Anda di halaman 1dari 19

37/LM/PROYEK/COLLECTION/IX/22

Monitoring Collection Pondasi dan atap All Cluster Per 01 Oktober 2022
ATAP
SLOOF/ TIE BEAM MANDOR
No NO. SPK JUMLAH UNIT AKTUAL DEVIASI

No Lokasi Pondasi 1 021 19 19 0

2 043 20 20 0

3 069 14 14 0
1 D15 DR No. 20 100 %
4 079 37 37 0

5 001 1 1 0

6 002 5 5 0

7 024 7 7 0

8 040 16 16 0

9 057 11 9 -2

10 061 10 4 -6

11 RBP 40 18 -22

Hasil Atap Minggu Ini


No SPK Lokasi
1 061 KS2 50
2 061 KS2 72
3 RBP KS1 57
4 RBP KU1 63
5 RBP KU1 67
6 RBP BANYAN NO. 2
7 RBP KASUARINA NO. 5
8 RBP KASUARINA NO. 3
MONITORING CUACA MINGGU KE-4 SEPTEMBER 2022
Hari/Jam 08.00 09.00 10.00 11.00 12.00 13.00 14.00 15.00 16.00 17.00 18.00
Senin
Selasa
Rabu
Kamis
Jum’at

NO. PEKERJAAN PROGRESS KONTRAKTOR


1 Rumah Pompa 100 % PT. SITU ANFERYU
2 DPT Natura 100 % PT. INERSIA BERKAH USAHA
3 Infratsuktur Insitu Utara 97 % PT. INERSIA BERKAH USAHA
4 Saluran H. Djole 100 % PT. SITU ANFERYU
5 Shopping Street 100 % PT. SITU ANFERYU
6 Jalan Tembus Botanica 75 % PT. INERSIA BERKAH USAHA
Pekerjaan Minggu Ini
No Pekerjaan Mengetahui Pengawas Tanggal Keterangan
1 Repair pasar alam Awal Didit (Project Team) 25/09/2022
2 Pengecoran, Jalan tembus Botanica Awal Didit (Project Team) 25/09/2022
3 Pengecoran, Jalan tembus Botanica (Finish) Awal Didit (Project Team) 25/09/2022
4 Cek pola genteng, KS2 No. 72 Awal Aan (Project Team) 26/09/2022
5 Cek lapisan atap, KS2 No. 72 Awal Aan (Project Team) 26/09/2022
6 Cek tampak bawah atap, KS2 No. 72 Awal Aan (Project Team) 26/09/2022
7 Cek tampak bawah atap, KS2 No. 72 Awal Aan (Project Team) 26/09/2022
8 Pengecekan lapisan atap, KS2 No. 50 Awal Aan (Project Team) 26/09/2022
9 Pengecekan pola atap, KS2 No. 50 Awal Aan (Project Team) 26/09/2022
10 Tampak bawah atap, KS2 No. 50 Awal Aan (Project Team) 26/09/2022
11 Tampak depan, KS2 No. 50 Awal Aan (Project Team) 26/09/2022
12 Curring beton, Jalan Tembus Botanica Awal Didit (Project Team) 26/09/2022
13 Finish openingan, Banyan No. 5 Awal Irman (Project Team) 26/09/2022
14 Keramik dinding kamar mandi, KS2 No. 10 Awal Irman (Project Team) 26/09/2022
15 Keramik dinding kamar mandi, Tamarind No. 25 Awal Irman (Project Team) 26/09/2022
16 Keramik dinding kamar mandi, Tamarind No. 29 Awal Irman (Project Team) 26/09/2022
17 Leveling carport, DK No. 10 Awal Irman (Project Team) 26/09/2022
18 Pekerjaan acian dinding, Tamarind No. 32 Awal Irman (Project Team) 26/09/2022
19 Pengecoran, Jalan Tembus Botanica Awal Didit (Project Team) 27/09/2022
20 Pengecoran, Jalan Tembus Botanica (Finish) Awal Didit (Project Team) 27/09/2022
21 Bobok dinding tampak depan, KS2 No. 61 Awal Faisal (Project Team) 27/09/2022
22 Cek elevasi tie beam, D15 DR No. 20 Awal Irman (Project Team) 27/09/2022
23 Finishing openingan, Banyan No. 5 Awal Irman (Project Team) 27/09/2022
24 Pekerjaan keramik dinding kamar mandi lantai 1, Tamarind No. 53 Awal Irman (Project Team) 27/09/2022
Pekerjaan Minggu Ini
No Pekerjaan Mengetahui Pengawas Tanggal Keterangan
25 Pemasangan hebel lantai 1, Tamarind No. 50 Awal Irman (Project Team) 27/09/2022
26 Pemasangan keramik lantai 2, KS2 No. 22 Awal Irman (Project Team) 27/09/2022
27 Plester dinding dalam, KS3 No. 10 Awal Irman (Project Team) 27/09/2022
28 Pekerjaan dinding pembatas carport, DK No. 10 Awal Irman (Project Team) 27/09/2022
29 Tes rendam wp dak talang, Banyan No. 2 Awal Irman (Project Team) 27/09/2022
30 Tes rendam wp dak talang, Banyan No. 5 Awal Irman (Project Team) 27/09/2022
