DATA PROJECT
Schedule
6 Pelaksanaan
- Durasi Pekerjaan : 98 ( Sembilan Puluh Delapan ) hari kalender
- Mulai Pekerjaan : 03 Februari 2020
- Handover : 11 Mei 2020
- Masa Perawatan : 12 Bulan Sejak BAST Ke 1
DATA TIM CONAKA DILAPANGAN
PERSONAL PROJECT
A. STAFF
1 Project Manager : 1 Person
2 Site Manager : 1 Person
3 Supervisor : 4 Persons
4 Logistic : 1 Person
5 K.3 : 1 Person
B. MANPOWER
1 Sipil : 77 Person
2 MEP : 16 Person
3 Gypsum & Acoustic : 20 Person
4 Kaca dan Pintu : 0 Person
5 Marble : 48 Person
MAIN MATERIAL
1. Bata Ringan
2. Mortal Cement ( Pasangan, Plester Aci, Secreding )
3. Semen PCC @ 50 Kg
4. Gypsum Board 12mm
5. PVC Conduit & Acc
6. Kabel Power / Data / Telephone
7. Hollow steel 4/4 & 4/2
8. Besi Kolom Balok Praktis
9. Material kerja Bantu ( Benang, Paku , Kawar dll )
10. Glasswool
TOOLS
1. Panel Power
2. Mesin Bor Gerinda
3. Bending Conduit
4. Water pass
5. Alat kerja Bantu ( Kabel Power + Penerangan
Project )
6. Scaffolding & Tangga
7. Hois liftup Marble
PERFORMA PROJECT FOR THIS WEEK
PENANGANAN PROBLEM
1. Food Court & Lounge terkendala tahapan pek Kontruksi yang masih berjalan
2. Kontraktor push vendor ( krn sdg terbit PO jauh jauh hari )
3. Kontraktor akan ganti tenaga kerja baru , akan berdampak pada perlambatan
laju progres
4. Mohon dapat segera di putuskan deal wiring lampu
PEKERJAAN SEDANG BERJALAN
Kolom Kisi-Kisi Marble Lt. GF Pek. Dinding Lobby Lift Cover Marble
PROGRES PARTISI DAN LT. KERAMIK PROGRES CEILING DAN COVER KOLOM