PTM KELAS C - KELOMPOK 4 :

DIAH WIDYA (1307113147)


INTAN MONICA.MG (1507123488)
ROMA DEARNI (1507113645)
SUTOPO (1407123297)
TENGKU SYAHILLA INDRIYATI (1507113188)
VIRA AFRILLA (1507113087)
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

SKEMA
1 • Land Clearing
DENAH LOKASI

TEBAL PERKERASAN 2 • Embankment


JALAN RENCANA

3 • Compacting
4 • Asphalt Pavement
5 • Cooling
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

Asphalt Mixing Plant Heavy Equipment Storage Stone Crusher


SKEMA

DENAH LOKASI

TEBAL PERKERASAN
JALAN RENCANA

7 km - Proyek Jalan yang dikerjakan


Gambar 1. Denah lokasi
Sumber : Leosentosa, 2010
1 2
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

SKEMA
Tabel 1. Klasifikasi Jalan menurut lebar badan jalan

DENAH LOKASI 1. Jalan Arteri 1) Kecepatan rencana > 60 km/jam.


2) Lebar badan jalan > 8,0 m.
TEBAL PERKERASAN
JALAN RENCANA 2. Jalan Kolektor 1) Kecepatan rencana > 40 km/jam.
2) Lebar badan jalan > 7,0 m.

3. Jalan Lokal 1) Kecepatan rencana > 20 km/jam.


2) Lebar badan jalan > 6,0 m.

Sumber : Leosentosa, 2010

1 2
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

Dengan menggunakan Bina Marga metode konstruksi langsung


SKEMA

DENAH LOKASI

TEBAL PERKERASAN
JALAN RENCANA

Gambar 2. Tebal Perkerasan


Sumber : Dokumen Pribadi, 2015
1 2
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

SKEMA

DENAH LOKASI

TEBAL PERKERASAN
JALAN RENCANA

1 2
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

URUTAN KERJA

SIKLUS

BULLDOZER

EXCAVATOR

WHEEL LOADER

Pemotongan Penggalian
DUMP TRUCK Pembersihan
Pohon Akar Pohon
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

STEP 1
URUTAN KERJA

SIKLUS

40 m 40 m
BULLDOZER
7KM
EXCAVATOR STEP 2

WHEEL LOADER

DUMP TRUCK

7KM
Gambar 3. Siklus Land Clearing
Sumber : Leosentosa, 2010
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

URUTAN KERJA

SIKLUS

BULLDOZER

EXCAVATOR

WHEEL LOADER

DUMP TRUCK

Gambar 4. Bulldozer

1 2 3 4 5 6 7 8 9 10 11
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

URUTAN KERJA

SIKLUS
No. URAIAN KODE KOEF. SATUAN

BULLDOZER
A. URAIAN PERALATAN
1. Jenis Peralatan BULLDOZER 100-150 HP
EXCAVATOR
2. Tenaga Pw 200,0 HP
3. Kapasitas Cp - -
WHEEL LOADER 4. Alat Baru : a. Umur Ekonomis A 5,0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2.000,0 Jam
c. Harga Alat B 1.200.000.000 Rupiah
DUMP TRUCK

1 2 3 4 5 6 7 8 9 10 11
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

URUTAN KERJA

SIKLUS

BULLDOZER

EXCAVATOR

WHEEL LOADER

DUMP TRUCK

1 2 3 4 5 6 7 8 9 10 11
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

URUTAN KERJA

SIKLUS

BULLDOZER

EXCAVATOR

WHEEL LOADER

DUMP TRUCK

1 2 3 4 5 6 7 8 9 10 11
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

URUTAN KERJA

SIKLUS

BULLDOZER

EXCAVATOR

WHEEL LOADER

DUMP TRUCK

1 2 3 4 5 6 7 8 9 10 11
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

URUTAN KERJA Produktivitas bulldozer dapat dihitung dengan rumus ;


Q = q x CT x e x F
Dengan :
SIKLUS Q = produktivitas (m3/jam)
q = produksi persiklus(m3/jam) = q1 x a
BULLDOZER CT = waktu siklus (menit)
e = faktor kelandaian
F = efisiensi kerja
EXCAVATOR
Kondisi Kerja Efisiensi Kerja
WHEEL LOADER Baik 0,83

DUMP TRUCK
Sedang 0,75
Kurang Baik 0,67
Jelek 0,58
Sumber : Leosentosa0.wordpress.com 1 2 3 4 5 6 7 8 9 10 11
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

URUTAN KERJA
TABEL FAKTOR BLADE
SIKLUS
Kondisi Permukaan / Pengupasan Faktor

BULLDOZER Mudah Lapis permukaan tidak keras, tidak terlalu padat, tanah 1,1 - 0,9
biasa, kadar air rendah, bahan timbunan
EXCAVATOR Sedang Lapis permukaan tidak terlalu padat, sedikit mengandung 0,9 – 0,7
pasir, kerikil, atau agregat halus

WHEEL LOADER Agak Sukar Kadar air agak tinggi, mengandung tanah liat, berpasir, 0,7 – 0,6
tanah liat kering dan keras
Sukar Batu hasil ledakan atau batu belah ukuran besar 0,6 – 0,4
DUMP TRUCK
Sumber : Leosentosa, 2010

1 2 3 4 5 6 7 8 9 10 11
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

URUTAN KERJA GRAFIK FAKTOR KELANDAIAN

SIKLUS

BULLDOZER

EXCAVATOR

WHEEL LOADER

DUMP TRUCK

Gambar 5. Grafik Faktor Kelandaian


Sumber : Leosentosa, 2010
1 2 3 4 5 6 7 8 9 10 11
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

URUTAN KERJA DATA YANG DIPEROLEH:

SIKLUS Sebuah bulldozer 100-150 HP


Koefisien traksi = 0,4
Berat alat = 12.250 kg
BULLDOZER Kapasitas blade(q1) = 2,87 m3
Kecepatan dorong (Vf) = 5 km/jam
EXCAVATOR Kecepatan mundur(Vr) = 7 km/jam

Harus memindahkan tanah pada jarak efektif sejauh 40 meter, dengan kondisi tanah sebagai
WHEEL LOADER berikut :
Berat tanah =1.250 kg/m3, material mudah didorong
faktor blade(a) = 0,9
DUMP TRUCK faktor pengembangan (swell) =1,25
Lokasi datar tanpa ada daerah landai/mendaki
Kondisi operasi sangat baik dengan faktor efisiensi (F) = 0,83

1 2 3 4 5 6 7 8 9 10 11
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

URUTAN KERJA

SIKLUS

BULLDOZER

EXCAVATOR

WHEEL LOADER

DUMP TRUCK
Produktifitas;
Q = q x CT x e x F
Q = 2,583 x (60/0,92) x 1,0 x 0,83
Q = 140 m3/jam
1 2 3 4 5 6 7 8 9 10 11
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

URUTAN KERJA
Biaya Sewa Total
SIKLUS
Produktifitas = 140 m3/jam
total biaya sewa alat / jam = Rp 612.543,50
BULLDOZER
Volume lahan yang dibersihkan = 14.000 m3
EXCAVATOR Waktu pekerjaan yang dibutuhkan = 14.000 / 140 = 100 jam

Asumsi waktu kerja efektif alat berat dalam 1 hari = 7 jam


WHEEL LOADER
Jadi, waktu hari yang dibutuhkan = 100/7 = 14,28~ 15 hari/ 1 alat

DUMP TRUCK Waktu dengan 4 bulldozer = 15/4 = 3,75 ~ 4 hari.