31 Tes rendam wp dak talang, Casuarina No. 3 Awal Irman (Project Team) 27/09/2022
32 Tes rendam wp dak talang, Casuarina No. 5 Awal Irman (Project Team) 27/09/2022
33 Waterproofing kamar mandi lantai 2, Banyan No. 5 Awal Irman (Project Team) 27/09/2022
34 Setting bekisting, Jalan Tembus Awal Didit (Project Team) 28/09/2022
35 Pengecoran, Jalan tembus botanica Awal Didit (Project Team) 28/09/2022
36 Bekisting dan pembesian wiremesh, DK No. 10 Awal Irman (Project Team) 28/09/2022
37 Pekerjaan rangka atap, KS2 No. 27 Awal Irman (Project Team) 28/09/2022
38 Pekerjaan rangka plafond, Banyan No. 5 Awal Irman (Project Team) 28/09/2022
39 Pengecekan jarak sengkang tumpuan, D15 DR No. 20 Awal Irman (Project Team) 28/09/2022
40 Pengecoran carport, DK No. 10 Awal Irman (Project Team) 28/09/2022
41 Tutup atap GRC, KS2 No. 10 Awal Irman (Project Team) 28/09/2022
42 Waterproofing kamar mandi lantai 2, Banyan No. 5 Awal Irman (Project Team) 28/09/2022
43 Curing beton, Jalan Tembus Awal Didit (Project Team) 30/09/2022
44 Pemasangan street inlet, Jalan Tembus Awal Didit (Project Team) 30/09/2022
45 Kepalaan plester dinding, Jacaranda No. 9 Awal Irman (Project Team) 30/09/2022
46 Kepalaan plester dinding, Tamarin No. 12 Awal Irman (Project Team) 30/09/2022
47 Pekerjaan keramik lantai 1, Banyan No. 5 Awal Irman (Project Team) 30/09/2022
48 Pekerjaan tali air dinding, KS2 No. 2 Awal Irman (Project Team) 30/09/2022
Pekerjaan Minggu Ini
No Pekerjaan Mengetahui Pengawas Tanggal Keterangan
49 Pekerjaan tutup atap bitumen, KS2 No. 10 Awal Irman (Project Team) 30/09/2022
50 Pekerjaan tutup atap GRC, KU1 No. 65 Awal Irman (Project Team) 30/09/2022
51 Pemasangan atap bitumen, KS1 No. 57 Awal Irman (Project Team) 30/09/2022
52 Pemasangan keramik lantai 1, KS2 No. 18 Awal Irman (Project Team) 30/09/2022
53 Tali air dinding, Banyan No. 5 Awal Irman (Project Team) 30/09/2022
54 Tes rendam wp kamar mandi, Banyan No. 2 Awal Irman (Project Team) 30/09/2022
55 Tes rendam dak talang, Banyan No. 2 Awal Irman (Project Team) 30/09/2022
56 Tes megger, Banyan No. 2 dan 5 Awal Supri (Project Team) 30/09/2022
57 Tes megger, Tamarind No. 29, 30, 32 dan 36 Awal Supri (Project Team) 30/09/2022
58 Tes megger, KS1 No. 57 Awal Supri (Project Team) 30/09/2022
59 Tes megger, KS2 No. 3, 18, 22, 27, 31 dan 38 Awal Supri (Project Team) 30/09/2022
60 Tes megger, KU1 No. 57, 61, 63, 65 dan 67 Awal Supri (Project Team) 30/09/2022
61 Cor sloof, D15 DR No. 20 Awal Irman(Project Team) 01/10/2022
62 Finishing tampak, Banyan No. 2 Awal Irman(Project Team) 01/10/2022
63 Pekerjaan tali air dinding, Banyan No. 5 Awal Irman(Project Team) 01/10/2022
64 Pemasangan keramik lantai kamar mandi, Banyan No. 5 Awal Irman(Project Team) 01/10/2022
65 Pemasangan rangka pladond, Banyan No. 5 Awal Irman (Project Team) 01/10/2022
66 Repair acian dinding, KU3 No. 20 Awal Faisal (Project Team) 01/10/2022
67 Pemasangan keramik dinding kamar mandi lantai 1, KU3 No. 20 Awal Faisal (Project Team) 01/10/2022
68 Pemadatan dudukan kanstin slipform, Jalan Tembus Botanica Awal Didit (Project Team) 01/10/2022
Foto Progres Pekerjaan Sampai 01 Oktober 2022

1. Repair pasar alam 2. Pengecoran, Jalan tembus Botanica 3. Pengecoran, Jalan tembus Botanica (Finish)

4. Cek pola genteng, KS2 No. 72 5. Cek lapisan atap, KS2 No. 72 6. Cek tampak bawah atap, KS2 No. 72
Foto Progres Pekerjaan Sampai 01 Oktober 2022

