23 A. 4.2.1.21 Pemasangan 1m2 Rangka Besi hollow1x40.40.2mm, modul 60 x 60 cm, untuk Plafond
0.3500 Pekerja O/H 120,000.00
0.3500 Tukang O/H 200,000.00
0.0350 Kepala Tukang O/H 160,000.00
0.0180 Mandor O/H 180,000.00
4.0000 Hollow 40.40.2 mm m 70,833.33
1.0000 Assesoris (perkuatan, las dll) Ls 70,833.33
Jumlah
24 A.4.5.1.5 Pemasangan 1 m2 langit-langit tripleks ukuran (120 x 240) cm, tebal 3 mm, 4 mm & 6 mm
0.1000 Pekerja O/H 120,000.00
0.1000 Tukang O/H 200,000.00
0.0100 Kepala Tukang O/H 160,000.00
0.0050 Mandor O/H 180,000.00
0.3750 Tripleks 120x240 Lembar 97,500.00
0.0300 Paku Kg 42,500.00
Jumlah
25 A. 4.2.1.22 Pemasangan 1m2 Atap Plana rangka atap baja canai dingin profil C75
0.7340 Pekerja O/H 120,000.00
0.7340 Tukang O/H 200,000.00
0.0730 Kepala Tukang O/H 160,000.00
0.0370 Mandor O/H 180,000.00
3.0650 Baja Ringan Canai Dingin C75 Kg 44,117.65
Jumlah
29 A.4.6.1.1 Pembuatan dan pemasangan 1 m3 kusen pintu dan kusen jendela, kayu kelas I
7.0000 Pekerja O/H 120,000.00
21.0000 Tukang O/H 200,000.00
2.1000 Kepala Tukang O/H 160,000.00
0.3500 Mandor O/H 180,000.00
1.1000 Kayu Balok Kelas I M3 5,234,852.49
1.2500 Paku Kg 30,000.00
1.0000 Lem Kayu Kg 90,000.00
Jumlah
31 A.4.6.1.6 Pembuatan dan pemasangan 1 m2 pintu dan jendela kaca, Kayu kelas I
0.8000 Pekerja O/H 120,000.00
2.4000 Tukang O/H 200,000.00
0.2400 Kepala Tukang O/H 160,000.00
0.0400 Mandor O/H 180,000.00
0.0240 Kayu Papan Kelas I M3 5,234,852.49
0.3000 Lem Kayu Kg 90,000.00
Jumlah
46 A.4.7.1.4 1 m2 Pengecatan bidang kayu baru (1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup)
0.1500 Pekerja O/H 120,000.00
0.0080 Tukang O/H 200,000.00
0.1500 Kepala Tukang O/H 160,000.00
0.0080 Mandor O/H 180,000.00
0.0500 Cat menie Kg 50,000.00
0.0500 Plamur Kg 17,500.00
0.0500 Cat Dasar Kg 45,000.00
0.0500 Cat kayu Kg 75,000.00
0.0500 Kuas 3" eterna Bh 28,750.00
0.0500 Pengencer Kg 50,000.00
0.0500 Amplas Lbr 37,500.00
Jumlah
47 A.4.7.1.10 Pengecatan 1 m2 tembok baru (1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup)
0.0200 Pekerja O/H 120,000.00
0.0630 Tukang O/H 200,000.00
0.0060 Kepala Tukang O/H 160,000.00
0.0030 Mandor O/H 180,000.00
0.1000 Plamur Kg 17,500.00
0.1000 Cat Dasar Kg 45,000.00
0.2600 Cat Tembok Kg 70,000.00
Jumlah
- - 12,000.00 12,000.00
- - 20,000.00 20,000.00
- - 1,600.00 1,600.00
- - 900.00 900.00
26,218.23 - - 26,218.23
600.00 - - 600.00
152,939.67 - - 152,939.67
179,757.90 - 34,500.00 214,257.90
- - 90,000.00 90,000.00
- - 4,500.00 4,500.00
- - 94,500.00 94,500.00
- - 60,000.00 60,000.00
- - 9,000.00 9,000.00
- - 69,000.00 69,000.00
- - 36,000.00 36,000.00
- - 1,800.00 1,800.00
2,306,531.98 - - 2,306,531.98
- - 37,800.00 2,344,331.98
- - 60,000.00 60,000.00
- - 9,000.00 9,000.00
2,723,645.98 - - 2,723,645.98
- - 69,000.00 2,792,645.98
