ANALISA BIAYA KONSTRUKSI

PEKERJAAN PERSIAPAN

PA 6.1.
1 m' Pagar Sementara dari kayu tinggi 2 meter
6.1.1. Bahan
Kayu Laut/Dolken
1.250 Btg x
Semen Portland
2.500 Kg x
Pasir Beton
0.005 M3 x
Koral Beton
0.009 M3 x
Kayu 5/7
0.072 M3 x
Paku Biasa 2" - 5"
0.060 Kg x
Residu/colter
0.400 Lt
x
6.1.2. Tenaga
Tukang kayu
Pekerja
Kepala tukang
Mandor

0.200
0.400
0.020
0.020

Oh
Oh
Oh
Oh

Rp
20,750
Rp
1,200
Rp
102,000
Rp
159,500
Rp
3,144,900
Rp
10,120
Rp
20,460
Jumlah (1)

=
=
=
=
=
=
=
=

Rp
Rp
Rp
Rp
Rp
Rp
Rp
Rp

25,937.50
3,000.00
510.00
1,435.50
226,432.80
607.20
8,184.00
266,107.00

Rp
65,000
Rp
45,000
Rp
75,000
Rp
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

Rp
Rp
Rp
Rp
Rp
Rp

13,000.00
18,000.00
1,500.00
1,100.00
33,600.00
299,707.00

=
=
=
=
=
=
=
=

Rp
Rp
Rp
Rp
Rp
Rp
Rp
Rp

25,937.50
3,000.00
65,064.00
510.00
1,435.50
607.20
19,750.50
116,304.70

=
=
=
=
=
=

Rp
Rp
Rp
Rp
Rp
Rp

13,000.00
18,000.00
1,500.00
1,100.00
33,600.00
149,904.70

x Rp
3,144,900
x Rp
10,120
x Rp
3,144,900
Jumlah (1)

=
=
=
=

Rp
Rp
Rp
Rp

37,738.80
202.40
22,014.30
59,955.50

x
x
x
x

=
=
=
=
=
=

Rp
Rp
Rp
Rp
Rp
Rp

6,500.00
4,500.00
750.00
275.00
12,025.00
71,980.50

45,000 = Rp
55,000 = Rp
= Rp

4,500.00
2,750.00
7,250.00

x
x
x
x

PA 6.2.
1 m' Pagar sementara dari seng gelombang tinggi 2 meter
6.2.1. Bahan
Kayu Laut/Dolken
1.250 Btg x Rp
20,750
Semen Portland
2.500 Kg x Rp
1,200
Seng gelombang
1.200 Lbr x Rp
54,220
Pasir beton
0.005 M3 x Rp
102,000
Koral beton
0.009 M3 x Rp
159,500
Paku biasa 2" - 5"
0.060 Kg x Rp
10,120
Meni besi
0.450 Kg x Rp
43,890
Jumlah (1)
6.2.2. Tenaga
Tukang kayu
0.200 Oh x Rp
65,000
Pekerja
0.400 Oh x Rp
45,000
Kepala tukang
0.020 Oh x Rp
75,000
Mandor
0.020 Oh x Rp
55,000
Jumlah (2)
Jumlah (1) + (2)
PA 6.4
Pengukuran dan Pemasangan bouplank
6.4.1. Bahan
Kayu 5/7
0.012 M3
Paku biasa 2" - 5"
0.020 Kg
Kayu papan 3/20
0.007 M3
6.4.2. Tenaga
Tukang kayu
Pekerja
Kepala tukang
Mandor

PA 6.8
6.8.1

0.100
0.100
0.010
0.005

Oh
Oh
Oh
Oh

1 m Membersihkan lapangan dan perataan


Tenaga
Pekerja
0.100 Oh
Mandor
0.050 Oh

PA 6.12
1 m Pembuatan jalan sementara
6. 12.1 Bahan
Batu belah 15/20
0.150 M
Batu pecah 5/7
0.090 M
Pasir pasang
0.010 M
6.12.2 Tenaga
Pekerja
Mandor

1.000 Oh
0.050 Oh

Rp
65,000
Rp
45,000
Rp
75,000
Rp
55,000
Jumlah (2)
Jumlah (1) + (2)

x Rp
x Rp
Jumlah

x Rp
131,670
x Rp
143,430
x Rp
94,500
Jumlah (1)

=
=
=
=

Rp
Rp
Rp
Rp

19,750.50
12,908.70
945.00
33,604.20

x Rp
45,000
x Rp
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=

Rp
Rp
Rp
Rp

45,000.00
2,750.00
47,750.00
81,354.20

PA 6.13
1 m Bongkaran beton betulang
6.13.1 Tenaga
Pekerja
Mandor

6.667 Oh
0.333 Oh

PA 6.14
1m Bongkaran dinding tembok bata merah
6.14.1 Tenaga
Pekerja
6.667 Oh
Mandor
0.033 Oh

x Rp
x Rp
Jumlah

45,000 = Rp
55,000 = Rp
= Rp

300,015.00
18,315.00
318,330.00

x Rp
x Rp
Jumlah

45,000 = Rp
55,000 = Rp
= Rp

300,015.00
1,815.00
301,830.00

PA 6.15
1m Pasangan pagar kawat jaring galvanis, tinggi 1.00 m
6.15.1 Bahan
Kawat jaring galvanis/BRC
0.434 Lbr x Rp
184,800
Jumlah (1)
6.15.2. Tenaga
Pekerja
0.042 Oh x Rp
45,000
Kepala tukang
0.004 Oh x Rp
75,000
Tukang
0.042 Oh x Rp
65,000
Mandor
0.002 Oh x Rp
55,000
Jumlah (2)
Jumlah (1) + (2)
BERSAMBUNG : ABK PEKERJAAN TANAH

= Rp
= Rp

80,203.20
80,203.20

=
=
=
=
=
=

1,890.00
300.00
2,730.00
110.00
5,030.00
85,233.20

Rp
Rp
Rp
Rp
Rp
Rp

ANALISA BIAYA KONSTRUKSI


PEKERJAAN TANAH

PT 6.1. 1 m Galian tanah biasa sedalam 1 meter


6.1.1. Tenaga
Pekerja
0.400 Oh x Rp.
45,000
Mandor
0.040 Oh x Rp.
55,000
Jumlah (1)
PT 6.2. 1 m Galian tanah biasa sedalam 2 meter
6.2.1. Tenaga
Pekerja
0.400 Oh x Rp.
45,000
Mandor
0.040 Oh x Rp.
55,000
Jumlah (1)
PT 6.3. 1 m Galian tanah biasa sedalam 3 meter
6.3.1. Tenaga
Pekerja
0.400 Oh x Rp.
45,000
Mandor
0.040 Oh x Rp.
55,000
Jumlah (1)
PT 6.4. 1 m Galian tanah keras sedalam 1 meter
6.4. Tenaga
Pekerja
0.625 Oh x Rp.
45,000
Mandor
0.062 Oh x Rp.
55,000
Jumlah
PT 6.5. 1 m Galian tanah cadas sedalam 1 meter
6.5.1. Tenaga
Pekerja
1.250 Oh x Rp.
45,000
Mandor
0.125 Oh x Rp.
55,000
Jumlah
PT 6.6.. 1 m Galian tanah lumpur sedalam 1 meter
6.6.1. Tenaga
Pekerja
0.823 Oh x Rp.
45,000
Mandor
0.083 Oh x Rp.
55,000
Jumlah
PT 6.7. 1 m Pekerjaan stripping setinggi 1 meter
6.7.1. Tenaga
Pekerja
0.050 Oh x Rp.
45,000
Mandor
0.005 Oh x Rp.
55,000
Jumlah (1)
PT 6.8. 1 m Pembuangan tanah sejauh 150 meter
6.8.1. Tenaga
Pekerja
0.050 Oh x Rp.
45,000
Mandor
0.005 Oh x Rp.
55,000
Jumlah
PT 6.9. 1 m Urugan kembali
6.9.1. Tenaga
Pekerja
0.192 Oh x Rp.
45,000
Mandor
0.019 Oh x Rp.
55,000
Jumlah
PT 6.10. 1 m Pemadatan tanah
6.10.1.Tenaga
Pekerja
0.500 Oh x Rp.
45,000
Mandor
0.050 Oh x Rp.
55,000
Jumlah
PT 6.11. 1 m Urugan pasir
6.11.1.Bahan
Pasir urug
1.200 M x Rp.
65,200
Jumlah (1)
6.11.2.Tenaga
Pekerja
0.500 Oh x Rp.
45,000
Mandor
0.050 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)
PT 6.16. 1 m Pembuatan jalan sementara, tebal 25 cm
6.16.1.Bahan
Batu belah 10/15
0.275 M x Rp.
136,950
Batu koral 5/7
0.030 M x Rp.
159,500
Pasir pasang
0.050 M x Rp.
94,500
Jumlah (1)
6.16.2.Tenaga
Pekerja
0.500 Oh x Rp.
45,000
Mandor
0.050 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)
BERSAMBUNG : .ABK PEKERJAAN PONDASI.

=
=
=

Rp.
Rp.
Rp.

18,000.00
2,200.00
20,200.00

=
=
=

Rp.
Rp.
Rp.

18,000.00
2,200.00
20,200.00

=
=
=

Rp.
Rp.
Rp.

18,000.00
2,200.00
20,200.00

=
=
=

Rp.
Rp.
Rp.

28,125.00
3,410.00
31,535.00

=
=
=

Rp.
Rp.
Rp.

56,250.00
6,875.00
63,125.00

=
=
=

Rp.
Rp.
Rp.

37,035.00
4,565.00
41,600.00

=
=
=

Rp.
Rp.
Rp.

2,250.00
275.00
2,525.00

=
=

Rp.
Rp.
Rp.

2,250.00
275.00
2,525.00

=
=
=

Rp.
Rp.
Rp.

8,640.00
1,045.00
9,685.00

=
=
=

Rp.
Rp.
Rp.

22,500.00
2,750.00
25,250.00

=
=

Rp.
Rp.

78,240.00
78,240.00

=
=
=
=

Rp.
Rp.
Rp.
Rp.

22,500.00
2,750.00
25,250.00
103,490.00

=
=
=
=

Rp.
Rp.
Rp.
Rp.

37,661.25
4,785.00
4,725.00
47,171.25

=
=
=
=

Rp.
Rp.
Rp.
Rp.

22,500.00
2,750.00
25,250.00
72,421.25

ANALISA BIAYA KONSTRUKSI


PEKERJAAN PONDASI

PP 6.1.
1 M Pasangan pondasi batu kali, 1 Pc : 1 Ps
6.1.1. Bahan :
Batu belah 15/20
1.100 M
Semen porland
392.000 Kg
Pasir pasang
0.314 M
6.1.2. Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

1.500
0.600
0.060
0.075

Oh
Oh
Oh
Oh

PP 6.2.
1 M Pasang pondasi batu kali 1 Pc : 2 Ps
6.2.1. Bahan
Batu belah 15/20 cm
1.100 M
Semen porland
267.000 Kg
Pasir Pasang
0.427 M
6.2.2. Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

1.500
0.600
0.060
0.075

Oh
Oh
Oh
Oh

PP 6.3.
1 M Pasang pondasi batu kali, 1 Pc : 2,5 Ps
6.3.1. Bahan
Batu belah 15/20 cm
1.100 M
Semen porland
392.000 Kg
Pasir Pasang
0.314 M
6.3.2. Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

1.500
0.600
0.060
0.075

Oh
Oh
Oh
Oh

PP 6.4.
1 M Pasang pondasi batu kali, Pc : 3 Ps
6.4.1. Bahan
Batu belah 15/20 cm
1.100 M
Semen porland
202.000 Kg
Pasir Pasang
0.485 M
6.4.2. Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

1.500
0.600
0.060
0.075

Oh
Oh
Oh
Oh

PP 6.5.
1 M Pasang pondasi batu kali, 1 Pc : 4 Ps.
6.5.1. Bahan
Batu belah 15/20 cm
1.100 M
Semen porland
163.000 Kg
Pasir Pasang
0.520 M
6.5.2. Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

1.500
0.600
0.060
0.075

Oh
Oh
Oh
Oh

x Rp.
131,670.00
x Rp.
1,200.00
x Rp.
94,500.00
Jumlah (1)

=
=
=
=

Rp.
Rp.
Rp.
Rp.

144,837.00
470,400.00
29,673.00
644,910.00

x
x
x
x

Rp.
45,000.00
Rp.
65,000.00
Rp.
75,000.00
Rp.
55,000.00
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

67,500.00
39,000.00
4,500.00
4,125.00
115,125.00
760,035.00

x Rp.
131,670.00
x Rp.
1,200.00
x Rp.
94,500.00
Jumlah (1)

=
=
=
=

Rp.
Rp.
Rp.
Rp.

144,837.00
320,400.00
40,351.50
505,588.50

x
x
x
x

Rp.
45,000.00
Rp.
65,000.00
Rp.
75,000.00
Rp.
55,000.00
Jumlah (2)
Jumlah (1) +(2)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

67,500.00
39,000.00
4,500.00
4,125.00
115,125.00
620,713.50

x Rp.
131,670.00
x Rp.
1,200.00
x Rp.
94,500.00
Jumlah (1)

=
=
=
=

Rp.
Rp.
Rp.
Rp.

144,837.00
470,400.00
29,673.00
644,910.00

x
x
x
x

Rp.
45,000.00
Rp.
65,000.00
Rp.
75,000.00
Rp.
55,000.00
Jumlah (2)
Jumlah (1) +(2)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

67,500.00
39,000.00
4,500.00
4,125.00
115,125.00
760,035.00

x Rp.
131,670.00
x Rp.
1,200.00
x Rp.
94,500.00
Jumlah (1)

=
=
=
=

Rp.
Rp.
Rp.
Rp.

144,837.00
242,400.00
45,832.50
433,069.50

x
x
x
x

Rp.
45,000.00
Rp.
65,000.00
Rp.
75,000.00
Rp.
55,000.00
Jumlah (2)
Jumlah (1) +(2)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

67,500.00
39,000.00
4,500.00
4,125.00
115,125.00
548,194.50

x Rp.
131,670.00
x Rp.
1,200.00
x Rp.
94,500.00
Jumlah (1)

=
=
=
=

Rp.
Rp.
Rp.
Rp.

144,837.00
195,600.00
49,140.00
389,577.00

x
x
x
x

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

67,500.00
39,000.00
4,500.00
4,125.00
115,125.00
504,702.00

Rp.
45,000.00
Rp.
65,000.00
Rp.
75,000.00
Rp.
55,000.00
Jumlah (2)
Jumlah (1) +(2)

PP 6.6.
1 M Pasang pondasi batu kali, 1 Pc : 5 Ps
6.6.1. Bahan
Batu belah 15/20 cm
1.100 M
Semen porland
136.000 Kg
Pasir Pasang
0.544 M
6.6.2. Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

1.500
0.600
0.060
0.075

Oh
Oh
Oh
Oh

PP 6.7.
1 M Pasang pondasi batu kali, 1 Pc : 6 Ps
6.7.1. Bahan
Batu belah 15/20 cm
1.100 M
Semen porland
117.000 Kg
Pasir Pasang
0.561 M
6.7.2. Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

PP 6.14. 1 M Pasang pondasi batu kosong


6.14.1. Bahan
Batu belah 10/15 cm
Pasir urug

1.500
0.600
0.060
0.075

Oh
Oh
Oh
Oh

x Rp.
131,670.00
x Rp.
1,200.00
x Rp.
94,500.00
Jumlah (1)

=
=
=
=

Rp.
Rp.
Rp.
Rp.

144,837.00
163,200.00
51,408.00
359,445.00

x
x
x
x

Rp.
45,000.00
Rp.
65,000.00
Rp.
75,000.00
Rp.
55,000.00
Jumlah (2)
Jumlah (1) +(2)

=
=
=
=

Rp.
Rp.
Rp.
Rp.

67,500.00
39,000.00
4,500.00
4,125.00
115,125.00
474,570.00

x Rp.
131,670.00
x Rp.
1,200.00
x Rp.
94,500.00
Jumlah (1)

=
=
=
=

Rp.
Rp.
Rp.
Rp.

144,837.00
140,400.00
53,014.50
338,251.50

x
x
x
x

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

67,500.00
39,000.00
4,500.00
4,125.00
115,125.00
453,376.50

Rp.
45,000.00
Rp.
65,000.00
Rp.
75,000.00
Rp.
55,000.00
Jumlah (2)
Jumlah (1) +(2)

1.200 M
0.300 M

x Rp.
136,950.00
x Rp.
94,500.00
Jumlah (1)

= Rp.
= Rp.
= Rp.

164,340.00
28,350.00
192,690.00

0.780
0.390
0.039
0.039

Oh
Oh
Oh
Oh

x
x
x
x

Rp.
45,000.00
Rp.
65,000.00
Rp.
75,000.00
Rp.
55,000.00
Jumlah (2)
Jumlah (1) +(2)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

35,100.00
25,350.00
2,925.00
2,145.00
65,520.00
258,210.00

PP 6.15. 1 M Pasang pondasi siklop 40 % batu kali


6.15.1. Bahan
Besi beton
75.000
Semen portland
202.000
Pasir beton
0.320
Koral beton
0.490
Kawat beton
0.800

Kg
Kg
Kg
M
Kg

x
x
x
x
x

Rp.
12,390.00
Rp.
1,200.00
Rp.
102,000.00
Rp.
175,890.00
Rp.
11,620.00
Jumlah (1)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

929,250.00
242,400.00
32,640.00
86,186.10
9,296.00
1,299,772.10

Oh
Oh
Oh
Oh

x
x
x
x

Rp.
45,000.00
Rp.
65,000.00
Rp.
75,000.00
Rp.
55,000.00
Jumlah (2)
Jumlah (1) +(2)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

135,000.00
55,250.00
6,375.00
8,250.00
204,875.00
1,504,647.10

x Rp.
131,670.00
x Rp.
1,200.00
x Rp.
94,500.00
Jumlah (1)

=
=
=
=

Rp.
Rp.
Rp.
Rp.

59,251.50
336,000.00
63,315.00
458,566.50

x
x
x
x

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

107,100.00
19,500.00
2,250.00
4,400.00
133,250.00
591,816.50

6.14.2. Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

6.15.2. Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

3.000
0.850
0.085
0.150

PP 6.16. 1 M Pasang pondasi sumuran diameter 100 Cm


6.16.1. Bahan
Batu belah 15/20 cm
0.450 M
Semen portland
280.000 Kg
Pasir Pasang
0.670 M
6.16.2. Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

2.380
0.300
0.030
0.080

Oh
Oh
Oh
Oh

Rp.
45,000.00
Rp.
65,000.00
Rp.
75,000.00
Rp.
55,000.00
Jumlah (2)
Jumlah (1) +(2)

PP 6.17. 1 M Pembuatan tiang pancang (40 x 40) Cm, beton bertulang


6.17.1. Bahan
Pasir urug darat
0.019 M x Rp.
65,200.00
Pasir beton
0.094 M x Rp.
102,000.00
Koral beton
0.150 M x Rp.
175,890.00
Semen porland
60.500 Kg x Rp.
1,200.00
Besi beton
45.000 Kg x Rp.
12,390.00
Kawat beton
0.900 Kg x Rp.
11,620.00
Kayu kaso 5/7
0.032 M x Rp. 3,144,900.00
Paku
0.120 Kg x Rp.
10,120.00
Minyak bekisting
0.090 Lt
x Rp.
5,720.00
Plamur tembok
0.240 Kg x Rp.
14,300.00
Jumlah (1)
6.17.2. Tenaga
Pekerja
1.000 Oh x Rp.
45,000.00
Tukang batu
0.670 Oh x Rp.
65,000.00
Kepala tukang
0.067 Oh x Rp.
75,000.00
Mandor
0.050 Oh x Rp.
55,000.00
Jumlah (2)
Jumlah (1) +(2)
PP 6.18. 1 M Pembuatan tiang pancang (35 x 35) Cm, beton bertulang
6.18.1. Bahan
Pasir urug darat
0.016 M x Rp.
65,200.00
Pasir beton
0.080 M x Rp.
102,000.00
Koral beton
0.125 M x Rp.
175,890.00
Semen porland
49.000 Kg x Rp.
1,200.00
Besi beton
34.500 Kg x Rp.
12,390.00
Kawat beton
0.700 Kg x Rp.
11,620.00
Kayu kaso 5/7
0.027 M x Rp. 3,144,900.00
Paku
0.120 Kg x Rp.
10,120.00
Minyak bekisting
0.090 Lt
x Rp.
5,720.00
Plamur tembok
0.200 Kg x Rp.
14,300.00
Jumlah (1)
6.18.2. Tenaga
Pekerja
0.800 Oh x Rp.
45,000.00
Tukang batu
0.500 Oh x Rp.
65,000.00
Kepala tukang
0.050 Oh x Rp.
75,000.00
Mandor
0.040 Oh x Rp.
55,000.00
Jumlah (2)
Jumlah (1) +(2)
BERSAMBUNG : . ABK PEKERJAAN DINDING

=
=
=
=
=
=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

1,238.80
9,588.00
26,383.50
72,600.00
557,550.00
10,458.00
100,636.80
1,214.40
514.80
3,432.00
783,616.30

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

45,000.00
43,550.00
5,025.00
2,750.00
96,325.00
879,941.30

=
=
=
=
=
=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

1,043.20
8,160.00
21,986.25
58,800.00
427,455.00
8,134.00
84,912.30
1,214.40
514.80
2,860.00
615,079.95

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

36,000.00
32,500.00
3,750.00
2,200.00
74,450.00
689,529.95

ANALISA BIAYA KONSTRUKSI


PEKERJAAN DINDING

PD 6.1.
1 M Pasangan bata merah tebal 1 bata, 1 Pc : 1 Ps
6.1.1. Bahan
Bata merah 5 x 10 x 20 cm
140.000 Bh x
Semen portland
64.030 Kg x
Pasir pasang
0.059 M x
6.1.2

PD 6.2
6.2.1

6.2.2

PD 6.3
6.3.1

6.3.2

PD 6.4
6.4.1

6.4.2

PD 6.8
6.8.1

Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

650
1,200
94,500
Jumlah (1)

=
=
=
=

Rp
Rp
Rp
Rp

91,000.00
76,836.00
5,575.50
173,411.50

Oh
Oh
Oh
Oh

x
x
x
x

Rp.
Rp.
Rp.
Rp.

45,000
65,000
75,000
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

Rp
Rp
Rp
Rp
Rp
Rp

29,250.00
13,000.00
1,500.00
1,650.00
45,400.00
218,811.50

1m Pasangan bata merah tebal 1 bata, 1Pc : 2 Ps


Bahan
Bata merah 5 x 10 x 20 cm
140.000 Bh
Semen portland
43.500 Kg
Pasir pasang
0.080 M

x
x
x

Rp.
Rp.
Rp.

650
1,200
94,500
Jumlah (1)

=
=
=
=

Rp
Rp
Rp
Rp

91,000.00
52,200.00
7,560.00
150,760.00

Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

x
x
x
x

Rp.
Rp.
Rp.
Rp.

45,000
65,000
75,000
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

Rp
Rp
Rp
Rp
Rp
Rp

29,250.00
13,000.00
1,500.00
1,650.00
45,400.00
196,160.00

1 m Pasangan bata merah tebal 1 bata, 1Pc : 3 Ps


Bahan
Bata merah 5 x 10 x 20 cm
140.000 Bh x
Semen portland
32.950 Kg x
Pasir pasang
0.091 M x

Rp.
Rp.
Rp.

650
1,200
94,500
Jumlah (1)

=
=
=
=

Rp
Rp
Rp
Rp

91,000.00
39,540.00
8,599.50
139,139.50

Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

x
x
x
x

Rp.
Rp.
Rp.
Rp.

45,000
65,000
75,000
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

Rp
Rp
Rp
Rp
Rp
Rp

29,250.00
13,000.00
1,500.00
1,650.00
45,400.00
184,539.50

1 m Pasangan bata merah tebal 1 bata, 1Pc : 4 Ps


Bahan
Bata merah 5 x 10 x 20 cm
140.000 Bh x
Semen portland
26.550 Kg x
Pasir pasang
0.093 M x

Rp.
Rp.
Rp.

650
1,200
94,500
Jumlah (1)

=
=
=
=

Rp
Rp
Rp
Rp

91,000.00
31,860.00
8,788.50
131,648.50

Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

x
x
x
x

Rp.
Rp.
Rp.
Rp.

45,000
65,000
75,000
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

Rp
Rp
Rp
Rp
Rp
Rp

29,250.00
13,000.00
1,500.00
29,250.00
43,750.00
175,398.50

1 m Pasangan bata merah tebal 1/2 bata, 1Pc : 1 Ps


Bahan
Bata merah 5 x 10 x 20 cm
70.000 Bh x
Semen portland
27.800 Kg x
Pasir pasang
0.028 M x

Rp.
Rp.
Rp.

650
1,200
94,500
Jumlah (1)

=
=
=
=

Rp
Rp
Rp
Rp

45,500.00
33,360.00
2,646.00
81,506.00

Rp.
Rp.
Rp.
Rp.

45,000
65,000
75,000
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

Rp
Rp
Rp
Rp
Rp
Rp

14,400.00
6,500.00
750.00
825.00
22,475.00
103,981.00

6.8.2 Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

0.650
0.200
0.020
0.030

Rp.
Rp.
Rp.

0.650
0.200
0.020
0.030

0.650
0.200
0.020
0.030

0.650
0.200
0.020
0.030

0.320
0.100
0.010
0.015

Oh
Oh
Oh
Oh

Oh
Oh
Oh
Oh

Oh
Oh
Oh
Oh

Oh
Oh
Oh
Oh

x
x
x
x

PD 6.9
6.9.1

1 m Pasangan bata merah tebal 1/2 bata, 1Pc : 2 Ps


Bahan
Bata merah 5 x 10 x 20 cm
70.000 Bh x
Semen portland
18.950 Kg x
Pasir pasang
0.038 M x

Rp.
Rp.
Rp.

650
1,200
94,500
Jumlah (1)

=
=
=
=

Rp
Rp
Rp
Rp

45,500.00
22,740.00
3,591.00
71,831.00

Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

x
x
x
x

Rp.
Rp.
Rp.
Rp.

45,000
65,000
75,000
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

Rp
Rp
Rp
Rp
Rp
Rp

14,400.00
6,500.00
750.00
825.00
22,475.00
94,306.00

PD 6.10 1 m Pasangan bata merah tebal 1/2 bata, 1Pc : 3 Ps


6.10.1 Bahan
Bata merah 5 x 10 x 20 cm
70.000 Bh x
Semen portland
14.370 Kg x
Pasir pasang
0.040 M x

Rp.
Rp.
Rp.

650
1,200
94,500
Jumlah (1)

=
=
=
=

Rp
Rp
Rp
Rp

45,500.00
17,244.00
3,780.00
66,524.00

x
x
x
x

Rp.
Rp.
Rp.
Rp.

PD 6.11 1 m Pasangan bata merah tebal 1/2 bata, 1Pc : 4 Ps


6.11.1 Bahan
Bata merah 5 x 10 x 20 cm
70.000 Bh x
Semen portland
11.500 Kg x
Pasir pasang
0.043 M x

45,000
65,000
75,000
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

Rp
Rp
Rp
Rp
Rp
Rp

14,400.00
6,500.00
750.00
825.00
22,475.00
88,999.00

Rp.
Rp.
Rp.

650
1,200
94,500
Jumlah (1)

=
=
=
=

Rp
Rp
Rp
Rp

45,500.00
13,800.00
4,063.50
63,363.50

6.9.2

6.10.2 Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

6.11.2 Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

0.320
0.100
0.010
0.015

0.320
0.100
0.010
0.015

Oh
Oh
Oh
Oh

Oh
Oh
Oh
Oh

0.320
0.100
0.010
0.015

Oh
Oh
Oh
Oh

x
x
x
x

Rp.
Rp.
Rp.
Rp.

PD 6.21 1 m Pasangan dinding Conblock (HB.20)


6.21.1 Bahan
Concrete block (CB 20)
12.500
Semen portland
14.050
Pasir beton
0.004
Pasir pasang
0.042
Besi beton polos
3.870
Paku biasa 2" - 5"
0.006
Kayu sembarang
0.001
Kawat beton
0.030
Koral beton
0.005

45,000
65,000
75,000
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

Rp
Rp
Rp
Rp
Rp
Rp

14,400.00
6,500.00
750.00
825.00
22,475.00
85,838.50

Bh
Kg
M
M
Bh
Kg
M
Kg
M

x
x
x
x
x
x
x
x
x

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

2,650
1,200
102,000
94,500
15,000
10,120
3,144,900
11,620
175,890
Jumlah (1)

=
=
=
=
=
=
=
=
=
=

Rp
Rp
Rp
Rp
Rp
Rp
Rp
Rp
Rp
Rp

33,125.00
16,860.00
408.00
3,969.00
58,050.00
60.72
3,144.90
348.60
879.45
116,845.67

0.370
0.157
0.007
0.0164
0.0185

Oh
Oh
Oh
Oh
Oh

x
x
x
x
x

Rp.
Rp.
Rp.
Rp.
Rp.

45,000
65,000
65,000
75,000
75,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=
=

Rp
Rp
Rp
Rp
Rp
Rp
Rp

16,650.00
10,205.00
455.00
1,230.00
1,387.50
29,927.50
146,773.17

PD 6.22 1 m Pasangan dinding Conblock (CB.15)


6.22.1 Bahan
Concrete block (CB 15)
12.500
Semen portland
10.460
Pasir beton
0.003
Pasir pasang
0.032
Besi beton polos 8 mm
0.870
Paku biasa 2" - 5"
0.004
Kayu sembarang
0.001
Kawat beton
0.020
Koral beton
0.004

Bh
Kg
M
M
Bh
Kg
M
M
M

x
x
x
x
x
x
x
x
x

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

1,450
1,200
102,000
94,500
15,000
10,120
3,144,900
11,620
175,890
Jumlah (1)

=
=
=
=
=
=
=
=
=
=

Rp
Rp
Rp
Rp
Rp
Rp
Rp
Rp
Rp
Rp

18,125.00
12,552.00
306.00
3,024.00
13,050.00
40.48
3,144.90
232.40
703.56
51,178.34

Oh
Oh
Oh
Oh
Oh

x
x
x
x
x

Rp.
Rp.
Rp.
Rp.
Rp.

45,000
65,000
65,000
75,000
75,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=
=

Rp
Rp
Rp
Rp
Rp
Rp
Rp

15,300.00
8,450.00
455.00
1,027.50
1,275.00
26,507.50
77,685.84

6.21.2 Tenaga
Pekerja
Tukang batu
Tukang besi
Kepala tukang
Mandor

6.22.2 Tenaga
Pekerja
Tukang batu
Tukang besi
Kepala tukang
Mandor

0.340
0.130
0.007
0.0137
0.017

PD 6.23 1 m Pasangan dinding Conblock (CB.10)


6.23.1 Bahan
Concrete block (CB 10)
12.500
Semen portland
7.200
Pasir beton
0.002
Pasir pasang
0.021
Besi beton polos
2.540
Paku biasa 2" - 5"
0.003
Kayu sembarang
0.001
Kawat beton
0.015
Koral beton
0.003

Bh
Kg
M
M
Bh
Kg
M
M
M

x
x
x
x
x
x
x
x
x

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

675
1,200
102,000
94,500
15,000
10,120
3,144,900
11,620
175,890
Jumlah (1)

=
=
=
=
=
=
=
=
=
=

Rp
Rp
Rp
Rp
Rp
Rp
Rp
Rp
Rp
Rp

8,437.50
8,640.00
204.00
1,984.50
38,100.00
30.36
3,144.90
174.30
527.67
61,243.23

0.340
0.107
0.007
0.0114
0.017

Oh
Oh
Oh
Oh
Oh

x
x
x
x
x

Rp.
Rp.
Rp.
Rp.
Rp.

45,000
65,000
65,000
75,000
75,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=
=

Rp
Rp
Rp
Rp
Rp
Rp
Rp

15,300.00
6,955.00
455.00
855.00
1,275.00
24,840.00
86,083.23

2.500
5.100
0.080
1.500
0.150

Bh
Kg
M
Kg
M

x
x
x
x
x

Rp.
Rp.
Rp.
Rp.
Rp.

31,120
1,200
102,000
12,390
175,890
Jumlah (1)

=
=
=
=
=
=

Rp
Rp
Rp
Rp
Rp
Rp

77,800.00
6,120.00
8,160.00
18,585.00
26,383.50
137,048.50

0.100
0.030
0.030
0.006
0.005

Oh
Oh
Oh
Oh
Oh

x
x
x
x
x

Rp.
Rp.
Rp.
Rp.
Rp.

45,000
65,000
65,000
75,000
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=
=

Rp
Rp
Rp
Rp
Rp
Rp
Rp

4,500.00
1,950.00
1,950.00
450.00
275.00
9,125.00
146,173.50

36.000 Bh
12.800 Kg
0.035 M

x
x
x

Rp.
Rp.
Rp.

6,960
1,200
94,500
Jumlah (1)

=
=
=
=

Rp
Rp
Rp
Rp

250,560.00
15,360.00
3,307.50
269,227.50

x
x
x
x

Rp.
Rp.
Rp.
Rp.

45,000
65,000
75,000
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

Rp
Rp
Rp
Rp
Rp
Rp

13,500.00
6,500.00
750.00
825.00
21,575.00
290,802.50

1 m Pasang bata berongga ukuran ( 5 x 10 x 20 ) cm


Bahan
Roster/terawang
80.000 Bh x
Semen portland
23.650 Kg x
Pasir pasang
0.570 M x

Rp.
Rp.
Rp.

6,960
1,200
94,500
Jumlah (1)

=
=
=
=

Rp
Rp
Rp
Rp

556,800.00
28,380.00
53,865.00
639,045.00

Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

x
x
x
x

Rp.
Rp.
Rp.
Rp.

45,000
65,000
75,000
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

Rp
Rp
Rp
Rp
Rp
Rp

14,400.00
9,750.00
1,125.00
825.00
26,100.00
665,145.00

x
x
x
x

Rp.
Rp.
Rp.
Rp.

14,850
5,131,500
10,120
5,131,500
Jumlah (1)

=
=
=
=
=

Rp
Rp
Rp
Rp
Rp

22,275.00
71,841.00
121.44
15,394.50
109,631.94

x
x
x
x

Rp.
Rp.
Rp.
Rp.

45,000
65,000
75,000
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

Rp
Rp
Rp
Rp
Rp
Rp

4,500.00
3,250.00
375.00
110.00
8,235.00
117,866.94

6.23.2 Tenaga
Pekerja
Tukang batu
Tukang besi
Kepala tukang
Mandor

PD 6.24 1 m Pasang dinding lantai


6.24.1 Bahan
Bondbeam 40 x 20 x 20 cm
Semen portland
Pasir beton
Besi beton polos
Koral beton
6.24.2 Tenaga
Pekerja
Tukang batu
Tukang besi
Kepala tukang
Mandor

PD 6.25 1 m Pasang dinding lantai


6.25.1 Bahan
Roster/terawang
Semen portland
Pasir pasang
6.25.2 Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

PD 6.26
6.26.1
6.26.2
-

0.300
0.100
0.010
0.015

0.320
0.150
0.015
0.015

Oh
Oh
Oh
Oh

Oh
Oh
Oh
Oh

PD 6.27 1 m Pasang dinding anyaman bambu, rangka kayu


6.27.1 Bahan
Bilik bambu
1.500 M
Kayu 5/7
0.014 M
Paku
0.012 Kg
List kayu 2/4
0.003 M
6.27.2 Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

0.100
0.050
0.005
0.002

Oh
Oh
Oh
Oh

BERSAMBUNG : PEKERJAAN PELESTERAN

ANALISA BIAYA KONSTRUKSI


PEKERJAAN PLESTERAN
PPL 6.1.
6.1.1.

6.1.2.

PPL 6.2.
6.2.1.

6.2.2.

PPL 6.3.
6.3.1.

6.3.2.

PPL 6.4.
6.4.1.

6.4.2.

1 M Plesteran 1 Pc : 1 Ps, tebal 15 mm


Bahan
Semen portland
12.920 Kg x Rp.
Pasir pasang
0.013 M x Rp.
Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

0.200
0.150
0.015
0.010

Oh
Oh
Oh
Oh

x
x
x
x

Rp.
Rp.
Rp.
Rp.

1 M Plesteran 1 Pc : 2 Ps, tebal 15 mm


Bahan
Semen portland
8.520 Kg x Rp.
Pasir pasang
0.017 M x Rp.
Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

0.200
0.150
0.015
0.010

Oh
Oh
Oh
Oh

x
x
x
x

Rp.
Rp.
Rp.
Rp.

1 M Plesteran 1 Pc : 3 Ps, tebal 15 mm


Bahan
Semen portland
6.480 Kg x Rp.
Pasir pasang
0.019 M x Rp.
Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

0.200
0.150
0.015
0.010

Oh
Oh
Oh
Oh

x
x
x
x

Rp.
Rp.
Rp.
Rp.

1 M Plesteran 1 Pc : 4 Ps, tebal 15 mm


Bahan
Semen portland
5.200 Kg x Rp.
Pasir pasang
0.020 M x Rp.
Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

0.200
0.150
0.015
0.010

Oh
Oh
Oh
Oh

x
x
x
x

Rp.
Rp.
Rp.
Rp.

PPL 6.13. 1 M Plesteran 1 Pc : 2 Ps, tebal 20 mm


6.13.1. Bahan
Semen Portland
14.280 Kg x Rp.
Pasir pasang
0.023 M x Rp.
6.13.2. Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

0.250
0.200
0.020
0.0125

Oh
Oh
Oh
Oh

x
x
x
x

Rp.
Rp.
Rp.
Rp.

PPL 6.14. 1 M Plesteran 1 Pc : 3 Ps, tebal 20 mm


6.14.1. Bahan
Semen Portland
10.800 Kg x Rp.
Pasir pasang
0.026 M x Rp.
6.14.2. Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

0.250
0.200
0.020
0.0125

Oh
Oh
Oh
Oh

x
x
x
x

Rp.
Rp.
Rp.
Rp.

1,200 = Rp.
94,500 = Rp.
Jumlah (1)
= Rp.

15,504.00
1,228.50
16,732.50

45,000
65,000
75,000
55,000
Jumlah (2)
Jumlah (1) + (2)

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

9,000.00
9,750.00
1,125.00
550.00
20,425.00
37,157.50

1,200 = Rp.
94,500 = Rp.
Jumlah (1)
= Rp.

10,224.00
1,606.50
11,830.50

45,000
65,000
75,000
55,000
Jumlah (2)
Jumlah (1) + (2)

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

9,000.00
9,750.00
1,125.00
550.00
20,425.00
32,255.50

1,200 = Rp.
94,500 = Rp.
Jumlah (1)
= Rp.

7,776.00
1,795.50
9,571.50

45,000
65,000
75,000
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

9,000.00
9,750.00
1,125.00
550.00
20,425.00
29,996.50

1,200 = Rp.
94,500 = Rp.
Jumlah (1)
= Rp.

6,240.00
1,890.00
8,130.00

45,000
65,000
75,000
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

9,000.00
9,750.00
1,125.00
550.00
20,425.00
28,555.00

1,200 = Rp.
94,500 = Rp.
Jumlah (1)
= Rp.

17,136.00
2,173.50
19,309.50

45,000
65,000
75,000
55,000
Jumlah (2)
Jumlah (1) + (2)

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

11,250.00
13,000.00
1,500.00
687.50
26,437.50
45,747.00

1,200 = Rp.
94,500 = Rp.
Jumlah (1)
= Rp.

12,960.00
2,457.00
15,417.00

45,000
65,000
75,000
55,000
Jumlah (2)
Jumlah (1) + (2)

11,250.00
13,000.00
1,500.00
687.50
26,437.50
41,854.50

=
=
=
=
=
=

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

PPL 6.15. 1 M Plesteran 1 Pc : 4 Ps, tebal 20 mm


6.15.1. Bahan
Semen Portland
8.680 Kg x Rp.
Pasir pasang
0.028 M x Rp.
6.15.2. Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

0.250
0.200
0.020
0.0125

Oh
Oh
Oh
Oh

x
x
x
x

Rp.
Rp.
Rp.
Rp.

PPL 6.19. 1 M Plesteran 1 Pc : 2 Ps, tebal 25 mm


6.19.1. Bahan
Semen Portland
15.500 Kg x Rp.
Pasir pasang
0.013 M x Rp.
6.19.2. Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

0.250
0.200
0.020
0.013

Oh
Oh
Oh
Oh

x
x
x
x

Rp.
Rp.
Rp.
Rp.

PPL 6.20. 1 M Plesteran 1 Pc : 3 Ps, tebal 25 mm


6.20.1. Bahan
Semen Portland
11.750 Kg x Rp.
Pasir pasang
0.035 M x Rp.
6.20.2. Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

0.250
0.200
0.020
0.013

Oh
Oh
Oh
Oh

x
x
x
x

Rp.
Rp.
Rp.
Rp.

PPL 6.21. 1 M Plesteran 1 Pc : 4 Ps, tebal 25 mm


6.21.1. Bahan
Semen Portland
9.480 Kg x Rp.
Pasir pasang
0.038 M x Rp.
6.21.2. Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

0.300
0.200
0.020
0.013

Oh
Oh
Oh
Oh

x
x
x
x

Rp.
Rp.
Rp.
Rp.

PPL 6.23. 1 M Plesteran 1 Pc : 2 Ps, tebal 30 mm


6.23.1. Bahan
Semen Portland
18.650 Kg x Rp.
Pasir pasang
0.035 M x Rp.
6.23.2. Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

0.320
0.250
0.025
0.015

Oh
Oh
Oh
Oh

x
x
x
x

Rp.
Rp.
Rp.
Rp.

PPL 6.24. 1 M Plesteran 1 Pc : 3 Ps, tebal 30 mm


6.24.1. Bahan
Semen Portland
14.150 Kg x Rp.
Pasir pasang
0.039 M x Rp.
6.24.2. Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

0.320
0.250
0.025
0.015

Oh
Oh
Oh
Oh

x
x
x
x

Rp.
Rp.
Rp.
Rp.

1,200 = Rp.
94,500 = Rp.
Jumlah (1)
= Rp.

10,416.00
2,646.00
13,062.00

45,000
65,000
75,000
55,000
Jumlah (2)
Jumlah (1) + (2)

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

11,250.00
13,000.00
1,500.00
687.50
26,437.50
39,499.50

1,200 = Rp.
94,500 = Rp.
Jumlah (1)
= Rp.

18,600.00
1,228.50
19,828.50

45,000
65,000
75,000
55,000
Jumlah (2)
Jumlah (1) + (2)

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

11,250.00
13,000.00
1,500.00
687.50
26,437.50
46,266.00

1,200 = Rp.
94,500 = Rp.
Jumlah (1)
= Rp.

14,100.00
3,307.50
17,407.50

45,000
65,000
75,000
55,000
Jumlah (2)
Jumlah (1) + (2)

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

11,250.00
13,000.00
1,500.00
715.00
26,465.00
43,872.50

1,200 = Rp.
94,500 = Rp.
Jumlah (1)
= Rp.

11,376.00
3,591.00
14,967.00

45,000
65,000
75,000
55,000
Jumlah (2)
Jumlah (1) + (2)

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

13,500.00
13,000.00
1,500.00
715.00
28,715.00
43,682.00

1,200 = Rp.
94,500 = Rp.
Jumlah (1)
= Rp.

22,380.00
3,307.50
25,687.50

45,000
65,000
75,000
55,000
Jumlah (2)
Jumlah (1) + (2)

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

14,400.00
16,250.00
1,875.00
825.00
33,350.00
59,037.50

1,200 = Rp.
94,500 = Rp.
Jumlah (1)
= Rp.

16,980.00
3,685.50
20,665.50

45,000
65,000
75,000
55,000
Jumlah (2)
Jumlah (1) + (2)

14,400.00
16,250.00
1,875.00
825.00
33,350.00
54,015.50

=
=
=
=
=
=

=
=
=
=
=
=

=
=
=
=
=
=

=
=
=
=
=
=

=
=
=
=
=
=

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

PPL 6.25. 1 M Plesteran 1 Pc : 4 Ps, tebal 30 mm


6.25.1. Bahan
Semen Portland
11.380 Kg x Rp.
Pasir pasang
0.042 M x Rp.
6.25.2. Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

0.320
0.250
0.025
0.015

Oh
Oh
Oh
Oh

x
x
x
x

Rp.
Rp.
Rp.
Rp.

PPL 6.29. 1 M Plesteran Beton 1 Pc : 2 Ps, tebal 15 mm


6.29.1. Bahan
Semen Portland
9.300 Kg x Rp.
Pasir pasang
0.018 M x Rp.
6.29.2. Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

0.260
0.200
0.020
0.013

Oh
Oh
Oh
Oh

x
x
x
x

Rp.
Rp.
Rp.
Rp.

PPL 6.30. 1 M Plesteran Beton 1 Pc : 3 Ps, tebal 15 mm


6.30.1. Bahan
Semen Portland
7.070 Kg x Rp.
Pasir pasang
0.021 M x Rp.
6.30.2. Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

0.260
0.200
0.020
0.013

Oh
Oh
Oh
Oh

x
x
x
x

Rp.
Rp.
Rp.
Rp.

PPL 6.31. 1 M Plesteran Skoning 1 Pc : 2 Ps


6.31.1. Bahan
Semen Portland
0.500 Kg x Rp.
Pasir pasang
0.002 M x Rp.
6.31.2. Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

0.057
0.038
0.038
0.002

Oh
Oh
Oh
Oh

x
x
x
x

Rp.
Rp.
Rp.
Rp.

PPL 6.34. 1 M Plesteran Ciprat, 1 Pc : 2 Ps, tebal 10 mm


6.34.1. Bahan
Semen portland
4.320 Kg x Rp.
Pasir pasang
0.016 M x Rp.
6.34.2. Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

0.250
0.100
0.010
0.015

Oh
Oh
Oh
Oh

x
x
x
x

Rp.
Rp.
Rp.
Rp.

PPL 6.35. 1 M Plesteran Siar adukan, 1 Pc : 2 Ps


6.35.1. Bahan
Semen portland
4.320 Kg x Rp.
Pasir pasang
0.016 M x Rp.
6.35.2. Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

0.150
0.070
0.007
0.008

Oh
Oh
Oh
Oh

BERSAMBUNG : .ABK PEKERJAAN KAYU

x
x
x
x

Rp.
Rp.
Rp.
Rp.

1,200 = Rp.
94,500 = Rp.
Jumlah (1)
= Rp.

13,656.00
3,969.00
17,625.00

45,000
65,000
75,000
55,000
Jumlah (2)
Jumlah (1) + (2)

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

14,400.00
16,250.00
1,875.00
825.00
33,350.00
50,975.00

1,200 = Rp.
94,500 = Rp.
Jumlah (1)
= Rp.

11,160.00
1,701.00
12,861.00

45,000
65,000
75,000
55,000
Jumlah (2)
Jumlah (1) + (2)

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

11,700.00
13,000.00
1,500.00
715.00
26,915.00
39,776.00

1,200 = Rp.
94,500 = Rp.
Jumlah (1)
= Rp.

