RENCANA BIAYA

SURVEY TOPOGRAFI SELUAS + 100 Ha, SKALA : 1 : 1000


LOKASI : Seratai dan Bekoso, Kab Paser, Kalimantan Timur

VOLUME : 500.0 HA
JUMLAH TIM PENGUKURAN YANG DIBUTUHKAN :
Koordinator Lapangan/Team Leader 1 Orang
Processing Data 1 Orang
Surveyor Total Station 2 Orang
Ass. Surveyor Total Station 1 Orang
5 Orang

TENAGA LOKAL :
TIM Total Station (1 tim @ 4 orang) 6 Orang
TIM Rintisan (1 tim @ 2 orang) 3 Orang
TOTAL ORANG KERJA 9 Orang

Perjalanan (PP) 2 hari


Pengukuran 39 hari
Processing dan Reporting 20 hari
TOTAL WAKTU 61 Hari

No Diskripsi Jml Sat Jml Sat


Hari

I PERSIAPAN
a Persiapan
- Biaya koordinasi, komunikasi dll Lsm Lsm Lsm

b Mobilisasi/Demobilisasi
- Transportasi Lokal Jakarta 5 Orang 2
- Transport Jakarta-Jambi 5 Orang 2
- Transport Balikpapan ke Lokasi 2 Mobil 2

II PEKERJAAN LAPANGAN
c Transportasi di Lokasi
- Kendaraan 1 Mobil 39
- BBM 40 liter 39

d Gaji
- Koord Lap/Team Leader 1 Org 61
- Data Processing 1 Org 61
- Surveyor Total Station 2 Org 61
- Ass Surveyor Total Station 1 Org 41
- Crew Total Station 6 Org 39
- Crew Rintisan 3 Org 39

e Konsumsi
- Koord Lap/Logistik/Team Leader 1 Org 61
- Data Processing 1 Org 61
- Surveyor Total Station 2 Org 61
- Ass Surveyor Total Station 1 Org 41
- Crew Total Station 6 Org 39
- Crew Rintisan 3 Org 39

f Peralatan
- Total Station 2 Unit 41
- GPS Handheld/navigasi 2 Unit 41
- Komputer + printer 2 Unit 61
- Radio HT 4 Unit 41
- Kompas Shunto 3 Buah 41
- Kamera 2 Buah 41

g Material
- Stationary (ATK) 2 Set Lsm
- Meteran 5 mtr 6 Buah Lsm
- Rubber Shoes 5 Psg Lsm
- Bateray u/ GPS Navigasi 3 box Lsm
- Tas lapangan 2 Buah 1
- Parang 6 Buah 1
- Base Camp 3 Unit 39
- Genset + BBM 1 Unit 39
'- Bench Mark (BM) beton 20 unit 10
- Bench Mark (BM) paralon 100 Buah 15

III PEMBUATAN LAPORAN


h Reporting
(Plotting, CD, Jilid dll) Lsm

Total (a+b+c+d+e+f+g+h)
SATUAN PER HA =
Total Biaya
CANA BIAYA
ELUAS + 100 Ha, SKALA : 1 : 1000
koso, Kab Paser, Kalimantan Timur

ALAT YANG DIGUNAKAN :


Total Station 2 buah

Poligon Utama 6,000 m


Poligon Cabang - m
Poligon Ray (per 50 meter) - m
Total Jalur Pengukuran Pol 6,000 m

Kapasitas pengukuran per-hari 500 m


Waktu Pengukuran poligon 6 hari

Topografi 100 HA
Kapasitas pengukuran per-hari 1.50 HA
Waktu Pengukuran Topografi
dengan 3 tim = 33 hari

Total Waktu pengukuran Topo


dan Poligon 39 hari

Harga Satuan Sub Total Total


Rupiah

3,000,000 3,000,000 3,000,000

200,000 2,000,000
750,000 7,500,000
1,000,000 4,000,000 13,500,000

750,000 29,500,000
10,000 15,733,333 45,233,333

500,000 30,666,667
300,000 18,400,000
300,000 36,800,000
250,000 10,333,333
150,000 35,400,000
150,000 17,700,000 149,300,000

50,000 3,066,667
50,000 3,066,667
50,000 6,133,333
50,000 2,066,667
50,000 11,800,000
50,000 5,900,000 32,033,333

350,000 28,933,333
50,000 4,133,333
50,000 6,133,333
30,000 4,960,000
30,000 3,720,000
30,000 2,480,000
50,360,000

1,000,000 2,000,000
50,000 300,000
100,000 500,000
200,000 600,000
150,000 300,000
100,000 600,000
200,000 23,600,000
100,000 3,933,333
200,000 4,000,000
50,000 5,000,000 40,833,333
-