Biaya total sewa Bulldozer = 100 jam x Rp 612.543,50 = Rp 61.254.300,-

1 2 3 4 5 6 7 8 9 10 11
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

URUTAN KERJA

SIKLUS

BULLDOZER

EXCAVATOR

WHEEL LOADER

DUMP TRUCK Gambar 7. Excavator


Dalam pekerjaan land clearing, excavator di gunakan untuk
menggali tanah atau memuat material sisa pembersihan ke
dump truck.
1 2 3 4 5 6 7 8
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

URUTAN KERJA

SIKLUS
No. URAIAN KODE KOEF. SATUAN

BULLDOZER
A. URAIAN PERALATAN

EXCAVATOR 1. Jenis Peralatan EXCAVATOR CAT 385BL ME

2. Tenaga Pw 247,0 HP
WHEEL LOADER
3. Kapasitas Cp 0,80 M3
Alat Baru
DUMP TRUCK 4. : a. Umur Ekonomis A 5,0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2.000,0 Jam
c. Harga Alat B 1.500.000.000 Rupiah

1 2 3 4 5 6 7 8
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

URUTAN KERJA

SIKLUS

BULLDOZER

EXCAVATOR

WHEEL LOADER

DUMP TRUCK

1 2 3 4 5 6 7 8
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

URUTAN KERJA

SIKLUS

BULLDOZER

EXCAVATOR

WHEEL LOADER

DUMP TRUCK

1 2 3 4 5 6 7 8
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

URUTAN KERJA Produktivitas excavator dapat dihitung dengan rumus ;

SIKLUS

BULLDOZER

EXCAVATOR

WHEEL LOADER Dengan :


V = kapasitas bucket(heaped)
Fa = faktor efisiensi kerja
DUMP TRUCK
Fb = faktor bucket
Fv = faktor konversi
TS = waktu siklus standar

1 2 3 4 5 6 7 8
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

URUTAN KERJA
Tabel Faktor Bucket
SIKLUS
Faktor
Kondisi
BULLDOZER Bucket
Penggalian tanah biasa, clay, atau tanah
Mudah 1,1 – 1,2
EXCAVATOR lembut
Penggalian tanah biasa berpasir atau tanah
Sedang 1,0 – 1,1
WHEEL LOADER kering
Agak Sukar Penggalian tanah biasa berbatu batu 1,0 – 0,9
DUMP TRUCK
Sukar Pengambilan batu pecah hasil ledakan 0,9 – 0,8
Sumber : Leosentosa, 2010

1 2 3 4 5 6 7 8
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

URUTAN KERJA

Diketahui Specifikasi alat Excavator


SIKLUS KapasitasBucket : 0.8 m3 kondisi baik(alat baru)
Tinggi gross alat : 4,60 m.
BULLDOZER Swing putar dari : 45o s/d 180o.

Jawab :
EXCAVATOR
Faktor Efisisensi:
WHEEL LOADER Efisiensi Kerja = 0,83 (alat Baik)
Faktor Bucket = 1.0 (Sedang)
DUMP TRUCK Faktor Posisi = 1.0 (Lapangan datar)
Kondisi Galian = (3.8/4.6)*100% = 82.61% jadi faktor konversi (Fv)= 0.9
Waktu Siklus = 17 detik
Produktivitas (Q) = (0,8 x 0.83 x 1 x 1 x 3600)/(0.9 x 17) = 312,47 m3/jam
1 2 3 4 5 6 7 8
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

URUTAN KERJA

SIKLUS

BULLDOZER

EXCAVATOR

WHEEL LOADER

DUMP TRUCK

Biaya total sewa Excavator = Rp 44,8 x Rp 755.296,16 = Rp 33.837.267,97

1 2 3 4 5 6 7 8
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

URUTAN KERJA
Untuk memuat
material ke dalam
SIKLUS dump truck

BULLDOZER

EXCAVATOR

WHEEL LOADER

DUMP TRUCK

Gambar 6. Wheel Loader

1 2 3 4 5 6 7 8 9 10
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

URUTAN KERJA

SIKLUS

BULLDOZER

EXCAVATOR

WHEEL LOADER

DUMP TRUCK

1 2 3 4 5 6 7 8 9 10
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

URUTAN KERJA

SIKLUS

BULLDOZER

EXCAVATOR

WHEEL LOADER

DUMP TRUCK

1 2 3 4 5 6 7 8 9 10
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

URUTAN KERJA

SIKLUS

BULLDOZER

EXCAVATOR

WHEEL LOADER

DUMP TRUCK

1 2 3 4 5 6 7 8 9 10
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

URUTAN KERJA
Area untuk
pergerakan bucket
SIKLUS

BULLDOZER
Faktor efisiensi kerja Kondisi material
EXCAVATOR

WHEEL LOADER

DUMP TRUCK
Tipe bucket dan
Waktu siklus
kapasitasnya

1 2 3 4 5 6 7 8 9 10
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

URUTAN KERJA

SIKLUS

BULLDOZER

EXCAVATOR

WHEEL LOADER

DUMP TRUCK

1 2 3 4 5 6 7 8 9 10
URAIAN COMPACTING
MIND MAP LAND CLEARING EMBANKMENT
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

URUTAN KERJA Produktivitas wheel loader dapat dihitung dengan rumus ;

SIKLUS
P = q x 60/CT x Fa
BULLDOZER
Dengan :
EXCAVATOR P = Produktivitas (m3/jam)
q = Produksi per siklus (m3)
WHEEL LOADER CT = Eaktu Siklus (menit)

DUMP TRUCK q = q1 x k
dengan :
q1 = Kapasitas bucket
k = Faktor bucket 1 2 3 4 5 6 7 8 9 10
URAIAN COMPACTING
MIND MAP LAND CLEARING EMBANKMENT
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

URUTAN KERJA

SIKLUS FAKTOR BUCKET

BULLDOZER Kondisi Penumpahan Wheel Loader Track Loader


Mudah 1,0 – 1,1 1,0 – 1,1
EXCAVATOR
Sedang 0,85 – 0,95 0,95 – 1,0

WHEEL LOADER
Agak Sukar 0,80 – 0,85 0,90 – 0,95
Sukar 0,75 – 0,80 0,85 – 0,90
DUMP TRUCK
Sumber : Leosentosa, 2010

1 2 3 4 5 6 7 8 9 10
URAIAN COMPACTING
MIND MAP LAND CLEARING EMBANKMENT
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

URUTAN KERJA
WAKTU SIKLUS BERDASARKAN KAPASITAS BUCKET DAN KONDISI KERJA
SIKLUS
Kapasitas Bucket
Kondisi Kerja
BULLDOZER s/d 3 m3 3,1 m3 s/d 5 m3 > 5,1 m3
Mudah 0,45 0,55 0,65
EXCAVATOR
Sedang 0,55 0,65 0,70
WHEEL LOADER Agak Sukar 0,70 0,70 0,75
Sukar 0,75 0,75 0,80
DUMP TRUCK
Sumber : Leosentosa, 2010

1 2 3 4 5 6 7 8 9 10
URAIAN COMPACTING
MIND MAP LAND CLEARING EMBANKMENT
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

URUTAN KERJA
Perhitungan Produktifitas Wheel Loader
SIKLUS
Kapasitas Bucket = 1.6 m3
Tingkat kesulitan penumpahan = sedang
BULLDOZER
faktor bucket = 0.85
Faktor efisiensi alat = 0.83
EXCAVATOR
Waktu siklus = 0.45 menit
WHEEL LOADER Produktivitas :
P = q x 60/CT x Fa
DUMP TRUCK = 1.6 x 0.85 x 60/0.45 x 0.83
= 150,51 m3

1 2 3 4 5 6 7 8 9 10
URAIAN COMPACTING
MIND MAP LAND CLEARING EMBANKMENT
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

URUTAN KERJA Total Biaya Sewa Wheel Loader

SIKLUS
Produktifitas = 150,51 m3/jam
BULLDOZER total biaya sewa alat / jam = Rp 276.928,46
Volume lahan yang dibersihkan = 10 x 7.000 x 0,2 = 14.000 m3
Waktu pekerjaan yang dibutuhkan = 14000 / 150,51 = 93,02 jam
EXCAVATOR
Asumsi waktu kerja efektif alat berat dalam 1 hari = 7 jam
Jadi, waktu hari yang dibutuhkan = 93,02/7 = 13,29~ 14 hari/ 1 alat
WHEEL LOADER
Waktu dengan 2 wheel loader = 14/2 = 7 hari.
DUMP TRUCK

Biaya total sewa Wheel Loader= 93,02 x Rp 276.928,46 = Rp 25.759.885,35

1 2 3 4 5 6 7 8 9 10
URAIAN COMPACTING
MIND MAP LAND CLEARING EMBANKMENT
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

URUTAN KERJA

SIKLUS
Kapasitas : 24 M3
Tenaga : 100 HP
BULLDOZER

EXCAVATOR

WHEEL LOADER

DUMP TRUCK

Gambar 8. Dump truck

1 2 3 4 5 6 7 8 9 10 11 12
URAIAN COMPACTING
MIND MAP LAND CLEARING EMBANKMENT
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

URUTAN KERJA

SIKLUS
No. URAIAN KODE KOEF. SATUAN
BULLDOZER

A. URAIAN PERALATAN
EXCAVATOR 1. Jenis Peralatan DUMP TRUCK FM 260 JD
2. Tenaga Pw 100,0 HP
WHEEL LOADER 3. Kapasitas Cp 24,0 M3
4. Alat Baru : a. Umur Ekonomis A 5,0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2.000,0 Jam
DUMP TRUCK c. Harga Alat B 845.000.000 Rupiah

