Anda di halaman 1dari 509

HARGA

NO URAIAN PEKERJAAN ANALISA VOLUME SAT SATUAN (Rp)

A. PEMBANGUNAN R. RAPAT FRAKSI


I PEK. PERSIAPAN
1 Pengukuran dan Pemasangan Bowplank 2.2.1.4.a 74,16 M Rp 50,831.96
2 Papan Nama Kegiatan - 1,00 Ls Rp 500,000.00
Sub Total
II PEK. PONDASI
1 Galian tanah 2.3.1.4 21,38 M3 Rp 107,916.00
2 Urugan Galian Tanah Pondasi 2.3.1.9.a 13,89 M3 Rp 27,025.00
3 Tiang Pancang (Mini Pile ) uk. Π 25 x 25, 8 D 13 K 350 - 6m/18m Unit Price 120,00 Btg
4 Pemancangan Tiang Pancang - 680,00 M'
5 Pemecahan Ujung Tiang Pancang - 40,00 Btg
6 Urugan pasir di bawah pondasi 2.3.1.11 2,25 M3 Rp 170,568.00
7 Lantai kerja beton tumbuk 1:3:5 4.1.1.4 1,13 M3 Rp 1,028,956.56
8 Pek. Pondasi P1
- Tapak Pondasi
a. Bekesting 4.1.1.20.a 24,00 M2 Rp 174,194.64
b. Tulangan DIA. 16 4.1.1.17 119,32 Kg Rp 14,817.75
c. Beton K250 4.1.1.8 9,00 M3 Rp 1,342,148.13
- Kolom Pondasi 35/35
b. Tulangan DIA. 16 (overstek) 4.1.1.17 163,28 Kg Rp 14,817.75
- Sloff Pondasi 20/40
a. Bekesting 4.1.1.21 56,00 M2 Rp 213,744.75
b. Tulangan DIA. 16 4.1.1.17 527,52 Kg Rp 14,817.75
c. Begl dia.10 4.1.1.17 278,26 Kg Rp 14,817.75
d. Beton K250 4.1.1.8 4,48 M3 Rp 1,342,148.13
Sub Total
III PEK. STRUKTUR BETON BERTULANG
Lantai 1
1 Kolom 35/35
a. Bekesting 4.1.1.22.a 68,20 M2 Rp 352,525.83
b. Tulangan DIA 16 4.1.1.17 753,60 Kg Rp 14,817.75
c. begl dia. 10 4.1.1.17 215,26 Kg Rp 14,817.75
d. Beton K250 4.1.1.8 5,29 M3 Rp 1,342,148.13
2 Balok 30/60
a. Bekesting 4.1.1.23.a 52,44 M2 Rp 362,615.01
b. Tulangan DIA 16 4.1.1.17 536,94 Kg Rp 14,817.75
c. Begl dia. 10 4.1.1.17 257,25 Kg Rp 14,817.75
d. Beton K250 4.1.1.8 5,53 M3 Rp 1,342,148.13
3 Balok 25/55
a. Bekesting 4.1.1.23.a 54,12 M2 Rp 362,615.01
b. Tulangan DIA 16 4.1.1.17 621,72 Kg Rp 14,817.75
c. Begl dia. 10 4.1.1.17 262,48 Kg Rp 14,817.75
d. Beton K250 4.1.1.8 4,71 M3 Rp 1,342,148.13
4 Balok B2 20/30
a. Bekesting 4.1.1.23.a 61,54 M2 Rp 362,615.01
b. Tulangan Utama 4.1.1.17 564,72 Kg Rp 14,817.75
c. Begl dia. 8 4.1.1.17 202,61 Kg Rp 14,817.75
d. Beton K250 4.1.1.8 3,76 M3 Rp 1,342,148.13
Lantai 2
5 Kolom K 250 35/35
a. Bekesting 4.1.1.22.a 49,60 M3 Rp 352,525.83
b. Tulangan DIA 16 4.1.1.17 502,40 Kg Rp 14,817.75
c. begl dia. 10 4.1.1.17 153,76 Kg Rp 14,817.75
d. Beton K250 4.1.1.8 3,84 M3 Rp 1,342,148.13
6 Kolom Praktis 11/11 4.1.1.35 85,80 M Rp 91,878.91
7 Balok Praktis 11/11 4.1.1.35 33,00 M Rp 91,878.91
8 Plat Lantai 2
a. Bekesting 4.1.1.24.a 163,00 M2 Rp 396,225.83
b. Wiremesh M5 4.1.1.17 717,20 Kg Rp 14,817.75
c. Beton K250 4.1.1.8 50,01 M3 Rp 1,342,148.13
9 Ring Balk 15/40
a. Bekesting 4.1.1.23.a 78,02 M2 Rp 362,615.01
b. Tulangan Utama dia. 10 4.1.1.24.a 308,76 Kg Rp 396,225.83
c. Begl dia. 8 4.1.1.17 164,56 Kg Rp 14,817.75
d. Beton K250 4.1.1.8 3,29 M3 Rp 1,342,148.13
10 Tangga
a. Bekesting 4.1.1.26 17,01 M2 Rp 359,399.15
b. besi dia. 10 4.1.1.17 318,99 Kg Rp 14,817.75
c. Beton K250 4.1.1.8 3,36 M3 Rp 1,342,148.13
Sub Total
IV PEK. ATAP
1 Rangka Atap Baja Ringan - 289,26 M2
2 Penutup Atap Gnteng Metal Pasir 0.35 4.5.2.32.f 289,26 M2 Rp 132,158.00
3 Perabung Atap Genteng Metal Pasir 0.35 A.4.5.2.36.a 30,39 M1 Rp 170,573.75
4 Lisplank Papan GRC Tekstur Kayu - 172,28 M1
Sub Total
V PEK. LANTAI, DINDING
1 Cor Lantai t. 20 cm k250 (lantai 1) 4.1.1.10 57,20 M2 Rp 1,384,244.46
2 Lantai Flooring (R. Rapat ) 4.4.3.46 112,00 M2 Rp 492,384.00
3 List Lantai Flooring (R. Rapat ) - 44,00 M2
4 Lantai Keramik Uk. 60/60 Setaraf Indogress (R. Hall/lt 2 ) 4.4.3.34.c 50,69 M2
5 Lantai Keramik Tangga Uk. 30/60 Setaraf Indogress (lt 2) 4.4.3.34.c 25,50 M2
6 Dinding Pasangan Batako 4.4.1.17.b 200,88 M2 Rp 104,089.61
7 Plesteran dinding, Tiang & Balok 4.4.2.14 865,61 M2 Rp 75,687.37
8 Papan Belian Eksterior A.4.6.2.2. 45,00 M2 Rp 128,800.00
9 Papan Belian (Kolom lt 1) A.4.6.2.2. 11,20 M2 Rp 128,800.00
10 Pemasangan Walpeper (r. rapat) - 142,12 M2
11 Pemasangan Walpeper (r. hall dan kolom lt 2) - 35,62 M2
Sub Total
VI PEK. PLAFOND
1 Pekerjaan Plafond lt 1
a. Plafond GRC Ekspos Plat Lantai A.4.5.1.7.a 183,52 M2 Rp 53,479.37
2 Pekerjaan Plafond lt 2
R. RAPAT
a. Rangka Plafond furing Ruang Rapat (lengkung) 4.2.1.21.a 89,60 M2
b. Rangka Plafond furing Flat 4.2.1.21.a 93,00 M2
c. Plafond Gypsum (lt 2) A.4.5.1.7. 194,27 M2 Rp 54,760.01
d. Trap Bias (r. rapat) - 59,20 M
e. Rangka Ekspos Melengkung (r. rapat) - 60,80 M
f. List Profil 5 cm (r. rapat) - 59,20 M
g. List Profil 15 cm (r. rapat) - 44,00 M
3 R. HALL
a. Rangka Plafond furing 4.2.1.21.a 75,00 M2
b. Plafond Gypsum (lt 2) 4.2.1.21.a 75,00 M2
4 PLAFOND KAKI ATAP - M
a. Rangka Plafond furing Flat 4.2.1.21.a 77,00 M2
b. Plafond Gypsum (lt 2) A.4.5.1.7. 77,00 M2
Sub Total
VII PEK. PINTU, JENDELA, KOSEN, VENTILASI
1 Pintu, Kaca Alumunium 4" Lengkap (2 Daun) - 2,00 Unit
2 Daun Jendela 3" + Kaca 6 mm Lengkap - 30,00 M2
Sub Total
VIII PEK. INSTALASI LISTRIK
1 Instalasi Titik Lampu ( kabel di dalam dinding + pipa kabel/SNI) - 22,000 Titik
2 Stop Kontak + Inbodus (setara panassonic) - 10,000 Titik
3 Saklar Ganda + Inbodus (setara panassonic) - 6,000 Buah
4 Saklar Tunggal + Inbodus (setara panassonic) - 2,000 Buah
5 Lampu Gantung Klasik - 1,000 Buah
6 Lampu LED 14 watt (setara panassonic/philips) - 22,000 Buah
7 Lampu Bias (1 pcs = 5m) (setara panassonic/philips) - 6,000 Pcs
8 Trafo 10 A (setara panassonic/philips) - 4,000 Buah
9 Box MCB (setara panassonic/philips) - 1,000 Buah
Sub Total
IX PEKERJAAN PENGECATAN
1 Cat Tembok/Setara Mowilex A.4.7.1.10.c 1.237,50 M2
2 Cat Tembok (cat dasar untuk walpeper) A.4.7.1.10.d 177,74 M3
3 Cat Kilat/Setara Avian A.4.7.1.4. 115,44 M2
Sub Total
X PEK. LAIN-LAIN
1 Ornamen Kayu (lisplank dan Ornamen Bunga depan) - 1,00 Lsm
2 Pagar Tangga Kayu Bengkirai + Gagang - 21,20 M
3 Kolom Entrance Utama - 1,00 Unit
4 Membuat List Profil Entrance Depan - 12,00 M
5 List Profil Kayu Belian (kolom lt 1) - 8,00 Unit
6 List Profil Rangka Furing + Gypsum (entrance Pintu) - 11,60 M
7 Membuat Sambungan Overstek Ke Bangunan Lama - 1,00 Lsm
8 Pekerjaan Pembongkaran Dinding Bangunan Utama - 1,00 Lsm
9 Dinding Pas. Batako (Bangunan Lama) 4.4.1.17.b 31,50 M2
10 Plesteran dinding 4.4.2.14 63,00 M2
11 Paving Blok Samping Bangunan Lama - 29,15 M2
Sub Total
B PEK. SELASAR PENGHUBUNG
I PEK. PONDASI
1 Galian tanah 2.2.1.4.a 4,28 M3
2 Urugan Galian Tanah Pondasi 2.3.1.9.a 2,78 M3
3 Tiang Pancang (Mini Pile ) uk. Π 25 x 25, 8 D 13 K 350 - 6m Unit Price 24,00 Btg
4 Pemancangan Tiang Pancang - 136,00 M'
5 Pemecahan Ujung Tiang Pancang - 8,00 Btg
6 Urugan pasir di bawah pondasi 2.3.1.11 0,45 M3
7 Lantai kerja beton tumbuk 1:3:5 4.1.1.4.a 0,23 M3
8 Pek. Pondasi P1
- Tapak Pondasi
a. Bekesting 4.1.1.20.a 4,80 M2
b. Tulangan DIA. 16 4.1.1.17 23,86 Kg
c. Beton K250 4.1.1.8 1,80 M3
- Kolom Pondasi 35/35
b. Tulangan DIA. 16 (overstek) 4.1.1.17 32,66 Kg
- Slop Pondasi 20/40
a. Bekesting 4.1.1.21 19,16 M2
b. Tulangan DIA. 16 4.1.1.17 180,49 Kg
c. Begl dia.10 4.1.1.17 95,23 Kg
d. Beton K250 4.1.1.8 1,53 M3
Sub Total
II PEK. STRUKTUR BETON BERTULANG
1 Kolom 35/35
a. Bekesting 4.1.1.22 b 10,91 M2
b. Tulangan DIA 16 4.1.1.17 165,79 Kg
c. begl dia. 10 4.1.1.17 54,56 Kg
d. Beton K250 4.1.1.8 1,69 M3
2 Balok 25/50
a. Bekesting 4.1.1.23.b 16,66 M2
b. Tulangan DIA 16 4.1.1.17 235,41 Kg
c. Begl dia. 10 4.1.1.17 92,22 Kg
d. Beton K250 4.1.1.8 1,61 M3
3 Balok B2 20/30
a. Bekesting 4.1.1.23.b 3,40 M2
b. Tulangan Utama 4.1.1.17 31,20 Kg
c. Begl dia. 8 4.1.1.17 11,09 Kg
d. Beton K250 4.1.1.8 0,21 M3
4 Ring Balk 15/40
a. Bekesting 4.1.1.23.b 13,83 M2
b. Tulangan Utama dia. 10 4.1.1.17 61,98 Kg
c. Begl dia. 8 4.1.1.17 31,21 Kg
d. Beton K250 4.1.1.5 0,66 M3
5 Kolom Praktis 11/11 4.1.1.35 6,60 M
6 Balok Praktis 11/11 4.1.1.35 5,00 M
7 Plat Lantai 2
a. Bekesting 4.1.1.24.a 20,83 M2
b. Wiremesh M5 4.1.1.17 18,87 Kg
c. Beton K250 B. 13.d.2 2,50 M3
Sub Total
III PEK. ATAP
1 Rangka Atap Baja Ringan - 35,12 M2
2 Penutup Atap Gnteng Metal Pasir 0.35 4.5.2.32.f 35,12 M2
3 Perabung Atap Genteng Metal Pasir 0.35 A.4.5.2.36.a 14,66 M
4 Lisplank Papan GRC Tekstur Kayu - 29,32 M
5 Membuat Sambungan Atap Ke Bangunan Lama - 1,00 lsm
Sub Total
IV PEK. LANTAI, DINDING
1 Lantai Keramik Uk. 60/60 Cm 4.4.3.34.c 20,83 M2
2 Dinding Pasangan Batako 4.4.1.17.a 31,78 M2
3 Plesteran dinding, Tiang & Balok 4.4.2.13 136,51 M2
Sub Total
V PEK. PLAFOND
1 Rangka Plafond furing 4.2.1.21.a 18,33 M2
2 Plafond Gypsum (lt 2) A.4.5.1.7. 18,33 M2
3 Rangka Plafond furing (Kaki Atap) 4.2.1.21.a 7,33 M2
4 Plafond Gypsum (Kaki Atap) A.4.5.1.7. 7,33 M2
Sub Total
VI PEK. PINTU, JENDELA, KOSEN, VENTILASI
PENGGANTUNG DAN PENGUNCI
1 Jendela + Ventelasi Alumunium 3"+ Kaca 6mm lengkap - 10,00 M2
Sub Total
VII PEK. INSTALASI LISTRIK
1 Instalasi Titik Lampu - 3,000 Titik
2 Stop Kontak + Inbodus (setara panassonic) - 1,000 Titik
3 Saklar Ganda + Inbodus (setara panassonic) - 1,000 Buah
4 Lampu LED 14 watt (setara panassonic/philips) - 3,000 Buah
Sub Total
VIII PEKERJAAN PENGECATAN
1 Cat Tembok A.4.7.1.10.c 162,16 M2
3 Cat Kilat A.4.7.1.4. 8,80 M2
Sub Total
IX PEK. LAIN-LAIN
1 Membuat List Profil Kayu Belian (Kolom lt 1) - 2,00 Unit
JUMLAH
HARGA (Rp)

Rp 3,769,697.78
#VALUE!
Rp 4,269,697.78

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!

#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
Rp 54,598,997.18

#VALUE!
#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!
#VALUE!

#VALUE!
#VALUE!
#VALUE!
Rp 519,928,060.56
#VALUE!
#VALUE!
#VALUE!
#VALUE!
Rp 43,411,759.34

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
Rp 227,989,610.89

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
Rp -
#VALUE!
#VALUE!
Rp -
#VALUE!
#VALUE!

Rp -
#VALUE!
#VALUE!

Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -
Rp -

Rp -
#VALUE!
#VALUE!
#VALUE!

Rp -
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

Rp -
Rp -
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
Rp -
Rp -
#VALUE!
#VALUE!
#VALUE!
Rp -
#VALUE!
Rp -
#VALUE!
#VALUE!
#VALUE!
#VALUE!
Rp -
Rp -
#VALUE!
#VALUE!
#VALUE!
#VALUE!
Rp -
#VALUE!
#VALUE!
#VALUE!
#VALUE!
Rp -
#VALUE!
#VALUE!
#VALUE!
#VALUE!
Rp -
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
Rp -
#VALUE!
#VALUE!
#VALUE!

Rp -
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

Rp -
#VALUE!
#VALUE!
#VALUE!

Rp -
#VALUE!
#VALUE!
#VALUE!
#VALUE!

Rp -
Rp -
#VALUE!

Rp -
Rp -
Rp -
Rp -
Rp -

Rp -
#VALUE!
#VALUE!

Rp -
#VALUE!
Rp -
KOP PERUSAHAAN

REKAPITULASI
HARGA PERKIRAAN SEMENTARA
( HPS )

K/L/D/I : Kepolisian Negara Republik Indonesia


SATKER : Dir Polair Plda Kabbar
PEKERJAAN : Pembangunan Dermaga Dit Polair Polda Kalbar
LOKASI : Jalan Khatulistiwa No. 300
PAGU DANA : Rp. 16.518.500,00
SUMBER DANA / TA : APBN 2017

No. Jenis Pekerjaan

1 2

I PEKERJAAN PERSIAPAN

II PEKERJAAN DERMAGA

III PEKERJAAN PERKUATAN TEBING

IV PEKERJAAN JALAN RAMP

V PEKERJAAN SAUNG SPEED BOAT

VI PEKERJAAN INSTALASI PENERANGAN DAN INSTALASI AIR

VII PEKERJAAN PERBAIKAN LINGKUNGAN

(A) Jumlah Harga Pekerjaan ( termasuk Biaya Umum dan Keuntungan )


(B) Pajak Pertambahan Nilai ( PPN ) = 10% x (A)
(C) JUMLAH TOTAL HARGA PEKERJAAN = (A) + (B)
DIBULATKAN

Terbilang : Enam Belas Milyar Lima Ratus Tiga Belas Juta Empat Ratus Delapan Puluh Enam Ri

Pontianak , 06 JuIi 201


PT. VISTA EMAS SEJ

ENDANG MASRONI, SH
Direktur Utama
ERUSAHAAN

REKAPITULASI
PERKIRAAN SEMENTARA
( HPS )

Jumlah Harga
(Rp)
3

308,215,244.45

11,205,898,948.65

2,314,275,229.09

60,474,139.99

894,743,578.01

61,721,700.00

166,931,312.80

15,012,260,152.99
1,501,226,015.30
16,513,486,168.29
16,513,486,000.00

us Tiga Belas Juta Empat Ratus Delapan Puluh Enam Ribu Rupiah

Pontianak , 06 JuIi 2017


PT. VISTA EMAS SEJATI

ENDANG MASRONI, SH, MH


Direktur Utama
RENCANA ANGGARAN BIAYA
HARGA PERKIRAAN SEMENTARA
( HPS )
K/L/D/I : Kepolisian Negara Republik Indonesia
satker : Dir Polair Plda Kabbar
PEKERJAAN : Pembangunan Dermaga Dit Polair Polda Kalbar
LOKASI : Jalan Khatulistiwa No. 300
PAGU DANA : Rp. 16.518.500,00
SUMBER DANA / TA : APBN 2017

No. Jenis Pekerjaan Volume Satuan

1 2 3 4

I PEKERJAAN PERSIAPAN

1. Mobilisasi dan Demobilisasi 1.00 Ls


2. Pengukuran, Penetapan Titik, Pemasangan Bowplank dan Elevasi 220.65 M'
3. Penerangan dan Keamanan 150.00 Hari
4. Pelaporan Dan Dokumentasi 1.00 Ls
5. Direksi Keet 6 x 8 m 48.00 M2
6. Shop Drawing dan Asbuilt Drawing 1.00 Ls
7. Papan Nama Proyek 1.00 Ls
8. Pembersihan Lokasi 2,152.95 M2

JUML

II PEKERJAAN DERMAGA

1. Pengadaan Spun Pile OD500-A (K-600) P = 42 m


- Spun Pile OD500-A (K-600) Upper (With Flange) P = 12 m dan 10 m 4,288.00 M'
- Spun Pile OD500-A (K-600) Bottom (Pointed) P = 10 m 1,340.00 M'

2. Pemancangan Tiang Pancang


- Pemancangan Tiang Pancang Tegak 3,811.00 M'
- Pemancangan Tiang Pancang Miring 1,147.00 M'

4. Beton Bertulang Isian Tiang Pancang


- Beton K-225 21.56 M3
- Pembesian 3,771.39 Kg
- Plat Isian 169.27 Kg

5. Beton Bertulang Poer


- Beton K-300 63.50 M3
- Pembesian 13,023.08 Kg
- Bekisting 408.24 M2

6. Beton Bertulang Balok


- Beton K-300 85.90 M3
- Pembesian 19,476.21 Kg
- Bekisting 145.42 M2

7. Beton Bertulang Plat


- Beton K-300 271.15 M3
- Pembesian 38,085.36 Kg
- Bekisting 1,355.76 M2

8. Beton Bertulang Dudukan Fender


- Beton K-300 5.21 M3
- Pembesian 1,066.14 Kg
- Bekisting 66.96 M2

9. Beton Kansteen
- Beton K-225 4.67 M3
- Bekisting 93.36 M2

10. Pengadaan dan Pemasangan Fender SVF 250 x 1500 31.00 Buah
11. Pengadaan dan Pemasangan Bollard 6.00 Buah
12. Pengecatan Kansteen 116.70 M2
13. Besi Siku Untuk Delatasi L 70.70.7 286.34 Kg

JUML

No. Jenis Pekerjaan Volume Satuan

1 2 3 4

III PEKERJAAN PERKUATAN TEBING

1. Pengadaan Mini Pile 35 x 35 cm P = 18 m (K-400)


- Mini Pile 35 x 35 cm P = 18 m 846.00 M'

2. Pemancangan Tiang Pancang


- Pemancangan Tiang Pancang Miring 775.50 M'
- Pemotongan Kepala Tiang pancang 47.00 Titik

3. Pengadaan SHEETPILE FLAT 150 - 500 2,502.00 M'


P = 9 m fc = 50 MPa (K-400)

4. Pemancangan SHEETPILE FLAT 150 -500 2,502.00 M'


5. Pemotongan Kepala Sheetpile 138.90 M'

5. Beton Bertulang Caping Beam


- Beton K-300 83.34 M3
- Pembesian 7,110.49 Kg
- Bekisting 140.10 M2

J U M LA

IV PEKERJAAN JALAN RAMP

1. Pengadaan Mini Pile 25 x 25 36.00 M'


2. Pemancangan Mini Pile 36.00 M'
3. Pemotongan kepala Mini Pile 2.00 Titik
4. Beton Bertulang Poer
- Beton K-300 0.43 M3
- Pembesian 98.51 Kg
- Bekisting 3.60 M2

5. Beton Bertulang Balok 20/40


- Beton K-300 1.40 M3
- Pembesian 227.61 Kg
- Bekisting 17.48 M2

6. Beton Bertulang Plat


- Beton K-300 3.43 M3
- Pembesian 991.02 Kg
- Bekisting 22.85 M2

J U M LA

V PEKERJAAN SAUNG SPEED BOAT

1. Pengadaan Spun Pile OD500-A (K-600) P = 42 m


- Spun Pile OD500-A (K-600) Upper (With Flange) P = 10 m dan 12 m 192.00 M'
- Spun Pile OD500-A (K-600) Bottom (Pointed) P = 10 m 60.00 M'

2. Pemancangan Tiang Pancang


- Pemancangan Tiang Pancang Tegak 234.00 M'

3. Beton Bertulang Isian Tiang Pancang


- Beton K-225 0.97 M3
- Pembesian 168.87 Kg
- Plat Isian 7.58 Kg

4. Pengadaan Mini Pile 25 x 25 72.00 M'


5. Pemancangan Mini Pile 72.00 M'
6. Pemotongan kepala Mini Pile 4.00 Titik
7. Beton Bertulang Poer
- Beton K-300 3.55 M3
- Pembesian 806.10 Kg
- Bekisting 24.48 M2
8. Beton Bertulang Balok 20/40
- Beton K-300 1.20 M3
- Pembesian 191.33 Kg
- Bekisting 7.50 M2
No. Jenis Pekerjaan Volume Satuan

1 2 3 4

9. Beton Bertulang Balok 30/60


- Beton K-300 5.95 M3
- Pembesian 946.14 Kg
- Bekisting 49.58 M2

10. Beton Bertulang Plat


- Beton K-300 4.72 M3
- Pembesian 1,396.01 Kg
- Bekisting 25.99 M2

11. Beton Bertulang Tangga


- Beton K-300 1.30 M3
- Pembesian 318.49 Kg
- Bekisting 6.40 M2

12. Beton Bertulang Kolom 40 x 40


- Beton K-300 3.19 M3
- Pembesian 464.51 Kg
- Bekisting 31.87 M2

13. Beton Bertulang Balok 30/60


- Beton K-300 8.64 M3
- Pembesian 1,374.15 Kg
- Bekisting 72.00 M2

14. Beton Bertulang Kolom 20 x 20


- Beton K-300 0.80 M3
- Pembesian 212.93 Kg
- Bekisting 15.94 M2

15. Beton Bertulang Plat


- Beton K-300 12.75 M3
- Pembesian 1,810.24 Kg
- Bekisting 63.75 M2

16. Beton Bertulang Tangga


- Beton K-300 0.92 M3
- Pembesian 228.69 Kg
- Bekisting 4.19 M2

17. Dinding Batako 84.67 M2


18. Plesteran dan Acian 169.33 M2
19. Rangka Atap Baja Ringan 117.39 M2
20. Penutup Atap Genteng Metal 117.39 M2
21. Rangka Plafond 105.35 M2
22. Plafond 105.35 M2
23. Jendela 1 2.64 M2
24. Jendela 2 2.70 M2
25. Pintu 2.20 M2
26. Pengecatan Plafond 210.70 M2
27. Pengecatan Dinding 338.67 M2
28. Pengadaan Dermaga Apung HDPE 8.00 M2

JUML

VI PEKERJAAN INSTALASI PENERANGAN DAN INSTALASI AIR

1 Pemasangan Daya Baru 10.600 (VA) 3 Phase 1.00 Set


2 Tiang Lampu dengan Besi GI Ø. 6"- 8 mtr + Pemasangan 5.00 Btg
3 Kabel 3 x 3 mm 193.00 Mtr
4 Lampu Jalan Taman Lengkap 5.00 Set
5 Saklar Ganda 3.00 Bh
6 Skring Box 1.00 Bh
7 MCB 1.00 Bh
8 Pemasangan Instalasi 22.00 Ttk
9 Pipa instalasi Listrik PVC. Ø 0,5 " 35.00 Btg
10 Pipa PVC. Ø 2 " Untuk Instalasi Air 34.00 Btg
11 Tee PVC. Ø 2 " 1.00 Bh
12 Tee PVC. Ø 1 "- 2 " 6.00 Bh
13 Krant Air. Ø 1 " 6.00 Bh
14 Pengadaan dan Pemasangan Pompa Air 1.00 Bh

J U M LA
No. Jenis Pekerjaan Volume Satuan

1 2 3 4

VII PEKERJAAN PERBAIKAN LINGKUNGAN

1. Pengembalian Kondisi Jalan


- Lapis Perekat (Aspal Cair) 130.79 Liter
- Lataston Lapis Aus (HRS-WC) 97.22 Ton

J U M LA
ANGGARAN BIAYA
KIRAAN SEMENTARA
( HPS )

Harga Jumlah
Kode Analisa Satuan Harga Satuan
(Rp) (Rp)
5 6 7

2.2 89,200,000.00 89,200,000.00


2.2.1.4.a 50,831.96 11,216,070.87
2.1 281,290.00 42,193,500.00
4,000,000.00 4,000,000.00
2.2.1.6 2,499,318.46 119,967,286.08
4,000,000.00 4,000,000.00
500,000.00 500,000.00
2.2.1.9 17,250.00 37,138,387.50

J U M LAH I 308,215,244.45

EI-768a 969,331.48 4,156,493,385.84


EI-768b 1,080,904.29 1,448,411,752.17

F.04.e 452,627.53 1,724,963,519.48


F.04.f 590,894.06 677,755,487.86

B. 13.f.2 1,544,261.40 33,298,158.50


4.1.1.17 14,817.75 55,883,445.02
11,000.00 1,861,923.11

B. 13.i.2 1,635,051.60 103,832,316.81


4.1.1.17 14,817.75 192,972,669.58
4.1.1.22 a 352,525.83 143,915,144.84

B. 13.i.2 1,635,051.60 140,444,392.23


4.1.1.17 14,817.75 288,593,581.09
4.1.1.23.a 362,615.01 52,731,474.75

B. 13.i.2 1,635,051.60 443,347,511.44


4.1.1.17 14,817.75 564,339,276.95
4.1.1.24.a 396,225.83 537,187,131.28

B. 13.i.2 1,635,051.60 8,515,348.73


4.1.1.17 14,817.75 15,797,744.12
4.1.1.24.a 396,225.83 26,531,281.58

B. 13.f.2 1,544,261.40 7,208,612.22


4.1.1.20.a 174,194.64 16,262,811.59

17,000,000.00 527,000,000.00
4,000,000.00 24,000,000.00
A.4.7.1.10.c 45,842.45 5,349,813.92
4.2.1.1 32,136.75 9,202,165.54

J U M L A H II 11,205,898,948.65

Harga Jumlah
Kode Analisa Satuan Harga Satuan
(Rp) (Rp)
5 6 7

EI-7610a 535,746.37 453,241,431.81

F.04.c 286,231.80 221,972,764.17


110,000.00 5,170,000.00

EI-765 375,354.11 939,135,984.63

F.07.b 154,695.02 387,046,951.90


110,000.00 15,279,000.00

B. 13.i.2 1,635,051.60 136,265,200.34


4.1.1.17 14,817.75 105,361,533.33
4.1.1.23.a 362,615.01 50,802,362.90

J U M L A H III 2,314,275,229.09

230,000.00 8,280,000.00
200,000.00 7,200,000.00
110,000.00 220,000.00

B. 13.i.2 1,635,051.60 706,342.29


4.1.1.17 14,817.75 1,459,678.77
4.1.1.22 a 352,525.83 1,269,092.99

B. 13.i.2 1,635,051.60 2,286,456.16


4.1.1.17 14,817.75 3,372,700.08
4.1.1.23.a 362,615.01 6,338,510.37

B. 13.i.2 1,635,051.60 5,603,648.84


4.1.1.17 14,817.75 14,684,742.71
4.1.1.24.a 396,225.83 9,052,967.76

J U M L A H IV 60,474,139.99

EI-768a 969,331.48 186,111,644.14


EI-768b 1,080,904.29 64,854,257.56

F.04.e 452,627.53 105,914,842.18

B. 13.f.2 1,544,261.40 1,490,962.32


4.1.1.17 14,817.75 2,502,243.81
11,000.00 83,369.69

230,000.00 16,560,000.00
200,000.00 14,400,000.00
110,000.00 440,000.00

B. 13.i.2 1,635,051.60 5,807,703.28


4.1.1.17 14,817.75 11,944,540.86
4.1.1.22 a 352,525.83 8,629,832.32
B. 13.i.2 1,635,051.60 1,962,061.92
4.1.1.17 14,817.75 2,835,145.31
4.1.1.23.a 362,615.01 2,719,612.58
Harga Jumlah
Kode Analisa Satuan Harga Satuan
(Rp) (Rp)
5 6 7

B. 13.i.2 1,635,051.60 9,726,921.97


4.1.1.17 14,817.75 14,019,729.21
4.1.1.23.a 362,615.01 17,976,639.12

B. 13.i.2 1,635,051.60 7,723,166.23


4.1.1.17 14,817.75 20,685,800.28
4.1.1.24.a 396,225.83 10,297,909.32

B. 13.i.2 1,635,051.60 2,126,875.12


4.1.1.17 14,817.75 4,719,247.90
4.1.1.26 359,399.15 2,300,154.56

B. 13.i.2 1,635,051.60 5,211,236.46


4.1.1.17 14,817.75 6,882,946.82
4.1.1.22 a 352,525.83 11,235,703.25

B. 13.i.2 1,635,051.60 14,126,845.82


4.1.1.17 14,817.75 20,361,817.09
4.1.1.23.a 362,615.01 26,108,280.72

B. 13.i.2 1,635,051.60 1,302,809.11


4.1.1.17 14,817.75 3,155,151.81
4.1.1.22 a 352,525.83 5,617,851.63

B. 13.i.2 1,635,051.60 20,846,907.90


4.1.1.17 14,817.75 26,823,735.62
4.1.1.24.a 396,225.83 25,259,396.66

B. 13.i.2 1,635,051.60 1,508,923.72


4.1.1.17 14,817.75 3,388,716.49
4.1.1.26 359,399.15 1,507,320.04

4.4.1.19.a 107,171.61 9,073,898.28


4.4.2.3 + 4.4.2.27 108,780.00 18,420,151.67
- 225,000.00 26,412,390.00
A.4.5.2.32. 116,439.80 13,668,681.82
A.4.6.1.19. 142,447.03 15,006,794.29
A.4.5.1.7.a 53,479.37 5,634,051.63
A.4.6.1.6. 915,241.30 2,416,237.03
A.4.6.2.18.+A.4.6.1.6. 1,124,530.95 3,036,233.57
A.4.6.1.6. 915,241.30 2,013,530.86
A.4.7.1.10.d 54,189.15 11,417,653.91
A.4.7.1.10.b 54,547.95 18,473,645.13
10,000,000.00 80,000,000.00

J U M LAH V 894,743,578.01

18,000,000.00 18,000,000.00
3,500,000.00 17,500,000.00
51,000.00 9,843,000.00
900,000.00 4,500,000.00
25,000.00 75,000.00
25,000.00 25,000.00
44,800.00 44,800.00
140,000.00 3,080,000.00
21,300.00 745,500.00
79,600.00 2,706,400.00
18,000.00 18,000.00
14,000.00 84,000.00
150,000.00 900,000.00
4,200,000.00 4,200,000.00

J U M L A H VI 61,721,700.00
Harga Jumlah
Kode Analisa Satuan Harga Satuan
(Rp) (Rp)
5 6 7

EI-611a 15,043.45 1,967,532.92


EI-633a 1,696,809.09 164,963,779.88

J U M L A H VI 166,931,312.80
ANALISIS HARGA SATUAN PEKERJAAN

Jenis Pekerjaan : Penerangan, Keselamatan dan Keamanan Kerja


Harga Satuan/Lumpsum : Lumpsum /hr Rp. 281,290.00
2.1(AHSP PM Perhubungan No. 78 Tahun 2014 Kode: 3040)

No. Uraian Satuan Kuantitas Harga Satuan Jumlah (Rp.)


1 Peralatan
Genset Jam 0.0056 1,500,000.00 8,400.00
2 Upah .
-satpam oh 2.4000 75,000.00 180,000.00
3 Bahan
- Solar oh 10.5000 8,100.00 85,050.00
- Perlengkapan keamanan ls 0.0056 750,000.00 4,200.00
- Perlengkapan PPPK ls 0.0056 650,000.00 3,640.00

281,290.00

Jenis Pekerjaan : Mobilisasi - Demobilisasi Peralatan


Harga Satuan/Lumpsum : Lumpsum Rp. 89,200,000.00
2.2 (AHSP PM Perhubungan No. 78 Tahun 2014 Kode: 3044)*

No. Uraian Satuan Kuantitas Harga Satuan Jumlah (Rp.)


1 Tug Boat Hari 2 18,000,000.00 36,000,000.00
2 Tongkang Hari 2 10,000,000.00 20,000,000.00
3 Crane Hari 2 9,000,000.00 18,000,000.00
4 Pile Drive Hari 2 1,000,000.00 2,000,000.00
5 Wheel Loader Hari 2 1,400,000.00 2,800,000.00
6 Genset Hari 2 500,000.00 1,000,000.00
7 Dump Truck Hari 2 500,000.00 1,000,000.00
8 Asphalt Finisher Hari 2 1,400,000.00 2,800,000.00
9 Tandem Roller Hari 2 1,400,000.00 2,800,000.00
10 P. Tyre Roller Hari 2 1,400,000.00 2,800,000.00

89,200,000.00
2.2.1.4.a Pengukuran dan Pemasangan 1m Bouplank

Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
1 Pekerja L.01 OH 0.100 90,000.00
2 Tukang Kayu L.02 OH 0.100 100,000.00
3 Kepala Tukang L.03 OH 0.010 110,000.00
4 Mandor L.04 OH 0.005 120,000.00
JUMLAH TENAGA KERJA
B BAHAN
Kayu Pancang (Dolken) d = 6-8 cm, p = 4m Btg 1.000 8,300.00
Paku Kg 0.020 20,500.00
Papan Kayu Kelas III M3 0.007 2,113,100.00
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)
2.2.1.5 Pembuatan 1 m² kantor sementara lantai plesteran

Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
1 Pekerja L.01 OH 2.000 90,000.00
2 Tukang Kayu L.02 OH 2.000 100,000.00
3 Tukang Batu L.02 OH 1.000 100,000.00
4 Kepala Tukang L.03 OH 0.300 110,000.00
5 Mandor L.04 OH 0.050 120,000.00
JUMLAH TENAGA KERJA
B BAHAN
1 Dolken kayu ф 8-10/400cm Batang 1.250 9,500.00
2 Kayu m³ 0.180 6,510,400.00
3 Paku Biasa Kg 0.080 20,500.00
4 Besi Strip Kg 1.100 15,000.00
5 Semen Portland Kg 35.000 1,500.00
6 Pasir Pasang m³ 0.150 100,100.00
7 Koral Beton m³ 0.150 458,100.00
8 Bata Merah Bh 30.000 1,500.00
9 Seng Plat Lbr 0.250 49,900.00
10 Jendela Naco Bh 0.200 250,000.00
11 Kaca Polos m² 0.080 82,500.00
12 Kunci Tanam Bh 0.150 55,000.00
13 Plywood 6mm Lbr 0.060 120,000.00
JUMLAH HARGA ALAT
C PERALATAN

JUMLAH HARGA BAHAN

D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)
Jumlah Harga (Rp)

9,000.00
10,000.00
1,100.00
600.00
20,700.00

8,300.00
410.00
14,791.70
23,501.70

44,201.70
6,630.26
50,831.96
Jumlah Harga (Rp)

180,000.00
200,000.00
100,000.00
33,000.00
6,000.00
519,000.00

11,875.00
1,171,872.00
1,640.00
16,500.00
52,500.00
15,015.00
68,715.00
45,000.00
12,475.00
50,000.00
6,600.00
8,250.00
7,200.00
1,467,642.00

1,986,642.00
297,996.30
2,284,638.30
2.3.1. HARGA SATUAN PEKERJAAN TANAH
2.3.1.1 Penggalian 1 m³ tanah biasa sedalam 1m

Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
1 Pekerja L.01 OH 0.750 90,000.00
2 Mandor L.04 OH 0.025 120,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)

2.3.1.2 Penggalian 1 m³ tanah biasa sedalam 2 m

Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
1 Pekerja L.01 OH 0.900 90,000.00
2 Mandor L.04 OH 0.045 120,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)

2.3.1.3 Penggalian 1 m³ tanah biasa sedalam3 m

Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
1 Pekerja L.01 OH 1.050 90,000.00
2 Mandor L.04 OH 0.067 120,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)
2.3.1.4 Penggalian 1 m³ tanah keras sedalam 1 m

Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
1 Pekerja L.01 OH 1.000 90,000.00
2 Mandor L.04 OH 0.032 120,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)

2.3.1.5 Penggalian 1 m³ tanah cadas sedalam 1 m

Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
1 Pekerja L.01 OH 1.500 90,000.00
2 Mandor L.04 OH 0.060 120,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)

2.3.1.6 Penggalian 1 m³ tanah lumpur sedalam 1 m

Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
1 Pekerja L.01 OH 1.200 90,000.00
2 Mandor L.04 OH 0.045 120,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)
2.3.1.7 Pengerjaan stripping 1 m² tanah tebing setinggi 1 m

Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
1 Pekerja L.01 OH 0.050 90,000.00
2 Mandor L.04 OH 0.005 120,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)

2.3.1.8 Pembuangan 1 m³ tanah sejauh 30 m

Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
1 Pekerja L.01 OH 0.330 90,000.00
2 Mandor L.04 OH 0.010 120,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)

2.3.1.9 Pengurugan kembali 1 m³ galian tanah (tanah cadas)


Pengurugan kembali 1 m³ galian dihitung dari 1/3 kali dari koefisien pekerjaan galiaan
Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
1 Pekerja L.01 OH 0.500 90,000.00
2 Mandor L.04 OH 0.050 120,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)
2.3.1.9.a Pengurugan kembali 1 m³ galian tanah biasa
Pengurugan kembali 1 m³ galian dihitung dari 1/3 kali dari koefisien pekerjaan galiaan
Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
1 Pekerja L.01 OH 0.250 90,000.00
2 Mandor L.04 OH 0.008 120,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)

2.3.1.10 Pemadatan tanah 1 m³ tanah (per 20 cm)

Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
1 Pekerja L.01 OH 0.500 90,000.00
2 Mandor L.04 OH 0.050 120,000.00
JUMLAH TENAGA KERJA
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)

2.3.1.11 Pengurugan 1 m³ dengan pasir urug

Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
1 Pekerja L.01 OH 0.300 90,000.00
2 Mandor L.04 OH 0.010 120,000.00
JUMLAH TENAGA KERJA
B BAHAN
Pasir Urug 1.200 100,100.00
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)
2.3.1.11.a Pengurugan 1 m³ dengan tanah pilihan

Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
1 Pekerja L.01 OH 0.300 90,000.00
2 Mandor L.04 OH 0.010 120,000.00
JUMLAH TENAGA KERJA
B BAHAN

Tanah pilihan (peladis/bukit tokok) 1.200 320,200.00

JUMLAH HARGA BAHAN


C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)

E Overhead & Profit (Contoh 15%) 15% x D


F Harga Satuan Pekerjaan (D+E)

2.3.1.11.b Pengurugan 1 m³ dengan tanah ex. peniraman

Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
1 Pekerja L.01 OH 0.300 90,000.00
2 Mandor L.04 OH 0.010 120,000.00
JUMLAH TENAGA KERJA
B BAHAN
Tanah ex. peniraman 1.200 235,000.00
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)

E Overhead & Profit (Contoh 15%) 15% x D


F Harga Satuan Pekerjaan (D+E)
Jumlah Harga (Rp)

67,500.00
3,000.00
70,500.00

70,500.00
10,575.00
81,075.00

Jumlah Harga (Rp)

81,000.00
5,400.00
86,400.00

86,400.00
12,960.00
99,360.00

Jumlah Harga (Rp)

94,500.00
8,040.00
102,540.00
102,540.00
15,381.00
117,921.00
Jumlah Harga (Rp)

90,000.00
3,840.00
93,840.00

93,840.00
14,076.00
107,916.00

Jumlah Harga (Rp)

135,000.00
7,200.00
142,200.00

142,200.00
21,330.00
163,530.00

Jumlah Harga (Rp)

108,000.00
5,400.00
113,400.00
113,400.00
17,010.00
130,410.00
Jumlah Harga (Rp)

4,500.00
600.00
5,100.00

5,100.00
765.00
5,865.00

Jumlah Harga (Rp)

29,700.00
1,200.00
30,900.00

30,900.00
4,635.00
35,535.00

Jumlah Harga (Rp)

45,000.00
6,000.00
51,000.00
51,000.00
7,650.00
58,650.00
Jumlah Harga (Rp)

22,500.00
1,000.00
23,500.00

23,500.00
3,525.00
27,025.00

Jumlah Harga (Rp)

45,000.00
6,000.00
51,000.00

51,000.00
7,650.00
58,650.00

Jumlah Harga (Rp)

27,000.00
1,200.00
28,200.00

120,120.00
120,120.00
148,320.00
22,248.00
170,568.00
Jumlah Harga (Rp)

27,000.00
1,200.00
28,200.00

384,240.00

384,240.00

412,440.00

61,866.00
474,306.00

Jumlah Harga (Rp)

27,000.00
1,200.00
28,200.00

282,000.00
282,000.00

310,200.00

46,530.00
356,730.00
3.2.1 HARGA SATUAN PEKERJAAN PONDASI
3.2.1.1 Pemasangan 1 m³ pondasi batu belah campuran 1SP:3PP

Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
1 Pekerja L.01 OH 1.500 90,000.00
2 Tukang L.02 OH 0.750 100,000.00
3 Kepala Tukang L.03 OH 0.075 110,000.00
4 Mandor L.04 OH 0.075 120,000.00
JUMLAH TENAGA KERJA
B BAHAN
1 Batu Belah m³ 1.200 336,700.00
2 Semen Portland Kg 202.000 1,500.00
3 Pasir Pasang m³ 0.485 100,100.00
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)

3.2.1.2 Pemasangan 1 m³ pondasi batu belah campuran 1SP:4PP

Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
1 Pekerja L.01 OH 1.500 90,000.00
2 Tukang L.02 OH 0.750 100,000.00
3 Kepala Tukang L.03 OH 0.075 110,000.00
4 Mandor L.04 OH 0.075 120,000.00
JUMLAH TENAGA KERJA
B BAHAN
1 Batu Belah m³ 1.200 336,700.00
2 Semen Portland Kg 163.000 1,500.00
3 Pasir Pasang m³ 0.520 100,100.00
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)

3.2.1.9 Pemasangan 1 m³ batu kosong (anstamping)


Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
1 Pekerja L.01 OH 0.780 90,000.00
2 Tukang L.02 OH 0.390 100,000.00
3 Kepala Tukang L.03 OH 0.039 110,000.00
4 Mandor L.04 OH 0.039 120,000.00
JUMLAH TENAGA KERJA
B BAHAN
1 Batu Belah m³ 1.200 336,700.00
2 Pasir Urug m³ 0.432 100,100.00
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)
3.2.1.10 Pemasangan 1 m³ pondasi siklop, 60% beton campuran 1SP:2PB:3Kr dan 40% batu belah

Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
1 Pekerja L.01 OH 3.400 90,000.00
2 Tukang L.02 OH 0.850 100,000.00
3 Kepala Tukang L.03 OH 0.085 110,000.00
4 Mandor L.04 OH 0.170 120,000.00
JUMLAH TENAGA KERJA
B BAHAN
1 Batu Belah m³ 0.480 336,700.00
2 Semen Portlan Kg 194.000 1,500.00
3 Pasir Beton m³ 0.312 100,100.00
4 Kerikil m³ 0.468 581,900.00
5 Besi Beton Kg 126.000 10,600.00
6 Kawat Beton Kg 1.800 20,000.00
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)

P.06.a.7 Pasangan Bronjong Pabrikasi (Tenaga Kerja Untuk 1 m3 Batu Bronjong)

Harga Satuan
No Uraian Kode Satuan Koefisien
(Rp)
A TENAGA
1 Pekerja L.01 OH 0.250 90,000.00
2 Mandor L.04 OH 0.025 120,000.00
JUMLAH TENAGA KERJA
B BAHAN
1 Batu Belah m³ 1.300 421,200.00
2 Kawat Bronjong Buah 1.000 453,000.00
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)
Jumlah Harga (Rp)

135,000.00
75,000.00
8,250.00
9,000.00
227,250.00

404,040.00
303,000.00
48,548.50
755,588.50

982,838.50
147,425.78
1,130,264.28

Jumlah Harga (Rp)

135,000.00
75,000.00
8,250.00
9,000.00
227,250.00

404,040.00
244,500.00
52,052.00
700,592.00

927,842.00
139,176.30
1,067,018.30
Jumlah Harga (Rp)

70,200.00
39,000.00
4,290.00
4,680.00
118,170.00

404,040.00
43,243.20
447,283.20

565,453.20
84,817.98
650,271.18
Jumlah Harga (Rp)

306,000.00
85,000.00
9,350.00
20,400.00
420,750.00

161,616.00
291,000.00
31,231.20
272,329.20
1,335,600.00
36,000.00
2,127,776.40

2,548,526.40
382,278.96
2,930,805.36

Jumlah Harga (Rp)

22,500.00
3,000.00
25,500.00

547,560.00
453,000.00
1,000,560.00

1,026,060.00
153,909.00
1,179,969.00
4.1.1 HARGA SATUAN PEKERJAAN BETON
4.1.1.1 Membuat 1 m³ beton mutu f'c =7,4 Mpa ( K 100), slump (12 ± 2) cm ,w/c =0,87

