PERIHAL : BILL OF QUANTITY

PROYEK : PEMBANGUNAN KITA


ALAMAT : JL. BINJAI, BELAKANG SWALAYAN MANDIRI
UKURAN

HARGA SATUAN MODAL


NO. ITEM PEKERJAAN VOLUME SAT. Bahan Upah HARGA SATUAN JUMLAH HARGA
(Rp.) (Rp.) (Rp.) (Rp.)
A PEKERJAAN PENDAHULUAN
1 Pekerjaan Pembersihan 53.96 m 3,000 3,000 161,880
2 Pekerjaan Pemasangan dan Pengukuran Bowplank 36.00 m 26,000 4,000 30,000 1,080,000

Subtotal A 1,241,880
B PEKERJAAN STRUKTUR BAWAH
1 Pekerjaan Galian Tanah (15 x 20 ) 2.31 m - 85,000 85,000 196,350
2 Pekerjaan Pasir Urug t=5 cm 0.41 m 209,000 20,000 229,000 94,463
3 Pekerjaan Lantai kerja Sloof Camp 1:3:5 0.25 m 460,000 100,000 560,000 138,600
4 Pekerjaan Pengecoran Sloof (15 x 20) 1.65 m 755,000 100,000 855,000 1,410,750

Subtotal B 1,840,163
C. PEKERJAAN DINDING DAN PENGECATAN
1 Pasangan 1/2 Bata Camp 1:4 128.50 m 57,000 25,000 82,000 10,537,000
2 Pekerjaan Plasteran Camp 1:4 199.70 m 13,000 20,000 33,000 6,590,100
3 Pekerjaan Acian 199.70 m 3,000 7,000 10,000 1,997,000
4 Pekerjaan Pengecetan
A. Pengecetan Dinding 199.70 m 9,137 10,000 20,000 3,994,000
B. Pengecetan Kusen dan Pintu 52.40 m 36,775 21,087 58,000 3,039,084

Subtotal C 26,157,184
D PEKERJAAN KUSEN DAN PINTU
1 Pintu (PJ1) 6.00 Unit
Spesifikasi :
* Kusen ex. SK 850,000 120,000 970,000 5,820,000
* Daun Pintu ex. SK uk. 80 x 210 cm 1,200,000 120,000 1,320,000 7,920,000
* Aksesoris 250,000 25,000 275,000 1,650,000

Subtotal D 15,390,000
E PEKERJAAN KERAMIK
1 Pekerjaan Pasir Urug t = 5 cm 2.70 m 209,000 20,000 229,000 617,842
2 Pekerjaan Lantai Kerja Camp 1:3:5 1.62 m 460,000 100,000 560,000 906,528
3 Pekerjaan Pemasangan Keramik Uk 40x40 52.44 m 110,500 32,500 143,000 7,498,920

Subtotal E 9,023,290
F PEKERJAAN LISTRIK
1 Instalasi Titik Lampu 6.00 Titik 130,500 65,000 196,000 1,176,000
2 Instalasi Stop Kontak 6.00 Titik 130,500 65,000 196,000 1,176,000

Subtotal F 2,352,000
HARGA SATUAN MODAL
NO. ITEM PEKERJAAN VOLUME SAT. Bahan Upah HARGA SATUAN JUMLAH HARGA
(Rp.) (Rp.) (Rp.) (Rp.)
G PEKERJAAN SANITER
1 Saklar Seri ex. Panasonic 6.00 Unit 32,500 5,000 38,000 228,000
2 Stop Kontak ex. Panasonic 6.00 Unit 32,500 5,000 38,000 228,000
3 Fitting Lampu 6.00 Unit 25,000 5,000 30,000 180,000
4 Bola Lampu 18 watt Hannoc 6.00 Unit 25,000 5,000 30,000 180,000

Subtotal G 816,000
H PEKERJAAN RENOVASI KIOS BAGIAN DEPAN
1 Pekerjaan Pengecetan Dinding Luas Bangunan (26 x 3.8 m) 378.84 m 9,137 10,000 20,000 7,576,800
2 Pekerjaan Pengecetan Plafond ( 4.33 x 3.8 ) 98.72 m 4,830 9,000 14,000 1,382,136
3 Pekerjaan Bongkar Pasang Pintu Besi 6.00 Unit - 850,000 850,000 5,100,000
4 Pekerjaan Pasang 1/2 Batu Bata Camp 1:4 10.40 m 57,000 25,000 82,000 852,800

Subtotal G 14,911,736
GRAND TOTAL 71,732,253
PEMBULATAN 71,700,000
HARGA PER METER
Terbilang : Tujuh Puluh Satu Juta Tujuh Ratus Ribu Rupiah