PEKERJA 11,715,000.00
MATERIAL JUMLAH VOLUME KODE Harga Biaya Sub Total
SATUAN (Rp./unit) (Rp.) (Rp.)
PERALATAN 7,559,291.82
TOTAL (Rp.) 131,184,291.82
PEKERJA 585,000.00
M A T E R I A L Jumlah Satuan Kode Harga Biaya Sub Total
(Rp./unit) (Rp.) (Rp.)
MATERIAL 38,635,000.00
P E R A L A T A N Jumlah Hari Kode Jam Harga Biaya Sub Total
Alat Kerja Kerja (Rp./jam) (Rp.) (Rp.)
1 Mesin gilas 3 roda 8-10 T 1.00 1.00 E.080 5.00 234,011.66 1,170,058.32
2 Truk tangki air 68 HP 1.00 1.00 E.182 5.00 298,760.02 1,493,800.12
3 Motor Grader 110 HP 1.00 1.00 E.010 5.00 481,882.95 2,409,414.74
PERALATAN 5,073,273.18
TOTAL (Rp.) 44,293,273.18
PEKERJA 1,285,000.00
MATERIAL TOTAL VOLUME KODE Harga Biaya Sub Total
VOL SATUAN (Rp./unit) (Rp.) (Rp.)
MATERIAL 115,640,000.00
P E R A L A T A N Jumlah Hari Kode Jam Harga Biaya Sub Total
Alat Kerja Kerja (Rp./jam) (Rp.) (Rp.)
1 Mesin gilas tandem 6-10 T 1.00 1.00 E.081 5.00 249,493.45 1,247,467.27
2 Dump Truck ( 3,5 ton/44Hp) 1.00 1.00 E.211 5.00 254,459.33 1,272,296.67
PERALATAN 2,519,763.94
TOTAL (Rp.) 119,444,763.94