- - 60,000.00 60,000.00
- - 9,000.00 9,000.00
2,445,569.98 - - 2,445,569.98
- - 69,000.00 2,514,569.98
- - 93,600.00 93,600.00
- - 78,000.00 78,000.00
- - 6,240.00 6,240.00
- - 7,020.00 7,020.00
2,445,569.98 - - 2,445,569.98
830,351.51 - - 830,351.51
3,275,921.49 - 184,860.00 3,460,781.49
- - 180,000.00 180,000.00
- - 150,000.00 150,000.00
- - 12,000.00 12,000.00
- - 13,500.00 13,500.00
2,445,569.98 - - 2,445,569.98
970,136.61 - - 970,136.61
999,497.19 - - 999,497.19
4,415,203.78 - 355,500.00 4,770,703.78
- - 198,000.00 198,000.00
- - 55,000.00 55,000.00
- - 4,480.00 4,480.00
- - 14,940.00 14,940.00
1,393,974.89 - - 1,393,974.89
2,416,413.88 - - 2,416,413.88
939,088.02 - - 939,088.02
- - - -
4,749,476.79 - 272,420.00 5,021,896.79
- - 198,000.00 198,000.00
- - 55,000.00 55,000.00
- - 4,480.00 4,480.00
- - 14,940.00 14,940.00
1,374,953.79 - - 1,374,953.79
1,642,685.30 - - 1,642,685.30
1,136,790.76 - - 1,136,790.76
- - - -
4,154,429.85 - 272,420.00 4,426,849.85
- - 8,400.00 8,400.00
- - 14,000.00 14,000.00
- - 1,120.00 1,120.00
- - 720.00 720.00
214,135.76 - - 214,135.76
7,500.00 - - 7,500.00
221,635.76 - 24,240.00 245,875.76
JUMLAH/1 KG 24,587.58
- - 8,400.00 8,400.00
- - 14,000.00 14,000.00
- - 1,120.00 1,120.00
- - 720.00 720.00
148,832.10 - - 148,832.10
7,500.00 - - 7,500.00
156,332.10 - 24,240.00 180,572.10
JUMLAH/1 KG 18,057.21
- - 62,400.00 62,400.00
- - 52,000.00 52,000.00
- - 4,160.00 4,160.00
- - 4,680.00 4,680.00
98,318.36 - - 98,318.36
9,000.00 - - 9,000.00
2,945.00 - - 2,945.00
110,263.36 - 123,240.00 233,503.36
- - 79,200.00 79,200.00
- - 66,000.00 66,000.00
- - 5,280.00 5,280.00
- - 5,940.00 5,940.00
87,394.10 - - 87,394.10
12,000.00 - - 12,000.00
5,890.00 - - 5,890.00
32,772.79 - - 32,772.79
87,500.00 - - 87,500.00
60,000.00 - - 60,000.00
285,556.89 - 156,420.00 441,976.89
- - 79,200.00 79,200.00
- - 66,000.00 66,000.00
- - 5,280.00 5,280.00
- - 5,940.00 5,940.00
87,394.10 - - 87,394.10
12,000.00 - - 12,000.00
5,890.00 - - 5,890.00
71,727.34 - - 71,727.34
87,500.00 - - 87,500.00
60,000.00 - - 60,000.00
324,511.44 - 156,420.00 480,931.44
- - 79,200.00 79,200.00
- - 66,000.00 66,000.00
- - 5,280.00 5,280.00
- - 5,940.00 5,940.00
87,394.10 - - 87,394.10
12,000.00 - - 12,000.00
5,890.00 - - 5,890.00
59,772.79 - - 59,772.79
87,500.00 - - 87,500.00
180,000.00 - - 180,000.00
432,556.89 - 156,420.00 588,976.89
- - 30,000.00 30,000.00
- - 25,000.00 25,000.00
- - 2,080.00 2,080.00
- - 2,340.00 2,340.00
160,225.00 - - 160,225.00
58,327.23 - - 58,327.23
16,500.00 - - 16,500.00
86,494.95 - - 86,494.95
321,547.18 - 59,420.00 380,967.18
- - 31,200.00 31,200.00
- - 26,000.00 26,000.00
- - 2,080.00 2,080.00
- - 2,340.00 2,340.00
167,259.09 - - 167,259.09
59,517.58 - - 59,517.58
16,500.00 - - 16,500.00
3,375.00 - - 3,375.00
246,651.67 - 61,620.00 308,271.67
