TUGAS STRUKTUR BETON 1

Disusun oleh :
Muhammad Samsul Hidayat
022113145
JURUSAN TEKNIK SIPIL









FAKULTAS TEKNIK
UNIVERSITAS ISLAM SULTAN AGUNG SEMARANG
2012
SOAL NOMOR 1
Nomor : 1.
Kolom bertulangan 4 sisi, fc'=150 kg/cm2 (15 MPa); fy=4000 kg/cm2 (400 MPa);
dimensi b=40cm; h=40cm; Menahan Momen Mu=20 ton.m ; Gaya aksial Pu=100
ton.
Hitung jumlah tulangan (pakai D19) dan gambarkan penampang kolom tersebut.
Jawab :
Diketahui :
fc' = 150 kg/cm
2
=15 MPa
fy =4000 kg/cm
2
=400 MPa
b =40cm
h =40cm
Mu =20 ton.m = 20 x

kg.cm
Pu =100 ton = 100 x

kg
Ditanya : Jumlah tulangan dan Gambar ?
Jawab :
1. Sumbu X =

= 0,38
Sumbu Y =


= 0,75
2. Diagram Interaksi Kolom Persegi; Tulangan Disebar Merata 4 sisi :

















Kolom tidak kuat,maka dimensi harus diperbesar:
b =50cm
h =50cm
Sumbu X =

= 0,19
Sumbu Y =


= 0,48
Diagram Interaksi Kolom Persegi; Tulangan Disebar Merata 4 sisi :
























Dari grafik : fc = 150 kg/cm
2
= 15 MPa = 0,6
r = 0,016
t = r .
= 0,016 .0,6 = 0,0096
Yang dipakai min = 0,01

Ast = min . b. h
= 0,01 . 50. 50 = 25
db = 1,9 cm Luas tulangan = 2,83 cm
2

m =

= 8,8312 D 19
Gambar











Nomor : 2.
Kolombertulangan 2 sisi, fc'=200 kg/cm2 (15 MPa); fy=4000 kg/cm2 (400 MPa);
dimensi b=40cm; h=70cm; MenahanMomen Mu=30 ton.m ; Gaya aksialPu=150 ton.
Hitung jumlah tulangan (pakai D19) dangambarkan penampang kolom tersebut.
Jawab :
Diketahui :
fc' =200 kg/cm
2
=20MPa
fy =4000 kg/cm
2
=400 MPa
b =40cm
h =70cm
Mu =30 ton.m = 30 x

kg.cm
Pu =150 ton = 150 x

kg
Ditanya : Jumlah tulangan dan Gambar ?
Jawab :
Sumbu X =

= 0,14
Sumbu Y =


= 0,48


50 cm
50 cm
12D 19
3. Diagram Interaksi Kolom Persegi; Tulangan Disebar Merata 2 sisi :


Dari grafik : fc = 150 kg/cm
2
= 15 MPa = 0,8
r = 0,004
t = r .
= 0,004 .0,8 = 0,0032
Yang dipakai min = 0,01
Ast = min . b. h
= 0,01 . 40. 70 = 28
db = 1,9 cm Luas tulangan = 2,83 cm
2

m =

= 9,898 D 19



Gambar














Nomor : 3.
Kolom bertulangan 4 sisi, fc'=150 kg/cm2 (15 MPa); fy=4000 kg/cm2 (400 MPa);
dimensi b=50cm; h=50cm; bertulangan 20D22.
Kolom tersebut akan dibebani Momen Mu=40 ton.m dan Gaya aksial Pu=300 ton.
Apakah kolom tersebut kuat ?
Jawab :
Diketahui :
m =20
db =22 mm = 2,2 cm
fc' =150 kg/cm
2
=15MPa
fy =4000 kg/cm
2
=400 MPa
b =50cm
h =50cm
Mu =40 ton.m = 40 x

kg.cm
Pu =300 ton = 300 x

kg
Ditanya : kolom kuat atau tidak?
Jawab :
1. Sumbu X =

= 0,39
Sumbu Y =


= 1,48

4. Diagram Interaksi Kolom Persegi; Tulangan Disebar Merata 4 sisi :
70 cm
12D 19
40 cm
























Dari grafik : kolom harus diperbesar
db = 1,9 cm Luas tulangan = 2,83 cm
2

m =



20 =


Ast = 56,6
Ast = t . b. h
56,6= t . 50. 50
t = 0,224
fc = 150 kg/cm
2
= 15 MPa = 0,6
t = r .
0,224 = r .0,6
r = 0,373 r di luar grafik,artinya kolom tidak kuat menahan beban