7. Cek tampak bawah atap, KS2 No. 72 8. Pengecekan lapisan atap, KS2 No. 50 9. Pengecekan pola atap, KS2 No. 50

10. Tampak bawah atap, KS2 No. 50 11. Tampak depan, KS2 No. 50 12. Curring beton, Jalan Tembus Botanica
Foto Progres Pekerjaan Sampai 01 Oktober 2022

13. Finish openingan, Banyan No. 5 14. Keramik dinding kamar mandi, KS2 No. 10 15. Keramik dinding kamar mandi,
Tamarind No. 25

1 6 . Ke ra m i k d i n d i n g k a m a r m a n d i , 17. Leveling carport, DK No. 10 18. Pekerjaan acian dinding,


Tamarind No. 29 Tamarind No. 32
Foto Progres Pekerjaan Sampai 01 Oktober 2022

19. Pengecoran, Jalan Tembus Botanica 20. Pengecoran, Jalan Tembus Botanica
21. Bobok dinding tampak depan, KS2 No. 61
(Finish)

24. Pekerjaan keramik dinding kamar


22. Cek elevasi tie beam, D15 DR No. 20 23. Finishing openingan, Banyan No. 5
mandi lantai 1, Tamarind No. 53
Foto Progres Pekerjaan Sampai 01 Oktober 2022

25. Pemasangan hebel lantai 1,


26. Pemasangan keramik lantai 2, KS2 No. 22 27. Plester dinding dalam, KS3 No. 10
Tamarind No. 50

28. Pekerjaan dinding pembatas carport, 29. Tes rendam wp dak talang, 30. Tes rendam wp dak talang,
DK No. 10 Banyan No. 2 Banyan No. 5
Foto Progres Pekerjaan Sampai 01 Oktober 2022

31. Tes rendam wp dak talang, 32. Tes rendam wp dak talang, 33. Waterproofing kamar mandi lantai
Casuarina No. 3 Casuarina No. 5 2, Banyan No. 5

34. Setting bekisting, Jalan Tembus 35. Pengecoran, Jalan tembus botanica 36. Bekisting dan pembesian
wiremesh, DK No. 10
Foto Progres Pekerjaan Sampai 01 Oktober 2022

37. Pekerjaan rangka atap, 3 8 . Pe ke r j a a n ra n g ka p l afo n d , 3 9 . Pe n ge c e ka n j a ra k s e n g k a n g


KS2 No. 27 Banyan No. 5 tumpuan, D15 DR No. 20

40. Pengecoran carport, DK No. 10 41. Tutup atap GRC, KS2 No. 10 42. Waterproofing kamar mandi lantai 2,
Banyan No. 5
Foto Progres Pekerjaan Sampai 01 Oktober 2022

43. Curing beton, Jalan Tembus 44. Pemasangan street inlet, Jalan Tembus 45. Kepalaan plester dinding,
Jacaranda No. 9

46.Kepalaan plester dinding, 47. Pekerjaan keramik lantai 1, 48. Pekerjaan tali air dinding,
Tamarin No. 12 Banyan No. 5 KS2 No. 2
Foto Progres Pekerjaan Sampai 01 Oktober 2022

49. Pekerjaan tutup atap bitumen, 50. Pekerjaan tutup atap GRC, KU1 No. 65 51. Pemasangan atap bitumen,
KS2 No. 10 KS1 No. 57

52. Pemasangan keramik lantai 1, 53. Tali air dinding, Banyan No. 5 54. Tes rendam wp kamar mandi, Banyan
KS2 No. 18 No. 2
Foto Progres Pekerjaan Sampai 01 Oktober 2022

55. Tes rendam dak talang, Banyan No. 2 56. Tes megger, Banyan No. 2 dan 5 57. Tes megger, Tamarind No. 29, 30, 32
dan 36

58. Tes megger, KS1 No. 57 59. Tes megger, KS2 No. 3, 18, 22, 27, 31 60. Tes megger, KU1 No. 57, 61, 63, 65
dan 38 dan 67
Foto Progres Pekerjaan Sampai 01 Oktober 2022

62. Finishing tampak, Banyan 63. Pekerjaan tali air dinding, Banyan
61. Cor sloof, D15 DR No. 20
No. 2 No. 5

64. Pemasangan keramik lantai kamar 65. Pemasangan rangka pladond, Banyan 66. Repair acian dinding, KU3 No. 20
mandi, Banyan No. 5 No. 5
Foto Progres Pekerjaan Sampai 01 Oktober 2022

67. Pemasangan keramik dinding kamar 68. Pemadatan dudukan kanstin


mandi lantai 1, KU3 No. 20 slipform, Jalan Tembus Botanica
Created by : Approved by :

Awaludin Mawardani Paksi Handoyo


Project Manager Deputy GM

Anda mungkin juga menyukai