No Uraian Kode Satuan Koefisien


A TENAGA
1 Pekerja L.01 OH 1.650
2 Tukang L.02 OH 0.275
3 Kepala Tukang L.03 OH 0.028
4 Mandor L.04 OH 0.083
JUMLAH TENAGA KERJA
B BAHAN
1 Semen Portlan Kg 247.000
2 Pasir Beton Kg 869.000
3 Kerikil (Maks 30mm) Kg 999.000
4 Air Liter -
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)

4.1.1.1.a Membuat 1 m³ beton mutu f'c =7,4 Mpa ( K 100), slump (12 ± 2) cm ,w/c =0,87 (Menggunakan Molen)

No Uraian Kode Satuan Koefisien


A TENAGA
1 Pekerja L.01 OH 1.323
2 Tukang L.02 OH 0.189
3 Kepala Tukang L.03 OH 0.019
4 Mandor L.04 OH 0.066
JUMLAH TENAGA KERJA
B BAHAN
1 Semen Portlan Kg 247.000
2 Pasir Beton Kg 869.000
3 Kerikil (Maks 30mm) Kg 999.000
4 Air Liter -
JUMLAH HARGA BAHAN
C PERALATAN
Sewa Molen Sewa-hari 0.250
JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)

CATATAN
bobot pasir =1.400 Kg/m³, Bobot isi kerikil = 1.350 Kg/m³, Buckling factor pasir =20%
4.1.1.2 Membuat 1 m³ beton mutu f'c =9,8 Mpa ( K 125), slump (12 ± 2) cm ,w/c =0,78

No Uraian Kode Satuan Koefisien


A TENAGA
1 Pekerja L.01 OH 1.650
2 Tukang L.02 OH 0.275
3 Kepala Tukang L.03 OH 0.028
4 Mandor L.04 OH 0.083
JUMLAH TENAGA KERJA
B BAHAN
1 Semen Portlan Kg 276.000
2 Pasir Beton Kg 828.000
3 Kerikil (Maks 30mm) Kg 1,012.000
4 Air Liter -
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)
4.1.1.2.a Membuat 1 m³ beton mutu f'c =9,8 Mpa ( K 125), slump (12 ± 2) cm ,w/c =0,78 (Menggunakan Molen)

No Uraian Kode Satuan Koefisien


A TENAGA
1 Pekerja L.01 OH 1.323
2 Tukang L.02 OH 0.189
3 Kepala Tukang L.03 OH 0.019
4 Mandor L.04 OH 0.066
JUMLAH TENAGA KERJA
B BAHAN
1 Semen Portlan Kg 276.000
2 Pasir Beton Kg 828.000
3 Kerikil (Maks 30mm) Kg 1,012.000
4 Air Liter -
JUMLAH HARGA BAHAN
C PERALATAN
Sewa Molen Sewa-hari 0.250
JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)

CATATAN
bobot pasir =1.400 Kg/m³, Bobot isi kerikil = 1.350 Kg/m³, Buckling factor pasir =20%

4.1.1.3 Membuat 1 m³ beton mutu f'c =12,2 Mpa ( K 150), slump (12 ± 2) cm ,w/c =0,72

No Uraian Kode Satuan Koefisien


A TENAGA
1 Pekerja L.01 OH 1.650
2 Tukang L.02 OH 0.275
3 Kepala Tukang L.03 OH 0.028
4 Mandor L.04 OH 0.083
JUMLAH TENAGA KERJA
B BAHAN
1 Semen Portlan Kg 299.000
2 Pasir Beton Kg 799.000
3 Kerikil (Maks 30mm) Kg 1,017.000
4 Air Liter -
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)

4.1.1.3.a Membuat 1 m³ beton mutu f'c =12,2 Mpa ( K 150), slump (12 ± 2) cm ,w/c =0,72 (Menggunakan Molen)
No Uraian Kode Satuan Koefisien
A TENAGA
1 Pekerja L.01 OH 1.323
2 Tukang L.02 OH 0.189
3 Kepala Tukang L.03 OH 0.019
4 Mandor L.04 OH 0.066
JUMLAH TENAGA KERJA
B BAHAN
1 Semen Portlan Kg 299.000
2 Pasir Beton Kg 799.000
3 Kerikil (Maks 30mm) Kg 1,017.000
4 Air Liter -
JUMLAH HARGA BAHAN
C PERALATAN
Sewa Molen Sewa-hari 0.250
JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)

CATATAN
bobot pasir =1.400 Kg/m³, Bobot isi kerikil = 1.350 Kg/m³, Buckling factor pasir =20%
4.1.1.4 Membuat 1 m³ lantai kerja beton mutu f'c =7,4 Mpa ( K 100), slump (3-6) cm ,w/c =0,87

No Uraian Kode Satuan Koefisien


A TENAGA
1 Pekerja L.01 OH 1.200
2 Tukang L.02 OH 0.200
3 Kepala Tukang L.03 OH 0.020
4 Mandor L.04 OH 0.060
JUMLAH TENAGA KERJA
B BAHAN
1 Semen Portlan Kg 230.000
2 Pasir Beton Kg 893.000
3 Kerikil (Maks 30mm) Kg 1,027.000
4 Air Liter -
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)

4.1.1.4.a Membuat 1 m³ lantai kerja beton mutu f'c =7,4 Mpa ( K 100), slump (3-6) cm ,w/c =0,87 (Menggunakan Mol

No Uraian Kode Satuan Koefisien


A TENAGA
1 Pekerja L.01 OH 0.960
2 Tukang L.02 OH 0.130
3 Kepala Tukang L.03 OH 0.013
4 Mandor L.04 OH 0.048
JUMLAH TENAGA KERJA
B BAHAN
1 Semen Portlan Kg 230.000
2 Pasir Beton Kg 893.000
3 Kerikil (Maks 30mm) Kg 1,027.000
4 Air Liter -
JUMLAH HARGA BAHAN
C PERALATAN
Sewa Molen Sewa-hari 0.250
JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)

CATATAN
bobot pasir =1.400 Kg/m³, Bobot isi kerikil = 1.350 Kg/m³, Buckling factor pasir =20%

4.1.1.5 Membuat 1 m³ beton mutu f'c =14,5 Mpa ( K 175), slump (12 ± 2) cm ,w/c = 0,66
No Uraian Kode Satuan Koefisien
A TENAGA
1 Pekerja L.01 OH 1.650
2 Tukang L.02 OH 0.275
3 Kepala Tukang L.03 OH 0.028
4 Mandor L.04 OH 0.083
JUMLAH TENAGA KERJA
B BAHAN
1 Semen Portlan Kg 326.000
2 Pasir Beton Kg 760.000
3 Kerikil (Maks 30mm) Kg 1,029.000
4 Air Liter -
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)
4.1.1.5.a Membuat 1 m³ beton mutu f'c =14,5 Mpa ( K 175), slump (12 ± 2) cm ,w/c = 0,66 (Menggunakan Molen)

No Uraian Kode Satuan Koefisien


A TENAGA
1 Pekerja L.01 OH 1.323
2 Tukang L.02 OH 0.189
3 Kepala Tukang L.03 OH 0.019
4 Mandor L.04 OH 0.066
JUMLAH TENAGA KERJA
B BAHAN
1 Semen Portlan Kg 326.000
2 Pasir Beton Kg 760.000
3 Kerikil (Maks 30mm) Kg 1,029.000
4 Air Liter -
JUMLAH HARGA BAHAN
C PERALATAN
Sewa Molen Sewa-hari 0.250
JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)

CATATAN
bobot pasir =1.400 Kg/m³, Bobot isi kerikil = 1.350 Kg/m³, Buckling factor pasir =20%

4.1.1.6 Membuat 1 m³ beton mutu f'c =16,9 Mpa ( K 200), slump (12 ± 2) cm ,w/c = 0,61

No Uraian Kode Satuan Koefisien


A TENAGA
1 Pekerja L.01 OH 1.650
2 Tukang L.02 OH 0.275
3 Kepala Tukang L.03 OH 0.028
4 Mandor L.04 OH 0.083
JUMLAH TENAGA KERJA
B BAHAN
1 Semen Portlan Kg 352.000
2 Pasir Beton Kg 731.000
3 Kerikil (Maks 30mm) Kg 1,031.000
4 Air Liter -
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)

4.1.1.6.a Membuat 1 m³ beton mutu f'c =16,9 Mpa ( K 200), slump (12 ± 2) cm ,w/c = 0,61 (Menggunakan Molen)
No Uraian Kode Satuan Koefisien
A TENAGA
1 Pekerja L.01 OH 1.323
2 Tukang L.02 OH 0.189
3 Kepala Tukang L.03 OH 0.019
4 Mandor L.04 OH 0.066
JUMLAH TENAGA KERJA
B BAHAN
1 Semen Portlan Kg 352.000
2 Pasir Beton Kg 731.000
3 Kerikil (Maks 30mm) Kg 1,031.000
4 Air Liter -
JUMLAH HARGA BAHAN
C PERALATAN
Sewa Molen Sewa-hari 0.250
JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)

CATATAN
bobot pasir =1.400 Kg/m³, Bobot isi kerikil = 1.350 Kg/m³, Buckling factor pasir =20%
4.1.1.7 Membuat 1 m³ beton mutu f'c =19,3 Mpa ( K 225), slump (12 ± 2) cm ,w/c = 0,58

No Uraian Kode Satuan Koefisien


A TENAGA
1 Pekerja L.01 OH 1.650
2 Tukang L.02 OH 0.275
3 Kepala Tukang L.03 OH 0.028
4 Mandor L.04 OH 0.083
JUMLAH TENAGA KERJA
B BAHAN
1 Semen Portlan Kg 371.000
2 Pasir Beton Kg 698.000
3 Kerikil (Maks 30mm) Kg 1,047.000
4 Air Liter -
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)

4.1.1.7.a Membuat 1 m³ beton mutu f'c =19,3 Mpa ( K 225), slump (12 ± 2) cm ,w/c = 0,58 (Menggunakan Molen)

No Uraian Kode Satuan Koefisien


A TENAGA
1 Pekerja L.01 OH 1.323
2 Tukang L.02 OH 0.189
3 Kepala Tukang L.03 OH 0.019
4 Mandor L.04 OH 0.066
JUMLAH TENAGA KERJA
B BAHAN
1 Semen Portlan Kg 371.000
2 Pasir Beton Kg 698.000
3 Kerikil (Maks 30mm) Kg 1,047.000
4 Air Liter -
JUMLAH HARGA BAHAN
C PERALATAN
Sewa Molen Sewa-hari 0.250
JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)

CATATAN
bobot pasir =1.400 Kg/m³, Bobot isi kerikil = 1.350 Kg/m³, Buckling factor pasir =20%

4.1.1.8 Membuat 1 m³ beton mutu f'c =21,7 Mpa ( K 250), slump (12 ± 2) cm ,w/c = 0,56
No Uraian Kode Satuan Koefisien
A TENAGA
1 Pekerja L.01 OH 1.650
2 Tukang L.02 OH 0.275
3 Kepala Tukang L.03 OH 0.028
4 Mandor L.04 OH 0.083
JUMLAH TENAGA KERJA
B BAHAN
1 Semen Portlan Kg 384.000
2 Pasir Beton Kg 692.000
3 Kerikil (Maks 30mm) Kg 1,039.000
4 Air Liter -
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)

CATATAN
bobot pasir =1.400 Kg/m³, Bobot isi kerikil = 1.350 Kg/m³, Buckling factor pasir =20%
4.1.1.9 Membuat 1 m³ beton mutu f'c =24,0 Mpa ( K 275), slump (12 ± 2) cm ,w/c = 0,53

No Uraian Kode Satuan Koefisien


A TENAGA
1 Pekerja L.01 OH 1.650
2 Tukang L.02 OH 0.275
3 Kepala Tukang L.03 OH 0.028
4 Mandor L.04 OH 0.083
JUMLAH TENAGA KERJA
B BAHAN
1 Semen Portlan Kg 406.000
2 Pasir Beton Kg 684.000
3 Kerikil (Maks 30mm) Kg 1,026.000
4 Air Liter -
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)

CATATAN
bobot pasir =1.400 Kg/m³, Bobot isi kerikil = 1.350 Kg/m³, Buckling factor pasir =20%

4.1.1.10 Membuat 1 m³ beton mutu f'c =26,4 Mpa ( K 300), slump (12 ± 2) cm ,w/c = 0,52

No Uraian Kode Satuan Koefisien


A TENAGA
1 Pekerja L.01 OH 1.650
2 Tukang L.02 OH 0.275
3 Kepala Tukang L.03 OH 0.028
4 Mandor L.04 OH 0.083
JUMLAH TENAGA KERJA
B BAHAN
1 Semen Portlan Kg 413.000
2 Pasir Beton Kg 681.000
3 Kerikil (Maks 30mm) Kg 1,021.000
4 Air Liter -
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)
CATATAN
bobot pasir =1.400 Kg/m³, Bobot isi kerikil = 1.350 Kg/m³, Buckling factor pasir =20%

4.1.1.11 Membuat 1 m³ beton mutu f'c =28,8 Mpa ( K 325), slump (12 ± 2) cm ,w/c = 0,49

No Uraian Kode Satuan Koefisien


A TENAGA
1 Pekerja L.01 OH 2.100
2 Tukang L.02 OH 0.350
3 Kepala Tukang L.03 OH 0.075
4 Mandor L.04 OH 0.105
JUMLAH TENAGA KERJA
B BAHAN
1 Semen Portlan Kg 439.000
2 Pasir Beton Kg 670.000
3 Kerikil (Maks 30mm) Kg 1,006.000
4 Air Liter -
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)

CATATAN
bobot pasir =1.400 Kg/m³, Bobot isi kerikil = 1.350 Kg/m³, Buckling factor pasir =20%
4.1.1.12 Membuat 1 m³ beton mutu f'c =31,2 Mpa ( K 350), slump (12 ± 2) cm ,w/c = 0,48

No Uraian Kode Satuan Koefisien


A TENAGA
1 Pekerja L.01 OH 2.100
2 Tukang L.02 OH 0.350
3 Kepala Tukang L.03 OH 0.075
4 Mandor L.04 OH 0.105
JUMLAH TENAGA KERJA
B BAHAN
1 Semen Portlan Kg 448.000
2 Pasir Beton Kg 667.000
3 Kerikil (Maks 30mm) Kg 1,000.000
4 Air Liter -
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)
CATATAN
bobot pasir =1.400 Kg/m³, Bobot isi kerikil = 1.350 Kg/m³, Buckling factor pasir =20%

4.1.1.14 Pemasangan 1m PVC waterstop lebar 150 mm

No Uraian Kode Satuan Koefisien


A TENAGA
1 Pekerja L.01 OH 0.060
2 Tukang L.02 OH 0.030
3 Kepala Tukang L.03 OH 0.003
4 Mandor L.04 OH 0.003
JUMLAH TENAGA KERJA
B BAHAN
1 waterstop lebar 150 mm m 1.050
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)

4.1.1.15 Pemasangan 1m PVC waterstop lebar 200 mm

No Uraian Kode Satuan Koefisien


A TENAGA
1 Pekerja L.01 OH 0.070
2 Tukang L.02 OH 0.035
3 Kepala Tukang L.03 OH 0.004
4 Mandor L.04 OH 0.007
JUMLAH TENAGA KERJA
B BAHAN
1 waterstop lebar 200 mm m 1.050
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)

4.1.1.16 Pemasangan 1m PVC waterstop lebar 230-320 mm

No Uraian Kode Satuan Koefisien


A TENAGA
1 Pekerja L.01 OH 0.080
2 Tukang L.02 OH 0.040
3 Kepala Tukang L.03 OH 0.004
4 Mandor L.04 OH 0.004
JUMLAH TENAGA KERJA
B BAHAN
1 waterstop lebar 230 -320 mm m 1.050
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)
4.1.1.17 Pembesian 10 Kg dengan besi polos atau besi ulir U 32

No Uraian Kode Satuan Koefisien


A TENAGA
1 Pekerja L.01 OH 0.070
2 Tukang L.02 OH 0.070
3 Kepala Tukang L.03 OH 0.007
4 Mandor L.04 OH 0.004
JUMLAH TENAGA KERJA
B BAHAN
1 Besi Beton (polos/ulir) U 32 Kg 10.500
2 Kawat Beton Kg 0.150
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)
G Harga Satuan Pekerjaan (D+E) per 1 kg

4.1.1.17.a Pembesian 10 Kg dengan besi polos atau besi ulir U 24

No Uraian Kode Satuan Koefisien


A TENAGA
1 Pekerja L.01 OH 0.070
2 Tukang L.02 OH 0.070
3 Kepala Tukang L.03 OH 0.007
4 Mandor L.04 OH 0.004
JUMLAH TENAGA KERJA
B BAHAN
1 Besi Beton (polos/ulir) U 24 Kg 10.500
2 Kawat Beton Kg 0.150
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)
G Harga Satuan Pekerjaan (D+E) per 1 kg

4.1.1.18 Pemasangan 10 Kg kabel presstressed polos/strands

No Uraian Kode Satuan Koefisien


A TENAGA
1 Pekerja L.01 OH 0.050
2 Tukang L.02 OH 0.050
3 Kepala Tukang L.03 OH 0.005
4 Mandor L.04 OH 0.003
JUMLAH TENAGA KERJA
B BAHAN
1 Besi Beton (polos/ulir) U32 Kg 10.500
2 Kawat Beton Kg 0.100
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)
G Harga Satuan Pekerjaan (D+E) per 1 kg

4.1.1.19 Pemasangan 10 Kg jaring kawat baja (wiremesh)

No Uraian Kode Satuan Koefisien


A TENAGA
1 Pekerja L.01 OH 0.025
2 Tukang L.02 OH 0.025
3 Kepala Tukang L.03 OH 0.025
4 Mandor L.04 OH 0.001
JUMLAH TENAGA KERJA
B BAHAN
1 Wiremesh m5 Kg 10.200
2 Kawat Beton Kg 0.050
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)
G Harga Satuan Pekerjaan (D+E) per 1 kg
4.1.1.20 Pemasangan 1m² bekisting untuk pondasi

No Uraian Kode Satuan Koefisien


A TENAGA
1 Pekerja L.01 OH 0.520
2 Tukang L.02 OH 0.260
3 Kepala Tukang L.03 OH 0.026
4 Mandor L.04 OH 0.026
JUMLAH TENAGA KERJA
B BAHAN
1 Ky klas III uk. 3/5 - 4 M ( tdk ketam) m³ 0.040
2 Paku 5 - 10 cm Kg 0.300
3 Minyak Bekisting Liter 0.100
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)

4.1.1.20.a Pemasangan 1m² bekisting untuk pondasi (papan mal)

No Uraian Kode Satuan Koefisien


A TENAGA
1 Pekerja L.01 OH 0.520
2 Tukang L.02 OH 0.260
3 Kepala Tukang L.03 OH 0.026
4 Mandor L.04 OH 0.026
JUMLAH TENAGA KERJA
B BAHAN
1 Papan Mal kelas III m³ 0.031
2 Paku 5 - 10 cm Kg 0.300
3 Cerucuk ф 6-8 cm - panj 4 m Btg 0.125
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)

4.1.1.20.b Pemasangan berulang 1m² bekisting untuk pondasi (papan mal)

No Uraian Kode Satuan Koefisien


A TENAGA
1 Pekerja L.01 OH 0.520
2 Tukang L.02 OH 0.260
3 Kepala Tukang L.03 OH 0.026
4 Mandor L.04 OH 0.026
JUMLAH TENAGA KERJA
B BAHAN
1 Papan Mal kelas III m³ 0.031
2 Paku 5 - 10 cm Kg 0.300
3 Cerucuk ф 6-8 cm - panj 4 m Btg 0.125
JUMLAH HARGA BAHAN
JUMLAH HARGA BAHAN x 55 %
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)

4.1.1.21 Pemasangan 1m² bekisting untuk sloof

No Uraian Kode Satuan Koefisien


A TENAGA
1 Pekerja L.01 OH 0.520
2 Tukang L.02 OH 0.260
3 Kepala Tukang L.03 OH 0.026
4 Mandor L.04 OH 0.026
JUMLAH TENAGA KERJA
B BAHAN
1 Kayu kelas III m³ 0.045
2 Paku 5 - 10 cm Kg 0.300
3 Minyak Bekisting Liter 0.100
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)
4.1.1.22 Pemasangan 1m² bekisting untuk kolom

No Uraian Kode Satuan Koefisien


A TENAGA
1 Pekerja L.01 OH 0.660
2 Tukang L.02 OH 0.330
3 Kepala Tukang L.03 OH 0.033
4 Mandor L.04 OH 0.033
JUMLAH TENAGA KERJA
B BAHAN
1 Kayu kelas III m³ 0.040
2 Paku 5 - 12 cm Kg 0.400
3 Minyak Bekisting Liter 0.200
4 Balok kayu kelas II m³ 0.015
5 Plywood tebal 9mm Lbr 0.350
6 Dolken kayu ф 8-10 cm - panj 4 m Batang 2.000
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)

4.1.1.22 a Pemasangan 1m² bekisting untuk kolom (papan mal)

No Uraian Kode Satuan Koefisien


A TENAGA
1 Pekerja L.01 OH 0.660
2 Tukang L.02 OH 0.330
3 Kepala Tukang L.03 OH 0.033
4 Mandor L.04 OH 0.033
JUMLAH TENAGA KERJA
B BAHAN
1 Kayu kelas III m³ 0.040
2 Paku 5 - 12 cm Kg 0.400
3 Minyak Bekisting Liter -
4 Balok kayu kelas II m³ 0.015
5 Papan Mal kelas III m³ 0.022
6 Dolken kayu ф 8-10 cm - panj 4 m Batang 2.000
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)

4.1.1.22 b Pemasangan berulang 1m² bekisting untuk kolom (papan mal)


No Uraian Kode Satuan Koefisien
A TENAGA
1 Pekerja L.01 OH 0.660
2 Tukang L.02 OH 0.330
3 Kepala Tukang L.03 OH 0.033
4 Mandor L.04 OH 0.033
JUMLAH TENAGA KERJA
B BAHAN
1 Kayu kelas III m³ 0.040
2 Paku 5 - 12 cm Kg 0.400
3 Minyak Bekisting Liter -
4 Balok kayu kelas II m³ 0.015
5 Papan Mal kelas III m³ 0.022
6 Dolken kayu ф 8-10 cm - panj 4 m Batang 2.000
JUMLAH HARGA BAHAN
JUMLAH HARGA BAHAN x 55 %
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)
4.1.1.23 Pemasangan 1m² bekisting untuk balok

No Uraian Kode Satuan Koefisien


A TENAGA
1 Pekerja L.01 OH 0.660
2 Tukang L.02 OH 0.330
3 Kepala Tukang L.03 OH 0.033
4 Mandor L.04 OH 0.033
JUMLAH TENAGA KERJA
B BAHAN
1 Kayu kelas III m³ 0.040
2 Paku 5 - 12 cm Kg 0.400
3 Minyak Bekisting Liter 0.200
4 Balok kayu kelas II m³ 0.018
5 Plywood tebal 9mm Lbr 0.350
6 Dolken kayu ф 8-10 cm - panj 4 m Batang 2.000
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)

4.1.1.23.a Pemasangan 1m² bekisting untuk balok (papan mal)

No Uraian Kode Satuan Koefisien


A TENAGA
1 Pekerja L.01 OH 0.660
2 Tukang L.02 OH 0.330
3 Kepala Tukang L.03 OH 0.033
4 Mandor L.04 OH 0.033
JUMLAH TENAGA KERJA
B BAHAN
1 Kayu kelas III m³ 0.040
2 Paku 5 - 12 cm Kg 0.400
3 Minyak Bekisting Liter -
4 Balok kayu kelas II m³ 0.018
5 Papan Mal kelas III m³ 0.022
6 Dolken kayu ф 8-10 cm - panj 4 m Batang 2.000
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)

4.1.1.23.b Pemasangan berulang 1m² bekisting untuk balok (papan mal)


No Uraian Kode Satuan Koefisien
A TENAGA
1 Pekerja L.01 OH 0.660
2 Tukang L.02 OH 0.330
3 Kepala Tukang L.03 OH 0.033
4 Mandor L.04 OH 0.033
JUMLAH TENAGA KERJA
B BAHAN
1 Kayu kelas III m³ 0.040
2 Paku 5 - 12 cm Kg 0.400
3 Minyak Bekisting Liter -
4 Balok kayu kelas II m³ 0.018
5 Papan Mal kelas III m³ 0.022
6 Dolken kayu ф 8-10 cm - panj 4 m Batang 2.000
JUMLAH HARGA BAHAN
JUMLAH HARGA BAHAN x 55 %
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)
4.1.1.24 Pemasangan 1m² bekisting untuk lantai

No Uraian Kode Satuan Koefisien


A TENAGA
1 Pekerja L.01 OH 0.660
2 Tukang L.02 OH 0.330
3 Kepala Tukang L.03 OH 0.033
4 Mandor L.04 OH 0.033
JUMLAH TENAGA KERJA
B BAHAN
1 Kayu kelas III m³ 0.040
2 Paku 5 - 12 cm Kg 0.400
3 Minyak Bekisting Liter 0.200
4 Balok kayu kelas II m³ 0.015
5 Plywood tebal 9mm Lbr 0.350
6 Dolken kayu ф 8-10 cm - panj 4 m Batang 6.000
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)

4.1.1.24.a Pemasangan 1m² bekisting untuk lantai (papan mal)

No Uraian Kode Satuan Koefisien


A TENAGA
1 Pekerja L.01 OH 0.660
2 Tukang L.02 OH 0.330
3 Kepala Tukang L.03 OH 0.033
4 Mandor L.04 OH 0.033
JUMLAH TENAGA KERJA
B BAHAN
1 Kayu kelas III m³ 0.040
2 Paku 5 - 12 cm Kg 0.400
3 Minyak Bekisting Liter -
4 Balok kayu kelas II m³ 0.015
5 Papan Mal kelas III m³ 0.022
6 Dolken kayu ф 8-10 cm - panj 4 m Batang 6.000
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)

4.1.1.24.b Pemasangan berulang 1m² bekisting untuk lantai (papan mal)


No Uraian Kode Satuan Koefisien
A TENAGA
1 Pekerja L.01 OH 0.660
2 Tukang L.02 OH 0.330
3 Kepala Tukang L.03 OH 0.033
4 Mandor L.04 OH 0.033
JUMLAH TENAGA KERJA
B BAHAN
1 Kayu kelas III m³ 0.040
2 Paku 5 - 12 cm Kg 0.400
3 Minyak Bekisting Liter -
4 Balok kayu kelas II m³ 0.015
5 Papan Mal kelas III m³ 0.022
6 Dolken kayu ф 8-10 cm - panj 4 m Batang 6.000
JUMLAH HARGA BAHAN
JUMLAH HARGA BAHAN x 55 %
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)
4.1.1.25 Pemasangan 1m² bekisting untuk dinding

No Uraian Kode Satuan Koefisien


A TENAGA
1 Pekerja L.01 OH 0.660
2 Tukang L.02 OH 0.330
3 Kepala Tukang L.03 OH 0.033
4 Mandor L.04 OH 0.033
JUMLAH TENAGA KERJA
B BAHAN
1 Kayu kelas III m³ 0.030
2 Paku 5 - 12 cm Kg 0.400
3 Minyak Bekisting Liter 0.200
4 Balok kayu kelas II m³ 0.020
5 Plywood tebal 9mm Lbr 0.350
6 Dolken kayu ф 8-10 cm - panj 4 m Batang 3.000
7 Penjaga jarak bekisting/spacer Buah 4.000
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)

4.1.1.25.a Pemasangan 1m² bekisting untuk dinding (papan mal)

No Uraian Kode Satuan Koefisien


A TENAGA
1 Pekerja L.01 OH 0.660
2 Tukang L.02 OH 0.330
3 Kepala Tukang L.03 OH 0.033
4 Mandor L.04 OH 0.033
JUMLAH TENAGA KERJA
B BAHAN
1 Kayu kelas III m³ 0.030
2 Paku 5 - 12 cm Kg 0.400
3 Minyak Bekisting Liter -
4 Balok kayu kelas II m³ 0.020
5 Papan Mal kelas III m³ 0.022
6 Dolken kayu ф 8-10 cm - panj 4 m Batang 3.000
7 Penjaga jarak bekisting/spacer Buah 4.000
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)
4.1.1.25.b Pemasangan berulang 1m² bekisting untuk dinding (papan mal)

No Uraian Kode Satuan Koefisien


A TENAGA
1 Pekerja L.01 OH 0.660
2 Tukang L.02 OH 0.330
3 Kepala Tukang L.03 OH 0.033
4 Mandor L.04 OH 0.033
JUMLAH TENAGA KERJA
B BAHAN
1 Kayu kelas III m³ 0.030
2 Paku 5 - 12 cm Kg 0.400
3 Minyak Bekisting Liter -
4 Balok kayu kelas II m³ 0.020
5 Papan Mal kelas III m³ 0.022
6 Dolken kayu ф 8-10 cm - panj 4 m Batang 3.000
7 Penjaga jarak bekisting/spacer Buah 4.000
JUMLAH HARGA BAHAN
JUMLAH HARGA BAHAN x 55 %
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)
4.1.1.26 Pemasangan 1m² bekisting untuk tangga

No Uraian Kode Satuan Koefisien


A TENAGA
1 Pekerja L.01 OH 0.660
2 Tukang L.02 OH 0.330
3 Kepala Tukang L.03 OH 0.033
4 Mandor L.04 OH 0.033
JUMLAH TENAGA KERJA
B BAHAN
1 Kayu kelas III m³ 0.030
2 Paku 5 - 12 cm Kg 0.400
3 Minyak Bekisting Liter 0.150
4 Balok kayu kelas II m³ 0.015
5 Plywood tebal 9mm Lbr 0.350
6 Dolken kayu ф 8-10 cm - panj 4 m Batang 2.000
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)

4.1.1.27 Pemasangan 1m² jembatan untuk pengecoran beton

No Uraian Kode Satuan Koefisien


A TENAGA
1 Pekerja L.01 OH 0.150
2 Tukang L.02 OH 0.050
3 Kepala Tukang L.03 OH 0.005
4 Mandor L.04 OH 0.008
JUMLAH TENAGA KERJA
B BAHAN
1 Kayu kelas III (papan) m³ 0.026
2 Paku 5 - 12 cm Kg 0.600
3 Dolken kayu ф 8-10 cm - panj 4 m Batang 0.500
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)

4.1.1.35 Membuat 1 m³ kolom praktis beton bertulang (11 x 11 ) cm


No Uraian Kode Satuan Koefisien
A TENAGA
1 Pekerja L.01 OH 0.180
2 Tukang batu L.02 OH 0.020
3 Tukang kayu L.02 OH 0.020
4 Tukang Besi L.02 OH 0.020
5 Kepala Tukang L.03 OH 0.006
6 Mandor L.04 OH 0.009
JUMLAH TENAGA KERJA
B BAHAN
1 Kayu kelas III (papan) m³ 0.002
2 Paku 5 - 12 cm Kg 0.010
3 Minyak bekisting Liter
4 Besi beton polos U 24 Kg 3.000
5 Kawat beton Kg 0.450
6 Semen portland Kg 4.000
7 Pasir beton m³ 0.006
8 Kerikil m³ 0.009
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)
B. 13.a.1 Membuat 1 m³ beton ready mix K 100 menggunakan pompa

No Uraian Kode Satuan Koefisien


A TENAGA
1 Pekerja L.01 OH 1.000
2 Tukang L.02 OH 0.250
3 Kepala Tukang L.03 OH 0.025
4 Mandor L.04 OH 0.100
JUMLAH TENAGA KERJA
B BAHAN
1 Beton Ready Mix K 100 m³ 1.020
JUMLAH HARGA BAHAN
C PERALATAN
1 Pompa Ready mix Sewa-hari 0.120
JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)

B. 13.a.2 Membuat 1 m³ beton ready mix K 100 tidak menggunakan pompa

No Uraian Kode Satuan Koefisien


A TENAGA
1 Pekerja L.01 OH 1.000
2 Tukang L.02 OH 0.250
3 Kepala Tukang L.03 OH 0.025
4 Mandor L.04 OH 0.100
JUMLAH TENAGA KERJA
B BAHAN
1 Beton Ready Mix K 100 m³ 1.020
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)

B. 13.b.1 Membuat 1 m³ beton ready mix K 125 menggunakan pompa

No Uraian Kode Satuan Koefisien


A TENAGA
1 Pekerja L.01 OH 1.000
2 Tukang L.02 OH 0.250
3 Kepala Tukang L.03 OH 0.025
4 Mandor L.04 OH 0.100
JUMLAH TENAGA KERJA
B BAHAN
1 Beton Ready Mix K 125 m³ 1.020
JUMLAH HARGA BAHAN
C PERALATAN
1 Pompa Ready mix Sewa-hari 0.120
JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)

B. 13.b.2 Membuat 1 m³ beton ready mix K 125 tidak menggunakan pompa

No Uraian Kode Satuan Koefisien


A TENAGA
1 Pekerja L.01 OH 1.000
2 Tukang L.02 OH 0.250
3 Kepala Tukang L.03 OH 0.025
4 Mandor L.04 OH 0.100
JUMLAH TENAGA KERJA
B BAHAN
1 Beton Ready Mix K 125 m³ 1.020
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)
B. 13.c.1 Membuat 1 m³ beton ready mix K 150 menggunakan pompa

No Uraian Kode Satuan Koefisien


A TENAGA
1 Pekerja L.01 OH 1.000
2 Tukang L.02 OH 0.250
3 Kepala Tukang L.03 OH 0.025
4 Mandor L.04 OH 0.100
JUMLAH TENAGA KERJA
B BAHAN
1 Beton Ready Mix K 150 m³ 1.020
JUMLAH HARGA BAHAN
C PERALATAN
1 Pompa Ready mix Sewa-hari 0.120
JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)

B. 13.c.2 Membuat 1 m³ beton ready mix K 150 tidak menggunakan pompa

No Uraian Kode Satuan Koefisien


A TENAGA
1 Pekerja L.01 OH 1.000
2 Tukang L.02 OH 0.250
3 Kepala Tukang L.03 OH 0.025
4 Mandor L.04 OH 0.100
JUMLAH TENAGA KERJA
B BAHAN
1 Beton Ready Mix K 150 m³ 1.020
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)

B. 13.d.1 Membuat 1 m³ beton ready mix K 175 menggunakan pompa

No Uraian Kode Satuan Koefisien


A TENAGA
1 Pekerja L.01 OH 1.000
2 Tukang L.02 OH 0.250
3 Kepala Tukang L.03 OH 0.025
4 Mandor L.04 OH 0.100
JUMLAH TENAGA KERJA
B BAHAN
1 Beton Ready Mix K 175 m³ 1.020
JUMLAH HARGA BAHAN
C PERALATAN
1 Pompa Ready mix Sewa-hari 0.120
JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)

B. 13.d.2 Membuat 1 m³ beton ready mix K 175 tidak menggunakan pompa

No Uraian Kode Satuan Koefisien


A TENAGA
1 Pekerja L.01 OH 1.000
2 Tukang L.02 OH 0.250
3 Kepala Tukang L.03 OH 0.025
4 Mandor L.04 OH 0.100
JUMLAH TENAGA KERJA
B BAHAN
1 Beton Ready Mix K 175 m³ 1.020
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)
B. 13.e.1 Membuat 1 m³ beton ready mix K 200 menggunakan pompa

No Uraian Kode Satuan Koefisien


A TENAGA
1 Pekerja L.01 OH 1.000
2 Tukang L.02 OH 0.250
3 Kepala Tukang L.03 OH 0.025
4 Mandor L.04 OH 0.100
JUMLAH TENAGA KERJA
B BAHAN
1 Beton Ready Mix K 200 m³ 1.020
JUMLAH HARGA BAHAN
C PERALATAN
1 Pompa Ready mix Sewa-hari 0.120
JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)

B. 13.e.2 Membuat 1 m³ beton ready mix K 200 tidak menggunakan pompa

No Uraian Kode Satuan Koefisien


A TENAGA
1 Pekerja L.01 OH 1.000
2 Tukang L.02 OH 0.250
3 Kepala Tukang L.03 OH 0.025
4 Mandor L.04 OH 0.100
JUMLAH TENAGA KERJA
B BAHAN
1 Beton Ready Mix K 200 m³ 1.020
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)

B. 13.f.1 Membuat 1 m³ beton ready mix K 225 menggunakan pompa

No Uraian Kode Satuan Koefisien


A TENAGA
1 Pekerja L.01 OH 1.000
2 Tukang L.02 OH 0.250
3 Kepala Tukang L.03 OH 0.025
4 Mandor L.04 OH 0.100
JUMLAH TENAGA KERJA
B BAHAN
1 Beton Ready Mix K 225 m³ 1.020
JUMLAH HARGA BAHAN
C PERALATAN
1 Pompa Ready mix Sewa-hari 0.120
JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)

B. 13.f.2 Membuat 1 m³ beton ready mix K 225 tidak menggunakan pompa

No Uraian Kode Satuan Koefisien


A TENAGA
1 Pekerja L.01 OH 1.000
2 Tukang L.02 OH 0.250
3 Kepala Tukang L.03 OH 0.025
4 Mandor L.04 OH 0.100
JUMLAH TENAGA KERJA
B BAHAN
1 Beton Ready Mix K 225 m³ 1.020
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)
B. 13.g.1 Membuat 1 m³ beton ready mix K 250 menggunakan pompa

No Uraian Kode Satuan Koefisien


A TENAGA
1 Pekerja L.01 OH 1.000
2 Tukang L.02 OH 0.250
3 Kepala Tukang L.03 OH 0.025
4 Mandor L.04 OH 0.100
JUMLAH TENAGA KERJA
B BAHAN
1 Beton Ready Mix K 250 m³ 1.020
JUMLAH HARGA BAHAN
C PERALATAN
1 Pompa Ready mix Sewa-hari 0.120
JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)

B. 13.g.2 Membuat 1 m³ beton ready mix K 250 tidak menggunakan pompa

No Uraian Kode Satuan Koefisien


A TENAGA
1 Pekerja L.01 OH 1.000
2 Tukang L.02 OH 0.250
3 Kepala Tukang L.03 OH 0.025
4 Mandor L.04 OH 0.100
JUMLAH TENAGA KERJA
B BAHAN
1 Beton Ready Mix K 250 m³ 1.020
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)

B. 13.h.1 Membuat 1 m³ beton ready mix K 275 menggunakan pompa

No Uraian Kode Satuan Koefisien


A TENAGA
1 Pekerja L.01 OH 1.000
2 Tukang L.02 OH 0.250
3 Kepala Tukang L.03 OH 0.025
4 Mandor L.04 OH 0.100
JUMLAH TENAGA KERJA
B BAHAN
1 Beton Ready Mix K 275 m³ 1.020
JUMLAH HARGA BAHAN
C PERALATAN
1 Pompa Ready mix Sewa-hari 0.120
JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)

B. 13.h.2 Membuat 1 m³ beton ready mix K 275 tidak menggunakan pompa

No Uraian Kode Satuan Koefisien


A TENAGA
1 Pekerja L.01 OH 1.000
2 Tukang L.02 OH 0.250
3 Kepala Tukang L.03 OH 0.025
4 Mandor L.04 OH 0.100
JUMLAH TENAGA KERJA
B BAHAN
1 Beton Ready Mix K 275 m³ 1.020
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)
B. 13.i.1 Membuat 1 m³ beton ready mix K 300 menggunakan pompa

No Uraian Kode Satuan Koefisien


A TENAGA
1 Pekerja L.01 OH 1.000
2 Tukang L.02 OH 0.250
3 Kepala Tukang L.03 OH 0.025
4 Mandor L.04 OH 0.100
JUMLAH TENAGA KERJA
B BAHAN
1 Beton Ready Mix K 300 m³ 1.020
JUMLAH HARGA BAHAN
C PERALATAN
1 Pompa Ready mix Sewa-hari 0.120
JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)

B. 13.i.2 Membuat 1 m³ beton ready mix K 300 tidak menggunakan pompa

No Uraian Kode Satuan Koefisien


A TENAGA
1 Pekerja L.01 OH 1.000
2 Tukang L.02 OH 0.250
3 Kepala Tukang L.03 OH 0.025
4 Mandor L.04 OH 0.100
JUMLAH TENAGA KERJA
B BAHAN
1 Beton Ready Mix K 300 m³ 1.020
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)

B. 13.j.1 Membuat 1 m³ beton ready mix K 325 menggunakan pompa

No Uraian Kode Satuan Koefisien


A TENAGA
1 Pekerja L.01 OH 1.000
2 Tukang L.02 OH 0.250
3 Kepala Tukang L.03 OH 0.025
4 Mandor L.04 OH 0.100
JUMLAH TENAGA KERJA
B BAHAN
1 Beton Ready Mix K 325 m³ 1.020
JUMLAH HARGA BAHAN
C PERALATAN
1 Pompa Ready mix Sewa-hari 0.120
JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)

B. 13.j.2 Membuat 1 m³ beton ready mix K 325 tidak menggunakan pompa

No Uraian Kode Satuan Koefisien


A TENAGA
1 Pekerja L.01 OH 1.000
2 Tukang L.02 OH 0.250
3 Kepala Tukang L.03 OH 0.025
4 Mandor L.04 OH 0.100
JUMLAH TENAGA KERJA
B BAHAN
1 Beton Ready Mix K 325 m³ 1.020
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)
B. 13.k.1 Membuat 1 m³ beton ready mix K 350 menggunakan pompa

No Uraian Kode Satuan Koefisien


A TENAGA
1 Pekerja L.01 OH 1.000
2 Tukang L.02 OH 0.250
3 Kepala Tukang L.03 OH 0.025
4 Mandor L.04 OH 0.100
JUMLAH TENAGA KERJA
B BAHAN
1 Beton Ready Mix K 350 m³ 1.020
JUMLAH HARGA BAHAN
C PERALATAN
1 Pompa Ready mix Sewa-hari 0.120
JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)

B. 13.k.2 Membuat 1 m³ beton ready mix K 350 tidak menggunakan pompa

No Uraian Kode Satuan Koefisien


A TENAGA
1 Pekerja L.01 OH 1.000
2 Tukang L.02 OH 0.250
3 Kepala Tukang L.03 OH 0.025
4 Mandor L.04 OH 0.100
JUMLAH TENAGA KERJA
B BAHAN
1 Beton Ready Mix K 350 m³ 1.020
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)

B. 13.l.1 Membuat 1 m³ beton ready mix K 375 menggunakan pompa

No Uraian Kode Satuan Koefisien


A TENAGA
1 Pekerja L.01 OH 1.000
2 Tukang L.02 OH 0.250
3 Kepala Tukang L.03 OH 0.025
4 Mandor L.04 OH 0.100
JUMLAH TENAGA KERJA
B BAHAN
1 Beton Ready Mix K 375 m³ 1.020
JUMLAH HARGA BAHAN
C PERALATAN
1 Pompa Ready mix Sewa-hari 0.120
JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)

B. 13.l.2 Membuat 1 m³ beton ready mix K 375 tidak menggunakan pompa

No Uraian Kode Satuan Koefisien


A TENAGA
1 Pekerja L.01 OH 1.000
2 Tukang L.02 OH 0.250
3 Kepala Tukang L.03 OH 0.025
4 Mandor L.04 OH 0.100
JUMLAH TENAGA KERJA
B BAHAN
1 Beton Ready Mix K 375 m³ 1.020
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)
B. 13.m.1 Membuat 1 m³ beton ready mix K 400 menggunakan pompa

No Uraian Kode Satuan Koefisien


A TENAGA
1 Pekerja L.01 OH 1.000
2 Tukang L.02 OH 0.250
3 Kepala Tukang L.03 OH 0.025
4 Mandor L.04 OH 0.100
JUMLAH TENAGA KERJA
B BAHAN
1 Beton Ready Mix K 400 m³ 1.020
JUMLAH HARGA BAHAN
C PERALATAN
1 Pompa Ready mix Sewa-hari 0.120
JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)

B. 13.m.3 Membuat 1 m³ beton ready mix K 400 tidak menggunakan pompa

No Uraian Kode Satuan Koefisien


A TENAGA
1 Pekerja L.01 OH 1.000
2 Tukang L.02 OH 0.250
3 Kepala Tukang L.03 OH 0.025
4 Mandor L.04 OH 0.100
JUMLAH TENAGA KERJA
B BAHAN
1 Beton Ready Mix K 400 m³ 1.020
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)
Harga Satuan (Rp) Jumlah Harga (Rp)

90,000.00 148,500.00
100,000.00 27,500.00
110,000.00 3,080.00
120,000.00 9,960.00
JUMLAH TENAGA KERJA 189,040.00

1,500.00 370,500.00
71.50 62,133.50
339.33 338,994.00
- -
JUMLAH HARGA BAHAN 771,627.50

JUMLAH HARGA ALAT

960,667.50
15% x D 144,100.13
1,104,767.63

cm ,w/c =0,87 (Menggunakan Molen)

Harga Satuan (Rp) Jumlah Harga (Rp)

90,000.00 119,070.00
100,000.00 18,900.00
110,000.00 2,090.00
120,000.00 7,920.00
JUMLAH TENAGA KERJA 147,980.00

1,500.00 370,500.00
71.50 62,133.50
339.33 338,994.00
- -
JUMLAH HARGA BAHAN 771,627.50

170,000.00 42,500.00
JUMLAH HARGA ALAT 42,500.00

962,107.50
15% x D 144,316.13
1,106,423.63
Harga Satuan (Rp) Jumlah Harga (Rp)

90,000.00 148,500.00
100,000.00 27,500.00
110,000.00 3,080.00
120,000.00 9,960.00
JUMLAH TENAGA KERJA 189,040.00

1,500.00 414,000.00
71.50 59,202.00
339.33 343,405.33
- -
JUMLAH HARGA BAHAN 816,607.33

JUMLAH HARGA ALAT

1,005,647.33
15% x D 150,847.10
1,156,494.43
cm ,w/c =0,78 (Menggunakan Molen)

Harga Satuan (Rp) Jumlah Harga (Rp)

90,000.00 119,070.00
100,000.00 18,900.00
110,000.00 2,090.00
120,000.00 7,920.00
JUMLAH TENAGA KERJA 147,980.00

1,500.00 414,000.00
71.50 59,202.00
339.33 343,405.33
- -
JUMLAH HARGA BAHAN 816,607.33

170,000.00 42,500.00
JUMLAH HARGA ALAT 42,500.00

1,007,087.33
15% x D 151,063.10
1,158,150.43

Harga Satuan (Rp) Jumlah Harga (Rp)

90,000.00 148,500.00
100,000.00 27,500.00
110,000.00 3,080.00
120,000.00 9,960.00
JUMLAH TENAGA KERJA 189,040.00

1,500.00 448,500.00
71.50 57,128.50
339.33 345,102.00
- -
JUMLAH HARGA BAHAN 850,730.50

JUMLAH HARGA ALAT

1,039,770.50
15% x D 155,965.58
1,195,736.08

) cm ,w/c =0,72 (Menggunakan Molen)


Harga Satuan (Rp) Jumlah Harga (Rp)

90,000.00 119,070.00
100,000.00 18,900.00
110,000.00 2,090.00
120,000.00 7,920.00
JUMLAH TENAGA KERJA 147,980.00

1,500.00 448,500.00
71.50 57,128.50
339.33 345,102.00
- -
JUMLAH HARGA BAHAN 850,730.50

170,000.00 42,500.00
JUMLAH HARGA ALAT 42,500.00

1,041,210.50
15% x D 156,181.58
1,197,392.08
Harga Satuan (Rp) Jumlah Harga (Rp)

90,000.00 108,000.00
100,000.00 20,000.00
110,000.00 2,200.00
120,000.00 7,200.00
JUMLAH TENAGA KERJA 137,400.00

1,500.00 345,000.00
71.50 63,849.50
339.33 348,495.33
- -
JUMLAH HARGA BAHAN 757,344.83

JUMLAH HARGA ALAT

894,744.83
134,211.73
1,028,956.56

mp (3-6) cm ,w/c =0,87 (Menggunakan Molen)

Harga Satuan (Rp) Jumlah Harga (Rp)

90,000.00 86,400.00
100,000.00 13,000.00
110,000.00 1,430.00
120,000.00 5,760.00
JUMLAH TENAGA KERJA 106,590.00

1,500.00 345,000.00
71.50 63,849.50
339.33 348,495.33
- -
JUMLAH HARGA BAHAN 757,344.83

170,000.00 42,500.00
JUMLAH HARGA ALAT 42,500.00

906,434.83
135,965.23
1,042,400.06
Harga Satuan (Rp) Jumlah Harga (Rp)

