NO. ITEM PEKERJAAN VOLUME SATUAN (Rp) (Rp) I PENDAHULUAN
1 Pembersihan lahan 11.730 m2 750 8.797.500
2 Pengukuran dan pemasangan bouwplank 438 m 12.000 5.256.000 3 Direksikeet & gudang material 1 ls 4.000.000 4.000.000 SUB TOTAL I 18.053.500 II STRUKTUR BAMBU
1 Bambu petung 1.170 m 24.000 28.080.000
2 Bambu bir 7.700 m 11.000 84.700.000 3 Paranet 16.300 m2 9.500 154.850.000 SUB TOTAL II 267.630.000 TOTAL 285.683.500 PEMBULATAN 285.683.500