Tugas :
Gambarkan Diagram Interaksi Setiap Kolom Berikut :
fc'=250 kg/cm2; fy=4000 kg/cm2










Jawab :























SOAL NOMOR 2
2. a. Bandingkan hasil perhitungan kolom 4 sisi dengan grafik dan DsgWin?
Diketahui : fc = 200kg/cm
2
Fy = 4000 kg/cm
2
D19
b = h = 550 mm = 55cm
Pu = 300 ton
Mu = 30 ton.m
Ditanya : hitung jumlah tulangan dan gambar ?
Jawab :
1. Sumbu X =

= 0,16
Sumbu Y =


= 0,89
2. Diagram InteraksiKolomPersegi; TulanganDisebarMerata 4 sisi :


Dari grafik : fc = 200 kg/cm
2
= 20 MPa = 0,8
r = 0,022
t = r .
= 0,022 .0,8 = 0,0176
Yang dipakai = 0,0176
Ast = t . b. h
= 0,0176 .55.55 = 53,24
db = 1,9 cm Luas tulangan = 2,83 cm
2

m =

= 18,8 20 D 19











55cm






55 cm
DATA:

Column Width, Bw = 55.00 cm
Column Height, Ht = 55.00 cm

Factored Moment, Mu = 30000.00 kg.m
Factored Shear, Vu = 0.00 kg
Factored Normal, Pu = 300000.00 kg
Factored Torsion, Tu = 0.00 kg.m

Concrete Compressive Strength fc1 = 200.00 kg/cm2
Concrete Crack Strength fcr = 150.00 kg/cm2
Concrete Initial Strength fci = 120.00 kg/cm2
Main Rebar Yield Strength fy = 4000.00 kg/cm2
Stirrups Rebar Yield Strength fyv = 2400.00 kg/cm2

Main rebar diameter dbm = 1.90 cm
2nd main rebar diameter dbn = 1.90 cm
Stirrups Rebar diameter dbv = 1.00 cm

Min concrete cover, Cover = 5.00 cm
Min rebar clear space, Minclrspc = 2.50 cm

RESULT:

Flexural Reinforcement: OK
Balanced neutral axis, cbal = 29.0517 cm
Balanced Compr. block, abal = 24.6939 cm
Balanced Moment Capacity, Mnb = 66234.15 kg.m
Balanced Normal Capacity, Pnb = 233477.80 kg
Balanced Eccentricity, ebal = 28.37 cm
Location of neutral axis, c = 44.6802 cm
Length of compression block, a = 37.9782 cm
Total Rebar (incl. side bar) nbt = 20 d19
Total Side Rebar nbs = 0 d19
Total Rebar area, Ast = 56.7057 cm2 = 1.87%
Nominal Moment Capacity, Md = 31081.92 kg.m
Nominal Normal Capacity, Pd = 300083.95 kg

Shear Reinforcement: OK
Av = 2*(0.25*Pi*dbv*dbv) = 0.00 cm2
Ag = bw*h = 0.00 cm2
pw = Ast/(bw*d) = 0.0000
x1 = bw-2*cv-2*dbv = 0.00 cm
y1 = h-2*cv-2*dbv = 0.00 cm
Vn = Vu/phi = 0.00 kg
Tn = Tu/phi = 0.00 kg.m
Vc = = 0.00 kg
Tc = = 0.00 kg.m
Vnc = Vn - Vc = 0.00 kg
Tnc = Tn - Tc = 0.00 kg.m
Avs = Vnc/(fy*d) = 0.00 cm2
Ats = Tnc/(zt*x1*y1*fy) = 0.00 cm2
Atst = Avs + 2*Ats = 0.00 cm2

Additional Longitudinal Rebar, At = 0.00 cm2
Stirrups Spacing, spc = 30.40 cm


2. b. Bandingkan hasil perhitungan kolom 4 sisi dengan grafik dan DsgWin?
Diketahui : fc = 200kg/cm
2
Fy = 4000 kg/cm
2
D19
b = h = 550 mm = 55cm
Pu = 100 ton
Mu = 40 ton.m
Ditanya : hitung jumlah tulangan dan gambar ?
Jawab :
1. Sumbu X =

