PROJECT : Pengukuran Topografi Irigasi

VOLUME : 35 Km
LOCATION : Bekasi, Jawa Barat
Jumlah Satuan Jumlah Biaya Jumlah
Unit Unit Hari Satuan Biaya
1 Pengukuran Horizontal (Poligon) 123,883,088 Rp
a. Personil
- Chip Surveyor 1 Org 41 275,000 Rp 11,323,529 Rp
- Surveyor 1 Org 41 250,000 Rp 10,294,118 Rp
- Ass. Surveyor 1 Org 41 125,000 Rp 5,147,059 Rp
- Tenaga Lokal 2 Org 41 100,000 Rp 8,235,294 Rp
- Labour 2 Org 41 100,000 Rp 8,235,294 Rp
- Tim BM/Patok 2 Org 20 100,000 Rp 4,000,000 Rp
b. Mobilisasi
- Leader 1 Org 2 150,000 Rp 300,000 Rp
- Surveyor 1 Org 2 150,000 Rp 300,000 Rp
- Ass. Surveyor 1 Org 2 150,000 Rp 300,000 Rp
- Labour 2 Org 2 150,000 Rp 600,000 Rp
- Peralatan 1 Paket 2 150,000 Rp 300,000 Rp
- Tim BM/Patok 2 Org 2 150,000 Rp 600,000 Rp
c. Peralatan
- ETS (Electronic Total Station) 1 Set 41 250,000 Rp 10,294,118 Rp
- GPS Handheld 2 Set 41 35,000 Rp 2,882,353 Rp
- HT (Handy Talkie) 3 Set 41 25,000 Rp 3,088,235 Rp
- Digital Camera 1 Set 41 10,000 Rp 411,765 Rp
- Notebook (Laptop) 1 Set 41 25,000 Rp 1,029,412 Rp
- Mobil (4WD, Driver, BBM) 1 Set / Hari 41 500,000 Rp 20,588,235 Rp
- Consumable 1 Team/Hari 41 250,000 Rp 10,294,118 Rp
- Safety Tools 1 Set 1 500,000 Rp 500,000 Rp
- Basecamp 1 Set 41 150,000 Rp 6,176,471 Rp
- Komunikasi 1 Hari 41 17,500 Rp 720,588 Rp
- Supporting Tools 1 Set 1 500,000 Rp 500,000 Rp
- Pemasangan BM 1 Set 35 192,500 Rp 6,737,500 Rp
- Pemasangan Patok (Paralon) 1 Set 315 35,000 Rp 11,025,000 Rp
2 Pengukuran Vertical (WP) 51,294,118 Rp
a. Personil
- Chip Surveyor 0 Org 41 300,000 Rp - Rp
- Surveyor 1 Org 41 250,000 Rp 10,294,118 Rp
- Ass. Surveyor 1 Org 41 125,000 Rp 5,147,059 Rp
- Tenaga Lokal 0 Org 41 100,000 Rp - Rp
- Labour 2 Org 41 100,000 Rp 8,235,294 Rp
- Tim BM/Patok 0 Org 20 75,000 Rp - Rp
b. Mobilisasi
- Leader 0 Org 2 150,000 Rp - Rp
- Surveyor 1 Org 2 150,000 Rp 300,000 Rp
- Ass. Surveyor 1 Org 2 150,000 Rp 300,000 Rp
- Labour 2 Org 2 150,000 Rp 600,000 Rp
- Peralatan 1 Paket 2 150,000 Rp 300,000 Rp
- Tim BM/Patok 0 Org 2 150,000 Rp - Rp
c. Peralatan
- Waterrpass (WP) 1 Set 41 250,000 Rp 10,294,118 Rp
- GPS Handheld 0 Set 41 35,000 Rp - Rp
- HT (Handy Talkie) 3 Set 41 25,000 Rp 3,088,235 Rp
- Digital Camera 1 Set 41 10,000 Rp 411,765 Rp
- Notebook (Laptop) 1 Set 41 35,000 Rp 1,441,176 Rp
- Mobil (4WD, Driver, BBM) 0 Set / Hari 41 500,000 Rp - Rp
- Consumable 1 Team/Hari 41 200,000 Rp 8,235,294 Rp
- Safety Tools 1 Set 1 500,000 Rp 500,000 Rp
- Basecamp 0 Set 41 150,000 Rp - Rp
- Komunikasi 1 Hari 41 40,000 Rp 1,647,059 Rp
- Supporting Tools 1 Set 1 500,000 Rp 500,000 Rp
3 Reporting 3,400,000 Rp
a. Personil
- Drafter 1 Org/LS 1 1,500,000 Rp 1,500,000 Rp
- Surveyor 1 Org/LS 1 750,000 Rp 750,000 Rp
b. Peralatan
- PC (Komputer) 1 Set 1 300,000 Rp 300,000 Rp
- Print A0 1 Set 1 500,000 Rp 500,000 Rp
- Print A3 1 Set 1 350,000 Rp 350,000 Rp
4 Lain-Lain 2,750,000 Rp
a. Asuransi Personil 11 Org 1 250,000 Rp 2,750,000 Rp
181,327,206 Rp
No Deskripsi
RAB PENGUKURAN TOPOGRAFI
Grand Total :