8,484.00
1,984.50
10,468.50

45,000
65,000
75,000
55,000
Jumlah (2)
Jumlah (1) + (2)

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

11,700.00
13,000.00
1,500.00
715.00
26,915.00
37,383.50

1,200 = Rp.
94,500 = Rp.
Jumlah (1)
= Rp.

600.00
189.00
789.00

45,000
65,000
75,000
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

=
=
=
=
=
=

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

2,565.00
2,470.00
2,850.00
110.00
7,995.00
8,784.00

1,200 = Rp.
94,500 = Rp.
Jumlah (1)
= Rp.

5,184.00
1,512.00
6,696.00

45,000
65,000
75,000
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

11,250.00
6,500.00
750.00
825.00
19,325.00
26,021.00

1,200 = Rp.
94,500 = Rp.
Jumlah (1)
= Rp.

5,184.00
1,512.00
6,696.00

45,000
65,000
75,000
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

6,750.00
4,550.00
525.00
440.00
12,265.00
18,961.00

ANALISA BIAYA KONSTRUKSI


PEKERJAAN KAYU

PK 6.1.
6.1.1.

6.1.2.

PK 6.2.
6.2.1.

6.2.2.

PK 6.3.
6.3.1.

6.3.2.

PK 6.4.
6.4.1.

6.4.2.

PK 6.5.
6.5.1.

6.5.2.

PK 6.6.
6.6.1.

6.6.2.

1 M Pasang kusen pintu dan jendela kayu jati :


Bahan
Kayu jati, balok
1.100 M x Rp. 21,750,000.00
Jumlah (1)
Tenaga
Pekerja
6.000 Oh x Rp.
45,000.00
Tukang kayu
20.000 Oh x Rp.
65,000.00
Kepala tukang
2.000 Oh x Rp.
75,000.00
Mandor
0.300 Oh x Rp.
55,000.00
Jumlah (2)
Jumlah (1) +(2)
1 M Pasang kusen pintu dan jendela kayu Meranti batu :
Bahan
Kayu meranti batu, balok
1.200 M x Rp. 8,485,400.00
Jumlah (1)
Tenaga
Pekerja
6.000 Oh x Rp.
45,000.00
Tukang kayu
18.000 Oh x Rp.
65,000.00
Kepala tukang
2.000 Oh x Rp.
75,000.00
Mandor
0.300 Oh x Rp.
55,000.00
Jumlah (2)
Jumlah (1) +(2)
1 M Pasang kusen pintu dan jendela kayu meranti :
Bahan
Kayu meranti, balok
1.200 M x Rp. 5,131,500.00
Jumlah (1)
Tenaga
Pekerja
6.000 Oh x Rp.
45,000.00
Tukang kayu
18.000 Oh x Rp.
65,000.00
Kepala tukang
2.000 Oh x Rp.
75,000.00
Mandor
0.300 Oh x Rp.
55,000.00
Jumlah (2)
Jumlah (1) +(2)
1 M Pasang kusen pintu dan jendela kayu damar laut :
Bahan
Kayu damar laut, balok
1.200 M x Rp. 8,305,000.00
Jumlah (1)
Tenaga
Pekerja
6.000 Oh x Rp.
45,000.00
Tukang kayu
18.000 Oh x Rp.
65,000.00
Kepala tukang
2.000 Oh x Rp.
75,000.00
Mandor
0.300 Oh x Rp.
55,000.00
Jumlah (2)
Jumlah (1) +(2)
1 M Pasang pintu klamp kayu meranti batu :
Bahan
Kayu meranti batu, papan
0.036 M x Rp. 8,612,680.00
Paku biasa 2" - 5"
0.050 Kg x Rp.
10,120.00
Jumlah (1)
Tenaga
Pekerja
0.350 Oh x Rp.
45,000.00
Tukang kayu
1.050 Oh x Rp.
65,000.00
Kepala tukang
0.105 Oh x Rp.
75,000.00
Mandor
0.018 Oh x Rp.
55,000.00
Jumlah (2)
Jumlah (1) +(2)
1 M Pasang pintu klamp kayu jati :
Bahan
Kayu jati, papan
0.036 M x Rp. 21,913,130.00
Paku biasa 2" - 5"
0.050 Kg x Rp.
10,120.00
Jumlah (1)
Tenaga
Pekerja
0.350 Oh x Rp.
45,000.00
Tukang kayu
1.050 Oh x Rp.
65,000.00
Kepala tukang
0.105 Oh x Rp.
75,000.00
Mandor
0.018 Oh x Rp.
55,000.00
Jumlah (2)
Jumlah (1) +(2)

= Rp.
= Rp.

23,925,000.00
23,925,000.00

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

270,000.00
1,300,000.00
150,000.00
16,500.00
1,736,500.00
25,661,500.00

= Rp.
= Rp.

10,182,480.00
10,182,480.00

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

270,000.00
1,170,000.00
150,000.00
16,500.00
1,606,500.00
11,788,980.00

= Rp.
= Rp.

6,157,800.00
6,157,800.00

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

270,000.00
1,170,000.00
150,000.00
16,500.00
1,606,500.00
7,764,300.00

= Rp.
= Rp.

9,966,000.00
9,966,000.00

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

270,000.00
1,170,000.00
150,000.00
16,500.00
1,606,500.00
11,572,500.00

= Rp.
= Rp.
= Rp.

310,056.48
506.00
310,562.48

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

15,750.00
68,250.00
7,875.00
990.00
92,865.00
403,427.48

= Rp.
= Rp.
= Rp.

788,872.68
506.00
789,378.68

=
=
=
=
=
=

15,750.00
68,250.00
7,875.00
990.00
92,865.00
882,243.68

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

PK 6.7.
6.7.1.

6.7.2.

PK 6.8.
6.8.1.

6.8.2.

PK 6.9.
6.9.1.

6.9.2.

1 M Pasang pintu panel kayu jati :


Bahan
Kayu jati, papan
0.036 M
Tenaga
Pekerja
Tukang kayu
Kepala tukang
Mandor

0.350
1.050
0.105
0.018

= Rp.

788,872.68
788,872.68

x
x
x
x

Rp.
Rp.
Rp.
Rp.

45,000.00
65,000.00
75,000.00
55,000.00
Jumlah (2)
Jumlah (1) +(2)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

15,750.00
68,250.00
7,875.00
990.00
92,865.00
881,737.68

1 M Pasang pintu panel kayu meranti batu :


Bahan
Kayu meranti batu, papan
0.040 M

x Rp.

8,612,680.00
Jumlah (1)

= Rp.
= Rp.

344,507.20
344,507.20

Tenaga
Pekerja
Tukang kayu
Kepala tukang
Mandor

x
x
x
x

45,000.00
65,000.00
75,000.00
55,000.00
Jumlah (2)
Jumlah (1) +(2)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

45,000.00
162,500.00
18,750.00
2,750.00
229,000.00
573,507.20

= Rp.
= Rp.
= Rp.

766,959.55
105,600.00
766,959.55

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

36,000.00
130,000.00
15,000.00
2,200.00
183,200.00
950,159.55

= Rp.
= Rp.
= Rp.

301,443.80
105,600.00
301,443.80

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

36,000.00
130,000.00
15,000.00
2,200.00
183,200.00
484,643.80

= Rp.
= Rp.
= Rp.

182,296.45
105,600.00
182,296.45

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

36,000.00
130,000.00
15,000.00
2,200.00
183,200.00
365,496.45

x Rp. 21,913,130.00
Jumlah (1)

= Rp.
= Rp.

1,402,440.32
1,402,440.32

x
x
x
x

=
=
=
=
=
=

45,000.00
195,000.00
22,500.00
16,500.00
279,000.00
1,681,440.32

1.000
2.500
0.250
0.050

Oh
Oh
Oh
Oh

x Rp. 21,913,130.00
Jumlah (1)

Oh
Oh
Oh
Oh

Rp.
Rp.
Rp.
Rp.

1 M Pasang pintu dan jendela kaca panel kayu jati :


Bahan
Kayu jati, papan
0.035 M x Rp. 21,913,130.00
Kaca polos 5 mm
0.800 M x Rp.
132,000.00
Jumlah (1)
Tenaga
Pekerja
0.800 Oh x Rp.
45,000.00
Tukang kayu
2.000 Oh x Rp.
65,000.00
Kepala tukang
0.200 Oh x Rp.
75,000.00
Mandor
0.040 Oh x Rp.
55,000.00
Jumlah (2)
Jumlah (1) +(2)

PK 6.10.
1 M Pasang pintu dan jendela kaca panel kayu meranti batu :
6.10.1. Bahan
Kayu meranti batu, papan
0.035 M x Rp. 8,612,680.00
Kaca polos 5 mm
0.800 M x Rp.
132,000.00
Jumlah (1)
6.10.2. Tenaga
Pekerja
0.800 Oh x Rp.
45,000.00
Tukang kayu
2.000 Oh x Rp.
65,000.00
Kepala tukang
0.200 Oh x Rp.
75,000.00
Mandor
0.040 Oh x Rp.
55,000.00
Jumlah (2)
Jumlah (1) +(2)
PK 6.11.
1 M Pasang pintu dan jendela kaca panel kayu meranti :
6.11.1. Bahan
Kayu meranti, papan
0.035 M x Rp. 5,208,470.00
Kaca polos 5 mm
0.800 M x Rp.
132,000.00
Jumlah (1)
6.11.2. Tenaga
Pekerja
0.800 Oh x Rp.
45,000.00
Tukang kayu
2.000 Oh x Rp.
65,000.00
Kepala tukang
0.200 Oh x Rp.
75,000.00
Mandor
0.040 Oh x Rp.
55,000.00
Jumlah (2)
Jumlah (1) +(2)

PK 6.12.
1 M Pasang pintu dan jendela jalusi kayu jati
6.12.1. Bahan
Kayu jati, papan
0.064 M
6.12.2. Tenaga
Pekerja
Tukang kayu
Kepala tukang
Mandor

1.000
3.000
0.300
0.300

Oh
Oh
Oh
Oh

Rp.
Rp.
Rp.
Rp.

45,000.00
65,000.00
75,000.00
55,000.00
Jumlah (2)
Jumlah (1) +(2)

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

PK 6.13.
1 M Pasang pintu dan jendela jalusi kayu damar laut :
6.13.1. Bahan
Kayu damar laut, papan
0.064 M x Rp. 8,429,580.00
Jumlah (1)
6.13.2. Tenaga
Pekerja
1.000 Oh x Rp.
45,000.00
Tukang kayu
3.000 Oh x Rp.
65,000.00
Kepala tukang
0.300 Oh x Rp.
75,000.00
Mandor
0.500 Oh x Rp.
55,000.00
Jumlah (2)
Jumlah (1) +(2)
PK 6.14.
1 M Pasang pintu plywood rangka, rangka kayu jati :
6.14.1. Bahan
Kayu jati, papan
0.0196 M x Rp. 21,913,130.00
Paku biasa " - 1"
0.030 Kg x Rp.
10,930.00
Lem kayu
0.300 Lt
x Rp.
32,500.00
Playwood 4' x 3' x 4 mm
1.000 Lbr x Rp.
64,520.00
Jumlah (1)
6.14.2. Tenaga
Pekerja
0.600 Oh x Rp.
45,000.00
Tukang kayu
2.000 Oh x Rp.
65,000.00
Kepala tukang
0.200 Oh x Rp.
75,000.00
Mandor
0.030 Oh x Rp.
55,000.00
Jumlah (2)
Jumlah (1) +(2)
PK 6.15.
1 M Pasang pintu plywood rangka, rangka kayu Meranti batu :
6.15.1. Bahan
Kayu meranti batu, papan
0.0196 M x Rp. 8,612,680.00
Paku biasa " - 1"
0.030 Kg x Rp.
10,930.00
Lem kayu
0.300 Lt
x Rp.
32,500.00
Playwood 4' x 3' x 4 mm
1.000 Lbr x Rp.
64,520.00
Jumlah (1)
6.15.2. Tenaga
Pekerja
0.600 Oh x Rp.
45,000.00
Tukang kayu
2.000 Oh x Rp.
65,000.00
Kepala tukang
0.200 Oh x Rp.
75,000.00
Mandor
0.030 Oh x Rp.
55,000.00
Jumlah (2)
PK 6.16.
1 M Pasang jalusi mati kusen kayu jati :
Jumlah (1) +(2)
6.16.1. Bahan
Kayu jati, papan
0.060 M x Rp. 21,913,130.00
Paku biasa " - 1"
0.150 Kg x Rp.
10,930.00
Jumlah (1)
6.16.2. Tenaga
Pekerja
0.500 Oh x Rp.
45,000.00
Tukang kayu
2.000 Oh x Rp.
65,000.00
Kepala tukang
0.200 Oh x Rp.
75,000.00
Mandor
0.025 Oh x Rp.
55,000.00
Jumlah (2)
Jumlah (1) +(2)
PK 6.17.
1 M Pasang jalusi mati kusen kayu damar laut :
6.17.1. Bahan
Kayu meranti batu, papan
0.060 M x Rp. 8,612,680.00
Paku biasa " - 1"
0.150 Kg x Rp.
10,930.00
Jumlah (1)
6.17.2. Tenaga
Pekerja
0.500 Oh x Rp.
45,000.00
Tukang kayu
2.000 Oh x Rp.
65,000.00
Kepala tukang
0.200 Oh x Rp.
75,000.00
Mandor
0.025 Oh x Rp.
55,000.00
Jumlah (2)
Jumlah (1) +(2)
PK 6.18.
1 M Pasang pintu plywood rangka, rangka kayu meranti :
6.18.1. Bahan
Kayu meranti, papan
0.0196 M x Rp. 5,208,470.00
Paku biasa " - 1"
0.030 Kg x Rp.
10,930.00
Lem kayu
0.300 Lt
x Rp.
32,500.00
Playwood 4' x 3' x 4 mm
1.000 Lbr x Rp.
64,520.00
Jumlah (1)
6.18.2. Tenaga
Pekerja
0.600 Oh x Rp.
45,000.00
Tukang kayu
2.000 Oh x Rp.
65,000.00
Kepala tukang
0.200 Oh x Rp.
75,000.00
Mandor
0.030 Oh x Rp.
55,000.00
Jumlah (2)
Jumlah (1) +(2)

= Rp.
= Rp.

539,493.12
539,493.12

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

45,000.00
195,000.00
22,500.00
27,500.00
290,000.00
829,493.12

=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.

429,497.35
327.90
9,750.00
64,520.00
504,095.25

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

27,000.00
130,000.00
15,000.00
1,650.00
173,650.00
677,745.25

=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.

168,808.53
327.90
9,750.00
64,520.00
243,406.43

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

27,000.00
130,000.00
15,000.00
1,650.00
173,650.00
417,056.43

= Rp.
= Rp.
= Rp.

1,314,787.80
1,639.50
1,316,427.30

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

22,500.00
130,000.00
15,000.00
1,375.00
168,875.00
1,485,302.30

= Rp.
= Rp.
= Rp.

516,760.80
1,639.50
518,400.30

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

22,500.00
130,000.00
15,000.00
1,375.00
168,875.00
687,275.30

=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.

102,086.01
327.90
9,750.00
64,520.00
74,270.00

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

27,000.00
130,000.00
15,000.00
1,650.00
173,650.00
247,920.00

PK 6.19.
1 M Pasang pintu teakwood rangka, rangka kayu jati :
6.19.1. Bahan
Kayu jati, papan
0.0196 M x Rp. 21,913,130.00
Paku biasa " - 1"
0.300 Kg x Rp.
10,930.00
Lem kayu
0.300 Lt
x Rp.
32,500.00
Teakwood 4' x 8' x 4 mm
1.000 Lbr x Rp.
96,250.00
Jumlah (1)
6.19.2. Tenaga
Pekerja
0.600 Oh x Rp.
45,000.00
Tukang kayu
2.000 Oh x Rp.
65,000.00
Kepala tukang
0.200 Oh x Rp.
75,000.00
Mandor
0.030 Oh x Rp.
55,000.00
Jumlah (2)
Jumlah (1) +(2)
PK 6.20.
1 M Pasang pintu teakwood rangka, rangka kayu meranti batu :
6.20.1. Bahan
Kayu meranti batu, papan
0.0196 M x Rp. 8,612,680.00
Paku biasa " - 1"
0.300 Kg x Rp.
10,930.00
Lem kayu
0.300 Lt
x Rp.
32,500.00
Teakwood 4' x 8' x 4 mm
1.000 Lbr x Rp.
96,250.00
Jumlah (1)
6.20.2. Tenaga
Pekerja
0.600 Oh x Rp.
45,000.00
Tukang kayu
2.000 Oh x Rp.
65,000.00
Kepala tukang
0.200 Oh x Rp.
75,000.00
Mandor
0.030 Oh x Rp.
55,000.00
Jumlah (2)
Jumlah (1) +(2)
PK 6.21.
1 M Pasang pintu plywood & formika, rangka kayu jati :
6.21.1. Bahan
Kayu jati, papan
0.0196 M x Rp. 21,913,130.00
Paku biasa " - 1"
0.300 Kg x Rp.
10,930.00
Lem kayu
0.800 Lt
x Rp.
32,500.00
Plywood 4' x 8' x 4 mm
1.000 Lbr x Rp.
64,520.00
Formica 4' x 8'
1.000 Lbr x Rp.
81,950.00
Jumlah (1)
6.21.2. Tenaga
Pekerja
0.800 Oh x Rp.
45,000.00
Tukang kayu
2.500 Oh x Rp.
65,000.00
Kepala tukang
0.250 Oh x Rp.
75,000.00
Mandor
0.040 Oh x Rp.
55,000.00
Jumlah (2)
Jumlah (1) +(2)
PK 6.22.
1 M Pasang pintu plywood & formika, rangka kayu Meranti batu :
6.22.1. Bahan
Kayu meranti batu, papan
0.0196 M x Rp. 8,612,680.00
Paku biasa " - 1"
0.300 Kg x Rp.
10,930.00
Lem kayu
0.800 Lt
x Rp.
32,500.00
Plywood 4' x 8' x 4 mm
1.000 Lbr x Rp.
64,520.00
Formica 4' x 8'
1.000 Lbr x Rp.
81,950.00
Jumlah (1)
6.22.2. Tenaga
Pekerja
0.800 Oh x Rp.
45,000.00
Tukang kayu
2.500 Oh x Rp.
65,000.00
Kepala tukang
0.250 Oh x Rp.
75,000.00
Mandor
0.040 Oh x Rp.
55,000.00
Jumlah (2)
Jumlah (1) +(2)
PK 6.23.
1 M Pasang pintu teakwood & formika, rangka kayu jati :
6.23.1. Bahan
Kayu jati, papan
0.0196 M x Rp. 21,913,130.00
Paku biasa " - 1"
0.300 Kg x Rp.
10,930.00
Lem kayu
0.800 Lt
x Rp.
32,500.00
Teakwood 4' x 8' x 4 mm
1.000 Lbr x Rp.
96,250.00
Formica 4' x 8'
1.000 Lbr x Rp.
81,950.00
Jumlah (1)
6.23.2. Tenaga
Pekerja
0.800 Oh x Rp.
45,000.00
Tukang kayu
2.500 Oh x Rp.
65,000.00
Kepala tukang
0.250 Oh x Rp.
75,000.00
Mandor
0.040 Oh x Rp.
55,000.00
Jumlah (2)
Jumlah (1) +(2)

=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.

429,497.35
3,279.00
9,750.00
96,250.00
538,776.35

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

27,000.00
130,000.00
15,000.00
1,650.00
173,650.00
712,426.35

=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.

168,808.53
3,279.00
9,750.00
96,250.00
278,087.53

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

27,000.00
130,000.00
15,000.00
1,650.00
173,650.00
451,737.53

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

429,497.35
3,279.00
26,000.00
64,520.00
81,950.00
605,246.35

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

36,000.00
162,500.00
18,750.00
2,200.00
219,450.00
824,696.35

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

168,808.53
3,279.00
26,000.00
64,520.00
81,950.00
344,557.53

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

36,000.00
162,500.00
18,750.00
2,200.00
219,450.00
564,007.53

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

429,497.35
3,279.00
26,000.00
96,250.00
81,950.00
636,976.35

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

36,000.00
162,500.00
18,750.00
2,200.00
219,450.00
856,426.35

PK 6.24.
1 M Pasang pintu Teakwood & formika, rangka kayu meranti batu (divermis) :
6.24.1. Bahan
Kayu meranti batu, papan
0.0196 M x Rp. 8,612,680.00 = Rp.
Paku biasa " - 1"
0.300 Kg x Rp.
10,930.00 = Rp.
Lem kayu
0.800 Lt
x Rp.
32,500.00 = Rp.
Teakwood 4' x 8' x 4 mm
0.500 Lbr x Rp.
96,250.00 = Rp.
Vernis
0.500 Lt
x Rp.
43,890.00 = Rp.
Formica 4' x 8'
0.500 Lbr x Rp.
81,950.00 = Rp.
Jumlah (1)
= Rp.
6.24.2. Tenaga
Pekerja
0.800 Oh x Rp.
45,000.00 = Rp.
Tukang kayu
2.500 Oh x Rp.
65,000.00 = Rp.
Kepala tukang
0.250 Oh x Rp.
75,000.00 = Rp.
Mandor
0.040 Oh x Rp.
55,000.00 = Rp.
Jumlah (2)
= Rp.
Jumlah (1) +(2) = Rp.
PK 6.29.
1 M Pasang konstruksi kuda-kuda kayu damar laut :
6.29.1. Bahan
Kayu damar laut, balok
1.1000 M x Rp.
Besi strip
15.000 Kg x Rp.
Paku biasa 2" - 5"
0.800 Kg x Rp.
6.29.2. Tenaga
Pekerja
Tukang kayu
Kepala tukang
Mandor

4.000
12.000
1.200
0.200

Oh
Oh
Oh
Oh

x
x
x
x

PK 6.30.
1 M Pasang konstruksi kuda-kuda kayu meranti
6.30.1. Bahan
Kayu meranti, balok
1.1000 M x
Besi strip
15.000 Kg x
Paku biasa 2" - 5"
0.800 Kg x
6.30.2. Tenaga
Pekerja
Tukang kayu
Kepala tukang
Mandor

4.000
12.000
1.200
0.200

Oh
Oh
Oh
Oh

x
x
x
x

168,808.53
3,279.00
26,000.00
48,125.00
21,945.00
40,975.00
309,132.53
36,000.00
162,500.00
18,750.00
2,200.00
219,450.00
528,582.53

8,305,000.00
12,620.00
10,930.00
Jumlah (1)

=
=
=
=

Rp.
Rp.
Rp.
Rp.

9,135,500.00
189,300.00
8,744.00
9,333,544.00

45,000.00
65,000.00
75,000.00
55,000.00
Jumlah (2)
Jumlah (1) +(2)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

180,000.00
780,000.00
90,000.00
11,000.00
1,061,000.00
10,394,544.00

Rp.
Rp.
Rp.

5,131,500.00
12,620.00
10,930.00
Jumlah (1)

=
=
=
=

Rp.
Rp.
Rp.
Rp.

5,644,650.00
189,300.00
8,744.00
5,842,694.00

Rp.
Rp.
Rp.
Rp.

45,000.00
65,000.00
75,000.00
55,000.00
Jumlah (2)
Jumlah (1) +(2)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

180,000.00
780,000.00
90,000.00
11,000.00
1,061,000.00
6,903,694.00

= Rp.
= Rp.
= Rp.

61,578.00
1,639.50
63,217.50

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

4,500.00
6,500.00
750.00
275.00
12,025.00
75,242.50

= Rp.
= Rp.
= Rp.

99,660.00
1,639.50
101,299.50

=
=
=
=
=
=

4,500.00
6,500.00
750.00
275.00
12,025.00
113,324.50

Rp.
Rp.
Rp.
Rp.

PK 6.31.
1 M Pasang kaso + reng genteng kodok kayu meranti :
6.31.1. Bahan
Kayu meranti, balok
0.012 M x Rp. 5,131,500.00
Paku biasa 2" - 5"
0.150 Kg x Rp.
10,930.00
Jumlah (1)
6.31.2. Tenaga
Pekerja
0.100 Oh x Rp.
45,000.00
Tukang kayu
0.100 Oh x Rp.
65,000.00
Kepala tukang
0.010 Oh x Rp.
75,000.00
Mandor
0.005 Oh x Rp.
55,000.00
Jumlah (2)
Jumlah (1) +(2)
PK 6.32.
1 M Pasang kaso + reng genteng kodok kayu damar laut :
6.32.1. Bahan
Kayu damar laut, balok
0.012 M x Rp. 8,305,000.00
Paku biasa 2" - 5"
0.150 Kg x Rp.
10,930.00
Jumlah (1)
6.32.2. Tenaga
Pekerja
0.100 Oh x Rp.
45,000.00
Tukang kayu
0.100 Oh x Rp.
65,000.00
Kepala tukang
0.010 Oh x Rp.
75,000.00
Mandor
0.005 Oh x Rp.
55,000.00
Jumlah (2)
Jumlah (1) +(2)

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

PK 6.33.
1 M Pasang kaso + reng genteng monier kayu jati :
6.33.1. Bahan
Kayu jati, balok
0.014 M x Rp. 21,750,000.00
Paku biasa 2" - 5"
0.150 Kg x Rp.
10,930.00
Jumlah (1)
6.33.2. Tenaga
Pekerja
0.100 Oh x Rp.
45,000.00
Tukang kayu
0.100 Oh x Rp.
65,000.00
Kepala tukang
0.010 Oh x Rp.
75,000.00
Mandor
0.005 Oh x Rp.
55,000.00
Jumlah (2)
Jumlah (1) +(2)
PK 6.34.
1 M Pasang kaso + reng genteng monier kayu damar laut :
6.34.1. Bahan
Kayu damar laut, balok
0.014 M x Rp. 8,305,000.00
Paku biasa 2" - 5"
0.150 Kg x Rp.
10,930.00
Jumlah (1)
6.34.2. Tenaga
Pekerja
0.100 Oh x Rp.
45,000.00
Tukang kayu
0.100 Oh x Rp.
65,000.00
Kepala tukang
0.010 Oh x Rp.
75,000.00
Mandor
0.005 Oh x Rp.
55,000.00
Jumlah (2)
Jumlah (1) +(2)
PK 6.35.
1 M Pasang kaso + reng genteng beton kayu damar laut :
6.35.1. Bahan
Kayu damar laut, balok
0.014 M x Rp. 8,305,000.00
Paku biasa 2" - 5"
0.150 Kg x Rp.
10,930.00
Jumlah (1)
6.35.2. Tenaga
Pekerja
0.100 Oh x Rp.
45,000.00
Tukang kayu
0.100 Oh x Rp.
65,000.00
Kepala tukang
0.010 Oh x Rp.
75,000.00
Mandor
0.005 Oh x Rp.
55,000.00
Jumlah (2)
Jumlah (1) +(2)
PK 6.36.
1 M Pasang kaso + reng atap sirap kayu damar laut :
6.36.1. Bahan
Kayu damar laut, balok
0.165 M x Rp. 8,305,000.00
Paku biasa 2" - 5"
0.200 Kg x Rp.
10,930.00
Jumlah (1)
6.36.2. Tenaga
Pekerja
0.120 Oh x Rp.
45,000.00
Tukang kayu
0.120 Oh x Rp.
65,000.00
Kepala tukang
0.012 Oh x Rp.
75,000.00
Mandor
0.006 Oh x Rp.
55,000.00
Jumlah (2)
Jumlah (1) +(2)
PK 6.37.
1 M Pasang kaso + reng atap sirap kayu meranti :
6.37.1. Bahan
Kayu meranti, balok
0.165 M x Rp. 5,131,500.00
Paku biasa 2" - 5"
0.200 Kg x Rp.
10,930.00
Jumlah (1)
6.37.2. Tenaga
Pekerja
0.120 Oh x Rp.
45,000.00
Tukang kayu
0.120 Oh x Rp.
65,000.00
Kepala tukang
0.012 Oh x Rp.
75,000.00
Mandor
0.006 Oh x Rp.
55,000.00
Jumlah (2)
Jumlah (1) +(2)
PK 6.38.
1 M Pasang rangka langit-langit (1.00 x 1.00) m, kayu jati :
6.38.1. Bahan
Kayu jati, balok
0.012 M x Rp. 21,750,000.00
Paku biasa 2" - 5"
0.100 Kg x Rp.
10,930.00
Jumlah (1)
6.38.2. Tenaga
Pekerja
0.150 Oh x Rp.
45,000.00
Tukang kayu
0.250 Oh x Rp.
65,000.00
Kepala tukang
0.025 Oh x Rp.
75,000.00
Mandor
0.075 Oh x Rp.
55,000.00
Jumlah (2)
Jumlah (1) +(2)

= Rp.
= Rp.
= Rp.

304,500.00
1,639.50
306,139.50

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

4,500.00
6,500.00
750.00
275.00
12,025.00
318,164.50

= Rp.
= Rp.
= Rp.

116,270.00
1,639.50
117,909.50

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

4,500.00
6,500.00
750.00
275.00
12,025.00
129,934.50

= Rp.
= Rp.
= Rp.

116,270.00
1,639.50
117,909.50

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

4,500.00
6,500.00
750.00
275.00
12,025.00
129,934.50

= Rp.
= Rp.
= Rp.

1,370,325.00
2,186.00
1,372,511.00

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

5,400.00
7,800.00
900.00
330.00
14,430.00
1,386,941.00

= Rp.
= Rp.
= Rp.

846,697.50
2,186.00
848,883.50

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

5,400.00
7,800.00
900.00
330.00
14,430.00
863,313.50

= Rp.
= Rp.
= Rp.

261,000.00
1,093.00
262,093.00

=
=
=
=
=
=

6,750.00
16,250.00
1,875.00
4,125.00
29,000.00
291,093.00

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

PK 6.38.A 1 M Pasang rangka langit-langit (1.00 x 1.00) m, kayu Damar laut :


6.38.1. Bahan
Kayu damar laut, balok
0.012 M x Rp. 8,305,000.00
Paku biasa 2" - 5"
0.100 Kg x Rp.
10,930.00
Jumlah (1)
6.38.2. Tenaga
Pekerja
0.150 Oh x Rp.
45,000.00
Tukang kayu
0.250 Oh x Rp.
65,000.00
Kepala tukang
0.025 Oh x Rp.
75,000.00
Mandor
0.075 Oh x Rp.
55,000.00
Jumlah (2)
Jumlah (1) +(2)
PK 6.38.B 1 M Pasang rangka langit-langit (1.00 x 1.00) m, kayu meranti :
6.38.1. Bahan
Kayu meranti, balok
0.012 M x Rp. 5,131,500.00
Paku biasa 2" - 5"
0.100 Kg x Rp.
10,930.00
Jumlah (1)
6.38.2. Tenaga
Pekerja
0.150 Oh x Rp.
45,000.00
Tukang kayu
0.250 Oh x Rp.
65,000.00
Kepala tukang
0.025 Oh x Rp.
75,000.00
Mandor
0.075 Oh x Rp.
55,000.00
Jumlah (2)
Jumlah (1) +(2)
PK 6.44.
1 M Pasang rangka langit-langit (30 x 30) cm, kayu jati :
6.44.1. Bahan
Kayu jati, balok
0.027 M x Rp. 21,750,000.00
Paku biasa 2" - 5"
0.200 Kg x Rp.
10,930.00
Jumlah (1)
6.44.2. Tenaga
Pekerja
0.250 Oh x Rp.
45,000.00
Tukang kayu
0.350 Oh x Rp.
65,000.00
Kepala tukang
0.035 Oh x Rp.
75,000.00
Mandor
0.0125 Oh x Rp.
55,000.00
Jumlah (2)
Jumlah (1) +(2)
PK 6.45.
1 M Pasang rangka langit-langit (30 x 30) cm, kayu damar laut :
6.45.1. Bahan
Kayu damar laut, balok
0.027 M x Rp. 8,305,000.00
Paku biasa 2" - 5"
0.200 Kg x Rp.
10,930.00
Jumlah (1)
6.45.2. Tenaga
Pekerja
0.250 Oh x Rp.
45,000.00
Tukang kayu
0.350 Oh x Rp.
65,000.00
Kepala tukang
0.035 Oh x Rp.
75,000.00
Mandor
0.0125 Oh x Rp.
55,000.00
Jumlah (2)
Jumlah (1) +(2)
PK 6.46.
1 M Pasang rangka langit-langit (30 x 30) cm, kayu meranti :
6.46.1. Bahan
Kayu meranti, balok
0.027 M x Rp. 5,131,500.00
Paku biasa 2" - 5"
0.200 Kg x Rp.
10,930.00
Jumlah (1)
6.46.2. Tenaga
Pekerja
0.250 Oh x Rp.
45,000.00
Tukang kayu
0.350 Oh x Rp.
65,000.00
Kepala tukang
0.035 Oh x Rp.
75,000.00
Mandor
0.0125 Oh x Rp.
55,000.00
Jumlah (2)
Jumlah (1) +(2)
PK 6.47.
1 M Pasang lisplang ukuran (3 x 20) cm, kayu meranti :
6.47.1. Bahan
Kayu meranti, papan
0.0072 M x Rp. 5,208,470.00
Paku biasa 2" - 5"
0.050 Kg x Rp.
10,930.00
Jumlah (1)
6.47.2. Tenaga
Pekerja
0.100 Oh x Rp.
45,000.00
Tukang kayu
0.200 Oh x Rp.
65,000.00
Kepala tukang
0.025 Oh x Rp.
75,000.00
Mandor
0.005 Oh x Rp.
55,000.00
Jumlah (2)
Jumlah (1) +(2)

= Rp.
= Rp.
= Rp.

99,660.00
1,093.00
100,753.00

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

6,750.00
16,250.00
1,875.00
4,125.00
29,000.00
129,753.00

= Rp.
= Rp.
= Rp.

61,578.00
1,093.00
62,671.00

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

6,750.00
16,250.00
1,875.00
4,125.00
29,000.00
91,671.00

= Rp.
= Rp.
= Rp.

587,250.00
2,186.00
589,436.00

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

11,250.00
22,750.00
2,625.00
687.50
37,312.50
626,748.50

= Rp.
= Rp.
= Rp.

224,235.00
2,186.00
226,421.00

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

11,250.00
22,750.00
2,625.00
687.50
37,312.50
263,733.50

= Rp.
= Rp.
= Rp.

138,550.50
2,186.00
140,736.50

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

11,250.00
22,750.00
2,625.00
687.50
37,312.50
178,049.00

= Rp.
= Rp.
= Rp.

37,500.98
546.50
38,047.48

=
=
=
=
=
=

4,500.00
13,000.00
1,875.00
275.00
19,650.00
57,697.48

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

PK 6.48.
1 M Pasang lisplang ukuran (3 x 20) cm, kayu meranti batu :
6.48.1. Bahan
Meranti batu, papan
0.0072 M x Rp. 8,612,680.00
Paku biasa 2" - 5"
0.050 Kg x Rp.
10,930.00
Jumlah (1)
6.48.2. Tenaga
Pekerja
0.100 Oh x Rp.
45,000.00
Tukang kayu
0.200 Oh x Rp.
65,000.00
Kepala tukang
0.020 Oh x Rp.
75,000.00
Mandor
0.005 Oh x Rp.
55,000.00
Jumlah (2)
Jumlah (1) +(2)
PK 6.49.
1 M Pasang lisplang ukuran (3 x 30) cm, kayu jati :
6.49.1. Bahan
Kayu jati, papan
0.0110 M x Rp. 21,913,130.00
Paku biasa 2" - 5"
0.050 Kg x Rp.
10,930.00
Jumlah (1)
6.49.2. Tenaga
Pekerja
0.110 Oh x Rp.
45,000.00
Tukang kayu
0.220 Oh x Rp.
65,000.00
Kepala tukang
0.022 Oh x Rp.
75,000.00
Mandor
0.005 Oh x Rp.
55,000.00
Jumlah (2)
Jumlah (1) +(2)
PK 6.50.
1 M Pasang lisplang ukuran (3 x 30) cm, kayu meranti batu :
6.50.1. Bahan
Meranti batu, papan
0.011 M x Rp. 8,612,680.00
Paku biasa 2" - 5"
0.050 Kg x Rp.
10,930.00
Jumlah (1)
6.50.2. Tenaga
Pekerja
0.110 Oh x Rp.
45,000.00
Tukang kayu
0.220 Oh x Rp.
65,000.00
Kepala tukang
0.022 Oh x Rp.
75,000.00
Mandor
0.005 Oh x Rp.
55,000.00
Jumlah (2)
Jumlah (1) +(2)
PK 6.51.
1 M Pasang lisplang ukuran 2 x (3 x 20) cm, kayu meranti batu :
6.51.1. Bahan
Meranti batu, papan
0.0145 M x Rp. 8,612,680.00
Paku biasa 2" - 5"
0.060 Kg x Rp.
10,930.00
Jumlah (1)
6.51.2. Tenaga
Pekerja
0.150 Oh x Rp.
45,000.00
Tukang kayu
0.250 Oh x Rp.
65,000.00
Kepala tukang
0.025 Oh x Rp.
75,000.00
Mandor
0.075 Oh x Rp.
55,000.00
Jumlah (2)
Jumlah (1) +(2)
PK 6.52.
1 M Pasang lisplang ukuran 2 x (2 x 20) cm, kayu meranti batu :
6.52.1. Bahan
Meranti batu, papan
0.0086 M x Rp. 8,612,680.00
Paku biasa 2" - 5"
0.060 Kg x Rp.
10,930.00
Jumlah (1)
6.52.2. Tenaga
Pekerja
0.100 Oh x Rp.
45,000.00
Tukang kayu
0.100 Oh x Rp.
65,000.00
Kepala tukang
0.010 Oh x Rp.
75,000.00
Mandor
0.050 Oh x Rp.
55,000.00
Jumlah (2)
Jumlah (1) +(2)
PK 6.53.
1 M Pasang lisplang ukuran 2 x (2 x 20) cm, kayu meranti :
6.53.1. Bahan
Kayu meranti, papan
0.0086 M x Rp. 5,208,470.00
Paku biasa 2" - 5"
0.060 Kg x Rp.
10,930.00
Jumlah (1)
6.53.2. Tenaga
Pekerja
0.100 Oh x Rp.
45,000.00
Tukang kayu
0.100 Oh x Rp.
65,000.00
Kepala tukang
0.010 Oh x Rp.
75,000.00
Mandor
0.050 Oh x Rp.
55,000.00
Jumlah (2)
Jumlah (1) +(2)

= Rp.
= Rp.
= Rp.

62,011.30
546.50
62,557.80

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

4,500.00
13,000.00
1,500.00
275.00
19,275.00
81,832.80

= Rp.
= Rp.
= Rp.

241,044.43
546.50
241,590.93

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

4,950.00
14,300.00
1,650.00
275.00
21,175.00
262,765.93

= Rp.
= Rp.
= Rp.

94,739.48
546.50
95,285.98

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

4,950.00
14,300.00
1,650.00
275.00
21,175.00
116,460.98

= Rp.
= Rp.
= Rp.

124,883.86
655.80
125,539.66

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

6,750.00
16,250.00
1,875.00
4,125.00
29,000.00
154,539.66

= Rp.
= Rp.
= Rp.

74,069.05
655.80
74,724.85

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

4,500.00
6,500.00
750.00
2,750.00
14,500.00
89,224.85

= Rp.
= Rp.
= Rp.

44,792.84
655.80
45,448.64

=
=
=
=
=
=

4,500.00
6,500.00
750.00
2,750.00
14,500.00
59,948.64

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

PK 6.54.
1 M Pasang rangka dinding pemisah, kayu damar laut :
6.54.1. Bahan
Kayu damar laut, balok
0.0195 M x Rp. 8,305,000.00
Kayu meranti batu, papan
0.007 M x Rp. 8,612,680.00
Paku biasa 2" - 5"
0.100 Kg x Rp.
10,930.00
Jumlah (1)
6.54.2. Tenaga
Pekerja
0.150 Oh x Rp.
45,000.00
Tukang kayu
0.450 Oh x Rp.
65,000.00
Kepala tukang
0.045 Oh x Rp.
75,000.00
Mandor
0.075 Oh x Rp.
55,000.00
Jumlah (2)
Jumlah (1) +(2)

=
=
=
=

Rp.
Rp.
Rp.
Rp.

161,947.50
60,288.76
1,093.00
223,329.26

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

6,750.00
29,250.00
3,375.00
4,125.00
43,500.00
266,829.26

=
=
=
=

Rp.
Rp.
Rp.
Rp.

100,064.25
36,459.29
1,093.00
137,616.54

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

6,750.00
29,250.00
3,375.00
4,125.00
43,500.00
181,116.54

=
=
=
=

Rp.
Rp.
Rp.
Rp.

161,947.50
96,250.00
1,093.00
259,290.50

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

6,750.00
29,250.00
3,375.00
4,125.00
43,500.00
302,790.50

=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.

161,947.50
1,093.00
18,200.00
64,520.00
245,760.50

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

9,000.00
39,000.00
4,500.00
550.00
53,050.00
298,810.50

Rp. 21,750,000.00
Rp.
10,930.00
Rp.
17,250.00
Jumlah (1)

=
=
=
=

Rp.
Rp.
Rp.
Rp.

152,250.00
1,093.00
2,587.50
155,930.50

Rp.
Rp.
Rp.
Rp.

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

27,000.00
117,000.00
13,500.00
1,650.00
159,150.00
315,080.50

PK 6.55.
1 M Pasang rangka dinding pemisah, kayu meranti :
6.55.1. Bahan
kayu meranti, balok
0.0195 M x Rp. 5,131,500.00
kayu meranti, papan
0.007 M x Rp. 5,208,470.00
Paku biasa 2" - 5"
0.100 Kg x Rp.
10,930.00
Jumlah (1)
6.55.2. Tenaga
Pekerja
0.150 Oh x Rp.
45,000.00
Tukang kayu
0.450 Oh x Rp.
65,000.00
Kepala tukang
0.045 Oh x Rp.
75,000.00
Mandor
0.075 Oh x Rp.
55,000.00
Jumlah (2)
Jumlah (1) +(2)

PK 6.56.
1 M Pasang dinding pemisah teakwood, rangka kayu damar laut :
6.56.1. Bahan
Kayu damar laut, balok
0.0195 M x Rp. 8,305,000.00
Teakwood 4' x 8'
1.000 Lbr x Rp.
96,250.00
Paku biasa 2" - 5"
0.100 Kg x Rp.
10,930.00
Jumlah (1)
6.56.2. Tenaga
Pekerja
0.150 Oh x Rp.
45,000.00
Tukang kayu
0.450 Oh x Rp.
65,000.00
Kepala tukang
0.045 Oh x Rp.
75,000.00
Mandor
0.075 Oh x Rp.
55,000.00
Jumlah (2)
Jumlah (1) +(2)
PK 6.57.
1 M Pasang dinding pemisah plywood, rangka kayu damar laut :
6.57.1. Bahan
Kayu damar laut, balok
0.0195 M x Rp. 8,305,000.00
Paku biasa 2" - 5"
0.100 Kg x Rp.
10,930.00
Lem kayu
0.560 Lt
x Rp.
32,500.00
Plywood 4' x 8' x 4 mm
1.000 Lbr x Rp.
64,520.00
Jumlah (1)
6.57.2. Tenaga
Pekerja
0.200 Oh x Rp.
45,000.00
Tukang kayu
0.600 Oh x Rp.
65,000.00
Kepala tukang
0.060 Oh x Rp.
75,000.00
Mandor
0.010 Oh x Rp.
55,000.00
Jumlah (2)
Jumlah (1) +(2)

PK 6.58.
1 M Pasang dinding lambriziring dari papan jati
6.58.1. Bahan
Kayu jati, balok
0.0070 M x
Paku biasa 2" - 5"
0.100 Kg x
Paku skrup 3,5"
0.150 Kg x
6.58.2. Tenaga
Pekerja
Tukang kayu
Kepala tukang
Mandor

0.600
1.800
0.180
0.030

Oh
Oh
Oh
Oh

x
x
x
x

45,000.00
65,000.00
75,000.00
55,000.00
Jumlah (2)
Jumlah (1) +(2)

PK 6.59.
1 M Pasang plywood tebal 4 mm, untuk dinding :
6.59.1. Bahan
Plywood 4' x 8' x 4 mm
0.4000 Lbr x Rp.
Paku biasa 2" - 5"
0.050 Kg x Rp.
6.59.2. Tenaga
Pekerja
Tukang kayu
Kepala tukang
Mandor

0.025
0.075
0.0075
0.0013

Oh
Oh
Oh
Oh

PK 6.60.
1 M' Pasang list plafond kayu profil :
6.60.1. Bahan
Kayu profil 2"
1.050 M'
6.60.2. Tenaga
Pekerja
Tukang kayu
Kepala tukang
Mandor

0.021
0.021
0.002
0.001

Oh
Oh
Oh
Oh

64,520.00
10,930.00
Jumlah (1)

= Rp.
= Rp.
= Rp.

25,808.00
546.50
26,354.50

Rp.
Rp.
Rp.
Rp.

45,000.00
65,000.00
75,000.00
55,000.00
Jumlah (2)
Jumlah (1) +(2)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

1,125.00
4,875.00
562.50
71.50
6,634.00
32,988.50

x Rp.

11,400.00
Jumlah (1)

= Rp.
= Rp.

11,970.00
11,970.00

x
x
x
x

45,000.00
65,000.00
75,000.00
55,000.00
Jumlah (2)
Jumlah (1) +(2)

=
=
=
=
=
=

945.00
1,365.00
150.00
55.00
2,515.00
14,485.00

x
x
x
x

BERSAMBUNG : ABK PEKERJAAN BETON

Rp.
Rp.
Rp.
Rp.

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

ANALISA BIAYA KONSTRUKSI


PEKERJAAN BETON

PB 6.1.
6.1.1

6.1.2.

PB 6.2.
6.2.1

6.2.2.

PB 6.3.
6.3.1

6.3.2.

PB 6.4.
6.4.1

6.4.2.

PB 6.5.
6.5.1.

6.5.2.

1 M Membuat beton tumbuk, 1 Pc : 3 Ps : 5 Kr


Bahan
Semen portland
218.000 Kg x
Pasir beton
0.520 M x
Koral beton 5/7
0.870 M x

Rp.
Rp.
Rp.

1,200
102,000
159,500
Jumlah (1)

=
=
=
=

Rp.
Rp.
Rp.
Rp.

261,600.00
53,040.00
138,765.00
453,405.00

Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

x
x
x
x

Rp.
Rp.
Rp.
Rp.

45,000
65,000
75,000
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

74,250.00
16,250.00
1,875.00
4,400.00
96,775.00
550,180.00

1 M Membuat beton tumbuk, 1 Pc : 3 Ps : 6 Kr


Bahan
Semen portland
197.000 Kg x
Pasir beton
0.470 M x
Koral beton 5/7
0.940 M x

Rp.
Rp.
Rp.

1,200
102,000
159,500
Jumlah (1)

=
=
=
=

Rp.
Rp.
Rp.
Rp.