1 2 3 4 5 6 7 8 9 10 11 12
URAIAN COMPACTING
MIND MAP LAND CLEARING EMBANKMENT
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

URUTAN KERJA
BIAYA PASTI PER JAM
SIKLUS B. KERJA
1. Nilai Sisa Alat = 10 % x B C 84.500.000 Rupiah

BULLDOZER 2. Faktor Angsuran Modal = i x (1 + i)^A D 0,26380 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
EXCAVATOR a. Biaya Pengembalian Modal
= (B-C)xD E 100.308,99 Rupiah
W
WHEEL LOADER
b. Asuransi, dll = 0,002 x B F 845,00 Rupiah
DUMP TRUCK W

Biaya Pasti per Jam = (E+F) G 101.153,99 Rupiah

1 2 3 4 5 6 7 8 9 10 11 12
URAIAN COMPACTING
MIND MAP LAND CLEARING EMBANKMENT
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

C. BIAYA OPERASI PER JAM KERJA


URUTAN KERJA
1. Bahan Bakar = (12%-15%) x Pw x Ms H 132.000,00 Rupiah
SIKLUS 2. Pelumas = (2.5%-3%) x Pw x Mp I 27.500,00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 36.969


BULLDOZER W

3. Perawatan dan (12,5 % - 17,5 %) x B K 52.812,50 Rupiah


EXCAVATOR perbaikan
= W

WHEEL LOADER 4. Operator = ( 1 Orang / Jam ) x U1 L 12.982,14 Rupiah


Pembantu
5. Operator = ( 1 Orang / Jam ) x U2 M 9.410,71 Rupiah
DUMP TRUCK
Biaya Operasi per Jam = (H+I+K+L+M) P 271.674,11 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 372.828,10 Rupiah

1 2 3 4 5 6 7 8 9 10 11 12
URAIAN COMPACTING
MIND MAP LAND CLEARING EMBANKMENT
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

URUTAN KERJA Produktivitas dump truck dapat dihitung dengan rumus

SIKLUS

BULLDOZER P = C x 60/CTt x Fat

EXCAVATOR
Dengan :
WHEEL LOADER P = Prodiuktivitas (m3/jam)
C = Produksifitas per siklus (m3)
DUMP TRUCK Fat = Faktor efisiensi truck
CTt = Waktu siklus dump truck

1 2 3 4 5 6 7 8 9 10 11 12
URAIAN COMPACTING
MIND MAP LAND CLEARING EMBANKMENT
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

URUTAN KERJA
Waktu Siklus truck
SIKLUS

BULLDOZER

EXCAVATOR

WHEEL LOADER

DUMP TRUCK

1 2 3 4 5 6 7 8 9 10 11 12
URAIAN COMPACTING
MIND MAP LAND CLEARING EMBANKMENT
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

URUTAN KERJA
Waktu Siklus truck

SIKLUS Kecepatan
Maksimum
BULLDOZER Bermuatan 40 km/jam
`Datar
Kosong 60 km/jam
EXCAVATOR
Bermuatan 20 km/jam
Naik
WHEEL LOADER Kosong 40 km/jam
Bermuatan 20 km/jam
DUMP TRUCK Menurun
Kosong 40 km/jam

Sumber : Leosentosa, 2010

1 2 3 4 5 6 7 8 9 10 11 12
URAIAN COMPACTING
MIND MAP LAND CLEARING EMBANKMENT
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

URUTAN KERJA
Perkiraan waktu dumping (t1) dan waktu
SIKLUS mengetur posisi untuk di muat (t2)

BULLDOZER
Efisiensi kerja t1 ( menit) t2 (menit)
EXCAVATOR Baik 0,5 – 0,7 0,1 – 0,2
Sedang 1,0 – 1,3 0,25 – 1,35
WHEEL LOADER
Kurang Baik 1,5 – 2,0 0,4 – 0,5
DUMP TRUCK
Sumber : Leosentosa, 2010

1 2 3 4 5 6 7 8 9 10 11 12
URAIAN COMPACTING
MIND MAP LAND CLEARING EMBANKMENT
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

URUTAN KERJA

SIKLUS Faktor Efisiensi Dump Truck (Fat)

BULLDOZER
Kondisi Kerja Efisiensi Kerja
Baik 0,83
EXCAVATOR
Sedang 0,80
WHEEL LOADER Kurang Baik 0,75
Jelek 0,70
DUMP TRUCK
Sumber : Leosentosa, 2010

1 2 3 4 5 6 7 8 9 10 11 12
URAIAN COMPACTING
MIND MAP LAND CLEARING EMBANKMENT
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

URUTAN KERJA

SIKLUS

BULLDOZER

EXCAVATOR

WHEEL LOADER

DUMP TRUCK

1 2 3 4 5 6 7 8 9 10 11 12
URAIAN COMPACTING
MIND MAP LAND CLEARING EMBANKMENT
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

Menghitung Jumlah Trip Loader :


URUTAN KERJA
= C1/(Q1 X K)
= 24/(1,6 X 0,85) = 9,8 = 10 Trip
SIKLUS
Menghitung Produktivitas Loader Per Siklus:
BULLDOZER C = N X Q1 X K
C = 10 X 1,6 X 0.85 = 13,6 M3/Siklus
EXCAVATOR
Menghitung Waktu Siklus Dump Truck
WHEEL LOADER Ctt = N X Ctl + D/V1 + T1 + D/V2 + T2
Ctt = 10 X 0.4 +(4500/666.67) +1,2 + (4500/1000) + 0,75 = 17 Menit

DUMP TRUCK Menghitung Produktivitas Dump Truck


= C X 60/Ctt X Fat
= 13,6 X (60/17) X 0.83
= 40 M3/Jam
1 2 3 4 5 6 7 8 9 10 11 12
URAIAN COMPACTING
MIND MAP LAND CLEARING EMBANKMENT
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

URUTAN KERJA

SIKLUS

BULLDOZER

EXCAVATOR

WHEEL LOADER

DUMP TRUCK

Total Biaya Sewa Dump Truck = 350 X Rp 372.828,10 = Rp 130.489.835,-

1 2 3 4 5 6 7 8 9 10 11 12
URAIAN COMPACTING
MIND MAP LAND CLEARING EMBANKMENT
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

URUTAN KERJA

SIKLUS
Meratakan
RINCIAN
Mengangkut material
dari quari ke
lapangan
DUMP TRUCK Memuat ke
dump truck
Tempat
MOTOR GRADER
material
4. Motor
3. Dump Grader
2. Wheel Truck
1. Quarry Loader
URAIAN COMPACTING
MIND MAP LAND CLEARING EMBANKMENT
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

STEP 1
URUTAN KERJA

SIKLUS

Sub Base Course 0,35 m


RINCIAN
7 Km
STEP 2
DUMP TRUCK

MOTOR GRADER

Base Course 0,20 m

7 Km
Gambar 9. Siklus Embankment
Sumber : Leosentosa, 2010
URAIAN COMPACTING
MIND MAP LAND CLEARING EMBANKMENT
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

URUTAN KERJA

SurfaceCourse
Surface Course 7 cm
SIKLUS

Base Course
9800 m3
RINCIAN
Batu Pecah kelas A
20 cm 9800 m3
DUMP TRUCK

MOTOR GRADER Subbase Course 17150 m3


35 cm
Sirtu Kelas A

1 2
URAIAN COMPACTING
MIND MAP LAND CLEARING EMBANKMENT
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

URUTAN KERJA

SIKLUS

RINCIAN

DUMP TRUCK

MOTOR GRADER

1 2
URAIAN COMPACTING
MIND MAP LAND CLEARING EMBANKMENT
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

URUTAN KERJA
Total biaya sewa Dump Truck untuk
Pengangkutan Material Embankment
SIKLUS

RINCIAN
Produktifitas = 40 M3/Jam
Total Biaya Sewa Alat / Jam = Rp 372.828,10
DUMP TRUCK Volume Material Base Course = 9.800 M3
Waktu Pekerjaan Yang Dibutuhkan = 9.800 / 40 = 245 Jam
MOTOR GRADER
Asumsi Waktu Kerja Efektif Alat Berat Dalam 1 Hari = 7 Jam
Jadi, Waktu Hari Yang Dibutuhkan = 245/7 = 35 Hari / 1 Alat

Waktu Dengan 7 Dump Truck = 35/7 = 5 Hari.