90,000.00 148,500.00
100,000.00 27,500.00
110,000.00 3,080.00
120,000.00 9,960.00
JUMLAH TENAGA KERJA 189,040.00

1,500.00 489,000.00
71.50 54,340.00
339.33 349,174.00
- -
JUMLAH HARGA BAHAN 892,514.00

JUMLAH HARGA ALAT

1,081,554.00
162,233.10
1,243,787.10
2) cm ,w/c = 0,66 (Menggunakan Molen)

Harga Satuan (Rp) Jumlah Harga (Rp)

90,000.00 119,070.00
100,000.00 18,900.00
110,000.00 2,090.00
120,000.00 7,920.00
JUMLAH TENAGA KERJA 147,980.00

1,500.00 489,000.00
71.50 54,340.00
339.33 349,174.00
- -
JUMLAH HARGA BAHAN 892,514.00

170,000.00 42,500.00
JUMLAH HARGA ALAT 42,500.00

1,082,994.00
162,449.10
1,245,443.10

Harga Satuan (Rp) Jumlah Harga (Rp)

90,000.00 148,500.00
100,000.00 27,500.00
110,000.00 3,080.00
120,000.00 9,960.00
JUMLAH TENAGA KERJA 189,040.00

1,500.00 528,000.00
71.50 52,266.50
339.33 349,852.67
- -
JUMLAH HARGA BAHAN 930,119.17

JUMLAH HARGA ALAT

1,119,159.17
167,873.88
1,287,033.04

2) cm ,w/c = 0,61 (Menggunakan Molen)


Harga Satuan (Rp) Jumlah Harga (Rp)

90,000.00 119,070.00
100,000.00 18,900.00
110,000.00 2,090.00
120,000.00 7,920.00
JUMLAH TENAGA KERJA 147,980.00

1,500.00 528,000.00
71.50 52,266.50
339.33 349,852.67
- -
JUMLAH HARGA BAHAN 930,119.17

170,000.00 42,500.00
JUMLAH HARGA ALAT 42,500.00

1,120,599.17
168,089.88
1,288,689.04
Harga Satuan (Rp) Jumlah Harga (Rp)

90,000.00 148,500.00
100,000.00 27,500.00
110,000.00 3,080.00
120,000.00 9,960.00
JUMLAH TENAGA KERJA 189,040.00

1,500.00 556,500.00
71.50 49,907.00
339.33 355,282.00
- -
JUMLAH HARGA BAHAN 961,689.00

JUMLAH HARGA ALAT

1,150,729.00
172,609.35
1,323,338.35

2) cm ,w/c = 0,58 (Menggunakan Molen)

Harga Satuan (Rp) Jumlah Harga (Rp)

90,000.00 119,070.00
100,000.00 18,900.00
110,000.00 2,090.00
120,000.00 7,920.00
JUMLAH TENAGA KERJA 147,980.00

1,500.00 556,500.00
71.50 49,907.00
339.33 355,282.00
- -
JUMLAH HARGA BAHAN 961,689.00

165,000.00 41,250.00
JUMLAH HARGA ALAT 41,250.00

1,150,919.00
172,637.85
1,323,556.85
Harga Satuan (Rp) Jumlah Harga (Rp)

90,000.00 148,500.00
100,000.00 27,500.00
110,000.00 3,080.00
120,000.00 9,960.00
JUMLAH TENAGA KERJA 189,040.00

1,500.00 576,000.00
71.50 49,478.00
339.33 352,567.33
- -
JUMLAH HARGA BAHAN 978,045.33

JUMLAH HARGA ALAT

1,167,085.33
175,062.80
1,342,148.13
Harga Satuan (Rp) Jumlah Harga (Rp)

90,000.00 148,500.00
100,000.00 27,500.00
110,000.00 3,080.00
120,000.00 9,960.00
JUMLAH TENAGA KERJA 189,040.00

1,500.00 609,000.00
71.50 48,906.00
339.33 348,156.00
- -
JUMLAH HARGA BAHAN 1,006,062.00

JUMLAH HARGA ALAT

1,195,102.00
179,265.30
1,374,367.30

Harga Satuan (Rp) Jumlah Harga (Rp)

90,000.00 148,500.00
100,000.00 27,500.00
110,000.00 3,080.00
120,000.00 9,960.00
JUMLAH TENAGA KERJA 189,040.00

1,500.00 619,500.00
71.50 48,691.50
339.33 346,459.33
- -
JUMLAH HARGA BAHAN 1,014,650.83

JUMLAH HARGA ALAT

1,203,690.83
180,553.63
1,384,244.46
Harga Satuan (Rp) Jumlah Harga (Rp)

90,000.00 189,000.00
100,000.00 35,000.00
110,000.00 8,250.00
120,000.00 12,600.00
JUMLAH TENAGA KERJA 244,850.00

1,500.00 658,500.00
71.50 47,905.00
339.33 341,369.33
- -
JUMLAH HARGA BAHAN 1,047,774.33

JUMLAH HARGA ALAT

1,292,624.33
193,893.65
1,486,517.98
Harga Satuan (Rp) Jumlah Harga (Rp)

90,000.00 189,000.00
100,000.00 35,000.00
110,000.00 8,250.00
120,000.00 12,600.00
JUMLAH TENAGA KERJA 244,850.00

1,500.00 672,000.00
71.50 47,690.50
339.33 339,333.33
- -
JUMLAH HARGA BAHAN 1,059,023.83

JUMLAH HARGA ALAT


1,303,873.83
195,581.08
1,499,454.91

Harga Satuan (Rp) Jumlah Harga (Rp)

90,000.00 5,400.00
100,000.00 3,000.00
110,000.00 330.00
120,000.00 360.00
JUMLAH TENAGA KERJA 9,090.00

125,000.00 131,250.00
JUMLAH HARGA BAHAN 131,250.00

JUMLAH HARGA ALAT


140,340.00
21,051.00
161,391.00

Harga Satuan (Rp) Jumlah Harga (Rp)

90,000.00 6,300.00
100,000.00 3,500.00
110,000.00 440.00
120,000.00 840.00
JUMLAH TENAGA KERJA 11,080.00

135,000.00 141,750.00
JUMLAH HARGA BAHAN 141,750.00

JUMLAH HARGA ALAT


152,830.00
22,924.50
175,754.50

Harga Satuan (Rp) Jumlah Harga (Rp)

90,000.00 7,200.00
100,000.00 4,000.00
110,000.00 440.00
120,000.00 480.00
JUMLAH TENAGA KERJA 12,120.00

150,000.00 157,500.00
JUMLAH HARGA BAHAN 157,500.00

JUMLAH HARGA ALAT


169,620.00
25,443.00
195,063.00
Harga Satuan (Rp) Jumlah Harga (Rp)

90,000.00 6,300.00
100,000.00 7,000.00
110,000.00 770.00
120,000.00 480.00
JUMLAH TENAGA KERJA 14,550.00

10,600.00 111,300.00
20,000.00 3,000.00
JUMLAH HARGA BAHAN 114,300.00

JUMLAH HARGA ALAT


128,850.00
19,327.50
148,177.50
14,817.75

Harga Satuan (Rp) Jumlah Harga (Rp)

90,000.00 6,300.00
100,000.00 7,000.00
110,000.00 770.00
120,000.00 480.00
JUMLAH TENAGA KERJA 14,550.00

10,600.00 111,300.00
20,000.00 3,000.00
JUMLAH HARGA BAHAN 114,300.00

JUMLAH HARGA ALAT


128,850.00
19,327.50
148,177.50
14,817.75

Harga Satuan (Rp) Jumlah Harga (Rp)

90,000.00 4,500.00
100,000.00 5,000.00
110,000.00 550.00
120,000.00 360.00
JUMLAH TENAGA KERJA 10,410.00
10,600.00 111,300.00
20,000.00 2,000.00
JUMLAH HARGA BAHAN 113,300.00

JUMLAH HARGA ALAT


123,710.00
18,556.50
142,266.50
14,226.65

Harga Satuan (Rp) Jumlah Harga (Rp)

90,000.00 2,250.00
100,000.00 2,500.00
110,000.00 2,750.00
120,000.00 120.00
JUMLAH TENAGA KERJA 7,620.00

9,400.00 95,880.00
20,000.00 1,000.00
JUMLAH HARGA BAHAN 96,880.00

JUMLAH HARGA ALAT


104,500.00
15,675.00
120,175.00
12,017.50
Harga Satuan (Rp) Jumlah Harga (Rp)

90,000.00 46,800.00
100,000.00 26,000.00
110,000.00 2,860.00
120,000.00 3,120.00
JUMLAH TENAGA KERJA 78,780.00

2,225,000.00 89,000.00
20,500.00 6,150.00
8,100.00 810.00
JUMLAH HARGA BAHAN 95,960.00

JUMLAH HARGA ALAT


174,740.00
26,211.00
200,951.00

Harga Satuan (Rp) Jumlah Harga (Rp)

90,000.00 46,800.00
100,000.00 26,000.00
110,000.00 2,860.00
120,000.00 3,120.00
JUMLAH TENAGA KERJA 78,780.00

2,113,100.00 65,506.10
20,500.00 6,150.00
8,300.00 1,037.50
JUMLAH HARGA BAHAN 72,693.60

JUMLAH HARGA ALAT

151,473.60
22,721.04
174,194.64

Harga Satuan (Rp) Jumlah Harga (Rp)

90,000.00 46,800.00
100,000.00 26,000.00
110,000.00 2,860.00
120,000.00 3,120.00
JUMLAH TENAGA KERJA 78,780.00

2,113,100.00 65,506.10
20,500.00 6,150.00
8,300.00 1,037.50
JUMLAH HARGA BAHAN 72,693.60
JUMLAH HARGA BAHAN x 55 % 39,981.48

JUMLAH HARGA ALAT

118,761.48
17,814.22
136,575.70

Harga Satuan (Rp) Jumlah Harga (Rp)

90,000.00 46,800.00
100,000.00 26,000.00
110,000.00 2,860.00
120,000.00 3,120.00
JUMLAH TENAGA KERJA 78,780.00

2,225,000.00 100,125.00
20,500.00 6,150.00
8,100.00 810.00
JUMLAH HARGA BAHAN 107,085.00

JUMLAH HARGA ALAT

185,865.00
27,879.75
213,744.75
Harga Satuan (Rp) Jumlah Harga (Rp)

90,000.00 59,400.00
100,000.00 33,000.00
110,000.00 3,630.00
120,000.00 3,960.00
JUMLAH TENAGA KERJA 99,990.00

2,225,000.00 89,000.00
20,500.00 8,200.00
8,100.00 1,620.00
2,924,400.00 43,866.00
210,000.00 73,500.00
9,500.00 19,000.00
JUMLAH HARGA BAHAN 235,186.00

JUMLAH HARGA ALAT

335,176.00
50,276.40
385,452.40

Harga Satuan (Rp) Jumlah Harga (Rp)

90,000.00 59,400.00
100,000.00 33,000.00
110,000.00 3,630.00
120,000.00 3,960.00
JUMLAH TENAGA KERJA 99,990.00

2,225,000.00 89,000.00
20,500.00 8,200.00
8,100.00 -
2,924,400.00 43,866.00
2,113,100.00 46,488.20
9,500.00 19,000.00
JUMLAH HARGA BAHAN 206,554.20

JUMLAH HARGA ALAT

306,544.20
45,981.63
352,525.83
Harga Satuan (Rp) Jumlah Harga (Rp)

90,000.00 59,400.00
100,000.00 33,000.00
110,000.00 3,630.00
120,000.00 3,960.00
JUMLAH TENAGA KERJA 99,990.00

2,225,000.00 89,000.00
20,500.00 8,200.00
8,100.00 -
2,924,400.00 43,866.00
2,113,100.00 46,488.20
9,500.00 19,000.00
JUMLAH HARGA BAHAN 206,554.20
JUMLAH HARGA BAHAN x 55 % 113,604.81

JUMLAH HARGA ALAT

213,594.81
32,039.22
245,634.03
Harga Satuan (Rp) Jumlah Harga (Rp)

90,000.00 59,400.00
100,000.00 33,000.00
110,000.00 3,630.00
120,000.00 3,960.00
JUMLAH TENAGA KERJA 99,990.00

2,225,000.00 89,000.00
20,500.00 8,200.00
8,100.00 1,620.00
2,924,400.00 52,639.20
210,000.00 73,500.00
9,500.00 19,000.00
JUMLAH HARGA BAHAN 243,959.20

JUMLAH HARGA ALAT

343,949.20
51,592.38
395,541.58

Harga Satuan (Rp) Jumlah Harga (Rp)

90,000.00 59,400.00
100,000.00 33,000.00
110,000.00 3,630.00
120,000.00 3,960.00
JUMLAH TENAGA KERJA 99,990.00

2,225,000.00 89,000.00
20,500.00 8,200.00
8,100.00 -
2,924,400.00 52,639.20
2,113,100.00 46,488.20
9,500.00 19,000.00
JUMLAH HARGA BAHAN 215,327.40

JUMLAH HARGA ALAT

315,317.40
47,297.61
362,615.01
Harga Satuan (Rp) Jumlah Harga (Rp)

90,000.00 59,400.00
100,000.00 33,000.00
110,000.00 3,630.00
120,000.00 3,960.00
JUMLAH TENAGA KERJA 99,990.00

2,225,000.00 89,000.00
20,500.00 8,200.00
8,100.00 -
2,924,400.00 52,639.20
2,113,100.00 46,488.20
9,500.00 19,000.00
JUMLAH HARGA BAHAN 215,327.40
JUMLAH HARGA BAHAN x 55 % 118,430.07

JUMLAH HARGA ALAT

218,420.07
32,763.01
251,183.08
Harga Satuan (Rp) Jumlah Harga (Rp)

90,000.00 59,400.00
100,000.00 33,000.00
110,000.00 3,630.00
120,000.00 3,960.00
JUMLAH TENAGA KERJA 99,990.00

2,225,000.00 89,000.00
20,500.00 8,200.00
8,100.00 1,620.00
2,924,400.00 43,866.00
210,000.00 73,500.00
9,500.00 57,000.00
JUMLAH HARGA BAHAN 273,186.00

JUMLAH HARGA ALAT

373,176.00
55,976.40
429,152.40

Harga Satuan (Rp) Jumlah Harga (Rp)

90,000.00 59,400.00
100,000.00 33,000.00
110,000.00 3,630.00
120,000.00 3,960.00
JUMLAH TENAGA KERJA 99,990.00

2,225,000.00 89,000.00
20,500.00 8,200.00
8,100.00 -
2,924,400.00 43,866.00
2,113,100.00 46,488.20
9,500.00 57,000.00
JUMLAH HARGA BAHAN 244,554.20

JUMLAH HARGA ALAT

344,544.20
51,681.63
396,225.83
Harga Satuan (Rp) Jumlah Harga (Rp)

90,000.00 59,400.00
100,000.00 33,000.00
110,000.00 3,630.00
120,000.00 3,960.00
JUMLAH TENAGA KERJA 99,990.00

2,225,000.00 89,000.00
20,500.00 8,200.00
8,100.00 -
2,924,400.00 43,866.00
2,113,100.00 46,488.20
9,500.00 57,000.00
JUMLAH HARGA BAHAN 244,554.20
JUMLAH HARGA BAHAN x 55 % 134,504.81

JUMLAH HARGA ALAT

234,494.81
35,174.22
269,669.03
Harga Satuan (Rp) Jumlah Harga (Rp)

90,000.00 59,400.00
100,000.00 33,000.00
110,000.00 3,630.00
120,000.00 3,960.00
JUMLAH TENAGA KERJA 99,990.00

2,225,000.00 66,750.00
20,500.00 8,200.00
8,100.00 1,620.00
2,924,400.00 58,488.00
210,000.00 73,500.00
9,500.00 28,500.00
-
JUMLAH HARGA BAHAN 237,058.00

JUMLAH HARGA ALAT

337,048.00
50,557.20
387,605.20

Harga Satuan (Rp) Jumlah Harga (Rp)

90,000.00 59,400.00
100,000.00 33,000.00
110,000.00 3,630.00
120,000.00 3,960.00
JUMLAH TENAGA KERJA 99,990.00

2,225,000.00 66,750.00
20,500.00 8,200.00
8,100.00 -
2,924,400.00 58,488.00
2,113,100.00 46,488.20
9,500.00 28,500.00
-
JUMLAH HARGA BAHAN 208,426.20

JUMLAH HARGA ALAT

308,416.20
46,262.43
354,678.63
Harga Satuan (Rp) Jumlah Harga (Rp)

90,000.00 59,400.00
100,000.00 33,000.00
110,000.00 3,630.00
120,000.00 3,960.00
JUMLAH TENAGA KERJA 99,990.00

2,225,000.00 66,750.00
20,500.00 8,200.00
8,100.00 -
2,924,400.00 58,488.00
2,113,100.00 46,488.20
9,500.00 28,500.00
-
JUMLAH HARGA BAHAN 208,426.20
JUMLAH HARGA BAHAN x 55 % 114,634.41

JUMLAH HARGA ALAT

214,624.41
32,193.66
246,818.07
Harga Satuan (Rp) Jumlah Harga (Rp)

90,000.00 59,400.00
100,000.00 33,000.00
110,000.00 3,630.00
120,000.00 3,960.00
JUMLAH TENAGA KERJA 99,990.00

2,225,000.00 66,750.00
20,500.00 8,200.00
8,100.00 1,215.00
2,924,400.00 43,866.00
210,000.00 73,500.00
9,500.00 19,000.00
JUMLAH HARGA BAHAN 212,531.00

JUMLAH HARGA ALAT

312,521.00
46,878.15
359,399.15

Harga Satuan (Rp) Jumlah Harga (Rp)

90,000.00 13,500.00
100,000.00 5,000.00
110,000.00 550.00
120,000.00 960.00
JUMLAH TENAGA KERJA 20,010.00

2,113,100.00 55,785.84
20,500.00 12,300.00
9,500.00 4,750.00
JUMLAH HARGA BAHAN 72,835.84

JUMLAH HARGA ALAT

92,845.84
13,926.88
106,772.72
Harga Satuan (Rp) Jumlah Harga (Rp)

90,000.00 16,200.00
100,000.00 2,000.00
100,000.00 2,000.00
100,000.00 2,000.00
110,000.00 660.00
120,000.00 1,080.00
JUMLAH TENAGA KERJA 23,940.00

2,113,100.00 4,226.20
20,500.00 205.00
8,100.00 -
10,600.00 31,800.00
20,000.00 9,000.00
1,500.00 6,000.00
100,100.00 600.60
458,100.00 4,122.90
JUMLAH HARGA BAHAN 55,954.70

JUMLAH HARGA ALAT

79,894.70
11,984.21
91,878.91
Harga Satuan (Rp) Jumlah Harga (Rp)

90,000.00 90,000.00
100,000.00 25,000.00
110,000.00 2,750.00
120,000.00 12,000.00
JUMLAH TENAGA KERJA 129,750.00

944,000.00 962,880.00
JUMLAH HARGA BAHAN 962,880.00

2,750,000.00 330,000.00
JUMLAH HARGA ALAT 330,000.00
1,422,630.00
15% x D 213,394.50
1,636,024.50

Harga Satuan (Rp) Jumlah Harga (Rp)

90,000.00 90,000.00
100,000.00 25,000.00
110,000.00 2,750.00
120,000.00 12,000.00
JUMLAH TENAGA KERJA 129,750.00

944,000.00 962,880.00
JUMLAH HARGA BAHAN 962,880.00

JUMLAH HARGA ALAT -

1,092,630.00
15% x D 163,894.50
1,256,524.50

Harga Satuan (Rp) Jumlah Harga (Rp)

90,000.00 90,000.00
100,000.00 25,000.00
110,000.00 2,750.00
120,000.00 12,000.00
JUMLAH TENAGA KERJA 129,750.00
991,300.00 1,011,126.00
JUMLAH HARGA BAHAN 1,011,126.00

2,750,000.00 330,000.00
JUMLAH HARGA ALAT 330,000.00
1,470,876.00
15% x D 220,631.40
1,691,507.40

Harga Satuan (Rp) Jumlah Harga (Rp)

90,000.00 90,000.00
100,000.00 25,000.00
110,000.00 2,750.00
120,000.00 12,000.00
JUMLAH TENAGA KERJA 129,750.00

991,300.00 1,011,126.00
JUMLAH HARGA BAHAN 1,011,126.00

JUMLAH HARGA ALAT -

1,140,876.00
15% x D 171,131.40
1,312,007.40
Harga Satuan (Rp) Jumlah Harga (Rp)

90,000.00 90,000.00
100,000.00 25,000.00
110,000.00 2,750.00
120,000.00 12,000.00
JUMLAH TENAGA KERJA 129,750.00

1,025,000.00 1,045,500.00
JUMLAH HARGA BAHAN 1,045,500.00

2,750,000.00 330,000.00
JUMLAH HARGA ALAT 330,000.00

1,505,250.00
15% x D 225,787.50
1,731,037.50

Harga Satuan (Rp) Jumlah Harga (Rp)

90,000.00 90,000.00
100,000.00 25,000.00
110,000.00 2,750.00
120,000.00 12,000.00
JUMLAH TENAGA KERJA 129,750.00

1,025,000.00 1,045,500.00
JUMLAH HARGA BAHAN 1,045,500.00

JUMLAH HARGA ALAT -


1,175,250.00
15% x D 176,287.50
1,351,537.50

Harga Satuan (Rp) Jumlah Harga (Rp)

90,000.00 90,000.00
100,000.00 25,000.00
110,000.00 2,750.00
120,000.00 12,000.00
JUMLAH TENAGA KERJA 129,750.00
1,059,300.00 1,080,486.00
JUMLAH HARGA BAHAN 1,080,486.00

2,750,000.00 330,000.00
JUMLAH HARGA ALAT 330,000.00
1,540,236.00
15% x D 231,035.40
1,771,271.40

Harga Satuan (Rp) Jumlah Harga (Rp)

90,000.00 90,000.00
100,000.00 25,000.00
110,000.00 2,750.00
120,000.00 12,000.00
JUMLAH TENAGA KERJA 129,750.00

1,059,300.00 1,080,486.00
JUMLAH HARGA BAHAN 1,080,486.00

JUMLAH HARGA ALAT -

1,210,236.00
15% x D 181,535.40
1,391,771.40
Harga Satuan (Rp) Jumlah Harga (Rp)

90,000.00 90,000.00
100,000.00 25,000.00
110,000.00 2,750.00
120,000.00 12,000.00
JUMLAH TENAGA KERJA 129,750.00

1,134,000.00 1,156,680.00
JUMLAH HARGA BAHAN 1,156,680.00

2,750,000.00 330,000.00
JUMLAH HARGA ALAT 330,000.00
1,616,430.00
15% x D 242,464.50
1,858,894.50

Harga Satuan (Rp) Jumlah Harga (Rp)

90,000.00 90,000.00
100,000.00 25,000.00
110,000.00 2,750.00
120,000.00 12,000.00
JUMLAH TENAGA KERJA 129,750.00

1,134,000.00 1,156,680.00
JUMLAH HARGA BAHAN 1,156,680.00

JUMLAH HARGA ALAT -


1,286,430.00
15% x D 192,964.50
1,479,394.50

Harga Satuan (Rp) Jumlah Harga (Rp)

90,000.00 90,000.00
100,000.00 25,000.00
110,000.00 2,750.00
120,000.00 12,000.00
JUMLAH TENAGA KERJA 129,750.00

1,189,300.00 1,213,086.00
JUMLAH HARGA BAHAN 1,213,086.00

2,750,000.00 330,000.00
JUMLAH HARGA ALAT 330,000.00

1,672,836.00
15% x D 250,925.40
1,923,761.40

Harga Satuan (Rp) Jumlah Harga (Rp)

90,000.00 90,000.00
100,000.00 25,000.00
110,000.00 2,750.00
120,000.00 12,000.00
JUMLAH TENAGA KERJA 129,750.00

1,189,300.00 1,213,086.00
JUMLAH HARGA BAHAN 1,213,086.00

JUMLAH HARGA ALAT -


1,342,836.00
15% x D 201,425.40
1,544,261.40
Harga Satuan (Rp) Jumlah Harga (Rp)

90,000.00 90,000.00
100,000.00 25,000.00
110,000.00 2,750.00
120,000.00 12,000.00
JUMLAH TENAGA KERJA 129,750.00

1,225,000.00 1,249,500.00
JUMLAH HARGA BAHAN 1,249,500.00

2,750,000.00 330,000.00
JUMLAH HARGA ALAT 330,000.00
1,709,250.00
15% x D 256,387.50
1,965,637.50

Harga Satuan (Rp) Jumlah Harga (Rp)

90,000.00 90,000.00
100,000.00 25,000.00
110,000.00 2,750.00
120,000.00 12,000.00
JUMLAH TENAGA KERJA 129,750.00

1,225,000.00 1,249,500.00
JUMLAH HARGA BAHAN 1,249,500.00

JUMLAH HARGA ALAT -

1,379,250.00
15% x D 206,887.50
1,586,137.50

Harga Satuan (Rp) Jumlah Harga (Rp)

90,000.00 90,000.00
100,000.00 25,000.00
110,000.00 2,750.00
120,000.00 12,000.00
JUMLAH TENAGA KERJA 129,750.00
1,240,000.00 1,264,800.00
JUMLAH HARGA BAHAN 1,264,800.00

2,750,000.00 330,000.00
JUMLAH HARGA ALAT 330,000.00
1,724,550.00
15% x D 258,682.50
1,983,232.50

Harga Satuan (Rp) Jumlah Harga (Rp)

90,000.00 90,000.00
100,000.00 25,000.00
110,000.00 2,750.00
120,000.00 12,000.00
JUMLAH TENAGA KERJA 129,750.00

1,240,000.00 1,264,800.00
JUMLAH HARGA BAHAN 1,264,800.00

JUMLAH HARGA ALAT -

1,394,550.00
15% x D 209,182.50
1,603,732.50
Harga Satuan (Rp) Jumlah Harga (Rp)

90,000.00 90,000.00
100,000.00 25,000.00
110,000.00 2,750.00
120,000.00 12,000.00
JUMLAH TENAGA KERJA 129,750.00

1,266,700.00 1,292,034.00
JUMLAH HARGA BAHAN 1,292,034.00

2,750,000.00 330,000.00
JUMLAH HARGA ALAT 330,000.00
1,751,784.00
15% x D 262,767.60
2,014,551.60

Harga Satuan (Rp) Jumlah Harga (Rp)

90,000.00 90,000.00
100,000.00 25,000.00
110,000.00 2,750.00
120,000.00 12,000.00
JUMLAH TENAGA KERJA 129,750.00

1,266,700.00 1,292,034.00
JUMLAH HARGA BAHAN 1,292,034.00

JUMLAH HARGA ALAT -

1,421,784.00
15% x D 213,267.60
1,635,051.60

Harga Satuan (Rp) Jumlah Harga (Rp)

90,000.00 90,000.00
100,000.00 25,000.00
110,000.00 2,750.00
120,000.00 12,000.00
JUMLAH TENAGA KERJA 129,750.00
1,306,500.00 1,332,630.00
JUMLAH HARGA BAHAN 1,332,630.00

2,750,000.00 330,000.00
JUMLAH HARGA ALAT 330,000.00
1,792,380.00
15% x D 268,857.00
2,061,237.00

Harga Satuan (Rp) Jumlah Harga (Rp)

90,000.00 90,000.00
100,000.00 25,000.00
110,000.00 2,750.00
120,000.00 12,000.00
JUMLAH TENAGA KERJA 129,750.00

1,306,500.00 1,332,630.00
JUMLAH HARGA BAHAN 1,332,630.00

JUMLAH HARGA ALAT -

1,462,380.00
15% x D 219,357.00
1,681,737.00
Harga Satuan (Rp) Jumlah Harga (Rp)

90,000.00 90,000.00
100,000.00 25,000.00
110,000.00 2,750.00
120,000.00 12,000.00
JUMLAH TENAGA KERJA 129,750.00

1,341,500.00 1,368,330.00
JUMLAH HARGA BAHAN 1,368,330.00

2,750,000.00 330,000.00
JUMLAH HARGA ALAT 330,000.00

1,828,080.00
15% x D 274,212.00
2,102,292.00

Harga Satuan (Rp) Jumlah Harga (Rp)

90,000.00 90,000.00
100,000.00 25,000.00
110,000.00 2,750.00
120,000.00 12,000.00
JUMLAH TENAGA KERJA 129,750.00

1,341,500.00 1,368,330.00
JUMLAH HARGA BAHAN 1,368,330.00

JUMLAH HARGA ALAT -


1,498,080.00
15% x D 224,712.00
1,722,792.00

Harga Satuan (Rp) Jumlah Harga (Rp)

90,000.00 90,000.00
100,000.00 25,000.00
110,000.00 2,750.00
120,000.00 12,000.00
JUMLAH TENAGA KERJA 129,750.00
1,377,500.00 1,405,050.00
JUMLAH HARGA BAHAN 1,405,050.00

2,750,000.00 330,000.00
JUMLAH HARGA ALAT 330,000.00
1,864,800.00
15% x D 279,720.00
2,144,520.00

Harga Satuan (Rp) Jumlah Harga (Rp)

90,000.00 90,000.00
100,000.00 25,000.00
110,000.00 2,750.00
120,000.00 12,000.00
JUMLAH TENAGA KERJA 129,750.00

1,377,500.00 1,405,050.00
JUMLAH HARGA BAHAN 1,405,050.00

JUMLAH HARGA ALAT -

1,534,800.00
15% x D 230,220.00
1,765,020.00
Harga Satuan (Rp) Jumlah Harga (Rp)

90,000.00 90,000.00
100,000.00 25,000.00
110,000.00 2,750.00
120,000.00 12,000.00
JUMLAH TENAGA KERJA 129,750.00

1,406,500.00 1,434,630.00
JUMLAH HARGA BAHAN 1,434,630.00

2,750,000.00 330,000.00
JUMLAH HARGA ALAT 330,000.00

1,894,380.00
15% x D 284,157.00
2,178,537.00

Harga Satuan (Rp) Jumlah Harga (Rp)

90,000.00 90,000.00
100,000.00 25,000.00
110,000.00 2,750.00
120,000.00 12,000.00
JUMLAH TENAGA KERJA 129,750.00

1,406,500.00 1,434,630.00
JUMLAH HARGA BAHAN 1,434,630.00

JUMLAH HARGA ALAT -


1,564,380.00
15% x D 234,657.00
1,799,037.00
4.2.1. HARGA SATUAN PEKERJAAN BESI DAN ALUMUNIUM
4.2.1.1 Pemasangan 1 Kg besi profil

No Uraian Kode Satuan Koefisien Harga Satuan (Rp)


A TENAGA
1 Pekerja L.01 OH 0.060 90,000.00
2 Tukang Las Kontruksi L.03 OH 0.060 100,000.00
3 Kepala Tukang L.03 OH 0.006 110,000.00
4 Mandor L.04 OH 0.003 120,000.00
JUMLAH TENAGA KERJA
B BAHAN
1 Besi profil Kg 1.150 13,500.00
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)

4.2.1.2 Pemasangan 1 Kg rangka kuda-kuda baja IWF

No Uraian Kode Satuan Koefisien Harga Satuan (Rp)


A TENAGA
1 Pekerja L.01 OH 0.060 90,000.00
2 Tukang Las Kontruksi L.03 OH 0.060 100,000.00
3 Kepala Tukang L.03 OH 0.006 110,000.00
4 Mandor L.04 OH 0.003 120,000.00
JUMLAH TENAGA KERJA
B BAHAN
1 Besi baja IWF Kg 1.150 13,500.00
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)

4.2.1.3 Pengerjaan 100 kg pekerjaan perakitan

No Uraian Kode Satuan Koefisien Harga Satuan (Rp)


A TENAGA
1 Pekerja L.01 OH 0.100 90,000.00
2 Tukang Las Kontruksi L.03 OH 0.100 100,000.00
3 Kepala Tukang L.03 OH 0.001 110,000.00
4 Mandor L.04 OH 0.005 120,000.00
JUMLAH TENAGA KERJA
B BAHAN
1 Solar Liter 1.000 8,100.00
2 Minyak pelumas Liter 0.100 28,800.00
JUMLAH HARGA BAHAN
C PERALATAN
1 Sewa alat Jam 0.800 70,000.00
JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)
4.2.1.4 Pembuatan 1 m² pintu besi plat baja tebal 2mm rangkap, rangka baja siku

No Uraian Kode Satuan Koefisien Harga Satuan (Rp)


A TENAGA
1 Pekerja L.01 OH 1.050 90,000.00
2 Tukang Las Biasa L.03 OH 1.050 100,000.00
3 Kepala Tukang L.03 OH 0.105 110,000.00
4 Mandor L.04 OH 0.052 120,000.00
JUMLAH TENAGA KERJA
B BAHAN
1 Besi siku L 30.30.3 Kg 15.000 13,500.00
2 Besi plat baja Kg 32.800 13,500.00
3 Kawat las Kg 0.050 28,500.00
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)

4.2.1.5 Pengerjaan 10 cm pengelasan dengan las listrik

No Uraian Kode Satuan Koefisien Harga Satuan (Rp)


A TENAGA
1 Pekerja L.01 OH 0.040 90,000.00
2 Tukang Las Biasa L.03 OH 0.020 100,000.00
3 Kepala Tukang L.03 OH 0.002 110,000.00
4 Mandor L.04 OH 0.002 120,000.00
JUMLAH TENAGA KERJA
B BAHAN
1 Kawat Las listrik Kg 0.400 28,500.00
2 Solar Liter 0.300 8,100.00
3 Minyak pelumas Liter 0.040 28,800.00
JUMLAH HARGA BAHAN
C PERALATAN
1 Sewa alat Jam 0.170 70,000.00
JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)

4.2.1.14 Pemasangan 1 m² venetions blinds dan vertical blinds

No Uraian Kode Satuan Koefisien Harga Satuan (Rp)


A TENAGA
1 Pekerja L.01 OH 0.350 90,000.00
2 Tukang L.03 OH 0.350 100,000.00
3 Kepala Tukang L.03 OH 0.035 110,000.00
4 Mandor L.04 OH 0.018 120,000.00
JUMLAH TENAGA KERJA
B BAHAN

1 venetions blinds dan vertical blinds m 1.000


(tirai)
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)
4.2.1.15 Pemasangan 1 m² terali besi strip (2x3) mm

No Uraian Kode Satuan Koefisien Harga Satuan (Rp)


A TENAGA
1 Pekerja L.01 OH 1.670 90,000.00
2 Tukang L.03 OH 1.670 100,000.00
3 Kepala Tukang L.03 OH 0.167 110,000.00
4 Mandor L.04 OH 0.083 120,000.00
JUMLAH TENAGA KERJA
B BAHAN
1 Besi strip Kg 6.177 13,500.00
2 Pengelasan cm 27.080 2,104.20
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)

4.2.1.17 Pemasangan 1 m² jendela nako dan tralis

No Uraian Kode Satuan Koefisien Harga Satuan (Rp)


A TENAGA
1 Pekerja L.01 OH 0.200 90,000.00
2 Tukang L.03 OH 0.200 100,000.00
3 Kepala Tukang L.03 OH 0.020 110,000.00
4 Mandor L.04 OH 0.001 120,000.00
JUMLAH TENAGA KERJA
B BAHAN

1 Jendela nako (rangka + kaca 5mm) m² 1.100 250,000.00

2 Paku 1 cm - 2,5 cm buah 10.000 20,500.00


3 Besi strip Kg 7.000 13,500.00
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)

4.2.1.18 Pemasangan 1 m² talang datar/jurai seng bjls 30 lebar 90 cm

No Uraian Kode Satuan Koefisien Harga Satuan (Rp)


A TENAGA
1 Pekerja L.01 OH 0.200 90,000.00
2 Tukang L.03 OH 0.200 100,000.00
3 Kepala Tukang L.03 OH 0.020 110,000.00
4 Mandor L.04 OH 0.001 120,000.00
JUMLAH TENAGA KERJA
B BAHAN
1 Seng plat m² 1.050 66,300.00
2 Paku 1 cm - 2,5 cm Kg 0.015 20,500.00
3 Papan kayu kelas II m³ 0.019 6,250,000.00
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)
4.2.1.19 Pemasangan 1 m² talang talang ½ lingkaran D-15, seng plat bjls 30 lebar 45 cm

No Uraian Kode Satuan Koefisien Harga Satuan (Rp)


A TENAGA
1 Pekerja L.01 OH 0.150 90,000.00
2 Tukang L.03 OH 0.300 100,000.00
3 Kepala Tukang L.03 OH 0.030 110,000.00
4 Mandor L.04 OH 0.008 120,000.00
JUMLAH TENAGA KERJA
B BAHAN
1 Seng plat m² 1.050 20,000.00
2 Paku 1 cm - 2,5 cm Kg 0.010 20,500.00
3 Besi strip Kg 0.500 13,500.00
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)
Jumlah Harga (Rp)

5,400.00
6,000.00
660.00
360.00
12,420.00

15,525.00
15,525.00

27,945.00
4,191.75
32,136.75

Jumlah Harga (Rp)

5,400.00
6,000.00
660.00
360.00
12,420.00

15,525.00
15,525.00

27,945.00
4,191.75
32,136.75

Jumlah Harga (Rp)

9,000.00
10,000.00
110.00
600.00
19,710.00

8,100.00
2,880.00
10,980.00

56,000.00
56,000.00

86,690.00
13,003.50
99,693.50
Jumlah Harga (Rp)

94,500.00
105,000.00
11,550.00
6,240.00
217,290.00

202,500.00
442,800.00
1,425.00
646,725.00

864,015.00
129,602.25
993,617.25

Jumlah Harga (Rp)

3,600.00
2,000.00
220.00
240.00
6,060.00

11,400.00
2,430.00
1,152.00
14,982.00

11,900.00

21,042.00
3,156.30
24,198.30

Jumlah Harga (Rp)

31,500.00
35,000.00
3,850.00
2,160.00
72,510.00
-

72,510.00
10,876.50
83,386.50
Jumlah Harga (Rp)

150,300.00
167,000.00
18,370.00
9,960.00
345,630.00

83,389.50
56,981.74
140,371.24

486,001.24
72,900.19
558,901.42

Jumlah Harga (Rp)

18,000.00
20,000.00
2,200.00
120.00
40,320.00

275,000.00

205,000.00
94,500.00
574,500.00

614,820.00
92,223.00
707,043.00

Jumlah Harga (Rp)

18,000.00
20,000.00
2,200.00
120.00
40,320.00

69,615.00
307.50
118,750.00
188,672.50

228,992.50
34,348.88
263,341.38
Jumlah Harga (Rp)

13,500.00
30,000.00
3,300.00
960.00
47,760.00

21,000.00
205.00
6,750.00
27,955.00

75,715.00
11,357.25
87,072.25
4.4.1. HARGA SATUAN PEKERJAAN PASANGAN DINDING

4.4.1.3 Pemasangan 1 m² dinding bata merah (5x11x22) cm tebal 1 bata campuran 1SP:4PP

No Uraian Kode Satuan Koefisien Harga Satuan (Rp)


A TENAGA
1 Pekerja L.01 OH 0.600 90,000.00
2 Tukang batu L.02 OH 0.200 100,000.00
3 Kepala Tukang L.03 OH 0.020 110,000.00
4 Mandor L.04 OH 0.030 120,000.00
JUMLAH TENAGA KERJA
B BAHAN
1 Bata Merah bh 140.000 1,500.00
2 Semen Portland Kg 26.550 1,500.00
3 Pasir pasang m³ 0.093 100,100.00
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)

4.4.1.9 Pemasangan 1 m² dinding bata merah (5x11x22) cm tebal ½ bata campuran 1SP:4PP

No Uraian Kode Satuan Koefisien Harga Satuan (Rp)


A TENAGA
1 Pekerja L.01 OH 0.300 90,000.00
2 Tukang batu L.02 OH 0.100 100,000.00
3 Kepala Tukang L.03 OH 0.010 110,000.00
4 Mandor L.04 OH 0.015 120,000.00
JUMLAH TENAGA KERJA
B BAHAN
1 Bata Merah bh 70.000 1,500.00
2 Semen Portland Kg 11.500 1,500.00
3 Pasir pasang m³ 0.043 100,100.00
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)

4.4.1.17 Pemasangan 1 m² dinding conblock HB20 1SP:4PP

No Uraian Kode Satuan Koefisien Harga Satuan (Rp)


A TENAGA
1 Pekerja L.01 OH 0.350 90,000.00
2 Tukang batu L.02 OH 0.150 100,000.00
3 Kepala Tukang L.03 OH 0.015 110,000.00
4 Mandor L.04 OH 0.018 120,000.00
JUMLAH TENAGA KERJA
B BAHAN
1 HB-20 m³ 12.500
2 Semen portland Kg 24.260 1,500.00
3 Pasir pasang m³ 0.772 100,100.00
4 Besi angker diameter 8 kg 0.280 10,600.00
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)
4.4.1.17.a Pemasangan 1 m² dinding batako uk. 20/40/9

No Uraian Kode Satuan Koefisien Harga Satuan (Rp)


A TENAGA
1 Pekerja L.01 OH 0.350 90,000.00
2 Tukang batu L.02 OH 0.150 100,000.00
3 Kepala Tukang L.03 OH 0.015 110,000.00
4 Mandor L.04 OH 0.018 120,000.00
JUMLAH TENAGA KERJA
B BAHAN
1 Batako 20/40/9 (cetak mesin) Bh 12.500 2,500.00
2 Semen Portland Kg 7.500 1,500.00
3 Pasir pasang m³ 0.027 100,100.00
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)

4.4.1.17.b Pemasangan 1 m² dinding batako 20/40/7

No Uraian Kode Satuan Koefisien Harga Satuan (Rp)


A TENAGA
1 Pekerja L.01 OH 0.350 90,000.00
2 Tukang batu L.02 OH 0.150 100,000.00
3 Kepala Tukang L.03 OH 0.015 110,000.00
4 Mandor L.04 OH 0.018 120,000.00
JUMLAH TENAGA KERJA
B BAHAN
1 Batako 20/40/7 (cetak mesin) Bh 12.500 2,100.00
2 Semen Portland Kg 7.500 1,500.00
3 Pasir pasang m³ 0.027 100,100.00
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)

4.4.1.19 Pemasangan 1 m² dinding conblock HB15 1SP:4PP

No Uraian Kode Satuan Koefisien Harga Satuan (Rp)


A TENAGA
1 Pekerja L.01 OH 0.320 90,000.00
2 Tukang batu L.02 OH 0.120 100,000.00
3 Kepala Tukang L.03 OH 0.012 110,000.00
4 Mandor L.04 OH 0.016 120,000.00
JUMLAH TENAGA KERJA
B BAHAN
1 HB-15 m³ 12.500
2 Semen portland Kg 18.200 1,500.00
3 Pasir pasang m³ 0.582 100,100.00
4 Besi angker diameter 8 kg 0.280 10,600.00
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)
4.4.1.19.a Pemasangan 1 m² dinding batako 15/30/7

No Uraian Kode Satuan Koefisien Harga Satuan (Rp)


A TENAGA
1 Pekerja L.01 OH 0.320 90,000.00
2 Tukang batu L.02 OH 0.120 100,000.00
3 Kepala Tukang L.03 OH 0.012 110,000.00
4 Mandor L.04 OH 0.016 120,000.00
JUMLAH TENAGA KERJA
B BAHAN
1 Batako 15/30/7 (cetak mesin) Bh 22.000 1,600.00
2 Semen Portland Kg 7.500 1,500.00
3 Pasir pasang m³ 0.027 100,100.00
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)

4.4.1.23 Pemasangan 1 m² dinding terawang (rooster) 12x11x24 campuran 1SP:4PP

No Uraian Kode Satuan Koefisien Harga Satuan (Rp)


A TENAGA
1 Pekerja L.01 OH 0.300 90,000.00
2 Tukang batu L.02 OH 0.100 100,000.00
3 Kepala Tukang L.03 OH 0.010 110,000.00
4 Mandor L.04 OH 0.015 120,000.00
JUMLAH TENAGA KERJA
B BAHAN
1 Bata berongga m³ 30.000 20,000.00
2 Semen portland Kg 11.000 1,520.00
3 Pasir pasang m³ 0.035 89,000.00
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)

4.4.1.23.a Pemasangan 1 m² dinding terawang (rooster) 18x18 campuran 1SP:4PP

No Uraian Kode Satuan Koefisien Harga Satuan (Rp)


A TENAGA
1 Pekerja L.01 OH 0.300 90,000.00
2 Tukang batu L.02 OH 0.100 100,000.00
3 Kepala Tukang L.03 OH 0.010 110,000.00
4 Mandor L.04 OH 0.015 120,000.00
JUMLAH TENAGA KERJA
B BAHAN
1 Rooster 18 x 18 cm Bh 30.000 17,500.00
2 Semen portland Kg 11.000 1,500.00
3 Pasir pasang m³ 0.035 100,100.00
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)
Jumlah Harga (Rp)

54,000.00
20,000.00
2,200.00
3,600.00
79,800.00

210,000.00
39,825.00
9,309.30
259,134.30

338,934.30
50,840.15
389,774.45

Jumlah Harga (Rp)

27,000.00
10,000.00
1,100.00
1,800.00
39,900.00

105,000.00
17,250.00
4,304.30
126,554.30

166,454.30
24,968.15
191,422.45

Jumlah Harga (Rp)

31,500.00
15,000.00
1,650.00
2,160.00
50,310.00
-
36,390.00
77,277.20
2,968.00
116,635.20

166,945.20
25,041.78
191,986.98
Jumlah Harga (Rp)

31,500.00
15,000.00
1,650.00
2,160.00
50,310.00

31,250.00
11,250.00
2,702.70
45,202.70

95,512.70
14,326.91
109,839.61

Jumlah Harga (Rp)

31,500.00
15,000.00
1,650.00
2,160.00
50,310.00

26,250.00
11,250.00
2,702.70
40,202.70

90,512.70
13,576.91
104,089.61

Jumlah Harga (Rp)

28,800.00
12,000.00
1,320.00
1,920.00
44,040.00

-
27,300.00
58,258.20
2,968.00
88,526.20

132,566.20
19,884.93
152,451.13
Jumlah Harga (Rp)

28,800.00
12,000.00
1,320.00
1,920.00
44,040.00

35,200.00
11,250.00
2,702.70
49,152.70

93,192.70
13,978.91
107,171.61

Jumlah Harga (Rp)

27,000.00
10,000.00
1,100.00
1,800.00
39,900.00

600,000.00
16,720.00
3,115.00
619,835.00

659,735.00
98,960.25
758,695.25

Jumlah Harga (Rp)

27,000.00
10,000.00
1,100.00
1,800.00
39,900.00
525,000.00
16,500.00
3,503.50
545,003.50

584,903.50
87,735.53
672,639.03
4.4.2 HARGA SATUAN PEKERJAAN PLESTERAN
4.4.2.1 Pemasangan 1 m² plesteran 1SP:1PP tebal 15mm

No Uraian Kode Satuan Koefisien Harga Satuan (Rp)


A TENAGA
1 Pekerja L.01 OH 0.300 90,000.00
2 Tukang batu L.03 OH 0.150 100,000.00
3 Kepala Tukang L.03 OH 0.015 110,000.00
4 Mandor L.04 OH 0.015 120,000.00
JUMLAH TENAGA KERJA
B BAHAN
1 PC Kg 15.504 1,500.00
2 PP m³ 0.016 100,100.00
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)

4.4.2.2 Pemasangan 1 m² plesteran 1SP:2PP tebal 15mm

No Uraian Kode Satuan Koefisien Harga Satuan (Rp)


A TENAGA
1 Pekerja L.01 OH 0.300 90,000.00
2 Tukang batu L.03 OH 0.150 100,000.00
3 Kepala Tukang L.03 OH 0.015 110,000.00
4 Mandor L.04 OH 0.015 120,000.00
JUMLAH TENAGA KERJA
B BAHAN
1 PC Kg 10.224 1,500.00
2 PP m³ 0.020 100,100.00
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)

4.4.2.3 Pemasangan 1 m² plesteran 1SP:3PP tebal 15mm

No Uraian Kode Satuan Koefisien Harga Satuan (Rp)


A TENAGA
1 Pekerja L.01 OH 0.300 90,000.00
2 Tukang batu L.03 OH 0.150 100,000.00
3 Kepala Tukang L.03 OH 0.015 110,000.00
4 Mandor L.04 OH 0.015 120,000.00
JUMLAH TENAGA KERJA
B BAHAN
1 PC Kg 7.776 1,500.00
2 PP m³ 0.023 100,100.00
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)
4.4.2.4 Pemasangan 1 m² plesteran 1SP:4PP tebal 15mm