236,400.00
47,940.00
149,930.00
434,270.00

Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

x
x
x
x

Rp.
Rp.
Rp.
Rp.

45,000
65,000
75,000
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

74,250.00
16,250.00
1,875.00
4,400.00
96,775.00
531,045.00

1 M Membuat beton tumbuk, 1 Pc : 4 Ps : 6 Kr


Bahan
Semen portland
173.000 Kg x
Pasir beton
0.570 M x
Koral beton 5/7
0.870 M x

Rp.
Rp.
Rp.

1,200
102,000
159,500
Jumlah (1)

=
=
=
=

Rp.
Rp.
Rp.
Rp.

207,600.00
58,140.00
138,765.00
404,505.00

Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

Rp.
Rp.
Rp.
Rp.

45,000
65,000
75,000
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

74,250.00
16,250.00
1,875.00
4,400.00
96,775.00
501,280.00

1.650
0.250
0.025
0.080

1.650
0.250
0.025
0.080

1.650
0.250
0.025
0.080

Oh
Oh
Oh
Oh

Oh
Oh
Oh
Oh

Oh
Oh
Oh
Oh

x
x
x
x

1 M2 Membuat Lantai Kerja beton tumbuk, 1 Pc : 3 Ps : 5 Kr, Tebal 5 Cm


Bahan
Semen portland
Pasir beton
Koral beton

Rp.
Rp.
Rp.

1,200
102,000
159,500
Jumlah (1)

=
=
=
=

Rp.
Rp.
Rp.
Rp.

12,000.00
2,652.00
7,018.00
21,670.00

x
x
x
x

Rp.
Rp.
Rp.
Rp.

45,000
65,000
75,000
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

51,750.00
1,300.00
150.00
330.00
53,530.00
75,200.00

1 M Membuat beton tumbuk 1 Pc : 2 Ps : 3 Kr


Bahan
Semen portland
232.000 Kg x
Pasir beton
0.520 M x
Koral beton
0.780 M x

Rp.
Rp.
Rp.

1,200
102,000
159,500
Jumlah (1)

=
=
=
=

Rp.
Rp.
Rp.
Rp.

278,400.00
53,040.00
124,410.00
455,850.00

Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

Rp.
Rp.
Rp.
Rp.

45,000
65,000
75,000
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

74,250.00
16,250.00
1,875.00
4,400.00
96,775.00
552,625.00

Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

10.000 Kg x
0.026 M x
0.044 M x

1.150
0.020
0.002
0.006

1.650
0.250
0.025
0.080

Oh
Oh
Oh
Oh

Oh
Oh
Oh
Oh

x
x
x
x

PB 6.6.
6.6.1.

6.6.2.

PB 6.7.
6.7.1.

6.7.2.

PB 6.8.
6.8.1.

6.8.2.

PB 6.9.
6.9.1.

6.9.2.

PB 6.10.

1 M Membuat beton tumbuk 1 Pc : 2 Ps : 4 Kr


Bahan
Semen portland
Pasir beton
Koral beton 3/5
Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

280.000 Kg x
0.450 M x
0.900 M x

Rp.
Rp.
Rp.

1,200
102,000
175,890
Jumlah (1)

=
=
=
=

Rp.
Rp.
Rp.
Rp.

336,000.00
45,900.00
158,301.00
540,201.00

x
x
x
x

Rp.
Rp.
Rp.
Rp.

45,000
65,000
75,000
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

74,250.00
16,250.00
1,875.00
4,400.00
96,775.00
636,976.00

352.000 Kg x
0.560 M x
0.700 M x

Rp.
Rp.
Rp.

1,200
102,000
175,890
Jumlah (1)

=
=
=
=

Rp.
Rp.
Rp.
Rp.

422,400.00
57,120.00
123,123.00
602,643.00

x
x
x
x

Rp.
Rp.
Rp.
Rp.

45,000
65,000
75,000
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

74,250.00
16,250.00
1,875.00
4,400.00
96,775.00
699,418.00

357.000 Kg x
0.420 M x
0.540 M x

Rp.
Rp.
Rp.

1,200
102,000
175,890
Jumlah (1)

=
=
=
=

Rp.
Rp.
Rp.
Rp.

428,400.00
42,840.00
94,980.60
566,220.60

x
x
x
x

Rp.
Rp.
Rp.
Rp.

45,000
65,000
75,000
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

74,250.00
16,250.00
1,875.00
4,400.00
96,775.00
662,995.60

386.000 Kg x
0.470 M x
0.780 M x

Rp.
Rp.
Rp.

1,200
102,000
175,890
Jumlah (1)

=
=
=
=

Rp.
Rp.
Rp.
Rp.

463,200.00
47,940.00
137,194.20
648,334.20

x
x
x
x

Rp.
Rp.
Rp.
Rp.

45,000
65,000
75,000
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

74,250.00
16,250.00
1,875.00
4,400.00
96,775.00
745,109.20

479.000 Kg x
0.370 M x
0.740 M x

Rp.
Rp.
Rp.

1,200
102,000
175,890
Jumlah (1)

=
=
=
=

Rp.
Rp.
Rp.
Rp.

574,800.00
37,740.00
130,158.60
742,698.60

Rp.
Rp.
Rp.
Rp.

45,000
65,000
75,000
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

74,250.00
16,250.00
1,875.00
4,400.00
96,775.00
839,473.60

1.650
0.250
0.025
0.080

Oh
Oh
Oh
Oh

1 M Membuat beton tumbuk 1 Pc : 2 Ps : 2,5 Kr


Bahan
Semen portland
Pasir beton
Koral beton 3/5
Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

1.650
0.250
0.025
0.080

Oh
Oh
Oh
Oh

1 M Membuat beton tumbuk 1 Pc : 1,5 Ps : 3 Kr


Bahan
Semen portland
Pasir beton
Koral beton 3/5
Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

1.650
0.250
0.025
0.080

Oh
Oh
Oh
Oh

1 M Membuat beton tumbuk 1 Pc : 1,5 Ps : 2,5 Kr


Bahan
Semen portland
Pasir beton
Koral beton 3/5
Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

1.650
0.250
0.025
0.080

Oh
Oh
Oh
Oh

1 M Membuat beton tumbuk 1 Pc : 1 Ps : 2 Kr

6.10.1. Bahan
Semen portland
Pasir beton
Koral beton 3/5
6.10.2. Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

1.650
0.250
0.025
0.080

Oh
Oh
Oh
Oh

x
x
x
x

PB 6.11. 1 M Membuat tiang pancang prestressed beton


6.11.1. Bahan
Semen portland
440.000 Kg
Pasir beton
0.500 M
Koral Beton/batu pecah 2/3
0.800 M
Rapidrant
2.460 Gln

x
x
x
x

Rp.
Rp.
Rp.
Rp.

1,200 =
102,000 =
168,180 =
=
Jumlah (1)
=

Rp.
Rp.
Rp.
Rp.
Rp.

528,000.00
51,000.00
134,544.00
0.00
713,544.00

x
x
x
x

Rp.
Rp.
Rp.
Rp.

45,000
65,000
75,000
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

74,250.00
16,250.00
1,875.00
4,400.00
96,775.00
810,319.00

PB 6.13
1 M Membuat beton bertulang 1 Pc : 2 Ps : 3 Kr
6.13.1. Bahan
Semen portland
336.000 Kg x
Pasir beton
0.540 M x
Koral Beton/batu pecah 2/3
0.810 M x

Rp.
Rp.
Rp.

1,200
102,000
168,180
Jumlah (1)

=
=
=
=

Rp.
Rp.
Rp.
Rp.

403,200.00
55,080.00
136,225.80
594,505.80

x
x
x
x

Rp.
Rp.
Rp.
Rp.

45,000
65,000
75,000
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

90,000.00
22,750.00
2,625.00
55,000.00
170,375.00
764,880.80

PB 6.14. 1 M Membuat beton bertulang 1 Pc : 2 Ps : 4 Kr


6.14.1. Bahan
Semen portland
291.000 Kg x
Pasir beton
0.470 M x
Koral Beton/batu pecah 2/3
0.930 M x

Rp.
Rp.
Rp.

1,200
102,000
168,180
Jumlah (1)

=
=
=
=

Rp.
Rp.
Rp.
Rp.

349,200.00
47,940.00
156,407.40
553,547.40

x
x
x
x

Rp.
Rp.
Rp.
Rp.

45,000
65,000
75,000
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

90,000.00
22,750.00
2,625.00
55,000.00
170,375.00
723,922.40

1 M Membuat beton bertulang 1 Pc : 1,5 Ps : 3 Kr


Semen portland
367.000 Kg x
Pasir beton
0.440 M x
Koral beton 2/3
0.880 M x

Rp.
Rp.
Rp.

1,200
102,000
168,180
Jumlah (1)

=
=
=
=

Rp.
Rp.
Rp.
Rp.

440,400.00
44,880.00
147,998.40
633,278.40

Rp.
Rp.
Rp.
Rp.

45,000
65,000
75,000
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

90,000.00
22,750.00
2,625.00
55,000.00
170,375.00
803,653.40

x
x
x

Rp.
Rp.
Rp.

1,200
102,000
168,180
Jumlah (1)

=
=
=
=

Rp.
Rp.
Rp.
Rp.

480,000.00
48,960.00
147,998.40
676,958.40

x
x
x
x

Rp.
Rp.
Rp.
Rp.

45,000
65,000
75,000
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

90,000.00
22,750.00
2,625.00
55,000.00
170,375.00
847,333.40

PB 6.17. 1 M Membuat beton 1 Pc : 1 Ps : 1 Kr


6.17.1. Bahan
Semen portland
615.000 Kg x
Pasir beton
0.520 M x
Koral beton 2/3
0.520 M x

Rp.
Rp.
Rp.

1,200
102,000
168,180
Jumlah (1)

=
=
=
=

Rp.
Rp.
Rp.
Rp.

738,000.00
53,040.00
87,453.60
878,493.60

Rp.
Rp.
Rp.
Rp.

45,000
65,000
75,000
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

90,000.00
22,750.00
2,625.00
55,000.00
170,375.00
1,048,868.60

6.11.2. Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

6.13.2. Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

6.14.2. Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

PB 6.15.

6.15.2. Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

1.650
0.250
0.025
0.080

2.000
0.350
0.035
1.000

2.000
0.350
0.035
1.000

2.000
0.350
0.035
1.000

Oh
Oh
Oh
Oh

Oh
Oh
Oh
Oh

Oh
Oh
Oh
Oh

Oh
Oh
Oh
Oh

PB 6.16. 1 M Membuat beton bertulang 1 Pc : 1,5 Ps : 2,5


6.16.1. Bahan
Semen portland
400.000 Kg
Pasir beton
0.480 M
Koral beton 2/3
0.880 M
6.16.2. Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

6.17.2. Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

2.000
0.350
0.035
1.000

2.000
0.350
0.035
1.000

Oh
Oh
Oh
Oh

Oh
Oh
Oh
Oh

x
x
x
x

Kr

x
x
x
x

PB 6.25.

1 Kg Pembesian dengan besi polos

6.25.1. Bahan
Besi beton polos
Kawat beton

1.050 Kg x
0.015 Kg x

Rp.
Rp.

12,390 =
11,620 =
Jumlah (1)
=

Rp.
Rp.
Rp.

13,009.50
174.30
13,183.80

6.25.2. Tenaga
Pekerja
Tukang besi
Kepala tukang
Mandor

0.007
0.007
0.007
0.003

x
x
x
x

Rp.
Rp.
Rp.
Rp.

45,000
65,000
75,000
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

315.00
455.00
525.00
165.00
1,460.00
14,643.80

6.26.1. Bahan
Besi Prestressed polos
Kawat beton

1.050 Kg x
0.010 Kg x

Rp.
Rp.

12,390 =
11,620 =
Jumlah (1)
=

Rp.
Rp.
Rp.

13,009.50
116.20
13,125.70

6.26.2. Tenaga
Pekerja
Tukang besi
Kepala tukang
Mandor

0.005
0.005
0.005
0.003

x
x
x
x

Rp.
Rp.
Rp.
Rp.

45,000
65,000
75,000
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

225.00
325.00
375.00
165.00
1,090.00
14,215.70

6.28.1. Bahan
Kayu Sembarang
Paku biasa 2' - 5"
Minyak bekisting

0.040 M x
0.300 Kg x
0.100 Ltr x

Rp.
Rp.
Rp.

3,144,900
10,120
5,720
Jumlah (1)

=
=
=
=

Rp.
Rp.
Rp.
Rp.

125,796.00
3,036.00
572.00
129,404.00

6.28.2. Tenaga
Pekerja
Tukang kayu
Kepala tukang
Mandor

0.300
0.260
0.026
0.005

x
x
x
x

Rp.
Rp.
Rp.
Rp.

45,000
65,000
75,000
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

13,500.00
16,900.00
1,950.00
275.00
32,625.00
162,029.00

6.29.1. Bahan
Kayu Sembarang
Paku biasa 2' - 5"
Minyak bekisting

0.045 M x
0.300 Kg x
0.100 Ltr x

Rp.
Rp.
Rp.

3,144,900
10,120
5,720
Jumlah (1)

=
=
=
=

Rp.
Rp.
Rp.
Rp.

141,520.50
3,036.00
572.00
145,128.50

6.29.2. Tenaga
Pekerja
Tukang kayu
Kepala tukang
Mandor

0.300
0.260
0.026
0.005

Oh
Oh
Oh
Oh

x
x
x
x

Rp.
Rp.
Rp.
Rp.

45,000
65,000
75,000
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

13,500.00
16,900.00
1,950.00
275.00
32,625.00
177,753.50

6.30.1. Bahan
Kayu Sembarang
Paku biasa 2' - 5"
Minyak bekisting
Balok Kayu sembarang
Plywood tebal 9 mm
Kayu Dolken/Laut 3'-4'/4 m

0.040
0.400
0.200
0.015
0.350
2.000

M
Kg
Ltr
M
Lbr
Btg

x
x
x
x
x
x

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

3,144,900
10,120
5,720
3,144,900
156,530
20,750
Jumlah (1)

=
=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

125,796.00
4,048.00
1,144.00
47,173.50
54,785.50
41,500.00
274,447.00

6.30.2. Tenaga
Pekerja
Tukang kayu
Kepala tukang
Mandor

0.300
0.330
0.033
0.006

Oh
Oh
Oh
Oh

x
x
x
x

Rp.
Rp.
Rp.
Rp.

45,000
65,000
75,000
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

13,500.00
21,450.00
2,475.00
330.00
37,755.00
312,202.00

PB 6.26.

PB 6.28.

PB 6.29.

PB 6.30.

Oh
Oh
Oh
Oh

1 M Kg Kabel Presstressed polos / strands

Oh
Oh
Oh
Oh

1 M Pasang bekisting untuk Pondasi

Oh
Oh
Oh
Oh

1 M Pasang bekisting untuk Sloof

1 M Pasang bekisting untuk Kolom

PB 6.31.

1 M Pasang bekisting untuk Balok

6.31.1. Bahan
Kayu Sembarang
Paku biasa 2' - 5"
Minyak bekisting
Balok Kayu sembarang
Plywood tebal 9 mm
Kayu Dolken/Laut 3'-4'/4 m

0.040
0.400
0.200
0.018
0.350
2.000

M
Kg
Ltr
M
Lbr
Btg

x
x
x
x
x
x

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

3,144,900
10,120
5,720
3,144,900
156,530
20,750
Jumlah (1)

=
=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

125,796.00
4,048.00
1,144.00
56,608.20
54,785.50
41,500.00
283,881.70

6.31.2. Tenaga
Pekerja
Tukang kayu
Kepala tukang
Mandor

0.320
0.330
0.033
0.006

Oh
Oh
Oh
Oh

x
x
x
x

Rp.
Rp.
Rp.
Rp.

45,000
65,000
75,000
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

14,400.00
21,450.00
2,475.00
330.00
38,655.00
322,536.70

6.32.1. Bahan
Kayu Sembarang
Paku biasa 2' - 5"
Minyak bekisting
Balok Kayu sembarang
Plywood tebal 9 mm
Kayu Dolken/Laut 3'-4'/4 m

0.040
0.400
0.200
0.015
0.350
6.000

M
Kg
Ltr
M
Lbr
Btg

x
x
x
x
x
x

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

3,144,900
10,120
5,720
3,144,900
156,530
20,750
Jumlah (1)

=
=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

125,796.00
4,048.00
1,144.00
47,173.50
54,785.50
124,500.00
357,447.00

6.32.2. Tenaga
Pekerja
Tukang kayu
Kepala tukang
Mandor

0.320
0.330
0.033
0.006

Oh
Oh
Oh
Oh

x
x
x
x

Rp.
Rp.
Rp.
Rp.

45,000
65,000
75,000
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

14,400.00
21,450.00
2,475.00
330.00
38,655.00
396,102.00

6.33.1. Bahan
Kayu Sembarang
Paku biasa 2' - 5"
Minyak bekisting
Balok Kayu sembarang
Plywood tebal 9 mm
Kayu Dolken/Laut 3'-4'/4 m
Formtie/penjaga jarak bekisting/space

0.030
0.400
0.200
0.020
0.350
3.000
4.000

M
Kg
Ltr
M
Lbr
Btg
Btg

x
x
x
x
x
x
x

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

3,144,900
10,120
5,720
3,144,900
156,530
20,750
5,000
Jumlah (1)

=
=
=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

94,347.00
4,048.00
1,144.00
62,898.00
54,785.50
62,250.00
20,000.00
299,472.50

6.33.2. Tenaga
Pekerja
Tukang kayu
Kepala tukang
Mandor

0.320
0.330
0.033
0.006

Oh
Oh
Oh
Oh

x
x
x
x

Rp.
Rp.
Rp.
Rp.

45,000
65,000
75,000
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

14,400.00
21,450.00
2,475.00
330.00
38,655.00
338,127.50

6.34.1. Bahan
Kayu Sembarang
Paku biasa 2' - 5"
Minyak bekisting
Balok Kayu sembarang
Plywood tebal 9 mm
Kayu Dolken/Laut 3'-4'/4 m

0.030
0.400
0.150
0.015
0.350
2.000

M
Kg
Ltr
M
Lbr
Btg

x
x
x
x
x
x

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

3,144,900
10,120
5,720
3,144,900
156,530
20,750
Jumlah (1)

=
=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

94,347.00
4,048.00
858.00
47,173.50
54,785.50
41,500.00
242,712.00

6.34.2. Tenaga
Pekerja
Tukang kayu
Kepala tukang
Mandor

0.320
0.330
0.033
0.006

Oh
Oh
Oh
Oh

x
x
x
x

Rp.
Rp.
Rp.
Rp.

45,000
65,000
75,000
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

14,400.00
21,450.00
2,475.00
330.00
38,655.00
281,367.00

PB 6.32.

PB 6.33.

PB 6.34.

1 M Pasang bekisting untuk Lantai

1 M Pasang bekisting untuk Dinding

1 M Pasang bekisting untuk Tangga

PB 6.35. 1 M Pasang beton dengan mutu K 225


6.35.1. Bahan
Semen portland
388.000 Kg x
Pasir beton
0.650 M x
Batu pecah
0.650 M x

Rp.
Rp.
Rp.

1,200
102,000
184,680
Jumlah (1)

=
=
=
=

Rp.
Rp.
Rp.
Rp.

465,600.00
66,300.00
120,042.00
651,942.00

x
x
x
x

Rp.
Rp.
Rp.
Rp.

45,000
65,000
75,000
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

270,000.00
65,000.00
7,500.00
16,500.00
359,000.00
1,010,942.00

PB 6.36. 1 M Pasang beton dengan mutu K 275


6.36.1. Bahan
Semen portland
400.000 Kg x
Pasir beton
0.400 M x
Batu pecah
0.820 M x

Rp.
Rp.
Rp.

1,200
102,000
184,680
Jumlah (1)

=
=
=
=

Rp.
Rp.
Rp.
Rp.

480,000.00
40,800.00
151,437.60
672,237.60

x
x
x
x

Rp.
Rp.
Rp.
Rp.

45,000
65,000
75,000
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

270,000.00
65,000.00
7,500.00
16,500.00
359,000.00
1,031,237.60

0.0264 M x
0.600 Kg x
0.500 Btg x

Rp.
Rp.
Rp.

3,144,900
10,120
20,750
Jumlah (1)

=
=
=
=

Rp.
Rp.
Rp.
Rp.

83,025.36
6,072.00
10,375.00
99,472.36

45,000
65,000
75,000
55,000
Jumlah (2)
Jumlah (1) + (2)
1 M Membuat pondasi beton bertulang (150 kg besi + bekisting)
Bahan
Kayu Sembarang, Papan
0.2000 M x Rp.
3,144,900
Paku biasa 2" - 5 "
1.500 Kg x Rp.
10,120
Minyak bekisting
0.400 Ltr x Rp.
5,720
Besi beton polos
150.000 Kg x Rp.
12,390
Kawat beton
2.250 Kg x Rp.
11,620
Semen portland
323.000 Kg x Rp.
1,200
Pasir beton
0.520 M x Rp.
102,000
Koral beton
0.780 M x Rp.
184,680
Jumlah (1)
Tenaga
Pekerja
3.900 Oh x Rp.
45,000
Tukang batu
0.350 Oh x Rp.
65,000
Tukang kayu
1.040 Oh x Rp.
65,000
Tukang besi
1.050 Oh x Rp.
65,000
Kepala tukang
0.245 Oh x Rp.
75,000
Mandor
0.165 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)
1 M Membuat sloof beton bertulang (200 kg besi + bekisting)
Bahan
Kayu Sembarang, Papan
0.2700 M x Rp.
3,144,900
Paku biasa 2" - 5 "
2.000 Kg x Rp.
10,120
Minyak bekisting
0.600 Ltr x Rp.
5,720
Besi beton polos
200.000 Kg x Rp.
12,390
Kawat beton
3.000 Kg x Rp.
11,620
Semen portland
323.000 Kg x Rp.
1,200
Pasir beton
0.520 M x Rp.
102,000
Koral beton
0.780 M x Rp.
184,680
Jumlah (1)
Tenaga
Pekerja
4.850 Oh x Rp.
45,000
Tukang batu
0.350 Oh x Rp.
65,000
Tukang kayu
1.560 Oh x Rp.
65,000
Tukang besi
1.400 Oh x Rp.
65,000
Kepala tukang
0.331 Oh x Rp.
75,000
Mandor
0.170 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

6,750.00
3,250.00
375.00
385.00
10,760.00
110,232.36

=
=
=
=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

628,980.00
15,180.00
2,288.00
1,858,500.00
26,145.00
387,600.00
53,040.00
144,050.40
3,115,783.40

=
=
=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

175,500.00
22,750.00
67,600.00
68,250.00
18,375.00
9,075.00
361,550.00
3,477,333.40

=
=
=
=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

849,123.00
20,240.00
3,432.00
2,478,000.00
34,860.00
387,600.00
53,040.00
144,050.40
3,970,345.40

=
=
=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

218,250.00
22,750.00
101,400.00
91,000.00
24,825.00
9,350.00
467,575.00
4,437,920.40

6.35.2. Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

6.36.2. Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

PB 6.37. 1 M Pasang Bekisting Jembatan cor


6.37.1. Bahan
Kayu Sembarang, Papan
Paku biasa 2" - 5 "
Kayu Dolken/Laut 3'-4'/4 m
6.37.2. Tenaga
Pekerja
Tukang kayu
Kepala tukang
Mandor

PB 6.38.
6.38.1.

6.38.2.

PB 6.39.
6.39.1.

6.39.2.

6.000
1.000
0.100
0.300

6.000
1.000
0.100
0.300

0.150
0.050
0.005
0.007

Oh
Oh
Oh
Oh

Oh
Oh
Oh
Oh

Oh
Oh
Oh
Oh

x
x
x
x

Rp.
Rp.
Rp.
Rp.

PB 6.40.

1 M Membuat kolom beton bertulang (300 kg besi + bekisting)

6.40.1. Bahan
Kayu Sembarang, Papan
Paku biasa 2" - 5 "
Minyak bekisting
Besi beton polos
Kawat beton
Semen portland
Pasir beton
Koral beton
Kayu sembarang balok
Plywood 9 mm
Kayu Dolken/Laut 3'-4'/4 m
6.40.2. Tenaga
Pekerja
Tukang batu
Tukang kayu
Tukang besi
Kepala tukang
Mandor

0.4000
4.000
2.000
300.000
4.500
323.000
0.520
0.780
0.150
3.500
20.000

M
Kg
Ltr
Kg
Kg
Kg
M
M
M
Lbr
Btg

x
x
x
x
x
x
x
x
x
x
x

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

3,144,900
10,120
5,720
12,390
11,620
1,200
102,000
184,680
3,144,900
156,530
20,750
Jumlah (1)

=
=
=
=
=
=
=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

1,257,960.00
40,480.00
11,440.00
3,717,000.00
52,290.00
387,600.00
53,040.00
144,050.40
471,735.00
547,855.00
415,000.00
7,098,450.40

7.300
0.350
3.300
2.100
0.570
0.250

Oh
Oh
Oh
Oh
Oh
Oh

x
x
x
x
x
x

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

45,000
65,000
65,000
65,000
75,000
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

328,500.00
22,750.00
214,500.00
136,500.00
42,750.00
13,750.00
758,750.00
7,857,200.40

=
=
=
=
=
=
=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

1,006,368.00
32,384.00
9,152.00
2,478,000.00
34,860.00
387,600.00
53,040.00
144,050.40
440,286.00
438,284.00
332,000.00
5,356,024.40

=
=
=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

268,200.00
22,750.00
182,000.00
91,000.00
34,125.00
11,440.00
609,515.00
5,965,539.40

=
=
=
=
=
=
=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

1,006,368.00
32,384.00
9,152.00
1,858,500.00
26,145.00
387,600.00
53,040.00
144,050.40
377,388.00
438,284.00
664,000.00
4,996,911.40

=
=
=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

261,000.00
22,750.00
182,000.00
68,250.00
31,500.00
10,175.00
575,675.00
5,572,586.40

PB 6.41. 1 M Membuat balok beton bertulang (200 kg besi + bekisting)


6.41.1. Bahan
Kayu Sembarang, Papan
0.3200 M x Rp.
3,144,900
Paku biasa 2" - 5 "
3.200 Kg x Rp.
10,120
Minyak bekisting
1.600 Ltr x Rp.
5,720
Besi beton polos
200.000 Kg x Rp.
12,390
Kawat beton
3.000 Kg x Rp.
11,620
Semen portland
323.000 Kg x Rp.
1,200
Pasir beton
0.520 M x Rp.
102,000
Koral beton
0.780 M x Rp.
184,680
Kayu sembarang balok
0.140 M x Rp.
3,144,900
Plywood 9 mm
2.800 Lbr x Rp.
156,530
Kayu Dolken/Laut 3'-4'/4 m
16.000 Btg x Rp.
20,750
Jumlah (1)
6.41.2. Tenaga
Pekerja
5.960 Oh x Rp.
45,000
Tukang batu
0.350 Oh x Rp.
65,000
Tukang kayu
2.800 Oh x Rp.
65,000
Tukang besi
1.400 Oh x Rp.
65,000
Kepala tukang
0.455 Oh x Rp.
75,000
Mandor
0.208 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

PB 6.42. 1 M Membuat balok beton bertulang (150 kg besi + bekisting)


6.42.1. Bahan
Kayu Sembarang, Papan
0.320 M x Rp.
3,144,900
Paku biasa 2" - 5 "
3.200 Kg x Rp.
10,120
Minyak bekisting
1.600 Ltr x Rp.
5,720
Besi beton polos
150.000 Kg x Rp.
12,390
Kawat beton
2.250 Kg x Rp.
11,620
Semen portland
323.000 Kg x Rp.
1,200
Pasir beton
0.520 M x Rp.
102,000
Koral beton
0.780 M x Rp.
184,680
Kayu sembarang balok
0.120 M x Rp.
3,144,900
Plywood 9 mm
2.800 Lbr x Rp.
156,530
Kayu Dolken/Laut 3'-4'/4 m
32.000 Btg x Rp.
20,750
Jumlah (1)
6.42.2. Tenaga
Pekerja
5.800 Oh x Rp.
45,000
Tukang batu
0.350 Oh x Rp.
65,000
Tukang kayu
2.800 Oh x Rp.
65,000
Tukang besi
1.050 Oh x Rp.
65,000
Kepala tukang
0.420 Oh x Rp.
75,000
Mandor
0.185 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

PB 6.43. 1 M Membuat dinding beton bertulang (150 kg besi + bekisting)


6.43.1. Bahan
Kayu Sembarang, Papan
0.240 M x Rp.
3,144,900
Paku biasa 2" - 5 "
3.200 Kg x Rp.
10,120
Minyak bekisting
1.600 Ltr x Rp.
5,720
Besi beton polos
150.000 Kg x Rp.
12,390
Kawat beton
2.250 Kg x Rp.
11,620
Semen portland
323.000 Kg x Rp.
1,200
Pasir beton
0.520 M x Rp.
102,000
Koral beton
0.780 M x Rp.
184,680
Kayu sembarang balok
0.160 M x Rp.
3,144,900
Plywood 9 mm
2.800 Lbr x Rp.
156,530
Kayu Dolken/Laut 3'-4'/4 m
24.000 Btg x Rp.
20,750
Jumlah (1)
6.43.2. Tenaga
Pekerja
5.600 Oh x Rp.
45,000
Tukang batu
0.350 Oh x Rp.
65,000
Tukang kayu
2.640 Oh x Rp.
65,000
Tukang besi
1.050 Oh x Rp.
65,000
Kepala tukang
0.400 Oh x Rp.
75,000
Mandor
0.193 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)
PB 6.44.

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

754,776.00
32,384.00
9,152.00
1,858,500.00
26,145.00
387,600.00
53,040.00
144,050.40
503,184.00
438,284.00
498,000.00
4,705,115.40

=
=
=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

252,000.00
22,750.00
171,600.00
68,250.00
30,000.00
10,615.00
555,215.00
5,260,330.40

1 M Membuat tangga beton bertulang (150 kg besi + bekisting)

6.44.1. Bahan
Kayu Sembarang, Papan
Paku biasa 2" - 5 "
Minyak bekisting
Besi beton polos
Kawat beton
Semen portland
Pasir beton
Koral beton
Kayu sembarang balok
Plywood 9 mm
Kayu Dolken/Laut 3'-4'/4 m
6.44.2. Tenaga
Pekerja
Tukang batu
Tukang kayu
Tukang besi
Kepala tukang
Mandor

PB 6.46.

=
=
=
=
=
=
=
=
=
=
=
=

0.250
3.000
1.200
200.000
3.000
323.000
0.520
0.780
0.105
2.500
14.000

M
Kg
Ltr
Kg
Kg
Kg
M
M
M
Lbr
Btg

x
x
x
x
x
x
x
x
x
x
x

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

3,144,900
10,120
5,720
12,390
11,620
1,200
102,000
184,680
3,144,900
156,530
20,750
Jumlah (1)

=
=
=
=
=
=
=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

786,225.00
30,360.00
6,864.00
2,478,000.00
34,860.00
387,600.00
53,040.00
144,050.40
330,214.50
391,325.00
290,500.00
4,933,038.90

5.600
0.350
2.300
1.400
0.405
0.202

Oh
Oh
Oh
Oh
Oh
Oh

x
x
x
x
x
x

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

45,000
65,000
65,000
65,000
75,000
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

252,000.00
22,750.00
149,500.00
91,000.00
30,375.00
11,110.00
556,735.00
5,489,773.90

1 M' Membuat ring balok beton bertulang (10 x 15) cm

6.46.1. Bahan
Kayu Sembarang, Papan
Paku biasa 2" - 5 "
Besi beton polos
Kawat beton
Semen portland
Pasir beton
Koral beton

0.003
0.020
3.600
0.050
5.500
0.009
0.015

M
Kg
Kg
Kg
Kg
M
M

x
x
x
x
x
x
x

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

3,144,900
10,120
12,390
11,620
1,200
102,000
184,680
Jumlah (1)

=
=
=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

9,434.70
202.40
44,604.00
581.00
6,600.00
918.00
2,770.20
65,110.30

6.46.2. Tenaga
Pekerja
Tukang batu
Tukang kayu
Tukang besi
Kepala tukang
Mandor

0.100
0.033
0.033
0.033
0.010
0.005

Oh
Oh
Oh
Oh
Oh
Oh

x
x
x
x
x
x

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

45,000
65,000
65,000
65,000
75,000
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

4,500.00
2,145.00
2,145.00
2,145.00
750.00
275.00
11,960.00
77,070.30

BERSAMBUNG : ABK PEKERJAAN PENUTUP ATAP

ANALISA BIAYA KONSTRUKSI


PEKERJAAN PENUTUP ATAP

PPA 6.1
1 M Pasang atap genteng palentong kecil
6.1.1 Bahan
Genteng Pelantong
25.00 Buah x Rp.
1,520
Jumlah (1)
6.1.2 Tenaga
Pekerja
0.150 Oh x Rp.
45,000
Tukang Kayu
0.075 Oh x Rp.
65,000
Kepala Tukang
0.008 Oh x Rp.
75,000
Mandor
0.008 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)
PPA 6.2
1 M Pasang atap genteng kodok / glazzur
6.2.1 Bahan
Genteng kodok
25.00 Buah x Rp.
1,970
Jumlah (1)
6.2.2 Tenaga
Pekerja
0.150 Oh x Rp.
45,000
Tukang Kayu
0.075 Oh x Rp.
65,000
Kepala Tukang
0.008 Oh x Rp.
75,000
Mandor
0.008 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)
PPA 6.3
1 M Pasang atap genteng palentong super / besar
6.3.1 Bahan
Genteng pelantong super
12.00 Buah x Rp.
3,620
Jumlah (1)
6.3.2 Tenaga
Pekerja
0.150 Oh x Rp.
45,000
Tukang Kayu
0.060 Oh x Rp.
65,000
Kepala Tukang
0.006 Oh x Rp.
75,000
Mandor
0.008 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

PPA 6.4
1 M Pasang genteng bubung palentong
6.4.1 Bahan
Bubung genteng pelantong
5.00 Buah x Rp.
8,500
Semen portland
8.000 Kg x Rp.
1,200
Pasir Pasang
0.032 M x Rp.
94,500
Jumlah (1)
6.4.2 Tenaga
Pekerja
0.400 Oh x Rp.
45,000
Tukang Kayu
0.200 Oh x Rp.
65,000
Kepala Tukang
0.020 Oh x Rp.
75,000
Mandor
0.002 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

PPA 6.5
1 M' Pasang bubung genteng kodok glazzuur
6.5.1 Bahan
Bubung genteng kodok
5.00 Buah x Rp.
8,690
Semen portland
8.000 Kg x Rp.
1,200
Pasir Pasang
0.032 M x Rp.
94,500
Jumlah (1)
6.5.2 Tenaga
Pekerja
0.400 Oh x Rp.
45,000
Tukang Kayu
0.200 Oh x Rp.
65,000
Kepala Tukang
0.020 Oh x Rp.
75,000
Mandor
0.002 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

= Rp.
= Rp.

38,000.00
38,000.00

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

6,750.00
4,875.00
600.00
440.00
12,665.00
50,665.00

= Rp.
= Rp.

49,250.00
49,250.00

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

6,750.00
4,875.00
600.00
440.00
12,665.00
61,915.00

= Rp.
= Rp.

43,440.00
43,440.00

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

6,750.00
3,900.00
450.00
440.00
11,540.00
54,980.00

=
=
=
=

Rp.
Rp.
Rp.
Rp.

42,500.00
9,600.00
3,024.00
55,124.00

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

18,000.00
13,000.00
1,500.00
110.00
32,610.00
87,734.00

=
=
=
=

Rp.
Rp.
Rp.
Rp.

43,450.00
9,600.00
3,024.00
56,074.00

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

18,000.00
13,000.00
1,500.00
110.00
32,610.00
88,684.00

PPA 6.6
1 M' Pasang bubung genteng palentong besar
6.6.1 Bahan
Bubung genteng pelantong besar
4.00 Buah x Rp.
11,580
Semen portland
8.000 Kg x Rp.
1,200
Pasir Pasang
0.032 M x Rp.
94,500
Jumlah (1)
6.6.2 Tenaga
Pekerja
0.400 Oh x Rp.
45,000
Tukang Kayu
0.200 Oh x Rp.
65,000
Kepala Tukang
0.020 Oh x Rp.
75,000
Mandor
0.002 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)
PPA 6.7
1 M Pasang roof light fiberglass ( 180 x 90 ) cm
6.7.1 Bahan
Roof light fibreglass
0.600 Lbr x Rp.
41,170
Paku biasa " - 1"
0.050 Kg x Rp.
10,930
Jumlah (1)
6.7.2 Tenaga
Pekerja
0.140 Oh x Rp.
45,000
Tukang Kayu
0.067 Oh x Rp.
65,000
Kepala Tukang
0.007 Oh x Rp.
75,000
Mandor
0.007 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)
PPA 6.8
1 M Pasang atap asbes gelombang ( 2,70 x 0,92 m ) x 5 mm
6.8.1 Bahan
Atap asbes gelombang
0.450 Lbr x Rp.
91,300
Paku seng
0.120 Kg x Rp.
18,500
Jumlah (1)
6.8.2 Tenaga
Pekerja
0.140 Oh x Rp.
45,000
Tukang Kayu
0.075 Oh x Rp.
65,000
Kepala Tukang
0.008 Oh x Rp.
75,000
Mandor
0.008 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)
PPA 6.9
1 M Pasang atap asbes gelombang ( 2,40 x 0,92 m ) x 5 mm
6.9.1 Bahan
Atap asbes gelombang
0.500 Lbr x Rp.
83,000
Paku seng
0.120 Kg x Rp.
18,500
Jumlah (1)
6.9.2 Tenaga
Pekerja
0.140 Oh x Rp.
45,000
Tukang Kayu
0.075 Oh x Rp.
65,000
Kepala Tukang
0.008 Oh x Rp.
75,000
Mandor
0.008 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)
PPA 6.10 1 M Pasang atap asbes gelombang ( 2,1 x 0,92 m ) x 5 mm
6.10.1 Bahan
Atap asbes gelombang
0.600 Lbr x Rp.
76,090
Paku seng
0.120 Kg x Rp.
18,500
Jumlah (1)
6.10.2 Tenaga
Pekerja
0.140 Oh x Rp.
45,000
Tukang Kayu
0.075 Oh x Rp.
65,000
Kepala Tukang
0.008 Oh x Rp.
75,000
Mandor
0.008 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)
PPA 6.11 1 M Pasang atap asbes gelombang ( 1,80 x 0,92 m ) x 5 mm
6.11.1 Bahan
Atap asbes gelombang
0.750 Lbr x Rp.
60,860
Paku seng
0.120 Kg x Rp.
18,500
Jumlah (1)
6.11.2 Tenaga
Pekerja
0.140 Oh x Rp.
45,000
Tukang Kayu
0.070 Oh x Rp.
65,000
Kepala Tukang
0.007 Oh x Rp.
75,000
Mandor
0.007 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=

Rp.
Rp.
Rp.
Rp.

46,320.00
9,600.00
3,024.00
58,944.00

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

18,000.00
13,000.00
1,500.00
110.00
32,610.00
91,554.00

= Rp.
= Rp.
= Rp.

24,702.00
546.50
25,248.50

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

6,300.00
4,355.00
525.00
385.00
11,565.00
36,813.50

= Rp.
= Rp.
= Rp.

41,085.00
2,220.00
43,305.00

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

6,300.00
4,875.00
600.00
440.00
12,215.00
55,520.00

= Rp.
= Rp.
= Rp.

41,500.00
2,220.00
43,720.00

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

6,300.00
4,875.00
600.00
440.00
12,215.00
55,935.00

= Rp.
= Rp.
= Rp.

45,654.00
2,220.00
47,874.00

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

6,300.00
4,875.00
600.00
440.00
12,215.00
60,089.00

= Rp.
= Rp.
= Rp.

45,645.00
2,220.00
47,865.00

=
=
=
=
=
=

6,300.00
4,550.00
525.00
385.00
11,760.00
59,625.00

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

PPA 6.12 1 M Pasang atap asbes gelombang ( 2,40 x 1,05 m ) x 4 mm


6.12.1 Bahan
Atap asbes gelombang
0.450 Lbr x Rp.
94,500
Paku seng
0.120 Kg x Rp.
18,500
Jumlah (1)
6.12.2 Tenaga
Pekerja
0.140 Oh x Rp.
45,000
Tukang Kayu
0.070 Oh x Rp.
65,000
Kepala Tukang
0.007 Oh x Rp.
75,000
Mandor
0.007 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)
PPA 6.13 1 M Pasang atap asbes gelombang ( 2,10 x 1,05 m ) x 4 mm
6.13.1 Bahan
Atap asbes gelombang
0.500 Lbr x Rp.
81,530
Paku seng
0.120 Kg x Rp.
18,500
Jumlah (1)
6.13.2 Tenaga
Pekerja
0.140 Oh x Rp.
45,000
Tukang Kayu
0.070 Oh x Rp.
65,000
Kepala Tukang
0.007 Oh x Rp.
75,000
Mandor
0.007 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)
PPA 6.14 1 M Pasang atap asbes gelombang ( 1,80 x 1,05 m ) x 4 mm
6.14.1 Bahan
Atap asbes gelombang
0.600 Lbr x Rp.
51,980
Paku seng
0.120 Kg x Rp.
18,500
Jumlah (1)
6.14.2 Tenaga
Pekerja
0.140 Oh x Rp.
45,000
Tukang Kayu
0.067 Oh x Rp.
65,000
Kepala Tukang
0.007 Oh x Rp.
75,000
Mandor
0.007 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)
PPA 6.18 1 M Pasang atap asbes gelombang ( 2,70 x 1,08 m ) x 6 mm
6.18.1 Bahan
Atap asbes gelombang
0.380 Lbr x Rp.
131,130
Paku seng
0.120 Kg x Rp.
18,500
Jumlah (1)
6.18.2 Tenaga
Pekerja
0.140 Oh x Rp.
45,000
Tukang Kayu
0.067 Oh x Rp.
65,000
Kepala Tukang
0.007 Oh x Rp.
75,000
Mandor
0.007 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)
PPA 6.19 1 M Pasang atap asbes gelombang ( 2,4 x 1,08 m ) x 6 mm
6.19.1 Bahan
Atap asbes gelombang
0.450 Lbr x Rp.
108,330
Paku seng
0.120 Kg x Rp.
18,500
Jumlah (1)
6.19.2 Tenaga
Pekerja
0.140 Oh x Rp.
45,000
Tukang Kayu
0.067 Oh x Rp.
65,000
Kepala Tukang
0.007 Oh x Rp.
75,000
Mandor
0.007 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)
PPA 6.20 1 M Pasang atap asbes gelombang ( 2,1 x 1,08 m ) x 6 mm
6.20.1 Bahan
Atap asbes gelombang
0.490 Lbr x Rp.
101,700
Paku seng
0.120 Kg x Rp.
18,500
Jumlah (1)
6.16.2 Tenaga
Pekerja
0.140 Oh x Rp.
45,000
Tukang Kayu
0.067 Oh x Rp.
65,000
Kepala Tukang
0.007 Oh x Rp.
75,000
Mandor
0.007 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

= Rp.
= Rp.
= Rp.

42,525.00
2,220.00
44,745.00

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

6,300.00
4,550.00
525.00
385.00
11,760.00
56,505.00

= Rp.
= Rp.
= Rp.

40,765.00
2,220.00
42,985.00

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

6,300.00
4,550.00
525.00
385.00
11,760.00
54,745.00

= Rp.
= Rp.
= Rp.

31,188.00
2,220.00
33,408.00

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

6,300.00
4,355.00
525.00
385.00
11,565.00
44,973.00

= Rp.
= Rp.
= Rp.

49,829.40
2,220.00
52,049.40

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

6,300.00
4,355.00
525.00
385.00
11,565.00
63,614.40

= Rp.
= Rp.
= Rp.

48,748.50
2,220.00
50,968.50

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

6,300.00
4,355.00
525.00
385.00
11,565.00
62,533.50

= Rp.
= Rp.
= Rp.

49,833.00
2,220.00
52,053.00

=
=
=
=
=
=

6,300.00
4,355.00
525.00
385.00
11,565.00
63,618.00

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

PPA 6.21 1 M Pasang atap asbes gelombang ( 1,80 x 1,08 m ) x 6 mm


6.21.1 Bahan
Atap asbes gelombang
0.570 Lbr x Rp.
87,420
Paku seng
0.120 Kg x Rp.
18,500
Jumlah (1)
6.21.2 Tenaga
Pekerja
0.140 Oh x Rp.
45,000
Tukang Kayu
0.067 Oh x Rp.
65,000
Kepala Tukang
0.007 Oh x Rp.
75,000
Mandor
0.007 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)
PPA 6.22 1 M' Pasang bubung stel gelombang 0,92 m
6.22.1 Bahan
Bubung stel gelombang
2.40 Lbr
Paku seng
6.00 Bh
6.22.2 Tenaga
Pekerja
Tukang Kayu
Kepala Tukang
Mandor

0.084
0.125
0.013
0.004

Oh
Oh
Oh
Oh

PPA 6.23 1 M' Pasang nok stel gelombang 1,05 m


6.23.1 Bahan
Bubung stel gelombang
2.10 Lbr
Paku seng
6.00 Bh
6.23.2 Tenaga
Pekerja
Tukang Kayu
Kepala Tukang
Mandor

0.084
0.125
0.013
0.004

Oh
Oh
Oh
Oh

PPA 6.24 1 M' Pasang nok stel gelombang 1,08 m


6.24.1 Bahan
Bubung stel gelombang
2.05 Lbr
Paku seng
6.00 Bh
6.24.2 Tenaga
Pekerja
Tukang Kayu
Kepala Tukang
Mandor

PPA 6.25 1 M' Pasang nok paten 0,92 m


6.25.1 Bahan
Nok Paten 5 mm
Paku seng
6.25.2 Tenaga
Pekerja
Tukang Kayu
Kepala Tukang
Mandor

PPA 6.26 1 M' Pasang nok paten 1,05 m


6.26.1 Bahan
Nok Paten 4 mm
Paku seng
6.26.2 Tenaga
Pekerja
Tukang Kayu
Kepala Tukang
Mandor

0.084
0.125
0.013
0.004

Oh
Oh
Oh
Oh

1.20 Lbr
6.00 Bh

0.084
0.125
0.013
0.004

Oh
Oh
Oh
Oh

1.20 Lbr
6.00 Bh

0.084
0.125
0.013
0.004

Oh
Oh
Oh
Oh

= Rp.
= Rp.
= Rp.

49,829.40
2,220.00
52,049.40

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

6,300.00
4,355.00
525.00
385.00
11,565.00
63,614.40

x Rp.
17,810 = Rp.
x Rp.
18,500 = Rp.
Jumlah (1)
= Rp.

42,744.00
111,000.00
153,744.00

x
x
x
x

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

3,780.00
8,125.00
975.00
220.00
13,100.00
166,844.00

x Rp.
23,630 = Rp.
x Rp.
18,500 = Rp.
Jumlah (1)
= Rp.