= 0,21
Sumbu Y =


= 0,29


2. Diagram InteraksiKolomPersegi; TulanganDisebarMerata 4 sisi :


Dari grafik : fc = 200 kg/cm
2
= 20 MPa = 0,8
r = 0,022
t = r .
= 0,022 .0,8 = 0,0176
Yang dipakai = 0,0176
Ast = t . b. h
= 0,0176 .55.55 = 53,24
db = 1,9 cm Luas tulangan = 2,83 cm
2

m =

= 18,8 20 D 19










55cm






55 cm
DATA:

Column Width, Bw = 55.00 cm
Column Height, Ht = 55.00 cm

Factored Moment, Mu = 40000.00 kg.m
Factored Shear, Vu = 0.00 kg
Factored Normal, Pu = 100000.00 kg
Factored Torsion, Tu = 0.00 kg.m

Concrete Compressive Strength fc1 = 200.00 kg/cm2
Concrete Crack Strength fcr = 150.00 kg/cm2
Concrete Initial Strength fci = 120.00 kg/cm2
Main Rebar Yield Strength fy = 4000.00 kg/cm2
Stirrups Rebar Yield Strength fyv = 2400.00 kg/cm2

Main rebar diameter dbm = 1.90 cm
2nd main rebar diameter dbn = 1.90 cm
Stirrups Rebar diameter dbv = 1.00 cm

Min concrete cover, Cover = 5.00 cm
Min rebar clear space, Minclrspc = 2.50 cm

RESULT:

Flexural Reinforcement: OK
Balanced neutral axis, cbal = 29.0517 cm
Balanced Compr. block, abal = 24.6939 cm
Balanced Moment Capacity, Mnb = 66234.15 kg.m
Balanced Normal Capacity, Pnb = 233477.80 kg
Balanced Eccentricity, ebal = 28.37 cm
Location of neutral axis, c = 22.9521 cm
Length of compression block, a = 19.5093 cm
Total Rebar (incl. side bar) nbt = 20 d19
Total Side Rebar nbs = 0 d19
Total Rebar area, Ast = 56.7057 cm2 = 1.87%
Nominal Moment Capacity, Md = 41847.42 kg.m
Nominal Normal Capacity, Pd = 100027.28 kg

Shear Reinforcement: OK
Av = 2*(0.25*Pi*dbv*dbv) = 0.00 cm2
Ag = bw*h = 0.00 cm2
pw = Ast/(bw*d) = 0.0000
x1 = bw-2*cv-2*dbv = 0.00 cm
y1 = h-2*cv-2*dbv = 0.00 cm
Vn = Vu/phi = 0.00 kg
Tn = Tu/phi = 0.00 kg.m
Vc = = 0.00 kg
Tc = = 0.00 kg.m
Vnc = Vn - Vc = 0.00 kg
Tnc = Tn - Tc = 0.00 kg.m
Avs = Vnc/(fy*d) = 0.00 cm2
Ats = Tnc/(zt*x1*y1*fy) = 0.00 cm2
Atst = Avs + 2*Ats = 0.00 cm2

Additional Longitudinal Rebar, At = 0.00 cm2
Stirrups Spacing, spc = 30.40 cm


2. c. Bandingkan hasil perhitungan kolom 4 sisi dengan grafik dan DsgWin?
Diketahui : fc = 200kg/cm
2
Fy = 4000 kg/cm
2
D19
b = h = 550 mm = 55cm
Pu = 500 ton
Mu = 20 ton.m
Ditanya : hitung jumlah tulangan dan gambar ?
Jawab :
1. Sumbu X =

= 0,1
Sumbu Y =


= 1,49
2. Diagram Interaksi KolomPersegi; TulanganDisebarMerata 4 sisi :


Dari grafik : fc = 200 kg/cm
2
= 20 MPa = 0,8
r = 0,042
t = r .
= 0,042 .0,8 = 0,0336

Yang dipakai = 0,0336
Ast = t . b. h
= 0,0336 .55.55 = 101,64
db = 1,9 cm Luas tulangan = 2,83 cm
2

m =

= 35,91 36 D 19










55cm






55 cm
DATA:

Column Width, Bw = 55.00 cm
Column Height, Ht = 55.00 cm

Factored Moment, Mu = 20000.00 kg.m
Factored Shear, Vu = 0.00 kg
Factored Normal, Pu = 500000.00 kg
Factored Torsion, Tu = 0.00 kg.m

