RAB GEdung Kantor Malut 2023
RAB GEdung Kantor Malut 2023
ENGINEERING ESTIMATE ( EE )
TAHAP II
VOLUME
NO URAIAN JENIS PEKERJAAN KETERANGAN SATUAN HARGA SATUAN JML.HARGA
TOTAL I II (Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7)
I. PEKERJAAN PERSIAPAN
1 Mobilisasi dan Demobilisasi Ls 2.00 1.00 1.00 75,000,000.00 75,000,000.00
2 Pengurusan Izin Mendirikan Bangunan (IMB) Ls - - - - -
3 Land Clearing M2 31,000.00 7,200.00 23,800.00 13,282.50 316,123,500.00
4 Papan Nama Proyek Ls 2.00 1.00 1.00 500,000.00 500,000.00
5 Pembersihan Awal M2 - 1,560 - - -
6 Pembuatan Kantor sementara ( Direksi keet ) M2 12.00 12.00 - 1,883,033.95 -
7 Pembuatan Gudang Semen Dan Alat-alat M2 18.00 18.00 - - -
8 Penyediaan Air Kerja Ls 2.00 1.00 1.00 30,000,000.00 30,000,000.00
9 Pemasangan Bouwplank M1 328.00 164.00 164.00 81,378.60 13,346,090.40
10 Dokumentasi & Pelaporan Ls 2.00 1.00 1.00 81,378.60 81,378.60
11 Pembersihan Akhir Ls 2.00 1.00 1.00 20,000,000.00 20,000,000.00
Pengukuran Daya Dukung Tanah (Sondir ) Titik 4.00 4.00 - 6,500,000.00 -
Pengetesan Dan Pengujian Mutu Beton Ls 1.00 1.00 - 15,000,000.00 -
Penerangan & Managemen (K3) Ls 2.00 1.00 1.00 90,000,000.00 90,000,000.00
Jumlah I….Rp 545,050,969.00
II. PEKERJAAN LANTAI I
A. PEKERJAAN TANAH DAN PONDASI
1 Galian tanah pondasi M³ 242.19 242.19 - 59,771.25 -
2 Galian Tanah Untuk Pondasi Telapak M³ 452.03 452.03 - 59,771.25 -
3 Urugan pasir bawah pondasi M³ 34.23 34.23 - 198,628.50 -
4 Urugan Tanah Kembali Pondasi M³ 231.41 231.41 - 43,642.50 -
5 Urugan Pasir Bawah Lantai M³ 54.32 54.32 - 198,628.50 -
6 Urugan Tanah Bawah Lantai M³ 904.62 904.62 - 428,908.50 -
7 Pas. Batu Kosong Pondasi M³ 32.29 32.29 - 458,342.35 -
8 Pas. Pondasi Batu Kali , Camp. 1:4 M³ 137.24 137.24 - 1,100,912.25 -
9 Pas. Pondasi Rolag, Camp. 1:4 M³ 17.28 17.28 - 1,100,912.25 -
Jumlah II.A….Rp -
B. PEKERJAAN TIANG PANCANG
1 Pengukuran Dan Posision Tiang Pancang Ls 1.00 1.00 - 27,057,450.00 -
2 Pembuatan Kepala Penutup Tiang Pancang Titik 41.00 41.00 - 410,101.86 -
3 Pengadaan Tiang Pancang Beton K 500 Diameter 40 M1 820.00 820.00 - 630,000.00 -
4 Pemancangan Tiang Tegak M1 820.00 820.00 - 661,713.33 -
Jumlah II.B….Rp -
RAB, LT 1 6
VOLUME
NO URAIAN JENIS PEKERJAAN KETERANGAN SATUAN HARGA SATUAN JML.HARGA
TOTAL I II (Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7)
C. PEKERJAAN BETON
1 Pas.Lantai Kerja Pondasi Telapak Beton K- 125 M³ 18.08 18.08 - 1,670,885.62 -
-
2 Pas. Pondasi Telapak 180 Cm x 180 Cm x 40 Cm -
. Bekesting Pondasi Telapak Kayu kelas II M² 118.08 118.08 - 207,789.40 -
- Tulangan besi beton U-39 Besi Ulir Ø 16 Kg 8,347.31 8,347.31 - 20,820.06 -
- Beton K-300 M³ 53.14 53.14 - 2,020,713.12 -
3 Pas. Sloof 30 cm x 50 cm
- Bekisting Sloof beton Kayu kelas II M² 446.70 446.70 - 217,789.40 -
- Tulangan besi beton U-39 Besi Ulir Ø 16 Kg 9,887.67 9,887.67 - 20,820.06 -
- Tulangan besi beton U-24 Besi Polos Ø 8" Kg 1,969.66 1,969.66 - 20,820.06 -
- Beton K-300 M³ 67.01 67.01 - 2,020,713.12 -
4 Pas. Sloof 20 cm x 30 cm
- Bekisting Sloof beton Kayu kelas II M² 104.70 104.70 - 217,789.40 -
- Tulangan besi beton U-39 Besi Ulir Ø 16 Kg 1,932.24 1,932.24 - 20,820.06 -
- Tulangan besi beton U-24 Besi Polos Ø 8" Kg 518.06 518.06 - 20,820.06 -
- Beton K-300 M³ 10.47 10.47 - 2,020,713.12 -
5 Pas. Kolom 20 cm x 70 cm
- Bekisting kolom beton Kayu kelas II M² 79.38 79.38 - 402,431.20 -
- Tulangan besi beton U-24 Besi Polos Ø 12" Kg 469.80 469.80 - 20,820.06 -
- Tulangan besi beton U-24 Besi Polos Ø 8" Kg 235.16 235.16 - 20,820.06 -
- Beton K-300 M³ 3.81 3.81 - 2,020,713.12 -
6 Pas. Kolom 25 cm x 35 cm
- Bekisting kolom beton Kayu kelas II M² 5.52 5.52 - 402,431.20 -
- Tulangan besi beton U-24 Besi Polos Ø 12" Kg 49.00 49.00 - 20,820.06 -
- Tulangan besi beton U-24 Besi Polos Ø 8" Kg 13.64 13.64 - 20,820.06 -
- Beton K-300 M³ 0.40 0.40 - 2,020,713.12 -
7 Pas. Kolom 15 cm x 35 cm
- Bekisting kolom beton Kayu kelas II M² 33.80 33.80 - 402,431.20 -
- Tulangan besi beton U-24 Besi Polos Ø 12" Kg 180.04 180.04 - 20,820.06 -
- Tulangan besi beton U-24 Besi Polos Ø 8" Kg 79.16 79.16 - 411,167.20 -
- Beton K-300 M³ 1.77 1.77 - 2,020,713.12 -
8 Pas. Kolom 15 cm x 40 cm
- Bekisting kolom beton Kayu kelas II M² 27.94 27.94 - 402,431.20 -
- Tulangan besi beton U-24 Besi Polos Ø 12" Kg 180.39 180.39 - 20,820.06 -
RAB, LT 1 6
VOLUME
NO URAIAN JENIS PEKERJAAN KETERANGAN SATUAN HARGA SATUAN JML.HARGA
TOTAL I II (Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7)
- Tulangan besi beton U-24 Besi Polos Ø 8" Kg 67.08 67.08 - 353,551.20 -
- Beton K-300 M³ 1.52 1.52 - 2,020,713.12 -
9 Pas. Kolom 12 cm x 40 cm
- Bekisting kolom beton Kayu kelas II M² 14.56 14.56 - 402,431.20 -
- Tulangan besi beton U-24 Besi Polos Ø 12" Kg 99.43 99.43 - 20,820.06 -
- Tulangan besi beton U-24 Besi Polos Ø 8" Kg 34.86 34.86 - 20,820.06 -
- Beton K-300 M³ 0.67 0.67 - 2,020,713.12 -
10 Pas. Kolom 50 cm x 50 cm
- Bekisting kolom beton Kayu kelas II M² 360.80 360.80 - 402,431.20 -
- Tulangan besi beton U-39 Besi Ulir Ø 16 Kg 5,694.29 5,694.29 - 20,820.06 -
- Tulangan besi beton U-24 Besi Polos Ø 8" Kg 1,127.49 1,127.49 - 20,820.06 -
- Beton K-300 M³ 45.10 45.10 - 2,020,713.12 -
RAB, LT 1 6
VOLUME
NO URAIAN JENIS PEKERJAAN KETERANGAN SATUAN HARGA SATUAN JML.HARGA
TOTAL I II (Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7)
- Tulangan besi beton U-24 Besi Polos Ø 12 Kg 17.04 17.04 - 20,820.06 -
- Tulangan besi beton U-24 Besi Polos Ø 8" Kg 5.52 5.52 - 20,820.06 -
- Beton K-300 M³ 0.09 0.09 - 2,020,713.12 -
-
16 Pas. Lisplank Beton 10 Cm x 140 cm
- Bekisting Beton Kayu kelas II M² 561.54 561.54 - 353,551.20 -
- Tulangan besi beton U-24 Besi Polos Ø 10" Kg 2,163.68 2,163.68 - 20,820.06 -
- Beton K-300 M³ 28.08 28.08 - 2,020,713.12 -
RAB, LT 1 6
VOLUME
NO URAIAN JENIS PEKERJAAN KETERANGAN SATUAN HARGA SATUAN JML.HARGA
TOTAL I II (Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7)
9 Cat dinding M² 1,424.37 1,424.37 - 66,440.53 -
10 Nama & Logo Perhubungan (Stenlis Stile) Ls 1.00 - 1.00 40,000,000.00 40,000,000.00
11 Pas. Beton tumbuk lantai, tebal 5 cm M² 55.80 55.80 - 1,670,885.62 -
12 Pas.Granit Lantai 60 x 60 cm Lt. I M² 1,040.36 1,040.36 367,114.65 -
13 Pas. Plin Granit Lt 1 M¹ 222.36 222.36 109,331.96 -
14 Pas.Lantai Tangga (Granit textur ) 30 x 60 Cm M² 110.66 - 110.66 367,114.65 40,624,686.90
15 Pas.Keramik Lantai KM/WC 25 x 25 cm Lt 1&2 M² 41.89 41.89 - 302,342.05 -