49,623.00
111,000.00
160,623.00

x
x
x
x

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

3,780.00
8,125.00
975.00
220.00
13,100.00
173,723.00

x Rp.
25,920 = Rp.
x Rp.
18,500 = Rp.
Jumlah (1)
= Rp.

53,136.00
111,000.00
164,136.00

x
x
x
x

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

3,780.00
8,125.00
975.00
220.00
13,100.00
177,236.00

x Rp.
33,460 = Rp.
x Rp.
18,500 = Rp.
Jumlah (1)
= Rp.

40,152.00
111,000.00
151,152.00

x
x
x
x

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

3,780.00
8,125.00
975.00
220.00
13,100.00
164,252.00

x Rp.
28,140 = Rp.
x Rp.
18,500 = Rp.
Jumlah (1)
= Rp.

33,768.00
111,000.00
144,768.00

x
x
x
x

3,780.00
8,125.00
975.00
220.00
13,100.00
157,868.00

Rp.
45,000
Rp.
65,000
Rp.
75,000
Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

Rp.
45,000
Rp.
65,000
Rp.
75,000
Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

Rp.
45,000
Rp.
65,000
Rp.
75,000
Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

Rp.
45,000
Rp.
65,000
Rp.
75,000
Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

Rp.
45,000
Rp.
65,000
Rp.
75,000
Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

=
=
=
=
=
=

=
=
=
=
=
=

=
=
=
=
=
=

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

PPA 6.27 1 M' Pasang nok paten 1,08 m


6.27.1 Bahan
Nok Paten 6 mm
Paku seng
6.27.2 Tenaga
Pekerja
Tukang Kayu
Kepala Tukang
Mandor

PPA 6.28 1 M' Pasang nok stel rata 0,92 m


6.28.1 Bahan
Nok stel rata 5 mm
Paku seng
6.28.2 Tenaga
Pekerja
Tukang Kayu
Kepala Tukang
Mandor

1.20 Lbr
6.00 Bh

0.084
0.125
0.013
0.004

Oh
Oh
Oh
Oh

1.10 Lbr
6.00 Bh

0.100
0.150
0.013
0.004

Oh
Oh
Oh
Oh

x Rp.
39,050 = Rp.
x Rp.
18,500 = Rp.
Jumlah (1)
= Rp.

46,860.00
111,000.00
157,860.00

x
x
x
x

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

3,780.00
8,125.00
975.00
220.00
13,100.00
170,960.00

x Rp.
32,800 = Rp.
x Rp.
18,500 = Rp.
Jumlah (1)
= Rp.

36,080.00
111,000.00
147,080.00

x
x
x
x

Rp.
45,000
Rp.
65,000
Rp.
75,000
Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

Rp.
45,000
Rp.
65,000
Rp.
75,000
Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

4,500.00
9,750.00
975.00
220.00
15,445.00
162,525.00

x Rp.
27,500
x Rp.
18,500
Jumlah (1)
x Rp.
45,000
x Rp.
65,000
x Rp.
75,000
x Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

30,250.00
111,000.00
141,250.00
3,780.00
8,125.00
975.00
220.00
13,100.00
154,350.00

PPA 6.29 1 M' Pasang nok stel rata 1,05 m


6.29.1 Bahan
Nok stel rata 4 mm
Paku seng
6.29.2 Tenaga
Pekerja
Tukang Kayu
Kepala Tukang
Mandor

0.084
0.125
0.013
0.004

PPA 6.30 1 M Pasang atap genteng beton


6.30.1 Bahan
Atap genteng beton
Paku biasa 2" - 5"

11.00 Bh
0.03 Kg

x Rp.
5,430 = Rp.
x Rp.
10,120 = Rp.
Jumlah (1)
= Rp.

59,730.00
303.60
60,033.60

0.200
0.100
0.010
0.010

Oh
Oh
Oh
Oh

x
x
x
x

Rp.
45,000
Rp.
65,000
Rp.
75,000
Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

9,000.00
6,500.00
750.00
550.00
16,800.00
76,833.60

6.900
0.350
0.030
0.500

Lbr
Lbr
Kg
Bh

x
x
x
x

Rp.
10,290
Rp.
102,410
Rp.
10,930
Rp.
25,000
Jumlah (1)

=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.

71,001.00
35,843.50
327.90
12,500.00
119,672.40

0.200
0.300
0.003
0.010

Oh
Oh
Oh
Oh

x
x
x
x

Rp.
45,000
Rp.
65,000
Rp.
75,000
Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

9,000.00
19,500.00
225.00
550.00
29,275.00
148,947.40

x Rp.
96,250 = Rp.
x Rp.
10,120 = Rp.
Jumlah (1)
= Rp.

98,175.00
2,024.00
100,199.00

x
x
x
x

9,000.00
6,500.00
750.00
550.00
16,800.00
116,999.00

6.30.2 Tenaga
Pekerja
Tukang Kayu
Kepala Tukang
Mandor

PPA 6.31 1 M Pasang atap genteng aspal


6.31.1 Bahan
Nok genteng Aspal
Plywood 4" x 8" x 6 mm
Paku biasa " - 1"
Plastic aerator
6.31.2 Tenaga
Pekerja
Tukang Kayu
Kepala Tukang
Mandor

1.10 Lbr
6.00 Bh
Oh
Oh
Oh
Oh

PPA 6.32 1 M Pasang atap genteng metal / Multi Roof


6.32.1 Bahan
Atap genteng Metal
1.02 Lbr
Paku biasa 2" - 5"
0.200 Kg
6.32.2 Tenaga
Pekerja
Tukang Kayu
Kepala Tukang
Mandor

0.200
0.100
0.010
0.010

Oh
Oh
Oh
Oh

Rp.
45,000
Rp.
65,000
Rp.
75,000
Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

PPA 6.33 1 M Pasang atap sirap


6.33.1 Bahan
Atap Sirap
Paku biasa " - 1"
6.33.2 Tenaga
Pekerja
Tukang Kayu
Kepala Tukang
Mandor
PPA 6.34 1 M' Pasang nok genteng beton
6.34.1 Bahan
Nok atap Genteng beton
Paku biasa 2" x 5"
Semen PC
Pasir pasang
Semen warna
6.34.2 Tenaga
Pekerja
Tukang Kayu
Kepala Tukang
Mandor

PPA 6.35 1 M' Pasang nok genteng aspal


6.35.1 Bahan
Nok genteng Aspal
Paku biasa " - 1"
Kayu Papan
6.35.2 Tenaga
Pekerja
Tukang Kayu
Kepala Tukang
Mandor

PPA 6.36 1 M' Pasang nok genteng metal


6.36.1 Bahan
Nok genteng Decra bond
Paku biasa " - 1"
6.36.2 Tenaga
Pekerja
Tukang Kayu
Kepala Tukang
Mandor

PPA 6.37 1 M' Pasang nok sirap


6.37.1 Bahan
Seng plat 3" x 6" BJLS 35
Paku biasa " - 1"
Paku biasa 2" - 5"
Kayu papan tbl. 3 cm
6.37.2 Tenaga
Pekerja
Tukang Kayu
Kepala Tukang
Mandor

PPA 6.38 1 M2 Pasang atap seng gelombang


6.38.1 Bahan
Seng Gelombang 3"x 6" BJLS 30
Paku seng
6.38.2 Tenaga
Pekerja
Tukang Kayu
Kepala Tukang
Mandor

60.00 Bh
0.200 Kg

x Rp.
940 = Rp.
x Rp.
10,930 = Rp.
Jumlah (1)
= Rp.

56,400.00
2,186.00
58,586.00

0.166
0.250
0.025
0.008

Oh
Oh
Oh
Oh

x
x
x
x

Rp.
45,000
Rp.
65,000
Rp.
75,000
Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

7,470.00
16,250.00
1,875.00
440.00
26,035.00
84,621.00

3.50
0.050
10.800
0.032
1.000

Bh
Kg
Kg
M
Kg

x
x
x
x
x

Rp.
12,220
Rp.
10,120
Rp.
1,200
Rp.
94,500
Rp.
1,800
Jumlah (1)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

42,770.00
506.00
12,960.00
3,024.00
1,800.00
61,060.00

0.400
0.200
0.020
0.020

Oh
Oh
Oh
Oh

x
x
x
x

Rp.
45,000
Rp.
65,000
Rp.
75,000
Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

18,000.00
13,000.00
1,500.00
1,100.00
33,600.00
94,660.00

x Rp.
10,290
x Rp.
10,930
x Rp.
8,429,580
Jumlah (1)

=
=
=
=

Rp.
Rp.
Rp.
Rp.

20,580.00
546.50
29,503.53
50,630.03

x
x
x
x

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

5,625.00
16,250.00
1,875.00
330.00
24,080.00
74,710.03

1.10 Bh
0.050 Kg

x Rp.
37,400 = Rp.
x Rp.
10,930 = Rp.
Jumlah (1)
= Rp.

41,140.00
546.50
41,686.50

0.250
0.150
0.015
0.013

Oh
Oh
Oh
Oh

x
x
x
x

Rp.
45,000
Rp.
65,000
Rp.
75,000
Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

11,250.00
9,750.00
1,125.00
715.00
22,840.00
64,526.50

0.400
0.060
0.050
0.004

Lbr
Kg
Kg
M

x
x
x
x

Rp.
105,000
Rp.
10,930
Rp.
10,120
Rp.
8,429,580
Jumlah (1)

=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.

42,000.00
655.80
506.00
33,718.32
76,880.12

0.125
0.250
0.025
0.006

Oh
Oh
Oh
Oh

x
x
x
x

Rp.
45,000
Rp.
65,000
Rp.
75,000
Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

5,625.00
16,250.00
1,875.00
330.00
24,080.00
100,960.12

0.700 Lbr
0.040 Kg

x Rp.
54,220 = Rp.
x Rp.
18,500 = Rp.
Jumlah (1)
= Rp.

37,954.00
740.00
38,694.00

0.120
0.060
0.006
0.006

x
x
x
x

5,400.00
3,900.00
450.00
330.00
10,080.00
48,774.00

2.00 Bh
0.050 Kg
0.0035 M

0.125
0.250
0.025
0.006

Oh
Oh
Oh
Oh

Oh
Oh
Oh
Oh

Rp.
45,000
Rp.
65,000
Rp.
75,000
Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

Rp.
45,000
Rp.
65,000
Rp.
75,000
Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

PPA 6.39 1 M' Pasang atap nok seng


6.39.1 Bahan
Seng plat 3" x 6" BJLS 35
Paku Seng
6.39.2 Tenaga
Pekerja
Tukang Kayu
Kepala Tukang
Mandor

PPA 6.40 1 M2 Pasang atap aluminium


6.40.1 Bahan
Atap Alluminium gelombang 0,55
Paku hak panjang 15 cm
6.40.2 Tenaga
Pekerja
Tukang Kayu
Kepala Tukang
Mandor

PPA 6.41 1 M2 Pasang nok aluminium


6.41.1 Bahan
Nok Standar 40 cm 18 SWG 22
Paku hak panjang 15 cm
6.41.2 Tenaga
Pekerja
Tukang Kayu
Kepala Tukang
Mandor

0.300 Lbr
0.020 Kg

x Rp.
105,000 = Rp.
x Rp.
18,500 = Rp.
Jumlah (1)
= Rp.

31,500.00
370.00
31,870.00

0.150
0.070
0.008
0.006

x
x
x
x

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

6,750.00
4,550.00
600.00
330.00
12,230.00
44,100.00

1.050 M
0.020 Kg

x Rp.
89,250 = Rp.
x Rp.
27,750 = Rp.
Jumlah (1)
= Rp.

93,712.50
555.00
94,267.50

0.150
0.750
0.008
0.006

x
x
x
x

Oh
Oh
Oh
Oh

Oh
Oh
Oh
Oh

6,750.00
48,750.00
600.00
330.00
56,430.00
150,697.50

1.200 M
0.040 Kg

x Rp.
43,540 = Rp.
x Rp.
27,750 = Rp.
Jumlah (1)
= Rp.

52,248.00
1,110.00
53,358.00

0.100
1.000
0.010
0.010

x
x
x
x

Oh
Oh
Oh
Oh

0.150
0.050
0.005
0.008

Oh
Oh
Oh
Oh

BERSAMBUNG : ABK PEKERJAAN LANGIT - LANGIT

Rp.
45,000
Rp.
65,000
Rp.
75,000
Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

PPA 6.42 1 M2 Pasang aluminium foil / sisalation


6.42.1 Bahan
Sisalation / Alluminium foil
1.050 M
6.42.2 Tenaga
Pekerja
Tukang Kayu
Kepala Tukang
Mandor

Rp.
45,000
Rp.
65,000
Rp.
75,000
Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

Rp.
45,000
Rp.
65,000
Rp.
75,000
Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

4,500.00
65,000.00
750.00
550.00
70,800.00
124,158.00

x Rp.
70,180 = Rp.
Jumlah (1)
= Rp.

73,689.00
73,689.00

x
x
x
x

6,750.00
3,250.00
375.00
440.00
10,815.00
84,504.00

Rp.
45,000
Rp.
65,000
Rp.
75,000
Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

ANALISA BIAYA KONSTRUKSI ( ABK )


BANGUNAN GEDUNG DAN PERUMAHAN
NO

JENIS PEKERJAAN

ANA
LISA

VOLU
ME

HARGA
BAHAN
( Rp )

HARGA
UPAH
( Rp )

JUMLAH
HARGA
( Rp )

A. PEKERJAAN PERSIAPAN
1

Pagar Sementara dari kayu tinggi 2 m

PA 6. 1

1 M'

266,107.00

33,600.00

299,707.00

Pagar Sementara dari Seng Gelombang


tinggi 2 m

PA 6. 2

1 M'

116,304.70

33,600.00

149,904.70

Pengukuran dan Pemasangan Bouwplank

PA 6. 4

1 M'

59,955.50

12,025.00

71,980.50

Membersihkan Lapangan dan Perataan

PA 6. 8

1 M

0.00

7,250.00

7,250.00

Pembuatan Jalan Sementara

PA 6. 12

1 M

33,604.20

47,750.00

81,354.20

Bongkaran Beton Bertulang

PA 6. 13

1 M

0.00

318,330.00

318,330.00

Bongkaran Dinding Tembok Bata

PA 6. 14

1 M

0.00

301,830.00

301,830.00

Pas. Pagar Kawat Jaring Galvanis t = 1 m'

PA 6. 15

1 M'

80,203.20

5,030.00

85,233.20

B. PEKERJAAN TANAH
1

Galian Tanah Biasa sedalam 1 m'

PT 6. 1

1 M

0.00

20,200.00

20,200.00

Galian Tanah Biasa sedalam 2 m'

PT 6. 2

1 M

0.00

20,200.00

20,200.00

Galian Tanah Biasa sedalam 3 m'

PT 6. 3

1 M

0.00

20,200.00

20,200.00

Galian Tanah Keras sedalam 1 m'

PT 6. 4

1 M

0.00

31,535.00

31,535.00

Galian Tanah Cadas sedalam 1 m'

PT 6. 5

1 M

0.00

63,125.00

63,125.00

Galian Tanah Lumpur sedalam 1 m'

PT 6. 6

1 M

0.00

41,600.00

41,600.00

Stripping setinggi 1 m'

PT 6. 7

1 M

0.00

2,525.00

2,525.00

Pembuangan Tanah sejauh 150 m'

PT 6. 8

1 M

0.00

2,525.00

2,525.00

Urugan Kembali

PT 6. 9

1 M

0.00

9,685.00

9,685.00

10 Pemadatan Tanah

PT 6. 10

1 M

0.00

25,250.00

25,250.00

11 Urugan Pasir

PT 6. 11

1 M

78,240.00

25,250.00

103,490.00

12 Pembuatan jalan sementara tbl.25 cm

PT 6. 16

1 M

1,000.00

25,250.00

26,250.00

C. PEKERJAAN PONDASI
1

Pas. Pondasi Bt.Kali 1 Pc : 1 Ps

PP 6. 1

1 M

644,910.00

115,125.00

760,035.00

Pas. Pondasi Bt.Kali 1 Pc : 2 Ps

PP 6. 2

1 M

505,588.50

115,125.00

620,713.50

Pas. Pondasi Bt.Kali 1 Pc : 2 Ps

PP 6. 3

1 M

644,910.00

115,125.00

760,035.00

Pas. Pondasi Bt.Kali 1 Pc : 3 Ps

PP 6. 4

1 M

433,069.50

115,125.00

548,194.50

Pas. Pondasi Bt.Kali 1 Pc : 4 Ps

PP 6. 5

1 M

389,577.00

115,125.00

504,702.00

Pas. Pondasi Bt.Kali 1 Pc : 5 Ps

PP 6. 6

1 M

359,445.00

115,125.00

474,570.00

Pas. Pondasi Bt.Kali 1 Pc : 6 Ps

PP 6. 7

1 M

338,251.50

115,125.00

453,376.50

Pas. Pondasi Bato Kosong

PP 6. 14

1 M

192,690.00

65,520.00

258,210.00

Pas. Pondasi Siklop 40% Bt.Kali

PP 6. 15

1 M

1,299,772.10

204,875.00

1,504,647.10

PP 6. 16

1 M

458,566.50

133,250.00

591,816.50

PP 6. 17

1 M

783,616.30

96,325.00

879,941.30

PP 6. 18

1 M

615,079.95

74,450.00

689,529.95

10 Pas. Pondasi Sumuran 100 cm


Pembuatan tiang pancang 40 x 40 cm Beton
bertulang
Pembuatan tiang pancang 30 x 30 cm Beton
12
bertulang
11

D. PEKERJAAN DINDING
1

Pas. Bata Merah tbl.1 Bata, 1 Pc : 1 Ps

PD 6. 1

1 M

173,411.50

45,400.00

218,811.50

Pas. Bata Merah tbl.1 Bata, 1 Pc : 2 Ps

PD 6. 2

1 M

150,760.00

45,400.00

196,160.00

Pas. Bata Merah tbl.1 Bata, 1 Pc : 3 Ps

PD 6. 3

1 M

139,139.50

45,400.00

184,539.50

Pas. Bata Merah tbl.1 Bata, 1 Pc : 4 Ps

PD 6. 4

1 M

131,648.50

43,750.00

175,398.50

Pas. Bata Merah tbl. Bata, 1 Pc : 1 Ps

PD 6. 8

1 M

81,506.00

22,475.00

103,981.00

Pas. Bata Merah tbl. Bata, 1 Pc : 2 Ps

PD 6. 9

1 M

71,831.00

22,475.00

94,306.00

Pas. Bata Merah tbl. Bata, 1 Pc : 3 Ps

PD 6. 10

1 M

94,306.00

22,475.00

116,781.00

Pas. Bata Merah tbl. Bata, 1 Pc : 4 Ps

PD 6. 11

1 M

63,363.50

22,475.00

85,838.50

Pas. Dinding Conblock (HB.20)

PD 6. 21

1 M

116,845.67

29,927.50

146,773.17

10 Pas. Dinding Conblock (HB.15)

PD 6. 22

1 M

51,178.34

26,507.50

77,685.84

11 Pas. Dinding Conblock (HB.10)

PD 6. 23

1 M

61,243.23

24,840.00

86,083.23

12 Pas. Dinding Lantai

PD 6. 24

1 M

137,048.50

9,125.00

146,173.50

13 Pas. Dinding Lantai

PD 6. 25

1 M

269,227.50

21,575.00

290,802.50

14 Pas. Bata berongga uk.5x10x20 cm

PD 6. 26

1 M

639,045.00

26,100.00

665,145.00

15 Pas. Dinding Anyaman Bambu, rangka kayu

PD 6. 27

1 M

109,631.94

8,235.00

117,866.94

E. PEKERJAAN PELESTERAN
1

Pas. Plesteran Tbl.15 mm, 1 Pc : 1 Ps

PPL 6. 1

1 M

16,732.50

20,425.00

37,157.50

Pas. Plesteran Tbl.15 mm, 1 Pc : 2 Ps

PPL 6. 2

1 M

11,830.50

20,425.00

32,255.50

Pas. Plesteran Tbl.15 mm, 1 Pc : 3 Ps

PPL 6. 3

1 M

9,571.50

20,425.00

29,996.50

Pas. Plesteran Tbl.15 mm, 1 Pc : 4 Ps

PPL 6. 4

1 M

8,130.00

20,425.00

28,555.00

Pas. Plesteran Tbl.20 mm, 1 Pc : 2 Ps

PPL 6. 13

1 M

19,309.50

26,437.50

45,747.00

Pas. Plesteran Tbl.20 mm, 1 Pc : 3 Ps

PPL 6. 14

1 M

15,417.00

26,437.50

41,854.50

Pas. Plesteran Tbl.20 mm, 1 Pc : 4 Ps

PPL 6. 15

1 M

13,062.00

26,437.50

39,499.50

Pas. Plesteran Tbl.25 mm, 1 Pc : 2 Ps

PPL 6. 19

1 M

19,828.50

26,437.50

46,266.00

Pas. Plesteran Tbl.25 mm, 1 Pc : 3 Ps

PPL 6. 20

1 M

17,407.50

26,465.00

43,872.50

10 Pas. Plesteran Tbl.25 mm, 1 Pc : 4 Ps

PPL 6. 21

1 M

14,967.00

28,715.00

43,682.00

11 Pas. Plesteran Tbl.30 mm, 1 Pc : 2 Ps

PPL 6. 23

1 M

20,665.50

33,350.00

54,015.50

12 Pas. Plesteran Tbl.30 mm, 1 Pc : 3 Ps

PPL 6. 24

1 M

20,665.50

33,350.00

54,015.50

13 Pas. Plesteran Tbl.30 mm, 1 Pc : 4 Ps

PPL 6. 25

1 M

17,625.00

33,350.00

50,975.00

14 Plesteran Beton T=15 mm, 1 Pc : 2 Ps

PPL 6. 29

1 M

12,861.00

26,915.00

39,776.00

15 Plesteran Beton T=15 mm, 1 Pc : 3 Ps

PPL 6. 30

1 M

10,468.50

26,915.00

37,383.50

16 Plesteran Skoning 1 Pc : 2 Ps

PPL 6. 31

1 M

789.00

7,995.00

8,784.00

17 Plesteran Ciprat tbl.10 mm, 1 Pc : 2 Ps

PPL 6. 34

1 M

6,696.00

19,325.00

26,021.00

18 Plesteran Siar adukan, 1 Pc : 2 Ps

PPL 6. 35

1 M

6,696.00

12,265.00

18,961.00

F. PEKERJAAN KAYU
1

Pas. Kosen Pintu dan Jendela, kayu Jati

PK 6. 1

1 M

23,925,000.00 1,736,500.00 25,661,500.00

Pas. Kosen Pintu dan Jendela, kayu Meranti


Batu

PK 6. 2

1 M

10,182,480.00 1,606,500.00 11,788,980.00

Pas. Kosen Pintu dan Jendela, kayu Meranti

PK 6. 3

1 M

6,157,800.00 1,606,500.00

Pas. Kosen Pintu dan Jendela, kayu Damar


Laut

PK 6. 4

1 M

9,966,000.00 1,606,500.00 11,572,500.00

Pas.Pintu klamp, kayu Meranti Batu

PK 6. 5

1 M

310,562.48

92,865.00

403,427.48

Pas.Pintu klamp, kayu Jati

PK 6. 6

1 M

789,378.68

92,865.00

882,243.68

Pas.Pintu Panel, kayu Jati

PK 6. 7

1 M

788,872.68

92,865.00

881,737.68

Pas.Pintu Panel, kayu Meranti Batu

PK 6. 8

1 M

344,507.20

229,000.00

573,507.20

PK 6. 9

1 M

766,959.55

183,200.00

950,159.55

PK 6. 10

1 M

301,443.80

183,200.00

484,643.80

PK 6. 11

1 M

182,296.45

183,200.00

365,496.45

12 Pas.Pintu dan Jendela Jalusi, kayu Jati

PK 6. 12

1 M

1,402,440.32

279,000.00

1,681,440.32

13 Pas.Pintu dan Jendela Jalusi, kayu D.Laut

PK 6. 13

1 M

539,493.12

290,000.00

829,493.12

14 Pas.Pintu Plywood, Rangka kayu Jati

PK 6. 14

1 M

504,095.25

173,650.00

677,745.25

15 Pas.Pintu Plywood, Rangka kayu M.Batu

PK 6. 15

1 M

243,406.43

173,650.00

417,056.43

16 Pas.Pintu Jalusi mati, kusen kayu Jati

PK 6. 16

1 M

1,316,427.30

168,875.00

1,485,302.30

17 Pas.Pintu Jalusi mati, kusen kayu D.Laut

PK 6. 17

1 M

518,400.30

168,875.00

687,275.30

18 Pas.Pintu Plywood, Rangka kayu Meranti

PK 6. 18

1 M

74,270.00

173,650.00

247,920.00

18 Pas.Pintu Teakwood, Rangka kayu Jati

PK 6. 19

1 M

538,776.35

173,650.00

712,426.35

19 Pas.Pintu Teakwood, Rangka kayu M.Batu

PK 6. 20

1 M

278,087.53

173,650.00

451,737.53

PK 6. 21

1 M

605,246.35

219,450.00

824,696.35

PK 6. 22

1 M

344,557.53

219,450.00

564,007.53

PK 6. 23

1 M

636,976.35

219,450.00

856,426.35

PK 6. 24

1 M

309,132.53

219,450.00

528,582.53

24 Pas.Konstruksi Kuda-kuda, kayu D.Laut

PK 6. 29

1 M

9,333,544.00 1,061,000.00 10,394,544.00

25 Pas.Konstruksi Kuda-kuda, kayu Meranti

PK 6. 30

1 M

5,842,694.00 1,061,000.00

PK 6. 31

1 M

63,217.50

12,025.00

75,242.50

PK 6. 32

1 M

101,299.50

12,025.00

113,324.50

PK 6. 33

1 M

306,139.50

12,025.00

318,164.50

1 M

117,909.50

12,025.00

129,934.50

1 M

117,909.50

12,025.00

129,934.50

Pas.Pintu dan Jendela kaca panel, Rangka


kayu Jati
Pas.Pintu dan Jendela kaca panel, kayu
10
Meranti Batu
Pas.Pintu dan Jendela kaca panel, kayu
11
Meranti
9

Pas.Pintu Plywood + Formica, Rangka kayu


Jati
Pas.Pintu Plywood + Formica, Rangka kayu
21
Meranti Batu
Pas.Pintu Teakwood + Formica, Rangka kayu
22
Jati
Pas.Pintu Teakwood + Formica, Rangka kayu
23
Meranti Batu
20

Pas.Kaso + reng genteng kodok, kayu


Meranti
Pas.Kaso + reng genteng kodok, kayu
27
Damar Laut
26

28 Pas.Kaso + reng genteng monier, kayu Jati

Pas.Kaso + reng genteng monier, kayu


PK 6. 34
Damar Laut
Pas.Kaso + reng Genteng beton, kayu Damar
30
PK 6. 35
Laut
29

7,764,300.00

6,903,694.00

31 Pas.Kaso + reng Atap Sirap, kayu D.Laut

PK 6. 36

1 M

1,372,511.00

14,430.00

1,386,941.00

32 Pas.Kaso + reng Atap Sirap, kayu Meranti

PK 6. 37

1 M

848,883.50

14,430.00

863,313.50

33 Pas.Rangka Langit2 1 x 1 m, kayu Jati

PK 6. 38

1 M

262,093.00

29,000.00

291,093.00

34 Pas.Rangka Langit2 1 x 1 m, kayu D.Laut

PK 6. 38 A 1 M

100,753.00

29,000.00

129,753.00

35 Pas.Rangka Langit2 1 x 1 m, kayu Meranti

PK 6. 38 B 1 M

62,671.00

29,000.00

91,671.00

36 Pas.Rangka Langit2 30 x 30 cm, kayu Jati

3
PK 6. 44

Pas.Rangka Langit2 30 x 30 cm, kayu Damar


PK 6. 45
Laut
Pas.Rangka Langit2 30 x 30 cm, kayu
38
PK 6. 46
Meranti
37

1 M

589,436.00

37,312.50

626,748.50

1 M

226,421.00

37,312.50

263,733.50

1 M

140,736.50

37,312.50

178,049.00

39 Pas.Lisplank 3 x 20 cm, kayu Meranti

PK 6. 47

1 M'

38,047.48

19,650.00

57,697.48

40 Pas.Lisplank 3 x 20 cm, kayu Meranti Batu

PK 6. 48

1 M'

62,557.80

19,275.00

81,832.80

41 Pas.Lisplank 3 x 30 cm, kayu Jati

PK 6. 49

1 M'

241,590.93

21,175.00

262,765.93

42 Pas.Lisplank 3 x 30 cm, kayu Meranti Batu

PK 6. 50

1 M'

95,285.98

21,175.00

116,460.98

PK 6. 51

1 M'

125,539.66

29,000.00

154,539.66

PK 6. 52

1 M'

74,724.85

14,500.00

89,224.85

45 Pas.Lisplank 2 x ( 2 x 20) cm, kayu Meranti

PK 6. 53

1 M'

45,448.64

14,500.00

59,948.64

46 Pas.Rangka Dinding Pemisah, kayu D.Laut

PK 6. 54

1 M

223,329.26

43,500.00

266,829.26

47 Pas.Rangka Dinding Pemisah, kayu Meranti

PK 6. 55

1 M

137,616.54

43,500.00

181,116.54

PK 6. 56

1 M

259,290.50

43,500.00

302,790.50

PK 6. 57

1 M

245,760.50

53,050.00

298,810.50

50 Pas.Dinding Lambesring, kayu Jati

PK 6. 58

1 M

155,930.50

159,150.00

315,080.50

51 Pas.Plywood 4 mm utk Dinding

PK 6. 59

1 M

26,354.50

6,634.00

32,988.50

52 Pas.List Plafond, kayu profil

PK 6. 60

1 M'

11,970.00

2,515.00

14,485.00

Pas.Lisplank 2 x ( 3 x 20) cm, kayu Meranti


Batu
Pas.Lisplank 2 x ( 2 x 20) cm, kayu Meranti
44
Batu
43

Pas.Dinding Pemisah Teakwood, kayu


Damar Laut
Pas.Dinding Pemisah Plywood, kayu Damar
49
Laut
48

G. PEKERJAAN BETON
1

Pas. Beton Tumbuk, 1 Pc : 3 Ps : 5 Kr

PB 6. 1

1 M

453,405.00

96,775.00

550,180.00

Pas. Beton Tumbuk, 1 Pc : 3 Ps : 6 Kr

PB 6. 2

1 M

434,270.00

96,775.00

531,045.00

Pas. Beton Tumbuk, 1 Pc : 4 Ps : 6 Kr

PB 6. 3

1 M

404,505.00

96,775.00

501,280.00

Pas. Beton Tumbuk, 1 Pc : 3 Ps : 5 Kr, tebal


5 cm

PB 6. 4

1 M

21,670.00

53,530.00

75,200.00

Pas. Beton Tumbuk, 1 Pc : 2 Ps : 3 Kr

PB 6. 5

1 M

455,850.00

96,775.00

552,625.00

Pas. Beton Tumbuk, 1 Pc : 2 Ps : 4 Kr

PB 6. 6

1 M

540,201.00

96,775.00

636,976.00

Pas. Beton Tumbuk, 1 Pc : 2 Ps : 2 Kr

PB 6. 7

1 M

602,643.00

96,775.00

699,418.00

Pas. Beton Tumbuk, 1 Pc : 1 Ps : 3 Kr

PB 6. 8

1 M

566,220.60

96,775.00

662,995.60

Pas. Beton Tumbuk, 1 Pc : 1 Ps : 2 Kr

PB 6. 9

1 M

648,334.20

96,775.00

745,109.20

10 Pas. Beton Bertulang, 1 Pc : 1 Ps : 2 Kr

PB 6. 10

1 M

742,698.60

96,775.00

839,473.60

11 Membuat Tiang Pancang Prestressed Beton

PB 6. 11

1 M

713,544.00

96,775.00

810,319.00

12 Pas. Beton Bertulang, 1 Pc : 2 Ps : 3 Kr

PB 6. 13

1 M

594,505.80

170,375.00

764,880.80

13 Pas. Beton Bertulang, 1 Pc : 2 Ps : 4 Kr

PB 6. 14

1 M

553,547.40

170,375.00

723,922.40

14 Pas. Beton Bertulang, 1 Pc : 1 Ps : 3 Kr

PB 6. 15

1 M

633,278.40

170,375.00

803,653.40

15 Pas. Beton Bertulang, 1 Pc : 1 Ps : 2 Kr

PB 6. 16

1 M

676,958.40

170,375.00

847,333.40

16 Pas. Beton Bertulang, 1 Pc : 1 Ps : 1 Kr

PB 6. 17

1 M

878,493.60

170,375.00

1,048,868.60

17 Pembesian dengan besi polos

PB 6. 25

1 Kg

13,183.80

1,460.00

14,643.80

18 Kabel Prestressed polos / strends

PB 6. 26

1 Kg

13,125.70

1,090.00

14,215.70

19 Pas. Bekisting untuk Pondasi

PB 6. 28

1 M

129,404.00

32,625.00

162,029.00

20 Pas. Bekisting untuk Sloof

PB 6. 29

1 M

145,128.50

32,625.00

177,753.50

21 Pas. Bekisting untuk Kolom

PB 6. 30

1 M

274,447.00

37,755.00

312,202.00

22 Pas. Bekisting untuk Balok

PB 6. 31

1 M

283,881.70

38,655.00

322,536.70

23 Pas. Bekisting untuk Lantai

PB 6. 32

1 M

357,447.00

38,655.00

396,102.00

24 Pas. Bekisting untuk Dinding

PB 6. 33

1 M

299,472.50

38,655.00

338,127.50

25 Pas. Bekisting untuk Tangga

PB 6. 34

1 M

242,712.00

38,655.00

281,367.00

26 Pas. Beton dengan Mutu K 225

PB 6. 35

1 M

651,942.00

359,000.00

1,010,942.00

27 Pas. Beton dengan Mutu K 275

PB 6. 36

1 M

672,237.60

359,000.00

1,031,237.60

28 Pas. Bekisting Jembatan Cor

PB 6. 37

1 M

99,472.36

10,760.00

110,232.36

PB 6. 38

1 M

3,115,783.40

361,550.00

3,477,333.40

PB 6. 39

1 M

3,970,345.40

467,575.00

4,437,920.40

PB 6. 40

1 M

7,098,450.40

758,750.00

7,857,200.40

PB 6. 41

1 M

5,356,024.40

609,515.00

5,965,539.40

PB 6. 42

1 M

4,996,911.40

575,675.00

5,572,586.40

PB 6. 43

1 M

4,705,115.40

555,215.00

5,260,330.40

PB 6. 44

1 M

4,933,038.90

556,735.00

5,489,773.90

PB 6. 46

1 M

65,110.30

11,960.00

77,070.30

29
30
31
32
33
34
35

Membuat Pondasi beton bertulang


150 kg besi + bekisting )
Membuat Sloof beton bertulang
( 200 kg besi + bekisting )
Membuat Kolom beton bertulang
300 kg besi + bekisting )
Membuat Balok beton bertulang
200 kg besi + bekisting )
Membuat Balok beton bertulang
150 kg besi + bekisting )
Membuat Dinding beton bertulang
150 kg besi + bekisting )
Membuat Tangga beton bertulang
150 kg besi+bekisting )

36 Pas. Ringbalk Btn Bertulang, (10 x 15) cm

(
(
(
(
(

G. PEKERJAAN PENUTUP ATAP


1

Pas. Atap Genteng Plantong kecil

PPA 6 1

1 M

38,000.00

12,665.00

50,665.00

Pas. Atap Genteng kodok / Glazzur

PPA 6 2

1 M

49,250.00

12,665.00

61,915.00

Pas. Atap Genteng Plantong Super / besar

PPA 6 3

1 M

43,440.00

11,540.00

54,980.00

Pas. Bubung Genteng Plantong kecil

PPA 6 4

1 M'

55,124.00

32,610.00

87,734.00

Pas. Bubung Atap Genteng kodok

PPA 6 5

1 M'

56,074.00

32,610.00

88,684.00

Pas. Bubung Genteng Plantong besar

PPA 6 6

1 M'

58,944.00

32,610.00

91,554.00

Pas. Atap Roof light Fibreglass 180x90 cm

PPA 6 7

1 M

25,248.50

11,565.00

36,813.50

PPA 6 8

1 M

43,305.00

12,215.00

55,520.00

PPA 6 9

1 M

43,720.00

12,215.00

55,935.00

PPA 6 10

1 M

47,874.00

12,215.00

60,089.00

PPA 6 11

1 M

47,865.00

11,760.00

59,625.00

PPA 6 12

1 M

44,745.00

11,760.00

56,505.00

PPA 6 13

1 M

42,985.00

11,760.00

54,745.00

PPA 6 14

1 M

33,408.00

11,565.00

44,973.00

PPA 6 18

1 M

52,049.40

11,565.00

63,614.40

PPA 6 19

1 M

50,968.50

11,565.00

62,533.50

PPA 6 20

1 M

52,053.00

11,565.00

63,618.00

PPA 6 21

1 M

52,049.40

11,565.00

63,614.40

PPA 6 22

1 M'

153,744.00

13,100.00

166,844.00

8
9
10
11
12
13
14
15
16
17
18

Pas. Atap Asbes Gelombang


(2,70 x 0,92 x 5 mm)
Pas. Atap Asbes Gelombang
(2,40 x 0,92 x 5 mm)
Pas. Atap Asbes Gelombang
(2,10 x 0,92 x 5 mm)
Pas. Atap Asbes Gelombang
(1,80 x 0,92 x 5 mm)
Pas. Atap Asbes Gelombang
(2,40 x 1,05 x 4 mm)
Pas. Atap Asbes Gelombang
(2,10 x 1,05 x 4 mm)
Pas. Atap Asbes Gelombang
(1,80 x 1,05 x 4 mm)
Pas. Atap Asbes Gelombang
(2,70 x 1,08 x 6 mm)
Pas. Atap Asbes Gelombang
(2,40 x 1,08 x 6 mm)
Pas. Atap Asbes Gelombang
(2,10 x 1,08 x 6 mm)
Pas. Atap Asbes Gelombang
(1,80 x 1,08 x 6 mm)

19 Pas. Bubung/Nok stel gelombang 0,92 m

20 Pas. Bubung/Nok stel gelombang 1,05 m

PPA 6 23

1 M'

160,623.00

13,100.00

173,723.00

21 Pas. Bubung/Nok stel gelombang 1,08 m

PPA 6 24

1 M'

164,136.00

13,100.00

177,236.00

22 Pas. Nok Paten 0,92 m

PPA 6 25

1 M'

151,152.00

13,100.00

164,252.00

23 Pas. Nok Paten 1,05 m

PPA 6 26

1 M'

144,768.00

13,100.00

157,868.00

24 Pas. Nok Paten 1,08 m

PPA 6 27

1 M'

157,860.00

13,100.00

170,960.00

25 Pas. Nok stel rata 0,92 m

PPA 6 28

1 M'

147,080.00

15,445.00

162,525.00

26 Pas. Nok stel rata 1,05 m

PPA 6 29

1 M'

141,250.00

13,100.00

154,350.00

27 Pas. Atap Genteng Beton

PPA 6 30

1 M

60,033.60

16,800.00

76,833.60

28 Pas. Atap Genteng Aspal

PPA 6 31

1 M

119,672.40

29,275.00

148,947.40

29 Pas. Atap Genteng Metal/Multi roof

PPA 6 32

1 M

100,199.00

16,800.00

116,999.00

30 Pas. Atap Sirap

PPA 6 33

1 M

58,586.00

26,035.00

84,621.00

31 Pas. Nok genteng Beton

PPA 6 34

1 M'

61,060.00

33,600.00

94,660.00

32 Pas. Nok genteng Aspal

PPA 6 35

1 M'

50,630.03

24,080.00

74,710.03

33 Pas. Nok genteng Metal

PPA 6 36

1 M'

41,686.50

22,840.00

64,526.50

34 Pas. Nok genteng Sirap

PPA 6 37

1 M'

76,880.12

24,080.00

100,960.12

35 Pas. Atap Seng Gelombang

PPA 6 38

1 M

38,694.00

10,080.00

48,774.00

36 Pas. Nok Atap seng gelombang

PPA 6 39

1 M'

31,870.00

12,230.00

44,100.00

37 Pas. Atap Alluminium

PPA 6 40

1 M

94,267.50

56,430.00

150,697.50

38 Pas. Nok Alluminium

PPA 6 41

1 M'

53,358.00

70,800.00

124,158.00

39 Pas. Alluminium foil / sisalation

PPA 6 42

1 M

73,689.00

10,815.00

84,504.00

Pas. Langit2 Asbes (1 x 1) m tbl.6 mm

PLL 6 1

1 M

17,351.80

6,507.50

23,859.30

Pas. Langit2 Asbes (1 x 1) m tbl.5 mm

PLL 6 2

1 M

14,477.50

6,507.50

20,985.00

Pas. Langit2 Asbes (1 x 1) m tbl.4 mm

PLL 6 3

1 M

11,604.30

6,507.50

18,111.80

Pas. Langit2 Asbes (1 x 1) m tbl.3,5 mm

PLL 6 4

1 M

9,184.30

6,507.50

15,691.80

Pas. Langit2 Akustik (30 x 30) cm

PLL 6 5

1 M

94,041.50

11,565.00

105,606.50

Pas. Langit2 Akustik (30 x 60) cm

PLL 6 6

1 M

94,042.50

10,115.00

104,157.50

Pas. Langit2 Akustik (60 x 120) cm

PLL 6 7

1 M

94,046.00

10,115.00

104,161.00

Pas. Langit2 Plywood (30 x 60) cm t.4 mm

PLL 6 8

1 M

23,555.10

10,592.50

34,147.60

Pas. Langit2 Plywood (30 x 60) cm t.6 mm

PLL 6 9

1 M

37,195.50

10,592.50

47,788.00

10 Pas. Langit2 Plywood (60 x 120) cm t.4 mm

PLL 6 10

1 M

24,522.90

10,592.50

35,115.40

11 Pas. Langit2 Plywood (60 x 120) cm t.6 mm

PLL 6 11

1 M

38,731.65

10,592.50

49,324.15

12 Pas. Langit2 Teakwood (30 x 60) cm t.4 mm

PLL 6 12

1 M

34,977.90

10,592.50

45,570.40

13 Pas. Langit2 Teakwood (60 x 120) cm 4 mm

PLL 6 13

1 M

36,421.65

10,592.50

47,014.15

14 Pas. Langit2 Kayu Jati

PLL 6 14

1 M

526,886.92

53,050.00

579,936.92

15 Pas. Langit2 Papan Rider

PLL 6 16

1 M

205,721.80

53,050.00

258,771.80

16 Pas. Langit2 Soft board

PLL 6 17

1 M

19,896.80

34,415.00

54,311.80

H. PEKERJAAN LANGIT LANGIT

Pas. Langit2 Akustik 60 x 120 cm + Rangka


17
Alluminium

PLL 6 18

1 M

126,341.00

43,412.50

169,753.50

18 Pas. List Langit2 Kayu Profil 3"

PLL 6 19

1 M'

18,919.30

6,040.00

24,959.30

PLL 6 20

1 M

73,728.80

31,795.00

105,523.80

PLL 6 21

1 M

143,843.10

41,892.50

185,735.60

PLL 6 22

1 M

212,176.30

41,415.00

253,591.30

PLL 6 23

1 M

232,701.30

48,877.50

281,578.80

PLL 6 24

1 M

36,331.90

8,400.00

44,731.90

Pas. Langit2 Asbes (1 x 1) m, tbl.3,2 mm,


Rangka Kayu Meranti
Pas. Langit2 Plywood 4 mm + Rangka Kayu
20
Meranti
Pas. Langit2 Akustik (30 x 60) cm + Rangka
21
Kayu Meranti
Pas. Langit2 Akustik (30 x 30) cm + Rangka
22
Kayu Meranti
19

23 Pas. Langit2 Gypsum Board, tebal 9 mm


I.