10,000,000 10,000,000

= 344,260,000
688,520
= 344,260,000
tidak termasuk pajak
RENCANA BIAYA
SURVEY KERANGKA GPS GEODETIK
LOKASI : Seratai dan Bekoso, Kab Paser, Kalimantan Timur

VOLUME : 30.0 POINT


JUMLAH TIM PENGUKURAN YANG DIBUTUHKAN :
Koordinator Lapangan/Team Leader 1 Orang
Processing Data - Orang
Surveyor GPS 3 Orang
Ass. Surveyor GPS 1 Orang
5 Orang

TENAGA LOKAL :
TIM GPS (1 tim @ 4 orang) 9 Orang
TIM Rintisan (1 tim @ 2 orang) 3 Orang
TOTAL ORANG KERJA 12 Orang

Perjalanan (PP) 2 hari


Pengukuran 32 hari
Processing dan Reporting 10 hari
TOTAL WAKTU 44 Hari

No Diskripsi Jml Sat Jml Sat


Hari

I PERSIAPAN
a Persiapan
- Biaya koordinasi, komunikasi dll Lsm Lsm Lsm

b Mobilisasi/Demobilisasi
- Transportasi Lokal Jakarta 5 Orang 2
- Transport Jakarta-Balikpapan 5 Orang 2
- Transport Balikpapan ke Lokasi 1 Mobil 2

II PEKERJAAN LAPANGAN
c Transportasi di Lokasi
- Kendaraan 3 Mobil 32
- BBM 75 liter 32

d Gaji
- Koord Lap/Team Leader 1 Org 44
- Surveyor GPS 3 Org 44
- Ass Surveyor GPS 1 Org 34
- Crew GPS 9 Org 32
- Rintisan and Bench Mark 3 Org 32

e Konsumsi
- Koord Lap/Logistik/Team Leader 1 Org 44
- Surveyor GPS 3 Org 44
- Ass Surveyor GPS 1 Org 34
- Crew GPS 9 Org 32
- Rintisan and Bench Mark 3 Org 32

f Peralatan
- GPS Geodetik Dual Frekuensi 3 Unit 34
- GPS Handheld/navigasi 3 Unit 34
- Komputer + printer 1 Unit 44
- Radio HT 3 Unit 34
- Kamera 2 Buah 34

g Material
- Stationary (ATK) 1 Set Lsm
- Meteran 5 mtr 3 Buah Lsm
- Rubber Shoes 5 Psg Lsm
- Bateray u/ GPS Navigasi 2 box Lsm
- Base Camp 1 Unit 32
- Genset + BBM 1 Unit 32
'- Bench Mark (BM) beton 30 unit 10

III PEMBUATAN LAPORAN


h Reporting
(Plotting, CD, Jilid dll) Lsm

Total (a+b+c+d+e+f+g+h)
SATUAN PER Point =
Total Biaya
CANA BIAYA
ANGKA GPS GEODETIK
koso, Kab Paser, Kalimantan Timur

ALAT YANG DIGUNAKAN :


GPS Geodetik 3 UNIT

Pilar Beton 30 Unit


Pengikatan Referensi Bako 3 Point
Base Line 128 Line

Kapasitas pengukuran per-hari 4 Base line/Perhari


Pemasangan Bench Mark 3 titikk/perhari

Pemasangan Pilar Beton 10 Hari


Pengamatan GPS 32 Hari

Total Waktu Pengukuran GPS


dan Pemasangan Bench Mark 32 hari

Harga Satuan Sub Total Total


Rupiah

3,000,000 3,000,000 3,000,000

200,000 2,000,000
750,000 7,500,000
1,000,000 2,000,000 11,500,000

750,000 72,000,000
10,000 24,000,000 96,000,000

500,000 22,000,000
400,000 52,800,000
300,000 10,200,000
200,000 57,600,000
200,000 19,200,000 161,800,000

50,000 2,200,000
50,000 6,600,000
50,000 1,700,000
50,000 14,400,000
50,000 4,800,000 29,700,000

750,000 76,500,000
50,000 5,100,000
50,000 2,200,000
30,000 3,060,000
30,000 2,040,000
88,900,000

1,000,000 1,000,000
50,000 150,000
100,000 500,000
200,000 400,000
200,000 6,400,000
100,000 3,200,000
200,000 60,000,000
71,650,000 -

5,000,000 5,000,000

= 467,550,000
15,585,000
= 467,550,000
tidak termasuk pajak
RENCANA BIAYA
SURVEY RENCANA JALAN HAULING
LOKASI : Seratai dan Bekoso, Kab Paser, Kalimantan Timur

