TIME SCHEDULE

NAMA PROYEK ; PEMBANGUNAN 'VILA TRINITY


LOKASI : BLOK I-41 TRINITI JL SERSAN BAJURI
PEKERJAAN : STRUKTUR - SIPIL (TAHAP-1)
WAKTU PELAKSANAAN
BULAN KE-1 BULAN KE-2 BULAN KE-3 BULAN KE-4 BULAN KE-5 BULAN KE-6 BULAN KE-7 BULAN KE-8 BULAN KE-9 BULAN KE-10 BULAN KE-11 BULAN KE-12 BULAN KE-13 BULAN KE-14 X XX
No. Uraian Pekerjaan BOBOT NOTE KETERANGAN
MG.-1 MG.-2 MG.-3 MG.-4 MG.-5 MG.-6 MG.-7 MG.-8 MG.-9 MG.-10 MG.-11 MG.-12 MG.-13 MG.-14 MG.-15 MG.-16 MG.-17 MG.-18 MG.-19 MG.-20 MG.-21 MG.-22 MG.-23 MG.-24 MG.-25 MG.-26 MG.-27 MG.-28 MG.-29 MG.-30 MG.-31 MG.-32 36 40 44 48 52 56
TAHAP-1 %
I PEKERJAAN PEMATANGAN 1.324 0.441 0.441 0.063 0.063 0.063 0.063 0.063 0.063 0.063 99.6 99.6 99.6 99.6 100.0
98.7
98.0
96.8
PEKERJAAN STRUKTUR : -
II PERSIAPAN 4.542 1.136 1.136 1.136 0.162 0.162 0.162 0.162 0.162 0.162 0.162
93.2
III STRUKTUR ALAS
1 Tanah & Pondasi ; 8.715 2.179 2.179 2.179 0.545 0.545 0.545 0.545
89.4
2 Sloof & Kolom ;
- Sloof 5.253 1.313 1.313 1.313 0.328 0.328 0.328 0.328
85.4
- Kolom Lt.1 4.571 0.914 0.914 0.914 0.914 0.457 0.457
3 Dasaran Lantai (cor beton) 3.416 1.14 1.14 0.57 0.57
IV STRUKTUR ATAS (LT.2 & DAK) - 80.6
1 Balok Lantai-2 & Dak ; Beton 7.646 1.092 1.092 1.092 1.092 1.092 1.092 1.092
2 Lantai Beton (Plat lt.2 & dak ) 6.911 1.728 1.728 1.728 1.728
3 Kolom Lt.2 & Ring Balok 5.443 1.361 1.361 1.361 1.361 74.9
V STRUKTUR ATAP & PENUTUP -
Bangunan : -
1 Atap : Bedroom 1 & 2 3.685 0.61 0.61 0.61 0.6170.1 0.61 0.61
2 Atap : Kichen & Service 2.707 0.677 0.677 0.677 0.677
Penunjang : - 66.0
3 Canopy Selasar Dalam 1.407 0.352 0.352 0.352 0.176 0.176
4 Canopy Teras Belakang (r.makan) 0.479 61.9 0.239 0.239
5 Atap FOYER : kuda2 beton 1.703 0.852 0.852
6 Canopy pintu Roof Gaden (atap skylight kaca) - di tahap-2 58.1
7 Canopy area service (atap UPVC ex.Alderon) - di tahap-2
VI STRUKTUR TANGGA (pull kayu) - di tahap-2 54.7
PEKERJAAN FINISHING : (hitaman) -
51.4
VII DINDING (Hitaman)
1 Lantai-1 16.271 2.034 2.034
48.3 2.034 2.034 3.051 2.034 2.034 1.017
2 Lantai-2 7.403 1.234 1.234 1.234 1.234 1.234 1.234
VIII PEKERJAAN LAIN-LAIN : - 45.2
i Instalasi Air Hujan & Air Kotor 1.452 0.242 0.242 0.242 0.242 0.242 0.242
42.3
ii Ground tank & Fiber Torn 1.657 0.552 0.552 0.552
iii Benteng Kapling (kiri-kanan) p =76m1 6.092 0.508 0.508 0.508 0.508 1.015 0.508 1.015 1.015 0.127 0.127 0.127 0.127
39.0
iv Benteng Kapling (belakang) p =25m1 - hold
v Tembok Depan ; (pagar depan) 1.224 36.4 0.306 0.306 0.306 0.306
vi Carporch (garasi ;5mx6m) 3.529 34.1 0.588 0.588 0.588 0.588 0.588 0.588
vii Jalan Masuk (carport & drop off) 1.378 32.0 0.689 0.689
viii Septiktank & Resapan 0.848 0.212 0.212 0.212 0.212
29.9
ix POND (kolam Taman uk.5m x3,35m) 2.343 0.391 0.391 0.391 0.391 0.391 0.391

TAHAP-2 (FINISHING) 26.7


1 PERSIAPAN -
2 DINDING - 23.4
3 PLAFOND -
20.5
4 LANTAI -
5 KM/WC, PARTISI, SANITAIR & DAPUR - 18.2
6 PLUMBING (INST. AIR BERSIH & AIR KOTOR) - 16.4
7 PINTU & JENDELA -
13.5
8 INSTALASI LISTRIK -
9 LAIN-LAIN : -
- Pek. Tangga Kayu & Fin. - 10.0
- Pek. Atap/Canopy, Lisplank&Variasi -
- Pek. Railing - 6.5
- Pek. Pintu Pagar -
- Pek. Halaman, dll - 3.2
2.0
- Pompa2 & perlengkapan - 0.0 0.4
Total 100.00
JML RENCANA PROGRESS PER-MINGGU 0.441 1.577 1.136 3.314 3.492 3.492 2.934 1.850 2.295 2.847 3.359 3.173 2.039 2.169 2.270 2.561 3.337 2.947 3.109 3.010 3.394 3.394 3.799 4.090 4.055 4.860 5.661 4.787 4.013 3.834 3.557 1.221 0.689 0.901 - - - 0.391

JML. KUMULATIF RENC. PROGRESS PER-MINGGU 0 0.441 2.018 3.154 6.468 9.960 13.452 16.387 18.237 20.532 23.380 26.738 29.911 31.950 34.120 36.389 38.951 42.288 45.235 48.344 51.354 54.748 58.143 61.942 66.032 70.087 74.948 80.608 85.395 89.407 93.241 96.798 98.019 98.708 99.609 99.609 99.609 99.609 100.00

JML RIIL PROGRESS PER-MINGGU


JML RIIL KUMULATIF PER-MINGGU