PEKERJAAN SANITASI

Kloset Duduk / monoblok

PS 6

1 Bh

1,862,102.00

266,050.00

2,128,152.00

Kloset Jongkok Porselen

PS 6

1 Bh

212,965.00

164,300.00

377,265.00

Kloset Jongkok Teraso

PS 6

1 Bh

489,795.00

159,250.00

649,045.00

Urinoir

PS 6

1 Bh

591,057.00

123,000.00

714,057.00

Washtafel

PS 6

1 Bh

544,065.00

165,000.00

709,065.00

Bak Mandi Teraso volume 0,3 m

PS 6

1 Bh

173,145.00

154,925.00

328,070.00

Bak Mandi Fibreglass volume 0,3 m

PS 6

1 Bh

194,700.00

126,200.00

320,900.00

Bak Mandi Batu bata volume 0,3 m

PS 6

1 Bh

690,250.00

369,000.00

1,059,250.00

Bak Kift Porselen

PS 6

1 Bh

3,300,000.00

180,625.00

3,480,625.00

10 Bak Beton volume 1 m

PS 6

10

1 Bh

3,407,536.44

567,000.00

3,974,536.44

11 Bak Fibreglass volume 1 m

PS 6

11

1 Bh

184,800.00

544,500.00

729,300.00

12 Pas. Pipa Beton 30 - 100 cm

PS 6

15

1 M'

114,638.30

31,920.00

146,558.30

13 Bak Kontrol bt.bata (30 x30) cm, t= 35 cm

PS 6

16

1 Bh

191,546.90

210,967.50

402,514.40

14 Bak Kontrol bt.bata (45 x45) cm, t= 50 cm

PS 6

17

1 Bh

311,535.20

102,075.00

413,610.20

15 Bak Kontrol bt.bata (60 x60) cm, t= 65 cm

PS 6

18

1 Bh

472,725.07

159,840.00

632,565.07

16 Pas. Pipa Galvanis "

PS 6

19

1 M'

127,100.00

10,440.00

137,540.00

17 Pas. Pipa Galvanis "

PS 6

20

1 M'

178,250.00

10,440.00

188,690.00

18 Pas. Pipa Galvanis 1"

PS 6

21

1 M'

260,400.00

10,440.00

270,840.00

19 Pas. Pipa Galvanis 1"

PS 6

22

1 M'

333,250.00

18,207.00

351,457.00

20 Pas. Pipa Galvanis 2"

PS 6

23

1 M'

399,900.00

18,207.00

418,107.00

21 Pas. Pipa Galvanis 3"

PS 6

24

1 M'

443,300.00

18,207.00

461,507.00

22 Pas. Pipa PVC type AW "

PS 6

25

1 M'

46,887.50

6,069.00

52,956.50

23 Pas. Pipa PVC type AW "

PS 6

26

1 M'

62,829.25

6,069.00

68,898.25

24 Pas. Pipa PVC type AW 1"

PS 6

27

1 M'

104,625.00

6,069.00

110,694.00

25 Pas. Pipa PVC type AW 1"

PS 6

28

1 M'

151,125.00

6,069.00

157,194.00

26 Pas. Pipa PVC type AW 2"

PS 6

29

1 M'

178,250.00

9,103.50

187,353.50

27 Pas. Pipa PVC type AW 2"

PS 6

30

1 M'

204,600.00

6,069.00

210,669.00

28 Pas. Pipa PVC type AW 3"

PS 6

31

1 M'

237,150.00

13,658.00

250,808.00

29 Pas. Pipa PVC type AW 4"

PS 6

32

1 M'

398,350.00

13,658.00

412,008.00

30 Bak Cuci Piring Steinlees 2 lobang

PS 6

33

1 Bh

439,270.00

23,182.50

462,452.50

31 Bak Cuci Piring Teraso 2 lobang

PS 6

34

1 Bh

291,225.00

38,637.50

329,862.50

32 Pas. Kran air " atau "

PS 6

35

1 Bh

26,963.75

7,975.00

34,938.75

33 Pas. Floor Drain # 4"

PS 6

36

1 Bh

15,000.00

7,975.00

22,975.00

J. PEKERJAAN BESI DAN ALLUMINIUM


1

Pas. Rangka Atap baja

PBA 6 1

1 Kg

17,140.20

3,556.50

20,696.70

Pas. Pintu besi

PBA 6 1

2 M

458,850.00

78,135.00

536,985.00

Pas. Jendela besi

PBA 6 1

3 M

316,250.00

123,663.75

439,913.75

Pas. Pintu Gulung besi

PBA 6 1

5 M

500,250.00

141,330.00

641,580.00

Pas. Pintu Lipat besi

PBA 6 1

6 M

517,500.00

123,661.00

641,161.00

Pas. Sunscreen Alluminium

PBA 6 1

7 M

488,750.00

61,820.00

550,570.00

Pas. Rolling Door

PBA 6 1

8 M

477,250.00

152,911.00

630,161.00

Pas. Pintu Alluminium

PBA 6 1

9 M

546,250.00

123,661.00

669,911.00

Pas. Venetions blainds

PBA 6 1

10 M

146,625.00

40,092.50

186,717.50

10 Pas. Verticals blainds

PBA 6 1

11 M

155,250.00

40,092.50

195,342.50

11 Pas. Teralis besi

PBA 6 1

12 M

145,130.00

129,063.00

274,193.00

12 Pas. Kawat Harmonika # 2"

PBA 6 1

13 M

48,043.30

11,777.50

59,820.80

13 Pas. Kawat Nyamuk

PBA 6 1

14 M

22,919.30

11,777.50

34,696.80

14 Pas. Kawat Kassa

PBA 6 1

15 M

44,248.30

11,777.50

56,025.80

15 Pas. Kawat Burung

PBA 6 1

16 M

44,242.80

11,777.50

56,020.30

16 Pas. Jendela Naco dan Teralis

PBA 6 1

17 M

207,358.60

23,555.00

230,913.60

17 Pas. Talang Datar, Seng BJLS 35

PBA 6 1

18 M'

112,898.85

34,693.75

147,592.60

18 Pas. Talang Miring, Seng BJLS 35

PBA 6 1

19 M'

163,329.45

34,693.75

198,023.20

19 Pas. Talang 1/2 10 cm, Seng BJLS 35

PBA 6 1

20 M'

136,401.50

24,943.75

161,345.25

K. PEKERJAAN KUNCI DAN KACA


1

Pas. Kunci Tanam Antik

PKK 6 1

1 Bh

203,500.00

46,365.00

249,865.00

Pas. Kunci Tanam Biasa

PKK 6 2

1 Bh

81,840.00

33,975.00

115,815.00

Pas. Kunci Tanam Kmr.mandi

PKK 6 3

1 Bh

49,720.00

33,237.50

82,957.50

Pas. Kunci Silinder

PKK 6 4

1 Bh

167,750.00

33,113.75

200,863.75

Pas. Engsel Pintu

PKK 6 5

1 Bh

13,750.00

11,591.25

25,341.25

Pas. Engsel Jendela Kupu-kupu

PKK 6 6

1 Bh

10,230.00

7,727.50

17,957.50

Pas. Engsel Angin

PKK 6 7

1 Bh

22,770.00

15,950.00

38,720.00

Pas. Spring Knip

PKK 6 8

1 Bh

8,250.00

11,591.25

19,841.25

Pas. Kait Angin

PKK 6 9

1 Bh

17,380.00

11,591.25

28,971.25

10 Pas. Kunci Selot

PKK 6 10

1 Bh

99,770.00

38,637.50

138,407.50

11 Pas. Pegangan/Handle Pintu

PKK 6 11

1 Bh

40,370.00

15,455.00

55,825.00

12 Pas. Door Stop

PKK 6 12

1 Bh

102,740.00

38,637.50

141,377.50

13 Pas. Rel pintu dorong

PKK 6 13

1 Bh

34,650.00

7,727.50

42,377.50

14 Pas. Kunci Lemari

PKK 6 14

1 Bh

145,750.00

46,365.00

192,115.00

15 Pas. Kaca Polos tbl.3 mm

PKK 6 15

11,220.00

19,318.75

30,538.75

16 Pas. Kaca Polos tbl.5 mm

PKK 6 16

87,120.00

11,591.25

98,711.25

17 Pas. Kaca Polos tbl.8 mm

PKK 6 17

145,200.00

11,591.25

156,791.25

18 Pas. Kaca Buram tbl.5 mm

PKK 6 18

232,320.00

12,749.00

245,069.00

19 Pas. Kaca Cermin tbl.5 mm

PKK 6 19

122,787.50

19,318.75

142,106.25

20 Pas. Kaca Cermin tbl.8 mm

PKK 6 20

161,700.00

11,591.25

173,291.25

21 Pas. Kaca Wireglass tbl.5 mm

PKK 6 21

193,600.00

11,591.25

205,191.25

22 Pas. Kaca Patri tbl.5 mm

PKK 6 23

151,250.00

11,591.25

162,841.25

J. PEK. PENUTUP ATAP DAN LANTAI


1

Pas. Lantai Ubin Pc Abu-abu 40 x 40 cm

PPL 6 1

48,798.15

20,637.50

69,435.65

Pas. Lantai Ubin Pc Abu-abu 30 x 30 cm

PPL 6 2

49,285.65

21,477.50

70,763.15

Pas. Lantai Ubin Pc Abu-abu 20 x 20 cm

PPL 6 3

49,633.50

22,317.50

71,951.00

Pas. Lantai Ubin Warna 40 x 40 cm

PPL 6 4

83,364.00

20,637.50

104,001.50

Pas. Lantai Ubin Warna 30 x 30 cm

PPL 6 5

60,020.00

20,637.50

80,657.50

Pas. Lantai Ubin Warna 20 x 20 cm

PPL 6 6

58,525.50

22,317.50

80,843.00

Pas. Lantai Ubin Teraso 40 x 40 cm

PPL 6 7

135,019.25

20,637.50

155,656.75

Pas. Lantai Ubin Teraso 30 x 30 cm

PPL 6 8

37,192.25

22,152.50

59,344.75

Pas. Lantai Ubin Granito 40 x 40 cm

PPL 6 9

310,332.25

20,637.50

330,969.75

10 Pas. Lantai Ubin Granito 30 x 30 cm

PPL 6 10

300,893.65

21,477.50

322,371.15

11 Pas. Lantai Ubin Terralux Marmar 60/60 cm

PPL 6 13

571,689.75

20,637.50

592,327.25

12 Pas. Lantai Ubin Terralux Marmar 40/40 cm

PPL 6 14

290,646.75

48,320.00

338,966.75

13 Pas. Lantai Ubin Terralux Marmar 30/30 cm

PPL 6 15

311,339.25

58,075.00

369,414.25

14 Pas. Plint Ubin Pc Abu-abu 10 x 20 cm

PPL 6 16

M'

7,980.00

5,040.00

13,020.00

15 Pas. Plint Ubin Pc Abu-abu 10 x 30 cm

PPL 6 17

M'

7,980.00

5,040.00

13,020.00

16 Pas. Plint Ubin Pc Abu-abu 10 x 40 cm

PPL 6 18

M'

12,066.50

5,040.00

17,106.50

17 Pas. Plint Ubin Warna 10 x 20 cm

PPL 6 19

M'

8,000.00

5,040.00

13,040.00

18 Pas. Plint Ubin Warna 10 x 30 cm

PPL 6 20

M'

12,388.60

5,040.00

17,428.60

19 Pas. Plint Ubin Warna 10 x 40 cm

PPL 6 21

M'

15,367.50

6,720.00

22,087.50

20 Pas. Plint Ubin Teraso 10 x 30 cm

PPL 6 22

M'

30,074.50

6,720.00

36,794.50

21 Pas. Plint Ubin Teraso 10 x 40 cm

PPL 6 23

M'

31,108.50

6,720.00

37,828.50

22 Pas. Plint Ubin Granito 10 x 40 cm

PPL 6 24

M'

153,265.90

5,040.00

158,305.90

23 Pas. Plint Ubin Granito 10 x 30 cm

PPL 6 25

M'

87,132.70

47,272.50

134,405.20

24 Pas. Plint Terralux Marmar 10 x 60 cm

PPL 6 28

M'

68,517.40

47,272.50

115,789.90

25 Pas. Plint Terralux Marmar 10 x 40 cm

PPL 6 29

M'

68,517.40

47,272.50

115,789.90

26 Pas. Plint Terralux Marmar 10 x 30 cm

PPL 6 30

M'

51,967.90

47,272.50

99,240.40

27 Pas. Lantai Keramik Artistik 10 x 20 cm

PPL 6 34

103,650.00

54,925.00

158,575.00

28 Pas. Lantai Keramik Artistik 10 x 10 cm

PPL 6 35

63,575.00

54,925.00

118,500.00

29 Pas. Lantai Keramik Artistik 5 x 20 cm

PPL 6 36

103,650.00

54,925.00

158,575.00

30 Pas. Plint Keramik Artistik 10 x 20 cm

PPL 6 37

M'

10,767.40

10,822.50

21,589.90

31 Pas. Plint Keramik Artistik 10 x 10 cm

PPL 6 38

M'

10,814.40

10,822.50

21,636.90

32 Pas. Plint Keramik Artistik 5 x 20 cm

PPL 6 39

M'

5,635.40

10,822.50

16,457.90

33 Pas. Plint Keramik 10 x 20 cm

PPL 6 39A 1

M'

7,010.40

10,822.50

17,832.90

34 Pas. Plint Keramik 10 x 30 cm

PPL 6 39B 1

M'

11,430.20

10,822.50

22,252.70

35 Pas. Plint Keramik 10 x 40 cm

PPL 6 39C 1

M'

16,360.40

10,822.50

27,182.90

36 Pas. Plint Vynil tanpa adukan

PPL 6 41

M'

29,300.00

9,620.00

38,920.00

37 Pas. Lantai Keramik 10 x 20 cm

PPL 6 42

76,150.00

54,925.00

131,075.00

38 Pas. Lantai Keramik 15 x 15 cm

PPL 6 43

74,390.00

54,925.00

129,315.00

39 Pas. Lantai Keramik 20 x 20 cm

PPL 6 44

76,150.00

54,925.00

131,075.00

40 Pas. Lantai Keramik 20 x 25 cm

PPL 6 45

89,350.00

54,925.00

144,275.00

41 Pas. Lantai Keramik 25 x 25 cm

PPL 6 46

65,150.00

54,925.00

120,075.00

42 Pas. Lantai Keramik 30 x 30 cm

PPL 6 47

76,194.00

54,925.00

131,119.00

43 Pas. Lantai Keramik 30 x 30 cm anti slip

PPL 6 48

92,650.00

54,925.00

147,575.00

44 Pas. Lantai Keramik 40 x 40 cm

PPL 6 49

76,150.00

54,925.00

131,075.00

45 Pas. Lantai Mosaik 30 x 30 cm Ex lokal

PPL 6 50

177,165.50

54,925.00

232,090.50

46 Pas. Lantai Marmar

PPL 6 51

275,899.30

54,925.00

330,824.30

47 Pas. Lantai Karpet 100% Wool

PPL 6 52

95,025.00

20,442.50

115,467.50

48 Pas. Lantai Karpet 80% Wool, 20% Nylon

PPL 6 53

97,125.00

20,442.50

117,567.50

49 Pas. Lantai Karpet Vynil

PPL 6 55

100,275.00

20,442.50

120,717.50

50 Pas. Lantai Parquet Jati

PPL 6 56

375,150.00

56,412.50

431,562.50

51 Pas. Dinding Porselen 11 x 11 cm, putih

PPL 6 58

107,686.00

65,800.00

173,486.00

52 Pas. Dinding Porselen 11 x 11 cm, warna

PPL 6 59

125,946.00

65,800.00

191,746.00

53 Pas. Dinding Porselen 15 x 15 cm, putih

PPL 6 60

110,436.00

61,275.00

171,711.00

54 Pas. Dinding Porselen 15 x 15 cm, warna

PPL 6 61

120,336.00

61,275.00

181,611.00

55 Pas. Dinding Keramik artistik 10 x 20 cm

PPL 6 64

181,386.00

61,275.00

242,661.00

56 Pas. Dinding Keramik artistik 5 x 20 cm

PPL 6 65

98,886.00

61,275.00

160,161.00

57 Pas. Dinding Keramik 10 x 20 cm

PPL 6 66

71,386.00

61,275.00

132,661.00

58 Pas. Dinding Keramik 15 x 15 cm

PPL 6 67

70,836.00

61,275.00

132,111.00

59 Pas. Dinding Keramik 20 x 20 cm

PPL 6 68

71,386.00

38,525.00

109,911.00

60 Pas. Dinding Keramik 20 x 25 cm

PPL 6 69

71,386.00

37,712.50

109,098.50

61 Pas. Dinding Marmar

PPL 6 70

265,028.50

81,450.00

346,478.50

62 Pas. Dinding Bata pelapis 7 x 3 x 20 cm

PPL 6 71

136,376.50

67,150.00

203,526.50

63 Pas. Dinding Batu Poros

PPL 6 73

1,337,707.50

54,925.00

1,392,632.50

64 Pas. Dinding Batu tempel hitam

PPL 6 74

1,219,307.50

54,925.00

1,274,232.50

65 Pas. Lantai Vynil karet 30 x 30 cm Kls.I

PPL 6 75

101,574.00

18,037.50

119,611.50

66 Pas. Lantai Vynil karet 30 x 30 cm Kls.II

PPL 6 76

94,050.00

18,037.50

112,087.50

67 Pas. Lantai Vynil asbes 30 x 30 cm

PPL 6 77

85,272.00

18,037.50

103,309.50

68 Pas. Lantai Vynil motif kembang 30 x 30 cm

PPL 6 78

97,812.00

18,037.50

115,849.50

69 Pas. Wall corverting lbr 50 cm

PPL 6 79

77,625.00

46,542.50

124,167.50

70 Pas. Plint kayu jati 2 x 10 cm

PPL 6 82

M'

53,516.51

14,430.00

67,946.51

71 Pas. Plint kayu Meranti Batu 2 x 10 cm

PPL 6 82A 1

M'

21,595.43

14,430.00

36,025.43

PC 6

1,023.00

6,887.50

7,910.50

PC 6

687.50

6,887.50

7,575.00

PC 6

687.50

6,887.50

7,575.00

K. PEKERJAAN PENGECATAN
1
2
3

Mengikis/mengerok permukaan cat lama


Mencuci bidang permukaan tembok yang
pernah di cat
Mengerok karat cat lama permukaan baja
dengan cara manual

Mengikis/mengerok permukaan cat lama

PC 6

687.50

6,887.50

7,575.00

Menyabun permukaan tembok lama

PC 6

1,370.60

7,537.50

8,908.10

Mendempul/menggosok permukaan kayu

PC 6

185,000.00

8,725.00

193,725.00

Mengecat permukaan bidang kayu lama

PC 6

13

7,513.00

18,937.50

26,450.50

Pelaburan bidang kayu dgn vernis

PC 6

14

7,352.40

5,605.00

12,957.40

15

7,946.40

4,442.50

12,388.90

17

7,609.80

14,571.60

22,181.40

Pengecatan tembok baru ( 1lapis plamir, 1


PC 6
lps cat dasar, 2 lps cat penutup )
Pengecatan tembok lama ( 1 lps cat dasar, 2
10
PC 6
lps cat penutup )
9

11 Melabur tembok dgn kapur sirih

PC 6

18

37,677.00

2,300.00

39,977.00

12 Melabur tembok lama dgn kapur sirih

PC 6

19

40,796.00

14,187.50

54,983.50

13 Pas. Wall paper

PC 6

20

4,471.50

15,950.00

20,421.50

14 Pengecatan permukaan baja dgn cat menie

PC 6

21

10,761.30

27,975.00

38,736.30

PC 6

23

13,662.00

2,760.00

16,422.00

PC 6

24

12,617.00

108,000.00

120,617.00

PC 6

25

4,125.00

89,500.00

93,625.00

Pengecatan permukaan baja dgn cat menie


besi dgn perancah
Pengecatan permukaan baja lapis seng
16
(galbani), cara manual 1 lapis tbl.200
Pengecatan permukaan baja lapis seng
17
(galbani), cara manual 3 lapis tbl.200
15

Medan,
DIKETAHUI OLEH :
Kepala Dinas Penataan Ruang dan

Maret 2008

DIBUAT OLEH : TIM TEKNIS


1. Ir. Jeremias Sinaga, MAP

( . )

2. Ir. Herimas

( . )

3. H. Sugiarto Bharata, ST

( . )

4. H. Ali Muhar, ST

( . )

Ir. H. Syafruddin Siregar, MSi

5. Sakula Karo karo, ST

( . )

Pembina Utama Muda

6. Ebenser Saragih, SE

( . )

7. Sahat Hasudungan, ST

( . )

8. Ir. Tanogara Siahaan

( . )

9. Ali Fauzan, ST

( . )

Permukiman Prov. Sumatera Utara

NIP. 400025884

10. Ir. Naimul Ahmad R. ST

( . )

11. Chandra, ST

( . )

ANALISA BIAYA KONSTRUKSI


PEKERJAAN KUNCI DAN KACA

PKK 6.1
6.1.1

6.1.2

PKK 6.2
6.2.1

6.1.2

PKK 6.3
6.3.1

6.3.2

PKK 6.4
6.4.1

6.4.2

PKK 6.5
6.5.1

6.5.2

PKK 6.6
6.6.1

6.6.2

1 buah pasang kunci tanam antik


Bahan
Kunci tanam antik

1.000 Bh

x Rp.
203,500 = Rp.
Jumlah (1)
= Rp.

203,500.00
203,500.00

Tenaga
Pekerja
Tukang Kayu
Kepala Tukang
Mandor

0.060
0.600
0.060
0.003

x
x
x
x

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

2,700.00
39,000.00
4,500.00
165.00
46,365.00
249,865.00

1 buah pasang kunci tanam biasa


Bahan
Kunci tanam biasa

1.000 Bh

x Rp.
81,840 = Rp.
Jumlah (1)
= Rp.

81,840.00
81,840.00

Tenaga
Pekerja
Tukang Kayu
Kepala Tukang
Mandor

0.010
0.500
0.010
0.005

x
x
x
x

Oh
Oh
Oh
Oh

Oh
Oh
Oh
Oh

1 buah pasang kunci tanam kamar mandi


Bahan
Kunci tanam kamar mandi
1.000 Bh
Tenaga
Pekerja
Tukang Kayu
Kepala Tukang
Mandor

1 buah pasang kunci silinder


Bahan
Kunci silinder
Tenaga
Pekerja
Tukang Kayu
Kepala Tukang
Mandor

1 buah pasang engsel pintu


Bahan
engsel pintu
Tenaga
Pekerja
Tukang Kayu
Kepala Tukang
Mandor

0.005
0.500
0.005
0.0025

Oh
Oh
Oh
Oh

1.000 Bh

0.005
0.500
0.005
0.00025

Oh
Oh
Oh
Oh

1.000 Bh

0.015
0.150
0.015
0.00075

Oh
Oh
Oh
Oh

1 buah pasang engsel jendela kupu-kupu


Bahan
Engsel jendela
1.000 Bh
Tenaga
Pekerja
Tukang Kayu
Kepala Tukang
Mandor

0.010
0.100
0.010
0.0005

Oh
Oh
Oh
Oh

Rp.
45,000
Rp.
65,000
Rp.
75,000
Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

Rp.
45,000
Rp.
65,000
Rp.
75,000
Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

450.00
32,500.00
750.00
275.00
33,975.00
115,815.00

x Rp.
49,720 = Rp.
Jumlah (1)
= Rp.

49,720.00
49,720.00

x
x
x
x

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

225.00
32,500.00
375.00
137.50
33,237.50
82,957.50

x Rp.
167,750 = Rp.
Jumlah (1)
= Rp.

167,750.00
167,750.00

x
x
x
x

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

225.00
32,500.00
375.00
13.75
33,113.75
200,863.75

x Rp.
13,750 = Rp.
Jumlah (1)
= Rp.

13,750.00
13,750.00

x
x
x
x

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

675.00
9,750.00
1,125.00
41.25
11,591.25
25,341.25

x Rp.
10,230 = Rp.
Jumlah (1)
= Rp.

10,230.00
10,230.00

x
x
x
x

450.00
6,500.00
750.00
27.50
7,727.50
17,957.50

Rp.
45,000
Rp.
65,000
Rp.
75,000
Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

Rp.
45,000
Rp.
65,000
Rp.
75,000
Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

Rp.
45,000
Rp.
65,000
Rp.
75,000
Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

Rp.
45,000
Rp.
65,000
Rp.
75,000
Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

=
=
=
=
=
=

=
=
=
=
=
=

=
=
=
=
=
=

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

PKK 6.7
6.7.1

6.7.2

PKK 6.8
6.8.1

6.8.2

PKK 6.9
6.9.1

6.9.2

1 buah pasang engsel angin


Bahan
Engsel angin

1.000 Bh

x Rp.
22,770 = Rp.
Jumlah (1)
= Rp.

22,770.00
22,770.00

Tenaga
Pekerja
Tukang Kayu
Kepala Tukang
Mandor

0.020
0.200
0.020
0.010

x
x
x
x

1 buah pasang spring knip


Bahan
Spring knip

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

900.00
13,000.00
1,500.00
550.00
15,950.00
38,720.00

1.000 Bh

x Rp.
8,250 = Rp.
Jumlah (1)
= Rp.

8,250.00
8,250.00

Tenaga
Pekerja
Tukang Kayu
Kepala Tukang
Mandor

1 buah pasang kait angin


Bahan
Kait angin
Tenaga
Pekerja
Tukang Kayu
Kepala Tukang
Mandor

PKK 6.10 1 buah pasang door closer


6.10.1 Bahan
Door closer
6.10.2 Tenaga
Pekerja
Tukang Kayu
Kepala Tukang
Mandor

PKK 6.11 1 buah pasang kunci selot


6.11.1 Bahan
Kunci selot
6.11.2 Tenaga
Pekerja
Tukang Kayu
Kepala Tukang
Mandor

0.015
0.150
0.015
0.00075

Oh
Oh
Oh
Oh

Oh
Oh
Oh
Oh

1.000 Bh

0.015
0.150
0.015
0.00075

Oh
Oh
Oh
Oh

1.000 Bh

0.050
0.500
0.050
0.0025

Oh
Oh
Oh
Oh

PKK 6.13 1 buah pasang door stop


6.13.1 Bahan
Door stop
6.13.2 Tenaga
Pekerja
Tukang Kayu
Kepala Tukang
Mandor

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

675.00
9,750.00
1,125.00
41.25
11,591.25
19,841.25

x Rp.
17,380 = Rp.
Jumlah (1)
= Rp.

17,380.00
17,380.00

x
x
x
x

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

675.00
9,750.00
1,125.00
41.25
11,591.25
28,971.25

x Rp.
99,770 = Rp.
Jumlah (1)
= Rp.

99,770.00
99,770.00

Rp.
45,000
Rp.
65,000
Rp.
75,000
Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

1.000 Bh

x Rp.
40,370 = Rp.
Jumlah (1)
= Rp.

40,370.00
40,370.00

0.020
0.200
0.020
0.001

x
x
x
x

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

900.00
13,000.00
1,500.00
55.00
15,455.00
55,825.00

x Rp.
102,740 = Rp.
Jumlah (1)
= Rp.

102,740.00
102,740.00

x
x
x
x

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

2,250.00
32,500.00
3,750.00
137.50
38,637.50
141,377.50

x Rp.
34,650 = Rp.
Jumlah (1)
= Rp.

34,650.00
34,650.00

x
x
x
x

450.00
6,500.00
750.00
27.50
7,727.50
42,377.50

0.050
0.500
0.050
0.0025

Oh
Oh
Oh
Oh

1.000 Bh

0.010
0.100
0.010
0.0005

Oh
Oh
Oh
Oh

Rp.
45,000
Rp.
65,000
Rp.
75,000
Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

2,250.00
32,500.00
3,750.00
137.50
38,637.50
138,407.50

Oh
Oh
Oh
Oh

x
x
x
x

Rp.
45,000
Rp.
65,000
Rp.
75,000
Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

PKK 6.12 1 buah pasang pegangan pintu / door holder


6.12.1 Bahan
Pegangan pintu/door holder
1.000 Bh
6.12.2 Tenaga
Pekerja
Tukang Kayu
Kepala Tukang
Mandor

x
x
x
x

Rp.
45,000
Rp.
65,000
Rp.
75,000
Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

Rp.
45,000
Rp.
65,000
Rp.
75,000
Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

Rp.
45,000
Rp.
65,000
Rp.
75,000
Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

Rp.
45,000
Rp.
65,000
Rp.
75,000
Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

=
=
=
=
=
=

=
=
=
=
=
=

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

PKK 6.14 1 buah pasang rel pintu dorong


6.14.1 Bahan
Rel pintu dorong
6.14.2 Tenaga
Pekerja
Tukang Kayu
Kepala Tukang
Mandor
PKK 6.15 1 buah pasang kunci lemari
6.15.1 Bahan
Kunci lemari
6.15.2 Tenaga
Pekerja
Tukang Kayu
Kepala Tukang
Mandor

PKK 6.16 1 M pasang kaca, tebal 3 mm


6.16.1 Bahan
Kaca polos
6.16.2 Tenaga
Pekerja
Tukang Kayu
Kepala Tukang
Mandor

PKK 6.17 1 M pasang kaca, tebal 5 mm


6.17.1 Bahan
Kaca polos
6.17.2 Tenaga
Pekerja
Tukang Kayu
Kepala Tukang
Mandor

PKK 6.18 1 M pasang kaca, tebal 8 mm


6.18.1 Bahan
Kaca polos
6.18.2 Tenaga
Pekerja
Tukang Kayu
Kepala Tukang
Mandor

1.000 Bh

x Rp.
145,750 = Rp.
Jumlah (1)
= Rp.

145,750.00
145,750.00

0.060
0.600
0.060
0.003

x
x
x
x

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

2,700.00
39,000.00
4,500.00
165.00
46,365.00
192,115.00

x Rp.
11,220 = Rp.
Jumlah (1)
= Rp.

11,220.00
11,220.00

Oh
Oh
Oh
Oh

1.000 Bh

Rp.
45,000
Rp.
65,000
Rp.
75,000
Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

0.025
0.250
0.025
0.00125

Oh
Oh
Oh
Oh

x
x
x
x

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

1,125.00
16,250.00
1,875.00
68.75
19,318.75
30,538.75

1.100

x Rp.
79,200 = Rp.
Jumlah (1)
= Rp.

87,120.00
87,120.00

0.015
0.150
0.015
0.00075

Oh
Oh
Oh
Oh

x
x
x
x

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

675.00
9,750.00
1,125.00
41.25
11,591.25
98,711.25

1.100

x Rp.
132,000 = Rp.
Jumlah (1)
= Rp.

145,200.00
145,200.00

0.015
0.150
0.015
0.00075

Oh
Oh
Oh
Oh

x
x
x
x

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

675.00
9,750.00
1,125.00
41.25
11,591.25
156,791.25

1.100

x Rp.
211,200 = Rp.
Jumlah (1)
= Rp.

232,320.00
232,320.00

0.0165
0.165
0.0165
0.0008

Oh
Oh
Oh
Oh

x
x
x
x

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

742.50
10,725.00
1,237.50
44.00
12,749.00
245,069.00

x Rp.
110,000 = Rp.
x Rp.
35,750 = Rp.
Jumlah (1)
= Rp.

121,000.00
1,787.50
122,787.50

PKK 6.19 1 M pasang kaca buram, tebal 5 mm


6.19.1 Bahan
Kaca buram
1.100 M
Sealent
0.050 Kg
6.19.2 Tenaga
Pekerja
Tukang Kayu
Kepala Tukang
Mandor

Rp.
45,000
Rp.
65,000
Rp.
75,000
Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

Rp.
45,000
Rp.
65,000
Rp.
75,000
Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

Rp.
45,000
Rp.
65,000
Rp.
75,000
Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

Rp.
45,000
Rp.
65,000
Rp.
75,000
Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

=
=
=
=
=
=

=
=
=
=
=
=

0.025
0.250
0.025
0.00125

Oh
Oh
Oh
Oh

x
x
x
x

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

1,125.00
16,250.00
1,875.00
68.75
19,318.75
142,106.25

PKK 6.20 1 M pasang kaca cermin, tebal 5 mm


6.20.1 Bahan
Kaca cermin
1.100

x Rp.
147,000 = Rp.
Jumlah (1)
= Rp.

161,700.00
161,700.00

Oh
Oh
Oh
Oh

x
x
x
x

675.00
9,750.00
1,125.00
41.25
11,591.25
173,291.25

6.20.2 Tenaga
Pekerja
Tukang Kayu
Kepala Tukang
Mandor

0.015
0.150
0.015
0.00075

Rp.
45,000
Rp.
65,000
Rp.
75,000
Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

Rp.
45,000
Rp.
65,000
Rp.
75,000
Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

PKK 6.21 1 M pasang kaca cermin, tebal 8 mm


6.21.1 Bahan
Kaca cermin
1.100
6.21.2 Tenaga
Pekerja
Tukang Kayu
Kepala Tukang
Mandor

0.015
0.150
0.015
0.00075

x Rp.
176,000 = Rp.
Jumlah (1)
= Rp.

193,600.00
193,600.00

Oh
Oh
Oh
Oh

x
x
x
x

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

675.00
9,750.00
1,125.00
41.25
11,591.25
205,191.25

x Rp.
137,500 = Rp.
Jumlah (1)
= Rp.

151,250.00
151,250.00

PKK 6.23 1 M pasang kaca "wireglass" , tebal 5 mm


6.23.1 Bahan
Kaca Wireglass
1.100 M
6.23.2 Tenaga
Pekerja
Tukang Kayu
Kepala Tukang
Mandor

Rp.
45,000
Rp.
65,000
Rp.
75,000
Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

0.015
0.150
0.015
0.00075

Oh
Oh
Oh
Oh

x
x
x
x

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

675.00
9,750.00
1,125.00
41.25
11,591.25
162,841.25

PKK 6.24 1 M pasang kaca patri, tebal 5 mm


6.24.1 Bahan
Kaca Patri
1.100

x Rp.
154,000 = Rp.
Jumlah (1)
= Rp.

169,400.00
169,400.00

Oh
Oh
Oh
Oh

x
x
x
x

675.00
9,750.00
1,125.00
41.25
11,591.25
180,991.25

6.24.2 Tenaga
Pekerja
Tukang Kayu
Kepala Tukang
Mandor

0.015
0.150
0.015
0.00075

Rp.
45,000
Rp.
65,000
Rp.
75,000
Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

Rp.
45,000
Rp.
65,000
Rp.
75,000
Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

BERSAMBUNG : .ABK PEKERJAAN PENUTUP LANTAI DAN DINDING

=
=
=
=
=
=

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

ANALISA BIAYA KONSTRUKSI


PEKERJAAN PENUTUP LANTAI DAN DINDING

PPL 6.1
6.1.1

6.1.2

PPL 6.2
6.2.1

6.2.2

PPL 6.3
6.3.1

6.3.2

PPL 6.4
6.4.1

6.4.2

PPL 6.5
6.5.1

6.5.2

1 M Pasang lantai ubin pc abu-abu ukuran 40 x 40 cm


Bahan
Ubin PC 40 x 40 cm
6.630 Bh x Rp.
5,280
Semen portland
9.800 Kg x Rp.
1,200
Pasir pasang
0.0215 M x Rp.
94,500
Jumlah (1)
Tenaga
Pekerja
0.250 Oh x Rp.
45,000
Tukang batu
0.120 Oh x Rp.
65,000
Kepala tukang
0.012 Oh x Rp.
75,000
Mandor
0.0125 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)
1 M Pasang lantai ubin pc abu-abu ukuran 30 x 30 cm
Bahan
Ubin PC 30 x 30 cm
11.870 Bh x Rp.
2,970
Semen portland
10.000 Kg x Rp.
1,200
Pasir pasang
0.0215 M x Rp.
94,500
Jumlah (1)
Tenaga
Pekerja
0.260 Oh x Rp.
45,000
Tukang batu
0.125 Oh x Rp.
65,000
Kepala tukang
0.0125 Oh x Rp.
75,000
Mandor
0.013 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)
1 M Pasang lantai ubin pc abu-abu ukuran 20 x 20 cm
Bahan
Ubin PC 20 x 20 cm
26.500 Bh x Rp.
1,320
Semen portland
10.400 Kg x Rp.
1,200
Pasir pasang
0.0230 M x Rp.
94,500
Jumlah (1)
Tenaga
Pekerja
0.270 Oh x Rp.
45,000
Tukang batu
0.130 Oh x Rp.
65,000
Kepala tukang
0.013 Oh x Rp.
75,000
Mandor
0.0135 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)
1 M Pasang lantai ubin warna ukuran 40 x 40 cm
Bahan
Ubin warna 40 x 40 cm
6.630 Bh x Rp.
10,450
Semen portland
8.160 Kg x Rp.
1,200
Pasir pasang
0.023 M x Rp.
94,500
Semen warna
0.900 Kg x Rp.
2,350
Jumlah (1)
Tenaga
Pekerja
0.250 Oh x Rp.
45,000
Tukang batu
0.120 Oh x Rp.
65,000
Kepala tukang
0.012 Oh x Rp.
75,000
Mandor
0.0125 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)
1 M Pasang lantai ubin warna ukuran 30 x 30 cm
Bahan
Ubin warna 30 x 30 cm
11.870 Bh x Rp.
3,850
Semen portland
8.360 Kg x Rp.
1,200
Pasir pasang
0.023 M x Rp.
94,500
Semen warna
0.900 Kg x Rp.
2,350
Jumlah (1)
Tenaga
Pekerja
0.250 Oh x Rp.
45,000
Tukang batu
0.120 Oh x Rp.
65,000
Kepala tukang
0.012 Oh x Rp.
75,000
Mandor
0.0125 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=

Rp.
Rp.
Rp.
Rp.

35,006.40
11,760.00
2,031.75
48,798.15

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

11,250.00
7,800.00
900.00
687.50
20,637.50
69,435.65

=
=
=
=

Rp.
Rp.
Rp.
Rp.

35,253.90
12,000.00
2,031.75
49,285.65

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

11,700.00
8,125.00
937.50
715.00
21,477.50
70,763.15

=
=
=
=

Rp.
Rp.
Rp.
Rp.

34,980.00
12,480.00
2,173.50
49,633.50

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

12,150.00
8,450.00
975.00
742.50
22,317.50
71,951.00

=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.

69,283.50
9,792.00
2,173.50
2,115.00
83,364.00

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

11,250.00
7,800.00
900.00
687.50
20,637.50
104,001.50

=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.

45,699.50
10,032.00
2,173.50
2,115.00
60,020.00

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

11,250.00
7,800.00
900.00
687.50
20,637.50
80,657.50

PPL 6.6
6.6.1

6.6.2

PPL 6.7
6.7.1

6.7.2

PPL 6.8
6.8.1

6.8.2

PPL 6.9
6.9.1

6.9.2

1 M Pasang lantai ubin warna ukuran 20 x 20 cm


Bahan
Ubin warna 20 x 20 cm
26.500 Bh x Rp.
1,650
Semen portland
8.760 Kg x Rp.
1,200
Pasir pasang
0.023 M x Rp.
94,500
Semen warna
0.900 Kg x Rp.
2,350
Jumlah (1)
Tenaga
Pekerja
0.270 Oh x Rp.
45,000
Tukang batu
0.130 Oh x Rp.
65,000
Kepala tukang
0.013 Oh x Rp.
75,000
Mandor
0.0135 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)
1 M Pasang lantai ubin teraso ukuran 40 x 40 cm
Bahan
Ubin teraso 40 x 40 cm
6.250 Bh x Rp.
19,250
Semen portland
8.800 Kg x Rp.
1,200
Pasir pasang
0.0215 M x Rp.
94,500
Semen warna
0.900 Kg x Rp.
2,350
Jumlah (1)
Tenaga
Pekerja
0.250 Oh x Rp.
45,000
Tukang batu
0.120 Oh x Rp.
65,000
Kepala tukang
0.012 Oh x Rp.
75,000
Mandor
0.0125 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

1 M Pasang lantai ubin teraso ukuran 30 x 30 cm


Bahan
Ubin teraso 30 x 30 cm
1.870 Bh x Rp.
10,450
Semen portland
10.000 Kg x Rp.
1,200
Pasir pasang
0.0215 M x Rp.
94,500
Semen warna
1.540 Kg x Rp.
2,350
Jumlah (1)
Tenaga
Pekerja
0.260 Oh x Rp.
45,000
Tukang batu
0.125 Oh x Rp.
65,000
Kepala tukang
0.0215 Oh x Rp.
75,000
Mandor
0.013 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

1 M Pasang lantai ubin granito ukuran 40 x 40 cm


Bahan
Ubin granito 40 x 40 cm
6.930 Bh x Rp.
42,350
Semen portland
9.800 Kg x Rp.
1,200
Pasir pasang
0.0215 M x Rp.
94,500
Semen warna
1.300 Kg x Rp.
2,350
Jumlah (1)
Tenaga
Pekerja
0.250 Oh x Rp.
45,000
Tukang batu
0.120 Oh x Rp.
65,000
Kepala tukang
0.012 Oh x Rp.
75,000
Mandor
0.0125 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

PPL 6.10
1 M Pasang lantai ubin granito ukuran 30 x 30 cm
6.10.1 Bahan
Ubin granito 30 x 30 cm
11.870 Bh x Rp.
23,870
Semen portland
10.000 Kg x Rp.
1,200
Pasir pasang
0.0215 M x Rp.
94,500
Semen warna
1.500 Kg x Rp.
2,350
Jumlah (1)
6.10.2 Tenaga
Pekerja
0.260 Oh x Rp.
45,000
Tukang batu
0.125 Oh x Rp.
65,000
Kepala tukang
0.0125 Oh x Rp.
75,000
Mandor
0.013 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.

43,725.00
10,512.00
2,173.50
2,115.00
58,525.50

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

12,150.00
8,450.00
975.00
742.50
22,317.50
80,843.00

=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.

120,312.50
10,560.00
2,031.75
2,115.00
135,019.25

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

11,250.00
7,800.00
900.00
687.50
20,637.50
155,656.75

=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.

19,541.50
12,000.00
2,031.75
3,619.00
37,192.25

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

11,700.00
8,125.00
1,612.50
715.00
22,152.50
59,344.75

=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.

293,485.50
11,760.00
2,031.75
3,055.00
310,332.25

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

11,250.00
7,800.00
900.00
687.50
20,637.50
330,969.75

=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.

283,336.90
12,000.00
2,031.75
3,525.00
300,893.65

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

11,700.00
8,125.00
937.50
715.00
21,477.50
322,371.15

PPL 6.13
1 M Pasang lantai ubin teralux marmer ukuran 60 x 60 cm
6.13.1 Bahan
Ubin marmar 60 x 60 cm
5.600 Bh x Rp.
99,550
Semen portland
8.190 Kg x Rp.
1,200
Pasir pasang
0.0215 M x Rp.
94,500
Semen warna
1.000 Kg x Rp.
2,350
Jumlah (1)
6.13.2 Tenaga
Pekerja
0.250 Oh x Rp.
45,000
Tukang batu
0.120 Oh x Rp.
65,000
Kepala tukang
0.012 Oh x Rp.
75,000
Mandor
0.0125 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)
PPL 6.14
1 M Pasang lantai ubin teralux marmer ukuran 40 x 40 cm
6.14.1 Bahan
Ubin marmar 40 x 40 cm
6.250 Bh x Rp.
44,000
Semen portland
8.800 Kg x Rp.
1,200
Pasir pasang
0.0215 M x Rp.
94,500
Semen warna
1.300 Kg x Rp.
2,350
Jumlah (1)
6.14.2 Tenaga
Pekerja
0.672 Oh x Rp.
45,000
Tukang batu
0.224 Oh x Rp.
65,000
Kepala tukang
0.022 Oh x Rp.
75,000
Mandor
0.034 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

PPL 6.15
1 M Pasang lantai ubin teralux marmer ukuran 30 x 30 cm
6.15.1 Bahan
Ubin marmar 30 x 30 cm
11.870 Bh x Rp.
24,750
Semen portland
10.000 Kg x Rp.
1,200
Pasir pasang
0.0215 M x Rp.
94,500
Semen warna
1.500 Kg x Rp.
2,350
Jumlah (1)
6.15.2 Tenaga
Pekerja
0.700 Oh x Rp.
45,000
Tukang batu
0.340 Oh x Rp.
65,000
Kepala tukang
0.034 Oh x Rp.
75,000
Mandor
0.035 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

PPL 6.16
1 M' Pasang plint ubin pc abu-abu ukuran 10 x 20 cm
6.16.1 Bahan
Plint ubin 10 x 20 cm
5.300 Bh x Rp.
935
Semen portland
1.560 Kg x Rp.
1,200
Pasir pasang
0.003 M x Rp.
94,500
Jumlah (1)
6.16.2 Tenaga
Pekerja
0.060 Oh x Rp.
45,000
Tukang batu
0.030 Oh x Rp.
65,000
Kepala tukang
0.003 Oh x Rp.
75,000
Mandor
0.003 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

PPL 6.17
1 M' Pasang plint ubin pc abu-abu ukuran 10 x 30 cm
6.17.1 Bahan
Plint ubin 10 x 30 cm
3.530 Bh x Rp.
1,650
Semen portland
1.560 Kg x Rp.
1,200
Pasir pasang
0.003 M x Rp.
94,500
Jumlah (1)
6.17.2 Tenaga
Pekerja
0.060 Oh x Rp.
45,000
Tukang batu
0.030 Oh x Rp.
65,000
Kepala tukang
0.003 Oh x Rp.
75,000
Mandor
0.003 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.

557,480.00
9,828.00
2,031.75
2,350.00
571,689.75

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

11,250.00
7,800.00
900.00
687.50
20,637.50
592,327.25

=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.

275,000.00
10,560.00
2,031.75
3,055.00
290,646.75

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

30,240.00
14,560.00
1,650.00
1,870.00
48,320.00
338,966.75

=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.

293,782.50
12,000.00
2,031.75
3,525.00
311,339.25

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

31,500.00
22,100.00
2,550.00
1,925.00
58,075.00
369,414.25

=
=
=
=

Rp.
Rp.
Rp.
Rp.

4,955.50
1,872.00
283.50
7,111.00

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

2,700.00
1,950.00
225.00
165.00
5,040.00
12,151.00

=
=
=
=

Rp.
Rp.
Rp.
Rp.

5,824.50
1,872.00
283.50
7,980.00

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

2,700.00
1,950.00
225.00
165.00
5,040.00
13,020.00

PPL 6.18
1 M' Pasang plint ubin pc abu-abu ukuran 10 x 40 cm
6.18.1 Bahan
Plint ubin 10 x 40 cm
2.650 Bh x Rp.
3,740
Semen portland
1.560 Kg x Rp.
1,200
Pasir pasang
0.003 M x Rp.
94,500
Jumlah (1)
6.18.2 Tenaga
Pekerja
0.060 Oh x Rp.
45,000
Tukang batu
0.030 Oh x Rp.
65,000
Kepala tukang
0.003 Oh x Rp.
75,000
Mandor
0.003 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

PPL 6.19
1 M' Pasang plint ubin pc warna ukuran 10 x 20 cm
6.19.1 Bahan
Plint ubin pc warna 10 x 20 cm
5.300 Bh x Rp.
1,100
Semen portland
1.200 Kg x Rp.
1,200
Pasir pasang
0.003 M x Rp.
94,500
Semen warna
0.190 Kg x Rp.
2,350
Jumlah (1)
6.19.2 Tenaga
Pekerja
0.060 Oh x Rp.
45,000
Tukang batu
0.030 Oh x Rp.
65,000
Kepala tukang
0.003 Oh x Rp.
75,000
Mandor
0.003 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)
PPL 6.20
1 M' Pasang plint ubin pc warna ukuran 10 x 30 cm
6.20.1 Bahan
Plint ubin pc warna 10 x 30 cm
3.330 Bh x Rp.
2,970
Semen portland
1.650 Kg x Rp.
1,200
Pasir pasang
0.003 M x Rp.
94,500
Semen warna
0.100 Kg x Rp.
2,350
Jumlah (1)
6.20.2 Tenaga
Pekerja
0.060 Oh x Rp.
45,000
Tukang batu
0.030 Oh x Rp.
65,000
Kepala tukang
0.003 Oh x Rp.
75,000
Mandor
0.003 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)
PPL 6.21
1 M' Pasang plint ubin pc warna ukuran 10 x 40 cm
6.21.1 Bahan
Plint ubin pc warna 10 x 40 cm
2.650 Bh x Rp.
5,060
Semen portland
1.200 Kg x Rp.
1,200
Pasir pasang
0.003 M x Rp.
94,500
Semen warna
0.100 Kg x Rp.
2,350
Jumlah (1)
6.21.2 Tenaga
Pekerja
0.080 Oh x Rp.
45,000
Tukang batu
0.040 Oh x Rp.
65,000
Kepala tukang
0.004 Oh x Rp.
75,000
Mandor
0.004 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

PPL 6.22
1 M' Pasang plint ubin teraso ukuran 10 x 30 cm
6.22.1 Bahan
Plint ubin teraso 10 x 30 cm
3.330 Bh x Rp.
8,250
Semen portland
1.560 Kg x Rp.
1,200
Pasir pasang
0.003 M x Rp.
94,500
Semen warna
0.190 Kg x Rp.
2,350
Jumlah (1)
6.22.2 Tenaga
Pekerja
0.080 Oh x Rp.
45,000
Tukang batu
0.040 Oh x Rp.
65,000
Kepala tukang
0.004 Oh x Rp.
75,000
Mandor
0.004 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=

Rp.
Rp.
Rp.
Rp.

9,911.00
1,872.00
283.50
12,066.50

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

2,700.00
1,950.00
225.00
165.00
5,040.00
17,106.50

=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.

5,830.00
1,440.00
283.50
446.50
8,000.00

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

2,700.00
1,950.00
225.00
165.00
5,040.00
13,040.00

=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.

9,890.10
1,980.00
283.50
235.00
12,388.60

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

2,700.00
1,950.00
225.00
165.00
5,040.00
17,428.60

=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.

13,409.00
1,440.00
283.50
235.00
15,367.50

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

3,600.00
2,600.00
300.00
220.00
6,720.00
22,087.50

=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.

