a b c d e=bxd f
1 . BAHAN
1 . 1 Pipa PVC AW 4" (Casing) 10 btg 175,000 Rp 1,750,000
1 . 2 Pipa PVC AW 1 (inlet) 10 btg 46,000 Rp 460,000
1 . 3 Pipa PVC AW 1 (outlet) 2 btg 60,000 Rp 120,000
1 . 4 Pipa PVC AW 1" (distribusi) 2 btg 50,000 Rp 100,000
1 . 5 Pipa PVC AW 1 " (distribusi) 2 btg 50,000 Rp 100,000
1 . 6 Sock Draft Luar (SDL) 1 " 6 bh 8,000 Rp 48,000
1 . 7 Sock Draft Dlm (SDD) 1 1/4 " 6 bh 9,000 Rp 54,000
1 . 8 Sock Draft Luar (SDL) 1" 2 bh 8,000 Rp 16,000
1 . 9 Over Sock 1" 2 bh 7,000 Rp 14,000
1 . 10 Tee 3/4" 2 bh 8,000 Rp 16,000
1 . 11 Tee Draft Dalam 1 7 bh 8,000 Rp 56,000
1 . 12 SDL 3/4" - Dalam 1/2" 7 bh 7,000 Rp 49,000
1 . 13 Kran air besi 1/2" 7 bh 50,000 Rp 350,000
1 . 14 Knee 1 " 5 bh 10,000 Rp 50,000
1 . 15 Knee 3/4" 2 bh 6,000 Rp 12,000
1 . 16 Knee 1/2" 2 bh 6,000 Rp 12,000
1 . 17 Dop PVC 4" 2 bh 30,000 Rp 60,000
1 . 18 Dop Draft Dalam 1/2" 2 bh 8,500 Rp 17,000
1 . 19 Dop 3/4" 1 bh 8,000 Rp 8,000
1 . 20 Stop kran 1" 3 bh 33,200 Rp 99,600
1 . 21 Tandon Air 1000 ltr (Exel) 1 bh 3,500,000 Rp 3,500,000
1 . 22 Lem Isarplas kaleng 400 gr 1 bh 30,000 Rp 30,000
1 . 23 Seal Tape 10 bh 6,000 Rp 60,000
1 . 24 Kabel NYM 3 x 1,5 70 m 16,500 Rp 1,155,000
1 . 25 Klem pipa 1 1/4" 10 bh 3,000 Rp 30,000
1 . 26 Klem pipa 1 " 10 bh 2,700 Rp 27,000
1 . 27 Klem pipa 3/4" 15 bh 2,700 Rp 40,500
1 . 28 Piting Stop Kontak 1 bh 15,000 Rp 15,000
1 . 29 Klem kabel 1 bngkus 6,000 Rp 6,000
1 . 30 Isolasi 2 bh 7,000 Rp 14,000
1 . 31 PC (Semen) 4 zak 60,000 Rp 240,000
1 . 32 Pasir Pasang 2 m3 200,000 Rp 400,000
1 . 33 Split 1 m3 400,000 Rp 400,000
1 . 34 Besi Ø 10 12 btg 130,000 Rp 1,560,000
2 . 35 Besi Ø 6 5 btg 100,000 Rp 500,000
3 . 36 Bendrat 1 kg 361,112 Rp 361,112
Harga Satuan Jumlah Total
Uraian Volume Satuan Jumlah
( Rp ) ( Rp )
a b c d e=bxd f
a b c d e=bxd f
2 . ALAT
2 . 1 Pompa Submersible 1 unit 3,850,000 Rp 3,850,000
2 . 2 Saklar Tandon Air (otomatis) 1 unit 120,000 Rp 120,000
Mengetahui,
Kepala Sekolah TIM PENYUSUN
………………………….. ……………………………………
PERHITUNGAN KEBUTUHAN BAHAN DAN HOK
Kampung : Padjajaran
Kecamatan : Cicendo
1.5
1.5
1.5
1 1.5 1
Volume Galian
Panjang = 6.00 m
0.5 Volume = 0.60 x 0.50 x 6.00 = 1.8 m3
0.60
Volume Urugan
0.15 Panjang = 6.00 m
Volume 1 = Urugan kembali pondasi
0.5 = (0,15 + 0.05) / 2 x 0,5 x 6 x 2 = 0.60 m3
Volume 2 = Urugan lantai, dari tanah asli ke permukaan lantai, tinggi = 0.3 m
0.5 = 2.00 x 2.00 = 1.20 m3
0.6 = 1.80 m3
Volume Podasi
0.25 Panjang = 6.00 m
Volume = (0,25 + 0,5) / 2 x 0,6 x 6 = 1.35 m3
0.05
0.5
0.6
0.2
Volume = 0.2 x 0.2 x 3.00 x 4 = 0.480 m3
Ø 6 - 0.2
Besi Ø6 mm = 3.00 x 4 / 0.2 = 60.00 bh
= 60.00 x 0.64 = 38.40 m
= 38.40 / 12.00 = 3.20 ≈ 3.20 btg
9. SNI 7394 20083 6.4 Membuat 1 m3 lantai kerja (floor) beton mutu (K 100)
- PC (Semen) 4.6 x 0.61 = 2.82 zak
- Pasir Pasang 0.638 x 0.61 = 0.39 m3
- Split 0.761 x 0.61 = 0.47 m3
- Pekerja 1.2 x 0.61 = 0.74 HOK
- Tukang 0.2 x 0.61 0.12 HOK
12. SNI 7395 2008 6.36 Memasang 1 m2 lantai keramik uk. ( 20x20 cm )
- Keramik 26.500 x 12.25 = 324.63 bh
- PC (Semen) 0.208 x 12.25 = 2.55 zak
- Pasir Pasang 0.045 x 12.25 = 0.55 m3
- Semen warna 1.620 x 12.25 = 19.85 kg
- Pekerja 0.700 x 12.25 = 8.58 HOK
- Tukang 0.350 x 12.25 4.29 HOK
13. SNI 7395 2008 6.54 Memasang 1 m2 dinding keramik uk. ( 20x20 cm )
- Keramik 26.500 x 7.00 = 185.50 bh
- PC (Semen) 0.186 x 7.00 = 1.30 zak
- Pasir Pasang 0.018 x 7.00 = 0.13 m3
- Semen warna 1.940 x 7.00 = 13.58 kg
- Pekerja 0.900 x 7.00 = 6.30 HOK
- Tukang 0.450 x 7.00 3.15 HOK