Concrete Compressive Strength fc1 = 200.00 kg/cm2
Concrete Crack Strength fcr = 150.00 kg/cm2
Concrete Initial Strength fci = 120.00 kg/cm2
Main Rebar Yield Strength fy = 4000.00 kg/cm2
Stirrups Rebar Yield Strength fyv = 2400.00 kg/cm2

Main rebar diameter dbm = 1.90 cm
2nd main rebar diameter dbn = 1.90 cm
Stirrups Rebar diameter dbv = 1.00 cm

Min concrete cover, Cover = 5.00 cm
Min rebar clear space, Minclrspc = 2.50 cm

RESULT:

Flexural Reinforcement: OK
CONCENTRIC LOADING CONDITION
Total Rebar (incl. side bar) nbt = 44 d19
Total Side Rebar nbs = 0 d19
Total Rebar area, Ast = 124.7526 cm2 = 4.12%
Nominal Moment Capacity, Md = 20634.64 kg.m
Nominal Normal Capacity, Pd = 515865.97 kg

Shear Reinforcement: OK
Av = 2*(0.25*Pi*dbv*dbv) = 0.00 cm2
Ag = bw*h = 0.00 cm2
pw = Ast/(bw*d) = 0.0000
x1 = bw-2*cv-2*dbv = 0.00 cm
y1 = h-2*cv-2*dbv = 0.00 cm
Vn = Vu/phi = 0.00 kg
Tn = Tu/phi = 0.00 kg.m
Vc = = 0.00 kg
Tc = = 0.00 kg.m
Vnc = Vn - Vc = 0.00 kg
Tnc = Tn - Tc = 0.00 kg.m
Avs = Vnc/(fy*d) = 0.00 cm2
Ats = Tnc/(zt*x1*y1*fy) = 0.00 cm2
Atst = Avs + 2*Ats = 0.00 cm2

Additional Longitudinal Rebar, At = 0.00 cm2
Stirrups Spacing, spc = 30.40 cm

SOAL NOMOR 3
3. a. Diketahui: Mu = 10 ton.m = 1.000.000 kg.cm
h = 650mm = 65 cm
d = 0,9 x 65 = 58,5 cm
b = 32,5 cm
fc = 25 Mpa = 250 kg/cm
2

fy = 400Mpa = 4000 kg/cm
2

D 19
ditanya : tentukan jumlah tulangan dan gambar?
Jawab :
a) Koefisien penampang



b) Indeks Tulangan
( )

c) Rasio Tulangan 65cm 58,5cm


d) Luas Tulangan


e) Jumlah Tulangan 32,5cm


perhitungan pemasangan tulangan
=2x4+2x1+3x1,9+2x2,5
=20,7cm < 32,5 cm
DATA:

Beam Width, Bw = 32.50 cm
Beam Height, Ht = 65.00 cm

Factored Moment, Mu = 10000.00 kg.m
Factored Shear, Vu = 0.00 kg
Factored Normal, Pu = 0.00 kg
Factored Torsion, Tu = 0.00 kg.m

Concrete Compressive Strength fc1 = 250.00 kg/cm2
Concrete Crack Strength fcr = 150.00 kg/cm2
Concrete Initial Strength fci = 120.00 kg/cm2
Main Rebar Yield Strength fy = 4000.00 kg/cm2
Stirrups Rebar Yield Strength fyv = 2400.00 kg/cm2

Main rebar diameter dbm = 1.90 cm
2nd main rebar diameter dbn = 1.90 cm
Stirrups Rebar diameter dbv = 1.00 cm

Min concrete cover, Cover = 4.00 cm
Min rebar clear space, Minclrspc = 2.50 cm

RESULT:

Effective Depth, d = 59.05 cm
Distance, d1 = H - d = 5.95 cm
ds = 59.05 cm
ds1 = 5.95 cm
Minimum Rebar Ratio, romin = 0.00352 (Using Romin = 200/Fy)
Maximum Rebar Ratio, romax = 0.01916

Flexural Reinforcement: OK
Normal Direction:
Beta Factor, Beta = 0.850
Location of neutral axis, c = 5.8732 cm
Length of compression block, a = 4.9922 cm
Total Rebar, nb = 2/ 3 d19
Total Rebar area, Ast = 5.5212 cm2 (ro = 0.00443)
Nominal Moment Capacity, Md = 15405.71 kg.m