27,472.50
1,872.00
283.50
446.50
30,074.50

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

3,600.00
2,600.00
300.00
220.00
6,720.00
36,794.50

PPL 6.23
1 M' Pasang plint ubin teraso ukuran 10 x 40 cm
6.23.1 Bahan
Plint ubin teraso 10 x 40 cm
2.650 Bh x Rp.
11,000
Semen portland
1.200 Kg x Rp.
1,200
Pasir pasang
0.003 M x Rp.
94,500
Semen warna
0.100 Kg x Rp.
2,350
Jumlah (1)
6.23.2 Tenaga
Pekerja
0.080 Oh x Rp.
45,000
Tukang batu
0.040 Oh x Rp.
65,000
Kepala tukang
0.004 Oh x Rp.
75,000
Mandor
0.004 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)
PPL 6.24
1 M' Pasang plint ubin granito ukuran 10 x 40 cm
6.24.1 Bahan
Plint ubin granito 10 x 40 cm
2.650 Bh x Rp.
57,090
Semen portland
1.200 Kg x Rp.
1,200
Pasir pasang
0.0032 M x Rp.
94,500
Semen warna
0.100 Kg x Rp.
2,350
Jumlah (1)
6.24.2 Tenaga
Pekerja
0.060 Oh x Rp.
45,000
Tukang batu
0.030 Oh x Rp.
65,000
Kepala tukang
0.003 Oh x Rp.
75,000
Mandor
0.003 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)
PPL 6.25
1 M' Pasang plint ubin granito ukuran 10 x 30 cm
6.25.1 Bahan
Plint ubin granito 10 x 40 cm
3.330 Bh x Rp.
25,410
Semen portland
1.650 Kg x Rp.
1,200
Pasir pasang
0.0032 M x Rp.
94,500
Semen warna
0.100 Kg x Rp.
2,350
Jumlah (1)
6.25.2 Tenaga
Pekerja
0.900 Oh x Rp.
45,000
Tukang batu
0.090 Oh x Rp.
65,000
Kepala tukang
0.009 Oh x Rp.
75,000
Mandor
0.0045 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

PPL 6.28
1 M' Pasang plint ubin teralux marmer ukuran 10 x 60 cm
6.28.1 Bahan
Plint ubin marmer 10 x 60 cm
1.700 Bh x Rp.
59,730
Semen portland
1.650 Kg x Rp.
1,200
Pasir pasang
0.0032 M x Rp.
94,500
Semen warna
0.100 Kg x Rp.
2,350
Jumlah (1)
6.28.2 Tenaga
Pekerja
0.900 Oh x Rp.
45,000
Tukang batu
0.090 Oh x Rp.
65,000
Kepala tukang
0.009 Oh x Rp.
75,000
Mandor
0.0045 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

PPL 6.29
1 M' Pasang plint ubin teralux marmer ukuran 10 x 40 cm
6.29.1 Bahan
Plint ubin marmer 10 x 40 cm
2.500 Bh x Rp.
26,400
Semen portland
1.650 Kg x Rp.
1,200
Pasir pasang
0.0032 M x Rp.
94,500
Semen warna
0.100 Kg x Rp.
2,350
Jumlah (1)
6.29.2 Tenaga
Pekerja
0.900 Oh x Rp.
45,000
Tukang batu
0.090 Oh x Rp.
65,000
Kepala tukang
0.009 Oh x Rp.
75,000
Mandor
0.0045 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.

29,150.00
1,440.00
283.50
235.00
31,108.50

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

3,600.00
2,600.00
300.00
220.00
6,720.00
37,828.50

=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.

151,288.50
1,440.00
302.40
235.00
153,265.90

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

2,700.00
1,950.00
225.00
165.00
5,040.00
158,305.90

=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.

84,615.30
1,980.00
302.40
235.00
87,132.70

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

40,500.00
5,850.00
675.00
247.50
47,272.50
134,405.20

=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.

101,541.00
1,980.00
302.40
235.00
104,058.40

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

40,500.00
5,850.00
675.00
247.50
47,272.50
151,330.90

=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.

66,000.00
1,980.00
302.40
235.00
68,517.40

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

40,500.00
5,850.00
675.00
247.50
47,272.50
115,789.90

PPL 6.30
1 M' Pasang plint ubin teralux marmer ukuran 10 x 30 cm
6.30.1 Bahan
Plint ubin marmer 10 x 30 cm
3.330 Bh x Rp.
14,850
Semen portland
1.650 Kg x Rp.
1,200
Pasir pasang
0.0032 M x Rp.
94,500
Semen warna
0.100 Kg x Rp.
2,350
Jumlah (1)
6.30.2 Tenaga
Pekerja
0.900 Oh x Rp.
45,000
Tukang batu
0.090 Oh x Rp.
65,000
Kepala tukang
0.009 Oh x Rp.
75,000
Mandor
0.0045 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)
PPL 6.34
1 M Pasang lantai keramik artistik 10 x 20 cm
6.34.1 Bahan
Keramik artistik 10 x 20 cm
50.000 Bh x
Semen portland
11.380 Kg x
Pasir pasang
0.042 M x
Semen warna
1.500 Kg x
6.34.2 Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

0.620
0.350
0.035
0.030

Oh
Oh
Oh
Oh

x
x
x
x

PPL 6.35
1 M Pasang lantai keramik artistik 10 x 10 cm
6.35.1 Bahan
Keramik artistik 10 x 10 cm
50.000 Bh x
Semen portland
11.380 Kg x
Pasir pasang
0.042 M x
Semen warna
2.000 Kg x
6.35.2 Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

0.620
0.350
0.035
0.030

Oh
Oh
Oh
Oh

x
x
x
x

=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.

49,450.50
1,980.00
302.40
235.00
51,967.90

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

40,500.00
5,850.00
675.00
247.50
47,272.50
99,240.40

Rp.
1,650
Rp.
1,200
Rp.
94,500
Rp.
2,350
Jumlah (1)

=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.

82,500.00
13,656.00
3,969.00
3,525.00
103,650.00

Rp.
45,000
Rp.
65,000
Rp.
75,000
Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

27,900.00
22,750.00
2,625.00
1,650.00
54,925.00
158,575.00

Rp.
825
Rp.
1,200
Rp.
94,500
Rp.
2,350
Jumlah (1)

=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.

41,250.00
13,656.00
3,969.00
4,700.00
63,575.00

Rp.
45,000
Rp.
65,000
Rp.
75,000
Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

27,900.00
22,750.00
2,625.00
1,650.00
54,925.00
118,500.00

=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.

82,500.00
13,656.00
3,969.00
3,525.00
103,650.00

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

27,900.00
22,750.00
2,625.00
1,650.00
54,925.00
158,575.00

=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.

8,250.00
1,980.00
302.40
235.00
10,767.40

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

4,050.00
5,850.00
675.00
247.50
10,822.50
21,589.90

PPL 6.36
1 M Pasang lantai keramik artistik ukuran 5 x 20 cm
6.36.1 Bahan
Keramik artistik 5 x 20 cm
100.000 Bh x Rp.
825
Semen portland
11.380 Kg x Rp.
1,200
Pasir pasang
0.042 M x Rp.
94,500
Semen warna
1.500 Kg x Rp.
2,350
Jumlah (1)
6.36.2 Tenaga
Pekerja
0.620 Oh x Rp.
45,000
Tukang batu
0.350 Oh x Rp.
65,000
Kepala tukang
0.035 Oh x Rp.
75,000
Mandor
0.030 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

PPL 6.37
1 M' Pasang plint keramik artistik ukuran 10 x 20 cm
6.37.1 Bahan
Keramik artistik 10 x 20 cm
5.000 Bh x Rp.
1,650
Semen portland
1.650 Kg x Rp.
1,200
Pasir pasang
0.0032 M x Rp.
94,500
Semen warna
0.100 Kg x Rp.
2,350
Jumlah (1)
6.37.2 Tenaga
Pekerja
0.090 Oh x Rp.
45,000
Tukang batu
0.090 Oh x Rp.
65,000
Kepala tukang
0.009 Oh x Rp.
75,000
Mandor
0.0045 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

PPL 6.38
1 M' Pasang plint keramik artistik ukuran 10 x 10 cm
6.38.1 Bahan
Keramik artistik 10 x 10 cm
10.000 Bh x Rp.
825
Semen portland
1.650 Kg x Rp.
1,200
Pasir pasang
0.0032 M x Rp.
94,500
Semen warna
0.120 Kg x Rp.
2,350
Jumlah (1)
6.38.2 Tenaga
Pekerja
0.090 Oh x Rp.
45,000
Tukang batu
0.090 Oh x Rp.
65,000
Kepala tukang
0.009 Oh x Rp.
75,000
Mandor
0.0045 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.

8,250.00
1,980.00
302.40
282.00
10,814.40

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

4,050.00
5,850.00
675.00
247.50
10,822.50
21,636.90

=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.

4,125.00
1,020.00
302.40
188.00
5,635.40

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

4,050.00
5,850.00
675.00
247.50
10,822.50
16,457.90

Rp.
1,100
Rp.
1,200
Rp.
94,500
Rp.
2,350
Jumlah (1)

=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.

5,500.00
1,020.00
302.40
188.00
7,010.40

Rp.
45,000
Rp.
65,000
Rp.
75,000
Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

4,050.00
5,850.00
675.00
247.50
10,822.50
17,832.90

Rp.
2,970
Rp.
1,200
Rp.
94,500
Rp.
2,350
Jumlah (1)

=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.

9,919.80
1,020.00
302.40
188.00
11,430.20

PPL 6.39
1 M' Pasang plint keramik artistik ukuran 5 x 20 cm
6.39.1 Bahan
Keramik artistik 5 x 20 cm
5.000 Bh x Rp.
825
Semen portland
0.850 Kg x Rp.
1,200
Pasir pasang
0.0032 M x Rp.
94,500
Semen warna
0.080 Kg x Rp.
2,350
Jumlah (1)
6.39.2 Tenaga
Pekerja
0.090 Oh x Rp.
45,000
Tukang batu
0.090 Oh x Rp.
65,000
Kepala tukang
0.009 Oh x Rp.
75,000
Mandor
0.0045 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)
PPL 6,39 A 1 M' Pasang plint keramik ukuran 10 x 20 cm
6.39.1 Bahan
Keramik 10 x 20 cm
5.000 Bh x
Semen portland
0.850 Kg x
Pasir pasang
0.0032 M x
Semen warna
0.080 Kg x
6.39.2 Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

0.090
0.090
0.009
0.0045

Oh
Oh
Oh
Oh

x
x
x
x

PPL 6,39 B 1 M' Pasang plint keramik ukuran 10 x 30 cm


6.39.1 Bahan
Keramik 10 x 30 cm
3.340 Bh x
Semen portland
0.850 Kg x
Pasir pasang
0.0032 M x
Semen warna
0.080 Kg x
6.39.2 Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

0.090
0.090
0.009
0.0045

Oh
Oh
Oh
Oh

x
x
x
x

Rp.
45,000
Rp.
65,000
Rp.
75,000
Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

4,050.00
5,850.00
675.00
247.50
10,822.50
22,252.70

PPL 6,39 C 1 M' Pasang plint keramik 10 x 40 cm


6.39.1 Bahan
Keramik 10 x 40 cm
2.500
Semen portland
0.850
Pasir pasang
0.0032
Semen warna
0.080

Bh
Kg
M
Kg

x
x
x
x

Rp.
5,940
Rp.
1,200
Rp.
94,500
Rp.
2,350
Jumlah (1)

=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.

14,850.00
1,020.00
302.40
188.00
16,360.40

Oh
Oh
Oh
Oh

x
x
x
x

Rp.
45,000
Rp.
65,000
Rp.
75,000
Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

4,050.00
5,850.00
675.00
247.50
10,822.50
27,182.90

6.39.2 Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

0.090
0.090
0.009
0.0045

PPL 6.41
1 M' Pasang plint vinyil tanpa adukan
6.41.1 Bahan
Vinyl 30 x 30 cm
3.500 Bh
Lem vinyl
0.080 Kg

x Rp.
7,480 = Rp.
x Rp.
39,000 = Rp.
Jumlah (1)
= Rp.

26,180.00
3,120.00
29,300.00

Oh
Oh
Oh
Oh

x
x
x
x

Rp.
45,000
Rp.
65,000
Rp.
75,000
Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

3,600.00
5,200.00
600.00
220.00
9,620.00
38,920.00

PPL 6.42
1 M Pasang lantai keramik 10 x 20 cm
6.42.1 Bahan
Ubin keramik 10 x 20 cm
50.000 Bh
Semen portland
11.380 Kg
Pasir pasang
0.042 M
Semen warna
1.500 Kg

x
x
x
x

Rp.
1,100
Rp.
1,200
Rp.
94,500
Rp.
2,350
Jumlah (1)

=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.

55,000.00
13,656.00
3,969.00
3,525.00
76,150.00

Oh
Oh
Oh
Oh

x
x
x
x

Rp.
45,000
Rp.
65,000
Rp.
75,000
Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

27,900.00
22,750.00
2,625.00
1,650.00
54,925.00
131,075.00

PPL 6.43
1 M Pasang lantai keramik 15 x 15 cm
6.43.1 Bahan
Ubin keramik 15 x 15 cm
44.000 Bh
Semen portland
11.380 Kg
Pasir pasang
0.042 M
Semen warna
1.500 Kg

x
x
x
x

Rp.
1,210
Rp.
1,200
Rp.
94,500
Rp.
2,350
Jumlah (1)

=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.

53,240.00
13,656.00
3,969.00
3,525.00
74,390.00

Oh
Oh
Oh
Oh

x
x
x
x

Rp.
45,000
Rp.
65,000
Rp.
75,000
Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

27,900.00
22,750.00
2,625.00
1,650.00
54,925.00
129,315.00

PPL 6.44
1 M Pasang lantai keramik 20 x 20 cm
6.44.1 Bahan
Ubin keramik 20 x 20 cm
25.000 Bh
Semen portland
11.380 Kg
Pasir pasang
0.042 M
Semen warna
1.500 Kg

x
x
x
x

Rp.
2,200
Rp.
1,200
Rp.
94,500
Rp.
2,350
Jumlah (1)

=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.

55,000.00
13,656.00
3,969.00
3,525.00
76,150.00

Oh
Oh
Oh
Oh

x
x
x
x

Rp.
45,000
Rp.
65,000
Rp.
75,000
Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

27,900.00
22,750.00
2,625.00
1,650.00
54,925.00
131,075.00

PPL 6.45
1 M Pasang lantai keramik 20 x 25 cm
6.45.1 Bahan
Ubin keramik 20 x 25 cm
20.000 Bh
Semen portland
11.380 Kg
Pasir pasang
0.042 M
Semen warna
1.500 Kg

x
x
x
x

Rp.
3,410
Rp.
1,200
Rp.
94,500
Rp.
2,350
Jumlah (1)

=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.

68,200.00
13,656.00
3,969.00
3,525.00
89,350.00

x
x
x
x

Rp.
45,000
Rp.
65,000
Rp.
75,000
Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

27,900.00
22,750.00
2,625.00
1,650.00
54,925.00
144,275.00

6.41.2 Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

6.42.2 Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

6.43.2 Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

6.44.2 Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

6.45.2 Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

0.080
0.080
0.008
0.004

0.620
0.350
0.035
0.030

0.620
0.350
0.035
0.030

0.620
0.350
0.035
0.030

0.620
0.350
0.035
0.030

Oh
Oh
Oh
Oh

PPL 6.46
1 M Pasang lantai keramik 25 x 25 cm
6.46.1 Bahan
Ubin keramik 25 x 25 cm
16.000 Bh
Semen portland
11.380 Kg
Pasir pasang
0.042 M
Semen warna
1.500 Kg

x
x
x
x

Rp.
2,750
Rp.
1,200
Rp.
94,500
Rp.
2,350
Jumlah (1)

=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.

44,000.00
13,656.00
3,969.00
3,525.00
65,150.00

Oh
Oh
Oh
Oh

x
x
x
x

Rp.
45,000
Rp.
65,000
Rp.
75,000
Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

27,900.00
22,750.00
2,625.00
1,650.00
54,925.00
120,075.00

PPL 6.47
1 M Pasang lantai keramik 30 x 30 cm
6.47.1 Bahan
Ubin keramik 30 x 30 cm
11.120 Bh
Semen portland
11.380 Kg
Pasir pasang
0.042 M
Semen warna
1.500 Kg

x
x
x
x

Rp.
4,950
Rp.
1,200
Rp.
94,500
Rp.
2,350
Jumlah (1)

=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.

55,044.00
13,656.00
3,969.00
3,525.00
76,194.00

x
x
x
x

Rp.
45,000
Rp.
65,000
Rp.
75,000
Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

27,900.00
22,750.00
2,625.00
1,650.00
54,925.00
131,119.00

=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.

71,500.00
13,656.00
3,969.00
3,525.00
92,650.00

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

27,900.00
22,750.00
2,625.00
1,650.00
54,925.00
147,575.00

6.46.2 Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

6.47.2 Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

0.620
0.350
0.035
0.030

0.620
0.350
0.035
0.030

Oh
Oh
Oh
Oh

PPL 6.48
1 M Pasang lantai keramik 30 x 30 cm anti slip
6.48.1 Bahan
Keramik 30 x 30 cm anti slip
10.000 Bh x Rp.
7,150
Semen portland
11.380 Kg x Rp.
1,200
Pasir pasang
0.042 M x Rp.
94,500
Semen warna
1.500 Kg x Rp.
2,350
Jumlah (1)
6.48.2 Tenaga
Pekerja
0.620 Oh x Rp.
45,000
Tukang batu
0.350 Oh x Rp.
65,000
Kepala tukang
0.035 Oh x Rp.
75,000
Mandor
0.030 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)
PPL 6.49
1 M Pasang lantai keramik 40 x 40 cm
6.49.1 Bahan
Ubin keramik 40 x 40 cm
6.250 Bh
Semen portland
11.380 Kg
Pasir pasang
0.042 M
Semen warna
1.500 Kg
6.49.2 Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

0.620
0.350
0.035
0.030

Oh
Oh
Oh
Oh

x
x
x
x

Rp.
8,800
Rp.
1,200
Rp.
94,500
Rp.
2,350
Jumlah (1)

=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.

55,000.00
13,656.00
3,969.00
3,525.00
76,150.00

x
x
x
x

Rp.
45,000
Rp.
65,000
Rp.
75,000
Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

27,900.00
22,750.00
2,625.00
1,650.00
54,925.00
131,075.00

Rp.
12,650
Rp.
1,200
Rp.
94,500
Rp.
2,350
Jumlah (1)

=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.

151,800.00
16,980.00
3,685.50
4,700.00
177,165.50

Rp.
45,000
Rp.
65,000
Rp.
75,000
Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

27,900.00
22,750.00
2,625.00
1,650.00
54,925.00
232,090.50

PPL 6.50
1 M Pasang lantai mosaik 30 x 30 cm, ex lokal
6.50.1 Bahan
Mosaik 30 x 30 cm
12.000 Bh x
Semen portland
14.150 Kg x
Pasir pasang
0.039 M x
Semen warna
2.000 Kg x
6.50.2 Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

0.620
0.350
0.035
0.030

Oh
Oh
Oh
Oh

x
x
x
x

PPL 6.51
1 M Pasang lantai marmer
6.51.1 Bahan
Marmer
Semen portland
Pasir pasang
Semen warna
6.51.2 Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

1.052
14.150
0.039
2.000

Bh
Kg
M
Kg

x
x
x
x

Rp.
238,150
Rp.
1,200
Rp.
94,500
Rp.
2,350
Jumlah (1)

=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.

250,533.80
16,980.00
3,685.50
4,700.00
275,899.30

0.620
0.350
0.035
0.030

Oh
Oh
Oh
Oh

x
x
x
x

Rp.
45,000
Rp.
65,000
Rp.
75,000
Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

27,900.00
22,750.00
2,625.00
1,650.00
54,925.00
330,824.30

x Rp.
77,500 = Rp.
x Rp.
39,000 = Rp.
Jumlah (1)
= Rp.

81,375.00
13,650.00
95,025.00

PPL 6.52
1 M Pasang lantai karpet 100% wool
6.52.1 Bahan
Karpet wool
1.050 M
Lem vinyl
0.350 Kg
6.52.2 Tenaga
Pekerja
Tukang
Kepala tukang
Mandor

0.170
0.170
0.017
0.0085

Oh
Oh
Oh
Oh

x
x
x
x

Rp.
45,000
Rp.
65,000
Rp.
75,000
Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

PPL 6.53
1 M Pasang lantai karpet 80% wool, 20% nylon
6.53.1 Bahan
Karpet wool+nylon
1.050 M x Rp.
79,500
Lem vinyl
0.350 Kg x Rp.
39,000
Jumlah (1)
6.53.2 Tenaga
Pekerja
0.170 Oh x Rp.
45,000
Tukang
0.170 Oh x Rp.
65,000
Kepala tukang
0.017 Oh x Rp.
75,000
Mandor
0.0085 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)
PPL 6.55
1 M Pasang lantai karpet
6.55.1 Bahan
Carpet
1.050 M x Rp.
82,500
Lem vinyl
0.350 Kg x Rp.
39,000
Jumlah (1)
6.55.2 Tenaga
Pekerja
0.170 Oh x Rp.
45,000
Tukang
0.170 Oh x Rp.
65,000
Kepala tukang
0.017 Oh x Rp.
75,000
Mandor
0.0085 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)
PPL 6.56
1 M Pasang lantai parquet jati
6.56.1 Bahan
Perquet jati
1.050 M x Rp.
335,000
Lem vinyl
0.600 Kg x Rp.
39,000
Jumlah (1)
6.56.2 Tenaga
Pekerja
0.650 Oh x Rp.
45,000
Tukang
0.350 Oh x Rp.
65,000
Kepala tukang
0.035 Oh x Rp.
75,000
Mandor
0.0325 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)
PPL 6.58
1 M Pasang dinding porselin 11 x 11 cm, putih
6.58.1 Bahan
Porselin 11 x 11 cm
83.000 Bh x Rp.
1,100
Semen portland
9.300 Kg x Rp.
1,200
Pasir pasang
0.018 M x Rp.
94,500
Semen warna
1.500 Kg x Rp.
2,350
Jumlah (1)
6.58.2 Tenaga
Pekerja
0.620 Oh x Rp.
45,000
Tukang batu
0.500 Oh x Rp.
65,000
Kepala tukang
0.050 Oh x Rp.
75,000
Mandor
0.030 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

7,650.00
11,050.00
1,275.00
467.50
20,442.50
115,467.50

= Rp.
= Rp.
= Rp.

83,475.00
13,650.00
97,125.00

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

7,650.00
11,050.00
1,275.00
467.50
20,442.50
117,567.50

= Rp.
= Rp.
= Rp.

86,625.00
13,650.00
100,275.00

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

7,650.00
11,050.00
1,275.00
467.50
20,442.50
120,717.50

= Rp.
= Rp.
= Rp.

351,750.00
23,400.00
375,150.00

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

29,250.00
22,750.00
2,625.00
1,787.50
56,412.50
431,562.50

=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.

91,300.00
11,160.00
1,701.00
3,525.00
107,686.00

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

27,900.00
32,500.00
3,750.00
1,650.00
65,800.00
173,486.00

PPL 6.59
1 M Pasang dinding porselin 11 x 11 cm, warna
6.59.1 Bahan
Porselin 11 x 11 cm warna
83.000 Bh x Rp.
1,320
Semen portland
9.300 Kg x Rp.
1,200
Pasir pasang
0.018 M x Rp.
94,500
Semen warna
1.500 Kg x Rp.
2,350
Jumlah (1)
6.59.2 Tenaga
Pekerja
0.620 Oh x Rp.
45,000
Tukang batu
0.500 Oh x Rp.
65,000
Kepala tukang
0.050 Oh x Rp.
75,000
Mandor
0.030 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

PPL 6.60
1 M Pasang dinding porselin 15 x 15 cm, putih
6.60.1 Bahan
Porselin 15 x 15 cm putih
45.000 Bh x
Semen portland
9.300 Kg x
Pasir pasang
0.018 M x
Semen warna
1.500 Kg x
6.60.2 Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

0.600
0.450
0.045
0.030

Oh
Oh
Oh
Oh

x
x
x
x

=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.

109,560.00
11,160.00
1,701.00
3,525.00
125,946.00

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

27,900.00
32,500.00
3,750.00
1,650.00
65,800.00
191,746.00

Rp.
2,090
Rp.
1,200
Rp.
94,500
Rp.
2,350
Jumlah (1)

=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.

94,050.00
11,160.00
1,701.00
3,525.00
110,436.00

Rp.
45,000
Rp.
65,000
Rp.
75,000
Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

27,000.00
29,250.00
3,375.00
1,650.00
61,275.00
171,711.00

=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.

103,950.00
11,160.00
1,701.00
3,525.00
120,336.00

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

27,000.00
29,250.00
3,375.00
1,650.00
61,275.00
181,611.00

=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.

165,000.00
11,160.00
1,701.00
3,525.00
181,386.00

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

27,000.00
29,250.00
3,375.00
1,650.00
61,275.00
242,661.00

Rp.
825
Rp.
1,200
Rp.
94,500
Rp.
2,350
Jumlah (1)

=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.

82,500.00
11,160.00
1,701.00
3,525.00
98,886.00

Rp.
45,000
Rp.
65,000
Rp.
75,000
Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

27,000.00
29,250.00
3,375.00
1,650.00
61,275.00
160,161.00

PPL 6.61
1 M Pasang dinding porselin 15 x 15 cm, warna
6.61.1 Bahan
Porselin 15 x 15 cm warna
45.000 Bh x Rp.
2,310
Semen portland
9.300 Kg x Rp.
1,200
Pasir pasang
0.018 M x Rp.
94,500
Semen warna
1.500 Kg x Rp.
2,350
Jumlah (1)
6.61.2 Tenaga
Pekerja
0.600 Oh x Rp.
45,000
Tukang batu
0.450 Oh x Rp.
65,000
Kepala tukang
0.045 Oh x Rp.
75,000
Mandor
0.030 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)
PPL 6.64
1 M Pasang dinding keramik artistik 10 x 20 cm
6.64.1 Bahan
Keramik artistik 10x20 cm
100.000 Bh x Rp.
1,650
Portland Cement
9.300 Kg x Rp.
1,200
Pasir pasang
0.018 M x Rp.
94,500
Semen warna
1.500 Kg x Rp.
2,350
Jumlah (1)
6.64.2 Tenaga
Pekerja
0.600 Oh x Rp.
45,000
Tukang batu
0.450 Oh x Rp.
65,000
Kepala tukang
0.045 Oh x Rp.
75,000
Mandor
0.030 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

PPL 6.65
1 M Pasang dinding keramik artistik 5 x 20 cm
6.65.1 Bahan
Keramik artistik 5x20 cm
100.000 Bh x
Portland Cement
9.300 Kg x
Pasir pasang
0.018 M x
Semen warna
1.500 Kg x
6.65.2 Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

0.600
0.450
0.045
0.030

Oh
Oh
Oh
Oh

x
x
x
x

PPL 6.66
1 M Pasang dinding keramik 10 x 20 cm
6.66.1 Bahan
Keramik 10 x 20 cm
50.000 Bh
Portland Cement
9.300 Kg
Pasir pasang
0.018 M
Semen warna
1.500 Kg

x
x
x
x

Rp.
1,100
Rp.
1,200
Rp.
94,500
Rp.
2,350
Jumlah (1)

=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.

55,000.00
11,160.00
1,701.00
3,525.00
71,386.00

Oh
Oh
Oh
Oh

x
x
x
x

Rp.
45,000
Rp.
65,000
Rp.
75,000
Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

27,000.00
29,250.00
3,375.00
1,650.00
61,275.00
132,661.00

PPL 6.67
1 M Pasang dinding keramik 15 x 15 cm
6.67.1 Bahan
Keramik 15 x 15 cm
45.000 Bh
Portland Cement
9.300 Kg
Pasir pasang
0.018 M
Semen warna
1.500 Kg

x
x
x
x

Rp.
1,210
Rp.
1,200
Rp.
94,500
Rp.
2,350
Jumlah (1)

=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.

54,450.00
11,160.00
1,701.00
3,525.00
70,836.00

Oh
Oh
Oh
Oh

x
x
x
x

Rp.
45,000
Rp.
65,000
Rp.
75,000
Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

27,000.00
29,250.00
3,375.00
1,650.00
61,275.00
132,111.00

PPL 6.68
1 M Pasang dinding keramik 20 x 20 cm
PPL 6.68.1 Bahan
Keramik 20 x 20 cm
25.000 Bh
Portland Cement
9.300 Kg
Pasir pasang
0.018 M
Semen warna
1.500 Kg

x
x
x
x

Rp.
2,200
Rp.
1,200
Rp.
94,500
Rp.
2,350
Jumlah (1)

=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.

55,000.00
11,160.00
1,701.00
3,525.00
71,386.00

Oh
Oh
Oh
Oh

x
x
x
x

Rp.
45,000
Rp.
65,000
Rp.
75,000
Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

27,000.00
6,500.00
3,375.00
1,650.00
38,525.00
109,911.00

PPL 6.69
1 M Pasang dinding keramik 20 x 25 cm
6.69.1 Bahan
Keramik 10 x 20 cm
20.000 Bh
Portland Cement
9.300 Kg
Pasir pasang
0.018 M
Semen warna
1.500 Kg

x
x
x
x

Rp.
2,750
Rp.
1,200
Rp.
94,500
Rp.
2,350
Jumlah (1)

=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.

55,000.00
11,160.00
1,701.00
3,525.00
71,386.00

6.66.2 Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

6.67.2 Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

6.68.2 Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

6.69.2 Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

PPL 6.70
1 M Pasang dinding marmer
6.70.1 Bahan
Marmer
Paku pancing
Portland Cement
Pasir pasang
Semen warna
6.70.2 Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

0.600
0.450
0.045
0.030

0.600
0.450
0.045
0.030

0.600
0.100
0.045
0.030

0.600
0.125
0.0125
0.030

Oh
Oh
Oh
Oh

x
x
x
x

Rp.
45,000
Rp.
65,000
Rp.
75,000
Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

27,000.00
8,125.00
937.50
1,650.00
37,712.50
109,098.50

1.020
2.000
12.440
0.025
1.500

M
Bh
Kg
M
Kg

x
x
x
x
x

Rp.
238,150
Rp.
650
Rp.
1,200
Rp.
94,500
Rp.
2,350
Jumlah (1)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

242,913.00
1,300.00
14,928.00
2,362.50
3,525.00
265,028.50

0.720
0.650
0.065
0.035

Oh
Oh
Oh
Oh

x
x
x
x

Rp.
45,000
Rp.
65,000
Rp.
75,000
Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

32,400.00
42,250.00
4,875.00
1,925.00
81,450.00
346,478.50

PPL 6.71
1 M Pasang dinding bata pelapis 7 x 3 x 20 cm
6.71.1 Bahan
Bata pelapis dinding
60.000 Bh x Rp.
1,850
Portland Cement
12.440 Kg x Rp.
1,200
Pasir pasang
0.025 M x Rp.
94,500
Jumlah (1)
6.71.2 Tenaga
Pekerja
0.650 Oh x Rp.
45,000
Tukang batu
0.500 Oh x Rp.
65,000
Kepala tukang
0.050 Oh x Rp.
75,000
Mandor
0.030 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)
PPL 6.73
1 M Pasang dinding batu poros
6.73.1 Bahan
Batu poros
1.050 M x Rp.
104,250
Portland Cement
11.750 Kg x Rp.
1,200
Pasir pasang
0.035 M x Rp.
94,500
Jumlah (1)
6.73.2 Tenaga
Pekerja
0.620 Oh x Rp.
45,000
Tukang batu
0.350 Oh x Rp.
65,000
Kepala tukang
0.035 Oh x Rp.
75,000
Mandor
0.030 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)
PPL 6.74
1 M Pasang dinding batu tempel hitam
6.74.1 Bahan
Batu tempel hitam
1.050 M x Rp.
95,000
Portland Cement
11.750 Kg x Rp.
1,200
Pasir pasang
0.035 M x Rp.
94,500
Jumlah (1)
6.74.2 Tenaga
Pekerja
0.620 Oh x Rp.
45,000
Tukang batu
0.350 Oh x Rp.
65,000
Kepala tukang
0.035 Oh x Rp.
75,000
Mandor
0.030 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)
PPL 6.75
1 M Pasang lantai vinyl karet 30 x 30 cm Kls I
6.75.1 Bahan
Vinyl karet
11.050 Bh x Rp.
8,910
Lem vinyl
0.350 Kg x Rp.
39,000
Jumlah (1)
6.75.2 Tenaga
Pekerja
0.150 Oh x Rp.
45,000
Tukang batu
0.150 Oh x Rp.
65,000
Kepala tukang
0.015 Oh x Rp.
75,000
Mandor
0.0075 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)
PPL 6.76
1 M Pasang lantai vinyl karet 30 x 30 cm Kls II
6.76.1 Bahan
Vinyl karet
11.050 Bh x Rp.
8,250
Lem vinyl
0.350 Kg x Rp.
39,000
Jumlah (1)
6.76.2 Tenaga
Pekerja
0.150 Oh x Rp.
45,000
Tukang batu
0.150 Oh x Rp.
65,000
Kepala tukang
0.015 Oh x Rp.
75,000
Mandor
0.0075 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)
PPL 6.77
1 M Pasang lantai vinyl asbes 30 x 30 cm
6.77.1 Bahan
Vinyl asbes 30 x 30 cm
11.050 Bh x Rp.
7,480
Lem vinyl
0.350 Kg x Rp.
39,000
Jumlah (1)
6.77.2 Tenaga
Pekerja
0.150 Oh x Rp.
45,000
Tukang batu
0.150 Oh x Rp.
65,000
Kepala tukang
0.015 Oh x Rp.
75,000
Mandor
0.0075 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=

Rp.
Rp.
Rp.
Rp.

111,000.00
23,014.00
2,362.50
136,376.50

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

29,250.00
32,500.00
3,750.00
1,650.00
67,150.00
203,526.50

=
=
=
=

Rp.
Rp.
Rp.
Rp.

109,462.50
1,224,937.50
3,307.50
1,337,707.50

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

27,900.00
22,750.00
2,625.00
1,650.00
54,925.00
1,392,632.50

=
=
=
=

Rp.
Rp.
Rp.
Rp.

99,750.00
1,116,250.00
3,307.50
1,219,307.50

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

27,900.00
22,750.00
2,625.00
1,650.00
54,925.00
1,274,232.50

= Rp.
= Rp.
= Rp.

98,455.50
3,118.50
101,574.00

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

6,750.00
9,750.00
1,125.00
412.50
18,037.50
119,611.50

= Rp.
= Rp.
= Rp.

91,162.50
2,887.50
94,050.00

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

6,750.00
9,750.00
1,125.00
412.50
18,037.50
112,087.50

= Rp.
= Rp.
= Rp.

82,654.00
2,618.00
85,272.00

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

6,750.00
9,750.00
1,125.00
412.50
18,037.50
103,309.50

PPL 6.78
1 M Pasang lantai vinyl motif kembang 30 x 30 cm
6.78.1 Bahan
Vinyl motif kembang
11.050 Bh x Rp.
8,580
Lem vinyl
0.350 Kg x Rp.
39,000
Jumlah (1)
6.78.2 Tenaga
Pekerja
0.150 Oh x Rp.
45,000
Tukang batu
0.150 Oh x Rp.
65,000
Kepala tukang
0.015 Oh x Rp.
75,000
Mandor
0.0075 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)
PPL 6.79
1 M Pasang wall corvering lebar 50 cm
6.79.1 Bahan
Coverting L.50 cm
1.100 M
Lem
0.250 Kg
6.79.2 Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

PPL 6.82
1 M Plint kayu Jati 2 x 10 cm
6.82.1 Bahan
Kayu jati papan
Paku skrup 3,5"
6.82.2 Tenaga
Pekerja
Tukang kayu
Kepala tukang
Mandor

0.750
0.170
0.017
0.0085

Oh
Oh
Oh
Oh

0.0024 M
0.050 Kg

0.120
0.120
0.012
0.006

Oh
Oh
Oh
Oh

PPL 6,82.A 1 M Plint kayu Meranti batu 2 x 10 cm


6.82.1 Bahan
Kayu Meranti batu, papan
0.0024 M
Paku skrup 3,5"
0.050 Kg
6.82.2 Tenaga
Pekerja
Tukang kayu
Kepala tukang
Mandor

0.120
0.120
0.012
0.006

Oh
Oh
Oh
Oh

BERSAMBUNG : ..ABK PEKERJAAN PENGECATAN

= Rp.
= Rp.
= Rp.
Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

6,750.00
9,750.00
1,125.00
412.50
18,037.50
115,849.50

x Rp.
57,500 = Rp.
x Rp.
39,000 = Rp.
Jumlah (1)
= Rp.

63,250.00
14,375.00
77,625.00

x
x
x
x

Rp.
45,000
Rp.
65,000
Rp.
75,000
Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

94,809.00
3,003.00
97,812.00

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

33,750.00
11,050.00
1,275.00
467.50
46,542.50
124,167.50

x Rp. 21,913,130 = Rp.


x Rp.
18,500 = Rp.
Jumlah (1)
= Rp.

52,591.51
925.00
53,516.51

x
x
x
x

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

5,400.00
7,800.00
900.00
330.00
14,430.00
67,946.51

x Rp.
8,612,680 = Rp.
x Rp.
18,500 = Rp.
Jumlah (1)
= Rp.

20,670.43
925.00
21,595.43

x
x
x
x

5,400.00
7,800.00
900.00
330.00
14,430.00
36,025.43

Rp.
45,000
Rp.
65,000
Rp.
75,000
Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

Rp.
45,000
Rp.
65,000
Rp.
75,000
Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

=
=
=
=
=
=

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

ANALISA BIAYA KONTRUKSI


PEKERJAAN PENGECATAN

PC 6.1
6.1.1

6.1.2

PC 6.2.
6.2.1

6.2.2

PC 6.3.
6.3 .1

6.3.2

PC 6.4
6.4 .1

6.4.2

PC 6.6
6.4 .1

6.4.2

PC 6.7
6.7.1

6.7.2

1M Mengikis/ mengerok permukaan cat tembok lama


Bahan
Soda api
0.050 Kg x Rp.
20,460 =
Jumlah (1)
=
Tenaga
Pekerja
0.150 Oh x Rp.
45,000 =
Mandor
0.0025 Oh x Rp.
55,000 =
Jumlah (2)
=
Jumlah (1) + (2) =
1M Mencuci bidang permukaan tembok yang pernah di cat
Bahan
Sabun
0.050 Kg x Rp.
13,750 =
Jumlah (1)
=
Tenaga
Pekerja
0.150 Oh x Rp.
45,000 =
Mandor
0.0025 Oh x Rp.
55,000 =
Jumlah (2)
=
Jumlah (1) + (2) =
1M Mengerok karat cat lama permukaan baja dengan cara manual
Bahan
Sabun
0.050 Kg x Rp.
13,750 =
Jumlah (1)
=
Tenaga
Pekerja
0.150 Oh x Rp.
45,000 =
Mandor
0.0025 Oh x Rp.
55,000 =
Jumlah (2)
=
Jumlah (1) + (2) =
1M Menyabun permukaan tembok lama
Bahan
Sabun
0.050 Kg x Rp.
13,750 =
Jumlah (1)
=
Tenaga
Pekerja
0.150 Oh x Rp.
45,000 =
Mandor
0.0025 Oh x Rp.
55,000 =
Jumlah (2)
=
Jumlah (1) + (2) =
1M Mendempul dan menggosok kayu
Bahan
Dempul jadi
0.080 Kg x Rp.
10,780 =
Minyak cat
0.020 Kg x Rp.
10,010 =
Amplas
0.100 Lbr x Rp.
3,080 =
Jumlah (1)
=
Tenaga
Pekerja
0.040 Oh x Rp.
45,000 =
Tukang cat
0.040 Oh x Rp.
65,000 =
Kepala tukang
0.040 Oh x Rp.
75,000 =
Mandor
0.0025 Oh x Rp.
55,000 =
Jumlah (2)
=
Jumlah (1) + (2) =
1M Pengecatan bidang kayu lama
Bahan
Plamir
0.150 Kg x Rp.
14,300 =
Minyak cat
0.170 Kg x Rp.
10,010 =
Cat minyak
0.170 Kg x Rp.
42,350 =
Jumlah (1)
=
Tenaga
Pekerja
0.070 Oh x Rp.
45,000 =
Tukang cat
0.075 Oh x Rp.
65,000 =
Kepala tukang
0.0075 Oh x Rp.
75,000 =
Mandor
0.0025 Oh x Rp.
55,000 =
Jumlah (2)
=
Jumlah (1) + (2) =

Rp.
Rp.

1,023.00
1,023.00

Rp.
Rp.
Rp.
Rp.

6,750.00
137.50
6,887.50
7,910.50

Rp.
Rp.

687.50
687.50

Rp.
Rp.
Rp.
Rp.

6,750.00
137.50
6,887.50
7,575.00

Rp.
Rp.

687.50
687.50

Rp.
Rp.
Rp.
Rp.

6,750.00
137.50
6,887.50
7,575.00

Rp.
Rp.

687.50
687.50

Rp.
Rp.
Rp.
Rp.

6,750.00
137.50
6,887.50
7,575.00

Rp.
Rp.
Rp.
Rp.

862.40
200.20
308.00
1,370.60

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

1,800.00
2,600.00
3,000.00
137.50
7,537.50
8,908.10

Rp.
Rp.
Rp.
Rp.

45,000.00
65,000.00
75,000.00
185,000.00

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

3,150.00
4,875.00
562.50
137.50
8,725.00
193,725.00

PC 6.13
1M Peleburan bidang kayu dan vernis
6.13.1 Bahan
Vernis
0.150
Dempul
0.050
Ampelas
0.100
Kuas
0.010
6.13.2

Tenaga
Pekerja
Tukang cat
Kepala tukang
Mandor

0.160
0.160
0.016
0.0025

Ltr
Kg
Lbr
bh

x
x
x
x

Rp.
43,890
Rp.
10,780
Rp.
3,080
Rp.
8,250
Jumlah (1)

=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.

6,583.50
539.00
308.00
82.50
7,513.00

Oh
Oh
Oh
Oh

x
x
x
x

Rp.
45,000
Rp.
65,000
Rp.
75,000
Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

7,200.00
10,400.00
1,200.00
137.50
18,937.50
26,450.50

PC 6.14
1M Pengecatan tembok baru ( 1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup )
6.14.1 Bahan
Plamir
0.100 Kg x Rp.
14,300 = Rp.
1,430.00
Cat dasar
0.100 Kg x Rp.
13,750 = Rp.
1,375.00
Cat Tembok 2 x
0.260 Kg x Rp.
17,490 = Rp.
4,547.40
Jumlah (1)
= Rp.
7,352.40
6.14.2 Tenaga
Pekerja
0.020 Oh x Rp.
45,000 = Rp.
900.00
Tukang cat
0.063 Oh x Rp.
65,000 = Rp.
4,095.00
Kepala tukang
0.0063 Oh x Rp.
75,000 = Rp.
472.50
Mandor
0.0025 Oh x Rp.
55,000 = Rp.
137.50
Jumlah (2)
= Rp.
5,605.00
Jumlah (1) + (2) = Rp.
12,957.40

PC 6.15
1M Pengecatan tembok lama ( 1 lapis cat dasar, 2 lapis cat penutup )
6.15.1 Bahan
Cat dasar
0.120 Kg x Rp.
13,750 = Rp.
Cat Tembok 2 x
0.360 Kg x Rp.
17,490 = Rp.
Jumlah (1)
= Rp.
6.15.2 Tenaga
Pekerja
0.028 Oh x Rp.
45,000 = Rp.
Tukang cat
0.042 Oh x Rp.
65,000 = Rp.
Kepala tukang
0.0042 Oh x Rp.
75,000 = Rp.
Mandor
0.0025 Oh x Rp.
55,000 = Rp.
Jumlah (2)
= Rp.
Jumlah (1) + (2) = Rp.
PC 6.17
1M Melebur tembok dengan kapur sirih
6.17.1 Bahan
Ampelas
0.100
Alang - alang
0.250
Perancah kayu
0.002
Kapur sirih
0.150
6.17.2

Tenaga
Pekerja
Tukang cat
Kepala tukang
Mandor

0.150
0.001
0.0001
0.0025

1,650.00
6,296.40
7,946.40
1,260.00
2,730.00
315.00
137.50
4,442.50
12,388.90

Lbr
Ikat
M
Kg

x
x
x
x

Rp.
3,080
Rp.
2,200
Rp. 3,144,900
Rp.
3,080
Jumlah (1)

=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.

308.00
550.00
6,289.80
462.00
7,609.80

Oh
Oh
Oh
Oh

x
x
x
x

Rp.
45,000
Rp.
65,000
Rp.
75,000
Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

14,361.60
65.00
7.50
137.50
14,571.60
22,181.40

PC 6.18
1M Melebur tembok lama dengan kapur sirih ( untuk pemeriharaan )
6.18.1 Bahan
Perancah kayu
0.002 M x Rp. 3,144,900 = Rp.
Kapur sirih
0.300 Kg x Rp.
3,080 = Rp.
Jumlah (1)
= Rp.
6.18.2 Tenaga
Pekerja
0.040 Oh x Rp.
45,000 = Rp.
Tukang cat
0.005 Oh x Rp.
65,000 = Rp.
Kepala tukang
0.0005 Oh x Rp.
75,000 = Rp.
Mandor
0.0025 Oh x Rp.
55,000 = Rp.
Jumlah (2)
= Rp.
Jumlah (1) + (2) = Rp.

36,753.00
924.00
37,677.00
1,800.00
325.00
37.50
137.50
2,300.00
39,977.00

PC 6.19
1M Pemasangan wall paper
6.19.1 Bahan
wall paper
Perekat lem karet
6.19.2

Tenaga
Pekerja
Tukang cat
Kepala tukang
Mandor

1.200 M x Rp.
27,830 = Rp.
0.200 Kg x Rp.
37,000 = Rp.
Jumlah (1)
= Rp.
0.020
0.200
0.002
0.0025

Oh
Oh
Oh
Oh

x
x
x
x

Rp.
45,000
Rp.
65,000
Rp.
75,000
Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

PC 6.20
1M Pengecatan permukaan baja dengan meni besi
6.20.1 Bahan
Meni besi
0.100 Kg x Rp.
43,890
Kuas
0.010 Bh x Rp.
8,250
Jumlah (1)
6.20.2 Tenaga
Pekerja
0.020 Oh x Rp.
45,000
Tukang cat
0.200 Oh x Rp.
65,000
Kepala tukang
0.02 Oh x Rp.
75,000
Mandor
0.01 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) + (2)

=
=
=
=
=
=

33,396.00
7,400.00
40,796.00

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

900.00
13,000.00
150.00
137.50
14,187.50
54,983.50

= Rp.
= Rp.
= Rp.

