Please read Render’s book Quantitative Analysis for Management, 13th ed., Chapter 9 on
Transportation, Assignment, and Network Models.
Solve the following problem using QM.
In a job shop operation, four jobs may be performed on any of four machines. The hours required for
each job on each machine are presented in the following table. The plant supervisor would like to
assign jobs so that total time is minimized. Find the best solution. Which assignments should be
made?
Solusi optimal dapat dilihat pada window “Assignment Results”. Solusi optimal adalah sebagai
berikut:
• Job A12 ditugaskan ke mesin W, memerlukan waktu 10 jam
• Job A15 ditugaskan ke mesin Z, memerlukan waktu 12 jam
• Job B2 ditugaskan ke mesin Y, memerlukan 12 jam
• Job B9 ditugaskan ke mesin X, memerlukan waktu 16 jam
Total waktu yang diperlukan adalah 50 jam.