- - 48,000.00 48,000.00
- - 40,000.00 40,000.00
- - 3,200.00 3,200.00
- - 3,960.00 3,960.00
61,707.83 - - 61,707.83
59,585.41 - - 59,585.41
121,293.24 - 95,160.00 216,453.24
- - 36,000.00 36,000.00
- - 30,000.00 30,000.00
- - 2,400.00 2,400.00
- - 2,700.00 2,700.00
30,853.92 - - 30,853.92
49,974.86 - - 49,974.86
80,828.77 - 71,100.00 151,928.77
- - 48,000.00 48,000.00
- - 40,000.00 40,000.00
- - 3,200.00 3,200.00
- - 3,960.00 3,960.00
41,138.55 - - 41,138.55
67,273.85 - - 67,273.85
108,412.40 - 95,160.00 203,572.40
- - 36,000.00 36,000.00
- - 20,000.00 20,000.00
- - 1,600.00 1,600.00
- - 2,700.00 2,700.00
331,792.99 - - 331,792.99
85,526.77 - - 85,526.77
76,884.40 - - 76,884.40
494,204.16 - 60,300.00 554,504.16
- - 36,000.00 36,000.00
- - 20,000.00 20,000.00
- - 1,600.00 1,600.00
- - 2,700.00 2,700.00
331,792.99 - - 331,792.99
68,445.22 - - 68,445.22
82,650.73 - - 82,650.73
482,888.94 - 60,300.00 543,188.94
- - 24,000.00 24,000.00
- - 20,000.00 20,000.00
- - 1,600.00 1,600.00
- - 1,800.00 1,800.00
19,343.21 - - 19,343.21
19,343.21 - 47,400.00 66,743.21
untuk Plafond
- - 42,000.00 42,000.00
- - 70,000.00 70,000.00
- - 5,600.00 5,600.00
- - 3,240.00 3,240.00
283,333.33 - - 283,333.33
70,833.33 - - 70,833.33
354,166.67 - 120,840.00 475,006.67
m, 4 mm & 6 mm
- - 12,000.00 12,000.00
- - 20,000.00 20,000.00
- - 1,600.00 1,600.00
- - 900.00 900.00
36,562.50 - - 36,562.50
1,275.00 - - 1,275.00
37,837.50 - 34,500.00 72,337.50
- - 88,080.00 88,080.00
- - 146,800.00 146,800.00
- - 11,680.00 11,680.00
- - 6,660.00 6,660.00
135,220.59 - - 135,220.59
135,220.59 - 253,220.00 388,440.59
- - 18,000.00 18,000.00
- - 150,000.00 150,000.00
- - 12,800.00 12,800.00
- - 1,080.00 1,080.00
89,250.00 - - 89,250.00
10,000.00 - - 10,000.00
99,250.00 - 181,880.00 281,130.00
- - 12,000.00 12,000.00
- - 200,000.00 200,000.00
- - 16,000.00 16,000.00
- - 9,000.00 9,000.00
73,500.00 - - 73,500.00
10,000.00 - - 10,000.00
83,500.00 - 237,000.00 320,500.00
- - 12,000.00 12,000.00
- - 40,000.00 40,000.00
- - 3,200.00 3,200.00
- - 900.00 900.00
57,583.38 - - 57,583.38
1,500.00 - - 1,500.00
59,083.38 - 56,100.00 115,183.38
- - 840,000.00 840,000.00
- - 4,200,000.00 4,200,000.00
- - 336,000.00 336,000.00
- - 63,000.00 63,000.00
5,758,337.74 - - 5,758,337.74
37,500.00 - - 37,500.00
90,000.00 - - 90,000.00
5,885,837.74 - 5,439,000.00 11,324,837.74
- - 120,000.00 120,000.00
- - 600,000.00 600,000.00
- - 48,000.00 48,000.00
- - 9,000.00 9,000.00
209,394.10 - - 209,394.10
45,000.00 - - 45,000.00
254,394.10 - 777,000.00 1,031,394.10
- - 96,000.00 96,000.00
- - 480,000.00 480,000.00
- - 38,400.00 38,400.00
- - 7,200.00 7,200.00
125,636.46 - - 125,636.46
27,000.00 - - 27,000.00
152,636.46 - 621,600.00 774,236.46
- - 1,800.00 1,800.00
- - 30,000.00 30,000.00