No Uraian Kode Satuan Koefisien Harga Satuan (Rp)


A TENAGA
1 Pekerja L.01 OH 0.300 90,000.00
2 Tukang batu L.03 OH 0.150 100,000.00
3 Kepala Tukang L.03 OH 0.015 110,000.00
4 Mandor L.04 OH 0.015 120,000.00
JUMLAH TENAGA KERJA
B BAHAN
1 PC Kg 6.240 1,500.00
2 PP m³ 0.024 100,100.00
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)

4.4.2.13 Pemasangan 1 m² plesteran 1SP: 1PP tebal 20mm

No Uraian Kode Satuan Koefisien Harga Satuan (Rp)


A TENAGA
1 Pekerja L.01 OH 0.400 90,000.00
2 Tukang batu L.03 OH 0.200 100,000.00
3 Kepala Tukang L.03 OH 0.020 110,000.00
4 Mandor L.04 OH 0.022 120,000.00
JUMLAH TENAGA KERJA
B BAHAN
1 PC Kg 13.632 1,500.00
2 PP m³ 0.027 100,100.00
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)

4.4.2.14 Pemasangan 1 m² plesteran 1SP: 3PP tebal 20mm

No Uraian Kode Satuan Koefisien Harga Satuan (Rp)


A TENAGA
1 Pekerja L.01 OH 0.260 90,000.00
2 Tukang batu L.03 OH 0.200 100,000.00
3 Kepala Tukang L.03 OH 0.020 110,000.00
4 Mandor L.04 OH 0.013 120,000.00
JUMLAH TENAGA KERJA
B BAHAN
1 PC Kg 10.368 1,500.00
2 PP m³ 0.031 100,100.00
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)

4.4.2.15 Pemasangan 1 m² plesteran 1SP: 4PP tebal 20mm

No Uraian Kode Satuan Koefisien Harga Satuan (Rp)


A TENAGA
1 Pekerja L.01 OH 0.400 90,000.00
2 Tukang batu L.03 OH 0.200 100,000.00
3 Kepala Tukang L.03 OH 0.020 110,000.00
4 Mandor L.04 OH 0.022 120,000.00
JUMLAH TENAGA KERJA
B BAHAN
1 PC Kg 8.320 1,500.00
2 PP m³ 0.032 100,100.00
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)

4.4.2.20 Pemasangan 1 m² plesteran 1SP : 3PP lebar 10mm

No Uraian Kode Satuan Koefisien Harga Satuan (Rp)


A TENAGA
1 Pekerja L.01 OH 0.080 90,000.00
2 Tukang batu L.03 OH 0.400 100,000.00
3 Kepala Tukang L.03 OH 0.040 110,000.00
4 Mandor L.04 OH 0.004 120,000.00
JUMLAH TENAGA KERJA
B BAHAN
1 Semen PC Kg 0.500 1,500.00
2 Pasir pasang m³ 0.013 100,100.00
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)

4.4.2.23 Pemasangan 1 m² plesteran ciprat 1SP : 2PP

No Uraian Kode Satuan Koefisien Harga Satuan (Rp)


A TENAGA
1 Pekerja L.01 OH 0.300 90,000.00
2 Tukang batu L.03 OH 0.100 100,000.00
3 Kepala Tukang L.03 OH 0.010 110,000.00
4 Mandor L.04 OH 0.015 120,000.00
JUMLAH TENAGA KERJA
B BAHAN
1 Semen PC Kg 4.320 1,500.00
2 Pasir Pasang m³ 0.006 100,100.00
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)

4.4.2.24 Pemasangan 1 m² finishing siar pasangan bata merah

No Uraian Kode Satuan Koefisien Harga Satuan (Rp)


A TENAGA
1 Pekerja L.01 OH 0.150 90,000.00
2 Tukang batu L.03 OH 0.075 100,000.00
3 Kepala Tukang L.03 OH 0.008 110,000.00
4 Mandor L.04 OH 0.008 120,000.00
JUMLAH TENAGA KERJA
B BAHAN
1 Semen PC Kg 3.108 1,500.00
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)

4.4.2.25 Pemasangan 1 m² finishing siar pasangan conblock ekspose

No Uraian Kode Satuan Koefisien Harga Satuan (Rp)


A TENAGA
1 Pekerja L.01 OH 0.070 90,000.00
2 Tukang batu L.03 OH 0.035 100,000.00
3 Kepala Tukang L.03 OH 0.004 110,000.00
4 Mandor L.04 OH 0.004 120,000.00
JUMLAH TENAGA KERJA
B BAHAN
1 Semen PC Kg 1.600 1,500.00
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)

4.4.2.26 Pemasangan 1 m² finishing siar pasangan batu kali, campuran 1SP:2PP

No Uraian Kode Satuan Koefisien Harga Satuan (Rp)


A TENAGA
1 Pekerja L.01 OH 0.300 90,000.00
2 Tukang batu L.03 OH 0.150 100,000.00
3 Kepala Tukang L.03 OH 0.015 110,000.00
4 Mandor L.04 OH 0.015 120,000.00
JUMLAH TENAGA KERJA
B BAHAN
1 Semen PC Kg 6.340 1,500.00
2 Pasir pasang m³ 0.012 100,100.00
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)

4.4.2.27 Pemasangan 1 m² acian


No Uraian Kode Satuan Koefisien Harga Satuan (Rp)
A TENAGA
1 Pekerja L.01 OH 0.200 90,000.00
2 Tukang batu L.03 OH 0.100 100,000.00
3 Kepala Tukang L.03 OH 0.010 110,000.00
4 Mandor L.04 OH 0.010 120,000.00
JUMLAH TENAGA KERJA
B BAHAN
1 Semen PC Kg 3.250 1,500.00
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)
Jumlah Harga (Rp)

27,000.00
15,000.00
1,650.00
1,800.00
45,450.00

23,256.00
1,601.60
24,857.60

70,307.60
10,546.14
80,853.74

Jumlah Harga (Rp)

27,000.00
15,000.00
1,650.00
1,800.00
45,450.00

15,336.00
2,002.00
17,338.00

62,788.00
9,418.20
72,206.20

Jumlah Harga (Rp)

27,000.00
15,000.00
1,650.00
1,800.00
45,450.00

11,664.00
2,302.30
13,966.30

59,416.30
8,912.45
68,328.75
Jumlah Harga (Rp)

27,000.00
15,000.00
1,650.00
1,800.00
45,450.00

9,360.00
2,402.40
11,762.40

57,212.40
8,581.86
65,794.26

Jumlah Harga (Rp)

36,000.00
20,000.00
2,200.00
2,640.00
60,840.00

20,448.00
2,702.70
23,150.70

83,990.70
12,598.61
96,589.31

Jumlah Harga (Rp)

23,400.00
20,000.00
2,200.00
1,560.00
47,160.00

15,552.00
3,103.10
18,655.10

65,815.10
9,872.27
75,687.37

Jumlah Harga (Rp)

36,000.00
20,000.00
2,200.00
2,640.00
60,840.00

12,480.00
3,203.20
15,683.20

76,523.20
11,478.48
88,001.68

Jumlah Harga (Rp)

7,200.00
40,000.00
4,400.00
480.00
52,080.00

750.00
1,301.30
2,051.30

54,131.30
8,119.70
62,251.00

Jumlah Harga (Rp)

27,000.00
10,000.00
1,100.00
1,800.00
39,900.00

6,480.00
600.60
7,080.60

46,980.60
7,047.09
54,027.69

Jumlah Harga (Rp)

13,500.00
7,500.00
880.00
960.00
22,840.00

4,662.00
4,662.00

27,502.00
4,125.30
31,627.30

Jumlah Harga (Rp)

6,300.00
3,500.00
440.00
480.00
10,720.00

2,400.00
2,400.00

13,120.00
1,968.00
15,088.00

Jumlah Harga (Rp)

27,000.00
15,000.00
1,650.00
1,800.00
45,450.00

9,510.00
1,201.20
10,711.20

56,161.20
8,424.18
64,585.38
Jumlah Harga (Rp)

18,000.00
10,000.00
1,100.00
1,200.00
30,300.00

4,875.00
4,875.00

35,175.00
5,276.25
40,451.25
4.4.3 HARGA SATUAN PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING

4.4.3.34.a Pemasangan 1 m² lantai keramik 40 cm x 40 cm polished (setaraf indogres)

No Uraian Kode Satuan Koefisien Harga Satuan (Rp)


A TENAGA
1 Pekerja L.01 OH 0.700 90,000.00
2 Tukang batu L.02 OH 0.350 100,000.00
3 Kepala Tukang L.03 OH 0.035 110,000.00
4 Mandor L.04 OH 0.035 120,000.00
JUMLAH TENAGA KERJA
B BAHAN
1 keramik 40 X 40 cm Bh 6.250 25,733.33
2 Semen Portlan Kg 8.190 1,500.00
3 Pasir pasang m³ 0.045 100,100.00
4 Semen warna Kg 0.150 13,100.00
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)

4.4.3.34.b Pemasangan 1 m² lantai keramik 40 cm x 40 cm unpolished (setaraf indogres)

No Uraian Kode Satuan Koefisien Harga Satuan (Rp)


A TENAGA
1 Pekerja L.01 OH 0.700 90,000.00
2 Tukang batu L.02 OH 0.350 100,000.00
3 Kepala Tukang L.03 OH 0.035 110,000.00
4 Mandor L.04 OH 0.035 120,000.00
JUMLAH TENAGA KERJA
B BAHAN
1 keramik 40 X 40 cm Bh 6.250 25,833.33
2 Semen Portlan Kg 8.190 1,500.00
3 Pasir pasang m³ 0.045 100,100.00
4 Semen warna Kg 0.150 13,100.00
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)

4.4.3.35 Pemasangan 1 m² lantai keramik 30 cm x 30 cm

No Uraian Kode Satuan Koefisien Harga Satuan (Rp)


A TENAGA
1 Pekerja L.01 OH 0.700 90,000.00
2 Tukang batu L.02 OH 0.350 100,000.00
3 Kepala Tukang L.03 OH 0.035 110,000.00
4 Mandor L.04 OH 0.035 120,000.00
JUMLAH TENAGA KERJA
B BAHAN
1 Keramik 30 x 30 cm ex roman Bh 11.870 8,181.82
2 Semen Portlan Kg 10.000 1,500.00
3 Pasir pasang m³ 0.045 100,100.00
4 Semen warna Kg 1.500 13,100.00
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)
4.4.3.35.a Pemasangan 1 m² lantai keramik 30 cm x 30 cm polished

No Uraian Kode Satuan Koefisien Harga Satuan (Rp)


A TENAGA
1 Pekerja L.01 OH 0.700 90,000.00
2 Tukang batu L.02 OH 0.350 100,000.00
3 Kepala Tukang L.03 OH 0.035 110,000.00
4 Mandor L.04 OH 0.035 120,000.00
JUMLAH TENAGA KERJA
B BAHAN
1 Keramik 30 x 30 cm polish Bh 11.870 8,181.82
2 Semen Portlan Kg 10.000 1,500.00
3 Pasir pasang m³ 0.045 100,100.00
4 Semen warna Kg 0.150 13,100.00
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)

4.4.3.35.b Pemasangan 1 m² lantai keramik 30 cm x 30 cm unpolished

No Uraian Kode Satuan Koefisien Harga Satuan (Rp)


A TENAGA
1 Pekerja L.01 OH 0.700 90,000.00
2 Tukang batu L.02 OH 0.350 100,000.00
3 Kepala Tukang L.03 OH 0.035 110,000.00
4 Mandor L.04 OH 0.035 120,000.00
JUMLAH TENAGA KERJA
B BAHAN
1 Keramik 30 x 30 cm Bh 11.870 8,181.82
2 Semen Portlan Kg 10.000 1,500.00
3 Pasir pasang m³ 0.045 100,100.00
4 Semen warna Kg 0.150 13,100.00
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)

4.4.3.35.c Pemasangan 1 m² lantai keramik artistik 30 cm x 30 cm

No Uraian Kode Satuan Koefisien Harga Satuan (Rp)


A TENAGA
1 Pekerja L.01 OH 0.700 90,000.00
2 Tukang batu L.02 OH 0.350 100,000.00
3 Kepala Tukang L.03 OH 0.035 110,000.00
4 Mandor L.04 OH 0.035 120,000.00
JUMLAH TENAGA KERJA
B BAHAN
1 Keramik 30 x 30 cm Bh 11.870 8,181.82
2 Semen Portlan Kg 10.000 1,500.00
3 Pasir pasang m³ 0.045 100,100.00
4 Semen warna Kg 0.150 13,100.00
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C)
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E)
Jumlah Harga (Rp)

63,000.00
35,000.00
3,850.00
4,200.00
106,050.00

160,833.33
12,285.00
4,504.50
1,965.00
179,587.83

285,637.83
42,845.68
328,483.51

Jumlah Harga (Rp)

63,000.00
35,000.00
3,850.00
4,200.00
106,050.00

161,458.33
12,285.00
4,504.50
1,965.00
180,212.83

286,262.83
42,939.43
329,202.26

Jumlah Harga (Rp)

63,000.00
35,000.00
3,850.00
4,200.00
106,050.00

97,118.18
15,000.00
4,504.50
19,650.00
136,272.68

242,322.68
36,348.40
278,671.08
Jumlah Harga (Rp)

63,000.00
35,000.00
3,850.00
4,200.00
106,050.00

97,118.18
15,000.00
4,504.50
1,965.00
118,587.68

224,637.68
33,695.65
258,333.33

Jumlah Harga (Rp)

63,000.00
35,000.00
3,850.00
4,200.00
106,050.00

97,118.18
15,000.00
4,504.50
1,965.00
118,587.68

224,637.68
33,695.65
258,333.33

Jumlah Harga (Rp)

63,000.00
35,000.00
3,850.00
4,200.00
106,050.00
97,118.18
15,000.00
4,504.50
1,965.00
118,587.68

224,637.68
33,695.65
258,333.33
SATUAN PEKERJAAN LANGIT-LANGIT (PLAFOND)

A.4.5.1.5. Pemasangan 1 m² langit-langit tripleks ukuran (120 x 240) cm, tebal 3mm

No. URAIAN PEKERJAAN KODE SATUAN

1 2 3
A TENAGA
1 Pekerja L.01 OH
2 Tukang kayu L,02 OH
3 Kepala Tukang L,03 OH
4 Mandor L,04 OH
Jumlah
B BAHAN
1 Tripleks (3 mm) Lembar
2 Paku Tripleks Kg
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

A.4.5.1.5.a Pemasangan 1 m² langit-langit tripleks ukuran (120 x 240) cm, tebal 6 mm

No. URAIAN PEKERJAAN KODE SATUAN

1 2 3
A TENAGA
1 Pekerja L.01 OH
2 Tukang kayu L,02 OH
3 Kepala Tukang L,03 OH
4 Mandor L,04 OH
Jumlah
B BAHAN
1 Tripleks (6 mm) Lembar
2 Paku Tripleks Kg
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

A.4.5.1.6. Pemasangan 1 m² langit-langit lambrisering kayu, tebal 9mm

No. URAIAN PEKERJAAN KODE SATUAN

1 2 3
A TENAGA

Pekerjaan Langit-Langit 198


1 Pekerja L.01 OH
2 Tukang kayu L,02 OH
3 Kepala Tukang L,03 OH
4 Mandor L,04 OH
Jumlah
B BAHAN
1 Kayu papan (Kelas I Ketam) m³
2 Paku Tripleks Kg
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

Pekerjaan Langit-Langit 199


A.4.5.1.7. Pemasangan 1 m2 langit-langit gypsum board ukuran (120x240x9) mm, tebal 9 mm

No. URAIAN PEKERJAAN KODE SATUAN

1 2 3
A TENAGA
1 Pekerja L.01 OH
2 Tukang kayu L,02 OH
3 Kepala Tukang L,03 OH
4 Mandor L,04 OH
Jumlah
B BAHAN
1 Gypsum board Lembar
2 Paku Skrup Kg
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

A.4.5.1.7.a Pemasangan 1 m2 langit-langit GRC (120x240x4) mm, tebal 4 mm

No. URAIAN PEKERJAAN KODE SATUAN

1 2 3
A TENAGA
1 Pekerja L.01 OH
2 Tukang kayu L,02 OH
3 Kepala Tukang L,03 OH
4 Mandor L,04 OH
Jumlah
B BAHAN
1 GRC Board (120 x 240 x 4) Lembar
2 Paku GRC Kg
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

A.4.5.1.9. Pemasangan 1 m’ list langit-langit kayu profil

No. URAIAN PEKERJAAN KODE SATUAN

1 2 3
A TENAGA
1 Pekerja L.01 OH
2 Tukang kayu L,02 OH
3 Kepala Tukang L,03 OH

Pekerjaan Langit-Langit 200


4 Mandor L,04 OH
Jumlah
B BAHAN
1 List kayu profil m
2 Paku (1"-5") Kg
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

Pekerjaan Langit-Langit 201


IT-LANGIT (PLAFOND)

40) cm, tebal 3mm


HARGA BIAYA
KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

0.10 90,000.00 9,000.00


0.10 100,000.00 10,000.00
0.01 110,000.00 1,100.00
0.005 120,000.00 600.00
20,700.00

0.375 70,000.000 26,250.00


0.03 18,100.000 543.00
26,793.00
47,493.00
7,123.95
54,616.95

40) cm, tebal 6 mm


HARGA BIAYA
KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

0.10 90,000.00 9,000.00


0.10 100,000.00 10,000.00
0.01 110,000.00 1,100.00
0.005 120,000.00 600.00
20,700.00

0.375 120,000.000 45,000.00


0.03 18,100.000 543.00
45,543.00
66,243.00
9,936.45
76,179.45

HARGA BIAYA
KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

Pekerjaan Langit-Langit 202


0.80 90,000.00 72,000.00
0.80 100,000.00 80,000.00
0.08 110,000.00 8,800.00
0.04 120,000.00 4,800.00
165,600.00

0.015 11,188,300.000 167,824.50


0.01 18,100.000 181.00
168,005.50
333,605.50
50,040.83
383,646.33

Pekerjaan Langit-Langit 203


120x240x9) mm, tebal 9 mm
HARGA BIAYA
KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

0.10 90,000.00 9,000.00


0.05 100,000.00 5,000.00
0.005 110,000.00 550.00
0.005 120,000.00 600.00
15,150.00

0.364 74,600.000 27,154.40


0.11 48,300.000 5,313.00
32,467.40
47,617.40
7,142.61
54,760.01

ebal 4 mm
HARGA BIAYA
KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

0.10 90,000.00 9,000.00


0.05 100,000.00 5,000.00
0.005 110,000.00 550.00
0.005 120,000.00 600.00
15,150.00

0.364 79,700.000 29,010.80


0.11 21,300.000 2,343.00
31,353.80
46,503.80
6,975.57
53,479.37

HARGA BIAYA
KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

0.05 90,000.00 4,500.00


0.05 100,000.00 5,000.00
0.005 110,000.00 550.00

Pekerjaan Langit-Langit 204


0.003 120,000.00 360.00
10,410.00

1.05 30,700.000 32,235.00


0.01 20,500.000 205.00
32,440.00
42,850.00
6,427.50
49,277.50

Pekerjaan Langit-Langit 205


SATUAN PEKERJAAN PENUTUP ATAP

A.4.5.2.32. Pemasangan 1 m2 genteng metal (ex prima) 0.30

No. URAIAN PEKERJAAN KODE SATUAN

1 2 3
A TENAGA
1 Pekerja L.01 OH
2 Tukang kayu L.03 OH
3 Kepala Tukang L.11 OH
4 Mandor L.15 OH
Jumlah
B BAHAN
1 Genteng metal ex prima 0.30 Bh
2 Paku biasa ½"-1" Kg
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)
catatan : harga bahan genteng metal ex prima dikali 1,84 lembar

A.4.5.2.32.a Pemasangan 1 m2 genteng metal (ex royal) 0.30

No. URAIAN PEKERJAAN KODE SATUAN

1 2 3
A TENAGA
1 Pekerja L.01 OH
2 Tukang kayu L.03 OH
3 Kepala Tukang L.11 OH
4 Mandor L.15 OH
Jumlah
B BAHAN
1 Genteng metal ex royal 0.30 Bh
2 Paku biasa ½"-1" Kg
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)
catatan : harga bahan genteng metal ex royal dikali 1,71 lembar

A.4.5.2.32.b Pemasangan 1 m2 genteng metal (ex royal) 0.25

No. URAIAN PEKERJAAN SATUAN

Penutup Atap 206


No. URAIAN PEKERJAAN KODE SATUAN

1 2 3
A TENAGA
1 Pekerja L.01 OH
2 Tukang kayu L.03 OH
3 Kepala Tukang L.11 OH
4 Mandor L.15 OH
Jumlah
B BAHAN
1 Genteng metal ex royal 0.25 Bh
2 Paku biasa ½"-1" Kg
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)
catatan : harga bahan genteng metal ex royal dikali 1,71 lembar

Penutup Atap 207


A.4.5.2.32.c Pemasangan 1 m2 genteng metal (ex clasic) 0.30

No. URAIAN PEKERJAAN KODE SATUAN

1 2 3
A TENAGA
1 Pekerja L.01 OH
2 Tukang kayu L.03 OH
3 Kepala Tukang L.11 OH
4 Mandor L.15 OH
Jumlah
B BAHAN
1 Genteng metal ex clasic 0.30 Bh
2 Paku biasa ½"-1" Kg
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)
catatan : harga bahan genteng metal ex classic dikali 1,62 lembar

A.4.5.2.32.d Pemasangan 1 m2 genteng metal (ex clasic) 0.25

No. URAIAN PEKERJAAN KODE SATUAN

1 2 3
A TENAGA
1 Pekerja L.01 OH
2 Tukang kayu L.03 OH
3 Kepala Tukang L.11 OH
4 Mandor L.15 OH
Jumlah
B BAHAN
1 Genteng metal ex clasic 0.25 Bh
2 Paku biasa ½"-1" Kg
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)
catatan : harga bahan genteng metal ex classic dikali 1,62 lembar

A.4.5.2.32.e Pemasangan 1 m2 genteng metal stone (ex prima) 0.35

No. URAIAN PEKERJAAN KODE SATUAN

1 2 3
A TENAGA

Penutup Atap 208


1 Pekerja L.01 OH
2 Tukang kayu L.03 OH
3 Kepala Tukang L.11 OH
4 Mandor L.15 OH
Jumlah
B BAHAN
1 Genteng metal stone ex prima 0.35 Bh
2 Paku biasa ½"-1" Kg
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)
catatan : harga bahan genteng metal stone ex prima dikali 1,84 lembar

Penutup Atap 209


A.4.5.2.32.f Pemasangan 1 m2 genteng metal stone (ex classic) 0.35

No. URAIAN PEKERJAAN KODE SATUAN

1 2 3
A TENAGA
1 Pekerja L.01 OH
2 Tukang kayu L.03 OH
3 Kepala Tukang L.11 OH
4 Mandor L.15 OH
Jumlah
B BAHAN
1 Genteng metal stone ex classic 0.35 Bh
2 Paku biasa ½"-1" Kg
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)
catatan : harga bahan genteng metal stone ex classic dikali 1,62 lembar

A.4.5.2.33. Pemasangan 1 m2 atap sirap kayu

No. URAIAN PEKERJAAN KODE SATUAN

1 2 3
A TENAGA
1 Pekerja L.01 OH
2 Tukang kayu L.03 OH
3 Kepala Tukang L.11 OH
4 Mandor L.15 OH
Jumlah
B BAHAN
1 Sirap kayu (Belian) Bh
2 Paku biasa ½"-1" Kg
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

A.4.5.2.33.a Pemasangan 1 m2 atap sirap kayu 6 x 40 x 0,3 cm

No. URAIAN PEKERJAAN KODE SATUAN

1 2 3
A TENAGA
1 Pekerja L.01 OH
2 Tukang kayu L.03 OH
3 Kepala Tukang L.11 OH

Penutup Atap 210


4 Mandor L.15 OH
Jumlah
B BAHAN
1 Sirap kayu (Belian) 6x40x0,3 cm Bh
2 Paku biasa ½"-1" Kg
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

Penutup Atap 211


A.4.5.2.36. Pemasangan 1 m’ nok genteng metal kotak 0.35

No. URAIAN PEKERJAAN KODE SATUAN

1 2 3
A TENAGA
1 Pekerja L.01 OH
2 Tukang kayu L.03 OH
3 Kepala Tukang L.11 OH
4 Mandor L.15 OH
Jumlah
B BAHAN
1 Nok genteng metal kotak 0.35 Bh
2 Paku biasa ½"-1" Kg
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

A.4.5.2.36.a Pemasangan 1 m’ nok genteng metal stone kotak 0.35

No. URAIAN PEKERJAAN KODE SATUAN

1 2 3
A TENAGA
1 Pekerja L.01 OH
2 Tukang kayu L.03 OH
3 Kepala Tukang L.11 OH
4 Mandor L.15 OH
Jumlah
B BAHAN
1 Nok genteng metal stone kotak 0.35 Bh
2 Paku biasa ½"-1" Kg
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

A.4.5.2.36.b Pemasangan 1 m’ nok genteng metal 1/2 lingkaran 0.35 pjg. 40 cm

No. URAIAN PEKERJAAN KODE SATUAN

1 2 3
A TENAGA
1 Pekerja L.01 OH
2 Tukang kayu L.03 OH
3 Kepala Tukang L.11 OH

Penutup Atap 212


4 Mandor L.15 OH
Jumlah
B BAHAN
1 Nok genteng metal 1/2 lingkaran 0.35 pjg 40 cm Bh
2 Paku biasa ½"-1" Kg
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)
Catatan : Harga satuan nok genteng metal 1/2 lingkaran dikali 3

Penutup Atap 213


PENUTUP ATAP

HARGA BIAYA
KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

0.20 90,000.00 18,000.00


0.10 100,000.00 10,000.00
0.01 110,000.00 1,100.00
0.001 120,000.00 120.00
29,220.00

1.02 66,600.000 67,932.00


0.20 20,500.000 4,100.00
72,032.00
101,252.00
15,187.80
116,439.80

HARGA BIAYA
KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

0.20 90,000.00 18,000.00


0.10 100,000.00 10,000.00
0.01 110,000.00 1,100.00
0.001 120,000.00 120.00
29,220.00

1.02 66,600.000 67,932.00


0.20 20,500.000 4,100.00
72,032.00
101,252.00
15,187.80
116,439.80

HARGA BIAYA
KOEFISIEN

Penutup Atap 214


KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

0.20 90,000.00 18,000.00


0.10 100,000.00 10,000.00
0.01 110,000.00 1,100.00
0.001 120,000.00 120.00
29,220.00

1.02 51,800.000 52,836.00


0.20 20,500.000 4,100.00
56,936.00
86,156.00
12,923.40
99,079.40

Penutup Atap 215


HARGA BIAYA
KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

0.20 90,000.00 18,000.00


0.10 100,000.00 10,000.00
0.01 110,000.00 1,100.00
0.001 120,000.00 120.00
29,220.00

1.02 66,600.000 67,932.00


0.20 20,500.000 4,100.00
72,032.00
101,252.00
15,187.80
116,439.80

HARGA BIAYA
KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

0.20 90,000.00 18,000.00


0.10 100,000.00 10,000.00
0.01 110,000.00 1,100.00
0.001 120,000.00 120.00
29,220.00

1.02 51,800.000 52,836.00


0.20 20,500.000 4,100.00
56,936.00
86,156.00
12,923.40
99,079.40

HARGA BIAYA
KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

Penutup Atap 216


0.20 90,000.00 18,000.00
0.10 100,000.00 10,000.00
0.01 110,000.00 1,100.00
0.001 120,000.00 120.00
29,220.00

1.02 80,000.000 81,600.00


0.20 20,500.000 4,100.00
85,700.00
114,920.00
17,238.00
132,158.00

Penutup Atap 217


5
HARGA BIAYA
KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

0.20 90,000.00 18,000.00


0.10 100,000.00 10,000.00
0.01 110,000.00 1,100.00
0.001 120,000.00 120.00
29,220.00

1.02 80,000.000 81,600.00


0.20 20,500.000 4,100.00
85,700.00
114,920.00
17,238.00
132,158.00

HARGA BIAYA
KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

0.166 90,000.00 14,940.00


0.25 100,000.00 25,000.00
0.025 110,000.00 2,750.00
0.008 120,000.00 960.00
43,650.00

30.00 5,300.000 159,000.00


0.20 20,500.000 4,100.00
163,100.00
206,750.00
31,012.50
237,762.50

HARGA BIAYA
KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

0.166 90,000.00 14,940.00


0.25 100,000.00 25,000.00
0.025 110,000.00 2,750.00

Penutup Atap 218


0.008 120,000.00 960.00
43,650.00

60.00 5,300.000 318,000.00


0.20 20,500.000 4,100.00
322,100.00
365,750.00
54,862.50
420,612.50

Penutup Atap 219


HARGA BIAYA
KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

0.25 90,000.00 22,500.00


0.15 100,000.00 15,000.00
0.015 110,000.00 1,650.00
0.013 120,000.00 1,560.00
40,710.00

1.10 50,000.000 55,000.00


0.05 20,500.000 1,025.00
56,025.00
96,735.00
14,510.25
111,245.25

HARGA BIAYA
KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

0.25 90,000.00 22,500.00


0.15 100,000.00 15,000.00
0.015 110,000.00 1,650.00
0.013 120,000.00 1,560.00
40,710.00

1.10 96,900.000 106,590.00


0.05 20,500.000 1,025.00
107,615.00
148,325.00
22,248.75
170,573.75

pjg. 40 cm
HARGA BIAYA
KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

0.25 90,000.00 22,500.00


0.15 100,000.00 15,000.00
0.015 110,000.00 1,650.00

Penutup Atap 220


0.013 120,000.00 1,560.00
40,710.00

1.10 46,000.000 50,600.00


0.05 20,500.000 1,025.00
51,625.00
92,335.00
13,850.25
106,185.25

Penutup Atap 221


SATUAN PEKERJAAN KAYU

A.4.6.1.1. Pembuatan dan pemasangan 1 m3 kusen pintu dan kusen jendela, kayu kelas

No. URAIAN PEKERJAAN KODE SATUAN

1 2 3
A TENAGA
1 Pekerja L.01 OH
2 Tukang kayu L.03 OH
3 Kepala Tukang L.11 OH
4 Mandor L.15 OH
Jumlah
B BAHAN
1 Balok Kayu (Bengkirai 5/10 Ketam untuk kusen) m3
2 Paku 10 cm Kg
3 Lem kayu Kg
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

A.4.6.1.1.a Pembuatan dan pemasangan 1 m3 kusen pintu dan kusen jendela, kayu belia

No. URAIAN PEKERJAAN KODE SATUAN

1 2 3
A TENAGA
1 Pekerja L.01 OH
2 Tukang kayu L.03 OH
3 Kepala Tukang L.11 OH
4 Mandor L.15 OH
Jumlah
B BAHAN
1 Kayu belian Ketam m3
2 Paku 10 cm Kg
3 Lem kayu Kg
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

A.4.6.1.2.b Pembuatan dan pemasangan 1 m3 kusen pintu dan kusen jendela, kayu kelas

No. URAIAN PEKERJAAN KODE SATUAN

1 2 3
A TENAGA
1 Pekerja L.01 OH
Pekerjaan Kayu 222
2 Tukang kayu L.03 OH
3 Kepala Tukang L.03 OH
4 Mandor L.04 OH
Jumlah
B BAHAN
1 Balok Kayu (Ky. klas II Mabang uk. 5/10 ( tdk ketam ) m3
2 Paku 10 cm Kg
3 Lem kayu Kg
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

Pekerjaan Kayu 223


A.4.6.1.3. Pembuatan dan pemasangan 1 m2 pintu klamp standar, kayu kelas II

No. URAIAN PEKERJAAN KODE SATUAN

1 2 3
A TENAGA
1 Pekerja L.01 OH
2 Tukang kayu L.03 OH
3 Kepala Tukang L.03 OH
4 Mandor L.04 OH
Jumlah
B BAHAN
1 Papan kayu (Papan kayu klas II (mabang) tdk ketam m3
2 Paku 5-7 cm Kg
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

A.4.6.1.4. Pembuatan dan pemasangan 1 m2 pintu klamp sederhana, kayu kelas III

No. URAIAN PEKERJAAN KODE SATUAN

1 2 3
A TENAGA
1 Pekerja L.01 OH
2 Tukang kayu L.03 OH
3 Kepala Tukang L.03 OH
4 Mandor L.04 OH
Jumlah
B BAHAN
1 Papan kayu klas III m3
2 Paku 5-7 cm Kg
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

A.4.6.1.5. Pembuatan dan pemasangan 1 m2 daun pintu panel, kayu kelas I

No. URAIAN PEKERJAAN KODE SATUAN

1 2 3
A TENAGA
1 Pekerja L.01 OH
2 Tukang kayu L.03 OH
3 Kepala Tukang L.03 OH
4 Mandor L.04 OH
Jumlah

Pekerjaan Kayu 224


B BAHAN
1 Papan kayu (Papan kayu klas I (ketam) m3
2 Lem kayu Kg
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

A.4.6.1.5.a Pembuatan dan pemasangan 1 m2 daun pintu panel, kayu belian

No. URAIAN PEKERJAAN KODE SATUAN

1 2 3
A TENAGA
1 Pekerja L.01 OH
2 Tukang kayu L.03 OH
3 Kepala Tukang L.03 OH
4 Mandor L.04 OH
Jumlah
B BAHAN
1 Papan kayu (Papan belian (ketam) m3
2 Lem kayu Kg
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

Pekerjaan Kayu 225


A.4.6.1.5.b Pembuatan dan pemasangan 1 m2 daun pintu panel, kayu kelas II

No. URAIAN PEKERJAAN KODE SATUAN

1 2 3
A TENAGA
1 Pekerja L.01 OH
2 Tukang kayu L.03 OH
3 Kepala Tukang L.03 OH
4 Mandor L.04 OH
Jumlah
B BAHAN
1 Papan kayu (Papan kayu klas II (mabang) ketam) m3
2 Lem kayu Kg
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

A.4.6.1.6. Pembuatan dan pemasangan 1 m2 pintu dan jendela kaca, kayu kelas I

No. URAIAN PEKERJAAN KODE SATUAN

1 2 3
A TENAGA
1 Pekerja L.01 OH
2 Tukang kayu L.03 OH
3 Kepala Tukang L.03 OH
4 Mandor L.04 OH
Jumlah
B BAHAN
1 Papan kayu (Papan kayu klas I (ketam) m3
2 Lem kayu Kg
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

A.4.6.1.6.a Pembuatan dan pemasangan 1 m2 pintu dan jendela kaca, kayu belian

No. URAIAN PEKERJAAN KODE SATUAN

1 2 3
A TENAGA
1 Pekerja L.01 OH
2 Tukang kayu L.03 OH
3 Kepala Tukang L.03 OH
4 Mandor L.04 OH
Jumlah
B BAHAN
1 Papan kayu (Papan belian ketam) m3
Pekerjaan Kayu 226
2 Lem kayu Kg
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

A.4.6.1.6.b Pembuatan dan pemasangan 1 m2 pintu dan jendela kaca, kayu kelas II

No. URAIAN PEKERJAAN KODE SATUAN

1 2 3
A TENAGA
1 Pekerja L.01 OH
2 Tukang kayu L.03 OH
3 Kepala Tukang L.03 OH
4 Mandor L.04 OH
Jumlah
B BAHAN
1 Papan kayu (Papan kayu klas II (mabang) ketam) m3
2 Lem kayu Kg
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

Pekerjaan Kayu 227


A.4.6.1.7. Pembuatan dan pemasangan 1 m2 pintu dan jendela jalusi kayu kelas I

No. URAIAN PEKERJAAN KODE SATUAN

1 2 3
A TENAGA
1 Pekerja L.01 OH
2 Tukang kayu L.03 OH
3 Kepala Tukang L.03 OH
4 Mandor L.04 OH
Jumlah
B BAHAN
1 Papan kayu (Papan kayu klas I (ketam) m3
2 Lem kayu Kg
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

A.4.6.1.7.a Pembuatan dan pemasangan 1 m2 pintu dan jendela jalusi kayu belian

No. URAIAN PEKERJAAN KODE SATUAN

1 2 3
A TENAGA
1 Pekerja L.01 OH
2 Tukang kayu L.03 OH
3 Kepala Tukang L.03 OH
4 Mandor L.04 OH
Jumlah
B BAHAN
1 Papan kayu (Papan belian ketam) m3
2 Lem kayu Kg
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

A.4.6.1.7.b Pembuatan dan pemasangan 1 m2 pintu dan jendela jalusi kayu kelas II

No. URAIAN PEKERJAAN KODE SATUAN

1 2 3
A TENAGA
1 Pekerja L.01 OH
2 Tukang kayu L.03 OH
3 Kepala Tukang L.03 OH
4 Mandor L.04 OH
Jumlah
B BAHAN
1 Papan kayu (Papan kayu klas II (mabang) ketam) m3
2 Lem kayu Kg

Pekerjaan Kayu 228


Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

A.4.6.1.8. Pembuatan 1 m2 daun pintu plywood rangkap, rangka kayu kelas II tertutup (l

No. URAIAN PEKERJAAN KODE SATUAN

1 2 3
A TENAGA
1 Pekerja L.01 OH
2 Tukang kayu L.03 OH
3 Kepala Tukang L.03 OH
4 Mandor L.04 OH
Jumlah
B BAHAN
1 Papan kayu (Papan kayu klas II (mabang) ketam) m3
2 Paku 1 cm- 2,5 cm Kg
3 Lem kayu Kg
4 Plywood tebal 6 mm ukuran (90 x 220) cm Lembar
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

Pekerjaan Kayu 229


A.4.6.1.9. Pembuatan 1 m2 pintu plywood rangkap, rangka expose kayu kelas I

No. URAIAN PEKERJAAN KODE SATUAN

1 2 3
A TENAGA
1 Pekerja L.01 OH
2 Tukang kayu L.03 OH
3 Kepala Tukang L.03 OH
4 Mandor L.04 OH
Jumlah
B BAHAN
1 Papan kayu (Papan kayu klas I (ketam) m3
2 Paku 1 cm- 2,5 cm Kg
3 Lem kayu Kg
4 Plywood tebal 6 mm ukuran (90 x 220) cm Lembar
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

A.4.6.1.9.a Pembuatan 1 m2 pintu plywood rangkap, rangka expose kayu kelas II

No. URAIAN PEKERJAAN KODE SATUAN

1 2 3
A TENAGA
1 Pekerja L.01 OH
2 Tukang kayu L.03 OH
3 Kepala Tukang L.03 OH
4 Mandor L.04 OH
Jumlah
B BAHAN
1 Papan kayu (Papan kayu klas II (mabang) ketam) m3
2 Paku 1 cm- 2,5 cm Kg
3 Lem kayu Kg
4 Plywood tebal 6 mm ukuran (90 x 220) cm Lembar
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

A.4.6.1.10. Pemasangan 1 m2 jalusi kusen, kayu kelas I

No. URAIAN PEKERJAAN KODE SATUAN

1 2 3
A TENAGA
1 Pekerja L.01 OH
2 Tukang kayu L.03 OH
3 Kepala Tukang L.03 OH
4 Mandor L.04 OH

Pekerjaan Kayu 230


Jumlah
B BAHAN
1 Papan kayu (Papan kayu klas I (ketam) m3
2 Paku 1 cm- 2,5 cm Kg
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

A.4.6.1.10.a Pemasangan 1 m2 jalusi kusen, kayu kelas II

No. URAIAN PEKERJAAN KODE SATUAN

1 2 3
A TENAGA
1 Pekerja L.01 OH
2 Tukang kayu L.03 OH
3 Kepala Tukang L.03 OH
4 Mandor L.04 OH
Jumlah
B BAHAN
1 Papan kayu (Papan kayu klas II (mabang) ketam) m3
2 Paku 1 cm- 2,5 cm Kg
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

Pekerjaan Kayu 231


A.4.6.1.13. Pemasangan 1 m3 konstruksi kuda-kuda konvensional, kayu kelas II bentang

No. URAIAN PEKERJAAN KODE SATUAN

1 2 3
A TENAGA
1 Pekerja L.01 OH
2 Tukang kayu L.03 OH
3 Kepala Tukang L.03 OH
4 Mandor L.04 OH
Jumlah
B BAHAN
1 Balok kayu (Ky. klas II Mabang uk. 6/12 - 4 M ( tdk ketam ) m3
2 Besi strip tebal 5 mm Kg
3 Paku 12 cm Kg
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

A.4.6.1.14. Pemasangan 1 m3 konstruksi kuda-kuda expose, kayu kelas I

No. URAIAN PEKERJAAN KODE SATUAN

1 2 3
A TENAGA
1 Pekerja L.01 OH
2 Tukang kayu L.03 OH
3 Kepala Tukang L.03 OH
4 Mandor L.04 OH
Jumlah
B BAHAN
1 Ky. klas I Bengkirai uk. 5/10 - 4 M ( ketam ) m3
2 Besi strip tebal 5 mm Kg
3 Paku 12 cm Kg
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

A.4.6.1.15. Pemasangan 1 m3 konstruksi gordeng, kayu kelas II

No. URAIAN PEKERJAAN KODE SATUAN

1 2 3
A TENAGA

Pekerjaan Kayu 232


1 Pekerja L.01 OH
2 Tukang kayu L.03 OH
3 Kepala Tukang L.03 OH
4 Mandor L.04 OH
Jumlah
B BAHAN
1 Balok kayu (Ky. klas II Mabang uk. 5/10 - 4 M ( tdk ketam )) m3
2 Besi strip tebal 5 mm Kg
3 Paku 12 cm Kg
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

A.4.6.1.18. Pemasangan 1 m2 rangka atap sirap, kayu kelas II

No. URAIAN PEKERJAAN KODE SATUAN

1 2 3
A TENAGA
1 Pekerja L.01 OH
2 Tukang kayu L.03 OH
3 Kepala Tukang L.03 OH
4 Mandor L.04 OH
Jumlah
B BAHAN
1 Kayu kelas II (Ky. klas II Mabang uk. 4/6 - 4 M ( tdk ketam ) m3
2 Paku 5 - 10 cm Kg
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

Pekerjaan Kayu 233


A.4.6.1.19. Pemasangan 1 m2 rangka langit-langit (50 x 100) cm, kayu kelas II

No. URAIAN PEKERJAAN KODE SATUAN

1 2 3
A TENAGA
1 Pekerja L.01 OH
2 Tukang kayu L.03 OH
3 Kepala Tukang L.03 OH
4 Mandor L.04 OH
Jumlah
B BAHAN
1 Kaso-kaso 5 x 7 cm (Ky. klas II Mabang uk. 5/7 - 4 M ( tdk keta m3
2 Paku 7 - 10 cm Kg
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

A.4.6.1.20. Pemasangan 1 m2 rangka langit-langit (60 x 60) cm, kayu kelas II

No. URAIAN PEKERJAAN KODE SATUAN

1 2 3
A TENAGA
1 Pekerja L.01 OH
2 Tukang kayu L.03 OH
3 Kepala Tukang L.03 OH
4 Mandor L.04 OH
Jumlah
B BAHAN
1 Kaso-kaso 5 x 7 cm (Ky. klas II Mabang uk. 5/7 - 4 M ( tdk keta m3
2 Paku 7 - 10 cm Kg
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

A.4.6.1.21. Pemasangan 1 m’ lisplank ukuran (3 x 20) cm, kayu kelas I

No. URAIAN PEKERJAAN KODE SATUAN

1 2 3
A TENAGA
1 Pekerja L.01 OH
2 Tukang kayu L.03 OH
3 Kepala Tukang L.03 OH
4 Mandor L.04 OH

Pekerjaan Kayu 234


Jumlah
B BAHAN
1 Papan kayu (Papan kayu klas I (bengkirai) ketam) m3
2 Paku 7 - 10 cm Kg
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

A.4.6.1.21.a Pemasangan 1 m’ lisplank ukuran (3 x 20) cm, kayu belian

No. URAIAN PEKERJAAN KODE SATUAN

1 2 3
A TENAGA
1 Pekerja L.01 OH
2 Tukang kayu L.03 OH
3 Kepala Tukang L.03 OH
4 Mandor L.04 OH
Jumlah
B BAHAN
1 Papan kayu (Papan kayu belian ketam) m3
2 Paku 7 - 10 cm Kg
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

Pekerjaan Kayu 235


buat turunan kayu belian

A.4.6.1.22. Pemasangan 1 m’ lisplank ukuran (3 x 30) cm, kayu kelas I

No. URAIAN PEKERJAAN KODE SATUAN

1 2 3
A TENAGA
1 Pekerja L.01 OH
2 Tukang kayu L.03 OH
3 Kepala Tukang L.03 OH
4 Mandor L.04 OH
Jumlah
B BAHAN
1 Papan kayu (Papan kayu klas I (bengkirai) ketam) m3
2 Paku 7 - 10 cm Kg
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

A.4.6.1.22.a Pemasangan 1 m’ lisplank ukuran (3 x 30) cm, kayu belian

No. URAIAN PEKERJAAN KODE SATUAN

1 2 3
A TENAGA
1 Pekerja L.01 OH
2 Tukang kayu L.03 OH
3 Kepala Tukang L.03 OH
4 Mandor L.04 OH
Jumlah
B BAHAN
1 Papan kayu belian ketam m3
2 Paku 7 - 10 cm Kg
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

A.4.6.1.23. Pemasangan 1 m2 rangka dinding pemisah (60 x 120) cm kayu kelas II

No. URAIAN PEKERJAAN KODE SATUAN

1 2 3
A TENAGA
1 Pekerja L.01 OH
2 Tukang kayu L.03 OH
3 Kepala Tukang L.03 OH
4 Mandor L.04 OH
Jumlah
B BAHAN
Pekerjaan Kayu 236
1 Balok kayu mabang tidak ketam (7/7) m3
2 Paku 5 dan 7 cm Kg
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

A.4.6.1.25. Pemasangan 1 m2 dinding pemisah plywood rangkap, rangka kayu kelas II

No. URAIAN PEKERJAAN KODE SATUAN

1 2 3
A TENAGA
1 Pekerja L.01 OH
2 Tukang kayu L.03 OH
3 Kepala Tukang L.03 OH
4 Mandor L.04 OH
Jumlah
B BAHAN
1 Balok kayu (Ky. klas II Mabang uk. 6/12 - 4 M ( tdk ketam ) M3
2 Paku 5 dan 10 Kg
3 Plywood tebal 3 mm ukuran (120 x 240) cm Lembar
4 Lem kayu Kg
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

Pekerjaan Kayu 237


SATUAN PEKERJAAN KAYU

kusen pintu dan kusen jendela, kayu kelas I


HARGA BIAYA
KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

7.00 90,000.00 630,000.00


21.00 100,000.00 2,100,000.00
2.10 110,000.00 231,000.00
0.35 120,000.00 42,000.00
3,003,000.00

1.10 15,000,000.000 16,500,000.00


1.25 20,500.000 25,625.00
1.00 17,100.000 17,100.00
16,542,725.00
19,545,725.00
2,931,858.75
22,477,583.75

kusen pintu dan kusen jendela, kayu belian


HARGA BIAYA
KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

7.00 90,000.00 630,000.00


21.00 100,000.00 2,100,000.00
2.10 110,000.00 231,000.00
0.35 120,000.00 42,000.00
3,003,000.00

1.10 19,500,000.000 21,450,000.00


1.25 20,500.000 25,625.00
1.00 17,100.000 17,100.00
21,492,725.00
24,495,725.00
3,674,358.75
28,170,083.75

kusen pintu dan kusen jendela, kayu kelas II


HARGA BIAYA
KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

6.00 90,000.00 540,000.00


Pekerjaan Kayu 238
18.00 100,000.00 1,800,000.00
1.80 110,000.00 198,000.00
0.30 120,000.00 36,000.00
2,574,000.00

1.20 11,500,000.000 13,800,000.00


1.25 20,500.000 25,625.00
1.00 17,100.000 17,100.00
13,842,725.00
16,416,725.00
2,462,508.75
18,879,233.75

Pekerjaan Kayu 239


pintu klamp standar, kayu kelas II
HARGA BIAYA
KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

0.35 90,000.00 31,500.00


1.05 100,000.00 105,000.00
0.105 110,000.00 11,550.00
0.018 120,000.00 2,160.00
150,210.00