VOLUME : 30.0 KM
JUMLAH TIM PENGUKURAN YANG DIBUTUHKAN :
Koordinator Lapangan/Team Leader 1 Orang
Processing Data 1 Orang
Surveyor Total Station 2 Orang
Ass. Surveyor Total Station 2 Orang
6 Orang

TENAGA LOKAL :
TIM Total Station (1 tim @ 4 orang) 6 Orang
TIM Rintisan (1 tim @ 2 orang) 6 Orang
TOTAL ORANG KERJA 12 Orang

Perjalanan (PP) 2 hari


Pengukuran 32 hari
Processing dan Reporting 20 hari
TOTAL WAKTU 54 Hari

No Diskripsi Jml Sat Jml Sat


Hari

I PERSIAPAN
a Persiapan
- Biaya koordinasi, komunikasi dll Lsm Lsm Lsm

b Mobilisasi/Demobilisasi
- Transportasi Lokal Jakarta 6 Orang 2
- Transport Jakarta-Balikpapan 6 Orang 2
- Transport Balikpapan ke Lokasi 2 Mobil 2

II PEKERJAAN LAPANGAN
c Transportasi di Lokasi
- Kendaraan 1 Mobil 32
- BBM 40 liter 32

d Gaji
- Koord Lap/Team Leader 1 Org 54
- Data Processing 1 Org 54
- Surveyor Total Station 2 Org 54
- Ass Surveyor Total Station 2 Org 34
- Crew Total Station 6 Org 32
- Crew Rintisan 6 Org 32

e Konsumsi
- Koord Lap/Logistik/Team Leader 1 Org 54
- Data Processing 1 Org 54
- Surveyor Total Station 2 Org 54
- Ass Surveyor Total Station 2 Org 34
- Crew Total Station 6 Org 32
- Crew Rintisan 6 Org 32

f Peralatan
- Total Station 2 Unit 34
- GPS Handheld/navigasi 2 Unit 34
- Komputer + printer 1 Unit 54
- Radio HT 4 Unit 34
- Kompas Shunto 3 Buah 34
- Kamera 2 Buah 34

g Material
- Stationary (ATK) 2 Set Lsm
- Meteran 5 mtr 6 Buah Lsm
- Rubber Shoes 6 Psg Lsm
- Bateray u/ GPS Navigasi 3 box Lsm
- Tas lapangan 2 Buah 1
- Parang 6 Buah 1
- Base Camp 1 Unit 32
- Genset + BBM 1 Unit 32
'- Bench Mark (BM) beton 20 unit 10
- Bench Mark (BM) paralon 100 Buah 15

III PEMBUATAN LAPORAN


h Reporting
(Plotting, CD, Jilid dll) Lsm

Total (a+b+c+d+e+f+g+h)
SATUAN PER HA =
Total Biaya
CANA BIAYA
CANA JALAN HAULING
koso, Kab Paser, Kalimantan Timur

ALAT YANG DIGUNAKAN :


Total Station 2 buah

Poligon As Jalan 30 KM
Poligon Cabang -
Poligon Ray (per 25 meter) 60.05 KM
Total Jalur Pengukuran Pol 90 km

Pengukuran Poligon As Jalan 30 hari


Pengukuran Poligon Ray (per 25 me 30 hari

Topografi pelabuhan 5 Ha
Kapasitas pengukuran per-hari 1.50 HA
Waktu Pengukuran Topografi
dengan 3 tim = 2 hari

Total Waktu pengukuran Topo


dan Poligon 32 hari

Harga Satuan Sub Total Total


Rupiah

3,000,000 3,000,000 3,000,000

200,000 2,400,000
750,000 9,000,000
1,000,000 4,000,000 15,400,000

750,000 23,768,750
10,000 12,676,667 36,445,417

500,000 26,845,833
300,000 16,107,500
300,000 32,215,000
250,000 16,845,833
150,000 28,522,500
150,000 28,522,500 149,059,167

50,000 2,684,583
50,000 2,684,583
50,000 5,369,167
50,000 3,369,167
50,000 9,507,500
50,000 9,507,500 33,122,500

350,000 23,584,167
50,000 3,369,167
50,000 2,684,583
30,000 4,043,000
30,000 3,032,250
30,000 2,021,500
38,734,667

1,000,000 2,000,000
50,000 300,000
100,000 600,000
200,000 600,000
150,000 300,000
100,000 600,000
200,000 6,338,333
100,000 3,169,167
200,000 4,000,000
50,000 5,000,000 22,907,500
-

10,000,000 10,000,000

= 308,669,250
10,288,975
= 308,669,250
tidak termasuk pajak

Anda mungkin juga menyukai