KEGIATAN
LOKASI
KANTOR
T. A.
:
:
:
:
NO
JENIS PEKERJAAN
SAT.
1
I
1
2
3
4
PEKERJAAN PERSIAPAN
Pengukuran dan Bowplank
Pembersihan lahan
Administrasi, Dokumentasi dan P3K
Papan Proyek
1
2
3
PEKERJAAN TANAH
Galian Tanah
Urugan Tanah Kembali
Timbunan Tanah
1
2
3
4
5
6
7
1
2
PEKERJAAN PENGECATAN
Pengecatan Tembok
Pek.Pintu Pagar dan Papan Nama Kantor
II
III
IV
VOLUME
PEKERJAAN
HARGA SATUAN
(Rp)
4
TOTAL HARGA
(Rp)
m'
Ls
Ls
Ls
35.66
1.00
1.00
1.00
68,950.00
500,000.00
300,000.00
450,000.00
3,708,757.00
2,458,757.00
500,000.00
300,000.00
450,000.00
m3
28.02
7.18
2.88
34,800.00
16,680.00
167,700.00
1,578,621.61
974,991.60
119,833.29
483,796.72
3.7410
14.0180
34.4400
68.8800
0.5292
0.7650
68.8800
332,730.00
667,830.00
97,698.80
39,841.20
4,950,100.00
4,950,100.00
11,595.00
23,920,475.42
1,244,742.93
9,361,640.94
3,364,746.67
2,744,261.86
2,619,592.92
3,786,826.50
798,663.60
68.88
2.00
33,375.00
3,500,000.00
2,298,870.00
2,298,870.00
7,000,000.00
m3
m3
m3
m3
m2
m2
m3
m3
m2
M2
SET
JUMLAH
31,506,724.03
PPN 10%
3,150,672.40
GRAND TOTAL
34,657,396.43
DIBULATKAN
34,657,000.00
Benteng, 10 AGUSTUS 2016
Dibuat Oleh :
KONSULTAN PERENCANA
CV. ICHSAN KONSULTAN
WAHYUDI KURNIAWAN, ST
TEAM LEADER