0.04 6,377,300.000 255,092.00


0.05 20,500.000 1,025.00
256,117.00
406,327.00
60,949.05
467,276.05

pintu klamp sederhana, kayu kelas III


HARGA BIAYA
KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

0.35 90,000.00 31,500.00


1.05 100,000.00 105,000.00
0.105 110,000.00 11,550.00
0.018 120,000.00 2,160.00
150,210.00

0.04 2,113,100.000 84,524.00


0.05 20,500.000 1,025.00
85,549.00
235,759.00
35,363.85
271,122.85

daun pintu panel, kayu kelas I


HARGA BIAYA
KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

1.00 90,000.00 90,000.00


3.00 100,000.00 300,000.00
0.30 110,000.00 33,000.00
0.05 120,000.00 6,000.00
429,000.00
Pekerjaan Kayu 240
0.04 11,188,300.000 447,532.00
0.50 17,100.000 8,550.00
456,082.00
885,082.00
132,762.30
1,017,844.30

daun pintu panel, kayu belian


HARGA BIAYA
KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

1.00 90,000.00 90,000.00


3.00 100,000.00 300,000.00
0.30 110,000.00 33,000.00
0.05 120,000.00 6,000.00
429,000.00

0.04 13,252,300.000 530,092.00


0.50 17,100.000 8,550.00
538,642.00
967,642.00
145,146.30
1,112,788.30

Pekerjaan Kayu 241


daun pintu panel, kayu kelas II
HARGA BIAYA
KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

1.00 90,000.00 90,000.00


3.00 100,000.00 300,000.00
0.30 110,000.00 33,000.00
0.05 120,000.00 6,000.00
429,000.00

0.04 6,377,300.000 255,092.00


0.50 17,100.000 8,550.00
263,642.00
692,642.00
103,896.30
796,538.30

pintu dan jendela kaca, kayu kelas I


HARGA BIAYA
KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

0.80 90,000.00 72,000.00


2.40 100,000.00 240,000.00
0.24 110,000.00 26,400.00
0.04 120,000.00 4,800.00
343,200.00

0.04 11,188,300.000 447,532.00


0.30 17,100.000 5,130.00
452,662.00
795,862.00
119,379.30
915,241.30

pintu dan jendela kaca, kayu belian


HARGA BIAYA
KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

0.80 90,000.00 72,000.00


2.40 100,000.00 240,000.00
0.24 110,000.00 26,400.00
0.04 120,000.00 4,800.00
343,200.00

0.024 13,252,300.000 318,055.20


Pekerjaan Kayu 242
0.30 17,100.000 5,130.00
323,185.20
666,385.20
99,957.78
766,342.98

pintu dan jendela kaca, kayu kelas II


HARGA BIAYA
KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

0.80 90,000.00 72,000.00


2.40 100,000.00 240,000.00
0.24 110,000.00 26,400.00
0.04 120,000.00 4,800.00
343,200.00

0.024 6,377,300.000 153,055.20


0.30 17,100.000 5,130.00
158,185.20
501,385.20
75,207.78
576,592.98

Pekerjaan Kayu 243


pintu dan jendela jalusi kayu kelas I
HARGA BIAYA
KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

1.00 90,000.00 90,000.00


3.00 100,000.00 300,000.00
0.30 110,000.00 33,000.00
0.05 120,000.00 6,000.00
429,000.00

0.064 11,188,300.000 716,051.20


0.50 17,100.000 8,550.00
724,601.20
1,153,601.20
173,040.18
1,326,641.38

pintu dan jendela jalusi kayu belian


HARGA BIAYA
KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

1.00 90,000.00 90,000.00


3.00 100,000.00 300,000.00
0.30 110,000.00 33,000.00
0.05 120,000.00 6,000.00
429,000.00

0.064 13,252,300.000 848,147.20


0.50 17,100.000 8,550.00
856,697.20
1,285,697.20
192,854.58
1,478,551.78

pintu dan jendela jalusi kayu kelas II


HARGA BIAYA
KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

1.00 90,000.00 90,000.00


3.00 100,000.00 300,000.00
0.30 110,000.00 33,000.00
0.05 120,000.00 6,000.00
429,000.00

0.064 6,377,300.000 408,147.20


0.50 17,100.000 8,550.00

Pekerjaan Kayu 244


416,697.20
845,697.20
126,854.58
972,551.78

d rangkap, rangka kayu kelas II tertutup (lebar sampai 90 cm)


HARGA BIAYA
KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

0.70 90,000.00 63,000.00


2.10 100,000.00 210,000.00
0.21 110,000.00 23,100.00
0.035 120,000.00 4,200.00
300,300.00

0.025 6,377,300.000 159,432.50


0.03 20,500.000 615.00
0.50 17,100.000 8,550.00
1.00 120,000.000 120,000.00
288,597.50
588,897.50
88,334.63
677,232.13

Pekerjaan Kayu 245


gkap, rangka expose kayu kelas I
HARGA BIAYA
KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

0.80 90,000.00 72,000.00


2.40 100,000.00 240,000.00
0.24 110,000.00 26,400.00
0.04 120,000.00 4,800.00
343,200.00

0.0256 11,188,300.000 286,420.48


0.03 20,500.000 615.00
0.50 17,100.000 8,550.00
1.00 120,000.000 120,000.00
415,585.48
758,785.48
113,817.82
872,603.30

gkap, rangka expose kayu kelas II


HARGA BIAYA
KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

0.80 90,000.00 72,000.00


2.40 100,000.00 240,000.00
0.24 110,000.00 26,400.00
0.04 120,000.00 4,800.00
343,200.00

0.0256 6,377,300.000 163,258.88


0.03 20,500.000 615.00
0.50 17,100.000 8,550.00
1.00 120,000.000 120,000.00
292,423.88
635,623.88
95,343.58
730,967.46

u kelas I
HARGA BIAYA
KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

0.67 90,000.00 60,300.00


2.00 100,000.00 200,000.00
0.20 110,000.00 22,000.00
0.335 120,000.00 40,200.00

Pekerjaan Kayu 246


322,500.00

0.06 11,188,300.000 671,298.00


0.15 20,500.000 3,075.00
674,373.00
996,873.00
149,530.95
1,146,403.95

u kelas II
HARGA BIAYA
KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

0.67 90,000.00 60,300.00


2.00 100,000.00 200,000.00
0.20 110,000.00 22,000.00
0.335 120,000.00 40,200.00
322,500.00

0.06 6,377,300.000 382,638.00


0.15 20,500.000 3,075.00
385,713.00
708,213.00
106,231.95
814,444.95

Pekerjaan Kayu 247


kuda konvensional, kayu kelas II bentang 6 meter
HARGA BIAYA
KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

4.00 90,000.00 360,000.00


12.00 100,000.00 1,200,000.00
1.20 110,000.00 132,000.00
0.20 120,000.00 24,000.00
1,716,000.00

1.10 3,789,700.000 4,168,670.00


15.00 13,500.000 202,500.00
5.60 20,500.000 114,800.00
4,485,970.00
6,201,970.00
930,295.50
7,132,265.50

kuda expose, kayu kelas I


HARGA BIAYA
KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

6.70 90,000.00 603,000.00


21.10 100,000.00 2,110,000.00
2.01 110,000.00 221,100.00
0.335 120,000.00 40,200.00
2,974,300.00

1.20 8,100,000.000 9,720,000.00


15.00 13,500.000 202,500.00
5.60 20,500.000 114,800.00
10,037,300.00
13,011,600.00
1,951,740.00
14,963,340.00

eng, kayu kelas II


HARGA BIAYA
KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

Pekerjaan Kayu 248


6.70 90,000.00 603,000.00
21.10 100,000.00 2,110,000.00
2.01 110,000.00 221,100.00
0.335 120,000.00 40,200.00
2,974,300.00

1.10 2,924,400.000 3,216,840.00


15.00 13,500.000 202,500.00
3.00 20,500.000 61,500.00
3,480,840.00
6,455,140.00
968,271.00
7,423,411.00

p, kayu kelas II
HARGA BIAYA
KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

0.12 90,000.00 10,800.00


0.12 100,000.00 12,000.00
0.012 110,000.00 1,320.00
0.006 120,000.00 720.00
24,840.00

0.014 4,024,900.000 56,348.60


0.057 20,500.000 1,168.50
57,517.10
82,357.10
12,353.57
94,710.67

Pekerjaan Kayu 249


git (50 x 100) cm, kayu kelas II
HARGA BIAYA
KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

0.15 90,000.00 13,500.00


0.30 100,000.00 30,000.00
0.03 110,000.00 3,300.00
0.075 120,000.00 9,000.00
55,800.00

0.015 4,153,700.000 63,966.98


0.20 20,500.000 4,100.00
68,066.98
123,866.98
18,580.05
142,447.03

git (60 x 60) cm, kayu kelas II


HARGA BIAYA
KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

0.20 90,000.00 18,000.00


0.30 100,000.00 30,000.00
0.03 110,000.00 3,300.00
0.01 120,000.00 1,200.00
52,500.00

0.0163 4,153,700.000 67,705.31


0.25 20,500.000 5,125.00
72,830.31
125,330.31
18,799.55
144,129.86

3 x 20) cm, kayu kelas I


HARGA BIAYA
KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

0.10 90,000.00 9,000.00


0.20 100,000.00 20,000.00
0.02 110,000.00 2,200.00
0.005 120,000.00 600.00

Pekerjaan Kayu 250


31,800.00

0.0108 11,188,300.000 120,833.64


0.10 20,500.000 2,050.00
122,883.64
154,683.64
23,202.55
177,886.19

3 x 20) cm, kayu belian


HARGA BIAYA
KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

0.10 90,000.00 9,000.00


0.20 100,000.00 20,000.00
0.02 110,000.00 2,200.00
0.005 120,000.00 600.00
31,800.00

0.0108 13,252,300.000 143,124.84


0.10 20,500.000 2,050.00
145,174.84
176,974.84
26,546.23
203,521.07

Pekerjaan Kayu 251


3 x 30) cm, kayu kelas I
HARGA BIAYA
KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

0.10 90,000.00 9,000.00


0.20 100,000.00 20,000.00
0.02 110,000.00 2,200.00
0.005 120,000.00 600.00
31,800.00

0.0110 11,188,300.000 123,071.30


0.050 20,500.000 1,025.00
124,096.30
155,896.30
23,384.45
179,280.75

3 x 30) cm, kayu belian


HARGA BIAYA
KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

0.10 90,000.00 9,000.00


0.20 100,000.00 20,000.00
0.02 110,000.00 2,200.00
0.005 120,000.00 600.00
31,800.00

0.0110 13,252,300.000 145,775.30


0.050 20,500.000 1,025.00
146,800.30
178,600.30
26,790.05
205,390.35

emisah (60 x 120) cm kayu kelas II


HARGA BIAYA
KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

0.15 90,000.00 13,500.00


0.45 100,000.00 45,000.00
0.045 110,000.00 4,950.00
0.008 120,000.00 960.00
64,410.00

Pekerjaan Kayu 252


0.028 3,971,400.000 111,199.20
0.15 20,500.000 3,075.00
114,274.20
178,684.20
26,802.63
205,486.83

plywood rangkap, rangka kayu kelas II


HARGA BIAYA
KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

0.20 90,000.00 18,000.00


0.60 100,000.00 60,000.00
0.06 110,000.00 6,600.00
0.01 120,000.00 1,200.00
85,800.00

0.028 3,789,700.000 106,111.60


0.15 20,500.000 3,075.00
0.86 70,000.000 60,200.00
0.56 17,100.000 9,576.00
178,962.60
264,762.60
39,714.39
304,476.99

Pekerjaan Kayu 253


SATUAN PEKERJAAN KUNCI DAN KACA

A.4.6.2.1. Pemasangan 1 buah kunci tanam antik

No. URAIAN PEKERJAAN SATUAN KOEFISIEN

1 2 3 5
A TENAGA
1 Pekerja OH 0.06
2 Tukang kayu OH 0.60
3 Kepala Tukang OH 0.06
4 Mandor OH 0.003
Jumlah
B BAHAN
1 Kunci tanam antik Bh 1.00
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

A.4.6.2.2. Pemasangan 1 buah kunci tanam biasa

No. URAIAN PEKERJAAN SATUAN KOEFISIEN

1 2 3 5
A TENAGA
1 Pekerja OH 0.01
2 Tukang kayu OH 0.50
3 Kepala Tukang OH 0.05
4 Mandor OH 0.005
Jumlah
B BAHAN
1 Kunci tanam biasa Bh 1.00
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

A.4.6.2.2.a Pemasangan 1 buah kunci tanam 2 slag

No. URAIAN PEKERJAAN SATUAN KOEFISIEN

1 2 3 5
A TENAGA
1 Pekerja OH 0.01
2 Tukang kayu OH 0.50

Pekerjaan Kunci dan Kaca 254


3 Kepala Tukang OH 0.05
4 Mandor OH 0.005
Jumlah
B BAHAN
1 Kunci tanam 2 slag (setaraf beluci) Bh 1.00
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

Pekerjaan Kunci dan Kaca 255


A.4.6.2.3. Pemasangan 1 buah kunci kamar mandi

No. URAIAN PEKERJAAN SATUAN KOEFISIEN

1 2 3 5
A TENAGA
1 Pekerja OH 0.005
2 Tukang kayu OH 0.50
3 Kepala Tukang OH 0.05
4 Mandor OH 0.003
Jumlah
B BAHAN
1 Kunci tanam biasa Bh 1.00
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

A.4.6.2.4. Pemasangan 1 buah kunci silinder

No. URAIAN PEKERJAAN SATUAN KOEFISIEN

1 2 3 5
A TENAGA
1 Pekerja OH 0.005
2 Tukang kayu OH 0.50
3 Kepala Tukang OH 0.05
4 Mandor OH 0.003
Jumlah
B BAHAN
1 Kunci silinder Bh 1.00
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

A.4.6.2.5. Pemasangan 1 buah engsel pintu

No. URAIAN PEKERJAAN SATUAN KOEFISIEN

1 2 3 5
A TENAGA
1 Pekerja OH 0.015
2 Tukang kayu OH 0.15
3 Kepala Tukang OH 0.015

Pekerjaan Kunci dan Kaca 256


4 Mandor OH 0.0008
Jumlah
B BAHAN
1 Engsel pintu Bh 1.00
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

Pekerjaan Kunci dan Kaca 257


A.4.6.2.6. Pemasangan 1 buah engsel jendela kupu-kupu

No. URAIAN PEKERJAAN SATUAN KOEFISIEN

1 2 3 5
A TENAGA
1 Pekerja OH 0.01
2 Tukang kayu OH 0.10
3 Kepala Tukang OH 0.01
4 Mandor OH 0.0005
Jumlah
B BAHAN
1 Engsel kupu-kupu Bh 1.00
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

A.4.6.2.9. Pemasangan 1 buah kait angin

No. URAIAN PEKERJAAN SATUAN KOEFISIEN

1 2 3 5
A TENAGA
1 Pekerja OH 0.015
2 Tukang kayu OH 0.15
3 Kepala Tukang OH 0.015
4 Mandor OH 0.008
Jumlah
B BAHAN
1 Kait angin Bh 1.00
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

A.4.6.2.10. Pemasangan 1 buah door closer

No. URAIAN PEKERJAAN SATUAN KOEFISIEN

1 2 3 5
A TENAGA
1 Pekerja OH 0.05
2 Tukang kayu OH 0.50
3 Kepala Tukang OH 0.05
4 Mandor OH 0.003
Jumlah

Pekerjaan Kunci dan Kaca 258


B BAHAN
1 Door clooser Set 1.00
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

Pekerjaan Kunci dan Kaca 259


A.4.6.2.11. Pemasangan 1 buah kunci slot pintu

No. URAIAN PEKERJAAN SATUAN KOEFISIEN

1 2 3 5
A TENAGA
1 Pekerja OH 0.02
2 Tukang kayu OH 0.20
3 Kepala Tukang OH 0.02
4 Mandor OH 0.001
Jumlah
B BAHAN
1 Kunci slot pintu Bh 1.00
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

A.4.6.2.11.a Pemasangan 1 buah kunci slot jendela

No. URAIAN PEKERJAAN SATUAN KOEFISIEN

1 2 3 5
A TENAGA
1 Pekerja OH 0.02
2 Tukang kayu OH 0.20
3 Kepala Tukang OH 0.02
4 Mandor OH 0.001
Jumlah
B BAHAN
1 Kunci slot jendela Bh 1.00
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

A.4.6.2.12. Pemasangan 1 buah Door holder

No. URAIAN PEKERJAAN SATUAN KOEFISIEN

1 2 3 5
A TENAGA
1 Pekerja OH 0.05
2 Tukang kayu OH 0.50
3 Kepala Tukang OH 0.05
4 Mandor OH 0.003

Pekerjaan Kunci dan Kaca 260


Jumlah
B BAHAN
1 Door holder Bh 1.00
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

Pekerjaan Kunci dan Kaca 261


A.4.6.2.16. Pemasangan 1 m2 kaca tebal 3 mm

No. URAIAN PEKERJAAN SATUAN KOEFISIEN

1 2 3 5
A TENAGA
1 Pekerja OH 0.015
2 Tukang kayu OH 0.15
3 Kepala Tukang OH 0.015
4 Mandor OH 0.0008
Jumlah
B BAHAN
1 Kaca tebal 3mm m² 1.10
2 Sealant Kg 0.05
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

A.4.6.2.17. Pemasangan 1 m2 kaca tebal 5 mm

No. URAIAN PEKERJAAN SATUAN KOEFISIEN

1 2 3 5
A TENAGA
1 Pekerja OH 0.015
2 Tukang kayu OH 0.15
3 Kepala Tukang OH 0.015
4 Mandor OH 0.0008
Jumlah
B BAHAN
1 Kaca tebal 5 mm m² 1.10
2 Sealant Kg 0.05
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

Pekerjaan Kunci dan Kaca 262


AN KACA

HARGA BIAYA
SATUAN SATUAN
( Rp. ) ( Rp. )
4 6

90,000.00 5,400.00
100,000.00 60,000.00
110,000.00 6,600.00
120,000.00 360.00
72,360.00

47,500.000 47,500.00
47,500.00
119,860.00
17,979.00
137,839.00

HARGA BIAYA
SATUAN SATUAN
( Rp. ) ( Rp. )
4 6

90,000.00 900.00
100,000.00 50,000.00
110,000.00 5,500.00
120,000.00 600.00
57,000.00

55,000.000 55,000.00
55,000.00
112,000.00
16,800.00
128,800.00

HARGA BIAYA
SATUAN SATUAN
( Rp. ) ( Rp. )
4 6

90,000.00 900.00
100,000.00 50,000.00

Pekerjaan Kunci dan Kaca 263


110,000.00 5,500.00
120,000.00 600.00
57,000.00

179,100.000 179,100.00
179,100.00
236,100.00
35,415.00
271,515.00

Pekerjaan Kunci dan Kaca 264


HARGA BIAYA
SATUAN SATUAN
( Rp. ) ( Rp. )
4 6

90,000.00 450.00
100,000.00 50,000.00
110,000.00 5,500.00
120,000.00 360.00
56,310.00

55,000.000 55,000.00
55,000.00
111,310.00
16,696.50
128,006.50

HARGA BIAYA
SATUAN SATUAN
( Rp. ) ( Rp. )
4 6

90,000.00 450.00
100,000.00 50,000.00
110,000.00 5,500.00
120,000.00 360.00
56,310.00

60,800.000 60,800.00
60,800.00
117,110.00
17,566.50
134,676.50

HARGA BIAYA
SATUAN SATUAN
( Rp. ) ( Rp. )
4 6

90,000.00 1,350.00
100,000.00 15,000.00
110,000.00 1,650.00

Pekerjaan Kunci dan Kaca 265


120,000.00 96.00
18,096.00

27,500.000 27,500.00
27,500.00
45,596.00
6,839.40
52,435.40

Pekerjaan Kunci dan Kaca 266


HARGA BIAYA
SATUAN SATUAN
( Rp. ) ( Rp. )
4 6

90,000.00 900.00
100,000.00 10,000.00
110,000.00 1,100.00
120,000.00 60.00
12,060.00

18,800.000 18,800.00
18,800.00
30,860.00
4,629.00
35,489.00

HARGA BIAYA
SATUAN SATUAN
( Rp. ) ( Rp. )
4 6

90,000.00 1,350.00
100,000.00 15,000.00
110,000.00 1,650.00
120,000.00 960.00
18,960.00

14,400.000 14,400.00
14,400.00
33,360.00
5,004.00
38,364.00

HARGA BIAYA
SATUAN SATUAN
( Rp. ) ( Rp. )
4 6

90,000.00 4,500.00
100,000.00 50,000.00
110,000.00 5,500.00
120,000.00 360.00
60,360.00

Pekerjaan Kunci dan Kaca 267


175,500.000 175,500.00
175,500.00
235,860.00
35,379.00
271,239.00

Pekerjaan Kunci dan Kaca 268


HARGA BIAYA
SATUAN SATUAN
( Rp. ) ( Rp. )
4 6

90,000.00 1,800.00
100,000.00 20,000.00
110,000.00 2,200.00
120,000.00 120.00
24,120.00

17,000.000 17,000.00
17,000.00
41,120.00
6,168.00
47,288.00

HARGA BIAYA
SATUAN SATUAN
( Rp. ) ( Rp. )
4 6

90,000.00 1,800.00
100,000.00 20,000.00
110,000.00 2,200.00
120,000.00 120.00
24,120.00

6,400.000 6,400.00
6,400.00
30,520.00
4,578.00
35,098.00

HARGA BIAYA
SATUAN SATUAN
( Rp. ) ( Rp. )
4 6

90,000.00 4,500.00
100,000.00 50,000.00
110,000.00 5,500.00
120,000.00 360.00

Pekerjaan Kunci dan Kaca 269


60,360.00

135,000.000 135,000.00
135,000.00
195,360.00
29,304.00
224,664.00

Pekerjaan Kunci dan Kaca 270


HARGA BIAYA
SATUAN SATUAN
( Rp. ) ( Rp. )
4 6

90,000.00 1,350.00
100,000.00 15,000.00
110,000.00 1,650.00
120,000.00 96.00
18,096.00

80,000.000 88,000.00
106,900.000 5,345.00
93,345.00
111,441.00
16,716.15
128,157.15

HARGA BIAYA
SATUAN SATUAN
( Rp. ) ( Rp. )
4 6

90,000.00 1,350.00
100,000.00 15,000.00
110,000.00 1,650.00
120,000.00 96.00
18,096.00

82,500.000 90,750.00
106,900.000 5,345.00
96,095.00
114,191.00
17,128.65
131,319.65

Pekerjaan Kunci dan Kaca 271


SATUAN PEKERJAAN PENGECATAN

A.4.7.1.1. 1 m2 Pengikisan/pengerokan permukaan cat lama

No. URAIAN PEKERJAAN KODE SATUAN

1 2 3
A TENAGA
1 Pekerja L.01 OH
2 Mandor L.04 OH
Jumlah
B BAHAN
1 Soda api Kg
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

A.4.7.1.2. 1 m2 Pencucian bidang permukaan tembok yang pernah dicat

No. URAIAN PEKERJAAN KODE SATUAN

1 2 3
A TENAGA
1 Pekerja L.01 OH
2 Mandor L.04 OH
Jumlah
B BAHAN
1 Sabun Kg
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

A.4.7.1.3. 1 m2 Pengerokan karat pada permukaan baja cara manual

No. URAIAN PEKERJAAN KODE SATUAN

1 2 3
A TENAGA
1 Pekerja L.01 OH

Pekerjaan Pengecatan 272


2 Mandor L.04 OH
Jumlah
B BAHAN
1 Sabun Kg
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

A.4.7.1.4. 1 m2 Pengecatan bidang kayu baru (1 lapis plamuur, 1 lapis cat dasar, 2 lapis

No. URAIAN PEKERJAAN KODE SATUAN

1 2 3
A TENAGA
1 Pekerja L.01 OH
2 Tukang cat L.02 OH
3 Kepala tukang L.03 OH
4 Mandor L.04 OH
Jumlah
B BAHAN
Cat menie Kg
Plammur Kg
Cat dasar Kg
Cat penutup (cat kilat) Kg
Kuas Bh
Pengecer Kg
Ampelas Lbr
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

Pekerjaan Pengecatan 273


A.4.7.1.5. Pengecatan 1 m2 bidang kayu baru (1 lapis plamuur, 1 lapis cat dasar, 3 lapis

No. URAIAN PEKERJAAN KODE SATUAN

1 2 3
A TENAGA
1 Pekerja L.01 OH
2 Tukang cat L.02 OH
3 Kepala tukang L.03 OH
4 Mandor L.04 OH
Jumlah
B BAHAN
Cat menie Kg
Plammur Kg
Cat dasar Kg
Cat penutup (cat kilat) Kg
Kuas Bh
Pengecer Kg
Ampelas Lbr
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

A.4.7.1.6. Pelaburan 1 m2 bidang kayu dengan teak oil

No. URAIAN PEKERJAAN KODE SATUAN

1 2 3
A TENAGA
1 Pekerja L.01 OH
2 Tukang cat L.02 OH
3 Kepala tukang L.03 OH
4 Mandor L.04 OH
Jumlah
B BAHAN
Teak Oil L
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

A.4.7.1.7. Pelaburan 1 m2 bidang kayu dengan politur

No. URAIAN PEKERJAAN SATUAN

Pekerjaan Pengecatan 274


No. URAIAN PEKERJAAN KODE SATUAN

1 2 3
A TENAGA
1 Pekerja L.01 OH
2 Tukang cat L.02 OH
3 Kepala tukang L.03 OH
4 Mandor L.04 OH
Jumlah
B BAHAN
Politur L
Politur jadi L
Ampelas Lbr
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

A.4.7.1.8. Pelaburan 1 m2 bidang kayu dengan cat residu dan ter

No. URAIAN PEKERJAAN KODE SATUAN

1 2 3
A TENAGA
1 Pekerja L.01 OH
2 Mandor L.04 OH
Jumlah
B BAHAN
Residu atau ter L
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

Pekerjaan Pengecatan 275


A.4.7.1.9. Pelaburan 1 m2 bidang kayu dengan vernis

No. URAIAN PEKERJAAN KODE SATUAN

1 2 3
A TENAGA
1 Pekerja L.01 OH
2 Tukang cat L.02 OH
3 Kepala tukang L.03 OH
4 Mandor L.04 OH
Jumlah
B BAHAN
Vernis L
Dempul Kg
Ampelas Lbr
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

A.4.7.1.10. Pengecatan 1 m2 tembok baru ( 1lapis plamur, 1 lapis cat dasar, 2 lapis cat p

No. URAIAN PEKERJAAN KODE SATUAN

1 2 3
A TENAGA
1 Pekerja L.01 OH
2 Tukang cat L.02 OH
3 Kepala tukang L.03 OH
4 Mandor L.04 OH
Jumlah
B BAHAN
Plamur Kg
Cat dasar (setara vinilex) Kg
Cat penutup (setara vinilex) Kg
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

A.4.7.1.10.a Pengecatan 1 m2 tembok baru interior mutu baik setara mowilex ( 1lapis plam

No. URAIAN PEKERJAAN KODE SATUAN

1 2 3

Pekerjaan Pengecatan 276


A TENAGA
1 Pekerja L.01 OH
2 Tukang cat L.02 OH
3 Kepala tukang L.03 OH
4 Mandor L.04 OH
Jumlah
B BAHAN
Plamur Kg
Cat dasar (setara mowilex) Kg
Cat interior (setara mowilex) Kg
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

A.4.7.1.10.b Pengecatan 1 m2 tembok baru interior mutu baik setara dulux ( 1lapis plamu

No. URAIAN PEKERJAAN KODE SATUAN

1 2 3
A TENAGA
1 Pekerja L.01 OH
2 Tukang cat L.02 OH
3 Kepala tukang L.03 OH
4 Mandor L.04 OH
Jumlah
B BAHAN
Plamur Kg
Cat dasar (setara dulux) Kg
Cat interior (setara dulux) Kg
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

Pekerjaan Pengecatan 277


A.4.7.1.10.c Pengecatan 1 m2 tembok baru exterior mutu baik setara mowilex ( 1lapis pla

No. URAIAN PEKERJAAN KODE SATUAN

1 2 3
A TENAGA
1 Pekerja L.01 OH
2 Tukang cat L.02 OH
3 Kepala tukang L.03 OH
4 Mandor L.04 OH
Jumlah
B BAHAN
Palmmur Kg
Cat dasar (setara mowilex) Kg
Cat exterior wheatercoat (setara mowilex) Kg
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

A.4.7.1.10.d Pengecatan 1 m2 tembok baru exterior mutu baik setara dulux ( 1lapis plamu

No. URAIAN PEKERJAAN KODE SATUAN

1 2 3
A TENAGA
1 Pekerja L.01 OH
2 Tukang cat L.02 OH
3 Kepala tukang L.03 OH
4 Mandor L.04 OH
Jumlah
B BAHAN
Palmmur Kg
Cat dasar (setara dulux) Kg
Cat exterior wheater shield (setara dulux) Kg
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

A.4.7.1.11. Pengecatan 1 m2 tembok lama ( 1 lapis cat dasar, 2 lapis cat penutup)

No. URAIAN PEKERJAAN KODE SATUAN

1 2 3
A TENAGA
1 Pekerja L.01 OH
2 Tukang cat L.02 OH

Pekerjaan Pengecatan 278


3 Kepala tukang L.03 OH
4 Mandor L.04 OH
Jumlah
B BAHAN
Cat dasar (setara vnilex) Kg
Cat penutup (setara vinilex) Kg
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

A.4.7.1.11.a Pengecatan 1 m2 tembok lama interior mutu baik setara mowilex ( 1 lapis cat

No. URAIAN PEKERJAAN KODE SATUAN

1 2 3
A TENAGA
1 Pekerja L.01 OH
2 Tukang cat L.02 OH
3 Kepala tukang L.03 OH
4 Mandor L.04 OH
Jumlah
B BAHAN
Cat dasar (setara mowilex) Kg
Cat interior (setara mowilex) Kg
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

Pekerjaan Pengecatan 279


A.4.7.1.11.b Pengecatan 1 m2 tembok lama interior mutu baik setara dulux ( 1 lapis cat da

No. URAIAN PEKERJAAN KODE SATUAN

1 2 3
A TENAGA
1 Pekerja L.01 OH
2 Tukang cat L.02 OH
3 Kepala tukang L.03 OH
4 Mandor L.04 OH
Jumlah
B BAHAN
Cat dasar (setara dulux) Kg
Cat interior (setara dulux) Kg
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

A.4.7.1.11.c Pengecatan 1 m2 tembok lama exterior mutu baik setara mowilex ( 1 lapis ca

No. URAIAN PEKERJAAN KODE SATUAN

1 2 3
A TENAGA
1 Pekerja L.01 OH
2 Tukang cat L.02 OH
3 Kepala tukang L.03 OH
4 Mandor L.04 OH
Jumlah
B BAHAN
Cat dasar (setara mowilex) Kg
Cat exterior wheatercoat (setara mowilex) Kg
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

A.4.7.1.11.d Pengecatan 1 m2 tembok lama exterior mutu baik setara dulux ( 1 lapis cat d

No. URAIAN PEKERJAAN KODE SATUAN

1 2 3
A TENAGA
1 Pekerja L.01 OH
2 Tukang cat L.02 OH
3 Kepala tukang L.03 OH
4 Mandor L.04 OH

Pekerjaan Pengecatan 280


Jumlah
B BAHAN
Cat dasar (setara dulux) Kg
Cat exterior wheatercoat (setara dulux) Kg
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

A.4.7.1.16. Pengecatan 1 m2 permukaan baja dengan menie besi

No. URAIAN PEKERJAAN KODE SATUAN

1 2 3
A TENAGA
1 Pekerja L.01 OH
2 Tukang cat L.02 OH
3 Kepala tukang L.03 OH
4 Mandor L.04 OH
Jumlah
B BAHAN
Manie besi Kg
kuas (4") Bh
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

Pekerjaan Pengecatan 281


AN PEKERJAAN PENGECATAN

n cat lama
HARGA BIAYA
KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

0.15 90,000.00 13,500.00


0.003 120,000.00 360.00
13,860.00

0.05 0.000 0.00


0.00
13,860.00
2,079.00
15,939.00

bok yang pernah dicat


HARGA BIAYA
KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

0.15 90,000.00 13,500.00


0.003 120,000.00 360.00
13,860.00

0.05 15,700.000 785.00


785.00
14,645.00
2,196.75
16,841.75

n baja cara manual


HARGA BIAYA
KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

0.15 90,000.00 13,500.00

Pekerjaan Pengecatan 282


0.008 120,000.00 960.00
14,460.00

0.05 15,700.000 785.00


785.00
15,245.00
2,286.75
17,531.75

apis plamuur, 1 lapis cat dasar, 2 lapis cat penutup)


HARGA BIAYA
KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

0.07 90,000.00 6,300.00


0.009 100,000.00 900.00
0.006 110,000.00 660.00
0.003 120,000.00 360.00
8,220.00

0.2 48,000.00 9,600.00


0.15 31,500.00 4,725.00
0.17 54,000.00 9,180.00
0.26 54,000.00 14,040.00
0.01 22,500.00 225.00
0.03 22,100.00 663.00
0.2 3,000.00 600.00
39,033.00
47,253.00
7,087.95
54,340.95

Pekerjaan Pengecatan 283


apis plamuur, 1 lapis cat dasar, 3 lapis cat penutup)
HARGA BIAYA
KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

0.07 90,000.00 6,300.00


0.105 100,000.00 10,500.00
0.004 110,000.00 440.00
0.003 120,000.00 360.00
17,600.00

0.20 48,000.00 9,600.00


0.15 31,500.00 4,725.00
0.17 54,000.00 9,180.00
0.35 54,000.00 18,900.00
0.01 22,500.00 225.00
0.03 22,100.00 663.00
0.20 3,000.00 600.00
43,893.00
61,493.00
9,223.95
70,716.95

ak oil
HARGA BIAYA
KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

0.04 90,000.00 3,600.00


0.063 100,000.00 6,300.00
0.063 110,000.00 6,930.00
0.003 120,000.00 360.00
17,190.00

0.36 60,000.00 21,600.00


21,600.00
38,790.00
5,818.50
44,608.50

litur
HARGA BIAYA
KOEFISIEN

Pekerjaan Pengecatan 284


KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

0.04 90,000.00 3,600.00


0.06 100,000.00 6,000.00
0.016 110,000.00 1,760.00
0.003 120,000.00 360.00
11,720.00

0.15 50,600.00 7,590.00


0.372 50,600.00 18,823.20
2.00 3,000.00 6,000.00
32,413.20
44,133.20
6,619.98
50,753.18

t residu dan ter


HARGA BIAYA
KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

0.10 11.00 1.10


0.006 44.00 0.26
1.36

0.35 58,400.00 20,440.00


20,440.00
20,441.36
3,066.20
23,507.57

Pekerjaan Pengecatan 285


rnis
HARGA BIAYA
KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

0.16 90,000.00 14,400.00


0.16 100,000.00 16,000.00
0.016 110,000.00 1,760.00
0.003 120,000.00 360.00
32,520.00

0.15 32,000.00 4,800.00


0.05 31,500.00 1,575.00
0.10 3,000.00 300.00
6,675.00
39,195.00
5,879.25
45,074.25

plamur, 1 lapis cat dasar, 2 lapis cat penutup)


HARGA BIAYA
KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

0.02 90,000.00 1,800.00


0.063 100,000.00 6,300.00
0.0063 110,000.00 693.00
0.003 120,000.00 360.00
9,153.00

0.10 31,500.00 3,150.00


0.10 23,700.00 2,370.00
0.26 26,600.00 6,916.00
12,436.00
21,589.00
3,238.35
24,827.35

mutu baik setara mowilex ( 1lapis plamur, 1 lapis cat dasar, 2 lapis cat penutup)
HARGA BIAYA
KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

Pekerjaan Pengecatan 286


0.02 90,000.00 1,800.00
0.063 100,000.00 6,300.00
0.0063 110,000.00 693.00
0.003 120,000.00 360.00
9,153.00

0.10 31,500.00 3,150.00


0.10 52,000.00 5,200.00
0.26 70,400.00 18,304.00
26,654.00
35,807.00
5,371.05
41,178.05

mutu baik setara dulux ( 1lapis plamur, 1 lapis cat dasar, 2 lapis cat penutup)
HARGA BIAYA
KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

0.02 90,000.00 1,800.00


0.063 100,000.00 6,300.00
0.0063 110,000.00 693.00
0.003 120,000.00 360.00
9,153.00

0.10 31,500.00 3,150.00


0.10 92,600.00 9,260.00
0.26 99,500.00 25,870.00
38,280.00
47,433.00
7,114.95
54,547.95

Pekerjaan Pengecatan 287


mutu baik setara mowilex ( 1lapis plamur, 1 lapis cat dasar, 2 lapis cat penutup)
HARGA BIAYA
KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

0.02 90,000.00 1,800.00


0.063 100,000.00 6,300.00
0.0063 110,000.00 693.00
0.003 120,000.00 360.00
9,153.00

0.10 31,500.00 3,150.00


0.10 52,000.00 5,200.00
0.26 86,000.00 22,360.00
30,710.00
39,863.00
5,979.45
45,842.45

mutu baik setara dulux ( 1lapis plamur, 1 lapis cat dasar, 2 lapis cat penutup)
HARGA BIAYA
KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

0.02 90,000.00 1,800.00


0.063 100,000.00 6,300.00
0.0063 110,000.00 693.00
0.003 120,000.00 360.00
9,153.00

0.10 31,500.00 3,150.00


0.10 92,600.00 9,260.00
0.26 98,300.00 25,558.00
37,968.00
47,121.00
7,068.15
54,189.15

cat dasar, 2 lapis cat penutup)


HARGA BIAYA
KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

0.028 90,000.00 2,520.00


0.042 100,000.00 4,200.00

Pekerjaan Pengecatan 288


0.00420 110,000.00 462.00
0.003 120,000.00 360.00
7,542.00

0.12 23,700.00 2,844.00


0.18 26,600.00 4,788.00
7,632.00
15,174.00
2,276.10
17,450.10

mutu baik setara mowilex ( 1 lapis cat dasar, 2 lapis cat penutup)
HARGA BIAYA
KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

0.028 90,000.00 2,520.00


0.042 100,000.00 4,200.00
0.00420 110,000.00 462.00
0.003 120,000.00 360.00
7,542.00

0.12 52,000.00 6,240.00


0.18 70,400.00 12,672.00
18,912.00
26,454.00
3,968.10
30,422.10

Pekerjaan Pengecatan 289


mutu baik setara dulux ( 1 lapis cat dasar, 2 lapis cat penutup)
HARGA BIAYA
KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

0.028 90,000.00 2,520.00


0.042 100,000.00 4,200.00
0.00420 110,000.00 462.00
0.003 120,000.00 360.00
7,542.00

0.12 92,600.00 11,112.00


0.18 99,500.00 17,910.00
29,022.00
36,564.00
5,484.60
42,048.60

mutu baik setara mowilex ( 1 lapis cat dasar, 2 lapis cat penutup)
HARGA BIAYA
KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

0.028 90,000.00 2,520.00


0.042 100,000.00 4,200.00
0.00420 110,000.00 462.00
0.003 120,000.00 360.00
7,542.00

0.12 52,000.00 6,240.00


0.18 86,000.00 15,480.00
21,720.00
29,262.00
4,389.30
33,651.30

mutu baik setara dulux ( 1 lapis cat dasar, 2 lapis cat penutup)
HARGA BIAYA
KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

0.028 90,000.00 2,520.00


0.042 100,000.00 4,200.00
0.00420 110,000.00 462.00
0.003 120,000.00 360.00

Pekerjaan Pengecatan 290


7,542.00

0.12 92,600.00 11,112.00


0.18 98,300.00 17,694.00
28,806.00
36,348.00
5,452.20
41,800.20

an menie besi
HARGA BIAYA
KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

0.02 90,000.00 1,800.00


0.20 100,000.00 20,000.00
0.02 110,000.00 2,200.00
0.0025 120,000.00 300.00
24,300.00

0.10 48,000.00 4,800.00


0.01 22,500.00 225.00
5,025.00
29,325.00
4,398.75
33,723.75

Pekerjaan Pengecatan 291


ITEM PEMBAYARAN NO. : 7.6.(12).b
JENIS PEKERJAAN : Penyediaan Tiang Pancang Spun Pile OD500-A (K-600) Upper (With Flange) P =
SATUAN PEMBAYARAN : M1

No. URAIAN KODE

I. ASUMSI
1 Membeli Tiang Pancang jadi dari Pabrik
2 Lokasi pekerjaan : di setiap jembatan
3 Jarak rata-rata Base camp ke lokasi pekerjaan L
4 Jam kerja efektif per-hari Tk
5 Ukuran tiang pancang sesuai kebutuhan (diameter) Uk
6 Panjang Tiang Pancang p
7 Panjang Tiang Pancang Per Batang is
8 Tiang pancang diangkut menggunakan Ponton Ld2

II. URUTAN KERJA


1 Tiang pancang dikirim ke pelabuhan terdekat (di Jakarta)
atas tanggungan pabrik
2 Tiang Pancang dari pelabuhan diangkut dengan ponton
atas tanggungan kontraktor sampai ke lokasi pekerjaan
3 Memuat & menurunkan dari/ke dengan Crane

III. PEMAKAIAN BAHAN, ALAT DAN TENAGA

1. BAHAN
Tiang Pancang Spun Pile OD500-A (K-600) Upper (With Flange) (M50)

2. ALAT
2.a CRANE (E07)
Kapasitas V2
Faktor Efisiensi alat Fa
Waktu siklus
- Waktu memuat dan membongkar T1
- dan lain-lain ( termasuk mengatur dan menggeser) T2
Ts2

Kap. Prod. / jam = V x is x Fa x 60 Q2


Ts2

Koefisien Alat / M3 = 1 : Q2 (E07)

2.b Ponton + Tug Boat (E29)

Kapasitas muatan ponton (sesuai kapasitas pemancangan) V

Waktu siklus : v1
- Waktu memuat tiang pancang Ts2
- Waktu tempuh muatan ketitik pemancangan Ts1

- Lain-Lain ( bongkar dan muat) T3


Ts1
Kapasitas Produksi / Jam = V x 60 Q1
Ts1

Koefisien Alat / m3 = 1 : Q1 (E29)

2.c. ALAT BANTU


Diperlukan alat bantu untuk transportasi
- Tackle
- Tambang
- Alat kecil lainnya
EI-768a
ng Spun Pile OD500-A (K-600) Upper (With Flange) P = 12 m
URAIAN ANALISA HARGA SATUAN

KOEF. SATUAN KETERANGAN

0.3 KM
7.00 jam
500.00 mm
32.00 M
12.00 M
1.00 KM

1.0000 M'

1.00 batang
0.75 -

15.00 menit Lumpsum


15.00 menit
30.00 menit

18.00 M1/jam

0.0556 jam

3,960.00 M'

30.00 menit
120.00 menit

30.00 menit
180.00 menit
1,320.00 M'

0.0008 Jam

Lumpsum

Berlanjut ke hal. berikut.


ITEM PEMBAYARAN NO. : 7.6.(12).b
JENIS PEKERJAAN : Penyediaan Tiang Pancang Spun Pile OD500-A (K-600) Upper (With Flange) P =
SATUAN PEMBAYARAN : M1

No. URAIAN KODE

3. TENAGA
Produksi per hari (unloading) = Q2 x Tk Qt
Kebutuhan tenaga (di lokasi pekerjaan) :
- Mandor M
- Tukang Tb
- Pekerja P

Koefisien Tenaga / M3 :
- Mandor = (Tk x M) : Qt (L03)
- Tukang = (Tk x Tb) : Qt (L02)
- Pekerja = (Tk x P) : Qt (L01)

4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT


Lihat lampiran.

5. ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKEMAN ANALISA MASING-MASING HARGA
SATUAN.
Didapat Harga Satuan Pekerjaan :

Rp. 969,331.48 / M1

6. MASA PELAKSANAAN YANG DIPERLUKAN


Masa Pelaksanaan : . . . . . . . . . . . .

7. VOLUME PEKERJAAN YANG DIPERLUKAN


Volume pekerjaan : 0.00 M1
EI-768a
ng Spun Pile OD500-A (K-600) Upper (With Flange) P = 12 m
URAIAN ANALISA HARGA SATUAN
Lanjutan

KOEF. SATUAN KETERANGAN

126.00 M'

1.00 orang
2.00 orang
10.00 orang

0.0556 jam
0.1111 jam
0.5556 jam
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK :
No. PAKET KONT :
NAMA PAKET :
PROP / KAB / KOD:
ITEM PEMBAYARA: 7.6.(12).b
JENIS PEKERJAA : Penyediaan Tiang Pancang Spun Pile OD500-A (K-600) Upper (With Flange) P = 12 m
SATUAN PEMBAY : M1

PERKIRAAN
NO. KOMPONEN SATUANKUANTITAS

A. TENAGA

1. Pekerja (L01) jam 0.5556


2. Tukang (L02) jam 0.1111
3. Mandor (L03) jam 0.0556

MLAH HARGA TENAG

B. BAHAN

1. Tiang Pancang Spun Pile OD500-A (K-600) Upper (With Flange) M1 1.0000

UMLAH HARGA BAHA

C. PERALATAN
0

1. CRANE (E07) jam 0.0556


2. Ponton + Tug Boat Jam 0.0008
3. Alat Bantu jam 1.0000

JUMLAH HARGA PERALA


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )
E. OVERHEAD & PROFIT 15.0 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
EI-768a

FORMULIR STANDAR UNTUK


N ANALISA MASING-MASING HARGA SATUAN

PERKIRAAN VOL. P: 0.00


TOTAL HARGA (Rp.): 0.00
% THD. BIAYA PRO : 0.00

HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

12,857.14 7,142.86
14,285.71 1,587.30
17,142.86 952.38

MLAH HARGA TENAGA 9,682.54

792,000.00 792,000.00

UMLAH HARGA BAHAN 792,000.00

637,499.63 35,416.65
1,053,034.16 797.75
5,000.00 5,000.00

JUMLAH HARGA PERALATAN 41,214.40


842,896.94
126,434.54
969,331.48

ponen untuk menyelesaikan satu satuan pekerjaan dari nomor


ITEM PEMBAYARAN NO. : 7.6.(18).b
JENIS PEKERJAAN : Pemancangan Tiang Pancang Spun Pile OD500-A
SATUAN PEMBAYARAN : M1

No. URAIAN KODE

I. ASUMSI
1 Menggunakan alat (cara mekanik)
2 Lokasi pekerjaan : di lokasi
3 Jam kerja efektif per-hari Tk
4 Panjang Tiang p
5 Ukuran diameter Tiang
6 Berat per-meter tiang b

II. URUTAN KERJA


1 Material Tiang pancang yang telah siap ada dekat
lokasi pemancangan
2 Penyambungan dilakukan pada saat pemancangan

III. PEMAKAIAN BAHAN, ALAT DAN TENAGA

1. BAHAN
Plat baja (sbg perkuatan sambungan tiang)
kawat las secukupnya.

2. ALAT

2.a Crane on Track 35 Ton (E31)


Kapasitas V1
Faktor Efisiensi alat Fa
Waktu siklus
- Waktu penggeseran dan penyetelan tiang T1
- Waktu pemancangan T2
- Waktu penjambungan tiang T3
Ts1

Kap. Prod. / jam = V1 x p x Fa x 60 Q1


Ts1
Koefisien Alat / m' = 1 : Q1 (E31)

2.b PILE DRIVER HAMMER (E30)


Kapasitas V2
Faktor Efisiensi alat Fa
Waktu siklus
- Waktu pemancangan Ts2

Kap. Prod. / jam = V2 x p x Fa x 60 Q2


Ts2
Koefisien Alat / m' = 1 : Q2 (E07)

2.c Ponton + Tug Boat


Kapasitas muatan ponton (sesuai kapasitas pemancangan) V
Kapasitas produksi pemancangan/jam Qa
Waktu siklus : v1
- Waktu memuat tiang pancang Ts2
- Waktu tempuh muatan ketitik pemancangan Ts1
- Waktu tunggu pemancangan V x 60 T1
Qa
- Lain-Lain ( bongkar dan muat) T3
Ts1

Kapasitas Produksi / Jam = V x 60 Q1


Ts1

Koefisien Alat / m3 = 1 : Q1 (E29)

2.b. ALAT BANTU


Diperlukan alat bantu kecil selama penyetelan dan
penyambungan
- Rantai/sling baja, dan Lain-Lain
F.04.e

URAIAN ANALISA HARGA SATUAN

KOEF. SATUAN KETERANGAN

7.00 jam
37.00 M
500.00 mm
290.00 kg

7.92 kg
0.12 kg

1.00 Titik
0.75 -

60.00 menit
120.00 menit
60.00 menit
240.00 menit

6.94 M1/jam

0.1441 Jam

1.00 Titik
0.75 -

240.00 menit

6.94 M1/jam

0.1441 Jam
3,960.00 M'
6.94 M'

60.00 menit
15.00 menit
34,248.65 menit

10.00 menit
34,258.65 menit

6.94 M'

0.1442 Jam

Lumpsum

Berlanjut ke hal. berikut.


