ASUMSI - ASUMSI :
WAKTU PELAKSANAAN :
VOLUME KONTRAK : 1,000,000 M3.
1. EXCAVATOR (BEKO)
KEMAMPUAN ALAT (EXCAVATOR) 60 M3./JAM
GALI/MUAT PER HARI = 10 JAM 600 M3.
JML PEMAKAIAN ALAT 10 UNIT
GALI/MUAT PER HARI = 10 JAM 6,000 M3.
1 PEKERJAAN PERSIAPAN :
- DIREKSI KEET / SITE OFFICE
- MOBILISASI DAN DEMOBILISASI PERLATAN & PERSONIL
- PENGUKURAN LEVELING TANAH DASAR
- PEMBUATAN JALAN AKSES DARI QUARRY KE JALAN UMUM
I. PENDAPATAN :
NILAI KONTRAK 1,000,000 X 17,000.00 =
2 EXCAVATOR :
SEWA : 10 UNIT x 3.340 JAM x Rp. 140.000,- / JAM 4 Unit x 1,667 Jam x
BBM : 20 LTR x 3.340 JAM x 10 UNIT x Rp. 6.000,- 20 Liter x 1,667 Jam x
OPERATOR : Rp. 250.000,-/HARI x 334 HARI x 10 UNIT Rp 220,000 /hari x 167 Hari x
B. BIAYA PEMADATAN :
1 SEWA ALAT :
- BULDOZER D6 : 6 UNIT x 3.340 JAM x Rp. 135.000,-/JAM 3 Unit x 1,667 Jam x
- COMPACTOR/VIBRO R. : 3 UNIT x 2.338 JAM x Rp. 130.000,-/JAM 3 Unit x 933 Jam x
- MOTOR GRADER : 3 UNIT x 2.338 JAM x Rp. 130.000,-/JAM 3 Unit x 950 Jam x
- SHEEP FOOT ROLLER : 1 UNIT x 500 JAM x Rp. 135.000,-/JAM 1 Unit x 500 Jam x
- TRUK TANGKI AIR : 2 UNIT x Rp. 20.000.000,- x 11 BULAN 2 Unit x 20,000,000 x
2 BBM ALAT :
- BULDOZER D6 : 20 LTR x 3.340 JAM x 6 UNIT x Rp. 6.000,- 5 Liter x 1,667 Jam x
- COMPACTOR/VIBRO R. : 15 LTR x 2.338 JAM x 3 UNIT x Rp. 6.000,- 15 Liter x 933 Jam x
- MOTOR GRADER : 15 LTR x 2.338 JAM x 3 UNIT x Rp. 6.000,- 15 Liter x 950 Jam x
- SHEEP FOOT ROLLER : 15 LTR x 500 JAM x 1 UNIT x Rp. 6.000,- 15 Liter x 500 Jam x
- TRUK TANGKI AIR : 80 LTR x 334 HARI x 2 UNIT x Rp. 6.000,- 30 Liter x 167 Hari x
3 OPERATOR ALAT :
- BULDOZER D6 Rp 220,000 167 Hari x
- COMPACTOR/VIBRO R. Rp 220,000 224 Hari x
- MOTOR GRADER Rp 220,000 224 Hari x
- SHEEP FOOT ROLLER Rp 220,000 50 Hari x
- TRUK TANGKI AIR Rp 220,000 334 Hari x
REKAPITULASI :
PENDAPATAN :
BIAYA OPERASIONAL (PENGELUARAN PROYEK) :
A. JUMLAH BIAYA RITASE DUMP TRUCK DAN QUARRY
B. JUMLAH BIAYA PEMADATAN
C. JUMLAH PEMOTONGAN OLEH MAIN KONTRAKTOR
D. JUMLAH BIAYA PERSIAPAN / PENDAHULUAN PROYEK
17,000,000,000
6 Bln = Rp 2,500,000,000
Rp 11,600 /Liter = Rp 348,000,000
15 Unit = Rp 550,000,000
Rp 3,398,000,000
3 Unit = Rp 110,000,000
3 Unit = Rp 147,840,000
3 Unit = Rp 147,840,000
1 Unit = Rp 11,000,000
2 Unit = Rp 146,960,000
Unit Rp 563,640,000
Rp 3,738,962,222
= Rp 7,000,000,000
= Rp. Rp 75,000,000
= Rp. Rp 130,000,000
= Rp. Rp 10,000,000
= Rp. Rp 500,000,000
= Rp. Rp 275,000,000
= Rp. Rp 334,500,000
= Rp. Rp 1,324,500,000
Rp 17,000,000,000
Rp 5,198,000,000
Rp 3,738,962,222
Rp 7,000,000,000
Rp 1,324,500,000
Rp 17,261,462,222