4,389.00
82.50
4,471.50

=
=
=
=
=
=

PC 6.21. 1M Pengecatan permukaan baja dengan meni besi dan perancah


6.21.1 Bahan
Meni besi
0.100 Kg x Rp.
43,890 =
Kuas
0.010 Bh x Rp.
8,250 =
Peranca kayu
0.002 M x Rp. 3,144,900 =
Jumlah (1)
=
6.21.2 Tenaga
Pekerja
0.250 Oh x Rp.
45,000 =
Tukang cat
0.225 Oh x Rp.
65,000 =
Kepala tukang
0.0225 Oh x Rp.
75,000 =
Mandor
0.0075 Oh x Rp.
55,000 =
Jumlah (2)
=
Jumlah (1) + (2) =

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

900.00
13,000.00
1,500.00
550.00
15,950.00
20,421.50

Rp.
Rp.
Rp.
Rp.

4,389.00
82.50
6,289.80
10,761.30

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

11,250.00
14,625.00
1,687.50
412.50
27,975.00
38,736.30

PC 6.23.

1M Pengecatan permukaan baja lapis seng (galbani) secara manual


sistem 1 lapis cat konvensional dengan tebal 200 um.
6.23.1 Bahan
Cat minyak besi
0.300 Kg x Rp.
45,540 = Rp.
Jumlah (1)
= Rp.
6.23.2 Tenaga
Pekerja
0.006 Oh x Rp.
45,000 = Rp.
Tukang cat
0.006 Oh x Rp.
65,000 = Rp.
Kepala tukang
0.0225 Oh x Rp.
75,000 = Rp.
Mandor
0.0075 Oh x Rp.
55,000 = Rp.
Jumlah (2)
= Rp.
Jumlah (1) + (2) = Rp.

1M Pengecatan permukaan baja lapis seng (galbani) secara manual


sistem 3 lapis cat konvensional dengan tebal 200 um.
6.24.1 Bahan
Cat dasar
0.110 Kg x Rp.
13,750 = Rp.
Cat Menie besi
0.170 Kg x Rp.
43,890 = Rp.
Cat minyak besi
0.080 Kg x Rp.
45,540 = Rp.
Jumlah (1)
= Rp.
6.24.2 Tenaga
Pekerja
0.500 Oh x Rp.
45,000 = Rp.
Tukang cat
0.800 Oh x Rp.
65,000 = Rp.
Kepala tukang
0.300 Oh x Rp.
75,000 = Rp.
Mandor
0.200 Oh x Rp.
55,000 = Rp.
Jumlah (2)
= Rp.
Jumlah (1) + (2) = Rp.

13,662.00
13,662.00
270.00
390.00
1,687.50
412.50
2,760.00
16,422.00

PC 6.24.

1,512.50
7,461.30
3,643.20
12,617.00
22,500.00
52,000.00
22,500.00
11,000.00
108,000.00
120,617.00

PC 6.25.

1M Pengecatan permukaan baja lapis seng (galbani) secara semprot


(airless spray) dengan sistem 1 lapis cat konvensional dengan tebal 200 um.
6.25.1 Bahan
Cat dasar
0.300 Kg x Rp.
13,750 = Rp.
Jumlah (1)
= Rp.
6.25.2 Tenaga
Pekerja
0.400 Oh x Rp.
45,000 = Rp.
Tukang cat
0.700 Oh x Rp.
65,000 = Rp.
Kepala tukang
0.200 Oh x Rp.
75,000 = Rp.
Mandor
0.200 Oh x Rp.
55,000 = Rp.
Jumlah (2)
= Rp.
Jumlah (1) + (2)
= Rp.

Medan,
DIKETAHUI OLEH :

4,125.00
4,125.00
18,000.00
45,500.00
15,000.00
11,000.00
89,500.00
93,625.00

Maret 2008

DIBUAT OLEH : TIM TEKNIS

Kepala Dinas Penataan Ruang dan

1. Ir. Jeremias Sinaga, MAP

{.)

Permukiman Prov. Sumatera Utara

2. Ir. Herimas

{.)

3. H. Sugiarto Bharata, ST

{.)

4. H. Ali Muhar, ST

{.)

5. Sakula Karo karo, ST

{.)

6. Ebenser Saragih, SE

{.)

7. Sahat Hasudungan, ST

{.)

8. Ir. Tanogara Siahaan

{.)

9. Ali Fauzan, ST

{.)

Ir. H. Syafruddin Siregar, MSi


Pembina Utama Muda
NIP. 400025884

10. Ir. Naimul Ahmad R. ST

{.)

11. Chandra, ST

{.)

ANALISA BIAYA KONSTRUKSI


PEKERJAAN SANITASI

PS 6.1.
6.1.1.

6.1.2.

PS 6.2.
6.2.1.

6.2.2.

PS 6.3.
6.3.1.

6.3.2.

PS 6.4
6.4.1.

6.4.2.

PS 6.5
6.5.1.

6.5.2.

Memasang 1 buah kloset duduk/monoblok


Bahan
Klosed duduk/monoblok
1.000 Bh x Rp. 1,756,700 = Rp.
Perlengkapan
6%
harga klosed x Rp. 1,756,700 = Rp.
Jumlah (1) = Rp.
Tenaga
Pekerja
3.300 Oh x Rp.
45,000 = Rp.
Tukang batu
1.500 Oh x Rp.
65,000 = Rp.
Kepala tukang
0.150 Oh x Rp.
75,000 = Rp.
Mandor
0.160 Oh x Rp.
55,000 = Rp.
Jumlah (2) = Rp.
Jumlah (1) +(2)
= Rp.
Memasang 1 buah kloset jongkok porselen
Bahan
Klosed jongkok porselin
1.000 Bh x Rp. 204,820 = Rp.
Semen portland
6.000 Kg x Rp.
1,200 = Rp.
Pasir pasang
0.010 M x Rp.
94,500 = Rp.
Jumlah (1) = Rp.
Tenaga
Pekerja
1.100 Oh x Rp.
45,000 = Rp.
Tukang batu
1.500 Oh x Rp.
65,000 = Rp.
Kepala tukang
0.150 Oh x Rp.
75,000 = Rp.
Mandor
0.110 Oh x Rp.
55,000 = Rp.
Jumlah (2) = Rp.
Jumlah (1) +(2)
= Rp.
Memasang 1 buah kloset jongkok teraso
Bahan
Klosed jongkok teraso
1.000 Bh x Rp. 478,500 = Rp.
Bata merah 5x10x20 cm
7.000 Bh x Rp.
450 = Rp.
Semen portland
6.000 Kg x Rp.
1,200 = Rp.
Pasir pasang
0.010 M x Rp.
94,500 = Rp.
Jumlah (1) = Rp.
Tenaga
Pekerja
1.000 Oh x Rp.
45,000 = Rp.
Tukang batu
1.500 Oh x Rp.
65,000 = Rp.
Kepala tukang
0.150 Oh x Rp.
75,000 = Rp.
Mandor
0.100 Oh x Rp.
55,000 = Rp.
Jumlah (2) = Rp.
Jumlah (1) +(2)
= Rp.
Memasang 1 buah urinoir
Bahan
Urinoir
1.000 Bh x Rp. 506,880 = Rp.
Perlengkapan
15%
harga urinoir x Rp. 506,880 = Rp.
Semen portland
6.000 Kg x Rp.
1,200 = Rp.
Pasir pasang
0.010 M x Rp.
94,500 = Rp.
Jumlah (1) = Rp.
Tenaga
Pekerja
1.000 Oh x Rp.
45,000 = Rp.
Tukang batu
1.000 Oh x Rp.
65,000 = Rp.
Kepala tukang
0.100 Oh x Rp.
75,000 = Rp.
Mandor
0.100 Oh x Rp.
55,000 = Rp.
Jumlah (2) = Rp.
Jumlah (1) +(2)
= Rp.
Memasang 1 buah wastafel
Bahan
Wastafel
1.000 Bh x Rp. 478,500 = Rp.
Perlengkapan
12% harga wastafel x Rp. 478,500 = Rp.
Semen portland
6.000 Kg x Rp.
1,200 = Rp.
Pasir pasang
0.010 M x Rp.
94,500 = Rp.
Jumlah (1) = Rp.
Tenaga
Pekerja
1.200 Oh x Rp.
45,000 = Rp.
Tukang batu
1.450 Oh x Rp.
65,000 = Rp.
Kepala tukang
0.150 Oh x Rp.
75,000 = Rp.
Mandor
0.100 Oh x Rp.
55,000 = Rp.
Jumlah (2) = Rp.
Jumlah (1) +(2)
= Rp.

1,756,700.00
105,402.00
1,862,102.00
148,500.00
97,500.00
11,250.00
8,800.00
266,050.00
2,128,152.00

204,820.00
7,200.00
945.00
212,965.00
49,500.00
97,500.00
11,250.00
6,050.00
164,300.00
377,265.00

478,500.00
3,150.00
7,200.00
945.00
489,795.00
45,000.00
97,500.00
11,250.00
5,500.00
159,250.00
649,045.00

506,880.00
76,032.00
7,200.00
945.00
591,057.00
45,000.00
65,000.00
7,500.00
5,500.00
123,000.00
714,057.00

478,500.00
57,420.00
7,200.00
945.00
544,065.00
54,000.00
94,250.00
11,250.00
5,500.00
165,000.00
709,065.00

PS 6.6.
6.6.1.

6.6.2.

PS 6.7.
6.7.1.

6.7.2.

PS 6.8.
6.8.1.

6.8.2.

PS 6.9.
6.9.1.

6.9.2.

Memasang 1 buah bak mandi teraso volume 0,30 m


Bahan
Bak teraso
1.000 Bh x Rp. 165,000 = Rp.
Semen portland
6.000 Kg x Rp.
1,200 = Rp.
Pasir pasang
0.010 M x Rp.
94,500 = Rp.
Jumlah (1) = Rp.
Tenaga
Pekerja
2.100 Oh x Rp.
45,000 = Rp.
Tukang batu
0.750 Oh x Rp.
65,000 = Rp.
Kepala tukang
0.075 Oh x Rp.
75,000 = Rp.
Mandor
0.110 Oh x Rp.
55,000 = Rp.
Jumlah (2) = Rp.
Jumlah (1) +(2)
= Rp.
Memasang 1 buah bak mandi fibreglass volume 0,30 m
Bahan
Bak fibreglass
1.000 Bh x Rp. 165,000 = Rp.
Perlengkapan
18%
Harga bak x Rp. 165,000 = Rp.
Jumlah (1) = Rp.
Tenaga
Pekerja
1.800 Oh x Rp.
45,000 = Rp.
Tukang batu
0.540 Oh x Rp.
65,000 = Rp.
Kepala tukang
0.054 Oh x Rp.
75,000 = Rp.
Mandor
0.110 Oh x Rp.
55,000 = Rp.
Jumlah (2) = Rp.
Jumlah (1) +(2)
= Rp.
Memasang 1 buah bak mandi batu bata volume 0,30 m
Bahan
Batu bata
44.000 Bh x Rp.
650 = Rp.
Semen portland
120.000 Kg x Rp.
1,200 = Rp.
Pasir pasang
0.300 M x Rp.
94,500 = Rp.
Porselin (11x11) cm
360.000 Bh x Rp.
1,320 = Rp.
Semen putih
6.000 Kg x Rp.
2,350 = Rp.
Jumlah (1) = Rp.
Tenaga
Pekerja
3.000 Oh x Rp.
45,000 = Rp.
Tukang batu
3.000 Oh x Rp.
65,000 = Rp.
Kepala tukang
0.300 Oh x Rp.
75,000 = Rp.
Mandor
0.300 Oh x Rp.
55,000 = Rp.
Jumlah (2) = Rp.
Jumlah (1) +(2)
= Rp.

Memasang 1 buah badkip porselin


Bahan
Badkip
1.000 Bh x Rp. 2,750,000 = Rp.
Perlengkapan
20%
Harga badkip x Rp. 2,750,000 = Rp.
Jumlah (1) = Rp.
Tenaga
Pekerja
2.500 Oh x Rp.
45,000 = Rp.
Tukang batu
0.750 Oh x Rp.
65,000 = Rp.
Kepala tukang
0.075 Oh x Rp.
75,000 = Rp.
Mandor
0.250 Oh x Rp.
55,000 = Rp.
Jumlah (2) = Rp.
Jumlah (1) +(2)
= Rp.

PS 6.10. Memasang 1 buah bak beton volume 1 m air


6.10.1. Bahan
Beton 1 : 1 : 2
0.900 M x
Besi beton
180.000 Kg x
Kayu cetakan
0.096 M x
Ubin porselin
420.000 Bh' x
Perlengkapan
10% Hrg total bahan x
6.10.2. Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

3.500
4.500
0.900
0.900

Oh
Oh
Oh
Oh

x
x
x
x

165,000.00
7,200.00
945.00
173,145.00
94,500.00
48,750.00
5,625.00
6,050.00
154,925.00
328,070.00

165,000.00
29,700.00
194,700.00
81,000.00
35,100.00
4,050.00
6,050.00
126,200.00
320,900.00

28,600.00
144,000.00
28,350.00
475,200.00
14,100.00
690,250.00
135,000.00
195,000.00
22,500.00
16,500.00
369,000.00
1,059,250.00

2,750,000.00
550,000.00
3,300,000.00
112,500.00
48,750.00
5,625.00
13,750.00
180,625.00
3,480,625.00

Rp.
12,500 = Rp.
Rp.
12,390 = Rp.
Rp. 3,144,900 = Rp.
Rp.
1,320 = Rp.
Rp. 3,097,760 = Rp.
Jumlah (1) = Rp.

11,250.00
2,230,200.00
301,910.40
554,400.00
309,776.04
3,407,536.44

Rp.
Rp.
Rp.
Rp.

157,500.00
292,500.00
67,500.00
49,500.00
567,000.00
3,974,536.44

45,000 = Rp.
65,000 = Rp.
75,000 = Rp.
55,000 = Rp.
Jumlah (2) = Rp.
Jumlah (1) +(2)
= Rp.

PS 6.11. Memasang 1 buah bak fibreglass volume 1 m air


6.11.1. Bahan
Bak fibreglass
1.000 Bh x Rp.
Perlengkapan
12%
Harga bak x Rp.
6.11.2. Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

PS 6.15.
6.15.1.

6.15.2.

PS 6.16.
6.16.1.

6.16.2.

PS 6.17.
6.17.1.

6.17.2.

PS 6.18.
6.18.1.

6.18.2.

3.000
4.500
0.900
0.900

Oh
Oh
Oh
Oh

x
x
x
x

Rp.
Rp.
Rp.
Rp.

165,000 = Rp.
165,000 = Rp.
Jumlah (1) = Rp.

165,000.00
19,800.00
184,800.00

45,000 = Rp.
135,000.00
65,000 = Rp.
292,500.00
75,000 = Rp.
67,500.00
55,000 = Rp.
49,500.00
Jumlah (2) = Rp.
544,500.00
Jumlah (1) +(2)
= Rp.
729,300.00
Memasang 1 m' pipa beton, diameter 30 cm - 100 cm
Bahan
Pipa beton
1.100 Bh x Rp.
51,150 = Rp.
56,265.00
Batu bata
55.000 Bh x Rp.
650 = Rp.
35,750.00
Semen portland
10.300 Kg x Rp.
1,200 = Rp.
12,360.00
Pasir pasang
0.061 M x Rp.
94,500 = Rp.
5,764.50
Pasir urug
0.069 M x Rp.
65,200 = Rp.
4,498.80
Jumlah (1) = Rp.
114,638.30
Tenaga
Pekerja
0.380 Oh x Rp.
45,000 = Rp.
17,100.00
Tukang batu
0.190 Oh x Rp.
65,000 = Rp.
12,350.00
Kepala tukang
0.019 Oh x Rp.
75,000 = Rp.
1,425.00
Mandor
0.019 Oh x Rp.
55,000 = Rp.
1,045.00
Jumlah (2) = Rp.
31,920.00
Jumlah (1) +(2)
= Rp.
146,558.30
Memasang 1 buah Bak Kontrol pasangan batu bata uk.(30 x 30) cm tinggi 35 cm
Bahan
Batu bata
145.000 Bh x Rp.
650 = Rp.
94,250.00
Semen portland
44.000 Kg x Rp.
1,200 = Rp.
52,800.00
Pasir pasang
0.070 M x Rp.
94,500 = Rp.
6,615.00
Batu kerikil
0.070 M x Rp. 175,890 = Rp.
12,312.30
Besi beton
1.600 Kg x Rp.
12,390 = Rp.
19,824.00
Pasir beton
0.060 M x Rp.
95,760 = Rp.
5,745.60
Jumlah (1) = Rp.
191,546.90
Tenaga
Pekerja
3.200 Oh x Rp.
45,000 = Rp.
144,000.00
Tukang batu
1.015 Oh x Rp.
65,000 = Rp.
65,975.00
Kepala tukang
0.0015 Oh x Rp.
75,000 = Rp.
112.50
Mandor
0.016 Oh x Rp.
55,000 = Rp.
880.00
Jumlah (2) = Rp.
210,967.50
Jumlah (1) +(2)
= Rp.
402,514.40
Memasang 1 buah Bak Kontrol pasangan batu bata uk.(45 x 45) cm tinggi 50 cm
Bahan
Batu bata
250.000 Bh x Rp.
650 = Rp.
162,500.00
Semen portland
77.000 Kg x Rp.
1,200 = Rp.
92,400.00
Pasir pasang
0.130 M x Rp.
94,500 = Rp.
12,285.00
Batu kerikil
0.020 M x Rp. 175,890 = Rp.
3,517.80
Besi beton
2.600 Kg x Rp.
12,390 = Rp.
32,214.00
Pasir beton
0.090 M x Rp.
95,760 = Rp.
8,618.40
Jumlah (1) = Rp.
311,535.20
Tenaga
Pekerja
1.420 Oh x Rp.
45,000 = Rp.
63,900.00
Tukang batu
0.473 Oh x Rp.
65,000 = Rp.
30,745.00
Kepala tukang
0.047 Oh x Rp.
75,000 = Rp.
3,525.00
Mandor
0.071 Oh x Rp.
55,000 = Rp.
3,905.00
Jumlah (2) = Rp.
102,075.00
Jumlah (1) +(2)
= Rp.
413,610.20
Memasang 1 buah Bak Kontrol pasangan batu bata uk.(60 x 60) cm tinggi 65 cm
Bahan
Batu bata
371.000 Bh x Rp.
650 = Rp.
241,150.00
Semen portland
114.000 Kg x Rp.
1,200 = Rp.
136,800.00
Pasir pasang
0.184 M x Rp.
94,500 = Rp.
17,388.00
Batu koral
0.033 M x Rp. 175,890 = Rp.
5,804.37
Besi beton
4.850 Kg x Rp.
12,390 = Rp.
60,091.50
Pasir beton
0.120 M x Rp.
95,760 = Rp.
11,491.20
Jumlah (1) = Rp.
472,725.07
Tenaga
Pekerja
2.160 Oh x Rp.
45,000 = Rp.
97,200.00
Tukang batu
0.720 Oh x Rp.
65,000 = Rp.
46,800.00
Kepala tukang
0.072 Oh x Rp.
75,000 = Rp.
5,400.00
Mandor
0.108 Oh x Rp.
55,000 = Rp.
5,940.00
Tukang gali
0.100 Oh x Rp.
45,000 = Rp.
4,500.00
Jumlah (2) = Rp.
159,840.00
Jumlah (1) +(2)
= Rp.
632,565.07

PS 6.19. Memasang 1 m' pipa galvanis diameter "


6.19.1. Bahan
Pipa galvanis
1.200 M x Rp.
Perlengkapan
35%
harga pipa x Rp.
6.19.2. Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

0.054
0.090
0.009
0.027

Oh
Oh
Oh
Oh

x
x
x
x

Rp.
Rp.
Rp.
Rp.

PS 6.20. Memasang 1 m' pipa galvanis diameter 3/4"


6.20.1. Bahan
Pipa galvanis
1.200 M x Rp.
Perlengkapan
35%
harga pipa x Rp.
6.20.2. Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

0.054
0.090
0.009
0.027

Oh
Oh
Oh
Oh

x
x
x
x

Rp.
Rp.
Rp.
Rp.

PS 6.21. Memasang 1 m' pipa galvanis diameter 1"


6.21.1. Bahan
Pipa galvanis
1.200 M x Rp.
Perlengkapan
35%
harga pipa x Rp.
6.21.2. Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

0.054
0.090
0.009
0.027

Oh
Oh
Oh
Oh

x
x
x
x

Rp.
Rp.
Rp.
Rp.

PS 6.22. Memasang 1 m' pipa galvanis diameter 1 "


6.22.1. Bahan
Pipa galvanis
1.200 M x Rp.
Perlengkapan
35%
harga pipa x Rp.
6.22.2. Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

0.108
0.180
0.018
0.0054

Oh
Oh
Oh
Oh

x
x
x
x

Rp.
Rp.
Rp.
Rp.

PS 6.23. Memasang 1 m' pipa galvanis diameter 2"


6.23.1. Bahan
Pipa galvanis
1.200 M x Rp.
Perlengkapan
35%
harga pipa x Rp.
6.23.2. Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

0.108
0.180
0.018
0.0054

Oh
Oh
Oh
Oh

x
x
x
x

Rp.
Rp.
Rp.
Rp.

PS 6.24. Memasang 1 m' pipa galvanis diameter 3"


6.24.1. Bahan
Pipa galvanis
1.200 M x Rp.
Perlengkapan
35%
harga pipa x Rp.
6.24.2. Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

0.108
0.180
0.018
0.0054

Oh
Oh
Oh
Oh

x
x
x
x

Rp.
Rp.
Rp.
Rp.

82,000 = Rp.
82,000 = Rp.
Jumlah (1) = Rp.

98,400.00
28,700.00
127,100.00

45,000 = Rp.
65,000 = Rp.
75,000 = Rp.
55,000 = Rp.
Jumlah (2) = Rp.
Jumlah (1) +(2)
= Rp.

2,430.00
5,850.00
675.00
1,485.00
10,440.00
137,540.00

115,000 = Rp.
115,000 = Rp.
Jumlah (1) = Rp.

138,000.00
40,250.00
178,250.00

45,000 = Rp.
65,000 = Rp.
75,000 = Rp.
55,000 = Rp.
Jumlah (2) = Rp.
Jumlah (1) +(2)
= Rp.

2,430.00
5,850.00
675.00
1,485.00
10,440.00
188,690.00

168,000 = Rp.
168,000 = Rp.
Jumlah (1) = Rp.

201,600.00
58,800.00
260,400.00

45,000 = Rp.
65,000 = Rp.
75,000 = Rp.
55,000 = Rp.
Jumlah (2) = Rp.
Jumlah (1) +(2)
= Rp.

2,430.00
5,850.00
675.00
1,485.00
10,440.00
270,840.00

215,000 = Rp.
215,000 = Rp.
Jumlah (1) = Rp.

258,000.00
75,250.00
333,250.00

45,000 = Rp.
65,000 = Rp.
75,000 = Rp.
55,000 = Rp.
Jumlah (2) = Rp.
Jumlah (1) +(2)
= Rp.

4,860.00
11,700.00
1,350.00
297.00
18,207.00
351,457.00

258,000 = Rp.
258,000 = Rp.
Jumlah (1) = Rp.

309,600.00
90,300.00
399,900.00

45,000 = Rp.
65,000 = Rp.
75,000 = Rp.
55,000 = Rp.
Jumlah (2) = Rp.
Jumlah (1) +(2)
= Rp.

4,860.00
11,700.00
1,350.00
297.00
18,207.00
418,107.00

286,000 = Rp.
286,000 = Rp.
Jumlah (1) = Rp.

343,200.00
100,100.00
443,300.00

45,000 = Rp.
65,000 = Rp.
75,000 = Rp.
55,000 = Rp.
Jumlah (2) = Rp.
Jumlah (1) +(2)
= Rp.

4,860.00
11,700.00
1,350.00
297.00
18,207.00
461,507.00

PS 6.25. Memasang 1 m' pipa PVC tipe AW diameter "


6.25.1. Bahan
Pipa PVC
1.200 M x Rp.
Perlengkapan
35%
harga pipa x Rp.
6.25.2. Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

0.036
0.060
0.006
0.0018

Oh
Oh
Oh
Oh

x
x
x
x

Rp.
Rp.
Rp.
Rp.

PS 6.26. Memasang 1 m' pipa PVC tipe AW diameter "


6.26.1. Bahan
Pipa PVC
1.200 M x Rp.
Perlengkapan
35%
harga pipa x Rp.
6.26.2. Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

0.036
0.060
0.006
0.0018

Oh
Oh
Oh
Oh

x
x
x
x

Rp.
Rp.
Rp.
Rp.

PS 6.27. Memasang 1 m' pipa PVC tipe AW diameter 1"


6.27.1. Bahan
Pipa PVC
1.200 M x Rp.
Perlengkapan
35%
harga pipa x Rp.
6.27.2. Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

0.036
0.060
0.006
0.0018

Oh
Oh
Oh
Oh

x
x
x
x

Rp.
Rp.
Rp.
Rp.

PS 6.28. Memasang 1 m' pipa PVC tipe AW diameter 1 "


6.28.1. Bahan
Pipa PVC
1.200 M x Rp.
Perlengkapan
35%
harga pipa x Rp.
6.28.2. Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

0.036
0.060
0.006
0.0018

Oh
Oh
Oh
Oh

x
x
x
x

Rp.
Rp.
Rp.
Rp.

PS 6.29. Memasang 1 m' pipa PVC tipe AW diameter 2"


6.29.1. Bahan
Pipa PVC
1.200 M x Rp.
Perlengkapan
35%
harga pipa x Rp.
6.29.2. Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

0.054
0.090
0.009
0.0027

Oh
Oh
Oh
Oh

x
x
x
x

Rp.
Rp.
Rp.
Rp.

PS 6.30. Memasang 1 m' pipa PVC tipe AW diameter 2 "


6.30.1. Bahan
Pipa PVC
1.200 M x Rp.
Perlengkapan
35%
harga pipa x Rp.
6.30.2. Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

0.036
0.060
0.006
0.0018

Oh
Oh
Oh
Oh

x
x
x
x

Rp.
Rp.
Rp.
Rp.

30,250 = Rp.
30,250 = Rp.
Jumlah (1) = Rp.

36,300.00
10,587.50
46,887.50

45,000 = Rp.
65,000 = Rp.
75,000 = Rp.
55,000 = Rp.
Jumlah (2) = Rp.
Jumlah (1) +(2)
= Rp.

1,620.00
3,900.00
450.00
99.00
6,069.00
52,956.50

40,535 = Rp.
40,535 = Rp.
Jumlah (1) = Rp.

48,642.00
14,187.25
62,829.25

45,000 = Rp.
65,000 = Rp.
75,000 = Rp.
55,000 = Rp.
Jumlah (2) = Rp.
Jumlah (1) +(2)
= Rp.

1,620.00
3,900.00
450.00
99.00
6,069.00
68,898.25

67,500 = Rp.
67,500 = Rp.
Jumlah (1) = Rp.

81,000.00
23,625.00
104,625.00

45,000 = Rp.
65,000 = Rp.
75,000 = Rp.
55,000 = Rp.
Jumlah (2) = Rp.
Jumlah (1) +(2)
= Rp.

1,620.00
3,900.00
450.00
99.00
6,069.00
110,694.00

97,500 = Rp.
97,500 = Rp.
Jumlah (1) = Rp.

117,000.00
34,125.00
151,125.00

45,000 = Rp.
65,000 = Rp.
75,000 = Rp.
55,000 = Rp.
Jumlah (2) = Rp.
Jumlah (1) +(2)
= Rp.

1,620.00
3,900.00
450.00
99.00
6,069.00
157,194.00

115,000 = Rp.
115,000 = Rp.
Jumlah (1) = Rp.

138,000.00
40,250.00
178,250.00

45,000 = Rp.
65,000 = Rp.
75,000 = Rp.
55,000 = Rp.
Jumlah (2) = Rp.
Jumlah (1) +(2)
= Rp.

2,430.00
5,850.00
675.00
148.50
9,103.50
187,353.50

132,000 = Rp.
132,000 = Rp.
Jumlah (1) = Rp.

158,400.00
46,200.00
204,600.00

45,000 = Rp.
65,000 = Rp.
75,000 = Rp.
55,000 = Rp.
Jumlah (2) = Rp.
Jumlah (1) +(2)
= Rp.

1,620.00
3,900.00
450.00
99.00
6,069.00
210,669.00

PS 6.31. Memasang 1 m' pipa PVC tipe AW diameter 3"


6.31.1. Bahan
Pipa PVC
1.200 M x Rp.
Perlengkapan
35%
harga pipa x Rp.
6.31.2. Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

153,000 = Rp.
153,000 = Rp.
Jumlah (1) = Rp.

183,600.00
53,550.00
237,150.00

45,000 = Rp.
65,000 = Rp.
75,000 = Rp.
55,000 = Rp.
Jumlah (2) = Rp.
Jumlah (1) +(2)
= Rp.

3,645.00
8,775.00
1,012.50
225.50
13,658.00
250,808.00

257,000 = Rp.
257,000 = Rp.
Jumlah (1) = Rp.

308,400.00
89,950.00
398,350.00

45,000 = Rp.
65,000 = Rp.
75,000 = Rp.
55,000 = Rp.
Jumlah (2) = Rp.
Jumlah (1) +(2)
= Rp.

3,645.00
8,775.00
1,012.50
225.50
13,658.00
412,008.00

424,270 = Rp.
15,000 = Rp.
Jumlah (1) = Rp.

424,270.00
15,000.00
439,270.00

45,000 = Rp.
65,000 = Rp.
75,000 = Rp.
55,000 = Rp.
Jumlah (2) = Rp.
Jumlah (1) +(2)
= Rp.

1,350.00
19,500.00
2,250.00
82.50
23,182.50
462,452.50

Bh x Rp.
Bh x Rp.
Kg x Rp.
M x Rp.

247,500
15,000
1,200
94,500
Jumlah (1)

Rp.
Rp.
Rp.
Rp.
Rp.

247,500.00
15,000.00
24,000.00
4,725.00
291,225.00

Oh
Oh
Oh
Oh

45,000 = Rp.
65,000 = Rp.
75,000 = Rp.
55,000 = Rp.
Jumlah (2) = Rp.
Jumlah (1) +(2)
= Rp.

2,250.00
32,500.00
3,750.00
137.50
38,637.50
329,862.50

24,860 = Rp.
84,150 = Rp.
Jumlah (1) = Rp.

24,860.00
2,103.75
26,963.75

Rp.
Rp.
Rp.
Rp.

45,000 = Rp.
65,000 = Rp.
75,000 = Rp.
55,000 = Rp.
Jumlah (2)
Jumlah (1) +(2)

450.00
6,500.00
750.00
275.00
7,975.00
34,938.75

1.000 Bh x Rp.

15,000 = Rp.
Jumlah (1) = Rp.

15,000.00
15,000.00

0.010
0.100
0.010
0.005

45,000 = Rp.
65,000 = Rp.
75,000 = Rp.
55,000 = Rp.
Jumlah (2)
Jumlah (1) +(2)

450.00
6,500.00
750.00
275.00
7,975.00
22,975.00

0.081
0.135
0.0135
0.0041

Oh
Oh
Oh
Oh

x
x
x
x

Rp.
Rp.
Rp.
Rp.

PS 6.32. Memasang 1 m' pipa PVC tipe AW diameter 4"


6.32.1. Bahan
Pipa PVC
1.200 M x Rp.
Perlengkapan
35%
harga pipa x Rp.
6.32.2. Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

0.081
0.135
0.0135
0.0041

Oh
Oh
Oh
Oh

x
x
x
x

Rp.
Rp.
Rp.
Rp.

PS 6.33. Memasang 1 bh bak cuci piring stainles steel


6.33.1. Bahan
Bak cuci stainless steel
1.000 Bh x Rp.
Water drain asesories
1.000 Set x Rp.
6.33.2. Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

0.030
0.300
0.030
0.0015

PS 6.34. Memasang 1 bh bak cuci piring teraso


6.34.1. Bahan
Bak cuci teraso
1.000
Water drain + asesories
1.000
Semen portland
20.000
Pasir
0.050
6.34.2. Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

0.050
0.500
0.050
0.0025

Oh
Oh
Oh
Oh

x
x
x
x

x
x
x
x

Rp.
Rp.
Rp.
Rp.

Rp.
Rp.
Rp.
Rp.

PS 6.35. Memasang 1 bh kran diameter " atau "


6.35.1. Bahan
Kran air
1.000 Bh x Rp.
Seal tape
0.025 Bh x Rp.
6.35.2. Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

PS 6.36. Memasang 1 bh Floor drain


6.36.1. Bahan
Floor drain
6.36.2. Tenaga
Pekerja
Tukang batu
Kepala tukang
Mandor

0.010
0.100
0.010
0.005

Oh
Oh
Oh
Oh

Oh
Oh
Oh
Oh

x
x
x
x

x
x
x
x

BERSAMBUNG : .ABK PEKER BESI DAN ALUMINIUM

Rp.
Rp.
Rp.
Rp.

=
=
=
=
=

ANALISA BIAYA KONSTRUKSI


PEKERJAAN BESI DAN ALUMINIUM

PBA 6.1
6.1.1

1 Kg Pasang rangka atap baja


Bahan
Besi profil WF
Meni besi

6.1.2. Tenaga
Tukang besi
Pekerja
Kepala tukang
Mandor

PBA 6.2
6.2.1

1 M Pasang pintu besi baja


Bahan
Pintu besi baja

6.2.2. Tenaga
Tukang besi konstruksi
Pekerja
Kepala tukang
Mandor

PBA 6.3
6.3.1

1 M Pasang jendela besi


Bahan
Jendela besi

6.3.2. Tenaga
Tukang besi konstruksi
Pekerja
Kepala tukang
Mandor

PBA 6.5
6.5.1

1 M Pasang pintu gulung besi


Bahan
Pintu gulung besi

6.5.2. Tenaga
Tukang besi konstruksi
Pekerja
Kepala tukang
Mandor

PBA 6.6
6.6.1

1 M Pasang pintu lipat


Bahan
Pintu lipat

6.6.2. Tenaga
Tukang besi konstruksi
Pekerja
Kepala tukang
Mandor

PBA 6.7
6.7.1

1.100 Kg
0.080 Kg

0.006
0.060
0.006
0.0003

Oh
Oh
Oh
Oh

12,390 = Rp.
43,890 = Rp.
Jumlah (1)
= Rp.

13,629.00
3,511.20
17,140.20

x
x
x
x

65,000
45,000
75,000
55,000
Jumlah (2)
Jumlah (1) +(2)

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

390.00
2,700.00
450.00
16.50
3,556.50
20,696.70

Rp.
Rp.
Rp.
Rp.

=
=
=
=
=
=

1.000 M

x Rp.

458,850 = Rp.
Jumlah (1)
= Rp.

458,850.00
458,850.00

0.650
0.650
0.065
0.032

x
x
x
x

65,000
45,000
75,000
55,000
Jumlah (2)
Jumlah (1) +(2)

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

42,250.00
29,250.00
4,875.00
1,760.00
78,135.00
536,985.00

x Rp.

316,250 = Rp.
Jumlah (1)
= Rp.

316,250.00
316,250.00

x
x
x
x

65,000
45,000
75,000
55,000
Jumlah (2)
Jumlah (1) +(2)

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

68,250.00
47,250.00
7,875.00
288.75
123,663.75
439,913.75

Oh
Oh
Oh
Oh

1.000 M

1.050
1.050
0.105
0.00525

Oh
Oh
Oh
Oh

Rp.
Rp.
Rp.
Rp.

Rp.
Rp.
Rp.
Rp.

=
=
=
=
=
=

=
=
=
=
=
=

1.000 M

x Rp.

500,250 = Rp.
Jumlah (1)
= Rp.

500,250.00
500,250.00

1.200
1.200
0.120
0.006

x
x
x
x

65,000
45,000
75,000
55,000
Jumlah (2)
Jumlah (1) +(2)

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

78,000.00
54,000.00
9,000.00
330.00
141,330.00
641,580.00

x Rp.

517,500 = Rp.
Jumlah (1)
= Rp.

517,500.00
517,500.00

x
x
x
x

65,000
45,000
75,000
55,000
Jumlah (2)
Jumlah (1) +(2)

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

68,250.00
47,250.00
7,875.00
286.00
123,661.00
641,161.00

x Rp.

488,750 = Rp.
Jumlah (1)
= Rp.

488,750.00
488,750.00

x
x
x
x

65,000
45,000
75,000
55,000
Jumlah (2)
Jumlah (1) +(2)

52,000.00
3,600.00
6,000.00
220.00
61,820.00
550,570.00

Oh
Oh
Oh
Oh

1.000 M

1.050
1.050
0.105
0.0052

Oh
Oh
Oh
Oh

1 M Pasang pintu Sunscreen alluminium


Bahan
Sunscreen alluminium
1.000 M

6.7.2. Tenaga
Tukang besi konstruksi
Pekerja
Kepala tukang
Mandor

x Rp.
x Rp.

0.800
0.080
0.080
0.004

Oh
Oh
Oh
Oh

Rp.
Rp.
Rp.
Rp.

Rp.
Rp.
Rp.
Rp.

Rp.
Rp.
Rp.
Rp.

=
=
=
=
=
=

=
=
=
=
=
=

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

PBA 6.8
6.8.1

1 M Pasang Rolling door


Bahan
Roll door

6.8.2. Tenaga
Tukang besi konstruksi
Pekerja
Kepala tukang
Mandor

PBA 6.9
6.9.1

1 M Pasang pintu alluminium


Bahan
Pintu alluminium

6.9.2. Tenaga
Tukang besi konstruksi
Pekerja
Kepala tukang
Mandor

PBA 6.10 1 M Pasang Venetions blinds


6.10.1 Bahan
Venetions blinds
6.10.2. Tenaga
Tukang kayu
Pekerja
Kepala tukang
Mandor

PBA 6.11 1 M Pasang Vertikals blinds


6.11.1 Bahan
Vertikals blinds
6.11.2. Tenaga
Tukang kayu
Pekerja
Kepala tukang
Mandor

PBA 6.12 1 M Pasang terali besi


6.12.1 Bahan
Besi strip 2 x 3
6.12.2. Tenaga
Tukang las
Pekerja
Kepala tukang
Mandor

PBA 6.13 1 M Pasang kawat harmonika


6.13.1 Bahan
Kawat harmonika
Paku biasa " - 1"
Kayu Meranti
6.13.2. Tenaga
Pekerja
Tukang kayu
Kepala tukang
Mandor

1.000 M

1.500
1.050
0.105
0.0052

Oh
Oh
Oh
Oh

1.000 M

1.050
1.050
0.105
0.0052

Oh
Oh
Oh
Oh

1.000 M

0.350
0.350
0.035
0.00175

Oh
Oh
Oh
Oh

1.000 M

0.350
0.350
0.035
0.00175

Oh
Oh
Oh
Oh

x Rp.

477,250 = Rp.
Jumlah (1)
= Rp.

477,250.00
477,250.00

x
x
x
x

65,000
45,000
75,000
55,000
Jumlah (2)
Jumlah (1) +(2)

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

97,500.00
47,250.00
7,875.00
286.00
152,911.00
630,161.00

x Rp.

546,250 = Rp.
Jumlah (1)
= Rp.

546,250.00
546,250.00

x
x
x
x

65,000
45,000
75,000
55,000
Jumlah (2)
Jumlah (1) +(2)

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

68,250.00
47,250.00
7,875.00
286.00
123,661.00
669,911.00

x Rp.

146,625 = Rp.
Jumlah (1)
= Rp.

146,625.00
146,625.00

x
x
x
x

61,775
45,000
75,000
55,000
Jumlah (2)
Jumlah (1) +(2)

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

21,621.25
15,750.00
2,625.00
96.25
40,092.50
186,717.50

x Rp.

155,250 = Rp.
Jumlah (1)
= Rp.

155,250.00
155,250.00

x
x
x
x

61,775
45,000
75,000
55,000
Jumlah (2)
Jumlah (1) +(2)

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

21,621.25
15,750.00
2,625.00
96.25
40,092.50
195,342.50

Rp.
Rp.
Rp.
Rp.

Rp.
Rp.
Rp.
Rp.

Rp.
Rp.
Rp.
Rp.

Rp.
Rp.
Rp.
Rp.

=
=
=
=
=
=

=
=
=
=
=
=

=
=
=
=
=
=

=
=
=
=
=
=

11.500 Kg

x Rp.

12,620 = Rp.
Jumlah (1)
= Rp.

145,130.00
145,130.00

1.200
1.200
0.012
0.0006

x
x
x
x

Rp.
Rp.
Rp.
Rp.

61,775
45,000
75,000
55,000
Jumlah (2)
Jumlah (1) +(2)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

74,130.00
54,000.00
900.00
33.00
129,063.00
274,193.00

1.100 M
0.020 Kg
0.0018 M

x Rp.
x Rp.
x Rp.

35,080
10,930
5,131,500
Jumlah (1)

=
=
=
=

Rp.
Rp.
Rp.
Rp.

38,588.00
218.60
9,236.70
48,043.30

0.100
0.100
0.010
0.0005

x
x
x
x

45,000
65,000
75,000
55,000
Jumlah (2)
Jumlah (1) +(2)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

4,500.00
6,500.00
750.00
27.50
11,777.50
59,820.80

Oh
Oh
Oh
Oh

Oh
Oh
Oh
Oh

Rp.
Rp.
Rp.
Rp.

PBA 6.14 1 M Pasang kawat nyamuk


6.14.1 Bahan
Kawat nyamuk
Paku biasa " - 1"
Kayu Meranti
6.14.2. Tenaga
Pekerja
Tukang kayu
Kepala tukang
Mandor

PBA 6.15 1 M Pasang kawat kassa


6.15.1 Bahan
Kawat kassa
Paku biasa " - 1"
Kayu Meranti
6.15.2. Tenaga
Pekerja
Tukang kayu
Kepala tukang
Mandor

PBA 6.16 1 M Pasang kawat burung


6.15.1 Bahan
Kawat burung
Paku biasa " - 1"
Kayu Meranti

6.15.2. Tenaga
Pekerja
Tukang kayu
Kepala tukang
Mandor

1.100 M
0.020 Kg
0.0018 M

x Rp.
x Rp.
x Rp.

12,240
10,930
5,131,500
Jumlah (1)

=
=
=
=

Rp.
Rp.
Rp.
Rp.

13,464.00
218.60
9,236.70
22,919.30

0.100
0.100
0.010
0.0005

x
x
x
x

Rp.
Rp.
Rp.
Rp.

45,000
65,000
75,000
55,000
Jumlah (2)
Jumlah (1) +(2)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

4,500.00
6,500.00
750.00
27.50
11,777.50
34,696.80

1.100 M
0.020 Kg
0.0018 M

x Rp.
x Rp.
x Rp.

31,630
10,930
5,131,500
Jumlah (1)

=
=
=
=

Rp.
Rp.
Rp.
Rp.

34,793.00
218.60
9,236.70
44,248.30

0.100
0.100
0.010
0.0005

x
x
x
x

Rp.
Rp.
Rp.
Rp.

45,000
65,000
75,000
55,000
Jumlah (2)
Jumlah (1) +(2)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

4,500.00
6,500.00
750.00
27.50
11,777.50
56,025.80

1.100 M
0.020 Kg
0.0018 M

x Rp.
x Rp.
x Rp.

31,625
10,930
5,131,500
Jumlah (1)

=
=
=
=

Rp.
Rp.
Rp.
Rp.

34,787.50
218.60
9,236.70
44,242.80

0.100
0.100
0.010
0.0005

x
x
x
x

Rp.
Rp.
Rp.
Rp.

45,000
65,000
75,000
55,000
Jumlah (2)
Jumlah (1) +(2)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

4,500.00
6,500.00
750.00
27.50
11,777.50
56,020.30

x Rp.
x Rp.
x Rp.

171,100
10,930
12,620
Jumlah (1)

=
=
=
=

Rp.
Rp.
Rp.
Rp.

188,210.00
218.60
18,930.00
207,358.60

Oh
Oh
Oh
Oh

Oh
Oh
Oh
Oh

Oh
Oh
Oh
Oh

PBA 6.17 1 M Pasang jendela nako dan tralis


6.17.1 Bahan
Jendela nako
1.100 M
Paku biasa " - 1" atau skrup
0.020 Kg
Besi strip # 12 mm
1.500 Kg

6.17.2. Tenaga
Pekerja
Tukang kayu
Kepala tukang
Mandor

0.200
0.200
0.020
0.001

Oh
Oh
Oh
Oh

x
x
x
x

Rp.
Rp.
Rp.
Rp.

45,000
65,000
75,000
55,000
Jumlah (2)
Jumlah (1) +(2)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

9,000.00
13,000.00
1,500.00
55.00
23,555.00
230,913.60

PBA 6.18 1 M' Pasang talang datar, seng bjls 35


6.18.1 Bahan
Seng plat 3' x 6' bjls 35
0.500
Paku biasa " - 1" atau skrup
0.015
Kayu Meranti
0.0096
Flincote / meni besi
0.250

Lbr
Kg
M
Kg

x
x
x
x

Rp.
Rp.
Rp.
Rp.

105,000
10,930
5,131,500
43,890
Jumlah (1)

=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.

52,500.00
163.95
49,262.40
10,972.50
112,898.85

Oh
Oh
Oh
Oh

x
x
x
x

Rp.
Rp.
Rp.
Rp.

45,000
65,000
75,000
55,000
Jumlah (2)
Jumlah (1) +(2)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

6,750.00
26,000.00
1,875.00
68.75
34,693.75
147,592.60

6.18.2. Tenaga
Pekerja
Tukang kayu
Kepala tukang
Mandor

0.150
0.400
0.025
0.00125

PBA 6.19 1 M' Pasang talang miring, seng bjls 35


6.19.1 Bahan
Seng plat 3' x 6' bjls 35
0.500
Paku biasa " - 1" atau skrup
0.015
Kayu Meranti
0.019
Flincote / meni besi
0.300

6.19.2. Tenaga
Pekerja
Tukang kayu
Kepala tukang
Mandor

0.150
0.400
0.025
0.00125

Lbr
Kg
M
Kg

x
x
x
x

Rp.
Rp.
Rp.
Rp.

105,000
10,930
5,131,500
43,890
Jumlah (1)

=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.

52,500.00
163.95
97,498.50
13,167.00
163,329.45

Oh
Oh
Oh
Oh

x
x
x
x

Rp.
Rp.
Rp.
Rp.

45,000
65,000
75,000
55,000
Jumlah (2)
Jumlah (1) +(2)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

6,750.00
26,000.00
1,875.00
68.75
34,693.75
198,023.20

=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.

31,500.00
1,093.00
97,498.50
6,310.00
136,401.50

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

6,750.00
16,250.00
1,875.00
68.75
24,943.75
161,345.25

=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.

