Oleh:
Perencana Arsitektur:
PT. MENARA KARSA MANDIRI
Perencana M/E:
PT. STRONG
Konsultan MK:
PT. AMCK
Kontraktor :
PT. CBM
1. PENDAHULUAN
Gedung tinggi
kembar 4:
Tower B, Tower D,
Tower AC, Tower E
Masing-masing tower:
21 lapis
Pekerjaan Corewall
Bandung :
Wilayah Gempa 4
Wilayah Gempa Indonesia dgn Percepatan puncak batuan dasar dgn periode ulang 500 tahun
2. DATA TANAH DAN KEGEMPAAN
Wilayah Gempa Indonesia dgn Percepatan puncak batuan dasar dgn periode ulang 2500 tahun
2. PERBANDINGAN GEMPA LAMA DAN BARU
Perbandingan Nilai Cd (Lama vs Baru)
Bangunan Menengah 15 Lt, Medium Soil
∑
-13,00 Clayey silt, silty sand lenses, very stiff Su = 70 kPa
N > 50 5 ti
30
-15,00 Silty sand, very dense Su = 60 kPa
Su = m
i= 1
= = 44,1 < 50
N = 24 6
0,68
-18,50 Clayey silt, very stiff, hard Su = 95 kPa
N = 50 7
∑i= 1
t i /Sui
-24,50 Silty sand, very dense, clayey silt, hard Su=100 kPa
N = 23 8
-30,50 Clayey silt, very stiff, silty sand lenses, dense Su = 90 kPa
N > 50 9
-34,50 Silty sand, very dense Su=170 kPa
N = 19 10 Jenis Tanah di Lokasi
-44,50 Silty clay, very stiff Su = 75 kPa
N = 30 11 Gedung:
-49,00 Silty sand, medium dense Su=200 kPa
Percepatan puncak
batuan dasar: 0,20 g
Percepatan puncak ``
muka tanah: 0,34 g
Percepatan respons
maksimum: 0,85 g
Kedalaman pondasi
pancang spun pile= 15m
Masing-masing tower
dimodelkan secara
sendiri,karena tidak ada
penyatuan di level lt.dasar
TAMPAK MODE SHAPE -1 DARI TOWER D ABB nya.
3. STRUKTUR ATAS
3.1. SISTEM STRUKTUR
Eksentrisitas rencana antara
Pusat Massa Lantai dan Pusat
Rotasi Lantai ditinjau untuk
masing-masing arah gempa
Persyaratan:
T1 ≤ 0,18 jml tingkat = 0,18 x 25 = 3,57 det
T1= 2,96 det, T2= 2,22 det, T3 = 1,85 det (OK)
Gerak ragam ke-1 harus dominan dalam translasi
Gerak ragam ke-2, dominan dalam translasi-X (OK)
Gerak ragam ke-3, dominan dalam rotasi (OK)
3. STRUKTUR ATAS
Pembebanan Ultimit U :
Struktur Atas
U = 1,2 Dn + 1,6 Ln
U = 1,05 (Dn + Ln ± 1,0 Enx ± 0,3 Eny)
U = 1,05 (Dn + Ln ± 0,3 Enx ± 1,0 Eny)
U = 0,90 Dn + 1,10 (± 1,0 Enx ± 0,3 Eny)
U = 0,90 Dn + 1,10 (± 0,3 Enx ± 1,0 Eny)
3. STRUKTUR ATAS
3. STRUKTUR ATAS
Desain kapasitas:
Harus dipenuhi prinsip “kolom kuat balok
lemah”: kapasitas (momen leleh) penampang
kolom harus lebih besar dari kapasitas (momen
leleh) penampang baloknya disetiap pertemuan
berdasarkan tulangan terpasang
Panel pertemuan balok-kolom tdk boleh gagal
dlm geser lebih dahulu pada saat sendi-sendi
plastis terjadi pada ujung balok
3. STRUKTUR ATAS
3.7. DETAIL PENULANGAN COREWALL
Penulangan area boundary wall dan edge wall
SANSPRO For Windows V.4.90 - Output
Concrete Shearwall Stress and Design Calculation
Using Shearwall Design Group Code
Using ACI-2002 and PBI-2003 Concrete Code
(C) Nathan Madutujuh, 1989-2008
ASSUMPTIONS:
- Wall Thickness is already included for Area and Static Moment
- Each shearwall plane must be assigned a SAME and UNIQUE group id number
- All wall segments in a plane must have equal group id number
- Elements in a Group must have equal Thickness/Properties
- Shearwall for floor f1 is the one supporting floor f1 (below floor)
- Static Moment is calculated at centroid of element group
Syy
+----+ +----+
| | | |
| | Sxx | | Mxx,Mxy,Qx
+----+ +----+
Txy Myy,Mxy,Qy
FLOOR # 1, LEVEL= 300.00, WALL LAYOUT=1
AR IN MAJOR DIRECTION -------------- MOMENT AND SHEAR IN MINOR DIRECTION ------------ BOUNDARY EDGES
Forces | Edge Vert. Horiz.| Factored Forces |Vert. Horiz. Horiz.| Boundary
Vmax Mmax |Rebar Spcv Spch | Vminor Mminor|Spcv Spch spcvh | Lb Hb
-----------------------------------------------------------------------------------------------------
155594.5 10661669.0|15d19 d12-354 d13-122| 0.0 877719.2|d12-233 d13- 933 72 | 93.33 280.
101561.9 2336622.9|10d19 d12-354 d13-124| 0.0 461276.0|d12-206 d13- 617 72 | 61.67 185.
93698.3 3257828.4|10d19 d12-354 d13-138| 0.0 581533.5|d12-206 d13- 617 72 | 61.67 185.
281112.2 10825521.7|16d19 d12-354 d13- 63| 0.0 543031.8|d12-250 d13-1000 72 |100.00 300.
174001.6 7016226.4|11d19 d12-354 d13- 67| 0.0 388605.6|d12-217 d13- 650 72 | 65.00 195.
-----------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------