ITEM PEMBAYARAN NO. : 7.6.(18).b
JENIS PEKERJAAN : Pemancangan Tiang Pancang Spun Pile OD500-A
SATUAN PEMBAYARAN : M1

No. URAIAN KODE

2.c. GENSET (E12)


Diasumsi panjang tiang p

Koefisien Alat / kg = 1 : ( p x b : Ts3 ) (E12)

2.d. WELDING SET (E32)


Kapasitas V3
Faktor Efisiensi alat Fa
Diameter tiang pancang r
Panjang Pengelasan per Sambungan = 2 x p x ( r / 2 ) Nw
Waktu siklus
- Waktu Penyambungan tiang Ts3

Kap. Prod. / jam = 3 x V3 x Nw x Fa x 60 Q2


Ts3
Koefisien Alat / m' = 1 : Q2 (E07)

3. TENAGA
Produksi Tiang dalam 1 hari = Tk x Q1 Qt
Kebutuhan tenaga tambahan di lokasi :
- Mandor M
- Tukang Tb
- Pekerja P

Koefisien Tenaga / M1 :
- Mandor = ( Tk x M ) : Qt (L03)
- Tukang = ( Tk x Tb ) : Qt (L02)
- Pekerja = ( Tk x P ) : Qt (L01)

4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT


Lihat lampiran.

5. ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKEMAN ANALISA MASING-MASING HARGA
SATUAN.
Didapat Harga Satuan Pekerjaan :

Rp. 452,627.53 / M'


6. MASA PELAKSANAAN YANG DIPERLUKAN
Masa Pelaksanaan : . . . . . . . . . . . .

7. VOLUME PEKERJAAN YANG DIPERLUKAN


Volume pekerjaan : 0.00 M'
F.04.e

URAIAN ANALISA HARGA SATUAN


Lanjutan

KOEF. SATUAN KETERANGAN

32.00 M

0.0028 Jam

1.00 Titik
0.75 -
50.00 Cm
157.14 Cm

60.00 menit

353.57 M1/jam

0.0028 Jam

48.56 M'

1.00 orang
1.00 orang
6.00 orang

0.1441 jam
0.1441 jam
0.8649 jam
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK :
No. PAKET KONT :
NAMA PAKET :
PROP / KAB / KOD:
ITEM PEMBAYARA: 7.6.(18).b
JENIS PEKERJAA : Pemancangan Tiang Pancang Spun Pile OD500-A
SATUAN PEMBAY : M1

PERKIRAAN
NO. KOMPONEN SATUANKUANTITAS

A. TENAGA

1. Pekerja (L01) jam 0.8649


2. Tukang (L02) jam 0.1441
3. Mandor (L03) jam 0.1441

MLAH HARGA TENAG

B. BAHAN

1. Plat baja (sbg perkuatan sambungan tiang) Kg 7.9200


2. kawat las secukupnya. Kg 0.1176

UMLAH HARGA BAHA

C. PERALATAN

1. Crane on Track (E31) jam 0.1441


2. Pile Driver (E30) jam 0.1441
3. Genset jam 0.0028
4. Welding set jam 0.0028
5. Ponton + Tug Boat jam 0.1442
6. Alat Bantu Ls 1.0000

H HARGA PERALATA

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )


E. OVERHEAD & PROFIT 15.0 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau u
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dar
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk
yang dibayar dari kontrak) dan biaya-biaya lainnya.
F.04.e

FORMULIR STANDAR UNTUK


N ANALISA MASING-MASING HARGA SATUAN

PERKIRAAN VOL. P: 0.00


TOTAL HARGA (Rp.): 0.00
% THD. BIAYA PRO : 0.00

HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

12,857.14 11,119.69
14,285.71 2,059.20
17,142.86 2,471.04

MLAH HARGA TENAGA 15,649.94

11,000.00 87,120.00
28,500.00 3,352.22

UMLAH HARGA BAHAN 90,472.22

613,266.11 88,398.72
282,809.71 40,765.36
412,104.20 1,165.55
107,608.94 304.35
1,053,034.16 151,833.03
5,000.00 5,000.00

H HARGA PERALATAN 287,467.01

393,589.16
59,038.37
452,627.53
operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran

iap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor

ermasuk bahan bakar, bahan habis dipakai dan operator.


uaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
ITEM PEMBAYARAN NO. : 7.6.(18).b
JENIS PEKERJAAN : Pemancangan Tiang Pancang Spun Pile OD500-A (miring )
SATUAN PEMBAYARAN : M1

No. URAIAN KODE

I. ASUMSI
1 Menggunakan alat (cara mekanik)
2 Lokasi pekerjaan : di lokasi
3 Jam kerja efektif per-hari Tk
4 Panjang Tiang p
5 Ukuran diameter Tiang
6 Berat per-meter tiang b

II. URUTAN KERJA


1 Material Tiang pancang yang telah siap ada dekat
lokasi pemancangan
2 Penyambungan dilakukan pada saat pemancangan

III. PEMAKAIAN BAHAN, ALAT DAN TENAGA

1. BAHAN
Plat baja (sbg perkuatan sambungan tiang)
kawat las secukupnya.

2. ALAT

2.a Crane on Track 35 Ton (E31)


Kapasitas V1
Faktor Efisiensi alat Fa
Waktu siklus
- Waktu penggeseran dan penyetelan tiang T1
- Waktu pemancangan T2
- Waktu penjambungan tiang T3
Ts1

Kap. Prod. / jam = V1 x p x Fa x 60 Q1


Ts1
Koefisien Alat / m' = 1 : Q1 (E31)

2.b PILE DRIVER HAMMER (E30)


Kapasitas V2
Faktor Efisiensi alat Fa
Waktu siklus
- Waktu pemancangan Ts2

Kap. Prod. / jam = V2 x p x Fa x 60 Q2


Ts2
Koefisien Alat / m' = 1 : Q2 (E07)

2.c Ponton + Tug Boat


Kapasitas muatan ponton (sesuai kapasitas pemancangan) V
Kapasitas produksi pemancangan/jam Qa
Waktu siklus : v1
- Waktu memuat tiang pancang Ts2
- Waktu tempuh muatan ketitik pemancangan Ts1
- Waktu tunggu pemancangan V x 60 T1
Qa
- Lain-Lain ( bongkar dan muat) T3
Ts1

Kapasitas Produksi / Jam = V x 60 Q1


Ts1

Koefisien Alat / m3 = 1 : Q1 (E29)

2.b. ALAT BANTU


Diperlukan alat bantu kecil selama penyetelan dan
penyambungan
- Rantai/sling baja, dan Lain-Lain
ITEM PEMBAYARAN NO. : 7.6.(18).b
JENIS PEKERJAAN : Pemancangan Tiang Pancang Spun Pile OD500-A (miring )
SATUAN PEMBAYARAN : M1

No. URAIAN KODE

2.c. GENSET (E12)


Diasumsi panjang tiang p

Koefisien Alat / kg = 1 : ( p x b : Ts3 ) (E12)

2.d. WELDING SET (E32)


Kapasitas V3
Faktor Efisiensi alat Fa
Diameter tiang pancang r
Panjang Pengelasan per Sambungan = 2 x p x ( r / 2 ) Nw
Waktu siklus
- Waktu Penyambungan tiang Ts3

Kap. Prod. / jam = 2 x V3 x Nw x Fa x 60 Q2


Ts3
Koefisien Alat / m' = 1 : Q2 (E07)

3. TENAGA
Produksi Tiang dalam 1 hari = Tk x Q1 Qt
Kebutuhan tenaga tambahan di lokasi :
- Mandor M
- Tukang Tb
- Pekerja P

Koefisien Tenaga / M1 :
- Mandor = ( Tk x M ) : Qt (L03)
- Tukang = ( Tk x Tb ) : Qt (L02)
- Pekerja = ( Tk x P ) : Qt (L01)

4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT


Lihat lampiran.

5. ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKEMAN ANALISA MASING-MASING HARGA
SATUAN.
Didapat Harga Satuan Pekerjaan :

Rp. 590,894.06 / M'

6. MASA PELAKSANAAN YANG DIPERLUKAN


Masa Pelaksanaan : . . . . . . . . . . . .

7. VOLUME PEKERJAAN YANG DIPERLUKAN


Volume pekerjaan : 0.00 M'
F.04.f

URAIAN ANALISA HARGA SATUAN

KOEF. SATUAN KETERANGAN

7.00 jam
33.00 M
500.00 mm
290.00 kg

7.92 kg
0.13 kg

1.00 Titik
0.75 -

60.00 menit
180.00 menit
60.00 menit
300.00 menit

4.95 M1/jam

0.2020 Jam

1.00 Titik
0.75 -

300.00 menit

4.95 M1/jam

0.2020 Jam
3,960.00 M'
4.95 M'

60.00 menit
15.00 menit
48,000.00 menit

10.00 menit
48,010.00 menit

4.95 M'

0.2021 Jam

Lumpsum

Berlanjut ke hal. berikut.


F.04.f

URAIAN ANALISA HARGA SATUAN


Lanjutan

KOEF. SATUAN KETERANGAN

15.00 M

0.0042 Jam

1.00 Titik
0.75 -
50.00 Cm
157.14 Cm

60.00 menit

235.71 M1/jam

0.0042 Jam

34.65 M'

1.00 orang
1.00 orang
6.00 orang

0.2020 jam
0.2020 jam
1.2121 jam
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK :
No. PAKET KONT :
NAMA PAKET :
PROP / KAB / KOD:
ITEM PEMBAYARA: 7.6.(18).b
JENIS PEKERJAA : Pemancangan Tiang Pancang Spun Pile OD500-A (miring )
SATUAN PEMBAY : M1

PERKIRAAN
NO. KOMPONEN SATUANKUANTITAS

A. TENAGA

1. Pekerja (L01) jam 1.2121


2. Tukang (L02) jam 0.2020
3. Mandor (L03) jam 0.2020

MLAH HARGA TENAG

B. BAHAN

1. Plat baja (sbg perkuatan sambungan tiang) Kg 7.9200


2. kawat las secukupnya. Kg 0.1319

UMLAH HARGA BAHA

C. PERALATAN

1. Crane on Track (E31) jam 0.2020


2. Pile Driver (E30) jam 0.2020
3. Genset jam 0.0042
4. Welding set jam 0.0042
5. Ponton + Tug Boat jam 0.2021
6. Alat Bantu Ls 1.0000

H HARGA PERALATA

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )


E. OVERHEAD & PROFIT 15.0 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau u
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dar
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk
yang dibayar dari kontrak) dan biaya-biaya lainnya.
F.04.f

FORMULIR STANDAR UNTUK


N ANALISA MASING-MASING HARGA SATUAN

PERKIRAAN VOL. P: 0.00


TOTAL HARGA (Rp.): 0.00
% THD. BIAYA PRO : 0.00

HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

12,857.14 15,584.42
14,285.71 2,886.00
17,142.86 3,463.20

MLAH HARGA TENAGA 21,933.62

11,000.00 87,120.00
28,500.00 3,758.55

UMLAH HARGA BAHAN 90,878.55

613,266.11 123,892.14
282,809.71 57,133.27
412,104.20 1,748.32
107,608.94 456.52
1,053,034.16 212,778.49
5,000.00 5,000.00

H HARGA PERALATAN 401,008.76

513,820.92
77,073.14
590,894.06
operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran

iap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor

ermasuk bahan bakar, bahan habis dipakai dan operator.


uaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
ITEM PEMBAYARAN NO. :
JENIS PEKERJAAN : Penyediaan Tiang Pancang Baja Diameter300 mm tebal 8 mm
SATUAN PEMBAYARAN :

No. URAIAN KODE

I. ASUMSI
1 Membeli Tiang Pancang jadi dari Pabrik
2 Lokasi pekerjaan : di setiap jembatan
3 Jarak rata-rata Base camp ke lokasi pekerjaan L
4 Jam kerja efektif per-hari Tk
5 Ukuran tiang pancang sesuai kebutuhan (diameter) Uk
6 Panjang Tiang Pancang p
7 Panjang Tiang Pancang Per Batang is
8 Tiang pancang diangkut menggunakan Ponton Ld2

II. URUTAN KERJA


1 Tiang pancang dikirim ke pelabuhan terdekat (di Jakarta)
atas tanggungan pabrik
2 Tiang Pancang dari pelabuhan diangkut dengan ponton
atas tanggungan kontraktor sampai ke lokasi pekerjaan
3 Memuat & menurunkan dari/ke dengan Crane

III. PEMAKAIAN BAHAN, ALAT DAN TENAGA

1. BAHAN
Tiang Pancang Baja (M50)

2. ALAT
2.a CRANE (E07)
Kapasitas V2
Faktor Efisiensi alat Fa
Waktu siklus
- Waktu memuat dan membongkar T1
- dan lain-lain ( termasuk mengatur dan menggeser) T2
Ts2

Kap. Prod. / jam = V x is x Fa x 60 Q2


Ts2

Koefisien Alat / M3 = 1 : Q2 (E07)

2.b Ponton + Tug Boat (E29)

Kapasitas muatan ponton (sesuai kapasitas pemancangan) V

Waktu siklus : v1
- Waktu memuat tiang pancang Ts2
- Waktu tempuh muatan ketitik pemancangan Ts1

- Lain-Lain ( bongkar dan muat) T3


Ts1
Kapasitas Produksi / Jam = V x 60 Q1
Ts1

Koefisien Alat / m3 = 1 : Q1 (E29)

2.c. ALAT BANTU


Diperlukan alat bantu untuk transportasi
- Tackle
- Tambang
- Alat kecil lainnya
ITEM PEMBAYARAN NO. :
JENIS PEKERJAAN : Penyediaan Tiang Pancang Baja Diameter300 mm tebal 8 mm
SATUAN PEMBAYARAN :

No. URAIAN KODE

3. TENAGA
Produksi per hari (unloading) = Q2 x Tk Qt
Kebutuhan tenaga (di lokasi pekerjaan) :
- Mandor M
- Tukang Tb
- Pekerja P

Koefisien Tenaga / M3 :
- Mandor = (Tk x M) : Qt (L03)
- Tukang = (Tk x Tb) : Qt (L02)
- Pekerja = (Tk x P) : Qt (L01)

4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT


Lihat lampiran.

5. ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKEMAN ANALISA MASING-MASING HARGA
SATUAN.
Didapat Harga Satuan Pekerjaan :

Rp. Err:509 / M1

6. MASA PELAKSANAAN YANG DIPERLUKAN


Masa Pelaksanaan : . . . . . . . . . . . .

7. VOLUME PEKERJAAN YANG DIPERLUKAN


Volume pekerjaan : 0.00 M1
ITEM PEMBAYARAN NO. :
JENIS PEKERJAAN : Pemancangan Tiang Pancang Baja Diameter 300 mm tebal 8 mm
SATUAN PEMBAYARAN :

No. URAIAN KODE

I. ASUMSI
1 Menggunakan alat (cara mekanik)
2 Lokasi pekerjaan : di lokasi
3 Jam kerja efektif per-hari Tk
4 Panjang Tiang p
5 Ukuran diameter Tiang
6 Berat per-meter tiang b

II. URUTAN KERJA


1 Material Tiang pancang yang telah siap ada dekat
lokasi pemancangan
2 Penyambungan dilakukan pada saat pemancangan

III. PEMAKAIAN BAHAN, ALAT DAN TENAGA

1. BAHAN
Plat baja (sbg perkuatan sambungan tiang)
kawat las secukupnya.

2. ALAT

2.a Crane on Track 35 Ton (E31)


Kapasitas V1
Faktor Efisiensi alat Fa
Waktu siklus
- Waktu penggeseran dan penyetelan tiang T1
- Waktu pemancangan T2
- Waktu penjambungan tiang T3
Ts1

Kap. Prod. / jam = V1 x p x Fa x 60 Q1


Ts1
Koefisien Alat / m' = 1 : Q1 (E31)

2.b PILE DRIVER HAMMER (E30)


Kapasitas V2
Faktor Efisiensi alat Fa
Waktu siklus
- Waktu pemancangan Ts2

Kap. Prod. / jam = V2 x p x Fa x 60 Q2


Ts2
Koefisien Alat / m' = 1 : Q2 (E07)
2.c Ponton + Tug Boat
Kapasitas muatan ponton (sesuai kapasitas pemancangan) V
Kapasitas produksi pemancangan/jam Qa
Waktu siklus : v1
- Waktu memuat tiang pancang Ts2
- Waktu tempuh muatan ketitik pemancangan Ts1
- Waktu tunggu pemancangan V x 60 T1
Qa
- Lain-Lain ( bongkar dan muat) T3
Ts1

Kapasitas Produksi / Jam = V x 60 Q1


Ts1

Koefisien Alat / m3 = 1 : Q1 (E29)

2.b. ALAT BANTU


Diperlukan alat bantu kecil selama penyetelan dan
penyambungan
- Rantai/sling baja, dan Lain-Lain
Analisa EI-766b

URAIAN ANALISA HARGA SATUAN

KOEF. SATUAN KETERANGAN

0.3 KM
7.00 jam
300.00 mm
18.00 M
6.00 M
232.00 KM

Err:509 Kg

1.00 batang
0.75 -

15.00 menit Lumpsum


15.00 menit
30.00 menit

9.00 M1/jam

0.1111 jam

396.00 M'

30.00 menit
5,760.00 menit

11.82 menit
5,801.82 menit
4.10 M'

0.2442 Jam

Lumpsum

Berlanjut ke hal. berikut.


Analisa EI-766b

URAIAN ANALISA HARGA SATUAN


Lanjutan

KOEF. SATUAN KETERANGAN

63.00 M'

1.00 orang
2.00 orang
10.00 orang

0.1111 jam
0.2222 jam
1.1111 jam
Analisa EI-766b

URAIAN ANALISA HARGA SATUAN

KOEF. SATUAN KETERANGAN

7.00 jam
18.00 M
300.00 mm
Err:509 kg

7.92 kg
0.24 kg

1.00 Titik
0.75 -

60.00 menit
120.00 menit
60.00 menit
240.00 menit

3.38 M1/jam

0.2963 Jam

1.00 Titik
0.75 -

240.00 menit

3.38 M1/jam

0.2963 Jam
396.00 M'
3.38 M'

60.00 menit
15.00 menit
7,040.00 menit

10.00 menit
7,050.00 menit

3.37 M'

0.2967 Jam

Lumpsum

Berlanjut ke hal. berikut.


FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK :
No. PAKET KONT :
NAMA PAKET :
PROP / KAB / KOD:
ITEM PEMBAYARA:
JENIS PEKERJAA : Penyediaan Tiang Pancang Baja Diameter300 mm tebal 8 mm
SATUAN PEMBAY :

PERKIRAAN
NO. KOMPONEN SATUANKUANTITAS

A. TENAGA

1. Pekerja (L01) jam 1.1111


2. Tukang (L02) jam 0.2222
3. Mandor (L03) jam 0.1111

MLAH HARGA TENAG

B. BAHAN

1. Tiang Pancang Baja M1 Err:509

UMLAH HARGA BAHA

C. PERALATAN

1. CRANE (E07) jam 0.1111


2. Ponton + Tug Boat Jam 0.2442
3. Alat Bantu jam 1.0000

JUMLAH HARGA PERALA


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )
E. OVERHEAD & PROFIT 15.0 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Analisa EI-766b

FORMULIR STANDAR UNTUK


N ANALISA MASING-MASING HARGA SATUAN

PERKIRAAN VOL. P: 0.00


TOTAL HARGA (Rp.): 0.00
% THD. BIAYA PRO : 0.00

HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

12,857.14 14,285.71
14,285.71 3,174.60
17,142.86 1,904.76

MLAH HARGA TENAGA 19,365.08

792,000.00 Err:509

UMLAH HARGA BAHAN Err:509

637,499.63 70,833.29
1,053,034.16 257,134.46
5,000.00 5,000.00

JUMLAH HARGA PERALATAN 332,967.75


Err:509
Err:509
Err:509

ponen untuk menyelesaikan satu satuan pekerjaan dari nomor


ITEM PEMBAYARAN NO. :
JENIS PEKERJAAN : Pemancangan Tiang Pancang Baja Diameter 300 mm tebal 8 mm
SATUAN PEMBAYARAN :

No. URAIAN KODE

2.c. GENSET (E12)


Diasumsi panjang tiang p

Koefisien Alat / kg = 1 : ( p x b : Ts3 ) (E12)

2.d. WELDING SET (E32)


Kapasitas V3
Faktor Efisiensi alat Fa
Diameter tiang pancang r
Panjang Pengelasan per Sambungan = 2 x p x ( r / 2 ) Nw
Waktu siklus
- Waktu Penyambungan tiang Ts3

Kap. Prod. / jam = 2 x V3 x Nw x Fa x 60 Q2


Ts3
Koefisien Alat / m' = 1 : Q2 (E07)

3. TENAGA
Produksi Tiang dalam 1 hari = Tk x Q1 Qt
Kebutuhan tenaga tambahan di lokasi :
- Mandor M
- Tukang Tb
- Pekerja P

Koefisien Tenaga / M1 :
- Mandor = ( Tk x M ) : Qt (L03)
- Tukang = ( Tk x Tb ) : Qt (L02)
- Pekerja = ( Tk x P ) : Qt (L01)

4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT


Lihat lampiran.

5. ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKEMAN ANALISA MASING-MASING HARGA
SATUAN.
Didapat Harga Satuan Pekerjaan :

Rp. 819,733.78 / M'


6. MASA PELAKSANAAN YANG DIPERLUKAN
Masa Pelaksanaan : . . . . . . . . . . . .

7. VOLUME PEKERJAAN YANG DIPERLUKAN


Volume pekerjaan : 0.00 M'
ITEM PEMBAYARAN NO. :
JENIS PEKERJAAN : Pemancangan Tiang Pancang Baja Diameter 300 mm tebal 8 mm ( Miring )
SATUAN PEMBAYARAN :

No. URAIAN KODE

I. ASUMSI
1 Menggunakan alat (cara mekanik)
2 Lokasi pekerjaan : di lokasi
3 Jam kerja efektif per-hari Tk
4 Panjang Tiang p
5 Ukuran diameter Tiang
6 Berat per-meter tiang b

II. URUTAN KERJA


1 Material Tiang pancang yang telah siap ada dekat
lokasi pemancangan
2 Penyambungan dilakukan pada saat pemancangan

III. PEMAKAIAN BAHAN, ALAT DAN TENAGA

1. BAHAN
Plat baja (sbg perkuatan sambungan tiang)
kawat las secukupnya.

2. ALAT

2.a Crane on Track 35 Ton (E31)


Kapasitas V1
Faktor Efisiensi alat Fa
Waktu siklus
- Waktu penggeseran dan penyetelan tiang T1
- Waktu pemancangan T2
- Waktu penjambungan tiang T3
Ts1

Kap. Prod. / jam = V1 x p x Fa x 60 Q1


Ts1
Koefisien Alat / m' = 1 : Q1 (E31)

2.b PILE DRIVER HAMMER (E30)


Kapasitas V2
Faktor Efisiensi alat Fa
Waktu siklus
- Waktu pemancangan Ts2

Kap. Prod. / jam = V2 x p x Fa x 60 Q2


Ts2
Koefisien Alat / m' = 1 : Q2 (E07)
2.c Ponton + Tug Boat
Kapasitas muatan ponton (sesuai kapasitas pemancangan) V
Kapasitas produksi pemancangan/jam Qa
Waktu siklus : v1
- Waktu memuat tiang pancang Ts2
- Waktu tempuh muatan ketitik pemancangan Ts1
- Waktu tunggu pemancangan V x 60 T1
Qa
- Lain-Lain ( bongkar dan muat) T3
Ts1

Kapasitas Produksi / Jam = V x 60 Q1


Ts1

Koefisien Alat / m3 = 1 : Q1 (E29)

2.b. ALAT BANTU


Diperlukan alat bantu kecil selama penyetelan dan
penyambungan
- Rantai/sling baja, dan Lain-Lain
Analisa EI-766b

URAIAN ANALISA HARGA SATUAN


Lanjutan

KOEF. SATUAN KETERANGAN

18.00 M

0.0071 Jam

1.00 Titik
0.75 -
30.00 Cm
94.29 Cm

60.00 menit

141.43 M1/jam

0.0071 Jam

23.63 M'

1.00 orang
1.00 orang
6.00 orang

0.2963 jam
0.2963 jam
1.7778 jam
Analisa EI-766b
cang Baja Diameter 300 mm tebal 8 mm ( Miring )
URAIAN ANALISA HARGA SATUAN

KOEF. SATUAN KETERANGAN

7.00 jam
18.00 M
300.00 mm
Err:509 kg

7.92 kg
0.24 kg

1.00 Titik
0.75 -

60.00 menit
180.00 menit
60.00 menit
300.00 menit

2.70 M1/jam

0.3704 Jam

1.00 Titik
0.75 -

300.00 menit

2.70 M1/jam

0.3704 Jam
396.00 M'
2.70 M'

60.00 menit
15.00 menit
8,800.00 menit

10.00 menit
8,810.00 menit

2.70 M'

0.3708 Jam

Lumpsum

Berlanjut ke hal. berikut.


FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK :
No. PAKET KONT :
NAMA PAKET :
PROP / KAB / KOD:
ITEM PEMBAYARA:
JENIS PEKERJAA : Pemancangan Tiang Pancang Baja Diameter 300 mm tebal 8 mm
SATUAN PEMBAY :

PERKIRAAN
NO. KOMPONEN SATUANKUANTITAS

A. TENAGA

1. Pekerja (L01) jam 1.7778


2. Tukang (L02) jam 0.2963
3. Mandor (L03) jam 0.2963

MLAH HARGA TENAG

B. BAHAN

1. Plat baja (sbg perkuatan sambungan tiang) Kg 7.9200


2. kawat las secukupnya. Kg 0.2418

UMLAH HARGA BAHA

C. PERALATAN

1. Crane on Track (E31) jam 0.2963


2. Pile Driver (E30) jam 0.2963
3. Genset jam 0.0071
4. Welding set jam 0.0071
5. Ponton + Tug Boat jam 0.2967
6. Alat Bantu Ls 1.0000

H HARGA PERALATA

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )


E. OVERHEAD & PROFIT 15.0 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau u
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dar
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk
yang dibayar dari kontrak) dan biaya-biaya lainnya.
FORMULIR STANDAR UNTUK
N ANALISA MASING-MASING HARGA SATUAN

PERKIRAAN VOL. P: 0.00


TOTAL HARGA (Rp.): 0.00
% THD. BIAYA PRO : 0.00

HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

12,857.14 22,857.14
14,285.71 4,232.80
17,142.86 5,079.37

MLAH HARGA TENAGA 32,169.31

11,000.00 87,120.00
28,500.00 6,890.67

UMLAH HARGA BAHAN 94,010.67

613,266.11 181,708.48
282,809.71 83,795.47
412,104.20 2,913.87
107,608.94 760.87
1,053,034.16 312,453.32
5,000.00 5,000.00

H HARGA PERALATAN 586,632.00

712,811.98
106,921.80
819,733.78
operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
iap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor

ermasuk bahan bakar, bahan habis dipakai dan operator.


uaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
ITEM PEMBAYARAN NO. :
JENIS PEKERJAAN : Pemancangan Tiang Pancang Baja Diameter 300 mm tebal 8 mm ( Miring )
SATUAN PEMBAYARAN :

No. URAIAN KODE

2.c. GENSET (E12)


Diasumsi panjang tiang p

Koefisien Alat / kg = 1 : ( p x b : Ts3 ) (E12)

2.d. WELDING SET (E32)


Kapasitas V3
Faktor Efisiensi alat Fa
Diameter tiang pancang r
Panjang Pengelasan per Sambungan = 2 x p x ( r / 2 ) Nw
Waktu siklus
- Waktu Penyambungan tiang Ts3

Kap. Prod. / jam = 2 x V3 x Nw x Fa x 60 Q2


Ts3
Koefisien Alat / m' = 1 : Q2 (E07)

3. TENAGA
Produksi Tiang dalam 1 hari = Tk x Q1 Qt
Kebutuhan tenaga tambahan di lokasi :
- Mandor M
- Tukang Tb
- Pekerja P

Koefisien Tenaga / M1 :
- Mandor = ( Tk x M ) : Qt (L03)
- Tukang = ( Tk x Tb ) : Qt (L02)
- Pekerja = ( Tk x P ) : Qt (L01)

4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT


Lihat lampiran.

5. ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKEMAN ANALISA MASING-MASING HARGA
SATUAN.
Didapat Harga Satuan Pekerjaan :

Rp. 995,017.75 / M'


6. MASA PELAKSANAAN YANG DIPERLUKAN
Masa Pelaksanaan : . . . . . . . . . . . .

7. VOLUME PEKERJAAN YANG DIPERLUKAN


Volume pekerjaan : 0.00 M'
Analisa EI-766b
cang Baja Diameter 300 mm tebal 8 mm ( Miring )
URAIAN ANALISA HARGA SATUAN
Lanjutan

KOEF. SATUAN KETERANGAN

15.00 M

0.0071 Jam

1.00 Titik
0.75 -
30.00 Cm
94.29 Cm

60.00 menit

141.43 M1/jam

0.0071 Jam

18.90 M'

1.00 orang
1.00 orang
6.00 orang

0.3704 jam
0.3704 jam
2.2222 jam
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK :
No. PAKET KONT :
NAMA PAKET :
PROP / KAB / KOD:
ITEM PEMBAYARA:
JENIS PEKERJAA : Pemancangan Tiang Pancang Baja Diameter 300 mm tebal 8 mm ( Miring )
SATUAN PEMBAY :

PERKIRAAN
NO. KOMPONEN SATUANKUANTITAS

A. TENAGA

1. Pekerja (L01) jam 2.2222


2. Tukang (L02) jam 0.3704
3. Mandor (L03) jam 0.3704

MLAH HARGA TENAG

B. BAHAN

1. Plat baja (sbg perkuatan sambungan tiang) Kg 7.9200


2. kawat las secukupnya. Kg 0.2418

UMLAH HARGA BAHA

C. PERALATAN

1. Crane on Track (E31) jam 0.3704


2. Pile Driver (E30) jam 0.3704
3. Genset jam 0.0071
4. Welding set jam 0.0071
5. Ponton + Tug Boat jam 0.3708
6. Alat Bantu Ls 1.0000

H HARGA PERALATA

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )


E. OVERHEAD & PROFIT 15.0 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau u
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dar
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk
yang dibayar dari kontrak) dan biaya-biaya lainnya.
0

FORMULIR STANDAR UNTUK


N ANALISA MASING-MASING HARGA SATUAN

PERKIRAAN VOL. P: 0.00


TOTAL HARGA (Rp.): 0.00
% THD. BIAYA PRO : 0.00

HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

12,857.14 28,571.43
14,285.71 5,291.01
17,142.86 6,349.21

MLAH HARGA TENAGA 40,211.64

11,000.00 87,120.00
28,500.00 6,890.67

UMLAH HARGA BAHAN 94,010.67

613,266.11 227,135.60
282,809.71 104,744.34
412,104.20 2,913.87
107,608.94 760.87
1,053,034.16 390,455.85
5,000.00 5,000.00

H HARGA PERALATAN 731,010.52

865,232.83
129,784.92
995,017.75
operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran

iap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor

ermasuk bahan bakar, bahan habis dipakai dan operator.


uaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
ITEM PEMBAYARAN NO. : 7.6.(12).b
JENIS PEKERJAAN : Penyediaan Tiang Pancang Spun Pile OD500-A (K-600) Bottom (Pointed) P = 10
SATUAN PEMBAYARAN : M1

No. URAIAN KODE

I. ASUMSI
1 Membeli Tiang Pancang jadi dari Pabrik
2 Lokasi pekerjaan : di setiap jembatan
3 Jarak rata-rata Base camp ke lokasi pekerjaan L
4 Jam kerja efektif per-hari Tk
5 Ukuran tiang pancang sesuai kebutuhan (diameter) Uk
6 Panjang Tiang Pancang p
7 Panjang Tiang Pancang Per Batang is
8 Tiang pancang diangkut menggunakan Ponton Ld2

II. URUTAN KERJA


1 Tiang pancang dikirim ke pelabuhan terdekat (di Jakarta)
atas tanggungan pabrik
2 Tiang Pancang dari pelabuhan diangkut dengan ponton
atas tanggungan kontraktor sampai ke lokasi pekerjaan
3 Memuat & menurunkan dari/ke dengan Crane

III. PEMAKAIAN BAHAN, ALAT DAN TENAGA

1. BAHAN
Tiang Pancang Spun Pile OD500-A (K-600) Upper (With Flange) (M50)

2. ALAT
2.a CRANE (E07)
Kapasitas V2
Faktor Efisiensi alat Fa
Waktu siklus
- Waktu memuat dan membongkar T1
- dan lain-lain ( termasuk mengatur dan menggeser) T2
Ts2

Kap. Prod. / jam = V x is x Fa x 60 Q2


Ts2

Koefisien Alat / M3 = 1 : Q2 (E07)

2.b Ponton + Tug Boat (E29)

Kapasitas muatan ponton (sesuai kapasitas pemancangan) V

Waktu siklus : v1
- Waktu memuat tiang pancang Ts2
- Waktu tempuh muatan ketitik pemancangan Ts1

- Lain-Lain ( bongkar dan muat) T3


Ts1
Kapasitas Produksi / Jam = V x 60 Q1
Ts1

Koefisien Alat / m3 = 1 : Q1 (E29)

2.c. ALAT BANTU


Diperlukan alat bantu untuk transportasi
- Tackle
- Tambang
- Alat kecil lainnya

ITEM PEMBAYARAN NO. : 7.6.(12).b


JENIS PEKERJAAN : Penyediaan Tiang Pancang Spun Pile OD500-A (K-600) Bottom (Pointed) P = 10
SATUAN PEMBAYARAN : M1

No. URAIAN KODE

3. TENAGA
Produksi per hari (unloading) = Q2 x Tk Qt
Kebutuhan tenaga (di lokasi pekerjaan) :
- Mandor M
- Tukang Tb
- Pekerja P

Koefisien Tenaga / M3 :
- Mandor = (Tk x M) : Qt (L03)
- Tukang = (Tk x Tb) : Qt (L02)
- Pekerja = (Tk x P) : Qt (L01)

4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT


Lihat lampiran.

5. ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKEMAN ANALISA MASING-MASING HARGA
SATUAN.
Didapat Harga Satuan Pekerjaan :

Rp. 1,080,904.29 / M1

6. MASA PELAKSANAAN YANG DIPERLUKAN


Masa Pelaksanaan : . . . . . . . . . . . .

7. VOLUME PEKERJAAN YANG DIPERLUKAN


Volume pekerjaan : 0.00 M1
EI-768b
ng Spun Pile OD500-A (K-600) Bottom (Pointed) P = 10 m
URAIAN ANALISA HARGA SATUAN

KOEF. SATUAN KETERANGAN

0.3 KM
7.00 jam
500.00 mm
10.00 M
10.00 M
1.00 KM

1.0000 M'

1.00 batang
0.75 -

15.00 menit Lumpsum


15.00 menit
30.00 menit

15.00 M1/jam

0.0667 jam

3,960.00 M'

30.00 menit
120.00 menit

30.00 menit
180.00 menit
1,320.00 M'

0.0008 Jam

Lumpsum

Berlanjut ke hal. berikut.

EI-768b
ng Spun Pile OD500-A (K-600) Bottom (Pointed) P = 10 m
URAIAN ANALISA HARGA SATUAN
Lanjutan

KOEF. SATUAN KETERANGAN

105.00 M'

1.00 orang
2.00 orang
10.00 orang

0.0667 jam
0.1333 jam
0.6667 jam
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK :
No. PAKET KONT :
NAMA PAKET :
PROP / KAB / KOD:
ITEM PEMBAYARA: 7.6.(12).b
JENIS PEKERJAA : Penyediaan Tiang Pancang Spun Pile OD500-A (K-600) Bottom (Pointed) P = 10 m
SATUAN PEMBAY : M1

PERKIRAAN
NO. KOMPONEN SATUANKUANTITAS

A. TENAGA

1. Pekerja (L01) jam 0.6667


2. Tukang (L02) jam 0.1333
3. Mandor (L03) jam 0.0667

MLAH HARGA TENAG

B. BAHAN

1. Tiang Pancang Spun Pile OD500-A (K-600) Upper (With Flange) M1 1.0000

UMLAH HARGA BAHA

C. PERALATAN

1. CRANE (E07) jam 0.0667


2. Ponton + Tug Boat Jam 0.0008
3. Alat Bantu jam 1.0000

JUMLAH HARGA PERALA


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )
E. OVERHEAD & PROFIT 15.0 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
EI-768b

FORMULIR STANDAR UNTUK


N ANALISA MASING-MASING HARGA SATUAN

PERKIRAAN VOL. P: 0.00


TOTAL HARGA (Rp.): 0.00
% THD. BIAYA PRO : 0.00

HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

12,857.14 8,571.43
14,285.71 1,904.76
17,142.86 1,142.86

MLAH HARGA TENAGA 11,619.05

880,000.00 880,000.00

UMLAH HARGA BAHAN 880,000.00

637,499.63 42,499.98
1,053,034.16 797.75
5,000.00 5,000.00

JUMLAH HARGA PERALATAN 48,297.73


939,916.78
140,987.52
1,080,904.29
ponen untuk menyelesaikan satu satuan pekerjaan dari nomor
ITEM PEMBAYARAN NO. : 7.6.(12).b
JENIS PEKERJAAN : Penyediaan Tiang Pancang 35 x 35 cm P = 18 m
SATUAN PEMBAYARAN : M1 U

No. URAIAN KODE KOEF.

I. ASUMSI
1 Membeli Tiang Pancang jadi dari Pabrik
2 Lokasi pekerjaan
3 Jarak rata-rata Base camp ke lokasi pekerjaan L 0.3
4 Jam kerja efektif per-hari Tk 7.00
5 Ukuran tiang pancang sesuai kebutuhan (diameter) Uk 350.00
6 Panjang Tiang Pancang p 18.00
7 Panjang Tiang Pancang Per Batang is 9.00
8 Tiang pancang diangkut menggunakan Ponton Ld2 1.00

II. URUTAN KERJA


1 Tiang pancang dikirim ke pelabuhan terdekat (di Jakarta)
atas tanggungan pabrik
2 Tiang Pancang dari pelabuhan diangkut dengan ponton
atas tanggungan kontraktor sampai ke lokasi pekerjaan
3 Memuat & menurunkan dari/ke dengan Crane

III. PEMAKAIAN BAHAN, ALAT DAN TENAGA

1. BAHAN
Tiang Pancang 35 x 35 cm (M50) 1.0000

2. ALAT
2.a CRANE (E07)
Kapasitas V2 1.00
Faktor Efisiensi alat Fa 0.75
Waktu siklus
- Waktu memuat dan membongkar T1 15.00
- dan lain-lain ( termasuk mengatur dan menggeser) T2 15.00
Ts2 30.00

Kap. Prod. / jam = V x is x Fa x 60 Q2 13.50


Ts2

Koefisien Alat / M3 = 1 : Q2 (E07) 0.0741

2.b Ponton + Tug Boat (E29)

Kapasitas muatan ponton (sesuai kapasitas pemancangan) V 846.00

Waktu siklus : v1
- Waktu memuat tiang pancang Ts2 30.00
- Waktu tempuh muatan ketitik pemancangan Ts1 120.00

- Lain-Lain ( bongkar dan muat) T3 30.00


Ts1 180.00

Kapasitas Produksi / Jam = V x 60 Q1 282.00


Ts1

Koefisien Alat / m3 = 1 : Q1 (E29) 0.0035

2.c. ALAT BANTU


Diperlukan alat bantu untuk transportasi
- Tackle
- Tambang
- Alat kecil lainnya
ITEM PEMBAYARAN NO. : 7.6.(12).b
JENIS PEKERJAAN : Penyediaan Tiang Pancang 35 x 35 cm P = 18 m
SATUAN PEMBAYARAN : M1 U

No. URAIAN KODE KOEF.

3. TENAGA
Produksi per hari (unloading) = Q2 x Tk Qt 94.50
Kebutuhan tenaga (di lokasi pekerjaan) :
- Mandor M 1.00
- Tukang Tb 2.00
- Pekerja P 10.00

Koefisien Tenaga / M3 :
- Mandor = (Tk x M) : Qt (L03) 0.0741
- Tukang = (Tk x Tb) : Qt (L02) 0.1481
- Pekerja = (Tk x P) : Qt (L01) 0.7407

4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT


Lihat lampiran.

5. ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKEMAN ANALISA MASING-MASING HARGA
SATUAN.
Didapat Harga Satuan Pekerjaan :

Rp. 535,746.37 / M1

6. MASA PELAKSANAAN YANG DIPERLUKAN


Masa Pelaksanaan : . . . . . . . . . . . .

7. VOLUME PEKERJAAN YANG DIPERLUKAN


Volume pekerjaan : 0.00 M1
EI-7610a

URAIAN ANALISA HARGA SATUAN

SATUAN KETERANGAN

KM
jam
mm
M
M
KM

M'

batang
-

menit Lumpsum
menit
menit

M1/jam

jam

M'

menit
menit

menit
menit

M'

Jam

Lumpsum

Berlanjut ke hal. berikut.


EI-7610a

URAIAN ANALISA HARGA SATUAN


Lanjutan

SATUAN KETERANGAN

M'

orang
orang
orang

jam
jam
jam
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK :
No. PAKET KONT :
NAMA PAKET :
PROP / KAB / KOD:
ITEM PEMBAYARA: 7.6.(12).b
JENIS PEKERJAA : Penyediaan Tiang Pancang 35 x 35 cm P = 18 m
SATUAN PEMBAY : M1

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1. Pekerja (L01) jam 0.7407


2. Tukang (L02) jam 0.1481
3. Mandor (L03) jam 0.0741

JUMLAH HARGA TENA

B. BAHAN

1. Tiang Pancang 35 x 35 cm M1 1.0000

JUMLAH HARGA BAH

C. PERALATAN
0

1. CRANE (E07) jam 0.0741


2. Ponton + Tug Boat Jam 0.0035
3. Alat Bantu jam 1.0000

JUMLAH HARGA PERALA


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )
E. OVERHEAD & PROFIT 15.0 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
EI-7610a

ORMULIR STANDAR UNTUK


NALISA MASING-MASING HARGA SATUAN

PERKIRAAN VOL. P: 0.00


TOTAL HARGA (Rp.): 0.00
% THD. BIAYA PRO : 0.00

HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

12,857.14 9,523.81
14,285.71 2,116.40
17,142.86 1,269.84

JUMLAH HARGA TENAGA 12,910.05

397,000.00 397,000.00

JUMLAH HARGA BAHAN 397,000.00

637,499.63 47,222.19
1,053,034.16 3,734.16
5,000.00 5,000.00

JUMLAH HARGA PERALATAN 55,956.36


465,866.41
69,879.96
535,746.37
ITEM PEMBAYARAN NO. : 7.6.(18).b
JENIS PEKERJAAN : Pemancangan Tiang Pancang 35 x 35 cm P = 18 m
SATUAN PEMBAYARAN : M1 U

No. URAIAN KODE KOEF.

I. ASUMSI
1 Menggunakan alat (cara mekanik)
2 Lokasi pekerjaan : di lokasi
3 Jam kerja efektif per-hari Tk 7.00
4 Panjang Tiang p 18.00
5 Ukuran diameter Tiang 350.00
6 Berat per-meter tiang b 294.00

II. URUTAN KERJA


1 Material Tiang pancang yang telah siap ada dekat
lokasi pemancangan
2 Penyambungan dilakukan pada saat pemancangan

III. PEMAKAIAN BAHAN, ALAT DAN TENAGA

1. BAHAN
Plat baja (sbg perkuatan sambungan tiang) 7.92
kawat las secukupnya. 0.24

2. ALAT

2.a Crane on Track 35 Ton (E31)


Kapasitas V1 1.00
Faktor Efisiensi alat Fa 0.75
Waktu siklus
- Waktu penggeseran dan penyetelan tiang T1 30.00
- Waktu pemancangan T2 60.00
- Waktu penjambungan tiang T3 30.00
Ts1 120.00

Kap. Prod. / jam = V1 x p x Fa x 60 Q1 6.75


Ts1
Koefisien Alat / m' = 1 : Q1 (E31) 0.1481

2.b PILE DRIVER HAMMER (E30)


Kapasitas V2 1.00
Faktor Efisiensi alat Fa 0.75
Waktu siklus
- Waktu pemancangan Ts2 120.00

Kap. Prod. / jam = V2 x p x Fa x 60 Q2 6.75


Ts2
Koefisien Alat / m' = 1 : Q2 (E07) 0.1481

2.c Ponton + Tug Boat


Kapasitas muatan ponton (sesuai kapasitas pemancangan) V 846.00
Kapasitas produksi pemancangan/jam Qa 6.75
Waktu siklus : v1
- Waktu memuat tiang pancang Ts2 30.00
- Waktu tempuh muatan ketitik pemancangan Ts1 15.00
- Waktu tunggu pemancangan V x 60 T1 7,520.00
Qa
- Lain-Lain ( bongkar dan muat) T3 10.00
Ts1 7,530.00

Kapasitas Produksi / Jam = V x 60 Q1 6.74


Ts1

Koefisien Alat / m3 = 1 : Q1 (E29) 0.1483

2.b. ALAT BANTU


Diperlukan alat bantu kecil selama penyetelan dan
penyambungan
- Rantai/sling baja, dan Lain-Lain

ITEM PEMBAYARAN NO. : 7.6.(18).b


JENIS PEKERJAAN : Pemancangan Tiang Pancang 35 x 35 cm P = 18 m
SATUAN PEMBAYARAN : M1 U

No. URAIAN KODE KOEF.

2.c. GENSET (E12)


Diasumsi panjang tiang p 32.00

Koefisien Alat / kg = 1 : ( p x b : Ts3 ) (E12) 0.0020

2.d. WELDING SET (E32)


Kapasitas V3 1.00
Faktor Efisiensi alat Fa 0.75
Diameter tiang pancang r 35.00
Panjang Pengelasan per Sambungan = 2 x p x ( r / 2 ) Nw 110.00
Waktu siklus
- Waktu Penyambungan tiang Ts3 30.00

Kap. Prod. / jam = 3 x V3 x Nw x Fa x 60 Q2 495.00


Ts3
Koefisien Alat / m' = 1 : Q2 (E07) 0.0020
3. TENAGA
Produksi Tiang dalam 1 hari = Tk x Q1 Qt 47.25
Kebutuhan tenaga tambahan di lokasi :
- Mandor M 1.00
- Tukang Tb 1.00
- Pekerja P 6.00

Koefisien Tenaga / M1 :
- Mandor = ( Tk x M ) : Qt (L03) 0.1481
- Tukang = ( Tk x Tb ) : Qt (L02) 0.1481
- Pekerja = ( Tk x P ) : Qt (L01) 0.8889

4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT


Lihat lampiran.

5. ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKEMAN ANALISA MASING-MASING HARGA
SATUAN.
Didapat Harga Satuan Pekerjaan :

Rp. 286,231.80 / M'

6. MASA PELAKSANAAN YANG DIPERLUKAN


Masa Pelaksanaan : . . . . . . . . . . . .

7. VOLUME PEKERJAAN YANG DIPERLUKAN


Volume pekerjaan : 0.00 M'
F.04.c

URAIAN ANALISA HARGA SATUAN

SATUAN KETERANGAN

jam
M
mm
kg

kg
kg

Titik
-

menit
menit
menit
menit

M1/jam

Jam

Titik
-

menit

M1/jam

Jam
M'
M'

menit
menit
menit

menit
menit

M'

Jam

Lumpsum

Berlanjut ke hal. berikut.