16 Pas. Keramik Dinding 25 x 40 cm M² 159.71 159.71 - 347,506.62 -
17 Pas. Pagar Tangga Kaca Tempered 10 mm+ Rangka Stenlis M² 12.77 - 12.77 1,497,136.79 19,118,436.81
Jumlah II.D….Rp 770,420,034.91
E. PEKERJAAN PINTU & JENDELA
1 Pas. Kusen Alumunium Warna Silver M¹ 271.03 271.03 - 208,056.22 -
2 Pas. Ram Angin Rangka Galvanis M² 3.52 3.52 - 850,000.00 -
3 Pas. Pintu Kaca Tempered 19 mm + Acesoris M² 15.03 15.03 - 4,992,031.50 -
4 Pas. Daun Pintu Kaca Rangka Alumunium M² 45.65 45.65 - 1,702,126.32 -
5 Pas.Daun Jendela & Ventilasi Kaca Rangka Alumunium M² 4.87 4.87 - 1,069,626.32 -
6 Pas. Kunci Pintu 2 Slaag Kualitas Baik Bh 18.00 18.00 - 610,569.50 -
7 Pas. Kunci Tanam Km/ Wc Bh 8.00 8.00 - 405,073.70 -
8 Kunci Fitting Pintu Kaca 19 MM Bh 3.00 3.00 - 1,409,904.11 -
9 Pas. Engsel Pintu Kualitas Baik Bh 81.00 81.00 - 100,029.07 -
10 Pas. Engsel Jendela & Ventilasi Bh 14.00 14.00 - 53,817.70 -
11 Pas. Grendel Pintu Kualitas Baik Bh 23.00 23.00 - 61,849.07 -
12 Pas. Grendel Jendela Kualitas Baik Bh 7.00 7.00 - 61,849.07 -
13 Pas. Kait Angin Jendela & Ventilasi Kualitas Baik Bh 14.00 14.00 - 58,299.07 -
14 Pas. Kaca Rayband , 5 mm M² 35.77 35.77 - 311,677.14 -
15 Pas. Handle Pintu Bh 6.00 6.00 - 462,049.07 -
Jumlah II.E….Rp -
F. PEKERJAAN PLAFOND
1 Pas. Rangka Plafond Besi Holow Lt 1&2 M² 964.90 964.90 - 231,400.70 -
2 Pas. Penutup Plafond Gibsum 9 mm Lt 1&2 M² 964.90 964.90 - 78,213.11 -
3 Pas. Listprofil Gibsum M¹ 650.95 650.95 - 51,106.00 -
4 Cat Plafond M² 964.90 964.90 - 66,440.53 -
Jumlah II.F….Rp -
G. PEKERJAAN SANITASI
1 Kloset Duduk Toto Bh 8.00 8.00 - 4,794,724.90 -
2 Floor Drain Bh 8.00 8.00 - 62,939.50 -
3 Kran Air Bh 16.00 16.00 - 192,402.00 -
4 Pas. Pipa Air Bersih Pvc 1/2" Inc M¹ 300.00 300.00 - 31,121.30 -
5 Pas. Pipa Pembuangan Air Kotor Pvc 3 " Inc M¹ 50.00 50.00 - 145,254.20 -
6 Pas. Pipa Pembuangan Septicktangk Pvc 4 " Inc M¹ 20.00 20.00 - 180,425.23 -
7 Pas. Bak Cuci Piring 2 Lubang Set 1.00 1.00 - 2,086,397.50 -
RAB, LT 1 6
VOLUME
NO URAIAN JENIS PEKERJAAN KETERANGAN SATUAN HARGA SATUAN JML.HARGA
TOTAL I II (Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7)
8 Pas. Watafel Set 4.00 4.00 - 1,449,223.90 -
9 Pas. Septictank Vol. 10.39 M3 Unit 2.00 2.00 - 10,182,705.44 -
10 Pemasangan Sumur Bor M1 50.00 50.00 - 1,500,000.00 -
Jumlah II.G….Rp -
H. PEKERJAAN ELEKTRIKAL
1 Instalasi Titik Lampu Bh 187.00 187.00 - 358,282.50 -
2 Pas. Box Panel 6 Group Bh 4.00 4.00 - 299,849.39 -
3 Pas. MCB Bh 24.00 24.00 - 93,378.85 -
4 Pas. Stop Kontak Bh 40.00 40.00 - 58,248.85 -
5 Pas. Saklar Ganda Bh 10.00 10.00 - 68,150.35 -
6 Pas. Saklar Tunggal Bh 16.00 16.00 - 61,805.35 -
7 Pas. Lampu TL . RM 2 X 30 Watt. 120 Cm Komplit Set Bh 21.00 21.00 - 730,801.65 -
8 Pas. Lampu Down light Led 5 Watt Bh 20.00 20.00 - 103,051.65 -
9 Pas. Lampu Down light Led 7 Watt Bh 26.00 26.00 - 134,551.65 -
10 Pas. Lampu Jari-Jari 18 Watt Ttk 16.00 16.00 - 94,374.15 -
11 Pas. Lampu Jari-Jari 24 Watt Ttk 10.00 10.00 - 120,939.15 -
12 Pemasangan Neon Box Akrilik M2 12.60 12.60 - 1,268,555.75 -
13 Pas.Exhaust Fan Bh 4.00 4.00 - 583,843.50 -
14 Pas. Air Condusioner ( AC ) 1 Pk Bh 15.00 15.00 - 4,857,505.75 -
15 Pas. Instalasi Penangkal Petir Ls 1.00 1.00 - 20,000,000.00 -
Pengadaan Dan Pemasangan Kamera CCTV 2 Mp (Indoor/Outdoor- Pemasangan Dari
16 Ls 1.00 - 1.00 78,573,750.00 78,573,750.00
Infrared Full HD) 40 Channel Lengkap + 2 Unit Monitor LED 32" Lt.1, Lt.2 Dan Lt.3
17 Penyambungan Daya Listrik Baru Dari PLN, 23000 Watt Ls 1.00 1.00 - 45,000,000.00 -
Jumlah II.H….Rp 78,573,750.00
RAB, LT 1 6
RENCANA ANGGARAN BIAYA
LANTAI II
TAHAP II
VOLUME
NO URAIAN JENIS PEKERJAAN KETERANGAN SATUAN HARGA SATUAN JML.HARGA
TOTAL II (Rp) (Rp)
(1) (2) (3) (4) (6) (7)
III. PEKERJAAN LT. II
A. PEKERJAAN BETON
1 Pas. Kolom 50 cm x 50 cm
- Bekisting kolom beton Kayu kelas II M² 312.00 - 402,431.20 -
- Tulangan besi beton U-39 Besi Ulir Ø 16 Kg 4,924.11 - 20,820.06 -
- Tulangan besi beton U-24 Besi Polos Ø 8" Kg 1,025.86 - 20,820.06 -
- Beton K-300 M³ 39.00 - 2,020,713.12 -
- -
2 Pas. Ring Balok 30 cm x 60 cm - -
- Bekisting Balok beton Kayu kelas II M² 259.34 - 411,167.20 -
- Tulangan besi beton U-39 Besi Ulir Ø 16 Kg 5,823.58 - 20,820.06 -
- Tulangan besi beton U-24 Besi Polos Ø 8" Kg 1,365.02 - 20,820.06 -
- Beton K-300 M³ 38.90 - 2,020,713.12 -
- -
3 Pas. Ring Balok 20 cm x 35 cm - -
- Bekisting Balok beton Kayu kelas II M² 110.68 - 411,167.20 -
- Tulangan besi beton U-39 Besi Ulir Ø 16 Kg 2,385.79 - 20,820.06 -
- Tulangan besi beton U-24 Besi Polos Ø 8" Kg 497.15 - 20,820.06 -
- Beton K-300 M³ 12.91 - 2,020,713.12 -
- -
4 Pas. Ring Balok 25 cm x 40 cm - -
- Bekisting Balok beton Kayu kelas II M² 125.87 - 411,167.20 -
- Tulangan besi beton U-24 Besi Ulir dia. 13 Kg 1,080.41 - 20,820.06 -
- Tulangan besi beton U-24 Besi Polos dia. 12 Kg 613.73 - 20,820.06 -
- Tulangan besi beton U-24 Besi Polos Ø 8" Kg 409.43 - 20,820.06 -
- Beton K-300 M³ 10.49 - 2,020,713.12 -
- -
5 Pas. Ring Balok 10 cm x 25 cm - -
- Bekisting Balok beton Kayu kelas II M² 11.59 - 411,167.20 -
TAHAP II
VOLUME
NO URAIAN JENIS PEKERJAAN KETERANGAN SATUAN HARGA SATUAN JML.HARGA
TOTAL II (Rp) (Rp)
(1) (2) (3) (4) (6) (7)
- Tulangan besi beton U-24 Besi Polos Ø 10" Kg 95.29 - 20,820.06 -
- Tulangan besi beton U-24 Besi Polos Ø 6" Kg 21.44 - 20,820.06 -
- Beton K-300 M³ 0.48 - 2,020,713.12 -
- -
6 Pas. Ring Balok 15 cm x 25 cm - -
- Bekisting Balok beton Kayu kelas II M² 1.04 - 411,167.20 -
- Tulangan besi beton U-24 Besi Polos Ø 12" Kg 11.36 - 20,820.06 -
- Tulangan besi beton U-24 Besi Polos Ø 8" Kg 3.87 - 20,820.06 -
- Beton K-300 M³ 0.06 - 2,020,713.12 -
- -
7 Pas. Lisplang Beton 10 Cm x 75 cm - -
- Bekisting Lisplang Beton Kayu kelas II M² 25.28 - 353,551.20 -
- Tulangan besi beton U-24 Besi Polos Ø 10" Kg 448.85 - 20,820.06 -
- Beton K-300 M³ 11.85 - 411,167.20 -
- -
8 Pas. Plat Beton Lantai III - -
- Bekisting Lantai Beton Kayu kelas II M² 621.85 - 485,631.20 -
- Tulangan besi beton U-24 Besi Polos Ø 10" Kg 9,967.63 - 20,820.06 -
- Beton K-300 M³ 93.28 - 2,020,713.12 -
- -
9 Pas. Tangga Beton - -
- Bekisting Tangga Kayu kelas II M² - - 380,496.20 -
- Tulangan besi beton U-24 Besi beton dia. 12 Kg - - 20,820.06 -
- Beton K-300 M³ - - 2,020,713.12 -
- -
10 Pas. Kanopi Beton T 8cm M² 28.50 - 745,033.00 -
- -
11 Pas. Meja Beton M² 1.73 - 589,990.00 -
- -
