 60 M3.
Jumlah Jam Kerja 10 Jam
Jumlah Produksi/Alat 600 M3.
Jumlah Pemakaian Alat 10 Unit
Jumlah Produksi Per Hari 6,000 M3.
GAMBARAN UMUM PROYEK CUT AND FILL
xxxxxxxxxxxxxxxxxxxxxxx

OWNER : PT. xxxxxxxxxxxxxx

MAIN KONTRAKTOR : PT. xxxxxxxxxxxxxx


PT. xxxxxxxxxxxxxx

PEMBAYARAN : : PER 500.000 M3. (SKBDN / BANK GARANSI)


2. DUMP TRUCK :
Jarak Tempuh 0.50 km
Waktu muat dan manouver 6 menit
Kecepatan (dgn muatan) 20 km/jam
Waktu tempuh (dgn muatan) 6 menit
Waktu bongkar dan manouver 2 menit
Kecepatan (tanpa muatan) 30 km/jam
Waktu tempuh (tanpa muatan) 4 menit
Jml Waktu Bongkar/Muat/Perjalanan 18 menit/trip
Jumlah trip tiap jam 3.33 trip/jam
0.30 jam/trip
Jam kerja per hari 10 jam/hari
Total trip per hari (real time) 33 trip/hari

Total daya angkut per hari/DT 667 m3 /hr/DT


Target Volume Angkut per hari 6,000 m3
Jumlah Dump Truk yg diperlukan 9 Unit DT

PREDIKSI PELAKSANAAN PEKERJAAN PENGURUGAN :

1 PEKERJAAN PERSIAPAN :
- DIREKSI KEET / SITE OFFICE
- MOBILISASI DAN DEMOBILISASI PERLATAN & PERSONIL
- PENGUKURAN LEVELING TANAH DASAR
- PEMBUATAN JALAN AKSES DARI QUARRY KE JALAN UMUM

2 PEKERJAAN PEMATANGAN LAHAN SEPANJANG DAERAH TIMBUNAN TANAH :


- PEMBONGKARAN TERHADAP PENGHALANG YANG MUNGKIN ADA
- MEMINDAHKAN DAN MENANGANI AIR YANG ADA AGAR TIDAK TERHENTI
- MEMBUANG DAN MENANGANI LOKASI TIMBUNAN TANAH YANG BERLUMPUR
- MENGHENTIKAN / MENYUMBAT SUMBER AIR TANAH YANG TIMBUL APABILA ADA

3 PEKERJAAN PEMADATAN TANAH DASAR SEPANJANG LOKASI KERJA

4 PEKERJAAN PENIMBUNAN TANAH DAN PEMADATAN


- SETIAP PENGHAMPARAN 30 CM. ATAU SESUAI KETENTUAN YANG ADA DALAM
SPESIFIKASI YANG DIKELUARKAN PIHAK OWNER DAN ATAU STANDAR PT. JASA MARGA

5 PEKERJAAN COMMISIONING TEST PEMADATAN DENGAN MENGGUNAKAN PERALATAN


SAND CONE DAN ATAU SHEEP FOOT ROLLER SAMPAI DENGAN MEMENUHI TINGKAT
KEPADATAN DAN DAYA DUKUNG YANG DITETAPKAN SESUAI PERATURAN UNTUK
JALAN TOLL.

PERALATAN YANG DIGUNAKAN :

1 EXCAVATOR 5 MOTOR GRADER


2 DUMP TRUCK 6 SHEEP FOOT ROLLER
3 BULDOZER 7 TRUCK TANGKI AIR
4 COMPACTOR / VIBRO ROLLER 8 PERALATAN PENDUKUNG LAINNYA
RENCANA ANGGARAN PENDAPATAN DAN BIAYA OPERASIONAL
xxxxxxxxxxxxxxxxxxxxxxx

I. PENDAPATAN :
NILAI KONTRAK 1,000,000 X 17,000.00 =

II. BIAYA OPERASIONAL (PENGELUARAN PROYEK) :

A. BIAYA RITASE DUMP TRUCK DAN QUARRY :


1 DUMP TRUCK :
SEWA : 135 UNIT x Rp. 30.000.000,- x 11 BULAN 15 Unit x Rp 30,000,000 x
BBM : 20 LTR/TRIP x 250.000 TRIP x Rp. 6.000,- 20 Ltr/Rit x Rp 1,500 Rit x
SUPIR : Rp. 250.000,-/HARI x 334 HARI x 135 UNIT Rp 220,000 /hari x 167 Hari x

2 EXCAVATOR :
SEWA : 10 UNIT x 3.340 JAM x Rp. 140.000,- / JAM 4 Unit x 1,667 Jam x
BBM : 20 LTR x 3.340 JAM x 10 UNIT x Rp. 6.000,- 20 Liter x 1,667 Jam x
OPERATOR : Rp. 250.000,-/HARI x 334 HARI x 10 UNIT Rp 220,000 /hari x 167 Hari x

JUMLAH BIAYA RITASE DUMP TRUCK DAN QUARRY :