Total Biaya Sewa Dump truck = 245 jam X Rp 372.828,10 = Rp


91.342.884,5 1 2
URAIAN COMPACTING
MIND MAP LAND CLEARING EMBANKMENT
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

URUTAN KERJA
Total biaya sewa Dump Truck untuk
Pengangkutan Material Embankment
SIKLUS

RINCIAN Produktifitas = 40 M3/Jam


Total Biaya Sewa Alat / Jam = Rp 372.828,10
DUMP TRUCK Volume Material Subbase Course = 17150 M3
Waktu Pekerjaan Yang Dibutuhkan = 17150 / 40 = 428,75 Jam

MOTOR GRADER Asumsi Waktu Kerja Efektif Alat Berat Dalam 1 Hari = 7 Jam
Jadi, Waktu Hari Yang Dibutuhkan = 428,75/7 = 61,25 ~ 62 Hari / 1 Alat

Waktu Dengan 9 Dump Truck = 62/9 = 6,9 ~ 7 Hari.

Total Biaya Sewa Dump Truck= 428,75 X Rp 372.828,10 = Rp


159.850.047,9
1 2
URAIAN COMPACTING
MIND MAP LAND CLEARING EMBANKMENT
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

URUTAN KERJA

SIKLUS

RINCIAN

DUMP TRUCK

MOTOR GRADER

Gambar 10. Motor Grader

Untuk meratakan agregat


1 2 3 4 5 6 7 8 9 10
URAIAN COMPACTING
MIND MAP LAND CLEARING EMBANKMENT
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

URUTAN KERJA

No. URAIAN KODE KOEF. SATUAN


SIKLUS

A. URAIAN PERALATAN
RINCIAN
1. Jenis Peralatan MOTOR GRADER >100 HP
DUMP TRUCK
2. Tenaga Pw 136,0 HP

MOTOR GRADER 3. Kapasitas Cp 10.800,0 -


Alat Baru
4. : a. Umur Ekonomis A 5,0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2.000,0 Jam
c. Harga Alat B 760.000.000 Rupiah

1 2 3 4 5 6 7 8 9 10
URAIAN COMPACTING
MIND MAP LAND CLEARING EMBANKMENT
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

URUTAN KERJA
B. BIAYA PASTI PER JAM KERJA
SIKLUS 1. Nilai Sisa Alat = 10 % x B C 76.000.000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0,26380 -


RINCIAN (1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal
DUMP TRUCK = (B-C)xD E 90.218,74 Rupiah
W

MOTOR GRADER b. Asuransi, dll = 0,002 x B F 760,00 Rupiah


W

Biaya Pasti per Jam = (E+F) G 90.978,74 Rupiah

1 2 3 4 5 6 7 8 9 10
URAIAN COMPACTING
MIND MAP LAND CLEARING EMBANKMENT
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

URUTAN KERJA C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 179.520,00 Rupiah


SIKLUS
2. Pelumas = (2.5%-3%) x Pw x Mp I 37.400,00 Rupiah

RINCIAN Biaya bengkel (6.25% dan 8.75%) x B J 33.250 Rupiah


W

DUMP TRUCK 3. Perawatan dan (12,5 % - 17,5 %) x B K 47.500,00 Rupiah


perbaikan = W

MOTOR GRADER 4. Operator = ( 1 Orang / Jam ) x U1 L 12.982,14 Rupiah


Pembantu
5. Operator = ( 1 Orang / Jam ) x U2 M 9.410,71 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 320.062,86 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 411.041,60 Rupiah

1 2 3 4 5 6 7 8 9 10
URAIAN COMPACTING
MIND MAP LAND CLEARING EMBANKMENT
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

URUTAN KERJA

SIKLUS

RINCIAN

DUMP TRUCK

MOTOR GRADER

1 2 3 4 5 6 7 8 9 10
URAIAN COMPACTING
MIND MAP LAND CLEARING EMBANKMENT
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

URUTAN KERJA

SIKLUS

RINCIAN

DUMP TRUCK

MOTOR GRADER

1 2 3 4 5 6 7 8 9 10
URAIAN COMPACTING
MIND MAP LAND CLEARING EMBANKMENT
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

Lebar Blade Efektif


URUTAN KERJA
Panjang Pisau Panjang / Lebar / Pisau Efektif (m)
(m) Sudut Pisau 60 Sudut Pisau 45
SIKLUS
2,2 1,9 1,6
2,5 2,2 1,8
RINCIAN
2,8 2,4 2,0
3,05 2,6 2,2
DUMP TRUCK
3,1 2,7 2,2
3,4 2,9 2,4
MOTOR GRADER
3,7 3,2 2,6
4,0 3,5 2,8
4,3 3,7 3,0
4,9 4,2 3,5
Sumber : Leosentosa, 2015 1 2 3 4 5 6 7 8 9 10
URAIAN COMPACTING
MIND MAP LAND CLEARING EMBANKMENT
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

URUTAN KERJA

SIKLUS
Tabel Efisiensi Kerja
RINCIAN Kondisi Kerja Efisiensi

Pemeliharaan Jalan 0,8


DUMP TRUCK Pelebaran dan perataan 0,7
Sumber : Leosentosa, 2015
MOTOR GRADER

1 2 3 4 5 6 7 8 9 10
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

URUTAN KERJA

SIKLUS
Tabel Efisiensi Kerja
RINCIAN Kondisi Kerja Efisiensi

Pemeliharaan Jalan 0,8


DUMP TRUCK Pelebaran dan perataan 0,7
Sumber : Leosentosa, 2015
MOTOR GRADER

1 2 3 4 5 6 7 8 9 10
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

URUTAN KERJA

SIKLUS

RINCIAN

DUMP TRUCK

MOTOR GRADER

1 2 3 4 5 6 7 8 9 10
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

URUTAN KERJA Luas Jalan = 49.000 M2


Jumlah Lapisan = 2 Lapis
SIKLUS Waktu Pengerjaan
= Luas Jalan / Produktifitas Alat (Q)
RINCIAN = 49.000 / 2.195,75
= 23 Jam / Alat / Lapis
DUMP TRUCK Untuk 2 Lapisan = 23 X 2 = 46 Jam / Alat / Lapis

Asumsi Waktu Kerja Efektif Alat Berat Dalam 1 Hari = 7 Jam


MOTOR GRADER
Jadi, Waktu Hari Yang Dibutuhkan = 46/7 = 6,57 ~ 7 Hari / Alat

Waktu Dengan 2 Motor Grader = 7/2 = 3,5 ~ 4 Hari.


Total Biaya Sewa Alat = 46 X Rp 411.041,60 = Rp 18.907.913,6

1 2 3 4 5 6 7 8 9 10
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN

ASPHALT MOBILISASI DAN


COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

PENGERTIAN Manfaatnya

Mengurangi sifat
URUTAN KERJA
kembang susut
tanahhere.
SIKLUS Usaha untuk mengurangi
rongga-ronga udara dan
WATER TANKER air yang semula ada
diantara butiran tanah. Mengurangi
permeabilitas
VIBRATORY ROLLER

Memperbaiki kuat
geser tanah
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN

ASPHALT MOBILISASI DAN


COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

PENGERTIAN

URUTAN KERJA

SIKLUS
Menyiram
2
WATER TANKER

VIBRATORY ROLLER Material yang


sudah diratakan 1 Menggilas
3
Motor Grader
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN

ASPHALT MOBILISASI DAN


COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

PENGERTIAN

URUTAN KERJA

SIKLUS

WATER TANKER

VIBRATORY ROLLER

Gambar 11. Siklus Compacting


Sumber : Leosentosa, 2010
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN

ASPHALT MOBILISASI DAN


COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

PENGERTIAN

URUTAN KERJA

SIKLUS

WATER TANKER

VIBRATORY ROLLER

Gambar 12. Water Tanker


Berfungsi untuk menyiramkan air pada
tiap base.
1 2 3 4 5 6
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN

ASPHALT MOBILISASI DAN


COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

PENGERTIAN

URUTAN KERJA No. URAIAN KODE KOEF. SATUAN

SIKLUS
A. URAIAN PERALATAN
1. Jenis Peralatan WATER TANKER 3000-4500 L.
WATER TANKER 2. Tenaga Pw 100,0 HP
3. Kapasitas Cp 4.000,0 Liter
Alat Baru
VIBRATORY ROLLER 4. : a. Umur Ekonomis A 5,0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2.000,0 Jam
c. Harga Alat B 320.000.000 Rupiah

1 2 3 4 5 6
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN

ASPHALT MOBILISASI DAN


COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

PENGERTIAN
BIAYA PASTI PER JAM
B. KERJA
URUTAN KERJA 1. Nilai Sisa Alat = 10 % x B C 32.000.000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0,26380 -


SIKLUS
(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal
WATER TANKER
= (B-C)xD E 37.986,84 Rupiah
W
VIBRATORY ROLLER
b. Asuransi, dll = 0,002 x B F 320,00 Rupiah
W