12 Pas. Kolom Praktis 11 x 11 cm M1 400.00 - 122,373.00 -
- -
13 Pas. Balok Beton 10 x 15 cm (Di Atas Kusen) M1 57.76 - 153,723.10 -
Jumlah III.A.….Rp -
B. PEKERJAAN DINDING DAN LANTAI
TAHAP II
VOLUME
NO URAIAN JENIS PEKERJAAN KETERANGAN SATUAN HARGA SATUAN JML.HARGA
TOTAL II (Rp) (Rp)
(1) (2) (3) (4) (6) (7)
1 Pas. Dinding Lt. 1/2 bata, camp. 1:4 M² 840.30 434.33 159,001.75 69,059,160.26
2 Pas. Dinding Partisi Kaca Rangka Alumunium Lt. 1 M² 105.72 76.30 1,215,260.96 92,724,411.52
3 Pas. Dinding Kaca Tempered Polos 12mm M² 45.05 45.05 1,154,922.46 52,026,946.98
4 Pas. Plesteran dinding Lt 1 camp. 1:4 M² 1,680.61 868.66 88,486.83 76,864,892.04
5 Pemasangan 1 m2 Aluminium Composite Panel ACP SEVEN PFDV M² 813.05 813.05 1,492,850.70 1,213,760,022.36
6 Pas. Acian dinding, kolom & kanopi 1:3 M² 2,549.26 1,737.32 53,224.88 92,468,546.35
7 Cat dinding M² 1,063.56 1,063.56 66,440.53 70,663,225.65
8 Pas.Granit Lantai 60 x 60 cm M² 918.86 918.86 367,114.65 337,327,885.09
9 Pas. Plin Granit Lt M¹ 551.05 551.05 109,331.96 60,247,375.26
10 Pas.Lantai Tangga (Granit textur ) 30 x 60 Cm M² 17.14 17.14 367,114.65 6,290,876.64
11 Pas.Keramik Lantai KM/WC 25 x 25 cm Lt 1&2 M² 46.04 46.04 302,342.05 13,919,072.13
12 Pas. Keramik Dinding 25 x 40 cm M² 174.83 174.83 347,506.62 60,752,845.37
13 Pas. Ram Galvanis M² 3.50 3.50 1,022,104.49 3,575,321.51
14 Pas. Pagar Tangga Kaca Tempered 10mm + Rangka Stenlis M² 13.62 13.62 1,497,136.79 20,385,014.53
15 Pas. Pagar Kaca Tempered 10mm + Rangka Stenlis M² 57.67 57.67 1,497,136.79 86,336,884.41
Jumlah III.B….Rp 2,256,402,480.09
C. PEKERJAAN PINTU & JENDELA
1 Pas. Kusen Alumunium Warna Silver M¹ 321.99 21.90 208,056.22 4,556,431.11
2 Pas. Ram Angin Rangka Galvanis M² 3.52 - 850,000.00 -
3 Pas. Pintu Kaca Tempered 19 mm + Acisoris M² 7.36 7.36 4,992,031.50 36,741,351.84
4 Pas. Daun Pintu Kaca Rangka Alumunium M² 57.66 5.81 1,702,126.32 9,880,843.29
5 Pas.Daun Jendela & Ventilasi Kaca Rangka Alumunium M² 9.94 - 1,069,626.32 -
6 Pas. Kunci Pintu 2 Slaag Kualitas Baik Bh 17.00 3.00 610,569.50 1,831,708.50
7 Pas. Kunci Tanam Km/ Wc Bh 8.00 - 405,073.70 -
8 Kunci Fitting Pintu Kaca 19 MM Bh 2.00 2.00 1,409,904.11 2,819,808.22
9 Pas. Engsel Pintu Kualitas Baik Bh 111.00 111.00 100,029.07 11,103,226.77
10 Pas. Engsel Jendela & Ventilasi Bh 34.00 - 53,817.70 -
11 Pas. Grendel Pintu Kualitas Baik Bh 28.00 28.00 61,849.07 1,731,773.96
12 Pas. Grendel Jendela Kualitas Baik Bh 17.00 - 61,849.07 -
13 Pas. Kait Angin Jendela & Ventilasi Kualitas Baik Bh 34.00 - 58,299.07 -
14 Pas. Kaca Rayband , 5 mm M² 30.43 30.43 311,677.14 9,484,865.22
15 Pas. Handle Pintu Bh 6.00 6.00 462,049.07 2,772,294.42
Jumlah III.C….Rp 80,922,303.32
D. PEKERJAAN PLAFOND
TAHAP II
VOLUME
NO URAIAN JENIS PEKERJAAN KETERANGAN SATUAN HARGA SATUAN JML.HARGA
TOTAL II (Rp) (Rp)
(1) (2) (3) (4) (6) (7)
1 Pas. Rangka Plafond Besi Holow M² 1,029.97 1,029.97 231,400.70 238,335,778.98
2 Pas. Penutup Plafond Gibsum 9 mm Lt 1&2 M² 1,029.97 1,029.97 78,213.11 80,557,156.91
4 Pas. Listprofil Gibsum M¹ 486.70 486.70 51,106.00 24,873,290.20
5 Cat Plafond M² 1,029.97 1,029.97 66,440.53 68,431,747.53
Jumlah III.D….Rp 412,197,973.62
E. PEKERJAAN SANITASI
1 Kloset Duduk Toto Bh 8.00 8.00 4,794,724.90 38,357,799.20
2 Floor Drain Bh 8.00 8.00 62,939.50 503,516.00
3 Kran Air Bh 16.00 16.00 192,402.00 3,078,432.00
4 Pas. Pipa Air Bersih Pvc 1/2" Inc M¹ 150.00 150.00 31,121.30 4,668,195.00
5 Pas. Pipa Pembuangan Air Kotor Pvc 3 " Inc M¹ 50.00 50.00 145,254.20 7,262,710.00
6 Pas. Pipa Pembuangan Septicktangk Pvc 4 " Inc M¹ 60.00 60.00 180,425.23 10,825,513.50
7 Pas. Bak Cuci Piring 2 Lubang Set 1.00 1.00 2,086,397.50 2,086,397.50
8 Pas. Watafel Set 8.00 8.00 1,449,223.90 11,593,791.20
Jumlah III.E….Rp 78,376,354.40
F. PEKERJAAN ELEKTRIKAL
1 Instalasi Titik Lampu Bh 214.00 214.00 358,282.50 76,672,455.00
2 Pas. Box Panel 6 Group Bh 4.00 4.00 299,849.39 1,199,397.56
3 Pas. MCB Bh 24.00 24.00 93,378.85 2,241,092.40
4 Pas. Stop Kontak Bh 30.00 30.00 58,248.85 1,747,465.50
5 Pas. Saklar Ganda Bh 14.00 14.00 68,150.35 954,104.90
6 Pas. Saklar Tunggal Bh 14.00 14.00 61,805.35 865,274.90
7 Pas. Lampu TL . RM 2 X 30 Watt. 120 Cm Komplit Set Bh 20.00 20.00 730,801.65 14,616,033.00
8 Pas. Lampu Down light Led 5 Watt Bh 26.00 26.00 103,051.65 2,679,342.90
9 Pas. Lampu Down light Led 7 Watt Bh 30.00 30.00 134,551.65 4,036,549.50
10 Pas. Lampu Jari-Jari 18 Watt Ttk 16.00 16.00 94,374.15 1,509,986.40
11 Pas. Lampu Jari-Jari 24 Watt Ttk 16.00 16.00 120,939.15 1,935,026.40
13 Pas.Exhaust Fan Bh 20.00 20.00 583,843.50 11,676,870.00
14 Pas. Air Condusioner ( AC ) 1 Pk Bh 15.00 15.00 4,857,505.75 72,862,586.25
Jumlah III.F….Rp 192,996,184.71
RENCANA ANGGARAN BIAYA
LANTAI III
TAHAP II
VOLUME
NO URAIAN JENIS PEKERJAAN KETERANGAN SATUAN HARGA SATUAN JML.HARGA
II (Rp) (Rp)
(1) (2) (3) (4) (6) (7)
IV. PEKERJAAN LT. III
A. PEKERJAAN BETON
1 Pas. Kolom 30 cm x 30 cm
- Bekisting kolom beton Kayu kelas II M² - 402,431.20 -
- Tulangan besi beton U-39 Besi Polos Ø 16" Kg - 20,820.06 -
- Tulangan besi beton U-24 Besi Polos Ø 8" Kg - 20,820.06 -
- Beton K-300 M³ - 2,020,713.12 -
- -
2 Pas. Kolom 15 cm x 15 cm - -
- Bekisting kolom beton Kayu kelas II M² - 402,431.20 -
- Tulangan besi beton U-39 Besi Polos Ø 12" Kg - 20,820.06 -
- Tulangan besi beton U-24 Besi Polos Ø 8" Kg - 20,820.06 -
- Beton K-300 M³ - 2,020,713.12 -
- -
3 Pas. Ring Balok 20 cm x 35 cm - -
- Bekisting Balok beton Kayu kelas II M² - 411,167.20 -
- Tulangan besi beton U-24 Besi Ulir Ø 16" Kg - 20,820.06 -
- Tulangan besi beton U-24 Besi Polos Ø 8" Kg - 20,820.06 -
- Beton K-300 M³ - 2,020,713.12 -
- -
4 Pas. Ring Balok 15 cm x 20 cm - -
- Bekisting Balok beton Kayu kelas II M² - 411,167.20 -
- Tulangan besi beton U-24 Besi Polos dia. 12 Kg - 20,820.06 -
- Tulangan besi beton U-24 Besi Polos Ø 8" Kg - 20,820.06 -
- Beton K-300 M³ - 2,020,713.12 -
TAHAP II
VOLUME
NO URAIAN JENIS PEKERJAAN KETERANGAN SATUAN HARGA SATUAN JML.HARGA
II (Rp) (Rp)
(1) (2) (3) (4) (6) (7)
- -
5 Pas. Plat Atap Beton - -
- Bekisting Lantai Beton Kayu kelas II M² - 485,631.20 -
- Tulangan besi beton U-24 Besi Polos Ø 10" Kg - 20,820.06 -
- Beton K-300 M³ - 2,020,713.12 -
- -
6 Pas. Talang Beton - -
- Bekisting Lantai Beton Kayu kelas II M² - 353,551.20 -
- Tulangan besi beton U-24 Besi Polos Ø 10" Kg - 20,820.06 -
- Beton K-300 M³ - 2,020,713.12 -
- -