B. BIAYA PEMADATAN :
1 SEWA ALAT :
- BULDOZER D6 : 6 UNIT x 3.340 JAM x Rp. 135.000,-/JAM 3 Unit x 1,667 Jam x
- COMPACTOR/VIBRO R. : 3 UNIT x 2.338 JAM x Rp. 130.000,-/JAM 3 Unit x 933 Jam x
- MOTOR GRADER : 3 UNIT x 2.338 JAM x Rp. 130.000,-/JAM 3 Unit x 950 Jam x
- SHEEP FOOT ROLLER : 1 UNIT x 500 JAM x Rp. 135.000,-/JAM 1 Unit x 500 Jam x
- TRUK TANGKI AIR : 2 UNIT x Rp. 20.000.000,- x 11 BULAN 2 Unit x 20,000,000 x

2 BBM ALAT :
- BULDOZER D6 : 20 LTR x 3.340 JAM x 6 UNIT x Rp. 6.000,- 5 Liter x 1,667 Jam x
- COMPACTOR/VIBRO R. : 15 LTR x 2.338 JAM x 3 UNIT x Rp. 6.000,- 15 Liter x 933 Jam x
- MOTOR GRADER : 15 LTR x 2.338 JAM x 3 UNIT x Rp. 6.000,- 15 Liter x 950 Jam x
- SHEEP FOOT ROLLER : 15 LTR x 500 JAM x 1 UNIT x Rp. 6.000,- 15 Liter x 500 Jam x
- TRUK TANGKI AIR : 80 LTR x 334 HARI x 2 UNIT x Rp. 6.000,- 30 Liter x 167 Hari x

3 OPERATOR ALAT :
- BULDOZER D6 Rp 220,000 167 Hari x
- COMPACTOR/VIBRO R. Rp 220,000 224 Hari x
- MOTOR GRADER Rp 220,000 224 Hari x
- SHEEP FOOT ROLLER Rp 220,000 50 Hari x
- TRUK TANGKI AIR Rp 220,000 334 Hari x

JUMLAH BIAYA PEMADATAN :

C. BIAYA PEMOTONGAN DARI MAIN KONTRAKTOR :


UNTUK BIAYA PPH PAJAK KONSTRUKSI DAN BIAYA ADMINISTRASI 1,000,000 m3 Rp 7,000

D. BIAYA PERSIAPAN / PENDAHULUAN PROYEK :


1 BIAYA BIKIN DIREKSI KIT / SITE OFFICE
2 BIAYA MOBILISASI DAN DEMOBILISASI PERALATAN & PERSONIL
3 BIAYA PENGUKURAN LEVELING TANAH DASAR
4 BIAYA BIKIN JALAN AKSES DARI QUARRY KE JALAN UMUM
5 BIAYA PEMATANGAN LAHAN SEPANJANG LOKASI KERJA
6 BIAYA OVERHEAD PROYEK, BIAYA COMMISIONING TEST PEMADATAN DAN BIAYA TAK TERDUGA LAINNYA

JUMLAH BIAYA PERSIAPAN / PENDAHULUAN PROYEK :

Harga BBM Industri 11,600

REKAPITULASI :

PENDAPATAN :
BIAYA OPERASIONAL (PENGELUARAN PROYEK) :
A. JUMLAH BIAYA RITASE DUMP TRUCK DAN QUARRY
B. JUMLAH BIAYA PEMADATAN
C. JUMLAH PEMOTONGAN OLEH MAIN KONTRAKTOR
D. JUMLAH BIAYA PERSIAPAN / PENDAHULUAN PROYEK

KEUNTUNGAN KOTOR PROYEK :

NOTE : BELUM TERMASUK FEE SUKSES UNTUK PIHAK MEDIASI.-


SIONAL

17,000,000,000

6 Bln = Rp 2,500,000,000
Rp 11,600 /Liter = Rp 348,000,000
15 Unit = Rp 550,000,000
Rp 3,398,000,000

190,000 /Jam = Rp 1,266,666,667


Rp 11,600 = Rp 386,666,667
4 Unit = Rp 146,666,667
Rp 1,800,000,000
Rp 5,198,000,000

135,000 /Jam = Rp 675,000,000


130,000 /Jam = Rp 364,000,000
130,000 /Jam = Rp 370,500,000
135,000 /Jam = Rp 67,500,000
6 Bln = Rp 222,222,222
Rp 1,699,222,222

3 Unit x 11,600 = Rp 290,000,000


3 Unit x 11,600 = Rp 487,200,000
3 Unit x 11,600 = Rp 495,900,000
1 Unit x 11,600 = Rp 87,000,000
2 Unit x 11,600 = Rp 116,000,000
Rp 1,476,100,000

3 Unit = Rp 110,000,000
3 Unit = Rp 147,840,000
3 Unit = Rp 147,840,000
1 Unit = Rp 11,000,000
2 Unit = Rp 146,960,000
Unit Rp 563,640,000
Rp 3,738,962,222

= Rp 7,000,000,000

= Rp. Rp 75,000,000
= Rp. Rp 130,000,000
= Rp. Rp 10,000,000
= Rp. Rp 500,000,000
= Rp. Rp 275,000,000
= Rp. Rp 334,500,000

= Rp. Rp 1,324,500,000

Rp 17,000,000,000
Rp 5,198,000,000
Rp 3,738,962,222
Rp 7,000,000,000
Rp 1,324,500,000
Rp 17,261,462,222