Biaya Pasti per Jam


= (E+F) G 38.306,84 Rupiah

1 2 3 4 5 6
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN

ASPHALT MOBILISASI DAN


COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

C. BIAYA OPERASI PER JAM KERJA


PENGERTIAN
1. Bahan Bakar = (12%-15%) x Pw x Ms H 132.000,00 Rupiah

URUTAN KERJA 2. Pelumas = (2.5%-3%) x Pw x Mp I 27.500,00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 14.000 Rupiah


SIKLUS W

3. Perawatan dan (12,5 % - 17,5 %) x B K 20.000,00 Rupiah


WATER TANKER perbaikan
= W

4. Operator = ( 1 Orang / Jam ) x U1 L 12.982,14 Rupiah


VIBRATORY ROLLER Pembantu
5. Operator = ( 1 Orang / Jam ) x U2 M 9.410,71 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 215.892,86 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 254.199,69 Rupiah

1 2 3 4 5 6
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN

ASPHALT MOBILISASI DAN


COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

Total Volume timbunan : 26.950 m3


PENGERTIAN
Kadar air optimu (Lap.Mekanika Tanah 1) : 15 %
URUTAN KERJA Volume air yang dibutuhkan : 26.950 x 15 %= 4.043 m3
: 4.043.000 liter
SIKLUS
Kapasitas Tangki : 4.000 liter

WATER TANKER Jumlah Water yang digunakan : 4 unit


1 truck (Kt) : 1010625 liter
VIBRATORY ROLLER
Jarak sumber air (L) : 3.000 m
Rute 1 truck (s) : 3.500 m
Kebutuhan air (w) : 290 l/meter panjang
Kecepatan gerak (m/jam) : 10.000 m/jam
1 2 3 4 5 6
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN

ASPHALT MOBILISASI DAN


COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

Produktivitas
PENGERTIAN
𝑊(𝑙𝑒𝑏𝑎𝑟) 𝑥 𝑆 𝑥 𝐿
Produktifitas: = 17,02 m3/jam
𝐾𝑡
URUTAN KERJA
Efektif kerja dalam 1 hari adalah 7 jam, maka produktifitas
kerja Water Tank Truck adalah :
SIKLUS
P = 17,02 m3/jam x 7 jam
=119,14 m3
WATER TANKER
Makawaktu yang dibutuhkan Water Tank Truck
dalammenyelesaikanpekerjaannyaadalah:
VIBRATORY ROLLER
W : 4.043/119,14=32 hari
Dengan 4 water tanker
W= 32/4 = 8 hari
Total Biaya Sewa Water Tanker = 17,02 X Rp 254.199,69 = Rp 4.326.478,-

1 2 3 4 5 6
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN

ASPHALT MOBILISASI DAN


COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

PENGERTIAN

URUTAN KERJA

SIKLUS

WATER TANKER

VIBRATORY ROLLER

Gambar 13. Vibratory Roller


Untuk meratakan material yang bersifat kasar.
Sistem kerjanya dengan getaran
1 2 3 4 5 6 7
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN

ASPHALT MOBILISASI DAN


COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

PENGERTIAN

URUTAN KERJA KOD


No. URAIAN E KOEF. SATUAN

SIKLUS

A. URAIAN PERALATAN
WATER TANKER VIBRATORY ROLLER 1004 –
1. Jenis Peralatan 40TW.
2. Tenaga Pw 130,0 HP
VIBRATORY ROLLER
3. Kapasitas Cp 7,100 Ton
Alat Baru
4. : a. Umur Ekonomis A 5,0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2.000,0 Jam
c. Harga Alat B 635.000.000 Rupiah

1 2 3 4 5 6 7
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN

ASPHALT MOBILISASI DAN


COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

PENGERTIAN
B. BIAYA PASTI PER JAM KERJA
1. Nilai Sisa Alat = 10 % x B C 63.500.000 Rupiah
URUTAN KERJA
2. Faktor Angsuran Modal = i x (1 + i)^A D 0,26380 -
(1 + i)^A - 1
SIKLUS
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 75.380,13 Rupiah
WATER TANKER W

b. Asuransi, dll = 0,002 x B F 635,00 Rupiah


VIBRATORY ROLLER W

Biaya Pasti per Jam = (E+F) G 76.015,13 Rupiah

1 2 3 4 5 6 7
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN

ASPHALT MOBILISASI DAN


COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

PENGERTIAN C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 171.600,00 Rupiah


URUTAN KERJA
2. Pelumas = (2.5%-3%) x Pw x Mp I 35.750,00 Rupiah

SIKLUS Biaya bengkel (6.25% dan 8.75%) x B J 27.781 Rupiah


W

WATER TANKER 3. Perawatan dan (12,5 % - 17,5 %) x B K 39.687,50 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 12.982,14 Rupiah


VIBRATORY ROLLER Pembantu
5. Operator = ( 1 Orang / Jam ) x U2 M 9.410,71 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 297.211,61 Rupiah

TOTAL BIAYA SEWA ALAT / JAM = ( G + P


D. ) S 373.226,74 Rupiah

1 2 3 4 5 6 7
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN

ASPHALT MOBILISASI DAN


COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

PENGERTIAN
PRODUKTIFITAS
URUTAN KERJA
Q = (W x L x S ) / P
SIKLUS Ket :

W = Lebar pemadatan dalam suatu lintasan (m)


WATER TANKER
L = Tebal Lapisan (m)
VIBRATORY ROLLER
S = Kecepatan rata – rata ( km / jam )

P = Jumlah pass yang diperlukan dalam suatu kepadatan

1 2 3 4 5 6 7
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN

ASPHALT MOBILISASI DAN


COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

PENGERTIAN Subbase Course


Q = (W x L x S ) / P
URUTAN KERJA
= ( 2 x 0,35 x 15000 m/jam) / 6

SIKLUS
= 1.750 m/jam
= 1,75 km/jam
WATER TANKER Panjang lintasan total untuk 2 alat = 6 ( 2 x 4 x 3,5 ) = 168 km
Panjang lintasan untuk satu alat = 168/2 = 84 km
VIBRATORY ROLLER Jadi, waktu kerja per alat = 84 km / 1,75km/jam = 48 jam =7 hari

Total Biaya Sewa Vibratory Roller = 48 jam x 2 alat x 373.226,74 = Rp. 35.829.767,-

1 2 3 4 5 6 7
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN

ASPHALT MOBILISASI DAN


COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

PENGERTIAN
Base Course
Q = (W x L x S ) / P
URUTAN KERJA
= ( 2 x 0,2 x 15000 m/jam) / 4
SIKLUS = 1.500 m/jam
= 1,5 km/jam
WATER TANKER Panjang lintasan total untuk 2 alat = 4 ( 2 x 4 x 3,5 ) = 112 km
Panjang lintasan untuk satu alat = 112/2 = 56 km
VIBRATORY ROLLER
Jadi, waktu kerja per alat = 56 km / 1,5km/jam = 38 jam = 6 hari

Total Biaya Sewa Vibratory Roller = 38 jam x 2 alat x 373.226,74 = Rp. 28.365.232,-

1 2 3 4 5 6 7
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN

ASPHALT MOBILISASI DAN


COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

URUTAN KERJA
Pembersihan
SIKLUS permukaan lapisan
Base A dari debu Menyemprotkan aspal cair
ASPHALT SPRAYER dan kotoran.
01
02 dipadatkan
DUMP TRUCK menggunakan
Memasukkan Tandem roller dan
ASPHALT FINISHER agregat ke pneumatic tire roller
cool bin AMP
TANDEM ROLLER 03
04
Memasukkan aspal cair ke Hasil mixing dimasukkan
PNEUMATIC ROLLER campuran agregat, lalu kedalam dump truck dan
dicampur dan dipanaskan diangkat ke lokasi
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN

ASPHALT MOBILISASI DAN


COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

URUTAN KERJA STEP 1 Lapisan Dasar 1 STEP 2 Lapisan Bituminous

SIKLUS

ASPHALT SPRAYER

DUMP TRUCK

STEP 3 Lapisan Dasar 2 STEP 4 Lapisan Asphalt


ASPHALT FINISHER

TANDEM ROLLER

PNEUMATIC ROLLER
Gambar 14. Siklus Asphalt Pavement
Sumber : Leosentosa, 2010
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN

ASPHALT MOBILISASI DAN


COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

URUTAN KERJA

SIKLUS

ASPHALT SPRAYER

DUMP TRUCK

ASPHALT FINISHER

TANDEM ROLLER

PNEUMATIC ROLLER dalam pekerjaan jalan digunakan untuk Gambar 15. Asphalt Sprayer
Menyemprotkan aspal cair ke jalan
1 2 3 4 5
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN

ASPHALT MOBILISASI DAN


COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

URUTAN KERJA

KOD
SIKLUS No. URAIAN E KOEF. SATUAN

ASPHALT SPRAYER
A. URAIAN PERALATAN
1. Jenis Peralatan ASPHALT SPRAYER SS 1400AS
DUMP TRUCK 2. Tenaga Pw 4,0 HP
3. Kapasitas Cp 1400,0 Liter
Alat Baru
ASPHALT FINISHER 4. : a. Umur Ekonomis A 5,0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2.000,0 Jam
c. Harga Alat B 150.000.000 Rupiah
TANDEM ROLLER

PNEUMATIC ROLLER 5. Kapastas tangki aspal Ca 850 Liter

1 2 3 4 5
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN

ASPHALT MOBILISASI DAN


COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

URUTAN KERJA
B. BIAYA PASTI PER JAM KERJA
SIKLUS 1. Nilai Sisa Alat = 10 % x B C 15.000.000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0,26380 -


ASPHALT SPRAYER (1 + i)^A - 1
3. Biaya Pasti per Jam :

DUMP TRUCK a. Biaya Pengembalian Modal = (B-C)xD E 17.806,33 Rupiah


W

ASPHALT FINISHER b. Asuransi, dll = 0,002 x B F 150,00 Rupiah


W
TANDEM ROLLER
Biaya Pasti per Jam = (E+F) G 17.956,33 Rupiah

PNEUMATIC ROLLER

1 2 3 4 5
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN

ASPHALT MOBILISASI DAN


COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

C. BIAYA OPERASI PER JAM KERJA


URUTAN KERJA
1. Bahan Bakar = (12%-15%) x Pw x Ms H 5.280,00 Rupiah

SIKLUS Bahan Bakar Pemanas Aspal = 1/1000 *Ca*Ms H3 9.350,00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 1.100,00 Rupiah


ASPHALT SPRAYER
Biaya bengkel (6.25% dan 8.75%) x B J 6.563 Rupiah
W
DUMP TRUCK 3. Perawatan dan (12,5 % - 17,5 %) x B K 9.375,00 Rupiah

perbaikan = W
ASPHALT FINISHER
4. Operator = ( 1 Orang / Jam ) x U1 L 12.982,14 Rupiah
Pembantu
5. Operator = ( 1 Orang / Jam ) x U2 M 9.410,71 Rupiah
TANDEM ROLLER
Biaya Operasi per Jam = (H+I+K+L+M) P 54.060,36 Rupiah
PNEUMATIC ROLLER
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 72.016,69 Rupiah
1 2 3 4 5
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN

ASPHALT MOBILISASI DAN


COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

URUTAN KERJA Kapasitas Asphalt Sprayer = 1.400 L


Produktivitas = 5 L/m2
Luas total = 49.000 m2
SIKLUS
Kebutuhan total = 49.000 m2 x 5 L/m2 = 245.000 L aspal

ASPHALT SPRAYER 1 drum aspal cair = 156 L


Maka dibutuhkan = 245.000 L / 156 L = 1.580 drum.
@1 drum = Rp 1.700.000,-
DUMP TRUCK
Total biaya aspal cair = 1.580 x Rp 1.700.000,- = Rp 2.686.000.000,-
ASPHALT FINISHER Produktivitas = 60 m2/jam
Total waktu pengerjaan = 49.000 m2 x 60 m2/jam = 816,67 jam

TANDEM ROLLER
Total Biaya Sewa Asphalt Sprayer = 816,67 jam x Rp. 72.016,69
PNEUMATIC ROLLER = Rp. 58.813.870,-

1 2 3 4 5
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN

ASPHALT MOBILISASI DAN


COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

URUTAN KERJA

SIKLUS
ALAT ANGKUT ASPAL
ASPHALT SPRAYER

DUMP TRUCK

ASPHALT FINISHER

TANDEM ROLLER

PNEUMATIC ROLLER

Gambar 19. Dump Truck 1 2


URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN

ASPHALT MOBILISASI DAN


COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

URUTAN KERJA Jumlah Trip Loader = 10 Trip

SIKLUS Produktivitas Loader Per Siklus = 13,6 M3/Siklus


Menghitung Waktu Siklus Dump Truck pengangkutan aspal
Jarak dari AMP ke lokasi pekerjaan jalan = 6300 m
ASPHALT SPRAYER
Ctt = N X Ctl + D/V1 + T1 + D/V2 + T2
Ctt = 10 X 0.4 +(6300/666.67) +5(1,3) + (6300/1000) + 1,35 = 27,6
DUMP TRUCK Menit

ASPHALT FINISHER Menghitung Produktivitas Dump Truck


= C X 60/Ctt X Fat = 13,6 X (60/27,6) X 0.83 = 24 M3/Jam
TANDEM ROLLER
Lama Pengerjaan 3430 / 24 = 143 jam/alat
Untuk 1 unit truk = 143/7 = 20 hari
PNEUMATIC ROLLER
Total Biaya sewa Dump Truck= 143 jam x Rp 372.828,10 = Rp 53.314.418,-
1 2
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN

ASPHALT MOBILISASI DAN


COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

URUTAN KERJA

SIKLUS

ASPHALT SPRAYER

DUMP TRUCK

ASPHALT FINISHER

TANDEM ROLLER
Alat ini digunakan untuk menghamparkan proccesed material
PNEUMATIC ROLLER dari mixing plant dan untuk mendapatkan lapisan merata.
Gambar 16. Asphalt Finisher
1 2 3 4 5 6
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN

ASPHALT MOBILISASI DAN


COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

URUTAN KERJA

KOD
SIKLUS No. URAIAN E KOEF. SATUAN

ASPHALT SPRAYER
A. URAIAN PERALATAN
ASPHALT FINISHER HA 44W
DUMP TRUCK 1. Jenis Peralatan PAVER
2. Tenaga Pw 38,9 HP
3. Kapasitas Cp 4,9 Ton
ASPHALT FINISHER Alat Baru
4. : a. Umur Ekonomis A 5,0 Tahun
TANDEM ROLLER b. Jam Kerja Dalam 1 Tahun W 1.800,0 Jam
c. Harga Alat B 400.000.000 Rupiah

PNEUMATIC ROLLER

1 2 3 4 5 6
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN

ASPHALT MOBILISASI DAN


COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

URUTAN KERJA

B. BIAYA PASTI PER JAM KERJA


SIKLUS 1. Nilai Sisa Alat = 10 % x B C 40.000.000 Rupiah

ASPHALT SPRAYER 2. Faktor Angsuran Modal = i x (1 + i)^A D 0,26380 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
DUMP TRUCK
(B-C)x
a. Biaya Pengembalian Modal = D E 52.759,50 Rupiah

ASPHALT FINISHER W

b. Asuransi, dll = 0,002 x B F 444,44 Rupiah


TANDEM ROLLER W

PNEUMATIC ROLLER Biaya Pasti per Jam = (E+F) G 53.203,94 Rupiah

1 2 3 4 5 6
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN

ASPHALT MOBILISASI DAN


COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

C. BIAYA OPERASI PER JAM KERJA


URUTAN KERJA
1. Bahan Bakar = (12%-15%) x Pw x Ms H 51.348,00 Rupiah
SIKLUS 2. Pelumas = (2.5%-3%) x Pw x Mp I 10.697,50 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 19.444


ASPHALT SPRAYER W

3. Perawatan dan (12,5 % - 17,5 %) x B K 27.777,78 Rupiah


DUMP TRUCK perbaikan
= W

ASPHALT FINISHER 4. Operator = ( 1 Orang / Jam ) x U1 L 12.982,14 Rupiah


Pembantu
5. Operator = ( 1 Orang / Jam ) x U2 M 9.410,71 Rupiah
TANDEM ROLLER
Biaya Operasi per Jam
= (H+I+K+L+M) P 131.660,58 Rupiah
PNEUMATIC ROLLER
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 184.864,52 Rupiah
1 2 3 4 5 6
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN

