Anda di halaman 1dari 8

BILL OF QUANTITY

REKAPITULASI

PEKERJAAN : PEMBANGUNAN RUANG TUNGGU TAMBATAN PERAHU


LOKASI : DESA ITAWAKA - KAB. MALUKU TENGAH
TAHUN ANGGARAN : 2016

JUMLAH HARGA
NO URAIAN PEKERJAAN
(Rp)
I PEKERJAAN PERSIAPAN 10,450,000.00
II PEKERJAAN TANAH 221,340.00
III PEKERJAAN PASANGAN DAN BETON 77,175,000.00
IV PEKERJAAN LANTAI DAN PLESTERAN 33,366,200.00
V PEKERJAAN KAYU DAN PLAFON 54,555,600.00
VI PEKERJAAN PENGECATAN 38,738,160.00
VII PASANG INSTALASI LISTRIK 5,725,000.00
VIII PEKERJAAN PENGGANTUNG DAN PENGUNCI 8,022,000.00
IX PEKERJAAN SANTAIR 14,196,000.00
X PEKERJAAN LAIN-LAIN 7,550,000.00
JUMLAH 249,999,300.00
PPN 10% 24,999,930.00
TOTAL BIAYA PEKERJAAN 274,999,230.00
JUMLAH TOTAL DIBULATKAN 275,000,000.00
Terbilang : Dua Ratus Tujuh Puluh Lima Juta Rupiah

Ambon, 19 September 2018

Konsultan Perencana
KELOMPOK IV
mber 2018
BILL OF QUANTITY
(R A B)

PEKERJAAN : PEMBANGUNAN RUANG TUNGGU TAMBATAN PERAHU


LOKASI : DESA ITAWAKA - KAB. MALUKU TENGAH
TAHUN ANGGARAN : 2016

Harga Jumlah Durasi


Bobot
No. Uraian Pekerjaan Satuan
Volume Satuan Harga (Mingg Jangka Wa
(%)
(Rp) (Rp) u)