F.04.c

URAIAN ANALISA HARGA SATUAN


Lanjutan

SATUAN KETERANGAN

Jam

Titik
-
Cm
Cm

menit

M1/jam

Jam
M'

orang
orang
orang

jam
jam
jam
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK :
No. PAKET KONT :
NAMA PAKET :
PROP / KAB / KOD:
ITEM PEMBAYARA: 7.6.(18).b
JENIS PEKERJAA : Pemancangan Tiang Pancang 35 x 35 cm P = 18 m
SATUAN PEMBAY : M1

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1. Pekerja (L01) jam 0.8889


2. Tukang (L02) jam 0.1481
3. Mandor (L03) jam 0.1481

JUMLAH HARGA TENA

B. BAHAN

1. Plat baja (sbg perkuatan sambungan tiang) Kg 7.9200


2. kawat las secukupnya. Kg 0.2418

JUMLAH HARGA BAH

C. PERALATAN

1. Crane on Track (E31) jam 0.1481


2. Pile Driver (E30) jam 0.1481
3. Genset jam 0.0020
4. Welding set jam 0.0020
5. Ponton + Tug Boat jam 0.1483
6. Alat Bantu Ls 1.0000

JUMLAH HARGA PERALA

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )


E. OVERHEAD & PROFIT 15.0 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nom
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
F.04.c

ORMULIR STANDAR UNTUK


NALISA MASING-MASING HARGA SATUAN

PERKIRAAN VOL. P: 0.00


TOTAL HARGA (Rp.): 0.00
% THD. BIAYA PRO : 0.00

HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

12,857.14 11,428.57
14,285.71 2,116.40
17,142.86 2,539.68

JUMLAH HARGA TENAGA 16,084.66

11,000.00 87,120.00
28,500.00 6,890.67

JUMLAH HARGA BAHAN 94,010.67

613,266.11 90,854.24
282,809.71 41,897.73
412,104.20 832.53
107,608.94 217.39
1,053,034.16
5,000.00 5,000.00

JUMLAH HARGA PERALATAN 138,801.90

248,897.22
37,334.58
286,231.80
untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran

ponen untuk menyelesaikan satu satuan pekerjaan dari nomor

tuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN


ITEM PEMBAYARAN NO. : 7.6.(14).a
JENIS PEKERJAAN : Penyediaan SHEETPILE FLAT 150 - 500 P = 9 m fc = 50 MPa (K-400)
SATUAN PEMBAYARAN : M1

No. URAIAN KODE

I. ASUMSI
1 Membeli Tiang Pancang jadi dari Pabrik
2 Lokasi pekerjaan : di setiap jembatan
3 Jarak rata-rata Base camp ke lokasi pekerjaan L
4 Jam kerja efektif per-hari Tk
5 Ukuran Sheet Pile Uk
6 Panjang Sheet Pile p
7 Panjang Sheetpile Per Batang is
8 Tiang pancang diangkut menggunakan Ponton Ld2

II. URUTAN KERJA


1 Tiang pancang dikirim ke pelabuhan terdekat (di Jakarta)
atas tanggungan pabrik
2 Tiang Pancang dari pelabuhan diangkut dengan ponton
atas tanggungan kontraktor sampai ke lokasi pekerjaan
3 Memuat & menurunkan dari/ke dengan Crane

III. PEMAKAIAN BAHAN, ALAT DAN TENAGA

1. BAHAN
SHEETPILE CPC SHEETPILE FLAT 150 - 500 P = 9 m fc = 50 MPa (K-400) (M50)

2. ALAT
2.a CRANE (E07)
Kapasitas V2
Faktor Efisiensi alat Fa
Waktu siklus
- Waktu memuat dan membongkar T1
- dan lain-lain ( termasuk mengatur dan menggeser) T2
Ts2

Kap. Prod. / jam = V x is x Fa x 60 Q2


Ts2

Koefisien Alat / M3 = 1 : Q2 (E07)

2.b Ponton + Tug Boat (E29)

Kapasitas muatan ponton (sesuai kapasitas pemancangan) V

Waktu siklus : v1
- Waktu memuat tiang pancang Ts2
- Waktu tempuh muatan ketitik pemancangan Ts1

- Lain-Lain ( bongkar dan muat) T3


Ts1

Kapasitas Produksi / Jam = V x 60 Q1


Ts1

Koefisien Alat / m3 = 1 : Q1 (E29)

2.c. ALAT BANTU


Diperlukan alat bantu untuk transportasi
- Tackle
- Tambang
- Alat kecil lainnya
ITEM PEMBAYARAN NO. : 7.6.(14).a
JENIS PEKERJAAN : Penyediaan SHEETPILE FLAT 150 - 500 P = 9 m fc = 50 MPa (K-400)
SATUAN PEMBAYARAN : M1

No. URAIAN KODE

3. TENAGA
Produksi per hari (unloading) = Q2 x Tk Qt
Kebutuhan tenaga (di lokasi pekerjaan) :
- Mandor M
- Tukang Tb
- Pekerja P

Koefisien Tenaga / M3 :
- Mandor = (Tk x M) : Qt (L03)
- Tukang = (Tk x Tb) : Qt (L02)
- Pekerja = (Tk x P) : Qt (L01)

4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT


Lihat lampiran.

5. ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKEMAN ANALISA MASING-MASING HARGA
SATUAN.
Didapat Harga Satuan Pekerjaan :

Rp. 375,354.11 / M1

6. MASA PELAKSANAAN YANG DIPERLUKAN


Masa Pelaksanaan : . . . . . . . . . . . .

7. VOLUME PEKERJAAN YANG DIPERLUKAN


Volume pekerjaan : 0.00 M1
EI-765

URAIAN ANALISA HARGA SATUAN

KOEF. SATUAN KETERANGAN

0.3 KM
7.00 jam
500.00 mm
9.00 M
9.00 M
1.00 KM

1.0000 M'

1.00 batang
0.75 -

15.00 menit Lumpsum


15.00 menit
30.00 menit

13.50 M1/jam

0.0741 jam

2,502.00 M'

30.00 menit
120.00 menit

30.00 menit
180.00 menit

834.00 M'

0.0012 Jam

Lumpsum

Berlanjut ke hal. berikut.


EI-765

URAIAN ANALISA HARGA SATUAN


Lanjutan

KOEF. SATUAN KETERANGAN

94.50 M'

1.00 orang
2.00 orang
10.00 orang

0.0741 jam
0.1481 jam
0.7407 jam
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK :
No. PAKET KONT :
NAMA PAKET :
PROP / KAB / KOD:
ITEM PEMBAYARA: 7.6.(14).a
JENIS PEKERJAA : Penyediaan SHEETPILE FLAT 150 - 500 P = 9 m fc = 50 MPa (K-400)
SATUAN PEMBAY : M1

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1. Pekerja (L01) jam 0.7407


2. Tukang (L02) jam 0.1481
3. Mandor (L03) jam 0.0741

JUMLAH HARGA TENA

B. BAHAN

1. SHEETPILE CPC SHEETPILE FLAT 150 - 500 P = 9 m fc = 50 MPa M1 1.0000

JUMLAH HARGA BAH


###
C. PERALATAN

1. CRANE (E07) jam 0.0741


2. Ponton + Tug Boat Jam 0.0012
3. Alat Bantu jam 1.0000

JUMLAH HARGA PERALA


D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )
E. OVERHEAD & PROFIT 15.0 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
EI-765

ORMULIR STANDAR UNTUK


NALISA MASING-MASING HARGA SATUAN

PERKIRAAN VOL. P: 0.00


TOTAL HARGA (Rp.): 0.00
% THD. BIAYA PRO : 0.00

HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

12,857.14 9,523.81
14,285.71 2,116.40
17,142.86 1,269.84

JUMLAH HARGA TENAGA 12,910.05

260,000.00 260,000.00

JUMLAH HARGA BAHAN 260,000.00

637,499.63 47,222.19
1,053,034.16 1,262.63
5,000.00 5,000.00

JUMLAH HARGA PERALATAN 53,484.83


326,394.88
48,959.23
375,354.11
ITEM PEMBAYARAN NO. : 6.1.(2c)
JENIS PEKERJAAN : Pemancangan SHEETPILE FLAT 150 - 500 P = 9 m fc = 50 MPa (K-400)
SATUAN PEMBAYARAN : Liter

No. URAIAN KODE

I. ASUMSI
1 Menggunakan alat (cara mekanik)
2 Lokasi pekerjaan : di lokasi
3 Jam kerja efektif per-hari Tk
4 Panjang Tiang p
5 Ukuran diameter Tiang
6 Berat per-meter tiang b

II. URUTAN KERJA


1 Material Tiang pancang yang telah siap ada dekat
lokasi pemancangan
2 Penyambungan dilakukan pada saat pemancangan

III. PEMAKAIAN BAHAN, ALAT DAN TENAGA

1. BAHAN

2. ALAT

2.a Crane on Track 35 Ton (E31)


Kapasitas V1
Faktor Efisiensi alat Fa
Waktu siklus
- Waktu penggeseran dan penyetelan tiang T1
- Waktu pemancangan T2

Ts1

Kap. Prod. / jam = V1 x p x Fa x 60 Q1


Ts1
Koefisien Alat / m' = 1 : Q1 (E31)

2.b Pile Drive (E30)


Kapasitas V2
Faktor Efisiensi alat Fa
Waktu siklus
- Waktu pemancangan Ts2

Kap. Prod. / jam = V2 x p x Fa x 60 Q2


Ts2
Koefisien Alat / m' = 1 : Q2 (E07)
2.c Ponton + Tug Boat
Kapasitas muatan ponton (sesuai kapasitas pemancangan) V
Kapasitas produksi pemancangan/jam Qa
Waktu siklus : v1
- Waktu memuat tiang pancang Ts2
- Waktu tempuh muatan ketitik pemancangan Ts1
- Waktu tunggu pemancangan V x 60 T1
Qa
- Lain-Lain ( bongkar dan muat) T3
Ts1

Kapasitas Produksi / Jam = V x 60 Q1


Ts1

Koefisien Alat / m3 = 1 : Q1 (E29)

2.b. ALAT BANTU


Diperlukan alat bantu kecil selama penyetelan dan
penyambungan
- Rantai/sling baja, dan Lain-Lain
ITEM PEMBAYARAN NO. : 6.1.(2c)
JENIS PEKERJAAN : Pemancangan SHEETPILE FLAT 150 - 500 P = 9 m fc = 50 MPa (K-400)
SATUAN PEMBAYARAN : Liter

No. URAIAN KODE

2.c. GENSET (E12)


Diasumsi panjang tiang p

Koefisien Alat / kg = 1 : ( p x b : Ts3 ) (E12)

3. TENAGA
Produksi Tiang dalam 1 hari = Tk x Q1 Qt
Kebutuhan tenaga tambahan di lokasi :
- Mandor M
- Tukang Tb
- Pekerja P

Koefisien Tenaga / M1 :
- Mandor = ( Tk x M ) : Qt (L03)
- Tukang = ( Tk x Tb ) : Qt (L02)
- Pekerja = ( Tk x P ) : Qt (L01)

4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT


Lihat lampiran.

5. ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKEMAN ANALISA MASING-MASING HARGA
SATUAN.
Didapat Harga Satuan Pekerjaan :

Rp. 154,695.02 / M'

6. MASA PELAKSANAAN YANG DIPERLUKAN


Masa Pelaksanaan : . . . . . . . . . . . .

7. VOLUME PEKERJAAN YANG DIPERLUKAN


Volume pekerjaan : M'
F.07.b
FLAT 150 - 500 P = 9 m fc = 50 MPa (K-400)
URAIAN ANALISA HARGA SATUAN

KOEF. SATUAN KETERANGAN

7.00 jam
9.00 M
500.00 mm
195.56 kg

1.00 Titik
0.75 -

30.00 menit
30.00 menit
menit
60.00 menit

6.75 M1/jam

0.1481 Jam

1.00 Titik
0.75 -

30.00 menit

13.50 M1/jam

0.0741 Jam
2,502.00 M'
13.50 M'

30.00 menit
15.00 menit
11,120.00 menit

10.00 menit
11,130.00 menit

13.49 M'

0.0741 Jam

Lumpsum

Berlanjut ke hal. berikut.


F.07.b
FLAT 150 - 500 P = 9 m fc = 50 MPa (K-400)
URAIAN ANALISA HARGA SATUAN
Lanjutan

KOEF. SATUAN KETERANGAN

32.00 M

0.0741 Jam

47.25 M'

1.00 orang
1.00 orang
6.00 orang

0.1481 jam
0.1481 jam
0.8889 jam
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK :
No. PAKET KONT :
NAMA PAKET :
PROP / KAB / KOD:
ITEM PEMBAYARA: 6.1.(2c)
JENIS PEKERJAA : Pemancangan SHEETPILE FLAT 150 - 500 P = 9 m fc = 50 MPa (K-400)
SATUAN PEMBAY : Liter

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. TENAGA

1. Pekerja (L01) jam 0.8889


2. Tukang (L02) jam 0.1481
3. Mandor (L03) jam 0.1481

JUMLAH HARGA TENA

B. BAHAN

JUMLAH HARGA BAH

C. PERALATAN

1. Crane on Track (E31) jam 0.1481


2. Pile Drive (E30) jam 0.0741
3. Alat Bantu Ls 1.0000

UMLAH HARGA PERALAT

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )


E. OVERHEAD & PROFIT 15.0 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nom
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
F.07.b

ORMULIR STANDAR UNTUK


NALISA MASING-MASING HARGA SATUAN

PERKIRAAN VOL. P: 0.00


TOTAL HARGA (Rp.): 0.00
% THD. BIAYA PRO : 0.00

HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

12,857.14 11,428.57
14,285.71 2,116.40
17,142.86 2,539.68

JUMLAH HARGA TENAGA 16,084.66

JUMLAH HARGA BAHAN 0.00

613,266.11 90,854.24
304,810.00 22,578.52
5,000.00 5,000.00

UMLAH HARGA PERALATAN 118,432.76

134,517.41
20,177.61
154,695.02
untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran

ponen untuk menyelesaikan satu satuan pekerjaan dari nomor

k bahan bakar, bahan habis dipakai dan operator.


ntuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
HARGA SATUAN PEKERJAAN SANITASI DALAM GEDUN

A.5.1.1.1. Pemasangan 1 buah closet duduk/monoblock

No. URAIAN PEKERJAAN KODE SATUAN

1 2 3
A TENAGA
1 Pekerja L.01 OH
2 Tukang batu L.02 OH
3 Kepala tukang L.03 OH
4 Mandor L.04 OH
Jumlah
B BAHAN
1 Closet duduk Unit
2 Perlengkapan Ls
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

A.5.1.1.1.a Pemasangan 1 buah closet duduk setara toto

No. URAIAN PEKERJAAN KODE SATUAN

1 2 3
A TENAGA
1 Pekerja L.01 OH
2 Tukang batu L.02 OH
3 Kepala tukang L.03 OH
4 Mandor L.04 OH
Jumlah
B BAHAN
1 Closet duduk Unit
2 Perlengkapan Ls
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

A.5.1.1.2. Pemasangan 1 buah closet jongkok porslen setara INA

No. URAIAN PEKERJAAN KODE SATUAN

Pekerjaan Sanitasi dalam Gedung 408


No. URAIAN PEKERJAAN SATUAN

1 2 3
A TENAGA
1 Pekerja L.01 OH
2 Tukang batu L.02 OH
3 Kepala tukang L.03 OH
4 Mandor L.04 OH
Jumlah
B BAHAN
1 Jongkok (setaraf INA) Unit
2 Semen portland Kg
3 Pasir pasang M3
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

Pekerjaan Sanitasi dalam Gedung 409


A.5.1.1.2.a Pemasangan 1 buah closet jongkok porslen setara toto

No. URAIAN PEKERJAAN KODE SATUAN

1 2 3
A TENAGA
1 Pekerja L.01 OH
2 Tukang batu L.02 OH
3 Kepala tukang L.03 OH
4 Mandor L.04 OH
Jumlah
B BAHAN
1 Jongkok (setaraf toto) Unit
2 Semen portland Kg
3 Pasir pasang M3
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

A.5.1.1.4. Pemasangan 1 buah urinoir

No. URAIAN PEKERJAAN KODE SATUAN

1 2 3
A TENAGA
1 Pekerja L.01 OH
2 Tukang batu L.02 OH
3 Kepala tukang L.03 OH
4 Mandor L.04 OH
Jumlah
B BAHAN
1 Urinoir (ex Toto) Unit
2 Semen portland Kg
3 Pasir pasang M3
4 Perlengkapan %
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

A.5.1.1.5. Pemasangan 1 buah wastafel

No. URAIAN PEKERJAAN KODE SATUAN

1 2 3
A TENAGA
1 Pekerja L.01 OH
2 Tukang batu L.02 OH

Pekerjaan Sanitasi dalam Gedung 410


3 Kepala tukang L.03 OH
4 Mandor L.04 OH
Jumlah
B BAHAN
1 Wastafel (setara TOTO) Unit
2 Semen portland Kg
3 Pasir pasang M3
4 Perlengkapan %
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

Pekerjaan Sanitasi dalam Gedung 411


A.5.1.1.14. Pemasangan 1 buah floor drain stainlessteel

No. URAIAN PEKERJAAN KODE SATUAN

1 2 3
A TENAGA
1 Pekerja L.01 OH
2 Tukang batu L.02 OH
3 Kepala tukang L.03 OH
4 Mandor L.04 OH
Jumlah
B BAHAN
1 Floor drain stainlessteel (setara TOTO) Unit
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

A.5.1.1.14.a Pemasangan 1 buah floor drain PVC

No. URAIAN PEKERJAAN KODE SATUAN

1 2 3
A TENAGA
1 Pekerja L.01 OH
2 Tukang batu L.02 OH
3 Kepala tukang L.03 OH
4 Mandor L.04 OH
Jumlah
B BAHAN
1 Floor drain bahan PVC Unit
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

A.5.1.1.18. Pemasangan 1 m’ pipa galvanis diameter ½”

No. URAIAN PEKERJAAN KODE SATUAN

1 2 3
A TENAGA
1 Pekerja L.01 OH
2 Tukang batu L.02 OH
3 Kepala tukang L.03 OH
4 Mandor L.04 OH
Jumlah

Pekerjaan Sanitasi dalam Gedung 412


B BAHAN
1 Pipa galvanis ½” Bh
2 Perlengkapan Ls
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

Pekerjaan Sanitasi dalam Gedung 413


A.5.1.1.19. Pemasangan 1 buah kran diameter ½” atau 3/4”

No. URAIAN PEKERJAAN KODE SATUAN

1 2 3
A TENAGA
1 Pekerja L.01 OH
2 Tukang batu L.02 OH
3 Kepala tukang L.03 OH
4 Mandor L.04 OH
Jumlah
B BAHAN
1 Kran air M
2 Sealtape Bh
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

A.5.1.1.20. Pemasangan 1 m’ pipa galvanis diameter 3/4”

No. URAIAN PEKERJAAN KODE SATUAN

1 2 3
A TENAGA
1 Pekerja L.01 OH
2 Tukang batu L.02 OH
3 Kepala tukang L.03 OH
4 Mandor L.04 OH
Jumlah
B BAHAN
1 Pipa galvanis 3/4” M
2 Perlengkapan %
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

A.5.1.1.21. Pemasangan 1 m’ pipa galvanis diameter 1”

No. URAIAN PEKERJAAN KODE SATUAN

1 2 3
A TENAGA

Pekerjaan Sanitasi dalam Gedung 414


1 Pekerja L.01 OH
2 Tukang batu L.02 OH
3 Kepala tukang L.03 OH
4 Mandor L.04 OH
Jumlah
B BAHAN
1 Pipa galvanis 1” M
2 Perlengkapan %
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

Pekerjaan Sanitasi dalam Gedung 415


Pemasangan 1 m’ pipa galvanis diameter 1 ½”
A.5.1.1.22. No Uraian Kode Satuan Koefisien

No. URAIAN PEKERJAAN KODE SATUAN

1 2 3
A TENAGA
1 Pekerja L.01 OH
2 Tukang batu L.02 OH
3 Kepala tukang L.03 OH
4 Mandor L.04 OH
Jumlah
B BAHAN
1 Pipa galvanis 1 ½” M
2 Perlengkapan %
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

A.5.1.1.23. Pemasangan 1 m’ pipa galvanis diameter 3”

No. URAIAN PEKERJAAN KODE SATUAN

1 2 3
A TENAGA
1 Pekerja L.01 OH
2 Tukang batu L.02 OH
3 Kepala tukang L.03 OH
4 Mandor L.04 OH
Jumlah
B BAHAN
1 Pipa galvanis 3" M
2 Perlengkapan %
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

A.5.1.1.24. Pemasangan 1 m’ pipa galvanis diameter 4”

No. URAIAN PEKERJAAN KODE SATUAN

1 2 3
A TENAGA

Pekerjaan Sanitasi dalam Gedung 416


1 Pekerja L.01 OH
2 Tukang batu L.02 OH
3 Kepala tukang L.03 OH
4 Mandor L.04 OH
Jumlah
B BAHAN
1 Pipa galvanis 4” M
2 Perlengkapan %
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

Pekerjaan Sanitasi dalam Gedung 417


A.5.1.1.25. Pemasangan 1 m’ pipa PVC tipe AW diameter 1/2”

No. URAIAN PEKERJAAN KODE SATUAN

1 2 3
A TENAGA
1 Pekerja L.01 OH
2 Tukang batu L.02 OH
3 Kepala tukang L.03 OH
4 Mandor L.04 OH
Jumlah
B BAHAN
1 Pipa PVC 1/2" (setara wavin) M
2 Perlengkapan %
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

A.5.1.1.26. Pemasangan 1 m’ pipa PVC tipe AW diameter 3/4”

No. URAIAN PEKERJAAN KODE SATUAN

1 2 3
A TENAGA
1 Pekerja L.01 OH
2 Tukang batu L.02 OH
3 Kepala tukang L.03 OH
4 Mandor L.04 OH
Jumlah
B BAHAN
1 Pipa PVC 3/4" (setara wavin) M
2 Perlengkapan %
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

A.5.1.1.27. Pemasangan 1 m’ pipa PVC tipe AW diameter 1”

No. URAIAN PEKERJAAN KODE SATUAN

1 2 3
A TENAGA

Pekerjaan Sanitasi dalam Gedung 418


1 Pekerja L.01 OH
2 Tukang batu L.02 OH
3 Kepala tukang L.03 OH
4 Mandor L.04 OH
Jumlah
B BAHAN
1 Pipa PVC 1" (setara wavin) M
2 Perlengkapan %
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

Pekerjaan Sanitasi dalam Gedung 419


A.5.1.1.29. Pemasangan 1 m’ pipa PVC tipe AW diameter 2”

No. URAIAN PEKERJAAN KODE SATUAN

1 2 3
A TENAGA
1 Pekerja L.01 OH
2 Tukang batu L.02 OH
3 Kepala tukang L.03 OH
4 Mandor L.04 OH
Jumlah
B BAHAN
1 Pipa PVC 2” (setara wavin) M
2 Perlengkapan %
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

A.5.1.1.31. Pemasangan 1 m’ pipa PVC tipe AW diameter 3”

No. URAIAN PEKERJAAN KODE SATUAN

1 2 3
A TENAGA
1 Pekerja L.01 OH
2 Tukang batu L.02 OH
3 Kepala tukang L.03 OH
4 Mandor L.04 OH
Jumlah
B BAHAN
1 Pipa PVC 3” (setara wavin) M
2 Perlengkapan %
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

A.5.1.1.32. Pemasangan 1 m’ pipa PVC tipe AW diameter 4”

No. URAIAN PEKERJAAN KODE SATUAN

1 2 3
A TENAGA

Pekerjaan Sanitasi dalam Gedung 420


1 Pekerja L.01 OH
2 Tukang batu L.02 OH
3 Kepala tukang L.03 OH
4 Mandor L.04 OH
Jumlah
B BAHAN
1 Pipa PVC 4” (setara wavin) M
2 Perlengkapan %
Jumlah
C Jumlah A + B
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D)

Pekerjaan Sanitasi dalam Gedung 421


ANITASI DALAM GEDUNG

HARGA BIAYA
KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

3.30 90,000.00 297,000.00


1.10 100,000.00 110,000.00
0.01 110,000.00 1,100.00
0.16 120,000.00 19,200.00
427,300.00

1.000 2,962,700.000 2,962,700.00


6% x closet 2,962,700.000 177,762.00
3,140,462.00
3,567,762.00
535,164.30
4,102,926.30

HARGA BIAYA
KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

3.30 90,000.00 297,000.00


1.10 100,000.00 110,000.00
0.01 110,000.00 1,100.00
0.16 120,000.00 19,200.00
427,300.00

1.000 2,246,800.000 2,246,800.00


6% x closet 2,246,800.000 134,808.00
2,381,608.00
2,808,908.00
421,336.20
3,230,244.20

HARGA BIAYA
KOEFISIEN SATUAN SATUAN

Pekerjaan Sanitasi dalam Gedung 422


KOEFISIEN
( Rp. ) ( Rp. )
5 4 6

1.00 90,000.00 90,000.00


1.50 100,000.00 150,000.00
0.15 110,000.00 16,500.00
0.16 120,000.00 19,200.00
275,700.00

1.00 191,000.000 191,000.00


6.00 1,500.000 9,000.00
0.01 100,100.000 1,001.00
201,001.00
476,701.00
71,505.15
548,206.15

Pekerjaan Sanitasi dalam Gedung 423


HARGA BIAYA
KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

1.00 90,000.00 90,000.00


1.50 100,000.00 150,000.00
0.15 110,000.00 16,500.00
0.16 120,000.00 19,200.00
275,700.00

1.00 294,800.000 294,800.00


6.00 1,500.000 9,000.00
0.01 100,100.000 1,001.00
304,801.00
580,501.00
87,075.15
667,576.15

HARGA BIAYA
KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

1.00 90,000.00 90,000.00


1.00 100,000.00 100,000.00
0.10 110,000.00 11,000.00
0.05 120,000.00 6,000.00
207,000.00

1.00 1,878,300.000 1,878,300.00


6.00 1,500.000 9,000.00
0.01 100,100.000 1,001.00
30.00 1,878,300.000 563,490.00
2,451,791.00
2,658,791.00
398,818.65
3,057,609.65

HARGA BIAYA
KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

1.20 90,000.00 108,000.00


1.45 100,000.00 145,000.00

Pekerjaan Sanitasi dalam Gedung 424


0.15 110,000.00 16,500.00
0.06 120,000.00 7,200.00
276,700.00

1.20 966,100.000 1,159,320.00


6.00 1,500.000 9,000.00
0.01 100,100.000 1,001.00
12.00 966,100.000 115,932.00
1,285,253.00
1,561,953.00
234,292.95
1,796,245.95

Pekerjaan Sanitasi dalam Gedung 425


HARGA BIAYA
KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

0.01 90,000.00 900.00


0.10 100,000.00 10,000.00
0.01 110,000.00 1,100.00
0.005 120,000.00 600.00
12,600.00

1.00 319,100.000 319,100.00


319,100.00
331,700.00
49,755.00
381,455.00

HARGA BIAYA
KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

0.01 90,000.00 900.00


0.10 100,000.00 10,000.00
0.01 110,000.00 1,100.00
0.005 120,000.00 600.00
12,600.00

1.00 18,500.000 18,500.00


18,500.00
31,100.00
4,665.00
35,765.00

HARGA BIAYA
KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

0.054 90,000.00 4,860.00


0.09 100,000.00 9,000.00
0.009 110,000.00 990.00
0.027 120,000.00 3,240.00
18,090.00

Pekerjaan Sanitasi dalam Gedung 426


1.20 15,516.667 18,620.00
35 % x pipa 15,516.667 5,430.83
24,050.83
42,140.83
6,321.13
48,461.96

Pekerjaan Sanitasi dalam Gedung 427


HARGA BIAYA
KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

0.01 90,000.00 900.00


0.40 100,000.00 40,000.00
0.04 110,000.00 4,400.00
0.005 120,000.00 600.00
45,900.00

1.00 32,500.000 32,500.00


0.025 15,000.000 375.00
32,875.00
78,775.00
11,816.25
90,591.25

HARGA BIAYA
KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

0.054 90,000.00 4,860.00


0.09 100,000.00 9,000.00
0.009 110,000.00 990.00
0.027 120,000.00 3,240.00
18,090.00

1.20 19,716.667 23,660.00


35.00 19,716.667 6,900.83
30,560.83
48,650.83
7,297.63
55,948.46

HARGA BIAYA
KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

Pekerjaan Sanitasi dalam Gedung 428


0.054 90,000.00 4,860.00
0.09 100,000.00 9,000.00
0.009 110,000.00 990.00
0.027 120,000.00 3,240.00
18,090.00

1.20 23,300.000 27,960.00


35.00 23,300.000 8,155.00
36,115.00
54,205.00
8,130.75
62,335.75

Pekerjaan Sanitasi dalam Gedung 429


HARGA BIAYA
KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

0.108 90,000.00 9,720.00


0.18 100,000.00 18,000.00
0.018 110,000.00 1,980.00
0.005 120,000.00 600.00
30,300.00

1.20 41,050.000 49,260.00


35.00 41,050.000 14,367.50
63,627.50
93,927.50
14,089.13
108,016.63

HARGA BIAYA
KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

0.135 90,000.00 12,150.00


0.225 100,000.00 22,500.00
0.023 110,000.00 2,530.00
0.007 120,000.00 840.00
38,020.00

1.20 97,083.333 116,500.00


35.00 97,083.333 33,979.17
150,479.17
188,499.17
28,274.88
216,774.04

HARGA BIAYA
KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

Pekerjaan Sanitasi dalam Gedung 430


0.135 90,000.00 12,150.00
0.225 100,000.00 22,500.00
0.023 110,000.00 2,530.00
0.007 120,000.00 840.00
38,020.00

1.20 154,166.667 185,000.00


35.00 154,166.667 53,958.33
238,958.33
276,978.33
41,546.75
318,525.08

Pekerjaan Sanitasi dalam Gedung 431


HARGA BIAYA
KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

0.036 90,000.00 3,240.00


0.06 100,000.00 6,000.00
0.006 110,000.00 660.00
0.002 120,000.00 240.00
10,140.00

1.20 5,325.000 6,390.00


35.00 5,325.000 1,863.75
8,253.75
18,393.75
2,759.06
21,152.81

HARGA BIAYA
KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

0.036 90,000.00 3,240.00


0.06 100,000.00 6,000.00
0.006 110,000.00 660.00
0.002 120,000.00 240.00
10,140.00

1.20 7,125.000 8,550.00


35.00 7,125.000 2,493.75
11,043.75
21,183.75
3,177.56
24,361.31

HARGA BIAYA
KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

Pekerjaan Sanitasi dalam Gedung 432


0.036 90,000.00 3,240.00
0.06 100,000.00 6,000.00
0.006 110,000.00 660.00
0.002 120,000.00 240.00
10,140.00

1.20 10,125.000 12,150.00


35.00 10,125.000 3,543.75
15,693.75
25,833.75
3,875.06
29,708.81

Pekerjaan Sanitasi dalam Gedung 433


HARGA BIAYA
KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

0.054 90,000.00 4,860.00


0.09 100,000.00 9,000.00
0.009 110,000.00 990.00
0.003 120,000.00 360.00
15,210.00

1.20 19,900.000 23,880.00


35.00 19,900.000 6,965.00
30,845.00
46,055.00
6,908.25
52,963.25

HARGA BIAYA
KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

0.081 90,000.00 7,290.00


0.135 100,000.00 13,500.00
0.014 110,000.00 1,485.00
0.004 120,000.00 480.00
22,755.00

1.20 39,100.000 46,920.00


35.00 39,100.000 13,685.00
60,605.00
83,360.00
12,504.00
95,864.00

HARGA BIAYA
KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
5 4 6

Pekerjaan Sanitasi dalam Gedung 434


0.081 90,000.00 7,290.00
0.135 100,000.00 13,500.00
0.014 110,000.00 1,485.00
0.004 120,000.00 480.00
22,755.00

1.20 63,125.000 75,750.00


35.00 63,125.000 22,093.75
97,843.75
120,598.75
18,089.81
138,688.56

Pekerjaan Sanitasi dalam Gedung 435


ITEM PEMBAYARAN NO. : 6.1 (1)(a)
JENIS PEKERJAAN : Lapis Resap Pengikat - Aspal Cair
SATUAN PEMBAYARAN : Liter

No. URAIAN KODE

I. ASUMSI
1 Menggunakan alat berat (cara mekanik)
2 Lokasi pekerjaan : sepanjang jalan
3 Jarak rata-rata Base Camp ke lokasi pekerjaan L
4 Jam kerja efektif per-hari Tk
5 Faktor kehilangan bahan Fh
6 Komposisi campuran :
- Aspal Pen 60 atau Pen 80 As
- Kerosene K
7 Berat isi bahan :
- Aspal Pen 60 atau Pen 2 D1
- Kerosene D2
8 Bahan dasar (aspal & minyak pencair) semuanya
diterima di lokasi pekerjaan

II. URUTAN KERJA


1 Aspal dan Minyak Flux dicampur dan dipanaskan
sehingga menjadi campuran aspal cair
2 Permukaan yang akan dilapis dibersihkan dari debu
dan kotoran dengan Air Compressor
3 Campuran aspal cair disemprotkan dengan Asphalt
Distributor ke atas permukaan yang akan dilapis.

III. PEMAKAIAN BAHAN, ALAT DAN TENAGA

1. BAHAN
Untuk mendapatkan 1 liter Lapis Resap Pengikat
diperlukan : ( 1 liter x Fh ) PC

1.a. Aspal = As x PC x D1 (M10)


1.b. Kerosene = K x PC (M11)

2. ALAT
2.a. ASPHALT DISTRIBUTOR (E41)
Lebar penyemprotan b
Kecepatan penyemprotan V
Kapasitas pompa aspal pas
Faktor effisiensi kerja Fa

Kap. Prod. / jam = pas x Fa x 60 Q1

Koefisien Alat / Ltr = 1 : Q1 (E41)

2.b. AIR COMPRESSOR (E05)

Kap. Prod. / jam = Asphalt Distributor Q2

Koefisien Alat / Ltr = 1 : Q2 (E05)


3. TENAGA
Produksi menentukan : ASPHALT DISTRIBUTOR Q4
Produksi Lapis Resap Pengikat / hari = Tk x Q4 Qt
Kebutuhan tenaga :
- Pekerja P
- Mandor M
ITEM PEMBAYARAN NO. : 6.1 (1)(a)
JENIS PEKERJAAN : Lapis Resap Pengikat - Aspal Cair
SATUAN PEMBAYARAN : Liter

No. URAIAN KODE

Koefisien tenaga / liter :


- Pekerja = (Tk x P) : Qt (L01)
- Mandor = (Tk x M) : Qt (L03)

4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT


Lihat lampiran.

5. ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA
SATUAN.
Didapat Harga Satuan Pekerjaan :

Rp. 15,043.45 / liter.

6. WAKTU PELAKSANAAN YANG DIPERLUKAN


Masa Pelaksanaan : . . . . . . . . . . . . bulan

7. VOLUME PEKERJAAN YANG DIPERLUKAN


Volume pekerjaan : 1.00 Liter
ITEM PEMBAYARAN NO. : 6.3(3b)
JENIS PEKERJAAN : Lataston Lapis Aus Perata (HRS-WC(L)) (gradasi senjang/semi senjang)
SATUAN PEMBAYARAN : Ton

No. URAIAN KODE

I. ASUMSI
1 Menggunakan alat berat (cara mekanik)
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi existing jalan : sedang
4 Jarak rata-rata Base Camp ke lokasi pekerjaan L
5 Tebal Lapis (HRS) padat t
6 Jam kerja efektif per-hari Tk
7 Faktor kehilangan material : - Agregat Fh1
- Aspal Fh2
8 Berat isi Agregat (padat) Bip
9 Berat Isi Agregat (lepas) Bil
10 Komposisi campuran HRS
- Agr Pch Mesin 5 - 10 & 10 - 15 mm 5-10&10-15
- Agregat Pecah Mesin 0 - 5 mm 0-5
- Pasir Halus PH
- Semen FF
- Asphalt As
- Anti Stripping Agent Asa
11 Berat isi bahan :
- HRS-WC D1
- Agr Pch Mesin 5 - 10 & 10 - 15 mm D2
- Agr Pch Mesin 0 - 5 mm D3
- Pasir Halus D4
12 Jarak Stock pile ke Cold Bin l

II. URUTAN KERJA


1 Wheel Loader memuat Agregat ke dalam
Cold Bin AMP
2 Agregat dan aspal dicampur dan dipanaskan
dengan AMP untuk dimuat langsung ke dalam
Dump Truck dan diangkut ke lokasi pekerjaan
3 Campuran panas HRS dihampar dengan Finisher
dan dipadatkan dengan Tandem (Awal & Akhir) dan
Pneumatic Tire Roller (Intermediate Rolling)
4 Selama pemadatan, sekelompok pekerja akan
merapikan tepi hamparan dengan menggunakan
Alat Bantu

III. PEMAKAIAN BAHAN, ALAT DAN TENAGA

1. BAHAN
1.a. Agr 5-10 & 10-15 = ("5-10&10-15" x Fh1) : D2 (M92)
1.b. Agr 0-5 = ("0-5" x Fh1) : D3 (M91)
1.c. Pasir Halus = (PH x Fh1) : D4 (M01c)
1.d. Semen = (FF x Fh1) x 1000 (M05)
1.e. Aspal = (As x Fh2) x 1000 (M10)

2. ALAT
2.a. WHEEL LOADER (E15)
Kapasitas bucket V
Faktor bucket Fb
Faktor efisiensi alat Fa
Waktu Siklus T1 + T2 + T3 Ts1
- Kecepatan maju rata rata Vf
- Kecepatan kembali rata rata Vr
- Muat ke Bin = (l x 60) / Vf T1
- Kembali ke Stock pile = (l x 60) / Vr T2
- Lain - lain (waktu pasti) T3
Ts1
ITEM PEMBAYARAN NO. : 6.3(3b)
JENIS PEKERJAAN : Lataston Lapis Aus Perata (HRS-WC(L)) (gradasi senjang/semi senjang)
SATUAN PEMBAYARAN : Ton

No. URAIAN KODE

Kap. Prod. / jam = V x Fb x Fa x 60 x Bip Q1


Ts1

Koefisien Alat / Ton = 1 : Q1 (E15)

2.b. ASPHALT MIXING PLANT (AMP) (E01)


Kapasitas produksi V
Faktor Efisiensi alat Fa

Kap.Prod. / jam = V x Fa Q2

Koefisien Alat / ton = 1 : Q2 (E01)

2.c. GENERATOR SET ( GENSET ) (E12)


Kap.Prod. / Jam = SAMA DENGAN AMP Q3
Koefisien Alat / ton = 1 : Q3 (E12)

2.d. DUMP TRUCK (DT) (E08)


Kapasitas bak V
Faktor Efisiensi alat Fa
Kecepatan rata-rata bermuatan v1
Kecepatan rata-rata kosong v2
Kapasitas AMP / batch Q2b
Waktu menyiapkan 1 batch HRS Tb
Waktu Siklus Ts2
- Mengisi Bak = (V : Q2b) x Tb T1
- Angkut = (L : v1) x 60 menit T2
- Tunggu + dump + Putar T3
- Kembali = (L : v2) x 60 menit T4
Ts2

Kap.Prod. / jam = V x Fa x 60 Q4
Ts2

Koefisien Alat / ton = 1 : Q4 (E08)

2.e. ASPHALT FINISHER (E02)


Kecepatan menghampar V
Faktor efisiensi alat Fa
Lebar hamparan b
Kap.Prod. / jam = V x b x 60 x Fa x t x D1 Q5

Koefisien Alat / ton = 1 : Q5 (E02)

2.f. TANDEM ROLLER (E17)


Kecepatan rata-rata alat v
Lebar efektif pemadatan b
Jumlah lintasan n
Jumlah lajur lintasan N
Lebar overlap bo
Faktor Efisiensi alat Fa
Kap. Prod./jam = (v x 1000) x (N(b-bo)+bo) x Fa x t x D1 x (Bip/Bil) Q6
n
Koefisien Alat / ton = 1 : Q6 (E17)

2.g. PNEUMATIC TIRE ROLLER (E18)


Kecepatan rata-rata v
Lebar efektif pemadatan b
Jumlah lintasan n
Lajur lintasan N
Lebar Overlap bo
Faktor Efisiensi alat Fa

Kap.Prod./jam = (v x 1000) x (N(b-bo)+bo) x Fa x t x D1 Q7


n
Koefisien Alat / ton = 1 : Q7 (E18)
ITEM PEMBAYARAN NO. : 6.3(3b)
JENIS PEKERJAAN : Lataston Lapis Aus Perata (HRS-WC(L)) (gradasi senjang/semi senjang)
SATUAN PEMBAYARAN : Ton

No. URAIAN KODE

2.h. ALAT BANTU


diperlukan :
- Kereta dorong = 2 buah
- Sekop = 3 buah
- Garpu = 2 buah
- Tongkat Kontrol ketebalan hanparan

3. TENAGA
Produksi menentukan : Asphalt Finisher Q5
Produksi HRS / hari = Tk x Q5 Qt
Kebutuhan tenaga :
- Pekerja P
- Mandor M

Koefisien Tenaga / ton :


- Pekerja = (Tk x P) / Qt (L01)
- Mandor = (Tk x M) / Qt (L03)

4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT


Lihat lampiran.

5. ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA
SATUAN.
Didapat Harga Satuan Pekerjaan :

Rp. 1,696,809.09 / TON

6. WAKTU PELAKSANAAN YANG DIPERLUKAN


Masa Pelaksanaan : . . . . . . . . . . . . bulan

7. VOLUME PEKERJAAN YANG DIPERLUKAN


Volume pekerjaan : 130.79 ton
EI-611a

URAIAN ANALISA HARGA SATUAN

KOEF. SATUAN KETERANGAN

35.00 KM
7.00 Jam
1.03 -

64 % terhadap volume
36 % terhadap volume

1.03 Kg / liter
0.80 Kg / liter

1.03 liter

0.6790 Kg.
0.3708 Liter

3.00 M
30.00 m/menit Asumsi
100 liter/menit Panduan
0.80 Sedang

4,800.00 liter

0.0002 Jam

4,800.00 liter

0.0002 Jam
4,800.00 liter
33,600.00 liter

10.00 orang
2.00 orang

Berlanjut ke hal. berikut.


EI-611a

URAIAN ANALISA HARGA SATUAN


Lanjutan

KOEF. SATUAN KETERANGAN

0.0021 Jam
0.0004 Jam
EI-633a
rata (HRS-WC(L)) (gradasi senjang/semi senjang)
URAIAN ANALISA HARGA SATUAN

KOEF. SATUAN KETERANGAN

35.00 KM
0.03 M
7.00 Jam
1.05 -
1.03 -
1.81 ton/m3
1.51 ton/m3

33.00 % Gradasi harus -


23.00 % memenuhi -
34.50 % Spesifikasi
2.20 %
7.30 %
0.30 %As

2.23 ton / M3
1.42 ton / M3
1.57 ton / M3
1.46 ton / M3
0.05 km

0.2440 M3
0.1538 M3
0.2481 M3
23.1000 Kg
75.1900 Kg

1.50 M3 panduan
0.85 -
0.83 -

15.00 km/jam panduan


20.00 km/jam panduan
0.20 menit
0.00 menit
0.75 menit
0.95 menit

Berlanjut ke hal. berikut.


EI-633a
ata (HRS-WC(L)) (gradasi senjang/semi senjang)
URAIAN ANALISA HARGA SATUAN
Lanjutan

KOEF. SATUAN KETERANGAN

120.97

0.0083 Jam

60.00 ton / Jam


0.83 -

49.80 ton

0.0201 Jam

49.80 ton
0.0201 Jam

3.50 ton
0.80 -
20.00 KM / Jam
30.00 KM / Jam
1.00 ton
1.00 menit

3.50 menit
105.00 menit
15.00 menit
70.00 menit
193.50 menit

0.87 M2

1.1518 Jam

5.00 m/menit
0.83 -
3.15 meter
52.47 ton

0.0191 Jam

1.50 Km / Jam
1.48 M
6.00 lintasan 2 Awal & 4 Akhir
3.00
0.30 m
0.83 -
63.90 ton
0.0157 Jam

4.00 KM / jam
2.29 M
6.00 lintasan
3.00
0.30 M
0.83 -

232.10 M2

0.0043 Jam

Berlanjut ke hal. berikut.


EI-633a
ata (HRS-WC(L)) (gradasi senjang/semi senjang)
URAIAN ANALISA HARGA SATUAN
Lanjutan

KOEF. SATUAN KETERANGAN

Lump Sum

52.47 ton
367.31 ton

7.00 orang
1.00 orang

0.1334 Jam
0.0191 Jam
EI-611a

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK :
No. PAKET KONTRAK : ………………………………………………
NAMA PAKET : …………………………………………………………………..
………………………………………………………………….
PROP / KAB / KODYA : ………………………………………………
ITEM PEMBAYARAN NO. : 6.1 (1)(a) PERKIRAAN VOL. PEK. :
JENIS PEKERJAAN : Lapis Resap Pengikat - Aspal Cair TOTAL HARGA (Rp.) :
SATUAN PEMBAYARAN : Liter % THD. BIAYA PROYEK :

PERKIRAAN HARGA JUMLA


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARG
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Jam 0.0021 12,857.14


2. Mandor (L03) Jam 0.0004 17,142.86

JUMLAH HARGA TENAGA

B. BAHAN

1. Aspal (M10) Kg 0.6790 13,900.00


2. Kerosene (M11) liter 0.3708 9,600.00

0 JUMLAH HARGA BAHAN

C. PERALATAN

1. Asp. Distributor E41 Jam 0.0002 157,420.11


2. Compressor E05 Jam 0.0002 82,035.29

JUMLAH HARGA PERALATAN

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )


E. OVERHEAD & PROFIT 15.0 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukura
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerja
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecua
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lela
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PP
yang dibayar dari kontrak) dan biaya-biaya lainnya.
EI-633

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK :
No. PAKET KONTRAK : ………………………………………………
NAMA PAKET : …………………………………………………………………..
………………………………………………………………….
PROP / KAB / KODYA : ………………………………………………
ITEM PEMBAYARAN NO. : 6.3(3b) PERKIRAAN VOL. PEK. :
JENIS PEKERJAAN : Lataston Lapis Aus Perata (HRS-WC(L))TOTAL HARGA (Rp.) :
SATUAN PEMBAYARAN : Ton % THD. BIAYA PROYEK :

PERKIRAAN HARGA JUMLA


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARG
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Jam 0.1334 4,657.31


2. Mandor (L03) Jam 0.0191 7,281.29

JUMLAH HARGA TENAGA

B. BAHAN

1. Agr 5-10 & 10-15 M3 0.2440 421,200.00


2. Lolos screen2 ukuran ( 0 - 5) M3 0.1538 162,952.13
3 Pasir Halus (M01c) M3 0.2481 100,100.00
4 Semen (M05) Kg 23.1000 1,500.00
5 Aspal (M10) Kg 75.1900 13,900.00

JUMLAH HARGA BAHAN

C. PERALATAN
1. Wheel Loader E15 Jam 0.0083 262,099.45
2. AMP E01 Jam 0.0201 3,959,664.02
3. Genset E12 Jam 0.0201 230,331.53
4. Dump Truck E08 Jam 1.1518 131,467.37
5. Asphalt Finisher E02 Jam 0.0191 118,098.26
6. Tandem Roller E17 Jam 0.0157 109,222.93
7 P. Tyre Roller E18 Jam 0.0043 132,085.27
8 Alat Bantu Ls 1.0000 0.00

JUMLAH HARGA PERALATAN

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )


E. OVERHEAD & PROFIT 15.0 % x D
F. HARGA SATUAN PEKERJAAN ( D + E )
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukura
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerja
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecua
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lela
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PP
yang dibayar dari kontrak) dan biaya-biaya lainnya.
EI-611a

FORMULIR STANDAR UNTUK


AN ANALISA MASING-MASING HARGA SATUAN

1.00
6,709.48
0.00

JUMLAH
HARGA
(Rp.)

26.79
7.14

33.93

9,437.77
3,559.68

12,997.45

32.80
17.09

49.89

13,081.26
1,962.19
15,043.45
am operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran

perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan


ga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
lasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
h termasuk bahan bakar, bahan habis dipakai dan operator.
eluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
EI-633a

FORMULIR STANDAR UNTUK


AN ANALISA MASING-MASING HARGA SATUAN

130.79
1,967,532.92
0.12

JUMLAH
HARGA
(Rp.)