7 Pas. Kolom Praktis 11 x 11 cm M1 - 122,373.00 -
- -
8 Pas. Kolom Praktis 11 x 11 cm ( Area Talang ) M1 - 122,373.00 -
- -
9 Pas. Balok Beton 10 x 15 cm M1 0 153,723.10 -
Jumlah IV.A….Rp -
B. PEKERJAAN DINDING DAN LANTAI
1 Pas. Dinding Lt. 1/2 bata, camp. 1:4 M² - 159,001.75 -
2 Pas. Plesteran dinding Lt 1 camp. 1:4 M² - 88,486.83 -
3 Pemasangan 1 m2 Aluminium Composite Panel ACP SEVEN PFDV M² 350.45 1,492,850.70 523,169,527.82
4 Pas. Acian dinding, kolom & Talang 1:3 M² - 53,224.88 -
5 Cat dinding M² - 66,440.53 -
6 Pas.Granit Lantai 60 x 60 cm M² - 367,114.65 -
6 Pas.Granit Lantai (Anti Slip) 60 x 60 cm M² - 367,114.65 -
7 Pas.Keramik Lantai KM/WC 25 x 25 cm Lt 1&2 M² - 302,342.05 -
8 Pas. Keramik Dinding 25 x 40 cm M² - 347,506.62 -
9 Pas. Pagar Kaca Tempered 10mm + Rangka Stenlis M² - 1,497,136.79 -
Jumlah IV.B….Rp 523,169,527.82
C. PEKERJAAN PINTU & JENDELA
1 Pas. Kusen Alumunium Warna Silver M¹ - 208,056.22 -
TAHAP II
VOLUME
NO URAIAN JENIS PEKERJAAN KETERANGAN SATUAN HARGA SATUAN JML.HARGA
II (Rp) (Rp)
(1) (2) (3) (4) (6) (7)
2 Pas. Daun Pintu Kaca Rangka Alumunium M² - 1,702,126.32 -
3 Pas. Kunci Pintu 2 Slaag Kualitas Baik Bh - 610,569.50 -
4 Pas. Kunci Tanam Km/ Wc Bh - 405,073.70 -
5 Pas. Engsel Pintu Kualitas Baik Bh - 100,029.07 -
7 Pas. Grendel Pintu Kualitas Baik Bh - 61,849.07 -
10 Pas. Kaca Rayband , 5 mm M² - 311,677.14 -
11 Pas. Handle Pintu Bh - 462,049.07 -
Jumlah IV.C….Rp -
D. PEKERJAAN PLAFOND
1 Pas. Rangka Plafond Besi Holow M² - 231,400.70 -
2 Pas. Penutup Plafond Gibsum 9 mm Lt 1&2 M² - 78,213.11 -
3 Pas. Listprofil Gibsum M¹ - 51,106.00 -
4 Cat Plafond M² - 66,440.53 -
Jumlah IV.D….Rp -
E. PEKERJAAN ATAP
1 Pas. Rangka Atap Baja Double Siku M² - 620,419.35 -
2 Pas. Penutup atap seng Spandek M² - 341,420.48 -
3 Pas. Bubungan atap Seng Spandek M¹ - 158,473.45 -
4 Pas. Listplank GRC 0,4 mm M¹ - 250,000.00 -
Jumlah IV.E….Rp -
F. PEKERJAAN SANITASI
1 Kloset Duduk Toto Bh - 4,794,724.90 -
2 Pas. Watafel Bh - 1,449,223.90 -
3 Floor Drain Bh - 62,939.50 -
4 Kran Air Bh - 192,402.00 -
5 Pas. Pipa Air Bersih Pvc 1/2" Inc M¹ - 31,121.30 -
6 Pas. Pipa Pembuangan Septicktangk Pvc 4 " Inc M¹ - 180,425.23 -
7 Pas. PembuanganAir Kotor & Talang Pvc 3 " Inc M¹ - 145,254.20 -
8 Mesin Pompa Air Jet Pump Auoto Mat Komplit Bh - 4,687,500.00 -
9 Profil Tangki Air 3000 Liter Bh - 3,750,000.00 -
Jumlah IV.F….Rp -
TAHAP II
VOLUME
NO URAIAN JENIS PEKERJAAN KETERANGAN SATUAN HARGA SATUAN JML.HARGA
II (Rp) (Rp)
(1) (2) (3) (4) (6) (7)
G. PEKERJAAN ELEKTRIKAL
1 Instalasi Titik Lampu Bh - 358,282.50 -
2 Pas. Stop Kontak Bh - 58,248.85 -
3 Pas. Saklar Ganda Bh - 68,150.35 -
4 Pas. Saklar Tunggal Bh - 61,805.35 -
5 Pas. Lampu Jari-Jari 18 Watt Ttk - 94,374.15 -
Jumlah IV.G….Rp -
RENCANA ANGGARAN BIAYA (RAB)
PEKERJAAN JALAN
JUMLAH 5,613,897,126.81
REKAPITULASI RENCANA ANGGARAN BIAYA
PEKERJAAN PAGAR
JUMLAH Rp 1,236,250,000.00
RENCANA ANGGARAN BIAYA (RAB)
PAGAR DEPAN (50 m')
a. Tenaga
- Pekerja 0.400 Oh x Rp. 115,000.00 = Rp. 46,000.00
- Tukang Kayu 0.200 Oh x Rp. 172,500.00 = Rp. 34,500.00
- Kepala Tukang 0.020 Oh x Rp. 201,250.00 = Rp. 4,025.00
- Mandor 0.020 Oh x Rp. 225,400.00 = Rp. 4,508.00
JUMLAH (a) = Rp. 89,033.00
b. Bahan
- Dolken Kayu diameter 8-10/400 cm 1.250 Btg x Rp. 20,800.00 = Rp. 26,000.00
- Semen Portland 5.000 Kg x Rp. 2,679.50 = Rp. 13,397.50
- Pasir Beton 0.005 M³ x Rp. 208,000.00 = Rp. 1,040.00
- Koral Beton 0.009 M³ x Rp. 686,400.00 = Rp. 6,177.60
- Kayu 5/7 0.072 M³ x Rp. 2,912,000.00 = Rp. 209,664.00
- Paku Biasa 2" - 5" 0.060 Kg x Rp. 27,255.00 = Rp. 1,635.30
- Residu 0.400 Ltr x Rp. 15,000.00 = Rp. 6,000.00
JUMLAH (b) = Rp. 263,914.40
a. Tenaga
- Pekerja 0.200 Oh x Rp. 115,000.00 = Rp. 23,000.00
- Tukang Kayu 0.400 Oh x Rp. 172,500.00 = Rp. 69,000.00
- Kepala Tukang 0.020 Oh x Rp. 201,250.00 = Rp. 4,025.00
- Mandor 0.020 Oh x Rp. 225,400.00 = Rp. 4,508.00
JUMLAH (a) = Rp. 100,533.00
b. Bahan
- Dolken Kayu diameter 8-10/400 cm 1.250 Btg x Rp. 20,800.00 = Rp. 26,000.00
- Semen Portland 2.500 Kg x Rp. 2,679.50 = Rp. 6,698.75
- Seng Gelombang 0.20 mm 1.200 Lbr x Rp. 56,810.00 = Rp. 68,172.00
- Pasir Beton 0.005 M³ x Rp. 208,000.00 = Rp. 1,040.00
- Koral Beton 0.009 M³ x Rp. 686,400.00 = Rp. 6,177.60
- Kayu 5/7 0.072 M³ x Rp. 2,912,000.00 = Rp. 209,664.00
- Paku Biasa 2" - 5" 0.060 Kg x Rp. 27,255.00 = Rp. 1,635.30
- Meni Besi 0.450 Ltr x Rp. 51,175.00 = Rp. 23,028.75
JUMLAH (b) = Rp. 342,416.40
a. Tenaga
- Pekerja 0.200 Oh x Rp. 115,000.00 = Rp. 23,000.00
- Tukang Kayu 0.300 Oh x Rp. 172,500.00 = Rp. 51,750.00
- Kepala Tukang 0.020 Oh x Rp. 201,250.00 = Rp. 4,025.00
- Mandor 0.020 Oh x Rp. 225,400.00 = Rp. 4,508.00
JUMLAH (a) = Rp. 83,283.00
b. Bahan
- Dolken Kayu diameter 8-10/400 cm 1.000 Btg x Rp. 20,800.00 = Rp. 20,800.00
- Semen Portland 2.000 Kg x Rp. 2,679.50 = Rp. 5,359.00
- Seng Kawat Duri 25.000 M¹ x Rp. 7,288.47 = Rp. 182,211.75
- Pasir Beton 0.005 M³ x Rp. 208,000.00 = Rp. 1,040.00
- Koral Beton 0.009 M³ x Rp. 686,400.00 = Rp. 6,177.60
- Kayu 5/7 0.072 M³ x Rp. 2,912,000.00 = Rp. 209,664.00
- Paku Biasa 2" - 5" 0.060 Kg x Rp. 27,255.00 = Rp. 1,635.30
Persiapan 1
JUMLAH (b) = Rp. 426,887.65
a. Tenaga
- Pekerja 0.100 Oh x Rp. 115,000.00 = Rp. 11,500.00
- Tukang Kayu 0.100 Oh x Rp. 172,500.00 = Rp. 17,250.00
- Kepala Tukang 0.010 Oh x Rp. 201,250.00 = Rp. 2,012.50
- Mandor 0.005 Oh x Rp. 225,400.00 = Rp. 1,127.00
JUMLAH (a) = Rp. 31,889.50
b. Bahan
- Kayu Balok 5/7 0.012 M ³ x Rp. 2,912,000.00 = Rp. 34,944.00
- Paku 2"-3" 0.020 Kg x Rp. 27,255.00 = Rp. 545.10
- Kayu Papan 3/20 0.007 M ³ x Rp. 2,000,000.00 = Rp. 14,000.00
JUMLAH (b) = Rp. 49,489.10
a. Tenaga
- Pekerja 2.000 Oh x Rp. 115,000.00 = Rp. 230,000.00
- Tukang Kayu 2.000 Oh x Rp. 172,500.00 = Rp. 345,000.00
- Tukang Batu 1.000 Oh x Rp. 172,500.00 = Rp. 172,500.00
- Kepala Tukang 0.300 Oh x Rp. 201,250.00 = Rp. 60,375.00
- Mandor 0.050 Oh x Rp. 225,400.00 = Rp. 11,270.00
JUMLAH (a) = Rp. 819,145.00
b. Bahan
- Dolken Kayu diameter 8-10/400 cm 1.250 Btg x Rp. 20,800.00 = Rp. 26,000.00
- Kayu Kelas II 0.180 M³ x Rp. 2,912,000.00 = Rp. 524,160.00
- Paku Biasa 0.080 Kg x Rp. 27,255.00 = Rp. 2,180.40
- Besi Strip 1.100 Kg x Rp. = Rp. -
- Semen Portland 35.000 Kg x Rp. 2,679.50 = Rp. 93,782.50
- Pasir Pasang 0.150 M³ x Rp. 208,000.00 = Rp. 31,200.00
- Pasir Beton 0.100 M³ x Rp. 208,000.00 = Rp. 20,800.00
- Koral Beton 0.150 M³ x Rp. 686,400.00 = Rp. 102,960.00