1 2 3 4 5 6
I PEKERJAAN PERSIAPAN
1 Pengukuran dan Pemasangan Bouwplan M' 21.00 100,000 2,100,000 0.840 1
2 Papan Nama Proyek Ls 1.00 350,000 350,000 0.140 1
3 Pembuatan Gudang/Kantor Sementara M2 8.00 1,000,000 8,000,000 3.200 2
Jumlah I ###
II PEKERJAAN TANAH
1 Galian Tanah M3 1.94 105,000 203,700 0.081 1
2 Urugan Tanah Kembali M3 0.49 36,000 17,640 0.007 1
Jumlah II 221,340
III PEKERJAAN PASANGAN DAN BETON
1 Pasangan Batu Bata Untuk Dinding ad. 1 M2 111.4 175,000 19,495,000 7.798 2
2 Pekerjaan Beton :
- Balok Lantai Beton 25/35 ad. 1:2:3 (15 M3 3.41 5,000,000 6,450,000 2.580 2
- Ring Balok Beton 15/25 ad. 1:2:3 (170 M3 1.29 5,000,000 6,650,000 2.660 1
- Kolom Beton 25/25 ad. 1:2:3 (155 Kg/M M3 1.33 5,000,000 5,100,000 2.040 1
- Kolom Beton 15/15 ad. 1:2:3 (247 Kg/M M3 1.02 6,000,000 30,240,000 ### 2
- Plat Lantai T = 12 cm ad. 1:2:3 (110 K M3 5.04 4,200,000 5,040,000 2.016 2
-Pondasi Beton ad. 1:2:3 (110 Kg/M3 M3 1.20 3,500,000 4,200,000 1.680 1
Jumlah III ###
IV PEKERJAAN LANTAI DAN PLESTERAN
1 Rabat Beton Bawah Lantai ad. 1:3:5 M3 2.10 1,300,000 2,730,000 1.092 1
2 Lantai Tegal Keramik 40x40 cm ad. 1:3 M2 38.5 350,000 13,475,000 5.390 1
3 Plesteran Dinding ad. 1:5 M2 245.2 70,000 17,161,200 6.864 2
Jumlah IV ###
V PEKERJAAN KAYU DAN PLAFON
1 Kuda-kuda Kayu Kelas I M3 0.84 5,000,000 4,200,000 1.680 2
2 Gording Kayu Kelas II M3 0.31 3,500,000 1,085,000 0.434 1
3 Kosen Pintu Jendela Kayu Kelas I M3 0.59 5,500,000 3,245,000 1.298 1
4 Daun Pintu Panel Papan Kayu Kelas I M2 4.80 900,000 4,320,000 1.728 2
5 Daun Jendela Kaca Polos 3 mm M2 4.00 500,000 2,000,000 0.800 1
6 Atap Zink Gelombang BJLS 25 M2 117 105,000 12,287,100 4.915 1
7 Bubungan Zink Datar M' 21.90 65,000 1,423,500 0.569 1
8 Lisplank Papan Kayu Kelas I M' 32.00 150,000 4,800,000 1.920 1
9 List Plafond M' 78.00 90,000 7,020,000 2.808 1
10 Rangka Plafond Kayu Kelas II M2 63.00 155,000 9,765,000 3.906 1
11 Plafond Triplek 3 mm M2 63.00 70,000 4,410,000 1.764 1
Jumlah V ###
VI PEKERJAAN PENGECATAN
1 Cat Dinding Dengan Cat Tembok M2 245.2 90,000 22,064,400 8.826 2
2 Cat Plafond Dengan Cat Tembok M2 63.00 100,000 6,300,000 2.520 1
3 Cat Kosen Pintu Dengan Cat Kayu M2 15.36 66,000 1,013,760 0.406 1
4 Cat Pintu Bingkai Jendela Ventilasi Deng M2 14.40 650,000 9,360,000 3.744 1
Jumlah VI ###
VII PASANG INSTALASI LISTRIK
1 Pasang Instalasi Listrik Titik 18.00 250,000 4,500,000 1.800 1
2 Saklar Tunggal Buah 3.00 35,000 105,000 0.042 1
3 Saklar Ganda Buah 2.00 40,000 80,000 0.032 1
4 Stop Kontak Buah 2.00 35,000 70,000 0.028 1
5 Lampu Phillips 18 Watt Buah 4.00 50,000 200,000 0.080 1
6 Lampu Phillips 8 Watt Buah 7.00 30,000 210,000 0.084 1
7 Panel MCB 1 group Buah 1.00 60,000 60,000 0.024 1
8 Arde/Pertanahan Buah 1.00 500,000 500,000 0.200 1
Jumlah VII 5,725,000
VIII PEKERJAAN PENGGANTUNG DAN PENGUNCI
1 Kunci Tanam 2 Slaag Buah 4.00 450,000 1,800,000 0.720 1
2 Engsel Pintu 4" Buah 12.00 150,000 1,800,000 0.720 1
3 Grendel Pintu Buah 2.00 145,000 290,000 0.116 1
4 Angker Kosen Buah 52.00 41,000 2,132,000 0.853 1
5 Mur baut Buah 80.00 25,000 2,000,000 0.800 1
Jumlah VIII 8,022,000
IX PEKERJAAN SANTAIR
1 Dinding Tegel Keramik 10/20 M2 20.4 390,000 7,956,000 3.182 1
2 Lantai Tegel Keramik 20/20 M2 7.00 400,000 2,800,000 1.120 1
3 Bak Air KM/WC 0.8 m3 Bh 2.00 950,000 1,900,000 0.760 1
4 Floor Drain Bh 2.00 90,000 180,000 0.072 1
5 Pipa PVC Diameter 4" M' 4.00 340,000 1,360,000 0.544 1
Jumlah IX ###
X PEKERJAAN LAIN-LAIN
1 Pengadaan Kursi Besi (5 sheet) Bh 4.00 1,200,000 4,800,000 1.920 1
2 Meja 1/2 biro Bh 1.00 500,000 500,000 0.200 1
3 Kursi Chitos Bh 1.00 500,000 500,000 0.200 1
4 Dokumentasi & Pelaporan Ls 1.00 750,000 750,000 0.300 22
5 Pembersihan Akhir Ls 1.00 1,000,000 1,000,000 0.400 1
Jumlah X 7,550,000
Jumlah ###
100
PPN 10% 24,999,930
Total Biaya Pekerjaan ###
Jangka Waktu Pelaksanaan Pekerjaan ( 150 Hari kalender )
Ket
Minggu ke-
7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22

Anda mungkin juga menyukai