ANALISA HARGA SATUAN

Jenis Pekerjaan : Lapisan ATB


Satuan Pembayaran : Ton
No.URAIAN KEGIATAN SAT. KOEFFISIEN HARGA SATUAN
( Rp. )
1 2 3 4 5

1 Mandor Jam 0.0613 8,571.43


2 Pekerja Jam 0.4293 4,571.43
3 Agregat Kasar m3 0.7028 175,200.00
4 Agregat Halus m3 0.5341 173,880.00
5 Filter Kg 139.2000 1,350.00
6 Aspal Curah Kg 157.0000 7,300.00
7 Sewa Asphatt Mixing Plant Jam 0.0613 3,800,000.00
8 Sewa Wheel Leader 10-15 HP Jam 0.0421 482,502.02
9 Sewa Dump Truck 8-10 m3 Jam 0.5429 65,000.00
10 Sewa Asphatt Finisher Jam 0.0767 856,725.00
11 Sewa Todem Roller Jam 0.0476 223,436.00
12 Sewa Tire Roller Jam 0.0356 226,360.00
13 Sewa Alat Bantu set 1.0000 1,000.00

HARGA SATUAN PEKERJAAN / M3


HARGA SATUAN PEKERJAAN / TON
DIBULATKAN

Jenis Pekerjaan : Lapisan AC


Satuan Pembayaran : m2
No.URAIAN KEGIATAN SAT. KOEFFISIEN HARGA SATUAN
( Rp. )
1 2 3 4 5

1 Mandor Jam 0.0024 8,571.43


2 Pekerja Jam 0.0241 4,571.43
3 Agregat Kasar m3 0.0336 175,200.00
4 Agregat Halus m3 0.0149 173,880.00
5 Filter Kg 4.8015 1,350.00
6 Aspal Curah Kg 6.6150 7,300.00
7 Sewa Asphatt Mixing Plant Jam 0.0024 3,800,000.00
8 Sewa Wheel Leader 10-15 HP Jam 0.0016 482,502.02
9 Sewa Dump Truck 8-10 m3 Jam 0.0385 65,000.00
10 Sewa Asphatt Finisher Jam 0.0030 856,725.00
11 Sewa Todem Roller Jam 0.0018 223,436.00
12 Sewa Tire Roller Jam 0.0025 226,360.00
13 Sewa Alat Bantu set 1.0000 1,000.00

HARGA SATUAN PEKERJAAN


DIBULATKAN
Jenis Pekerjaan : Pengecatan Marka Jalan dengan Thermoplastic ( teb. 2mm)
Satuan Pembayaran : M2
No.URAIAN KEGIATAN SAT. KOEFFISIEN HARGA SATUAN
( Rp. )
1 2 3 4 5

1 Mandor Jam 0.0140 8,571.43


2 Operator Jam 0.0140 5,000.00
3 Pengemudi / sopir Jam 0.0140 5,000.00
4 Pekerja / buruh tak terampil Jam 0.0275 4,571.43
5 Thermoplastic kg 2.8000 27,000.00
6 Glass beed kg 0.5000 40,000.00
7 Cargo truck 5,0 ton jam 0.0500 109,814.52
8 Road marking machine jam 0.0500 41,600.00

HARGA SATUAN PEKERJAAN


DIBULATKAN

Jenis Pekerjaan : Lapisan Aspal Pengikat ( Tack Coat)


Satuan Pembayaran : Lt
No.URAIAN KEGIATAN SAT. KOEFFISIEN HARGA SATUAN
( Rp. )
1 2 3 4 5

1 Mandor Jam 0.0030 8,571.43


2 Pekerja Terampil Jam 0.0201 4,571.43
3 Aspal Curah Kg 0.8894 7,300.00
4 Minyak Tanah Ltr 0.2530 7,000.00
5 Sewa Aspal Spatyer Jam 0.0030 23,000.00
6 Sewa Compresor Jam 0.0063 75,000.00
7 Sewa Dump Truck 8-10 m3 Jam 0.0030 65,000.00

HARGA SATUAN PEKERJAAN


DIBULATKAN
JUMLAH
( Rp. )
6=4×5

525.43
1,962.51
123,130.56
92,869.31
187,920.00
1,146,100.00
232,940.00
20,313.34
35,288.50
65,710.81
10,635.55
8,058.42
1,000.00

1,926,454.42
844,936.15
844,930.00

JUMLAH
( Rp. )
6=4×5

20.66
110.17
5,886.72
2,590.81
6,482.03
48,289.50
9,158.00
772.00
2,502.50
2,570.18
402.18
565.90
1,000.00

80,350.65
80,350.00
JUMLAH
( Rp. )
6=4×5

120.00
70.00
70.00
125.71
75,600.00
20,000.00
5,490.73
2,080.00

103,556.44
103,555.00

JUMLAH
( Rp. )
6=4×5

25.71
91.89
6,492.62
1,771.00
69.00
472.50
195.00

9,117.72
9,115.00
DAFTAR HARGA SATUAN ALAT & BAHAN

Nama Kegiatan : #REF!


Nama Pekerjaan : #REF!
Lokasi : #REF!