- Bata Merah 30.000 Bh x Rp. 1,380.00 = Rp. 41,400.00
- Seng Gelombang 0.20 mm 1.500 Lbr x Rp. 56,810.00 = Rp. 85,215.00
- Seng Plat 0.250 Lbr x Rp. 102,235.00 = Rp. 25,558.75
- Jendela Nako 0.200 Bh x Rp. 294,630.00 = Rp. 58,926.00
- Kaca Polos 0.080 M² x Rp. 283,475.00 = Rp. 22,678.00
- Kunci Tanam 0.150 Bh x Rp. 154,560.00 = Rp. 23,184.00
- Plywood 4 mm 0.060 Lbr x Rp. 97,405.00 = Rp. 5,844.30
JUMLAH (b) = Rp. 1,063,888.95
a. Tenaga
- Pekerja 1.000 Oh x Rp. 115,000.00 = Rp. 115,000.00
- Tukang Kayu 2.000 Oh x Rp. 172,500.00 = Rp. 345,000.00
- Kepala Tukang 0.200 Oh x Rp. 201,250.00 = Rp. 40,250.00
- Mandor 0.050 Oh x Rp. 225,400.00 = Rp. 11,270.00
JUMLAH (a) = Rp. 511,520.00
b. Bahan
- Dolken Kayu diameter 8-10/400 cm 1.700 Btg x Rp. 20,800.00 = Rp. 35,360.00
Persiapan 2
- Kayu Kelas II 0.210 M³ x Rp. 2,912,000.00 = Rp. 611,520.00
- Paku Biasa 0.300 Kg x Rp. 27,255.00 = Rp. 8,176.50
- Semen Portland 10.500 Kg x Rp. 2,679.50 = Rp. 28,134.75
- Pasir Beton 0.030 M³ x Rp. 208,000.00 = Rp. 6,240.00
- Koral Beton 0.050 M³ x Rp. 686,400.00 = Rp. 34,320.00
- Seng Gelombang 0.20 mm 1.500 Lbr x Rp. 56,810.00 = Rp. 85,215.00
- Seng Plat 0.250 Lbr x Rp. 102,235.00 = Rp. 25,558.75
JUMLAH (b) = Rp. 834,525.00
a. Tenaga
- Pekerja 1.000 Oh x Rp. 115,000.00 = Rp. 115,000.00
- Tukang Kayu 1.500 Oh x Rp. 172,500.00 = Rp. 258,750.00
- Kepala Tukang 0.150 Oh x Rp. 201,250.00 = Rp. 30,187.50
- Mandor 0.050 Oh x Rp. 225,400.00 = Rp. 11,270.00
JUMLAH (a) = Rp. 415,207.50
b. Bahan
- Dolken Kayu diameter 8-10/400 cm 3.000 Btg x Rp. 20,800.00 = Rp. 62,400.00
- Kayu Kelas II 0.276 M³ x Rp. 2,912,000.00 = Rp. 803,712.00
- Paku Biasa 0.700 Kg x Rp. 27,255.00 = Rp. 19,078.50
- Seng Gelombang 0.20 mm 1.500 Lmr x Rp. 56,810.00 = Rp. 85,215.00
JUMLAH (b) = Rp. 970,405.50
a. Tenaga
- Pekerja 0.100 Oh x Rp. 75,900.00 = Rp. 7,590.00
- Mandor 0.050 Oh x Rp. 113,850.00 = Rp. 5,692.50
JUMLAH (a) = Rp. 13,282.50
Persiapan 3
HARGA SATUAN PEKERJAAN TANAH
A. TENAGA
- Pekerja 0.750 Oh x Rp. 75,900.00 = Rp. 56,925.00
- Mandor 0.025 Oh x Rp. 113,850.00 = Rp. 2,846.25
JUMLAH (A) = Rp. 59,771.25
A. TENAGA
- Pekerja 0.900 Oh x Rp. 75,900.00 = Rp. 68,310.00
- Mandor 0.045 Oh x Rp. 113,850.00 = Rp. 5,123.25
JUMLAH (A) = Rp. 73,433.25
A. TENAGA
- Pekerja 1.050 Oh x Rp. 75,900.00 = Rp. 79,695.00
- Mandor 0.067 Oh x Rp. 113,850.00 = Rp. 7,627.95
JUMLAH (A) = Rp. 87,322.95
A. TENAGA
- Pekerja 1.000 Oh x Rp. 106,950.00 = Rp. 106,950.00
- Mandor 0.032 Oh x Rp. 225,400.00 = Rp. 7,212.80
JUMLAH (A) = Rp. 114,162.80
A. TENAGA
- Pekerja 1.500 Oh x Rp. 75,900.00 = Rp. 113,850.00
- Mandor 0.060 Oh x Rp. 113,850.00 = Rp. 6,831.00
JUMLAH (A) = Rp. 120,681.00
A. TENAGA
- Pekerja 1.200 Oh x Rp. 75,900.00 = Rp. 91,080.00
- Mandor 0.045 Oh x Rp. 113,850.00 = Rp. 5,123.25
JUMLAH (A) = Rp. 96,203.25
A. TENAGA
- Pekerja 0.050 Oh x Rp. 75,900.00 = Rp. 3,795.00
- Mandor 0.005 Oh x Rp. 113,850.00 = Rp. 569.25
JUMLAH (A) = Rp. 4,364.25
A. TENAGA
- Pekerja 0.330 Oh x Rp. 75,900.00 = Rp. 25,047.00
- Mandor 0.010 Oh x Rp. 113,850.00 = Rp. 1,138.50
JUMLAH (A) = Rp. 26,185.50
A. TENAGA
- Pekerja 0.500 Oh x Rp. 75,900.00 = Rp. 37,950.00
- Mandor 0.050 Oh x Rp. 113,850.00 = Rp. 5,692.50
JUMLAH (A) = Rp. 43,642.50
Tanah 1
10. Memadatkan 1 M³ Tanah (per 20 cm)
A. TENAGA
- Pekerja 0.500 Oh x Rp. 75,900.00 = Rp. 37,950.00
- Mandor 0.050 Oh x Rp. 113,850.00 = Rp. 5,692.50
JUMLAH (A) = Rp. 43,642.50
A. TENAGA
- Pekerja 0.300 Oh x Rp. 75,900.00 = Rp. 22,770.00
- Mandor 0.010 Oh x Rp. 113,850.00 = Rp. 1,138.50
JUMLAH (A) = Rp. 23,908.50
B. BAHAN
- Pasir Urug 1.200 Oh x Rp. 145,600.00 = Rp. 174,720.00
JUMLAH (B) = Rp. 174,720.00
A. TENAGA
- Pekerja 0.300 Oh x Rp. 75,900.00 = Rp. 22,770.00
- Mandor 0.010 Oh x Rp. 113,850.00 = Rp. 1,138.50
JUMLAH (A) = Rp. 23,908.50
B. BAHAN
- Tanah Urug 1.200 Oh x Rp. 337,500.00 = Rp. 405,000.00
JUMLAH (B) = Rp. 405,000.00
Tanah 2
HARGA SATUAN PEKERJAAN BEKISTING
A. TENAGA
- Pekerja 0.520 OH x Rp. 115,000.00 = Rp. 59,800.00
- Tukang Kayu 0.260 OH x Rp. 172,500.00 = Rp. 44,850.00
- Kepala Tukang 0.026 OH x Rp. 201,250.00 = Rp. 5,232.50
- Mandor 0.026 OH x Rp. 225,400.00 = Rp. 5,860.40
JUMLAH (A) = Rp. 115,742.90
B. BAHAN
- Kayu Kelas III 0.040 M³ x Rp. 2,000,000.00 = Rp. 80,000.00
- Paku 5-10 cm 0.300 Kg x Rp. 27,255.00 = Rp. 8,176.50
- Minyak Bekisting 0.100 Ltr x Rp. 38,700.00 = Rp. 3,870.00
JUMLAH (B) = Rp. 92,046.50
A. TENAGA
- Pekerja 0.520 OH x Rp. 115,000.00 = Rp. 59,800.00
- Tukang Kayu 0.260 OH x Rp. 172,500.00 = Rp. 44,850.00
- Kepala Tukang 0.026 OH x Rp. 201,250.00 = Rp. 5,232.50
- Mandor 0.026 OH x Rp. 225,400.00 = Rp. 5,860.40
JUMLAH (A) = Rp. 115,742.90
B. BAHAN
- Kayu Kelas III 0.045 M³ x Rp. 2,000,000.00 = Rp. 90,000.00
- Paku 5-10 cm 0.300 Kg x Rp. 27,255.00 = Rp. 8,176.50
- Minyak Bekisting 0.100 Ltr x Rp. 38,700.00 = Rp. 3,870.00
JUMLAH (B) = Rp. 102,046.50
A. TENAGA
- Pekerja 0.660 OH x Rp. 115,000.00 = Rp. 75,900.00
- Tukang Kayu 0.330 OH x Rp. 172,500.00 = Rp. 56,925.00
- Kepala Tukang 0.033 OH x Rp. 201,250.00 = Rp. 6,641.25
- Mandor 0.033 OH x Rp. 225,400.00 = Rp. 7,438.20
JUMLAH (A) = Rp. 146,904.45
B. BAHAN
- Kayu Kelas III 0.040 M³ x Rp. 2,000,000.00 = Rp. 80,000.00
- Paku 5-10 cm 0.400 Kg x Rp. 27,255.00 = Rp. 10,902.00
- Minyak Bekisting 0.200 Ltr x Rp. 38,700.00 = Rp. 7,740.00
- Kayu Kelas II 0.015 M³ x Rp. 2,912,000.00 = Rp. 43,680.00
- Plywood Tebal 9 mm 0.350 Lbr x Rp. 204,585.00 = Rp. 71,604.75
- Dolken Kayu Ø 8-10 cm, Panjang 4 m 2.000 Btg x Rp. 20,800.00 = Rp. 41,600.00
JUMLAH (B) = Rp. 255,526.75
Bekisting 1
4. Pemasangan 1 M² Bekisting Untuk Balok
A. TENAGA
- Pekerja 0.660 OH x Rp. 115,000.00 = Rp. 75,900.00
- Tukang Kayu 0.330 OH x Rp. 172,500.00 = Rp. 56,925.00
- Kepala Tukang 0.033 OH x Rp. 201,250.00 = Rp. 6,641.25
- Mandor 0.033 OH x Rp. 225,400.00 = Rp. 7,438.20
JUMLAH (A) = Rp. 146,904.45
B. BAHAN
- Kayu Kelas III 0.040 M³ x Rp. 2,000,000.00 = Rp. 80,000.00
- Paku 5-10 cm 0.400 Kg x Rp. 27,255.00 = Rp. 10,902.00
- Minyak Bekisting 0.200 Ltr x Rp. 38,700.00 = Rp. 7,740.00
- Kayu Kelas II 0.018 M³ x Rp. 2,912,000.00 = Rp. 52,416.00
- Plywood Tebal 9 mm 0.350 Lbr x Rp. 204,585.00 = Rp. 71,604.75
- Dolken Kayu Ø 8-10 cm, Panjang 4 m 2.000 Btg x Rp. 20,800.00 = Rp. 41,600.00
JUMLAH (B) = Rp. 264,262.75
A. TENAGA
- Pekerja 0.660 OH x Rp. 115,000.00 = Rp. 75,900.00
- Tukang Kayu 0.330 OH x Rp. 172,500.00 = Rp. 56,925.00
