No.

URAIAN

SAT

VOLUME

HARGASAT

HARGA

N01 1M2Mengikis/MengerokPermukaanCatTembokLama

Sodaapi

Kg

0.0500

35,600.00

1,780.00

Pekerja

Oh

0.1500

42,000.00

6,300.00

Mandor

Oh

0.0025

80,000.00

200.00

Jumlah

8,280.00

Dibulatkan

8,280.00

N02 1M2MendempulDanMenggosokKayu

Dempul

Kg

0.0800

35,800.00

2,864.00

Minyakcat

Kg

0.0200

38,400.00

768.00

Batuapung

Kg

0.0100

29,600.00

296.00

Pekerja

Oh

0.0400

42,000.00

1,680.00

Tukangcat

Oh

0.0400

65,000.00

2,600.00

Kepalatukang

Oh

0.0040

75,000.00

300.00

Mandor

Oh

0.0025

80,000.00

200.00

Jumlah

8,708.00

Dibulatkan

8,708.00

N03 1M2PengecatanBidangKayuLamaSetaraSieve

Plamir

Kg

0.1500

25,000.00

3,750.00

Catdasar

Kg

0.1700

30,000.00

5,100.00

Kg

0.1700

41,700.00

7,089.00

Pekerja

Oh

0.0700

42,000.00

2,940.00

Tukangcat

Oh

0.0750

65,000.00

4,875.00

Kepalatukang

Oh

0.0075

75,000.00

562.50

Mandor

Oh

0.0025

80,000.00

200.00

Jumlah

24,516.50

Dibulatkan

24,517.00

Catpenutupsetarasieve
2x

N04 1M2PengecatanBidangKayuBaruSetaraSieve

Catmeni

Kg

0.2000

30,400.00

6,080.00

Plamir

Kg

0.1500

25,000.00

3,750.00

Catdasar

Kg

0.1700

30,000.00

5,100.00

Kg

0.3500

41,700.00

14,595.00

Pekerja

Oh

0.0700

42,000.00

2,940.00

Tukangcat

Oh

0.1050

65,000.00

6,825.00

Catpenutup3xsetara
sieve

Kepalatukang

Oh

0.0040

75,000.00

300.00

Mandor

Oh

0.0025

80,000.00

200.00

Jumlah

39,790.00

Dibulatkan

39,790.00

N05 1M2PelaburanBidangKayudenganPolitur

Politur

Ltr

0.1500

48,000.00

7,200.00

Politurjadi

Ltr

0.3720

112,700.00

41,924.40

Ampelas

Lbr

2.0000

5,000.00

10,000.00

Tukangcat

Oh

0.0600

65,000.00

3,900.00

Kepalatukang

Oh

0.0160

75,000.00

1,200.00

Mandor

Oh

0.0025

80,000.00

200.00

Jumlah

64,424.40

Dibulatkan

64,424.00

N06 1M2PelaburanBidangKayudenganCatResidudanTer

Residuatauter

Ltr

0.3500

8,100.00

2,835.00

Pekerja

Oh

0.1000

42,000.00

4,200.00

Mandor

Oh

0.0060

80,000.00

480.00

Jumlah

7,515.00

Dibulatkan

7,515.00

N07

1M2PengecatanTembokBaruSetara
ICI

Plamirtembok

Kg

0.1000

25,000.00

2,500.00

Catdasar

Kg

0.1000

30,000.00

3,000.00

Catpenutup2xsetaraICI

Kg

0.2600

75,000.00

19,500.00

Pekerja

Oh

0.0200

42,000.00

840.00

Tukangcat

Oh

0.0630

65,000.00

4,095.00

Kepalatukang

Oh

0.0063

75,000.00

472.50

Mandor

Oh

0.0025

80,000.00

200.00

Jumlah

30,607.50

Dibulatkan

30,608.00

N08 1M2PengecatanTembokLamaSetaraICI

Catdasar

Kg

0.1200

30,000.00

3,600.00

Catpenutup2x

Kg

0.1800

75,000.00

13,500.00

Pekerja

Oh

0.0280

42,000.00

1,176.00

Tukangcat

Oh

0.0420

65,000.00

2,730.00

Kepalatukang

Oh

0.0042

75,000.00

315.00

Mandor

Oh

0.0025

80,000.00

200.00

Jumlah

21,521.00

Dibulatkan

21,521.00

N09 1M2PengecatanPlafond(3x)SetaraICI

CattemboksetaraICI

Kg

0.2000

75,000.00

15,000.00

Plamirtembok

Kg

0.1600

25,000.00

4,000.00

Rolcat

Bh

0.0100

32,500.00

325.00

Stegerwerk

Ls

1.0000

1,000.00

1,000.00

Ampelas

Lbr

0.5000

5,000.00

2,500.00

Pekerja

Oh

0.2000

42,000.00

8,400.00

Tukangcat

Oh

0.3000

65,000.00

19,500.00

Kepalatukang

Oh

0.0300

75,000.00

2,250.00

Mandor

Oh

0.0100

80,000.00

800.00

Jumlah

53,775.00

Dibulatkan

53,775.00

N10 1M2PengecatanPlafond(3x)SetaraVinilex

CattemboksetaraVinilex

Kg

0.2000

25,000.00

5,000.00

Plamirtembok

Kg

0.1600

25,000.00

4,000.00

Rolcat

Bh

0.0100

32,500.00

325.00

Stegerwerk

Ls

1.0000

1,000.00

1,000.00

Ampelas

Lbr

0.5000

5,000.00

2,500.00

Pekerja

Oh

0.2000

42,000.00

8,400.00

Tukangcat

Oh

0.3000

65,000.00

19,500.00

Kepalatukang

Oh

0.0300

75,000.00

2,250.00

Mandor

Oh

0.0100

80,000.00

800.00

Jumlah

43,775.00

Dibulatkan

43,775.00

N10
r'

