CADANGAN MEMBINA DAN MENYIAPKAN RUMAH DI BAWAH PROGRAM PERUMAHAN RAKYAT TERMISKIN (PPRT)

Kadar
Anggaran Amaun
Bil. Huraian Item Unit Harga No. Helaian Progres (%)
Kuantiti (RM)
(RM)
Minggu 1 Minggu 2 Minggu 3 Minggu 4

11hb – 16hb 17hb - 22hb 23hb - 28hb 29hb – 5hb


MEMANCANG TANDA (SETTING
1 L/S 1.00 S01/S02/S03
OUT)
2 MENDIRIKAN PANCANG TANDA L/S 1.00 S01/S02/S03

3 ASAS DAN STUMP L/S 1.00 S01/S02/S03

4 RASUK BAWAH (GROUND BEAM) L/S 1.00 S04/S05

5 LANTAI (SLAB) L/S 1.00 S08

6 TIANG (COLUMN) L/S 1.00 S03

7 RASUK BUMBUNG (ROOF BEAM) L/S 1.00 S06/S07

PEMASANGAN KEKUDA BUMBUNG


8 L/S A02/A03
(ROOF TRUSSES)

PEMASANGAN BUMBUNG DAN


9 L/S A02/A03
RABUNG

10 PEMASANGAN POLYTANK L/S A02/A03/A09

PEMASANGAN FASCIA
11 L/S A02/A03/A09
BOARD/FIBRE CEMENT BOARD
MENDIRIKAN KERANGKA PINTU
12 L/S A10
(DOOR) FRAME)

13 DINDING L/S A01/A04

PEMASANGAN BINGKAI TINGKAP


14 L/S A11
(WINDOW FRAME)

15 PEMBINAAN LANTAI KONKRIT L/S A08/A09

16 KERJA – KERJA MELEPA DINDING L/S A01/A04

17 PEMASANGAN SILING L/S A03/A08

1
CADANGAN MEMBINA DAN MENYIAPKAN RUMAH DI BAWAH PROGRAM PERUMAHAN RAKYAT TERMISKIN (PPRT)

Kadar
Anggaran Amaun
Bil. Huraian Item Unit Harga No. Helaian Progres (%)
Kuantiti (RM)
(RM)
Minggu 1 Minggu 2 Minggu 3 Minggu 4

11hb – 16hb 17hb - 22hb 23hb - 28hb 29hb – 5hb


PEMASANGAN ROOF INSULATION
18 DAN ALUMINIUM FOIL BUBBLE L/S A02/A03
PACK
19 KERJA - KERJA ELEKTRIK L/S E01
M01/M02/M03
20 PEMASANGAN SISTEM PAIP AIR L/S
M04M05
PEMASANGAN GUTTER DAN PVC
21 L/S A04
RAIN CHAIN
22 PEMASANGAN JUBIN LANTAI L/S A08

23 PEMBINAAN KAKI LIMA (APRON) L/S A01/A02


PEMASANGAN PINTU, TINGKAP
23 L/S A10/A11
DAN KERJA-KERJA MENGECAT
*Sila rujuk drawing yang telah dilampirkan