- Kepala Tukang 0.033 OH x Rp. 201,250.00 = Rp. 6,641.25
- Mandor 0.033 OH x Rp. 225,400.00 = Rp. 7,438.20
JUMLAH (A) = Rp. 146,904.45
B. BAHAN
- Kayu Kelas III 0.040 M³ x Rp. 2,000,000.00 = Rp. 80,000.00
- Paku 5-10 cm 0.400 Kg x Rp. 27,255.00 = Rp. 10,902.00
- Minyak Bekisting 0.200 Ltr x Rp. 38,700.00 = Rp. 7,740.00
- Kayu Kelas II 0.015 M³ x Rp. 2,912,000.00 = Rp. 43,680.00
- Plywood Tebal 9 mm 0.350 Lbr x Rp. 204,585.00 = Rp. 71,604.75
- Dolken Kayu Ø 8-10 cm, Panjang 4 m 6.000 Btg x Rp. 20,800.00 = Rp. 124,800.00
JUMLAH (B) = Rp. 338,726.75
A. TENAGA
- Pekerja 0.660 OH x Rp. 115,000.00 = Rp. 75,900.00
- Tukang Kayu 0.330 OH x Rp. 172,500.00 = Rp. 56,925.00
- Kepala Tukang 0.033 OH x Rp. 201,250.00 = Rp. 6,641.25
- Mandor 0.033 OH x Rp. 225,400.00 = Rp. 7,438.20
JUMLAH (A) = Rp. 146,904.45
B. BAHAN
- Kayu Kelas III 0.030 M³ x Rp. 2,000,000.00 = Rp. 60,000.00
- Paku 5-10 cm 0.400 Kg x Rp. 27,255.00 = Rp. 10,902.00
- Minyak Bekisting 0.200 Ltr x Rp. 38,700.00 = Rp. 7,740.00
- Kayu Kelas II 0.020 M³ x Rp. 2,912,000.00 = Rp. 58,240.00
- Plywood Tebal 9 mm 0.350 Lbr x Rp. 204,585.00 = Rp. 71,604.75
- Dolken Kayu Ø 8-10 cm, Panjang 4 m 3.000 Btg x Rp. 20,800.00 = Rp. 62,400.00
Bekisting 2
- Penjaga Jarak Bekisting/Spacer 4.000 Bh x Rp. 15,000.00 = Rp. 60,000.00
JUMLAH (B) = Rp. 270,886.75
A. TENAGA
- Pekerja 0.660 OH x Rp. 115,000.00 = Rp. 75,900.00
- Tukang Kayu 0.330 OH x Rp. 172,500.00 = Rp. 56,925.00
- Kepala Tukang 0.033 OH x Rp. 201,250.00 = Rp. 6,641.25
- Mandor 0.033 OH x Rp. 225,400.00 = Rp. 7,438.20
JUMLAH (A) = Rp. 146,904.45
B. BAHAN
- Kayu Kelas III 0.030 M³ x Rp. 2,000,000.00 = Rp. 60,000.00
- Paku 5-10 cm 0.400 Kg x Rp. 27,255.00 = Rp. 10,902.00
- Minyak Bekisting 0.150 Ltr x Rp. 38,700.00 = Rp. 5,805.00
- Kayu Kelas II 0.015 M³ x Rp. 2,912,000.00 = Rp. 43,680.00
- Plywood Tebal 9 mm 0.350 Lbr x Rp. 204,585.00 = Rp. 71,604.75
- Dolken Kayu Ø 8-10 cm, Panjang 4 m 2.000 Btg x Rp. 20,800.00 = Rp. 41,600.00
JUMLAH (B) = Rp. 233,591.75
A. TENAGA
- Pekerja 0.660 OH x Rp. 115,000.00 = Rp. 75,900.00
- Tukang Kayu 0.330 OH x Rp. 172,500.00 = Rp. 56,925.00
- Kepala Tukang 0.033 OH x Rp. 201,250.00 = Rp. 6,641.25
- Mandor 0.033 OH x Rp. 225,400.00 = Rp. 7,438.20
JUMLAH (A) = Rp. 146,904.45
B. BAHAN
- Kayu Kelas III 0.020 M³ x Rp. 2,000,000.00 = Rp. 40,000.00
- Paku 5-10 cm 0.400 Kg x Rp. 27,255.00 = Rp. 10,902.00
- Minyak Bekisting 0.200 Ltr x Rp. 38,700.00 = Rp. 7,740.00
- Kayu Kelas III 0.018 M³ x Rp. 2,000,000.00 = Rp. 36,000.00
- Plywood Tebal 9 mm 0.350 Lbr x Rp. 204,585.00 = Rp. 71,604.75
- Dolken Kayu Ø 8-10 cm, Panjang 4 m 0.500 Btg x Rp. 20,800.00 = Rp. 10,400.00
- Penjaga Jarak Bekisting/Spacer 2.000 Bh x Rp. 15,000.00 = Rp. 30,000.00
JUMLAH (B) = Rp. 206,646.75
Bekisting 3
HARGA SATUAN PEKERJAAN DINDING
1. Pemasangan 1 M² Dinding Bata Semen Press (8x11x22) cm, Tebal ½ Bata, Camp. 1SP : 2PP
A. TENAGA
- Pekerja 0.300 Oh x Rp. 115,000.00 = Rp. 34,500.00
- Tukang Batu 0.100 Oh x Rp. 172,500.00 = Rp. 17,250.00
- Kepala Tukang 0.010 Oh x Rp. 201,250.00 = Rp. 2,012.50
- Mandor 0.015 Oh x Rp. 225,400.00 = Rp. 3,381.00
JUMLAH (A) = Rp. 57,143.50
B. BAHAN
- Bata Semen Press 30.000 Bh x Rp. 2,070.00 = Rp. 62,100.00
- Semen Portland 18.950 Kg x Rp. 2,679.50 = Rp. 50,776.53
- Pasir pasang 0.038 M3 x Rp. 208,000.00 = Rp. 7,904.00
JUMLAH (B) = Rp. 120,780.53
2. Pemasangan 1 M² Dinding Bata Semen Press (8x11x22) cm, Tebal ½ Bata, Camp. 1SP : 3PP
A. TENAGA
- Pekerja 0.300 Oh x Rp. 115,000.00 = Rp. 34,500.00
- Tukang Batu 0.100 Oh x Rp. 172,500.00 = Rp. 17,250.00
- Kepala Tukang 0.010 Oh x Rp. 201,250.00 = Rp. 2,012.50
- Mandor 0.015 Oh x Rp. 225,400.00 = Rp. 3,381.00
JUMLAH (A) = Rp. 57,143.50
B. BAHAN
- Bata Semen Press 30.000 Bh x Rp. 2,070.00 = Rp. 62,100.00
- Semen Portland 14.370 Kg x Rp. 2,679.50 = Rp. 38,504.42
- Pasir pasang 0.040 M3 x Rp. 208,000.00 = Rp. 8,320.00
JUMLAH (B) = Rp. 108,924.42
3. Pemasangan 1 M² Dinding Bata Semen Press (8x11x22) cm, Tebal ½ Bata, Camp. 1SP : 4PP
A. TENAGA
- Pekerja 0.300 Oh x Rp. 115,000.00 = Rp. 34,500.00
- Tukang Batu 0.100 Oh x Rp. 172,500.00 = Rp. 17,250.00
- Kepala Tukang 0.010 Oh x Rp. 201,250.00 = Rp. 2,012.50
- Mandor 0.015 Oh x Rp. 225,400.00 = Rp. 3,381.00
JUMLAH (A) = Rp. 57,143.50
B. BAHAN
- Bata Semen Press 30.000 Bh x Rp. 2,070.00 = Rp. 62,100.00
- Semen Portland 11.500 Kg x Rp. 2,679.50 = Rp. 30,814.25
- Pasir pasang 0.043 M3 x Rp. 208,000.00 = Rp. 8,944.00
JUMLAH (B) = Rp. 101,858.25
4. Pemasangan 1 M² Dinding Bata Semen Press (8x11x22) cm, Tebal ½ Bata, Camp. 1SP : 5PP
A. TENAGA
- Pekerja 0.300 Oh x Rp. 115,000.00 = Rp. 34,500.00
- Tukang Batu 0.100 Oh x Rp. 172,500.00 = Rp. 17,250.00
Dinding 1
- Kepala Tukang 0.010 Oh x Rp. 201,250.00 = Rp. 2,012.50
- Mandor 0.015 Oh x Rp. 225,400.00 = Rp. 3,381.00
JUMLAH (A) = Rp. 57,143.50
B. BAHAN
Dinding 2
HARGA SATUAN PEKERJAAN PLESTERAN
Plester 1
- Pasir Pasang 0.026 M3 x Rp. 208,000.00 = Rp. 5,408.00
JUMLAH (B) = Rp. 19,298.53
Plester 2
8. Pemasangan 1 M¹ Plesteran Skoning 1SP : 3PP Lebar 10 cm
A. TENAGA
- Pekerja 0.080 OH x Rp. 115,000.00 = Rp. 9,200.00
- Tukang Batu 0.400 OH x Rp. 172,500.00 = Rp. 69,000.00
- Kepala Tukang 0.040 OH x Rp. 201,250.00 = Rp. 8,050.00
- Mandor 0.004 OH x Rp. 225,400.00 = Rp. 901.60
JUMLAH (A) = Rp. 87,151.60
B. BAHAN
- Semen Portland 0.500 Kg x Rp. 2,679.50 = Rp. 1,339.75
- Pasir Pasang 0.013 M3 x Rp. 208,000.00 = Rp. 2,704.00
JUMLAH (B) = Rp. 4,043.75
9. Pemasangan 1 M² Acian
A. TENAGA
- Pekerja 0.200 OH x Rp. 115,000.00 = Rp. 23,000.00
- Tukang Batu 0.100 OH x Rp. 172,500.00 = Rp. 17,250.00
- Kepala Tukang 0.010 OH x Rp. 201,250.00 = Rp. 2,012.50
- Mandor 0.010 OH x Rp. 225,400.00 = Rp. 2,254.00
JUMLAH (A) = Rp. 44,516.50
B. BAHAN
- Semen Portland 3.250 Kg x Rp. 2,679.50 = Rp. 8,708.38
JUMLAH (B) = Rp. 8,708.38
Plester 3
Plester 4
HARGA SATUAN PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING
A. TENAGA
- Pekerja 0.700 OH x Rp. 115,000.00 = Rp. 80,500.00
- Tukang Batu 0.350 OH x Rp. 172,500.00 = Rp. 60,375.00
- Kepala Tukang 0.035 OH x Rp. 201,250.00 = Rp. 7,043.75
- Mandor 0.035 OH x Rp. 225,400.00 = Rp. 7,889.00
JUMLAH (A) = Rp. 155,807.75
B. BAHAN
- Keramik 25 x 25 cm 1.050 Dos x Rp. 89,700.00 = Rp. 94,185.00
- Semen Portland 10.400 Kg x Rp. 2,679.50 = Rp. 27,866.80
- Pasir Pasang 0.045 M3 x Rp. 208,000.00 = Rp. 9,360.00
- Semen Warna 0.500 Kg x Rp. 30,245.00 = Rp. 15,122.50