ASPHALT MOBILISASI DAN


COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

URUTAN KERJA
Panjang jalan = 7 km = 7000 m
Lebar hamparan aspal = 7 meter
SIKLUS Tebal aspal = 7 cm
Volume aspal padat = 3430 m3
Faktor pemadatan = 8%
ASPHALT SPRAYER
Faktor kembang padat pemadatan = 1,08
Volume Aspal gembur = 3430 m3 x 1,08 = 3704 m3
DUMP TRUCK
DATA TEKNIS AMP
Produktivitas aspal panas (ACBC) = 1500 kg/batch = 0,556 m3
ASPHALT FINISHER Waktu yang diperlukan 1 batch = 3,50 menit
Waktu saat proses pemanasan aspal = 1 jam
Efisiensi kerja AMP = 0,9 (keadaaan baik)
TANDEM ROLLER Produktivitas AMP = 0,556 x 60 = 33,360 m3/jam

PNEUMATIC ROLLER

1 2 3 4 5 6
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

URUTAN KERJA

SIKLUS

ASPHALT SPAYER

DUMP TRUCK

ASPHALT FINISHER

TANDEM ROLLER

Total Biaya sewa Asphalt Finisher = 21,388 x Rp 184.864,52


PNEUMATIC ROLLER
= Rp 3.953.883,-
1 2 3 4 5 6
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

URUTAN KERJA TANDEM ROLLER


SIKLUS Untuk penggilasan akhir
pada proses asphalt
ASPHALT SPAYER pavement (permukaan
yang rata).
DUMP TRUCK

ASPHALT FINISHER

Gambar 18. Tandem Roller


TANDEM ROLLER Sumber : Besta, 2014

PNEUMATIC ROLLER

1 2 3 4 5
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

URUTAN KERJA

SIKLUS No. URAIAN KODE KOEF. SATUAN

ASPHALT SPAYER
A. URAIAN PERALATAN

DUMP TRUCK 1. Jenis Peralatan TANDEM ROLLER 6-8 T.

2. Tenaga Pw 28,0 HP
ASPHALT FINISHER
3. Kapasitas Cp 4,0 Ton
TANDEM ROLLER Alat Baru
4. : a. Umur Ekonomis A 5,0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2.000,0 Jam
PNEUMATIC ROLLER c. Harga Alat B 457.872.000 Rupiah

1 2 3 4 5
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

URUTAN KERJA
BIAYA PASTI PER JAM
B. KERJA
SIKLUS 1. Nilai Sisa Alat = 10 % x B C 45.787.200 Rupiah

ASPHALT SPAYER 2. Faktor Angsuran Modal = i x (1 + i)^A D 0,26380 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
DUMP TRUCK a. Biaya Pengembalian Modal
= (B-C)xD E 54.353,47 Rupiah
W
ASPHALT FINISHER
b. Asuransi, dll = 0,002 x B F 457,87 Rupiah
W
TANDEM ROLLER
Biaya Pasti per Jam = (E+F) G 54.811,34 Rupiah
PNEUMATIC ROLLER

1 2 3 4 5
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

URUTAN KERJA C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 36.960,00 Rupiah


SIKLUS
2. Pelumas = (2.5%-3%) x Pw x Mp I 7.700,00 Rupiah

ASPHALT SPAYER Biaya bengkel (6.25% dan 8.75%) x B J 20.032 Rupiah


W

DUMP TRUCK 3. Perawatan dan (12,5 % - 17,5 %) x B K 28.617,00 Rupiah


perbaikan
= W
ASPHALT FINISHER
4. Operator = ( 1 Orang / Jam ) x U1 L 12.982,14 Rupiah
Pembantu
TANDEM ROLLER 5. Operator = ( 1 Orang / Jam ) x U2 M 9.410,71 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 115.701,76 Rupiah


PNEUMATIC ROLLER
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 170.513,10 Rupiah
1 2 310 411 512
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

URUTAN KERJA

SIKLUS

ASPHALT SPAYER

DUMP TRUCK

ASPHALT FINISHER

TANDEM ROLLER

Total Biaya sewa Tandem Roller = 28,35 x Rp 170.513,1 = Rp 4.834.047,-


PNEUMATIC ROLLER

1 2 3 4 5
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

URUTAN KERJA

SIKLUS
Alat ini terdiri
dari roda-roda
ASPHALT SPAYER ban karet yang
susunan
DUMP TRUCK rodanya pada
bagian depan
selang-seling
ASPHALT FINISHER terhadap roda
bagian
belakang. Biasanya digunakan
TANDEM ROLLER
. sebagai penggilas
Gambar 17. Pneumatic Roller
lapisan hot mix.
PNEUMATIC ROLLER

1 2 3 4 5
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

URUTAN KERJA

No. URAIAN KODE KOEF. SATUAN


SIKLUS

ASPHALT SPAYER A. URAIAN PERALATAN

1. Jenis Peralatan PNEUMATIC ROLLER


DUMP TRUCK
2. Tenaga Pw 21,3 HP
ASPHALT FINISHER 3. Kapasitas Cp 3,0 Ton

TANDEM ROLLER 4. Alat Baru : a. Umur Ekonomis A 5,0 Tahun


b. Jam Kerja Dalam 1
Tahun W 2.000,0 Jam
PNEUMATIC ROLLER c. Harga Alat B 400.000.000 Rupiah

1 2 3 4 5
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

URUTAN KERJA
BIAYA PASTI PER JAM
B.
SIKLUS KERJA
1. Nilai Sisa Alat = 10 % x B C 40.000.000 Rupiah

ASPHALT SPAYER 2. Faktor Angsuran Modal = i x (1 + i)^A D 0,26380 -


(1 + i)^A - 1
DUMP TRUCK 3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal
= (B-C)xD E 47.483,55 Rupiah
ASPHALT FINISHER W

b. Asuransi, dll = 0,002 x B F 400,00 Rupiah


TANDEM ROLLER
W

PNEUMATIC ROLLER Biaya Pasti per Jam = (E+F) G 47.883,55 Rupiah

1 2 3 4 5
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

URUTAN KERJA C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 28.116,00 Rupiah


SIKLUS
2. Pelumas = (2.5%-3%) x Pw x Mp I 5.857,50 Rupiah

ASPHALT SPAYER 3. Biaya bengkel = (6.25% dan 8.75%) x B J 17.500 Rupiah


W

DUMP TRUCK 4. Perawatan dan (12,5 % - 17,5 %) x B K 25.000,00 Rupiah


perbaikan = W

ASPHALT FINISHER 5. Operator = ( 1 Orang / Jam ) x U1 L 12.982,14 Rupiah


Pembantu
6. Operator = ( 1 Orang / Jam ) x U2 M 9.410,71 Rupiah
TANDEM ROLLER
Biaya Operasi per Jam
= (H+I+K+L+M) P 98.866,36 Rupiah
PNEUMATIC ROLLER
D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 146.749,90 Rupiah
1 2 3 4 5
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

URUTAN KERJA PRODUKTIVITAS PNEUMATIC ROLLER

SIKLUS

ASPHALT SPAYER

DUMP TRUCK

ASPHALT FINISHER

TANDEM ROLLER
Total Biaya sewa Pneumatic Roller = 28,437 x Rp 146.749,90
PNEUMATIC ROLLER = Rp 4.173.127,-

1 2 310 411 512


URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

SIKLUS PRODUKTIVITAS PNEUMATIC ROLLER

WATER TANKER

7 Km

Gambar 20. Siklus Cooling


Sumber : Leosentosa, 2010
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

SIKLUS PRODUKTIVITAS PNEUMATIC ROLLER

WATER TANKER
BERFUNGSI
MENYIRAM AIR
SETELAH
PENGHAMPARAN

Gambar 21. Water Tanker

1 2 3
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

SIKLUS PRODUKTIVITAS PNEUMATIC ROLLER


Kapasitas Tangki : 4.000 liter
WATER TANKER Kebutuhan air total : 245.000 liter
Jumlah Water Tanker yang digunakan : 4 unit
1 truck (Kt) : 245.000 liter
Jarak sumber air (L) : 3.000 m
Rute 1 truck (s) : 3.500 m
Kebutuhan air (w) : 70 l/meter panjang
Kecepatan gerak (m/jam) : 10.000 m/jam`

1 2 3
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

SIKLUS PRODUKTIVITAS PNEUMATIC ROLLER

WATER TANKER

Total Biaya Sewa Water Tanker = 7,02 X Rp 254.199,69 = Rp 1.784.481,-

1 2 3
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

TRAILER PRODUKTIVITAS PNEUMATIC ROLLER

MOBILISASI

DEMOBILISASI

Gambar 22. Trailer

PENGANGKUT
ALAT BERAT

1 2 3 4
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

TRAILER PRODUKTIVITAS PNEUMATIC ROLLER


No. URAIAN KODE KOEF. SATUAN
MOBILISASI

DEMOBILISASI A. URAIAN PERALATAN

1. Jenis Peralatan TRAILER 26 TON

2. Tenaga Pw 175,0 HP

3. Kapasitas Cp 26,00 Ton


Alat Baru
4. : a. Umur Ekonomis A 6,0 Tahun
b. Jam Kerja Dalam 1
Tahun W 2.000,0 Jam
c. Harga Alat B 1.100.000.000 Rupiah