NO. URAIAN SATUAN HARGA SATUAN

1 Batu pecah mesin 0,5/1 cm m3 Rp 173,880.00


3
2 Batu pecah mesin 1/2 cm m Rp 175,200.00
3
3 Batu pecah mesin 2/3 cm m Rp 171,240.00
4 Batu pecah mesin (3/5 cm) dan (4/6 cm) m3 Rp 164,400.00
3
5 Batu kali pecah 15/20 cm m Rp 131,894.00
3
6 Batu Pecah 2/3 Cm m Rp 171,240.00
7 Aspal panas AC 60/70 ( termasuk angkutan ) kg Rp 2,832.00
8 Aspal Curah kg Rp 7,300.00
3
9 Agregat Kasar m Rp 175,200.00
3
10 Agregat Halus m Rp 173,880.00
11 Filler kg Rp 1,350.00
12 Kawat Ikat Beton kg Rp 15,350.00
13 Besi Beton Polos kg Rp 12,500.00
14 Kayu Menganti ( Bekesting ) m3 Rp 1,636,000.00
15 Paku kg Rp 11,040.00
3
16 Batu Krikil Beton m Rp 114,000.00
3
17 Pasir Pasang m Rp 110,000.00
18 Minyak Tanah lt Rp 7,000.00
19 Sewa alat bantu ( 1 set @ 3 alat ) Set Rp 1,000.00
20 Sewa aspal finisher ( min. 3 jam ) jam Rp 856,725.00
21 Sewa aspal sprayer ( min. 4 jam ) jam Rp 23,000.00
22 Sewa pneumatic tire roller ( min. 5 jam ) jam Rp 226,360.00
23 Sewa tandem roller ( min. 5 jam ) jam Rp 223,436.00
24 Sewa compresor ( min. 5 jam ) jam Rp 75,000.00
25 Sewa dump truck 5 T ( min. 5 jam ) jam Rp 65,000.00
26 Sewa dump truck 8-10 jam Rp 65,000.00
27 Sewa motor grader 125-140 pk ( min. 5 jam ) jam Rp 270,000.00
28 Sewa truck tanki air ( min. 5 jam ) jam Rp 70,000.00
29 Sewa walles ( min. 5 jam ) jam Rp 80,000.00
30 Sewa Aspal Mixing Plant jam Rp 3,800,000.00
31 Sewa Vibarator Roller ( min. 5 Jam) jam Rp 135,000.00
32 Sewa Generator Set jam Rp 235,950.00
33 Sewa Wheel Loader 10-15 HP jam Rp 482,502.02
34 Sewa Concrete Mixer 0,5 m3 jam Rp 50,000.00
35 Biaya gilas perkerasan dengan tebal 15-20 cm m² Rp 9,200.00
36 Thermoplastic Kg Rp 27,000.00
37 Glass beed Kg Rp 40,000.00
38 Road marking machine Jam Rp 41,600.00
2
39 Gedeg Guling m Rp 29,500.00
40 Cargo truck 5,0 ton Jam Rp 109,814.52
41 Got Talang R.15 ( segmen ) Bh Rp 19,250.00
42 Got talang R.25 ( segmen ) Bh Rp 24,050.00
43 Paving Abu-abu Tb. 6 cm ( 4 persegi Pj. ) Bh Rp 950.00
44 Paving Abu-abu Tb. 8 cm ( 4 persegi Pj. ) Bh Rp 1,200.00
45 Stoper / Topi Uskup Merah tb. 6 cm Bh Rp 4,000.00
46 Stoper / Topi Uskup Merah tb. 8 cm Bh Rp 5,000.00
47 Batu Bata Bh Rp 300.00
48 Bambu Bongkotan dia. 8-12 cm ; Pj. 2,5 m Btg Rp 15,500.00
DAFTAR HARGA SATUAN ALAT & BAHAN

Nama Kegiatan : #REF!


Nama Pekerjaan : #REF!
Lokasi : #REF!

NO. URAIAN SATUAN HARGA SATUAN

49 Bambu Ori dia. 10-12 cm ; Pj. 3 m Btg Rp 21,600.00


1
50 Kastin Trap uk.15.25.40 m Rp 40,600.00
3
51 Pasir Cor m Rp 115,000.00
52 Sement PC ( Portland Cement ) 50 Kg Zak Rp 56,000.00
53 Pasir Urug m3 Rp 94,400.00
3
54 Tasirtu m Rp 87,850.00
55 Sewa Crane 30 T - min 8 jam Jam Rp 150,000.00

DAFTAR HARGA SATUAN UPAH

Nama Kegiatan : #REF!


Nama Pekerjaan : #REF!
Lokasi : #REF!

NO. URAIAN SATUAN HARGA SATUAN

1 Mandor Orang Hari Rp 60,000.00


2 Pekerja Terampil Orang Hari Rp 35,000.00
3 Pekerja / Buruh Tak Terampil Orang Hari Rp 32,000.00
4 Operator Orang Hari Rp 35,000.00
5 Pembantu Operator Orang Hari Rp 32,000.00
6 Tenaga Pemasak Aspal Orang Hari Rp 35,000.00
7 Sopir Orang Hari Rp 35,000.00
8 Pembantu Sopir Orang Hari Rp 32,000.00
9 Kepala Tukang batu Orang Hari Rp 50,000.00
10 Tukang batu Orang Hari Rp 40,000.00
11 Kepala Tukang Besi Orang Hari Rp 50,000.00
12 Tukang Besi Orang Hari Rp 35,000.00
13 Kepala Tukang Kayu Orang Hari Rp 50,000.00
14 Tukang kayu Orang Hari Rp 40,000.00
15 Masinis Orang Hari Rp 40,000.00
16 Pembantu masinis Orang Hari Rp 30,000.00