JUMLAH (B) = Rp. 146,534.30
A. TENAGA
- Pekerja 0.700 OH x Rp. 115,000.00 = Rp. 80,500.00
- Tukang Batu 0.350 OH x Rp. 172,500.00 = Rp. 60,375.00
- Kepala Tukang 0.035 OH x Rp. 201,250.00 = Rp. 7,043.75
- Mandor 0.035 OH x Rp. 225,400.00 = Rp. 7,889.00
JUMLAH (A) = Rp. 155,807.75
B. BAHAN
- Keramik 30 x 30 cm 1.050 Dos x Rp. 109,637.55 = Rp. 115,119.43
- Semen Portland 10.000 Kg x Rp. 2,679.50 = Rp. 26,795.00
- Pasir Pasang 0.045 M3 x Rp. 208,000.00 = Rp. 9,360.00
- Semen Warna 0.500 Kg x Rp. 30,245.00 = Rp. 15,122.50
JUMLAH (B) = Rp. 166,396.93
A. TENAGA
- Pekerja 0.700 OH x Rp. 115,000.00 = Rp. 80,500.00
- Tukang Batu 0.350 OH x Rp. 172,500.00 = Rp. 60,375.00
- Kepala Tukang 0.035 OH x Rp. 201,250.00 = Rp. 7,043.75
- Mandor 0.035 OH x Rp. 225,400.00 = Rp. 7,889.00
JUMLAH (A) = Rp. 155,807.75
B. BAHAN
- Keramik 40 x 40 cm 1.050 Dos x Rp. 133,939.93 = Rp. 140,636.92
- Semen Portland 10.000 Kg x Rp. 2,679.50 = Rp. 26,795.00
- Pasir Pasang 0.045 M
3
x Rp. 208,000.00 = Rp. 9,360.00
- Semen Warna 0.500 Kg x Rp. 30,245.00 = Rp. 15,122.50
JUMLAH (B) = Rp. 191,914.42
Lantai 1
4. Pemasangan 1 M² Lantai Keramik 50 cm x 50 cm
A. TENAGA
- Pekerja 0.700 OH x Rp. 115,000.00 = Rp. 80,500.00
- Tukang Batu 0.350 OH x Rp. 172,500.00 = Rp. 60,375.00
- Kepala Tukang 0.035 OH x Rp. 201,250.00 = Rp. 7,043.75
- Mandor 0.035 OH x Rp. 225,400.00 = Rp. 7,889.00
JUMLAH (A) = Rp. 155,807.75
B. BAHAN
- Keramik 50 x 50 cm 1.050 Dos x Rp. 166,290.00 = Rp. 174,604.50
- Semen Portland 10.000 Kg x Rp. 2,679.50 = Rp. 26,795.00
- Pasir Pasang 0.045 M3 x Rp. 208,000.00 = Rp. 9,360.00
- Semen Warna 0.500 Kg x Rp. 30,245.00 = Rp. 15,122.50
JUMLAH (B) = Rp. 225,882.00
A. TENAGA
- Pekerja 0.250 OH x Rp. 115,000.00 = Rp. 28,750.00
- Tukang Batu 0.130 OH x Rp. 172,500.00 = Rp. 22,425.00
- Kepala Tukang 0.013 OH x Rp. 201,250.00 = Rp. 2,616.25
- Mandor 0.013 OH x Rp. 225,400.00 = Rp. 2,930.20
JUMLAH (A) = Rp. 56,721.45
B. BAHAN
- Granit 60 x 60 3.100 bh x Rp. 74,175.00 = Rp. 229,942.50
- Semen Portland 9.600 Kg x Rp. 2,679.50 = Rp. 25,723.20
- Pasir Pasang 0.045 M
3
x Rp. 208,000.00 = Rp. 9,360.00
- Semen Warna 1.500 Kg x Rp. 30,245.00 = Rp. 45,367.50
JUMLAH (B) = Rp. 310,393.20
A. TENAGA
- Pekerja 0.900 OH x Rp. 115,000.00 = Rp. 103,500.00
- Tukang Batu 0.450 OH x Rp. 172,500.00 = Rp. 77,625.00
- Kepala Tukang 0.045 OH x Rp. 201,250.00 = Rp. 9,056.25
- Mandor 0.045 OH x Rp. 225,400.00 = Rp. 10,143.00
JUMLAH (A) = Rp. 200,324.25
B. BAHAN
- Keramik 25x 50 cm 1.050 Dos x Rp. 112,875.26 = Rp. 118,519.02
- Semen Portland 9.300 Kg x Rp. 2,679.50 = Rp. 24,919.35
- Pasir Pasang 0.018 M3 x Rp. 208,000.00 = Rp. 3,744.00
JUMLAH (B) = Rp. 147,182.37
A. TENAGA
Lantai 2
- Pekerja 0.060 OH x Rp. 115,000.00 = Rp. 6,900.00
- Tukang Batu 0.030 OH x Rp. 172,500.00 = Rp. 5,175.00
- Kepala Tukang 0.003 OH x Rp. 201,250.00 = Rp. 532.72
- Mandor 0.003 OH x Rp. 225,400.00 = Rp. 596.65
JUMLAH (A) = Rp. 13,204.37
B. BAHAN
A. TENAGA
- Pekerja 0.350 OH x Rp. 115,000.00 = Rp. 40,250.00
- Tukang Batu 0.175 OH x Rp. 172,500.00 = Rp. 30,187.50
- Kepala Tukang 0.017 OH x Rp. 201,250.00 = Rp. 3,421.25
- Mandor 0.002 OH x Rp. 225,400.00 = Rp. 450.80
JUMLAH (A) = Rp. 74,309.55
B. BAHAN
- Wallpaper 2.200 M x Rp. 15,000.00 = Rp. 33,000.00
- Lem 0.250 Kg x Rp. 125,000.00 = Rp. 31,250.00
JUMLAH (B) = Rp. 64,250.00
A. TENAGA
- Pekerja 0.250 OH x Rp. 115,000.00 = Rp. 28,750.00
- Tukang Batu 0.500 OH x Rp. 172,500.00 = Rp. 86,250.00
- Kepala Tukang 0.050 OH x Rp. 201,250.00 = Rp. 10,062.50
- Mandor 0.001 OH x Rp. 225,400.00 = Rp. 293.02
JUMLAH (A) = Rp. 125,355.52
B. BAHAN
- Batu Alam ( Palimanan ) 1.050 Ikat x Rp. 358,225.00 = Rp. 376,136.25
Semen Portland 9.300 Kg x Rp. 2,679.50 = Rp. 24,919.35
- Pasir Pasang 0.018 M3 x Rp. 208,000.00 = Rp. 3,744.00
JUMLAH (B) = Rp. 404,799.60
Lantai 3
8. Pemasangan 1 M² Paving Blok Natural
A. TENAGA
- Pekerja 0.250 OH x Rp. 115,000.00 = Rp. 28,750.00
- Tukang Batu 0.500 OH x Rp. 172,500.00 = Rp. 86,250.00
- Kepala Tukang 0.050 OH x Rp. 201,250.00 = Rp. 10,062.50
- Mandor 0.001 OH x Rp. 225,400.00 = Rp. 293.02
JUMLAH (A) = Rp. 125,355.52
B. BAHAN
- Paving Block 6 Cm 44.000 Bh x Rp. 7,006.72 = Rp. 308,295.68
- Pasir Beton 0.050 M3 x Rp. 208,000.00 = Rp. 10,400.00
JUMLAH (B) = Rp. 318,695.68
A. TENAGA
- Pekerja 0.250 OH x Rp. 115,000.00 = Rp. 28,750.00
- Tukang Batu 0.500 OH x Rp. 172,500.00 = Rp. 86,250.00
- Kepala Tukang 0.050 OH x Rp. 201,250.00 = Rp. 10,062.50
- Mandor 0.001 OH x Rp. 225,400.00 = Rp. 293.02
JUMLAH (A) = Rp. 125,355.52
B. BAHAN
- Papan GRC Motif 1.050 Ikat x Rp. 750,000.00 = Rp. 787,500.00
Semen Portland 9.300 Kg x Rp. 2,679.50 = Rp. 24,919.35
- Pasir Pasang 0.018 M3 x Rp. 208,000.00 = Rp. 3,744.00
JUMLAH (B) = Rp. 816,163.35
Lantai 4
HARGA SATUAN PEKERJAAN PENGECATAN
A. TENAGA
- Pekerja 0.150 OH x Rp. 75,900.00 = Rp. 11,385.00
- Mandor 0.003 OH x Rp. 113,850.00 = Rp. 341.55
JUMLAH (A) = Rp. 11,726.55
B. BAHAN
- Soda Api 0.040 Kg x Rp. = Rp. -
JUMLAH (B) = Rp. -
A. TENAGA
- Pekerja 0.150 OH x Rp. 75,900.00 = Rp. 11,385.00
- Mandor 0.003 OH x Rp. 113,850.00 = Rp. 341.55
JUMLAH (A) = Rp. 11,726.55
B. BAHAN
- Sabun 0.040 Kg x Rp. 5,000.00 = Rp. 200.00
JUMLAH (B) = Rp. 200.00
3. Pengecatan 1 M² Bidang Kayu Baru (1 lapis plamur, 1 lapis cat dasar, 2 lapis cat penutup)
A. TENAGA
- Pekerja 0.070 OH x Rp. 115,000.00 = Rp. 8,050.00
- Tukang Cat 0.009 OH x Rp. 172,500.00 = Rp. 1,552.50
- Kepala Tukang 0.006 OH x Rp. 201,250.00 = Rp. 1,207.50
- Mandor 0.003 OH x Rp. 225,400.00 = Rp. 676.20
JUMLAH (A) = Rp. 11,486.20
B. BAHAN
- Cat Menie 0.200 Kg x Rp. 46,230.00 = Rp. 9,246.00
- Plamuur 0.150 Kg x Rp. 3,000.00 = Rp. 450.00
- Cat Dasar 0.170 Kg x Rp. 86,940.00 = Rp. 14,779.80
- Cat Penutup 0.260 Kg x Rp. 86,940.00 = Rp. 22,604.40
- Kuas 0.010 Bh x Rp. 30,590.00 = Rp. 305.90
- Pengencer 0.030 L x Rp. 56,925.00 = Rp. 1,707.75
- Ampelas 0.200 Lbr x Rp. 13,685.00 = Rp. 2,737.00
JUMLAH (B) = Rp. 51,830.85
4. Pengecatan 1 M² Bidang Kayu Baru (1 lapis plamur, 1 lapis cat dasar, 3 lapis cat penutup)
A. TENAGA
- Pekerja 0.070 OH x Rp. 115,000.00 = Rp. 8,050.00
- Tukang Cat 0.105 OH x Rp. 172,500.00 = Rp. 18,112.50
- Kepala Tukang 0.004 OH x Rp. 201,250.00 = Rp. 805.00
- Mandor 0.003 OH x Rp. 225,400.00 = Rp. 676.20
Cat 1
JUMLAH (A) = Rp. 27,643.70
B. BAHAN
- Cat Menie 0.200 Kg x Rp. 46,230.00 = Rp. 9,246.00
- Plamuur 0.150 Kg x Rp. 3,000.00 = Rp. 450.00