1 2 3 4
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

TRAILER PRODUKTIVITAS PNEUMATIC ROLLER


BIAYA PASTI PER JAM
B. KERJA
MOBILISASI 1. Nilai Sisa Alat = 10 % x B C 110.000.000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0,22961 -


DEMOBILISASI
(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal
= (B-C)xD E 113.655,65 Rupiah
W

b. Asuransi, dll = 0,002 x B F 1.100,00 Rupiah


W

Biaya Pasti per Jam = (E+F) G 114.755,65 Rupiah

1 2 3 4
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

TRAILER C. PRODUKTIVITAS PNEUMATIC ROLLER


BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 231.000,00 Rupiah


MOBILISASI
2. Pelumas = (2.5%-3%) x Pw x Mp I 48.125,00 Rupiah

DEMOBILISASI Biaya bengkel (6.25% dan 8.75%) x B J 48.125 Rupiah


W

3. Perawatan dan (12,5 % - 17,5 %) x B K 68.750,00 Rupiah


perbaikan
= W

4. Operator = ( 1 Orang / Jam ) x U1 L 12.982,14 Rupiah


Pembantu
5. Operator = ( 1 Orang / Jam ) x U2 M 9.410,71 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 418.392,86 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 533.148,51 Rupiah

2 11
1 10 3 12
4
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

TRAILER PRODUKTIVITAS PNEUMATIC ROLLER

MOBILISASI Mobilisasi dan demobilisasi proyek adalah


kegiatan mendatangkan ke lokasi
DEMOBILISASI
(mobilisasi) dan mengembalikan
(demobilisasi) alat-alat proyek dengan
menggunakan alat angkutan darat (trailer /
truck besar) atau alat angkut air (ponton).

1 2 3 4
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

TRAILER PRODUKTIVITAS PNEUMATIC ROLLER


2 Unit Wheel Loader

MOBILISASI 2 Unit Excavator

DEMOBILISASI 2 Unit Bulldozer

TOTAL = 18 UNIT 2 Unit Motor Grader


ALAT BERAT
2 Unit Vibratory Roller

4 Unit Asphalt Finisher

2 Unit Tandem Roller

2 Unit Pneumatic Roller


1 2 3 4
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

TRAILER PRODUKTIVITAS PNEUMATIC ROLLER

MOBILISASI

DEMOBILISASI

2 11
1 10 3 12
4
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

TRAILER PRODUKTIVITAS PNEUMATIC ROLLER


Produktivitas : 5 menit + 20 menit + 5 menit + 15 menit = 45 menit/alat
MOBILISASI
Mobilisasi total : 45 x 18 unit = 810 menit=13,5 jam
DEMOBILISASI
Mobilisasi dengan menggunakan 2 unit trailer = 13,5/2 = 6,75 jam = 1 hari
Jadi, Biaya Total mobilisasi alat adalah = 13,5 jam x Rp 533.148,51
= Rp 7.197.504,-

1 2 3 4
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

TRAILER

MOBILISASI

DEMOBILISASI

1 2
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

TRAILER Produktivitas : 5 menit + 27 menit + 5 menit + 20 menit = 57 menit/alat

MOBILISASI Mobilisasi total : 57 x 18 unit = 1026 menit=17,1 jam

DEMOBILISASI Mobilisasi dengan menggunakan 2 unit trailer = 17,5/2 = 8,75 jam

Jadi, Biaya Total demobilisasi alat adalah = 17,1 jam x Rp 533.148,51


= Rp 9.116.839,-

1 2
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

TABEL REKAPITULASI
ALAT
No Uraian Total Harga Sewa Alat
MATERIAL (Rupiah)
1 Mobilisasi Alat Berat 16.314.343
TIME SCHEDULE 2 Land Clearing 251.341.287
3 Embankment 290.100.844
4 Compacting 68.521.477
5 Asphalt Pavement 125.089.345
6 Cooling 1.784.481
total = 753.151.777
Jadi, total lama pekerjaan jalan : 95 hari dengan harga sewa Rp 753.151.777
1 2
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

TABEL REKAPITULASI
ALAT
No Jenis Bahan Harga (Rp) Satuan Volume

MATERIAL 1 Base Course 2.829.750.000 m3 9800

2 Sub Base Course 3.802.400.000 m3 17150


TIME SCHEDULE
3 Asphalt Cair 2.686.000.000 Liter 245000

4 Asphalt AC-BC 8.000.640.000 m3 3704


(gembur)
Total = Rp 17.318.790.000

Jadi, total biaya pekerjaan konstruksi jalan 7 km = Rp 753.151.777 + Rp


17.318.790.000
= Rp 18.073.743.900
18.064.545.990/ 49000 = Rp 369.000 / m2
1 2
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

ALAT

MATERIAL

TIME SCHEDULE

1 2
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

KESIMPULAN
Total biaya pekerjaan konstruksi jalan sepanjang 7 km yaitu :
DAFTAR PUSTAKA
Harga total sewa alat + Harga total bahan =

Rp 753.151.777 + Rp 17.318.790.000

= Rp 18.073.743.900

Harga pembuatan jalan permeter perseginya adalah

18.064.545.990/ 49000 = Rp 369.000 / m2


URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

KESIMPULAN
1. Apple Equipments. (2015). Bitumen Sprayer. Diambil kembali dari Apple Equipments:
http://appleequipment.tradeindia.com/bitumen-sprayer-262403.html
DAFTAR PUSTAKA
2. Besta. (2014, Agustus 14). Alat Berat yang Digunakan pada Proyek Jalan . Diambil
kembali dari Besta's Blog: http://bestananda.blogspot.co.id/2014/08/alat-berat-yang-
digunakan-pada-proyek.html

3. Besta. (2014, Agustus 14). Alat Berat yang Digunakan pada Proyek Pelabuhan . Diambil
kembali dari Besta's Blog: http://bestananda.blogspot.co.id/2014/08/alat-berat-yang-
digunakan-pada-proyek_96.html

4. Harga Hino. (2015). HINO FM 260 JW self loader. Diambil kembali dari Harga Hino:
http://www.hargahino.com/?HINO_SELF_LOADER
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

KESIMPULAN
5. Indo Alat Berat. (2015, April 3). Scania P420 + Lowbed Trailer Balikpapan. Diambil
kembali dari Jual Beli Alat Berat Indonesia: http://www.indoalatberat.com/trailer/scania-
DAFTAR PUSTAKA
p420-lowbed-trailer_i187

6. Sentosa, L. (2010, September 1). Alat Gali. Diambil kembali dari Leo Sentrosa Wordpress:
https://leosentosa0.files.wordpress.com/2010/09/5-alat-gali.pdf

7. Sentosa, L. (2010, September 1). Aplikasi Penggunaan Alat Berat. Diambil kembali dari
Leo Sentosa Wordpress: https://leosentosa0.files.wordpress.com/2010/09/13-aplikasi-
penggunaan-alat-berat.pdf

8. Sentosa, L. (2010, September 1). Dozer. Diambil kembali dari Leo Sentosa Wordpress:
https://leosentosa0.wordpress.com/category/ptm/
URAIAN
MIND MAP LAND CLEARING EMBANKMENT COMPACTING
PEKERJAAN
ASPHALT MOBILISASI DAN
COOLING REKAPITULASI PENUTUP
PAVEMENT DEMOBILISASI

KESIMPULAN 9. Sentosa, L. (2010, September 1). Dump Truck. Diambil kembali dari Leo Sentosa Wordpress:
https://leosentosa0.files.wordpress.com/2010/09/9-dump-truck.pdf
DAFTAR PUSTAKA
10. Sentosa, L. (2010, September 4). Klasifikasi Jalan. Diambil kembali dari Leo Lentosa Wordpress:
https://leosentosa0.wordpress.com/category/jalan-raya-i/page/2/

11. Sentosa, L. (2010, September 1). Loader. Diambil kembali dari Leo Sentosa Wordpress:
https://leosentosa0.files.wordpress.com/2010/09/8-loader.pdf

12. Sentosa, L. (2010, September 1). Motor Grader. Diambil kembali dari Leo Sentosa Wordpress:
https://leosentosa0.files.wordpress.com/2010/09/7-motor-grader.pdf

13. Sinomach. (2013). Ashpalt Paver. Diambil kembali dari China-Loader: http://www.china-
loader.com/product.asp?cid=19

Anda mungkin juga menyukai