Inverted Section Direction
Beta Factor, Beta = 0.850
Location of neutral axis, c1 = 4.9819 cm
Length of compression block, a1 = 4.2346 cm
Total Rebar, nb = 3/ 2 d19
Total Rebar area, As1 = 5.6706 cm2 (ro1 = 0.00295)
Nominal Moment Capacity, Md1 = 10532.07 kg.m

Shear Reinforcement: OK
Av = 2*(0.25*Pi*dbv*dbv) = 0.00 cm2
Ag = bw*h = 0.00 cm2
pw = Ast/(bw*d) = 0.0000
x1 = bw-2*cv-2*dbv = 0.00 cm
y1 = h-2*cv-2*dbv = 0.00 cm
Vn = Vu/phi = 0.00 kg
Tn = Tu/phi = 0.00 kg.m
Vc = = 0.00 kg
Tc = = 0.00 kg.m
Vnc = Vn - Vc = 0.00 kg
Tnc = Tn - Tc = 0.00 kg.m
Avs = Vnc/(fy*d) = 0.00 cm2
Ats = Tnc/(zt*x1*y1*fy) = 0.00 cm2
Atst = Avs + 2*Ats = 0.00 cm2

Additional Longitudinal Rebar, At = 0.00 cm2
Stirrups Spacing, spc = 2540.01 cm

3. b. Diketahui: Mu = 20 ton.m = 2.000.000 kg.cm
h = 65 cm
d = 0,9 x 65 = 58,5 cm
b = 32,5 cm
fc = 250 kg/cm
2

fy = 4000 kg/cm
2

D 19
ditanya : tentukan jumlah tulangan dan gambar?

Jawab :
a) Koefisien penampang



b) Indeks Tulangan 65cm 58,5cm
( )

c) Rasio Tulangan



d) Luas Tulangan 32,5cm

perhitungan pemasangan tulangan

=2x4+2x1+4x1,9+3x2,5
e) Jumlah Tulangan =25,1 cm < 32,5 cm



DATA:

Beam Width, Bw = 32.50 cm
Beam Height, Ht = 65.00 cm

Factored Moment, Mu = 20000.00 kg.m
Factored Shear, Vu = 0.00 kg
Factored Normal, Pu = 0.00 kg
Factored Torsion, Tu = 0.00 kg.m

Concrete Compressive Strength fc1 = 250.00 kg/cm2
Concrete Crack Strength fcr = 150.00 kg/cm2
Concrete Initial Strength fci = 120.00 kg/cm2
Main Rebar Yield Strength fy = 4000.00 kg/cm2
Stirrups Rebar Yield Strength fyv = 2400.00 kg/cm2

Main rebar diameter dbm = 1.90 cm
2nd main rebar diameter dbn = 1.90 cm
Stirrups Rebar diameter dbv = 1.00 cm

Min concrete cover, Cover = 4.00 cm
Min rebar clear space, Minclrspc = 2.50 cm

RESULT:

Effective Depth, d = 59.05 cm
Distance, d1 = H - d = 5.95 cm
ds = 59.05 cm
ds1 = 5.95 cm
Minimum Rebar Ratio, romin = 0.00352 (Using Romin = 200/Fy)
Maximum Rebar Ratio, romax = 0.02040

Flexural Reinforcement: OK
Normal Direction:
Beta Factor, Beta = 0.850
Location of neutral axis, c = 6.7164 cm
Length of compression block, a = 5.7090 cm
Total Rebar, nb = 3/ 4 d19
Total Rebar area, Ast = 11.3411 cm2 (ro = 0.00591)
Nominal Moment Capacity, Md = 20247.14 kg.m

Inverted Section Direction
Beta Factor, Beta = 0.850
Location of neutral axis, c1 = 5.8987 cm
Length of compression block, a1 = 5.0139 cm
Total Rebar, nb = 4/ 3 d19
Total Rebar area, As1 = 8.5059 cm2 (ro1 = 0.00443)
Nominal Moment Capacity, Md1 = 15406.84 kg.m