- Cat Dasar 0.170 Kg x Rp. 86,940.00 = Rp. 14,779.80
- Cat Penutup 0.350 Kg x Rp. 86,940.00 = Rp. 30,429.00
5. Pengecatan 1 M² Bidang Tembok Baru (1 lapis plamur, 1 lapis cat dasar, 2 lapis cat penutup)
A. TENAGA
- Pekerja 0.020 OH x Rp. 115,000.00 = Rp. 2,300.00
- Tukang Cat 0.036 OH x Rp. 172,500.00 = Rp. 6,210.00
- Kepala Tukang 0.0063 OH x Rp. 201,250.00 = Rp. 1,267.88
- Mandor 0.003 OH x Rp. 225,400.00 = Rp. 676.20
JUMLAH (A) = Rp. 10,454.08
B. BAHAN
- Plamuur 0.100 Kg x Rp. 3,000.00 = Rp. 300.00
- Cat Dasar 0.100 Kg x Rp. 105,225.00 = Rp. 10,522.50
- Cat Penutup 0.260 Kg x Rp. 171,925.00 = Rp. 44,700.50
- Kuas Roll 0.010 Bh x Rp. 46,345.00 = Rp. 463.45
JUMLAH (B) = Rp. 55,986.45
6. Pengecatan 1 M² Bidang Tembok Lama (1 lapis cat dasar, 2 lapis cat penutup)
A. TENAGA
- Pekerja 0.028 OH x Rp. 115,000.00 = Rp. 3,220.00
- Tukang Cat 0.042 OH x Rp. 172,500.00 = Rp. 7,245.00
- Kepala Tukang 0.0042 OH x Rp. 201,250.00 = Rp. 845.25
- Mandor 0.003 OH x Rp. 225,400.00 = Rp. 676.20
JUMLAH (A) = Rp. 11,986.45
B. BAHAN
- Cat Dasar 0.120 Kg x Rp. 105,225.00 = Rp. 12,627.00
- Cat Penutup 0.180 Kg x Rp. 171,925.00 = Rp. 30,946.50
- Kuas Roll 0.010 Bh x Rp. 46,345.00 = Rp. 463.45
JUMLAH (B) = Rp. 44,036.95
Cat 2
7. Pengecatan 1 M² Plavon (1 lapis cat dasar, 2 lapis cat penutup)
A. TENAGA
- Pekerja 0.020 OH x Rp. 115,000.00 = Rp. 2,300.00
- Tukang Cat 0.036 OH x Rp. 172,500.00 = Rp. 6,210.00
- Kepala Tukang 0.0063 OH x Rp. 201,250.00 = Rp. 1,267.88
- Mandor 0.003 OH x Rp. 225,400.00 = Rp. 676.20
JUMLAH (A) = Rp. 10,454.08
B. BAHAN
- Plamuur 0.100 Kg x Rp. 3,000.00 = Rp. 300.00
- Cat Dasar 0.100 Kg x Rp. 105,225.00 = Rp. 10,522.50
- Cat Penutup 0.260 Kg x Rp. 171,925.00 = Rp. 44,700.50
- Kuas Roll 0.010 Bh x Rp. 46,345.00 = Rp. 463.45
7. Pemasangan 1 M² Wallpaper
A. TENAGA
- Pekerja 0.020 OH x Rp. 115,000.00 = Rp. 2,300.00
- Tukang Cat 0.200 OH x Rp. 172,500.00 = Rp. 34,500.00
- Kepala Tukang 0.020 OH x Rp. 201,250.00 = Rp. 4,025.00
- Mandor 0.0025 OH x Rp. 225,400.00 = Rp. 563.50
JUMLAH (A) = Rp. 41,388.50
B. BAHAN
- Wallpaper 1.200 M² x Rp. = Rp. -
- Lem 0.200 Kg x Rp. = Rp. -
JUMLAH (B) = Rp. -
Cat 3
7. Pengacatan 1 M² Permukaan Baja Dengan Menie Besi
A. TENAGA
- Pekerja 0.020 OH x Rp. 115,000.00 = Rp. 2,300.00
- Tukang Cat 0.200 OH x Rp. 172,500.00 = Rp. 34,500.00
- Kepala Tukang 0.020 OH x Rp. 201,250.00 = Rp. 4,025.00
- Mandor 0.0025 OH x Rp. 225,400.00 = Rp. 563.50
JUMLAH (A) = Rp. 41,388.50
B. BAHAN
- Menie Besi 0.100 Kg x Rp. 64,975.00 = Rp. 6,497.50
- Kwas 0.010 Bh x Rp. 146,510.00 = Rp. 1,465.10
JUMLAH (B) = Rp. 7,962.60
A. TENAGA
- Pekerja 0.400 OH x Rp. 115,000.00 = Rp. 46,000.00
- Tukang Cat 0.800 OH x Rp. 172,500.00 = Rp. 138,000.00
- Kepala Tukang 0.080 OH x Rp. 201,250.00 = Rp. 16,100.00
- Mandor 0.020 OH x Rp. 225,400.00 = Rp. 4,508.00
JUMLAH (A) = Rp. 204,608.00
B. BAHAN
- Cat Dasar 0.110 Kg x Rp. 51,175.00 = Rp. 5,629.25
- Cat Antara 0.170 Kg x Rp. 86,940.00 = Rp. 14,779.80
- Cat Penutup 0.080 Kg x Rp. 74,060.00 = Rp. 5,924.80
- Kwas 0.010 Bh x Rp. 30,590.00 = Rp. 305.90
- Pengencer 0.010 L x Rp. 56,925.00 = Rp. 569.25
JUMLAH (B) = Rp. 27,209.00
Cat 5
HARGA SATUAN PEKERJAAN ELEKTRIKAL
Listrik 1
- Mandor 0.014 Oh x Rp. 225,400.00 = Rp. 3,155.60
JUMLAH (A) = Rp. 13,683.85
B. BAHAN
- Mangkok Instalasi 1.00 Bh x Rp. 18,000.00 = Rp. 18,000.00
- Stop kontak 1.00 Bh x Rp. 25,300.00 = Rp. 25,300.00
- Perlengkapan instalasi 5.00 % x Rp. 1,265.00 = Rp. 1,265.00
Listrik 2
6. Memasang TL 30 Watt
A. TENAGA
- Pekerja 0.010 Oh x Rp. 115,000.00 = Rp. 1,150.00
- Tukang Batu 0.010 Oh x Rp. 172,500.00 = Rp. 1,725.00
- Kepala Tukang 0.001 Oh x Rp. 201,250.00 = Rp. 201.25
- Mandor 0.001 Oh x Rp. 225,400.00 = Rp. 225.40
JUMLAH (A) = Rp. 3,301.65
B. BAHAN
- Box Lampu TL 2 Groub 1.00 Bh x Rp. 150,000.00 = Rp. 150,000.00
- Lampu TL 30 w 2.00 Bh x Rp. 275,000.00 = Rp. 550,000.00
- Perlengkapan instalasi 5.00 % x Rp. 13,750.00 = Rp. 27,500.00
JUMLAH (B) = Rp. 727,500.00
Listrik 3
9. Memasang MCB 6 Ampere
A. TENAGA
- Pekerja 0.025 Oh x Rp. 115,000.00 = Rp. 2,875.00
- Tukang Batu 0.025 Oh x Rp. 172,500.00 = Rp. 4,312.50
- Kepala Tukang 0.017 Oh x Rp. 201,250.00 = Rp. 3,340.75
- Mandor 0.014 Oh x Rp. 225,400.00 = Rp. 3,155.60
JUMLAH (A) = Rp. 13,683.85
B. BAHAN
- MCB 6 Ampere 1.00 Bh x Rp. 75,900.00 = Rp. 75,900.00
- Perlengkapan instalasi 5.00 % x Rp. 3,795.00 = Rp. 3,795.00
JUMLAH (B) = Rp. 79,695.00
Listrik 5
JUMLAH (A) + (B) = Rp. 583,843.50
Listrik 7
ANALISA HARGA SATUAN PEKERJAAN (AHSP)
Permen PUPR no.28 /2016 Pekerjaan Pembuatan lantai kerja mutu f'c = 7,4 mpa ; K-100/ 1 m3
hal.583 NO. URAIAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA
A TENAGA
Pekerja Oh 1.2000 115,000.00 138,000.00
Tukang batu Oh 0.2000 172,500.00 34,500.00
Kepala tukang Oh 0.0200 201,250.00 4,025.00
Mandor Oh 0.0600 225,400.00 13,524.00
B BAHAN
Semen portland (PC) kg 230.0000 2,679.50 616,285.00
Pasir beton m3 0.6379 208,000.00 132,674.29
Kerikil m3 0.7607 686,400.00 522,172.44
Air ltr 200.0000 150.00 30,000.00
C PERALATAN
B BAHAN
Besi beton Wiremesh kg 1.0200 17,250.00 17,595.00
Kawat beton kg 0.0050 30,935.00 154.68
C PERALATAN
B BAHAN
Kayu kelas III m3 0.0450 2,000,000.00 90,000.00
Paku biasa 2"-3" kg 0.3000 27,255.00 8,176.50
Minyak bekisting ltr 0.1000 38,700.00 3,870.00
C PERALATAN
B BAHAN
Semen portland (PC) kg 413.0000 2,679.50 1,106,633.50
Pasir beton m3 0.4864 208,000.00 101,177.14
Kerikil m3 0.7563 686,400.00 519,121.78
Air ltr 215.0000 150.00 32,250.00
C PERALATAN
B BAHAN
Pasir pasang m3 1.2000 208,000.00 249,600.00
C PERALATAN
Permen PUPR no.28 /2016 Pekerjaan Timbunan dan Pemadatan Tanah biasa/ m3
hal.507 NO. URAIAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA
A TENAGA
Pekerja Oh 0.0085 115,000.00 977.50
Mandor Oh 0.0012 225,400.00 273.70
B BAHAN
Timbunan Tanah biasa m3 1.2586 120,000.00 151,032.00
C PERALATAN
Excavator jam 0.0085 415,000.00 3,527.50
Dumptruck jam 0.5043 181,500.00 91,530.45
Motor Grader jam 0.0043 415,000.00 1,784.50
Vibro Roller jam 0.0134 400,000.00 5,360.00
Water tank jam 0.0141 165,000.00 2,326.50
B BAHAN
Timbunan Sirtu m3 1.2586 150,000.00 188,790.00
C PERALATAN
Excavator jam 0.0085 415,000.00 3,527.50
Dumptruck jam 0.5043 181,500.00 91,530.45
Motor Grader jam 0.0043 415,000.00 1,784.50
Vibro Roller jam 0.0134 400,000.00 5,360.00
Water tank jam 0.0141 165,000.00 2,326.50
B BAHAN
C PERALATAN
Vibro Roller jam 0.0244 400,000.00 9,760.00