1M2PengecatanPlafond(2x)SetaraVinilex

CattemboksetaraVinilex

Kg

0.1300

25,000.00

3,250.00

Plamirtembok

Kg

0.1100

25,000.00

2,750.00

Rolcat

Bh

0.1000

32,500.00

3,250.00

Stegerwerk

Ls

0.6700

1,000.00

670.00

Ampelas

Lbr

0.3300

5,000.00

1,650.00

Pekerja

Oh

0.1300

42,000.00

5,460.00

Tukangcat

Oh

0.2000

65,000.00

13,000.00

Kepalatukang

Oh

0.0200

75,000.00

1,500.00

Mandor

Oh

0.0100

80,000.00

800.00

Jumlah

32,330.00

Dibulatkan

32,330.00

N11 1M2MemasangWallpaper

Wallpaper

m2

1.2000

55,700.00

66,840.00

LemPerekat

Kg

0.2500

35,700.00

8,925.00

Pekerja

Oh

0.3500

42,000.00

14,700.00

Tukangcat

Oh

0.1750

65,000.00

11,375.00

Kepalatukang

Oh

0.0170

75,000.00

1,275.00

Mandor

Oh

0.0017

80,000.00

136.00

Jumlah

103,251.00

Dibulatkan

103,251.00

N12 1M2PengecatanPermukaanBajadenganMeniBesi

Menibesi

Kg

0.1000

30,400.00

3,040.00

Kuas3"

Bh

0.0100

16,000.00

160.00

Pekerja

Oh

0.0200

42,000.00

840.00

Tukangcat

Oh

0.2000

65,000.00

13,000.00

Kepalatukang

Oh

0.0200

75,000.00

1,500.00

Mandor

Oh

0.0100

80,000.00

800.00

Jumlah

19,340.00

Dibulatkan

19,340.00

N13 1M2PengecatanPermukaanBajadenganMeniBesidanPerancah

Menibesi

Kg

0.1000

30,400.00

3,040.00

Kuas3"

Bh

0.0100

16,000.00

160.00

Kayuperancah

m3

0.0020

2,069,800.00

4,139.60

Pekerja

Oh

0.2500

42,000.00

10,500.00

Tukangcat

Oh

0.2250

65,000.00

14,625.00

Kepalatukang

Oh

0.0225

75,000.00

1,687.50

Mandor

Oh

0.0075

80,000.00

600.00

Jumlah

34,752.10

Dibulatkan

34,752.00

N14 1M2PengecatanPermukaanBajaLapisseng(galbani)secaramanual1lpscat2um

CatbesisetaraICI

Kg

0.3000

67,700.00

20,310.00

Pekerja

Oh

0.0060

42,000.00

252.00

Tukangcat

Oh

0.0600

65,000.00

3,900.00

Kepalatukang

Oh

0.0120

75,000.00

900.00

Mandor

Oh

0.0060

80,000.00

480.00

Jumlah

25,842.00

Dibulatkan

25,842.00

N15 1M2PengecatanTembokBaruSetaraVinilex(2xlaburan)

Plamirtembok

Kg

0.1000

25,000.00

2,500.00

Catdasar

Kg

0.1000

30,000.00

3,000.00

Kg

0.2600

25,000.00

6,500.00

Pekerja

Oh

0.0200

42,000.00

840.00

Tukangcat

Oh

0.0630

65,000.00

4,095.00

Kepalatukang

Oh

0.0063

75,000.00

472.50

Mandor

Oh

0.0025

80,000.00

200.00

Jumlah

17,607.50

Dibulatkan

17,608.00

Catpenutup2xsetara
vinilex

N15r' 1M2PengecatanTembokBaruSetaraVinilex(3xlaburan)

Plamirtembok

Kg

0.1000

25,000.00

2,500.00

Catdasar

Kg

0.1000

30,000.00

3,000.00

Kg

0.3900

25,000.00

9,750.00

Pekerja

Oh

0.0300

42,000.00

1,260.00

Tukangcat

Oh

0.0945

65,000.00

6,142.50

Kepalatukang

Oh

0.0095

75,000.00

712.50

Mandor

Oh

0.0038

80,000.00

304.00

Jumlah

23,669.00

Dibulatkan

23,669.00

Catpenutup3xsetara
vinilex

N16 1M2PengecatanTembokLamaSetaraVinilex

Catdasar

Kg

0.1200

30,000.00

3,600.00

Catpenutup2x

Kg

0.1800

25,000.00

4,500.00

Pekerja

Oh

0.0280

42,000.00

1,176.00

Tukangcat

Oh

0.0420

65,000.00

2,730.00

Kepalatukang

Oh

0.0042

75,000.00

315.00

Mandor

Oh

0.0025

80,000.00

200.00

Jumlah

12,521.00

Dibulatkan

12,521.00