Shear Reinforcement: OK
Av = 2*(0.25*Pi*dbv*dbv) = 0.00 cm2
Ag = bw*h = 0.00 cm2
pw = Ast/(bw*d) = 0.0000
x1 = bw-2*cv-2*dbv = 0.00 cm
y1 = h-2*cv-2*dbv = 0.00 cm
Vn = Vu/phi = 0.00 kg
Tn = Tu/phi = 0.00 kg.m
Vc = = 0.00 kg
Tc = = 0.00 kg.m
Vnc = Vn - Vc = 0.00 kg
Tnc = Tn - Tc = 0.00 kg.m
Avs = Vnc/(fy*d) = 0.00 cm2
Ats = Tnc/(zt*x1*y1*fy) = 0.00 cm2
Atst = Avs + 2*Ats = 0.00 cm2

Additional Longitudinal Rebar, At = 0.00 cm2
Stirrups Spacing, spc = 2540.01 cm

3. c. Diketahui: Mu = 40 ton.m = 4.000.000 kg.cm
h = 65 cm
d = 0,9 x 65 = 58,5 cm
b = 32,5 cm
fc = 250 kg/cm
2

fy = 4000 kg/cm
2

D 19
ditanya : tentukan jumlah tulangan dan gambar?
Jawab :
a) Koefisien penampang



b) Indeks Tulangan
( )

c) Rasio Tulangan




d) Luas Tulangan


e) Jumlah Tulangan 58,5cm 65cm






32,5cm
Perhitungan pemasangan tulangan
=2x4+2x1+5x1,9+4x2,5
=29,5 cm < 32,5 cm
DATA:

Beam Width, Bw = 32.50 cm
Beam Height, Ht = 65.00 cm

Factored Moment, Mu = 40000.00 kg.m
Factored Shear, Vu = 0.00 kg
Factored Normal, Pu = 0.00 kg
Factored Torsion, Tu = 0.00 kg.m

Concrete Compressive Strength fc1 = 250.00 kg/cm2
Concrete Crack Strength fcr = 150.00 kg/cm2
Concrete Initial Strength fci = 120.00 kg/cm2
Main Rebar Yield Strength fy = 4000.00 kg/cm2
Stirrups Rebar Yield Strength fyv = 2400.00 kg/cm2

Main rebar diameter dbm = 1.90 cm
2nd main rebar diameter dbn = 1.90 cm
Stirrups Rebar diameter dbv = 1.00 cm

Min concrete cover, Cover = 4.00 cm
Min rebar clear space, Minclrspc = 2.50 cm

RESULT:

Effective Depth, d = 59.05 cm
Distance, d1 = H - d = 5.95 cm
ds = 57.09 cm
ds1 = 6.68 cm
Minimum Rebar Ratio, romin = 0.00352 (Using Romin = 200/Fy)
Maximum Rebar Ratio, romax = 0.02268

Flexural Reinforcement: OK
Normal Direction:
Beta Factor, Beta = 0.850
Location of neutral axis, c = 10.7165 cm
Length of compression block, a = 9.1090 cm
Total Rebar, nb = 6/ 9 d19
Total Rebar area, Ast = 24.1673 cm2 (ro = 0.01330)
Nominal Moment Capacity, Md = 42234.94 kg.m

Inverted Section Direction
Beta Factor, Beta = 0.850
Location of neutral axis, c1 = 8.8654 cm
Length of compression block, a1 = 7.5356 cm
Total Rebar, nb = 9/ 6 d19
Total Rebar area, As1 = 17.0117 cm2 (ro1 = 0.00886)
Nominal Moment Capacity, Md1 = 29165.08 kg.m

Shear Reinforcement: OK
Av = 2*(0.25*Pi*dbv*dbv) = 0.00 cm2
Ag = bw*h = 0.00 cm2
pw = Ast/(bw*d) = 0.0000
x1 = bw-2*cv-2*dbv = 0.00 cm
y1 = h-2*cv-2*dbv = 0.00 cm
Vn = Vu/phi = 0.00 kg
Tn = Tu/phi = 0.00 kg.m
Vc = = 0.00 kg
Tc = = 0.00 kg.m
Vnc = Vn - Vc = 0.00 kg
Tnc = Tn - Tc = 0.00 kg.m
Avs = Vnc/(fy*d) = 0.00 cm2
Ats = Tnc/(zt*x1*y1*fy) = 0.00 cm2
Atst = Avs + 2*Ats = 0.00 cm2

Additional Longitudinal Rebar, At = 0.00 cm2
Stirrups Spacing, spc = 2540.01 cm