28,350.00
1,093.00
97,498.50
6,310.00
133,251.50

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

6,750.00
16,250.00
1,875.00
68.75
24,943.75
158,195.25

PBA 6.20 1 M' Pasang talang lingkaran D-10 cm, seng bjls 35
6.20.1 Bahan
Seng plat 3' x 6' bjls 35
0.300 Lbr x Rp.
105,000
Paku biasa " - 1" atau skrup
0.100 Kg x Rp.
10,930
Kayu Meranti
0.019 M x Rp.
5,131,500
Besi strip
0.500 Kg x Rp.
12,620
Jumlah (1)
6.20.2. Tenaga
Pekerja
0.150 Oh x Rp.
45,000
Tukang kayu
0.250 Oh x Rp.
65,000
Kepala tukang
0.025 Oh x Rp.
75,000
Mandor
0.00125 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) +(2)
PBA 6.21 1 M' Pasang talang lingkaran D-10 cm, seng bjls 30
6.21.1 Bahan
Seng plat 3' x 6' bjls 30
0.300 Lbr x Rp.
94,500
Paku biasa " - 1" atau skrup
0.100 Kg x Rp.
10,930
Kayu Meranti
0.019 M x Rp.
5,131,500
Besi strip
0.500 Kg x Rp.
12,620
Jumlah (1)
6.21.2. Tenaga
Pekerja
0.150 Oh x Rp.
45,000
Tukang kayu
0.250 Oh x Rp.
65,000
Kepala tukang
0.025 Oh x Rp.
75,000
Mandor
0.00125 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) +(2)
BERSAMBUNG :..

ABK PEKERJAAN KUNCI DAN KACA

ANALISA BIAYA KONSTRUKSI


PEKERJAAN LANGIT - LANGIT

PLL 6.1
6.1.1

6.1.2

PLL 6.2
6.2.1

6.2.2

PLL 6.3
6.3.1

6.3.2

PLL 6.4
6.4.1

6.4.2

PLL 6.5
6.5.1

6.5.2

1 M langit - langit asbes ( 1,00 x 1,00 ) m tebal 6 mm


Bahan
Pelat asbes tebal 6 mm
1.100 Lbr x Rp.
15,675
Paku
0.010 Kg x Rp.
10,930
Jumlah (1)
Tenaga
Pekerja
0.030 Oh x Rp.
45,000
Tukang kayu
0.070 Oh x Rp.
65,000
Kepala tukang
0.007 Oh x Rp.
75,000
Mandor
0.0015 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) +(2)
1 M langit - langit asbes ( 1,00 x 1,00 ) m tebal 5 mm
Bahan
Pelat asbes tebal 5 mm
1.100 Lbr x Rp.
13,062
Paku
0.010 Kg x Rp.
10,930
Jumlah (1)
Tenaga
Pekerja
0.030 Oh x Rp.
45,000
Tukang kayu
0.070 Oh x Rp.
65,000
Kepala tukang
0.007 Oh x Rp.
75,000
Mandor
0.0015 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) +(2)
1 M langit - langit asbes ( 1,00 x 1,00 ) m tebal 4 mm
Bahan
Pelat asbes tebal 4 mm
1.100 Lbr x Rp.
10,450
Paku
0.010 Kg x Rp.
10,930
Jumlah (1)
Tenaga
Pekerja
0.030 Oh x Rp.
45,000
Tukang kayu
0.070 Oh x Rp.
65,000
Kepala tukang
0.007 Oh x Rp.
75,000
Mandor
0.0015 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) +(2)
1 M langit - langit asbes ( 1,00 x 1,00 ) m tebal 3,5 mm
Bahan
Pelat asbes tebal 3,5 mm
1.100 Lbr x Rp.
8,250
Paku
0.010 Kg x Rp.
10,930
Jumlah (1)
Tenaga
Pekerja
0.030 Oh x Rp.
45,000
Tukang kayu
0.070 Oh x Rp.
65,000
Kepala tukang
0.007 Oh x Rp.
75,000
Mandor
0.0015 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) +(2)
1 M Langit - langit akustik ( 30 x 30 ) cm
Bahan
Akustik ukuran 30 x 30 cm
11.500 Lbr x Rp.
8,130
Paku
0.050 Kg x Rp.
10,930
Jumlah (1)
Tenaga
Pekerja
0.060 Oh x Rp.
45,000
Tukang kayu
0.120 Oh x Rp.
65,000
Kepala tukang
0.012 Oh x Rp.
75,000
Mandor
0.003 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) +(2)

= Rp.
= Rp.
= Rp.

17,242.50
109.30
17,351.80

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

1,350.00
4,550.00
525.00
82.50
6,507.50
23,859.30

= Rp.
= Rp.
= Rp.

14,368.20
109.30
14,477.50

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

1,350.00
4,550.00
525.00
82.50
6,507.50
20,985.00

= Rp.
= Rp.
= Rp.

11,495.00
109.30
11,604.30

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

1,350.00
4,550.00
525.00
82.50
6,507.50
18,111.80

= Rp.
= Rp.
= Rp.

9,075.00
109.30
9,184.30

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

1,350.00
4,550.00
525.00
82.50
6,507.50
15,691.80

= Rp.
= Rp.
= Rp.

93,495.00
546.50
94,041.50

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

2,700.00
7,800.00
900.00
165.00
11,565.00
105,606.50

PLL 6.6
6.6.1

6.6.2

PLL 6.7
6.7.1

6.7.2

PLL 6.8
6.8.1

6.8.2

PLL 6.9
6.9.1

6.9.2

1 M Langit - langit akustik ( 30 x 60 ) cm


Bahan
Akustik ukuran 30 x 60 cm
5.800 Lbr x Rp.
Paku
0.050 Kg x Rp.
Tenaga
Pekerja
Tukang kayu
Kepala tukang
Mandor

0.060
0.100
0.010
0.003

Oh
Oh
Oh
Oh

x
x
x
x

Rp.
Rp.
Rp.
Rp.

1 M Langit - langit akustik ( 60 x 120 ) cm


Bahan
Akustik arm strong.60/120 cm
1.500 Lbr x Rp.
Paku
0.050 Kg x Rp.
Tenaga
Pekerja
Tukang kayu
Kepala tukang
Mandor

0.060
0.100
0.010
0.003

Oh
Oh
Oh
Oh

x
x
x
x

Rp.
Rp.
Rp.
Rp.

16,120 = Rp.
10,930 = Rp.
Jumlah (1)
= Rp.
45,000
65,000
75,000
55,000
Jumlah (2)
Jumlah (1) +(2)

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

2,700.00
6,500.00
750.00
165.00
10,115.00
104,157.50

62,333 = Rp.
10,930 = Rp.
Jumlah (1)
= Rp.

93,499.50
546.50
94,046.00

45,000
65,000
75,000
55,000
Jumlah (2)
Jumlah (1) +(2)

1 M Langit - langit plywood ( 30 x 60 ) cm, tebal 4 mm


Bahan
Plywood 4' x 8' x 4 mm
0.360 Lbr x Rp.
64,520
Paku
0.030 Kg x Rp.
10,930
Jumlah (1)
Tenaga
Pekerja
0.070 Oh x Rp.
45,000
Tukang kayu
0.100 Oh x Rp.
65,000
Kepala tukang
0.010 Oh x Rp.
75,000
Mandor
0.0035 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) +(2)

1 M Langit - langit plywood ( 30 x 60 ) cm, tebal 6 mm


Bahan
Plywood 4' x 8' x 6 mm
0.360 Lbr x Rp.
102,410
Paku
0.030 Kg x Rp.
10,930
Jumlah (1)
Tenaga
Pekerja
0.070 Oh x Rp.
45,000
Tukang kayu
0.100 Oh x Rp.
65,000
Kepala tukang
0.010 Oh x Rp.
75,000
Mandor
0.0035 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) +(2)

PLL 6.10 1 M Langit - langit plywood ( 60 x 120 ) cm, tebal 4 mm


6.10.1 Bahan
Plywood 4' x 8' x 4 mm
0.375 Lbr x Rp.
64,520
Paku
0.030 Kg x Rp.
10,930
Jumlah (1)
6.10.2 Tenaga
Pekerja
0.070 Oh x Rp.
45,000
Tukang kayu
0.100 Oh x Rp.
65,000
Kepala tukang
0.010 Oh x Rp.
75,000
Mandor
0.0035 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) +(2)

=
=
=
=
=
=

93,496.00
546.50
94,042.50

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

2,700.00
6,500.00
750.00
165.00
10,115.00
104,161.00

= Rp.
= Rp.
= Rp.

23,227.20
327.90
23,555.10

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

3,150.00
6,500.00
750.00
192.50
10,592.50
34,147.60

= Rp.
= Rp.
= Rp.

36,867.60
327.90
37,195.50

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

3,150.00
6,500.00
750.00
192.50
10,592.50
47,788.00

= Rp.
= Rp.
= Rp.

24,195.00
327.90
24,522.90

=
=
=
=
=
=

3,150.00
6,500.00
750.00
192.50
10,592.50
35,115.40

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

PLL 6.11 1 M Langit - langit plywood ( 60 x 120 ) cm, tebal 6 mm


6.11.1 Bahan
Plywood 4' x 8' x 6 mm
0.375 Lbr x Rp.
102,410
Paku
0.030 Kg x Rp.
10,930
Jumlah (1)
6.11.2 Tenaga
Pekerja
0.070 Oh x Rp.
45,000
Tukang kayu
0.100 Oh x Rp.
65,000
Kepala tukang
0.010 Oh x Rp.
75,000
Mandor
0.0035 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) +(2)
PLL 6.12 1 M Langit - langit teakwood ( 30 x 60 ) cm, tebal 4 mm
6.12.1 Bahan
Teakwood 4' x 8' x 4 mm
0.360 Lbr x Rp.
96,250
Paku
0.030 Kg x Rp.
10,930
Jumlah (1)
6.12.2 Tenaga
Pekerja
0.070 Oh x Rp.
45,000
Tukang kayu
0.100 Oh x Rp.
65,000
Kepala tukang
0.010 Oh x Rp.
75,000
Mandor
0.0035 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) +(2)
PLL 6.13 1 M Langit - langit teakwood ( 60 x 120 ) cm, tebal 4 mm
6.13.1 Bahan
Teakwood 4' x 8' x 4 mm
0.375 Lbr x Rp.
96,250
Paku
0.030 Kg x Rp.
10,930
Jumlah (1)
6.13.2 Tenaga
Pekerja
0.070 Oh x Rp.
45,000
Tukang kayu
0.100 Oh x Rp.
65,000
Kepala tukang
0.010 Oh x Rp.
75,000
Mandor
0.0035 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) +(2)
PLL 6.14 1 M Langit - langit kayu jati
6.14.1 Bahan
Kayu jati, papan
Paku
Paku sekrup
6.14.2 Tenaga
Pekerja
Tukang kayu
Kepala tukang
Mandor

PLL 6.16 1 M Langit - langit papan rider


6.16.1 Bahan
Papan rider
Paku
Paku sekrup
6.16.2 Tenaga
Pekerja
Tukang kayu
Kepala tukang
Mandor

= Rp.
= Rp.
= Rp.

38,403.75
327.90
38,731.65

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

3,150.00
6,500.00
750.00
192.50
10,592.50
49,324.15

= Rp.
= Rp.
= Rp.

34,650.00
327.90
34,977.90

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

3,150.00
6,500.00
750.00
192.50
10,592.50
45,570.40

= Rp.
= Rp.
= Rp.

36,093.75
327.90
36,421.65

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

3,150.00
6,500.00
750.00
192.50
10,592.50
47,014.15

0.024 M x Rp.
0.010 Kg x Rp.
0.050 Kg x Rp.

21,913,130
10,930
17,250
Jumlah (1)

=
=
=
=

Rp.
Rp.
Rp.
Rp.

525,915.12
109.30
862.50
526,886.92

0.200
0.600
0.060
0.010

Rp.
Rp.
Rp.
Rp.

45,000
65,000
75,000
55,000
Jumlah (2)
Jumlah (1) +(2)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

9,000.00
39,000.00
4,500.00
550.00
53,050.00
579,936.92

2
1.000 M x Rp.
0.010 Kg x Rp.
0.050 Kg x Rp.

204,750
10,930
17,250
Jumlah (1)

=
=
=
=

Rp.
Rp.
Rp.
Rp.

204,750.00
109.30
862.50
205,721.80

0.200
0.600
0.060
0.010

45,000
65,000
75,000
55,000
Jumlah (2)
Jumlah (1) +(2)

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

9,000.00
39,000.00
4,500.00
550.00
53,050.00
258,771.80

Oh
Oh
Oh
Oh

Oh
Oh
Oh
Oh

x
x
x
x

x
x
x
x

Rp.
Rp.
Rp.
Rp.

PLL 6.17 1 M Langit - langit soft board


6.17.1 Bahan
Soft board 4' x 8' x 4 mm
Paku biasa
6.17.2 Tenaga
Pekerja
Tukang kayu
Kepala tukang
Mandor

PLL 6.18
6.18.1

6.18.2

PLL 6.19
6.19.1

6.19.2

0.350 Lbr x Rp.


0.030 Kg x Rp.

0.600
0.100
0.010
0.003

Oh
Oh
Oh
Oh

x
x
x
x

55,990 = Rp.
10,010 = Rp.
Jumlah (1)
= Rp.

Rp.
Rp.
Rp.
Rp.

45,000
65,000
75,000
55,000
Jumlah (2)
Jumlah (1) +(2)
1 M Langit - langit akustik 60 x 120 cm + rangka alluminium
Bahan
Profil alluminium "T"
3.600 M' x Rp.
8,050
Kawat seng polos
0.150 Kg x Rp.
21,410
Ramset/dina bolt
1.000 Bh x Rp.
650
Akustik arm strong 60/120 cm
1.500 Lbr x Rp.
62,333
Jumlah (1)
Tenaga
Pekerja
0.150 Oh x Rp.
45,000
Tukang kayu
0.500 Oh x Rp.
65,000
Kepala tukang
0.050 Oh x Rp.
75,000
Mandor
0.0075 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) +(2)
1 M' List Langit - langit Kayu profil 3"
Bahan
List kayu profil
1.100 M' x Rp.
17,100
Paku
0.010 Kg x Rp.
10,930
Jumlah (1)
Tenaga
Pekerja
0.050 Oh x Rp.
45,000
Tukang kayu
0.050 Oh x Rp.
65,000
Kepala tukang
0.005 Oh x Rp.
75,000
Mandor
0.003 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) +(2)

19,596.50
300.30
19,896.80

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

27,000.00
6,500.00
750.00
165.00
34,415.00
54,311.80

=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.

28,980.00
3,211.50
650.00
93,499.50
126,341.00

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

6,750.00
32,500.00
3,750.00
412.50
43,412.50
169,753.50

= Rp.
= Rp.
= Rp.

18,810.00
109.30
18,919.30

=
=
=
=
=
=

2,250.00
3,250.00
375.00
165.00
6,040.00
24,959.30

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

PLL 6.20 1 M Langit - langit asbes (1,00 x 1,00) m, tebal 3,2 mm, rangka Kayu Meranti
6.20.1 Bahan
Kayu Meranti
0.012 M x Rp.
5,131,500 = Rp.
61,578.00
Paku
0.060 Kg x Rp.
10,930 = Rp.
655.80
Asbes 1,00 x 1,00 m
1.100 Lbr x Rp.
10,450 = Rp.
11,495.00
Jumlah (1)
= Rp.
73,728.80
6.20.2 Tenaga
Pekerja
0.180 Oh x Rp.
45,000 = Rp.
8,100.00
Tukang kayu
0.320 Oh x Rp.
65,000 = Rp.
20,800.00
Kepala tukang
0.032 Oh x Rp.
75,000 = Rp.
2,400.00
Mandor
0.009 Oh x Rp.
55,000 = Rp.
495.00
Jumlah (2)
= Rp.
31,795.00
Jumlah (1) +(2) = Rp.
105,523.80
PLL 6.21 1 M Langit - langit plywood 4 mm + rangka kayu Meranti
6.21.1 Bahan
Kayu Meranti
0.023 M x Rp.
5,131,500
Paku biasa 2" - 5"
0.060 Kg x Rp.
10,930
Plywood 4' x 8' x 4 mm
0.390 Lbr x Rp.
64,520
Jumlah (1)
6.21.2 Tenaga
Pekerja
0.270 Oh x Rp.
45,000
Tukang kayu
0.400 Oh x Rp.
65,000
Kepala tukang
0.040 Oh x Rp.
75,000
Mandor
0.0135 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) +(2)

=
=
=
=

Rp.
Rp.
Rp.
Rp.

118,024.50
655.80
25,162.80
143,843.10

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

12,150.00
26,000.00
3,000.00
742.50
41,892.50
185,735.60

PLL 6.22 1 M Langit - langit akustik ( 30 x 60 ) cm + rangka kayu Meranti


6.22.1 Bahan
Kayu Meranti
0.023 M x Rp.
5,131,500
Paku
0.060 Kg x Rp.
10,930
Akustik 30 x 60 cm
5.800 Lbr x Rp.
16,120
Jumlah (1)
6.22.2 Tenaga
Pekerja
0.260 Oh x Rp.
45,000
Tukang kayu
0.400 Oh x Rp.
65,000
Kepala tukang
0.040 Oh x Rp.
75,000
Mandor
0.013 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) +(2)

=
=
=
=

Rp.
Rp.
Rp.
Rp.

118,024.50
655.80
93,496.00
212,176.30

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

11,700.00
26,000.00
3,000.00
715.00
41,415.00
253,591.30

=
=
=
=

Rp.
Rp.
Rp.
Rp.

138,550.50
655.80
93,495.00
232,701.30

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

13,950.00
30,550.00
3,525.00
852.50
48,877.50
281,578.80

94,600 = Rp.
17,250 = Rp.
Jumlah (1)
= Rp.

34,434.40
1,897.50
36,331.90

45,000
65,000
75,000
55,000
Jumlah (2)
Jumlah (1) +(2)

4,500.00
3,250.00
375.00
275.00
8,400.00
44,731.90

PLL 6.23 1 M Langit - langit akustik ( 30 x 30 ) cm + rangka kayu Meranti


6.23.1 Bahan
Kayu Meranti
0.027 M x Rp.
5,131,500
Paku
0.060 Kg x Rp.
10,930
Akustik 30 x 30 cm
11.500 Lbr x Rp.
8,130
Jumlah (1)
6.23.2 Tenaga
Pekerja
0.310 Oh x Rp.
45,000
Tukang kayu
0.470 Oh x Rp.
65,000
Kepala tukang
0.047 Oh x Rp.
75,000
Mandor
0.0155 Oh x Rp.
55,000
Jumlah (2)
Jumlah (1) +(2)
PLL 6.24 1 M Langit - langit gypsum board, tebal 9 mm
6.24.1 Bahan
Gypsum board (120/240/9) mm
0.364 Lbr x Rp.
Paku sekrup
0.110 Kg x Rp.
6.24.2 Tenaga
Pekerja
Tukang kayu
Kepala tukang
Mandor

0.100
0.050
0.005
0.005

Oh
Oh
Oh
Oh

BERSAMBUNG : ... ABK PEKERJAAN SANITASI

x
x
x
x

Rp.
Rp.
Rp.
Rp.

=
=
=
=
=
=

Rp.
Rp.
Rp.
Rp.
Rp.
Rp.

DAFTAR HARGA SATUAN UPAH DAN BAHAN


PEKERJAAN PEMBANGUNAN GEDUNG NEGARA
TAHUN ANGGARAN 2008
NO.
1
1
2
3
4
5
6
7
8
9
10
11

URAIAN HARGA UPAH


2
Pekerja
Mandor

HARGA

SATUAN

4
Org/Hari
OH
OH
OH
OH
OH
OH
OH
OH
OH
OM

@Rp.
-"-"-"-"-"-"-"-"-"-"-

Tukang Batu
Tukang Kayu
Tukang Besi
Tukang Keramik
Tukang Plafond
Tukang Pasang Pipa
Tukang Cat

Kepala Tukang
Jaga Malam

45,000.00
55,000.00
65,000.00
65,000.00
65,000.00
65,000.00
65,000.00
65,000.00
65,000.00
75,000.00
30,000.00

NO.

URAIAN HARGA BAHAN-BAHAN

HARGA

SATUAN

A.
1
2
3
4
5
6

TIMBUNAN / GALIAN
Tanah Timbun/Merah
Pasir Timbun / urug
Pasir Pasang
Pasir Beton
Sirtu
Tanah Humus

@Rp.
-"-"-"-"-"-

57,500.00
65,200.00
94,500.00
102,000.00
95,760.00
57,000.00

M3
M3
M3
M3
M3
M3

B.
1
2
3
4
5
7
8

BAHAN PEREKAT
Portland Cement (PC)
Cement Putih
Lem Kayu
Lem Karet
Lem Vinyl
Perekat Kaca
Waterfroof

@Rp.
-"-"-"-"-"-"-

1,200.00
2,350.00
32,500.00
37,000.00
39,000.00
52,400.00
47,500.00

Kg
Kg
Kg
Kg
Kg
Kg
Kg

C.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27

BATU / BATU CETAKAN


Batu Kerikil/koral 3 - 5 cm
Batu Kerikil/koral 5 - 7 cm
Batu Kerikil/Koral 7 - 10 cm
Batu Belah/Kali 10 - 15 cm
Batu Belah/Kali 15 - 20 cm
Batu Pecah 1 - 2 cm
Batu Pecah 2 - 3 cm
Batu Pecah 3 - 5 cm
Batu Pecah 5 - 7 cm
Batu Kacang/jagung 0,5 - 1 cm
Batu Splyt
Batu Bata Biasa 5x10x20 cm
Batu Bata Mesin 5x10x20 cm
Batu Bataco
6x12x24 cm
Batu Krawang 10x10x20 cm
Batu Krawang 10x15x15 cm
Batu Krawang 10x20x20 cm
Concrete Block (CB) 10
Concrete Block (CB) 15
Concrete Block (CB) 20
Bondbeam 40x20x20 cm
Con Block Warna type Hollan
Con Block Warna type Uni Pave
Con Block Warna type Dosex Six
Con Block Warna type Hexagon
Con Block K 125
Con Block K 175

@Rp.
-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-

175,890.00

M3
M3
M3
M3
M3
M3
M3
M3
M3
M3
M3
Bh
Bh
Bh
Bh
Bh
Bh
Bh
Bh
Bh
Bh
Bh
Bh
Bh
Bh
Bh
Bh

tbl 6 cm
tbl 6 cm
tbl 6 cm
tbl 6 cm

159,500.00
145,750.00
136,950.00
131,670.00
184,680.00
168,180.00
154,430.00
143,430.00
182,820.00
189,200.00
450.00
650.00
3,660.00
6,960.00
6,300.00
7,660.00

675.00
1,450.00
2,650.00
31,120.00
1,850.00
1,730.00
1,990.00
1,890.00
1,900.00
3,110.00

D.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43

KAYU / LANGIT-LANGIT
Balok Kayu Jati
Papan Kayu Jati
Balok Kayu Meranti Batu
Papan Kayu Meranti Batu
Balok Kayu Damar Laut
Papan Kayu Damar Laut
Balok Kayu Meranti Kls.II
Papan Kayu Meranti Kls.II
Kayu Sembarang/Bekisting
Kayu Bakar
Papan Lambsering/Rider
Kayu Lat Asbes 5x30x400 mm
Kayu Kaso 5 - 7 / 400 cm
Kayu Dolken / kayu laut 7,5 - 10 / 400 cm
Bambu 6 - 8 / 600 cm
Bilik bambu
Kayu Profil 1"
Kayu Profil 2"
Kayu Profil 3"
Kayu Profil 4"
Profil Gypsum 2"
Profil Gypsum 3"
Profil Gypsum 4"
Profil Gypsum 6"
Playwood 120 x 240 tbl.18 mm
Playwood 120 x 240 tbl.12 mm
Playwood 120 x 240 tbl. 9 mm
Playwood 120 x 240 tbl. 6 mm
Playwood 120 x 240 tbl. 4 mm
Teakwood 120 x 240 tbl. 3 mm
Triplek Jati 120 x 240 tbl. 3 mm
TriplekSungkai 120 x 240 tbl.3 mm
Formica 120 x 240 cm
Soft Board 120 x 240 tbl. 4 mm
Soft Board 120 x 240 tbl. 6 mm
Soft Board 120 x 240 tbl. 9 mm
Soft Board 120 x 240 tbl.12 mm
Gypsum 120 x 240 tbl. 6 mm
Gypsum 120 x 240 tbl. 9 mm
Gypsum 120 x 240 tbl.12 mm
Asbes Lokal 100 x 100 cm
Asbes Atrisco 100 x 100 cm
Akustik

@Rp. 21,750,000.00
-"- 21,913,130.00
-"8,485,400.00
-"8,612,680.00
-"8,305,000.00
-"8,429,580.00
-"5,131,500.00
-"5,208,470.00
-"3,144,900.00
-"174,900.00
-"204,750.00
-"8,125.00
-"51,750.00
-"20,750.00
-"12,500.00
-"14,850.00
-"5,700.00
-"11,400.00
-"17,100.00
-"22,800.00
-"4,180.00
-"4,950.00
-"6,050.00
-"7,150.00
-"233,640.00
-"191,950.00
-"156,530.00
-"102,410.00
-"64,520.00
-"96,250.00
-"104,720.00
-"93,830.00
-"81,950.00
-"55,990.00
-"84,150.00
-"126,230.00
-"168,250.00
-"71,500.00
-"94,600.00
-"104,500.00
-"8,250.00
-"10,450.00
-"93,500.00

M3
M3
M3
M3
M3
M3
M3
M3
M3
M3
M2
Btg
Btg
Btg
Btg
M2
M'
M'
M'
M'
M'
M'
M'
M'
Lbr
Lbr
Lbr
Lbr
Lbr
Lbr
Lbr
Lbr
Lbr
Lbr
Lbr
Lbr
Lbr
Lbr
Lbr
Lbr
Lbr
Lbr
M2

E.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20

BESI / ALLUMINIUM
Besi Beton Polos
Besi Beton Ulir
Besi Profil
Besi Siku
Besi CNP 100.50.2,3 - 6 m
Besi Plat Strip
Besi Plat Polos
Besi Plat Bordes
Kawat Besi Beton
Kawat Licin / seng polos
Kawat Duri
Kawat Nyamuk
Kawat Kasa
Kawat Harmonika # 1"
Kawat Burung
Pagar Kawat BRC 120
Pintu Besi
Pintu Gulung Besi
Pintu Lipat Besi
Pintu Rolling Door

@Rp.
-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-

Kg
Kg
Kg
Kg
Btg
Kg
Kg
Kg
Kg
Kg
M'
M2
M2
M2
M2
Lbr
M2
M2
M2
M2

12,390.00
12,590.00
14,060.00
13,050.00
212,750.00
12,620.00
12,820.00
13,230.00
11,620.00
21,410.00
3,820.00
12,240.00
31,630.00
35,080.00

31,625.00
184,800.00
458,850.00
500,250.00
517,500.00
477,250.00

1
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43

2
Jerajak Jendela Besi
Terali Besi Strip
Rangka Baja Ringan
Pintu Alluminium
Jendela Alluminium
Profil Alluminium T
Profil Alluminium Kosen Pintu
Profil Alluminium Kosen Jendela
Profil Alluminium Daun Pintu
Profil Alluminium Daun Jendela
Vention Blinds
Verticals Blinds
Bingkai Naco Niki hitam
Paku Beton 0,5 - 2"
Paku Beton 2" - 5"
Paku Biasa 0,5 - 2"
Paku Biasa 2 - 5"
Sekrup macam Ukuran
Sekrup 0,5 - 2"
Sekrup fisher
Bout 5/8" - 8"
Bout Angker 3/4" - 10"
Bout Ramset / Dina bolt

F.
1
2
3
4
5
6
7
8
9
10
11
12
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43

PENUTUP LANTAI DAN DINDING


Ubin PC abu-abu 20 x 20 cm
Ubin PC abu-abu 30 x 30 cm
Ubin PC abu-abu 40 x 40 cm
Ubin PC warna 20 x 20 cm
Ubin PC warna 30 x 30 cm
Ubin PC warna 40 x 40 cm
Ubin teraso 30 x 30 cm
Ubin teraso 40 x 40 cm
Ubin granito 30 x 30 cm
Ubin granito 40 x 40 cm
Ubin granito 60 x 60 cm
Ubin Mosaik 30 x 30 cm
Ubin Marmer Ex.DN
Ubin teralux marmer 30 x 30 cm
Ubin teralux marmer 40 x 40 cm
Ubin teralux marmer 60 x 60 cm
Ubin keramik 10 x 20 cm
Ubin keramik 15 x 15 cm
Ubin keramik 20 x 20 cm
Ubin keramik 20 x 25 cm
Ubin keramik 25 x 25 cm
Ubin keramik 30 x 30 cm
Ubin keramik 30 x 30 cm anti slip
Ubin keramik 40 x 40 cm
Ubin keramik artistik 5 x 20 cm
Ubin keramik artistik 10 x 10 cm
Ubin keramik artistik 10 x 20 cm
Ubin keramik Essenza 30 x 30 cm
Ubin keramik Essenza 40 x 40 cm
Porselin 11 x 11 cm putih
Porselin 11 x 11 cm, warna
Porselin 15 x 15 cm, putih
Porselin 15 x 15 cm, warna
Plint ubin Abu-abu 10 x 30 cm
Plint ubin Abu-abu 10 x 40 cm
Plint ubin Abu-abu 10 x 20 cm
Plint ubin Pc warna 10 x 20 cm
Plint ubin Pc warna 10 x 30 cm
Plint ubin Pc warna 10 x 40 cm
Plint ubin teraso 10 x 30 cm
Plint ubin teraso 10 x 40 cm
Plint ubin teralux marmer 10 x 30 cm

-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-

@Rp.
-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-

3
316,250.00
258,750.00
181,125.00
546,250.00
488,750.00
8,050.00
45,885.00
43,125.00
51,980.00
48,875.00
146,625.00
155,250.00

345.00
500.00
17,500.00
27,500.00
650.00

4
M2
M2
M2
M2
M2
M'
M'
M'
M'
M'
M2
M2
M2
Bh
Bh
Kg
Kg
Kg
Bh
Bh
Bh
Bh
Bh

1,320.00
2,970.00
5,280.00
1,650.00
3,850.00
6,820.00
10,450.00
19,250.00
23,870.00
42,350.00
95,150.00
12,650.00
238,150.00
24,750.00
44,000.00
99,550.00
1,100.00
1,210.00
2,200.00
2,750.00
3,410.00
4,950.00
7,150.00
8,800.00
825.00
825.00
1,650.00
19,250.00
34,210.00
1,100.00
1,320.00
2,090.00
2,310.00
1,650.00
3,740.00
935.00
1,100.00
2,970.00
5,060.00
8,250.00
11,000.00
14,850.00

Bh
Bh
Bh
Bh
Bh
Bh
Bh
Bh
Bh
Bh
Bh
Bh
M2
Bh
Bh
Bh
Bh
Bh
Bh
Bh
Bh
Bh
Bh
Bh
Bh
Bh
Bh
Bh
Bh
Bh
Bh
Bh
Bh
Bh
Bh
Bh
Bh
Bh
Bh
Bh
Bh
Bh

171,100.00
400.00
490.00
10,930.00
10,120.00
17,250.00

1
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71

2
Plint ubin teralux marmer 10 x 40 cm
Plint ubin teralux marmer 10 x 60 cm
Plint ubin granito 10 x 30 cm
Plint ubin granito 10 x 40 cm
Plint ubin granito 10 x 60 cm
Plint ubin keramik 10 x 30 cm
Plint ubin keramik 10 x 40 cm
Plint ubin keramik 10 x 60 cm
Plint ubin keramik 15 x 30 cm
Plint ubin keramik 15 x 40 cm
Plint ubin keramik 15 x 60 cm
Batu Lapis Dinding 7x3x24
Batu tempel hitam
Batu Poros
Carpet
Carpet 80 % wool, 20 % nylon
Feltex carpet 100 % wool-T-21
Underlyer tebal 6 mm / rubber corrugated
Vynil asbes 30 x 30 cm
Vynil karet 30 x 30 cm KL I
Vynil karet 30 x 30 cm KL II
Vynil motif kembang ex DN 30 x 30 cm
Vynil wall covering lebar 50 cm
Perquet Jati
Gymfloor
Paku Pancing 60 - 230
Sekrup 3,5"
Sekrup 3,5"

G.
1
2
3
4
5
6
7
8
9
10
11
12
25
13
14
15
16
17
18
19
20
21
22
23
24
26
27
28
29
30
31
32
33
34
35
36

PENUTUP ATAP
Atap Genteng Palentong
Atap Genteng Palentong super
Atap Genteng Kodok
Atap Genteng Beton
Atap Genteng Keramik
Atap Genteng Aspal
Atap Genteng Metal/Multi Roof 35
Atap Genteng Asbes Cement 0,35
Atap Sirap
Atap Aluminium gelombang tebal 0,55
Atap Seng gelombang 3' x 6' bjls 35
Atap Seng Super Deck 3' x 6' tbl.0,30
Roof light fibreglass gelombang 180 x 90 cm
Atap Asbes gelombang 1,8 x 1,05 tbl.4 mm
Atap Asbes gelombang 2,1 x 1,05 tbl.4 mm
Atap Asbes gelombang 2,4 x 1,05 tbl.4 mm
Atap Asbes gelombang 2,7 x 1,05 tbl.4 mm
Atap Asbes gelombang 1,8 x 0,92 tbl.5 mm
Atap Asbes gelombang 2,1 x 0,92 tbl.5 mm
Atap Asbes gelombang 2,4 x 0,92 tbl.5 mm
Atap Asbes gelombang 2,7 x 0,92 tbl.5 mm
Atap Asbes gelombang 1,8 x 1,08 tbl.6 mm
Atap Asbes gelombang 2,1 x 1,08 tbl.6 mm
Atap Asbes gelombang 2,4 x 1,08 tbl.6 mm
Atap Asbes gelombang 2,7 x 1,08 tbl.6 mm
Genteng bubung palentong
Genteng bubung palentong super
Genteng bubung kodok
Nok genteng Beton
Nok genteng Keramik
Nok genteng Aspal
Nok genteng Metal/Multi Roof (Decra bond)
Nok genteng Asbes gelomang Cement 0,35
Nok Alluminium standard 40 cm 18 swg 22
Bubung/Nok Stel Gelombang 0,92 m' tbl.5 mm
Bubung/Nok Stel Gelombang 1,05 m' tbl.4 mm

3
-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-

@Rp.
-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-

26,400.00
59,730.00
25,410.00
57,090.00
142,890.00
2,970.00
3,960.00
5,940.00
4,510.00
5,940.00
8,910.00
1,850.00
95,000.00
104,250.00
82,500.00
79,500.00
77,500.00
95,000.00
7,480.00
8,910.00
8,250.00
8,580.00
57,500.00
335,000.00
72,500.00
650.00
370.00
18,500.00

1,520.00
3,620.00
1,970.00
5,430.00
10,350.00
10,290.00
96,250.00
60,720.00
940.00
89,250.00
54,220.00
85,250.00
41,170.00
51,980.00
81,530.00
94,500.00
99,000.00
60,860.00
76,090.00
83,000.00
91,300.00
87,420.00
101,700.00
108,330.00
131,130.00
8,500.00
11,580.00
8,690.00
12,220.00
13,670.00
26,680.00
37,400.00
30,700.00
43,540.00
17,810.00
23,630.00

4
Bh
Bh
Bh
Bh
Bh
Bh
Bh
Bh
Bh
Bh
Bh
Bh
M2
M2
M2
M2
M2
M2
Bh
Bh
Bh
Bh
M2
M2
M2
Bh
Kg
Kg

Bh
Bh
Bh
Bh
Bh
Lbr
Lbr
Lbr
Bh
Lbr
Lbr
Lbr
Lbr
Lbr
Lbr
Lbr
Lbr
Lbr
Lbr
Lbr
Lbr
Lbr
Lbr
Lbr
Lbr
Bh
Bh
Bh
Bh
Bh
Bh
Bh
Lbr
M2
Lbr
Lbr

1
37
38
39
40
41
42
43
44
45
46
47
48
49
50

2
Bubung/Nok Stel Gelombang 1,08 m' tbl.6 mm
Bubung/Nok Paten 0,92 m' tbl.5 mm
Bubung/Nok Paten 1,05 m' tbl.4 mm
Bubung/Nok Paten 1,08 m' tbl.6 mm
Bubung/Nok Stel Rata 0,92 m' tbl.5 mm
Bubung/Nok Stel Rata 1,05 m' tbl.4 mm
Bubung/Nok Stel Rata 1,08 m' tbl.6 mm
Seng plat 3" x 6" bjls 35
Seng plat 3" x 6" bjls 30
Plastic aerator
Sisalation / aluminium foil
Paku Seng + Ring karet
Paku Seng + Ring karet
Paku hak panjang 15 cm

H.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33

KUNCI DAN KACA


Kunci tanam antik
Kunci tanam biasa
Kunci tanam kamar mandi
Kunci silinder
Kunci selot
Kunci lemari
Engsel pintu 4"
Engsel jendela 3"
Engsel angin
Kait angin
Rel pintu dorong
Sealent
Spring knip
Door closer
Door handle
Door stop
Espanyolet
Kaca Block 20 x 20 cm
Kaca Polos tbl. 3 mm
Kaca Polos tbl. 5 mm
Kaca Polos tbl. 8 mm
Kaca Reyben tbl. 5 mm
Kaca Reyben tbl. 8 mm
Kaca buram tbl.3 mm
Kaca buram tbl.5 mm
Kaca buram tbl.8 mm
Kaca cermin tebal 5 mm
Kaca cermin tebal 6 mm
Kaca cermin tebal 8 mm
Kaca patri
Kaca wireglass
Kaca Reyben Naco 30 x 60 cm tbl.5 mm
Kaca Bening Naco 30 x 60 cm tbl.5 mm

I.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17

CAT / MINYAK
Cat Dasar
Cat Tembok
Cat Minyak Kayu
Cat Minyak Besi
Cat Menie Kayu
Cat Menie Besi
Cat Sending
Cat Melamix
Vernis
Plamir
Dempul Cat
Minyak Cat
Minyak Bekisting
Residu / Kolter
Soda Api
Sabun
Kapur Sirih

18,500.00
370.00
27,750.00

4
Lbr
Lbr
Lbr
Lbr
Lbr
Lbr
Lbr
Lbr
Lbr
Bh
M2
Kg
Bh
Kg

@Rp.
-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-

203,500.00
81,840.00
49,720.00
167,750.00
40,370.00
11,220.00
13,750.00
10,230.00
22,770.00
17,380.00
145,750.00
35,750.00
8,250.00
99,770.00
102,740.00
34,650.00
80,410.00
27,500.00
79,200.00
132,000.00
211,200.00
172,000.00
275,200.00
66,000.00
110,000.00
176,000.00
147,000.00
176,400.00
235,200.00
154,000.00
137,500.00
12,350.00
9,750.00

Bh
Bh
Bh
Bh
Bh
Bh
Bh
Bh
Bh
Bh
Bh
Kg
Bh
Bh
Bh
Bh
Bh
Bh
M2
M2
M2
M2
M2
M2
M2
M2
M2
M2
M2
M2
M2
Lbr
Lbr

@Rp.
-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-

13,750.00
17,490.00
42,350.00
45,540.00
41,140.00
43,890.00
55,440.00
58,520.00
43,890.00
14,300.00
10,780.00
10,010.00
5,720.00
5,940.00
20,460.00
13,750.00
3,080.00

Kg
Kg
Kg
Kg
Kg
Kg
Kg
Kg
Kg
Kg
Kg
Kg
Ltr
Ltr
Kg
Kg
Kg

-"-"-"-"-"-"-"-"-"-"-"-"-"-"-

25,920.00
33,460.00
28,140.00
39,050.00
32,800.00
27,500.00
36,910.00

105,000.00
94,500.00
25,000.00
70,180.00

1
18
19
20
21
22
23
24

Kuas
Ampelas/Kertas Pasir
Alang-alang
Wall paper
Perekat
Aluminium B
Aluminium C

J.
1
2
3
4
5
6
7
9
8
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57

SANITASI / PIPA
Kloset duduk / monoblok Lengkap tangki
Kloset duduk / monoblok tanpa tangki
Kloset jongkok porselin
Bakkif Porselen
Wastafel
Urinoir
Kran air 1/2" - 3/4"
Kran air leher angsa 1/2"
Kran Shower
Kran Cebok
Bak fibreglass 0,3 M3
Bak fibreglass 1 M3
Bak cuci piring steinless 2 Lobang
Bak cuci piring teraso 2 Lobang
Tempat sabun keramik
Floor Drain 4" steinlees
Stop Kran 3/4"
Tutup Bak air 1" Kuningan
Instalasi air Bersih
Instalasi air Kotor/Limbah
Buis Beton 1/2 15 cm
Buis Beton 1/2 20 cm
Buis Beton 1/2 30 cm
Buis Beton 15 cm
Buis Beton 20 cm
Buis Beton 30 cm
Buis Beton 40 cm
Buis Beton 50 cm
Buis Beton 60 cm
Buis Beton 80 cm
Buis Beton 100 cm
Pipa PVC Tipe AW 1/2"
Pipa PVC Tipe AW 3/4"
Pipa PVC Tipe AW 1"
Pipa PVC Tipe AW 11/2"
Pipa PVC Tipe AW 2"
Pipa PVC Tipe AW 21/2"
Pipa PVC Tipe AW 3"
Pipa PVC Tipe AW 4"
Pipa Besi Hitam 1/2"
Pipa Besi Hitam 3/4"
Pipa Besi Hitam 1"
Pipa Besi Hitam 11/2"
Pipa Besi Hitam 2"
Pipa Besi Hitam 21/2"
Pipa Galvanis 1/2"
Pipa Galvanis 3/4"
Pipa Galvanis 1"
Pipa Galvanis 11/4"
Pipa Galvanis 11/2"
Pipa Galvanis 2"
Pipa Galvanis 21/2"
Fitting Pipa AW 1"
Knee AW 1"
Tee AW 1"
Socht AW 1"
F-Knee 1"

2
-"-"-"-"-"-"-"-

@Rp.
-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-

8,250.00
3,080.00
2,200.00
27,830.00
15,950.00
46,750.00
42,350.00

4
Bh
Lbr
Ikat
M2
Kg
Kg
Kg

1,756,700.00
1,265,000.00
204,820.00
2,750,000.00
478,500.00
506,880.00
24,860.00
70,180.00
84,150.00
65,670.00
165,000.00
475,200.00
424,270.00
247,500.00
51,150.00
15,000.00
27,500.00
12,500.00
100,000.00
125,000.00
10,230.00
16,170.00
18,260.00
17,490.00
24,860.00
51,150.00
57,640.00
87,230.00
123,640.00
182,820.00
314,380.00
30,250.00
40,535.00
67,500.00
97,500.00
115,000.00
132,000.00
153,000.00
257,000.00
75,000.00
105,000.00
158,000.00
210,000.00
248,000.00
274,000.00
82,000.00
115,000.00
168,000.00
172,000.00
215,000.00
258,000.00
286,000.00

Bh
Bh
Bh
Bh
Bh
Bh
Bh
Bh
Bh
Bh
Bh
Bh
Bh
Bh
Bh
Bh
Bh
Bh
Ttk
Ttk
M'
M'
M'
M'
M'
M'
M'
M'
M'
M'
M'
Btg
Btg
Btg
Btg
Btg
Btg
Btg
Btg
Btg
Btg
Btg
Btg
Btg
Btg
Btg
Btg
Btg
Btg
Btg
Btg
Btg

4,750.00
6,500.00
4,250.00
7,250.00

Bh
Bh
Bh
Bh

1
58
59
60
57
58
59
60

F-Tee 1"
DOP AW 1:
Bocht LL-D 1"
Union Socht 1"
D-Nipple 1"
Water Moer 1"
Plug 1"

K.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41

LISTRIK / ACSESORIES
Lampu TL 1 x 20 W Lengkap
Lampu TL 1 x 40 W Lengkap
Lampu TL 2 x 20 W Lengkap
Lampu TL 2 x 40 W Lengkap
Lampu TL Bambu 1 x 20 W Lengkap
Lampu TL Bambu 1 x 40 W Lengkap
Lampu XL 5 W + Fitting
Lampu XL 8 W + Fitting
Lampu XL10 W + Fitting
Lampu XL14 W + Fitting
Lampu XL18 W + Fitting
Lampu XL24 W + Fitting
Lampu Downlight 5 W Lengkap
Lampu Pijar 5 w + Fitting
Lampu Pijar 10 w + Fitting
Lampu Pijar 15 w + Fitting
Lampu Pijar 20 w + Fitting
Lampu Pijar 25 w + Fitting
Lampu Pijar 40 w + Fitting
Stop Kontak Tanam
Saklar Tunggal
Saklar Ganda
Saklar Triple
Zekring box 1 grup
Zekring box 2 grup
Zekring box 3 grup
Zekring box 4 grup
MCB 2 Ampere
MCB 4 Ampere
MCB 6 Ampere
MCB 8 Ampere
Kabel Listrik NGA 1,5 mm
Kabel Listrik NGA 2,5 mm
Kabel Listrik NGA 3 mm
Kabel Listrik NGA 4 mm
Kabel Listrik NYM 2 1,5 mm
Kabel Listrik NYM 2 2,5 mm
Kabel Listrik NYM 2 3 mm
Kabel Listrik NYM 2 4 mm
Instalasi listrik titik api
Instalasi listrik Lampu Nyala

Medan,
DIKETAHUI OLEH :
Kepala Dinas Penataan Ruang dan

-"-"-"-"-"-"-"-

11,500.00
4,500.00
22,500.00
6,750.00
16,500.00
29,500.00
3,500.00

@Rp.
-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-"-

60,500.00
78,650.00
112,500.00
127,500.00
75,000.00
87,500.00
9,500.00
15,500.00
17,500.00
27,500.00
31,000.00
38,500.00
45,500.00
3,000.00
4,000.00
4,750.00
6,500.00
7,500.00
9,500.00
7,250.00
15,100.00
16,950.00
21,200.00
48,500.00
65,000.00
95,000.00
125,000.00
30,250.00
36,300.00
90,000.00
135,000.00
750.00
900.00
1,150.00
1,500.00
1,600.00
2,085.00
2,375.00
2,875.00

85,000.00
75,000.00

Maret 2008

DIBUAT OLEH : TIM TEKNIS


1. Ir. Jeremias Sinaga, MAP

(....)

2. Ir. Herimas

(....)

3. H. Sugiarto Bharata, ST

(....)

4. H. Ali Muhar, ST

(....)

Ir. H. Syafruddin Siregar, MSi

5. Sakula Karo karo, ST

(....)

Pembina Utama Muda

6. Ebenser Saragih, SE

(....)

7. Sahat Hasudungan, ST

(....)

8. Ir. Tanogara Siahaan

(....)

9. Ali Fauzan, ST

(....)

Permukiman Prov. Sumatera Utara

NIP. 400025884

10. Ir. Naimul Ahmad R. ST

(....)

11. Chandra, ST

(....)

4
Bh
Bh
Bh
Bh
Bh
Bh
Bh
Set
Set
Set
Set
Set
Set
Set
Set
Set
Set
Set
Set
Set
Set
Set
Set
Set
Set
Set
Bh
Bh
Bh
Bh
Unt
Unt
Unt
Unt
Unt
Unt
Unt
Unt
M'
M'
M'
M'
M'
M'
M'
M'
Ttk
Ttk