EVALUASI TARGET PENYELESAIAN PEKERJAAN ARSITEKTUR
Rabu, 2 Juni 2021
PROGRESS
NO ITEM PEKERJAAN TARGET SELESAI S/D SAAT KETERANGAN
INI
1 Pasangan Bata J2 01-Jun-21 75% Kurang tenaga kerja
2 Ruang panel tiap lantai 03-Jun-21 75% On progress
3 Repair waterproofing KM 31-Mei-21 75% On progress
4 Expose beton mezzanine & void 02-Jun-21 90% Terkendala langsir material
5 Pondasi Panel PLN 02-Jun-21 90% On progress
6 Waterproofing GWT 5% On progress
7 Keramik GWT
8 Jendela CW 2 03-Jun-21 30% On progress
9 Jendela CW 3 03-Jun-21 100%
10 Screed Roof Tank 03-Jun-21 50% Tidak ada pekerja
11 Plafoond KM/WF 04-Jun-21 10% On progress
12 Partisi Gypsum 04-Jun-21
13 Facade Lt.1 04-Jun-21 25% On progress
14 Screed Waterproofing lt.atap 05-Jun-21 85% On progress
15 Keramik Tangga sisi timur 05-Jun-21 40% On progress
16 Floorhardener lantai 1 & Outdoor AC 05-Jun-21 60% On progress
17 Keramik Lantai 1 05-Jun-21 60% On progress
18 Dokumen administrasi Adddendum 05-Jun-21
19 Keramik Power House 05-Jun-21 Pondasi PLN
20 Screed Atap power House 05-Jun-21 Tidak ada pekerja
21 Keramik lantai Atap 05-Jun-21 Belum ada tenaga
22 Canopy Dropp Off 06-Jun-21 65% On progress
23 Canopy belakang 06-Jun-21 65% On progress
24 Keramik lantai KM/WC 07-Jun-21 20% Baru terpasang di lantai 3
25 Aspal 07-Jun-21 Area belum siap
26 Finishing ruang lift 08-Jun-21 60% On progress
27 Plafond semua lantai 08-Jun-21 80% On progress
28 Saluran U-ditch 10-Jun-21 80% On progress
29 Kansteen 10-Jun-21 Area belum siap
30 Cubicle toilet 10-Jun-21 Area belum siap
31 Cermin KM 12-Jun-21 Area belum siap
32 Dokumen PHO 12-Jun-21
33 Nat keramik 13-Jun-21 Area belum siap
34 Pintu semua ruangan 13-Jun-21 Material belum datang
35 Finishing bekas bobokan 13-Jun-21 40% On progress
36 Landscape paving 13-Jun-21 10% On progress
37 Cleaning Area 14-Jun-21