621.29
138.76

760.06

102,778.73
25,065.57
24,836.46
34,650.00
1,045,141.00

1,232,471.75

2,166.56
79,511.33
4,625.13
151,422.23
2,250.65
1,709.37
569.08
0.00

242,254.36

1,475,486.17
221,322.92
1,696,809.09
am operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran

perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan


ga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
lasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
h termasuk bahan bakar, bahan habis dipakai dan operator.
eluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
STANDAR HARGA SATUAN DASAR UPAH

NO MATERIAL SATUAN

A. UPAH
1 Pekerja Org/hari
2 Tukang Gali / Batu / Tembok / Pipa /Besi / Cat / Cor / Semen / Listrik / P Org/hari
3 Kepala Tukang Org/hari
4 Mandor Org/hari
5 Ahli alat berat (mekanik) Org/hari
6 Operator Alat Berat Org/hari
7 Pembantu Operator Org/hari
8 Supir Truk Org/hari
9 Kenek truk Org/hari
10 Pembantu Mekanik Org/hari

STANDAR HARGA SATUAN DASAR BAHAN

NO MATERIAL

B. BAHAN PENGISI
1 Batu Kong
2 Batu Sap Pinang
3 Batu pecah 15-20 cm
4 Batu pecah 10-15 cm
5 Batu pecah 5-7 cm
6 Batu pecah 3-5 cm
7 Batu pecah 2-3 cm
8 Batu pecah 1-2 cm
9 Batu pecah 1-1 cm
10 Batu pecah 0,5 cm
11 Stone Dust
12 Aspal
13 Aspal Sealent
14 Pasir Kasar
15 Pasir Halus
16 Semen PC
17 Semen PC
18 Tanah Ex. Peniraman
19 Tanah Pilihan
20 Paving Block
NO MATERIAL

21 Paving Stone
22 Batu Bata 5 x 11 x 22cm
23 Bataco 15 x 30 x 7 cm
24 Bataco 15 x 30 x 6 cm
25 Bataco 20 x 40 x 9 cm ( press )
26 Bataco 20 x 40 x 7 cm ( press )
27 Kerawang ( roster ) 18 x 18 cm
28 Kerawang press ( roster ) 30 x 30 cm
29 Keramik 20 x 20 cm Polished ex Roman
30 Keramik 20 x 20 cm Unpolished ex Roman
NO MATERIAL

31 Keramik 30 x 30 cm Polished ex Roman


32 Keramik 30 x 30 cm Unpolished ex Roman
33 Keramik 40 x 40 cm Polished ex Roman
34 Keramik 40 x 40 cm Unpolished ex Roman
35 Keramik 30 x 60 cm Polished (setaraf Indogress)
36 Keramik 30 x 60 cm Unpolished (setaraf Indogress)
37 Keramik 40 x 40 cm Polished (setaraf Indogress)
38 Keramik 40 x 40 cm Unpolished (setaraf Indogress)
39 Keramik 60 x 60 cm Polished (setaraf Indogress)
40 Keramik 60 x 60 cm Unpolished (setaraf Indogress)
41 Keramik dinding 20 x 20 cm ex Roman
42 Keramik dinding 20 x 25 cm ex Roman
43 Marmer
44 Wood Flooring
45 List Keramik WC. 8 x 20 cm
46 Plint Kayu uk. 2 x 10 cm
47 Floor Hardener
48 Additive Ready Mix
49 Karung Goni Curing Beton ( 0.7m² )
50 Tiang Pancang (Mini Pile / Ready Mix) uk. Π 25 x 25, K 300 - 6m
51 Sewa Pompa Ready Mix (Min. 100 M³)
52 Bahan Plastik Cor Beton
53 Kansteen / kerb beton 20x30x60
54 Kansteen / kerb beton 16x28x45
55 LPA (Lapis Pondasi Agregat Mutu A)
56 LPB (Lapis Pondasi Agregat Mutu B)

C. BAHAN KAYU
1 Ky. Belian tdk ketam Uk. 6/6 - 4 M
2 Ky. Belian tdk ketam Uk. 7/7 - 4 M
3 Ky. Belian tdk ketam Uk. 8/8 - 4 M
4 Ky. Belian tdk ketam Uk. 8/16 - 4 M
5 Ky. Belian tdk ketam Uk. 9/9 - 4 M
6 Ky. Belian tdk ketam Uk. 10/10 - 4 M
7 Ky. Belian tdk ketam Uk. 12/12 - 4 M
8 Ky. Belian tdk ketam Uk. 18/18 - 4 M
9 Ky. Belian tdk ketam Uk. 5/10 - 4 M
10 Ky. Belian ketam Uk. 6/6 - 4 M
11 Ky. Belian ketam Uk. 7/7 - 4 M
12 Ky. Belian ketam Uk. 8/8 - 4 M
13 Ky. Belian ketam Uk. 5/10 - 4 M
14 Ky. Belian ketam Uk. 4/8 - 4 M
15 Ky. klas I Bengkirai uk. 8/8 - 4 M ( tdk ketam )
16 Ky. klas I Bengkirai uk. 7/7 - 4 M ( tdk ketam )
NO MATERIAL

17 Ky. klas I Bengkirai uk. 8/8 - 4 M ( ketam )


18 Ky. klas I Bengkirai uk. 7/7 - 4 M ( ketam )
19 Ky. klas I Bengkirai uk. 5/10 - 4 M ( ketam )
20 Kusen Ky Belian uk. 5/10
21 Kusen Ky Kelas I Bangkirai uk. 5/10
22 Kusen Ky Kelas II uk. 5/10
23 Ky. klas II Mabang uk. 8/8 - 4 M ( tdk ketam )
24 Ky. klas II Mabang uk. 7/7 - 4 M ( tdk ketam )
25 Ky. klas II Mabang uk. 4/6 - 4 M ( tdk ketam )
26 Ky. klas II Mabang uk. 5/7 - 4 M ( tdk ketam )
27 Ky. klas II Mabang uk. 5/10 - 4 M ( tdk ketam )
NO MATERIAL

28 Ky. klas II Mabang uk. 6/10 - 4 M ( tdk ketam )


29 Ky. klas II Mabang uk. 6/12 - 4 M ( tdk ketam )
30 Ky. klas II Mabang uk. 4/8 - 4 M ( tdk ketam )
31 Ky. klas II Mabang uk. 8/15 - 4 M ( tdk ketam )
32 Ky. klas II Mabang uk. 8/12 - 4 M ( tdk ketam )
33 Ky. klas II Mabang uk. 8/8 - 4 M ( ketam )
34 Ky. klas II Mabang uk. 7/7 - 4 M ( ketam )
35 Ky klas III uk. 3/5 - 4 M ( tdk ketam)
36 Ky klas III uk. 4/6 - 4 M ( tdk ketam)
37 Papan belian ketam (4m)
38 Papan belian tdk ketam (4m)
39 Papan kayu klas II (mabang) tdk ketam
40 Papan kayu klas II (mabang) ketam
41 Papan kayu klas I tdk ketam
42 Papan kayu klas I ketam
43 Papan mal klas III
44 Papan Simpiran
45 Renglat kayu klas I uk 1/8 cm
46 Kayu profil 10cm
47 Kayu cerucuk /dolken ø 4 - 6 - Pj. 4 M
48 Kayu cerucuk /dolken ø 6 - 8 - Pj. 4 M
49 Kayu cerucuk /dolken ø 8 - 10 - Pj. 4 M
50 Kayu cerucuk /dolken ø12 - Pj. 8 M
51 Kayu cerucuk /dolken ø 15 - Pj. 12 M
52 Kayu Simpiran / Bakar
53 Alas laci
54 Wood Plank
55 Bambu Pj. 10 m

D. BAHAN CAT
1 Amplas
2 Minyak cat
3 Cat kilat setara Dulux
4 Cat kilat setara Avian
5 Plamur
6 Cat Dasar Setara Dulux
7 Cat Akhir Interior setara Dulux
8 Cat Akhir Eksterior (weather shield) setara Dulux
9 Cat Dasar setara Mowilex
10 Cat Akhir Interior setara Mowilex
11 Cat Akhir Eksterior (weather shield) setara Mowilex
12 Cat Dasar setara Vinilex
13 Cat Akhir Interior setara Vinilex
14 Cat seng (Zinc Chromate)
NO MATERIAL

15 Plitur
16 Thiner
17 Melamic
18 Vernis
19 Meni
20 Oker / Semen Warna
21 Lem Kayu
22 Sealent
23 Soda Api
24 Sabun / cream pembersih kotoran
25 Teak Oil
NO MATERIAL

26 Ter / Residu
27 Kuas 4"
28 Cat Marka (non Thermoplas)
29 Cat Marka (Thermoplastic)
30 Glass Bead
31 Weatherbond Emulsion ( cat kerb )
32 Cat Water Proofing

E. BAHAN BESI DAN ALUMINIUM


1 Besi Tulangan Beton U 24
2 Besi Tulangan Beton U 32
3 Besi wire mesh ø 5
4 Besi wire mesh ø 6
5 Besi wire mesh ø 8
6 Kawat baja/bendrat
7 Simpai roll
8 Kawat simpai
9 Baut dia 4/8 " pj = 20 cm
10 Besi Penahan
11 Beugel plat L. 3 cm
12 Plat 1,2 x 2,4 x 12
13 Besi Profil
14 Kawat Las
15 Kawat Las
16 Kawat harmonika
17 Kawat kasa
18 Pipa galvanis dia 3/4"
19 Pipa galvanis dia 1/2"
20 Pipa galvanis dia 1"
21 Pipa galvanis dia 1 1/4"
22 Pipa galvanis dia 1 1/2"
23 Pipa galvanis dia 2"
24 Pipa galvanis dia 2,5"
25 Pipa galvanis dia 3"
26 Pipa galvanis dia 4"
27 Pipa galvanis dia 5"
28 Pipa galvanis dia 6,5"
29 Folding gate
30 Rangka Aluminium 1 1/2" x 3"
31 Rangka Aluminium 1 3/4" x 4"
32 Pintu Aluminium std IKP, lengkap 4"
33 Kusen Aluminium 3" Putih
34 Kusen Aluminium 3" Hitam
35 Kusen Aluminium 3" Silver
NO MATERIAL

36 Rangka Baja Ringan Zincalume (truss/color) (Tanpa Jurai Dalam - Bentang s/d 16 m)
37 Rangka Baja Ringan Zincalume (truss/color) (Tanpa Jurai Dalam - Bentang 17 m s/d 3
38 Rangka Baja Ringan Zincalume (truss/color) (Dengan Jurai Dalam - Bentang s/d 16m)
39 Rangka Baja Ringan Zincalume (truss/color) (Dengan Jurai Dalam - Bentang 17 m s/d
40 Rangka Baja Ringan Zincalume (truss/polos) (Tanpa Jurai Dalam - Bentang s/d 16 m)
41 Rangka Baja Ringan Zincalume (truss/polos) (Tanpa Jurai Dalam - Bentang 17 m s/d 3
42 Rangka Baja Ringan Zincalume (truss/polos) (Dengan Jurai Dalam - Bentang s/d 16m)
43 Rangka Baja Ringan Zincalume (truss/polos) (Dengan Jurai Dalam - Bentang 17 m s/d
44 Reng Rangka Baja Ringan (Polos) uk. 0.40 - 0.45 Pjg 6 m
45 Rangka baja truss (0,75-6m)
46 Rangka baja truss (0,65-6m)
NO MATERIAL

47 Dinabolt
48 L. Braket
49 Baut truss
50 Baut reng
51 Baut atap 5 cm
52 Alumunium Komposit + Rangka Besi
53 Alumunium Komposit 1,24 x 2,44 m (setara alumatec)
54 Rangka Plafond Metal Furing + Pemasangan
55 Besi stainles 1"
56 Besi tempa
57 Pipa Baja
58 Plat Baja
59 Kawat bronjong

F. BAHAN PENGGANTUNG
1 Pintu PVC untuk WC
2 Kait angin
3 Handle Jendela
4 Handle Pintu
5 Engsel jendela
6 Engsel pintu
7 Slot pintu
8 Slot jendela
9 Kunci tanam 2 slag (setaraf Belluci)
10 Kunci tanam 1 slag
11 Kunci tanam antik
12 Kunci tanam biasa
13 Kunci silinder
14 Door Closer
15 Door Stoper
16 Paku Seng
17 Paku campuran 1" - 5 "
18 Paku beton
19 Paku triplek
20 Paku GRC
21 Paku Zincalum
22 Paku Onduline
23 Sekrup Onduline
24 Sekrup Gibsum
25 Sekrup Fixer
26 Sekrup Steel Sheet uk. 5 x 15 mm
27 Sekrup Steel Sheet uk. 5 x 25 mm
28 Sekrup Steel Sheet uk. 5 x 35 mm
29 Sekrup Steel Sheet uk. 5 x 45 mm
NO MATERIAL

30 Sekrup Steel Sheet uk. 5 x 50 mm


31 Sekrup Steel Sheet uk. 5 x 55 mm
32 Sekrup Steel Sheet uk. 5 x 65 mm
33 Sekrup Ulir Kayu
34 Paku asbes
35 Sekrup Zincalume
36 Pintu Tempered Polos 12 mm - uk. 87 x 213,5 cm
37 Pintu Alumunium + Engsel Tanam - uk. 90 x 215 cm
38 Pintu Alumunium + Engsel Kupu-kupu - uk. 90 x 215 cm
39 Jendela Casement - uk. 60 x 120 cm (Lengkap - Tanpa Kaca)
NO MATERIAL

G. BAHAN ATAP
1 Sirap belian
2 Asbes
3 Eternit
4 Genteng Metal Type Permata 0.30
5 Genteng Metal Type Prima 0.30
6 Genteng Metal Type Royal 0.30
7 Genteng Metal Type Classic 0.30
8 Genteng Metal Type Permata 0.25
9 Genteng Metal Type Classic 0.25
10 Genteng Metal Type Royal 0.25
11 Atap Genteng Onduline Transparan 2 x 0,95 m
12 Atap Genteng Onduline Warna 2 x 0,95 m (merah,hijau,coklat & hitam)
13 Atap Genteng Onduline Warna 2 x 0,95 m (Biru /Premium)
14 Atap Genteng Onduvilla Warna 1,06 x 0,4 m (merah,hijau,coklat & hitam)
15 Atap Genteng Onduvilla Warna 1,06 x 0,4 m (teracota 3D & florentino)
16 Perabung Onduline Warna 90 x 50 cm (merah, coklat, hijau & hitam)
17 Perabung Onduline Warna 90 x 50 cm (biru/premium)
18 Perabung Onduline Warna 90 x 50 cm (florentino)
19 Siku Onduline Warna 110 x 40 cm (merah,coklat,hijau & hitam)
20 Apron Piece Onduvilla 102 x 14 cm
21 Verge Piece Onduline/Onduvilla 104 x 10,5 cm tinggi 11,4 cm
22 Onduband
23 Atap Seng Metal Soka Abadi
24 Atap Seng Metal Soka Jempol
25 Atap Seng Metal Soka Tiara
26 Genteng Metal Stone ( Type Classic 0.35 )
27 Genteng Metal Stone ( Type Prima 0.35 )
28 Atap Metal Supersheet 0.35 (polos)
29 Atap Metal Supersheet 0.35 (colour)
30 Atap Metal Supersheet 0.25 (polos)
31 Atap Metal Supersheet 0.25 (colour)
32 Atap Trim Deck 0.3 (polos)
33 Atap Trim Deck 0.35 (color)
34 Atap polycarbonat
35 Nok bubungan genteng metal 1/2 lingkaran 0.35 (pj 40cm)
36 Nok bubungan genteng metal stone 1/2 lingkaran 0.35 (pj 40cm)
37 Nok bubungan genteng metal kotak 0.35
38 Nok bubungan genteng metal stone kotak 0.35
39 Nok bubungan Trim Deck (polos)
40 Nok bubungan Trim Deck (color)
41 Seng Gelombang Bjls 30
42 Seng Gelombang Bjls 20
NO MATERIAL

43 Seng Plat Bjls 20


44 Seng Plat Bjls 30
45 Seng Plat Bjls 30 (lebar 45 cm)
46 Plat Datar Color 0.35
47 Zincalume Gelombang Persegi 0.40 (polos)
48 Zincalume Gelombang Persegi 0.35 (polos)
49 Zincalume Gelombang Persegi 0.30 (polos)
50 Zincalume Gelombang Persegi 0.40(color)
51 Zincalume Gelombang Persegi 0.35 (color)
52 Zincalume Gelombang Persegi 0.30 (color)
53 Zincalume Plat 0.2
NO MATERIAL

54 Aluminium Foil
55 Papan Belian utk Atap uk. 1/15 pj. 50 cm
56 Atap Steel Sheet 0.30 lurus (silver)
57 Atap Steel Sheet 0.35 lurus (silver)
58 Atap Steel Sheet 0.4 lurus (silver)
59 Atap Steel Sheet 0.25 lurus (biru, merah, hijau tua)
60 Atap Steel Sheet 0.30 lurus (biru, merah, coklat, hijau tua, biru tua)
61 Atap Steel Sheet 0.35 lurus (coklat, biru, merah, hijau muda)
62 Atap Steel Sheet 0.40 lurus (biru)
63 Atap Steel Sheet 0.45 lurus (biru, merah, hijau muda)
64 Atap Steel Sheet 0.30 lengkung (silver)
65 Atap Steel Sheet 0.35 lengkung (silver)
66 Atap Steel Sheet 0.4 lengkung (silver)
67 Atap Steel Sheet 0.30 lengkung (biru, merah, coklat, hijau tua, biru tua)
68 Atap Steel Sheet 0.35 lengkung (coklat, biru, merah, hijau muda)
69 Atap Steel Sheet 0.40 lengkung (biru)
70 Atap Steel Sheet 0.45 lengkung (biru, merah, hijau muda)
71 Nok/Prabung Steel Sheet 0.30 lebar 333 mm (silver)
72 Nok/Prabung Steel Sheet 0.35 lebar 333 mm (silver)
73 Nok/Prabung Steel Sheet 0.40 lebar 333 mm (silver)
74 Nok/Prabung Steel Sheet 0.25 lebar 333 mm (biru, merah, hijau tua)
75 Nok/Prabung Steel Sheet 0.30 lebar 333 mm (biru, merah, coklat, hijau tua, biru tua)
76 Nok/Prabung Steel Sheet 0.35 lebar 333 mm (coklat, biru, merah, hijau muda)
77 Nok/Prabung Steel Sheet 0.40 lebar 333 mm (biru)
78 Nok/Prabung Steel Sheet 0.45 lebar 333 mm (biru, merah, hijau muda)
79 Nok/Prabung Steel Sheet 0.30 lebar 500 mm (silver)
80 Nok/Prabung Steel Sheet 0.35 lebar 500 mm (silver)
81 Nok/Prabung Steel Sheet 0.40 lebar 500 mm (silver)
82 Nok/Prabung Steel Sheet 0.25 lebar 500 mm (biru, merah, hijau tua)
83 Nok/Prabung Steel Sheet 0.30 lebar 500 mm (biru, merah, coklat, hijau tua, biru tua)
84 Nok/Prabung Steel Sheet 0.35 lebar 500 mm (coklat, biru, merah, hijau muda)
85 Nok/Prabung Steel Sheet 0.40 lebar 500 mm (biru)
86 Nok/Prabung Steel Sheet 0.45 lebar 500 mm (biru, merah, hijau muda)

H. BAHAN KACA
1 Kaca Polos, t = 3 mm
2 Kaca Polos, t = 5 mm
3 Kaca Polos, t = 8 mm
4 Kaca Polos, t = 12 mm
5 Kaca Rayben, t = 3 mm
6 Kaca Rayben, t = 5 mm
7 Kaca Rayben, t = 8 mm
8 Kaca Rayben, t = 12 mm
9 Kaca Cermin t = 3 mm
NO MATERIAL

10 Kaca Cermin t = 5 mm
11 Kaca Cermin t = 8 mm
12 Kaca Repsol, t = 5 mm
13 Kaca Patri, t = 5 mm
14 Sealent
15 Nako + Bingkai (80 x 15) x 10 daun polos
16 Nako + Bingkai (80 x 15) x 10 daun rayben
17 Kaca Es, t = 3 mm
18 Kaca Es, t = 5 mm
19 Kaca Raindown, t = 3 mm
20 Kaca Raindown, t = 5 mm
NO MATERIAL

I. BAHAN TRIPLEK
1 Triplek t = 3 mm
2 Triplek t = 6 mm
3 Triplek t =9 mm
4 Triplex t = 12 mm
5 Teakwood t = 3 mm
6 Formika t = 0,03 mm
7 Multiplex t = 6 mm
8 Multiplex t = 9 mm
9 Multiplex t = 10 mm
10 Multiplek t = 12 mm
11 Plywood 4' x 8' x 4mm
12 Panel GRC 120 x 240 x 40
13 GypsumBoard t = 9 mm
14 Super Plank 10 x 240 x 9 cm
15 Super Plank 20 x 240 x 9 cm
16 Super Plank 30 x 240 x 9 cm

J. BAHAN SANITASI
1 Wastafel setara Toto
2 Kloset duduk monoblok
3 Kloset duduk putih (setaraf TOTO)
4 Kloset duduk warna (setaraf TOTO)
5 Kloset jongkok (setaraf TOTO)
6 Kloset jongkok (setaraf INA)
7 Urinoir setaraf Toto
8 Bak air fibreglass uk. 55x55x60 cm
9 Shower Spray setara Toto
10 Sliding rail setara Toto
11 Floordrain stainless steel setara Toto
12 Floordrain PVC
13 Tempat Sabun Setara Toto
14 Kran zink setara Toto
15 Kitchenzink stainless steel 1 lubang
16 Kran dinding setara Toto
17 Kran air uk 1/2"
18 Pipa paralon dia 1/2"
19 Pipa paralon dia 3/4"
20 Pipa paralon dia 1"
21 Pipa paralon dia 2"
22 Pipa paralon dia 3"
23 Pipa paralon dia 4"
24 Pipa paralon dia 8"
25 Pipa PVC dia 1/2" AW ex Wavin
NO MATERIAL

26 Pipa PVC dia 3/4" AW ex Wavin


27 Pipa PVC dia 1" AW ex Wavin
28 Pipa PVC dia 2" AW ex Wavin
29 Pipa PVC dia 3" AW ex Wavin
30 Pipa PVC dia 4" AW ex Wavin
31 Pipa PVC dia 3/4" D ex Wavin
32 Pipa PVC dia 1" D ex Wavin
33 Pipa PVC dia 2" D ex Wavin
34 Pipa PVC dia 3" D ex Wavin
35 Pipa PVC dia 4" D ex Wavin
36 Stop kran dia 1/2" ex onda
NO MATERIAL

37 Stop kran dia 3/4" ex onda


38 Stop kran dia 1" ex onda
39 Tangki air 1000 liter
40 Tangki air 500 liter
41 Pelampung otomatis
42 Roof Drain Metal
43 Septicktank Biosel kap. 6,00 m3
44 Mesin Jet Pump kap.250 watt
45 Mesin Pompa tekan kap. 150 watt

K. BAHAN MINYAK (TANPA KEUNTUNGAN)


1 Minyak solar industri
2 Bensin industri
3 Minyak pelumas/Oli
4 Minyak tanah
5 Gas Elpiji Refill 12 kg
6 Sewa Molen
7 Sewa Alat Perakitan
8 Sewa Peralatan Las
9 Alat-alat bantu

L. BATU ALAM
1 Batu Andesit Ukuran 10 x 20 cm
2 Batu Andesit Ukuran 15 x 30 cm
3 Batu Andesit Ukuran 20 x 40 cm
4 Batu Andesit Ukuran 30 x 60 cm
5 Batu Candi Ukuran 10 x 20 cm
6 Batu Candi Ukuran 15 x 30 cm
7 Batu Candi Ukuran 20 x 40 cm
8 Batu Pacitoroso Ukuran 10 x 20 cm
9 Batu Pacitoroso Ukuran 15 x 30 cm
10 Batu Pacitoroso Ukuran 20 x 40 cm
11 Batu Bali Green Ukuran 10 x 20 cm
12 Batu Bali Green Ukuran 15 x 30 cm
13 Batu Bali Green Ukuran 20 x 40 cm
14 Batu Prasasti Peresmian (batu hitam) ukuran 40 x 60
15 Batu Prasasti Peresmian (batu hitam) ukuran 60 x 80
16 Batu Koral (batu taman)
17 Batu Granit Ukuran Lebar 60 cm

M. BAHAN ALAT-ALAT LISTRIK


1 Traffo HPL 400 Watt
2 Traffo HPL 250 Watt
3 Traffo HPL 125 Watt
NO MATERIAL

4 Traffo SON T 1000 Watt


5 Traffo SON T 400 Watt
6 Traffo SON T 250 Watt
7 Traffo SON T 150 Watt
8 Traffo SON T 125 Watt
9 Traffo SON T 70 Watt
10 Traffo Neon 40 Watt
11 Traffo Neon 20 Watt
12 HPL 250 Watt
13 HPL 125 Watt
14 Bola SON T 1000 Watt
NO MATERIAL

15 Bola SON T 400 Watt


16 Bola SON T 250 Watt
17 Bola SON T 150 Watt
18 Bola Lampu SON 70 Watt
19 Bola Lampu HPIT 400 Watt
20 Pijar 5 Watt
21 Pijar 25 Watt
22 Pijar 40 Watt
23 Pijar 60 Watt
24 Pijar 75 Watt
25 Pijar 100 Watt
26 Pijar 200 Watt
27 Neon 40 Watt
28 Neon 20 Watt
29 Neon 10 Watt
30 Lampu XL 14 Watt
31 Lampu Sorot 300 Watt
32 Lampu Superlox 25 Watt
33 Lampu Superlox 40 Watt
34 Lampu Fisikom 25 Watt
35 Lampu Fisikom 23 Watt
36 Lampu Fisikom 18 Watt
37 Lampu Mercury 125 Watt
38 Lampu Mercury 250 Watt
39 Lampu Sunyco 45 Watt
40 Lampu Matsuka 8 Watt
41 Lampu Matsuka 14 Watt
42 Lampu Matsuka 18 Watt
43 Lampu Matsuka 20 Watt
44 Lampu Matsuka 25 Watt
45 Lampu Par 38 Watt
46 SL 14 Watt
47 SL 18 Watt
48 SL 23 Watt
49 TL Rina 32 Watt
50 Bola Lampu Sorot 300 Watt
51 Hologen 500 Watt
52 Hologen 1.000 Watt
53 NYY 1 x 1.5 mm
54 NYY 1 x 2.5 mm
55 NYY 1 x 4 mm
56 NYY 1 x 6 mm
57 NYY 2 x 2.5 mm
58 NYY 2 x 4 mm
NO MATERIAL

59 NYY 2 x 6 mm
60 NYY 2 x 10 mm
61 NYY 3 x 4 mm
62 NYY 4 x 2.5 mm
63 NYY 4 x 4 mm
64 NYY 4 x 6 mm
65 NYY 4 x 10 mm
66 NYY 4 x 16 mm
67 NYY 4 x 25 mm
68 NYY 4 x 35 mm
69 NYY 4 x 50 mm
NO MATERIAL

70 NYN 2 x 2,5 mm
71 NYN 3 x 1,5 mm
72 NYN 3 x 2,5 mm
73 NYA 1 x 1,5 mm
74 NYA 1 x 2,5 mm
75 NYA 1 x 4 mm
76 NYA 1 x 6 mm
77 NYM 3 x 4 mm
78 NYM 2 x 4 mm
79 NYM 2 x 2,5 mm
80 NYM 2 x 1,5 mm
81 NYM 3 x 1,5 mm
82 NYM 3 x 2,5 mm
83 NYM 4 x 2,5 mm
84 NYM 4 x 4 mm
85 NYMHYM 2 x 0,75 mm
86 NYMHYM 2 x 1,5 mm
87 Kabel 3 x 2,5 mm
88 Kabel TC 2 x 10 mm
89 Kabel TC 2 x 16 mm
90 Box MCB 1 Group
91 Box Time Swich ( Lengkap pipa optic 1,5 +Klem + Kunci )
92 Box KWH Meter Uk. L 35 cm x T 50 cm x LS 25 cm
93 Fitting Gantung
94 Fitting Duduk
95 Fitting Atom
96 Fitting Gantung E 27
97 Fitting Duduk E 27
98 Full Breket
99 Isolasi Unibel
100 Icnitor SN 58
101 Inector
102 Ignator
103 Kap Hijau E 27
104 Kap Hijau E 40
105 Kop Skring
106 k. Skum 10-8
107 MCB 1.A
108 MCB 2.A
109 MCB 25 A
110 MCB 63 A
111 MCB 40 A
112 MCB 50 A
113 MCB 10 A
NO MATERIAL

114 MCB 16 A
115 MCB 6 A
116 MCB 32 A
117 MCB Box
118 Multi Tester
119 Macon Mec gmg-50 aC
120 Magnetic Contactor 100 A
121 NH Fuse 80 A
122 Ornamen Pijar
123 Obeng Plus
124 Obeng Minus
NO MATERIAL

125 Solar Seal / Photo Seal


126 Rangka Ring 32 Watt
127 Rel MCB
128 Saklar Tunggal setara Broco
129 Saklar Tunggal setara Panasonic
130 Saklar Double setara Broco
131 Saklar Double setara Panasonic
132 Saklar Engkel setara Broco
133 Saklar Tripel setara Broco
134 Saklar Tripel setara Panasonic
135 Solder Pistol
136 Solar Seal / Photo Seal
137 Steker Arde
138 Steker T
139 Sadel No. 6
140 Sadel No. 8
141 Sadel No. 9
142 Sadel No. 10
143 Sadel No. 12
144 Sadel No. 14
145 Sadel No. 19
146 Sadel No. 22
147 Stater
148 Tang Amper
149 Tang Potong
150 Tang Kombinasi
151 Time Swicht Theben
152 Taping Conector 1 baut
153 Taping Conector 2 baut
154 Tespen
155 Amatur Lampu Son T 250 Watt (lengkap)
156 Amatur Lampu Son T 150 Watt (lengkap)
157 Stang Ornamen Uk 2 x 1,5 meter ( lengkap Klim Tiang)
158 Stang Ornamen Uk 2 x 2 meter ( lengkap Klim Tiang)
159 Stang Ornamen Uk 2 x 3 meter ( lengkap Klim Tiang)
160 Stang Ornamen Uk 2 x 4 meter ( lengkap Klim Tiang)
161 Stang Ornamen Uk 2 x 6 meter ( lengkap Klim Tiang)
162 Wide Klem
163 Pole Breacket
164 Kapasitor
165 Kontraktor 100 A
166 Kontraktor 80 A
167 Kontraktor 32 A
NO MATERIAL
R HARGA SATUAN DASAR UPAH

HARGA SATUAN
DASAR (TIDAK
KODE TERMASUK
PROFIT &
OVERHEAD) (Rp)

L. 01 90,000.00
L. 02 100,000.00
L. 03 110,000.00
L. 04 120,000.00
L. 07 110,000.00
L. 08 130,000.00
L. 09 80,000.00
L. 10 100,000.00
L. 11 75,000.00
L. 16 95,000.00

R HARGA SATUAN DASAR BAHAN

HARGA SATUAN
DASAR (TIDAK
SATUAN TERMASUK
PROFIT &
OVERHEAD) (Rp)

M³ 251,400.00
M³ 319,400.00
M³ 336,700.00
M³ 421,200.00
M³ 371,000.00
M³ 393,100.00
M³ 418,700.00
M³ 458,100.00
M³ 467,500.00
M³ 581,900.00
M³ 469,100.00
Kg 13,900.00
Kg 30,000.00
M³ 100,100.00
M³ 100,100.00
Zak 75,000.00
Kg 1,500.00
M³ 235,000.00
M³ 320,200.00
Bh 3,000.00
HARGA SATUAN
DASAR (TIDAK
SATUAN TERMASUK
PROFIT &
OVERHEAD) (Rp)
Bh 3,500.00
Bh 1,500.00
Bh 1,600.00
Bh 1,000.00
Bh 2,500.00
Bh 2,100.00
Bh 17,500.00
Bh 54,100.00
Kotak 72,000.00
Kotak 75,500.00
HARGA SATUAN
DASAR (TIDAK
SATUAN TERMASUK
PROFIT &
OVERHEAD) (Rp)

Kotak 90,000.00
Kotak 90,000.00
Kotak 100,000.00
Kotak 111,000.00
Kotak 243,000.00
Kotak 243,000.00
Kotak 154,400.00
Kotak 155,000.00
Kotak 319,500.00
Kotak 323,000.00
Kotak 76,000.00
Kotak 89,000.00
M² 1,393,600.00
M² 297,000.00
Bh 11,600.00
Bh 61,000.00
Kg 16,600.00
Liter 38,300.00
Lembar 11,300.00
Btg 1,200,000.00
M³ 27,500.00
M² 4,000.00
bh 50,000.00
bh 35,000.00
M² 425,000.00
M² 375,000.00

M³ 10,142,500.00
M³ 9,621,000.00
M³ 7,936,100.00
M³ 7,617,200.00
M³ 9,567,900.00
M³ 9,412,000.00
M³ 13,020,900.00
M³ 10,416,700.00
M³ 10,000,000.00
M³ 11,154,500.00
M³ 10,058,300.00
M³ 11,015,700.00
M³ 10,928,600.00
M³ 10,273,400.00
M³ 6,699,200.00
M³ 6,510,400.00
HARGA SATUAN
DASAR (TIDAK
SATUAN TERMASUK
PROFIT &
OVERHEAD) (Rp)
M³ 5,227,600.00
M³ 5,739,800.00
M³ 8,100,000.00
M³ 19,500,000.00
M³ 15,000,000.00
M³ 11,500,000.00
M³ 3,828,100.00
M³ 3,971,400.00
M³ 4,024,900.00
M³ 4,153,700.00
M³ 2,924,400.00
HARGA SATUAN
DASAR (TIDAK
SATUAN TERMASUK
PROFIT &
OVERHEAD) (Rp)

M³ 3,135,000.00
M³ 3,789,700.00
M³ 4,583,300.00
M³ 4,108,800.00
M³ 4,199,200.00
M³ 3,993,000.00
M³ 4,557,300.00
M³ 2,225,000.00
M³ 1,963,500.00
M³ 13,252,300.00
M³ 12,682,300.00
M³ 6,250,000.00
M³ 6,377,300.00
M³ 10,819,800.00
M³ 11,188,300.00
M³ 2,113,100.00
M³ 1,064,800.00
Btg 18,000.00
Btg 30,700.00
Btg 5,600.00
Btg 8,300.00
Btg 9,500.00
Btg 75,000.00
Btg 91,200.00
M³ 266,700.00
Btg 11,000.00
M' 62,500.00
Btg 10,000.00

Lbr 3,000.00
Kg 27,200.00
Kg 58,000.00
Kg 54,000.00
Kg 31,500.00
Kg 92,600.00
Kg 99,500.00
Kg 98,300.00
Kg 52,000.00
Kg 70,400.00
Kg 86,000.00
Kg 23,700.00
Kg 26,600.00
Kg 43,900.00
HARGA SATUAN
DASAR (TIDAK
SATUAN TERMASUK
PROFIT &
OVERHEAD) (Rp)
Kg 50,600.00
Ltr 22,100.00
Ltr 62,400.00
Ltr 32,000.00
Kg 48,000.00
Kg 13,100.00
Kg 17,100.00
Kg 35,900.00
Kg 21,100.00
Kg 15,700.00
Ltr 60,000.00
HARGA SATUAN
DASAR (TIDAK
SATUAN TERMASUK
PROFIT &
OVERHEAD) (Rp)

Ltr 58,400.00
Bh 22,500.00
Kg 65,000.00
Kg 95,000.00
Kg 30,000.00
Kg 39,000.00
Kg 78,500.00

Kg 10,600.00
Kg 12,600.00
Kg 9,400.00
Kg 9,300.00
Kg 9,100.00
Kg 20,000.00
Kg 17,900.00
Kg 15,500.00
Btg 5,000.00
bh 16,000.00
bh 15,000.00
Bh 310,000.00
Kg 13,500.00
Btg 5,300.00
Kg 28,500.00
M² 26,300.00
M² 16,000.00
Btg 118,300.00
Btg 93,100.00
Btg 139,800.00
Btg 205,000.00
Btg 246,300.00
Btg 302,900.00
Btg 390,000.00
Btg 582,500.00
Btg 925,000.00
Btg 1,071,300.00
Btg 1,721,700.00
M² 621,700.00
Meter 85,000.00
Meter 95,000.00
Unit 1,500,000.00
Meter 120,000.00
Meter 65,000.00
Meter 65,000.00
HARGA SATUAN
DASAR (TIDAK
SATUAN TERMASUK
PROFIT &
OVERHEAD) (Rp)
M² 235,200.00
M² 272,500.00
M² 250,000.00
M² 304,100.00
M² 175,000.00
M² 225,400.00
M² 193,900.00
M² 257,000.00
btg 52,500.00
btg 82,000.00
btg 75,000.00
HARGA SATUAN
DASAR (TIDAK
SATUAN TERMASUK
PROFIT &
OVERHEAD) (Rp)

bh 5,700.00
bh 6,000.00
bh 800.00
bh 800.00
bh 800.00
M² 908,700.00
Lbr 1,339,100.00
M² 129,100.00
btg 119,600.00
btg 69,600.00
Kg 20,500.00
Kg 11,000.00
Buah 453,000.00

Bh 254,000.00
Bh 14,400.00
Bh 15,400.00
Bh 135,000.00
Bh 18,800.00
Bh 27,500.00
Bh 17,000.00
Bh 6,400.00
Bh 179,100.00
Bh 162,500.00
Bh 47,500.00
Bh 55,000.00
Bh 60,800.00
Bh 175,500.00
Bh 52,500.00
Kg 20,900.00
Kg 20,500.00
Kg 31,400.00
Kg 18,100.00
Kg 21,300.00
Kg 10,700.00
Bh 1,300.00
Bh 1,500.00
Kg 48,300.00
Bh 2,500.00
Bh 300.00
Bh 300.00
Bh 400.00
Bh 500.00
HARGA SATUAN
DASAR (TIDAK
SATUAN TERMASUK
PROFIT &
OVERHEAD) (Rp)
Bh 500.00
Bh 500.00
Bh 700.00
Bh 700.00
Bh 600.00
Bh 500.00
Unit 4,208,700.00
Unit 2,104,300.00
Unit 1,578,300.00
Unit 631,300.00
HARGA SATUAN
DASAR (TIDAK
SATUAN TERMASUK
PROFIT &
OVERHEAD) (Rp)

Lbr 5,300.00
Lbr 57,200.00
M² 68,400.00
Lbr 63,000.00
Lbr 66,600.00
Lbr 66,600.00
Lbr 66,600.00
Lbr 51,800.00
Lbr 51,800.00
Lbr 51,800.00
Lbr 270,000.00
Lbr 154,000.00
Lbr 193,000.00
Lbr 48,500.00
Lbr 54,000.00
Lbr 94,500.00
Lbr 95,000.00
Lbr 96,000.00
Lbr 85,000.00
Lbr 89,500.00
Lbr 89,500.00
M 55,000.00
Lbr 92,000.00
Lbr 64,000.00
Lbr 53,000.00
Lbr 80,000.00
Lbr 80,000.00
M² 81,300.00
M² 111,900.00
M² 47,000.00
M² 64,000.00
M² 100,000.00
M² 112,300.00
M² 78,300.00
Bh 46,000.00
Bh 70,000.00
M' 50,000.00
M' 96,900.00
M' 109,500.00
M' 123,100.00
Lbr 64,000.00
Lbr 47,400.00
HARGA SATUAN
DASAR (TIDAK
SATUAN TERMASUK
PROFIT &
OVERHEAD) (Rp)
Lbr 49,900.00
Lbr 66,300.00
M' 20,000.00
Lbr 54,300.00
M² 75,900.00
M² 120,100.00
M² 70,000.00
M² 83,800.00
M² 80,000.00
M² 55,000.00
Lbr 46,500.00
HARGA SATUAN
DASAR (TIDAK
SATUAN TERMASUK
PROFIT &
OVERHEAD) (Rp)

M² 52,600.00
Lbr 15,200.00
M 55,000.00
M 60,000.00
M 65,000.00
M 50,000.00
M 57,000.00
M 67,000.00
M 72,000.00
M 77,000.00
M 60,500.00
M 66,000.00
M 71,500.00
M 62,700.00
M 73,700.00
M 79,200.00
M 84,700.00
M 22,000.00
M 24,000.00
M 26,000.00
M 20,000.00
M 22,800.00
M 26,800.00
M 28,800.00
M 30,800.00
M 33,000.00
M 36,000.00
M 39,000.00
M 30,000.00
M 34,200.00
M 40,200.00
M 43,200.00
M 46,200.00

M² 80,000.00
M² 82,500.00
M² 140,000.00
M² 260,000.00
M² 65,000.00
M² 62,500.00
M² 125,000.00
M² 241,800.00
M² 85,000.00
HARGA SATUAN
DASAR (TIDAK
SATUAN TERMASUK
PROFIT &
OVERHEAD) (Rp)
M² 125,000.00
M² 190,000.00
M² 450,000.00
M² 2,350,000.00
Kg 106,900.00
Bh 250,000.00
Bh 300,000.00
M² 85,000.00
M² 145,000.00
M² 85,000.00
M² 145,000.00
HARGA SATUAN
DASAR (TIDAK
SATUAN TERMASUK
PROFIT &
OVERHEAD) (Rp)

Lbr 70,000.00
Lbr 120,000.00
Lbr 220,000.00
Lbr 300,000.00
Lbr 140,000.00
Lbr 110,000.00
Lbr 102,000.00
Lbr 210,000.00
Lbr 278,000.00
Lbr 282,100.00
Lbr 115,000.00
Lbr 79,700.00
Lbr 74,600.00
Lbr 65,000.00
Lbr 65,000.00
Lbr 65,000.00

Bh 966,100.00
Bh 2,962,700.00
Bh 2,246,800.00
Bh 2,401,200.00
Bh 294,800.00
Bh 191,000.00
Unit 1,878,300.00
Bh 280,000.00
Unit 230,400.00
Unit 328,700.00
Bh 319,100.00
Bh 18,500.00
Bh 65,200.00
Bh 307,000.00
Unit 650,000.00
Bh 150,000.00
Bh 32,500.00
Btg 21,100.00
Btg 27,100.00
Btg 40,000.00
Btg 66,500.00
Btg 114,000.00
Btg 187,700.00
Btg 655,200.00
Btg 21,300.00
HARGA SATUAN
DASAR (TIDAK
SATUAN TERMASUK
PROFIT &
OVERHEAD) (Rp)
Btg 28,500.00
Btg 40,500.00
Btg 79,600.00
Btg 156,400.00
Btg 252,500.00
Btg 17,100.00
Btg 22,500.00
Btg 45,400.00
Btg 77,000.00
Btg 116,900.00
Bh 39,700.00
HARGA SATUAN
DASAR (TIDAK
SATUAN TERMASUK
PROFIT &
OVERHEAD) (Rp)

Bh 51,200.00
Bh 115,500.00
Bh 1,397,500.00
Bh 813,300.00
Bh 75,000.00
Bh 75,000.00
Unit 115,000.00
Unit 1,440,000.00
Unit 550,000.00

Ltr 8,100.00
Ltr 7,400.00
Ltr 28,800.00
Ltr 9,600.00
Kg 28,800.00
Set 170,000.00
Set 70,000.00
Set 70,000.00
Set 66,400.00

M² 170,000.00
M² 200,000.00
M² 220,000.00
M² 260,000.00
M² 170,000.00
M² 200,000.00
M² 220,000.00
M² 170,000.00
M² 200,000.00
M² 220,000.00
M² 170,000.00
M² 200,000.00
M² 220,000.00
buah 2,500,000.00
buah 4,000,000.00
kg 7,500.00
M² 1,200,000.00

Buah 240,000.00
Buah 208,000.00
Buah 123,000.00
HARGA SATUAN
DASAR (TIDAK
SATUAN TERMASUK
PROFIT &
OVERHEAD) (Rp)
Buah 1,978,000.00
Buah 470,000.00
Buah 267,200.00
Buah 184,300.00
Buah 166,000.00
Buah 130,300.00
Buah 37,000.00
Buah 37,000.00
Buah 65,000.00
Buah 37,500.00
Buah 690,000.00
HARGA SATUAN
DASAR (TIDAK
SATUAN TERMASUK
PROFIT &
OVERHEAD) (Rp)

Buah 145,000.00
Buah 136,000.00
Buah 118,800.00
Buah 117,500.00
Buah 240,000.00
Buah 2,500.00
Buah 4,800.00
Buah 4,800.00
Buah 5,800.00
Buah 5,800.00
Buah 7,000.00
Buah 12,000.00
Buah 15,200.00
Buah 11,700.00
Buah 8,800.00
Buah 30,000.00
Buah 40,500.00
Buah 9,200.00
Buah 9,900.00
Buah 39,000.00
Buah 33,000.00
Buah 31,000.00
Buah 34,300.00
Buah 62,000.00
Buah 84,000.00
Buah 23,500.00
Buah 27,000.00
Buah 31,000.00
Buah 36,000.00
Buah 39,000.00
Buah 98,000.00
Buah 29,500.00
Buah 36,500.00
Buah 39,500.00
Buah 33,900.00
Buah 31,500.00
Buah 34,800.00
Buah 46,000.00
roll 176,000.00
Meter 2,800.00
Meter 4,500.00
Meter 6,700.00
Meter 15,000.00
Meter 20,000.00
HARGA SATUAN
DASAR (TIDAK
SATUAN TERMASUK
PROFIT &
OVERHEAD) (Rp)
Meter 25,000.00
Meter 38,800.00
Meter 24,000.00
Meter 22,000.00
Meter 30,000.00
Meter 37,900.00
Meter 64,000.00
Meter 88,500.00
Meter 136,000.00
Meter 180,000.00
Meter 244,000.00
HARGA SATUAN
DASAR (TIDAK
SATUAN TERMASUK
PROFIT &
OVERHEAD) (Rp)

Meter 8,000.00
Meter 7,200.00
Meter 10,200.00
Meter 4,200.00
Meter 6,300.00
Meter 8,600.00
Meter 12,800.00
Meter 22,000.00
Meter 16,000.00
Meter 10,000.00
Meter 8,000.00
Meter 11,000.00
Meter 13,000.00
Meter 18,000.00
Meter 26,000.00
Meter 6,000.00
Meter 9,000.00
Meter 510,000.00
Meter 6,000.00
Meter 6,500.00
Buah 4,000.00
Set 2,695,700.00
Buah 781,700.00
Buah 3,800.00
Buah 11,800.00
Buah 3,500.00
Buah 11,000.00
Buah 24,800.00
Buah 47,500.00
Buah 8,300.00
Buah 63,000.00
Buah 73,500.00
Buah 59,200.00
Buah 11,800.00
Buah 17,000.00
Buah 7,000.00
Buah 900.00
Buah 11,000.00
Buah 38,500.00
Buah 33,000.00
Buah 159,000.00
Buah 31,500.00
Buah 159,000.00
Buah 39,500.00
HARGA SATUAN
DASAR (TIDAK
SATUAN TERMASUK
PROFIT &
OVERHEAD) (Rp)
Buah 44,800.00
Buah 33,000.00
Buah 33,000.00
Buah 2,000.00
Buah 94,500.00
Buah 484,500.00
Buah 670,000.00
Buah 28,000.00
Buah 89,000.00
Buah 13,000.00
Buah 13,000.00
HARGA SATUAN
DASAR (TIDAK
SATUAN TERMASUK
PROFIT &
OVERHEAD) (Rp)

Buah 44,300.00
Buah 48,000.00
Buah 10,500.00
Buah 16,500.00
Buah 17,000.00
Buah 19,000.00
Buah 25,000.00
Buah 17,000.00
Buah 21,000.00
Buah 38,500.00
Buah 20,000.00
Buah 62,000.00
Buah 10,500.00
Buah 23,500.00
Bungkus 7,000.00
Bungkus 8,000.00
Bungkus 8,000.00
Bungkus 9,500.00
Bungkus 10,500.00
Bungkus 14,500.00
Bungkus 21,000.00
Bungkus 26,000.00
Buah 6,500.00
Buah 1,024,000.00
Buah 38,000.00
Buah 48,000.00
Buah 388,500.00
Buah 16,000.00
Buah 21,000.00
Buah 21,000.00
Set 3,856,500.00
Set 3,304,300.00
Btg 530,400.00
Btg 667,800.00
Btg 739,300.00
Btg 848,700.00
Btg 934,700.00
Buah 5,800.00
Buah 21,600.00
Buah 181,200.00
Buah 598,100.00
Buah 460,300.00
Buah 383,500.00
HARGA SATUAN
DASAR (TIDAK
SATUAN TERMASUK
PROFIT &
OVERHEAD) (Rp)

Anda mungkin juga menyukai