- - 2,400.00 2,400.00
- - 180.00 180.00
756,250.00 - - 756,250.00
5,000.00 - - 5,000.00
761,250.00 - 34,380.00 795,630.00
- - 1,200.00 1,200.00
- - 100,000.00 100,000.00
- - 8,000.00 8,000.00
- - 900.00 900.00
185,000.00 - - 185,000.00
185,000.00 - 110,100.00 295,100.00
- - 1,800.00 1,800.00
- - 30,000.00 30,000.00
- - 2,400.00 2,400.00
- - 180.00 180.00
20,000.00 - - 20,000.00
20,000.00 - 34,380.00 54,380.00
- - 1,200.00 1,200.00
- - 20,000.00 20,000.00
- - 1,600.00 1,600.00
- - 180.00 180.00
22,500.00 - - 22,500.00
22,500.00 - 22,980.00 45,480.00
- - 2,400.00 2,400.00
- - 40,000.00 40,000.00
- - 3,200.00 3,200.00
- - 180.00 180.00
20,000.00 - - 20,000.00
20,000.00 - 45,780.00 65,780.00
- - 2,400.00 2,400.00
- - 40,000.00 40,000.00
- - 3,200.00 3,200.00
- - 180.00 180.00
40,000.00 - - 40,000.00
40,000.00 - 45,780.00 85,780.00
- - 1,800.00 1,800.00
- - 30,000.00 30,000.00
- - 2,400.00 2,400.00
- - 1,440.00 1,440.00
45,000.00 - - 45,000.00
45,000.00 - 35,640.00 80,640.00
- - 4,320.00 4,320.00
- - 12,000.00 12,000.00
- - 960.00 960.00
- - 360.00 360.00
15,000.00 - - 15,000.00
5,250.00 - - 5,250.00
20,250.00 - 17,640.00 37,890.00
- - 4,320.00 4,320.00
- - 12,000.00 12,000.00
- - 960.00 960.00
- - 360.00 360.00
43,500.00 - - 43,500.00
15,225.00 - - 15,225.00
58,725.00 - 17,640.00 76,365.00
- - 1,200.00 1,200.00
- - 80,000.00 80,000.00
- - 6,400.00 6,400.00
- - 900.00 900.00
50,000.00 - - 50,000.00
187.50 - - 187.50
50,187.50 - 88,500.00 138,687.50
- - 1,200.00 1,200.00
- - 20,000.00 20,000.00
- - 1,600.00 1,600.00
- - 900.00 900.00
25,000.00 - - 25,000.00
25,000.00 - 23,700.00 48,700.00
- - 396,000.00 396,000.00
- - 220,000.00 220,000.00
- - 1,600.00 1,600.00
- - 28,800.00 28,800.00
1,425,000.00 - - 1,425,000.00
85,500.00 - - 85,500.00
1,510,500.00 - 646,400.00 2,156,900.00
- - 120,000.00 120,000.00
- - 200,000.00 200,000.00
- - 16,000.00 16,000.00
- - 9,000.00 9,000.00
2,700,000.00 - - 2,700,000.00
35,710.55 - - 35,710.55
19,221.10 - - 19,221.10
826,479.49 - - 826,479.49
3,581,411.14 - 345,000.00 3,926,411.14
- - 144,000.00 144,000.00
- - 290,000.00 290,000.00
- - 24,000.00 24,000.00
- - 10,800.00 10,800.00
1,440,000.00 - - 1,440,000.00
35,710.55 - - 35,710.55
19,221.10 - - 19,221.10
179,391.80 - - 179,391.80
1,674,323.45 - 468,800.00 2,143,123.45
- - 18,000.00 18,000.00
- - 1,600.00 1,600.00
- - 24,000.00 24,000.00
- - 1,440.00 1,440.00
2,500.00 - - 2,500.00
875.00 - - 875.00
2,250.00 - - 2,250.00
3,750.00 - - 3,750.00
1,437.50 - - 1,437.50
2,500.00 - - 2,500.00
1,875.00 - - 1,875.00
15,187.50 - 45,040.00 60,227.50
- - 2,400.00 2,400.00
- - 12,600.00 12,600.00
- - 960.00 960.00
- - 540.00 540.00
1,750.00 - - 1,750.00
4,500.00 - - 4,500.00
18,200.00 - - 18,200.00
24,450.00 - 16,500.00 40,950.00
- - 100,000.00 100,000.00
- - 60,000.00 60,000.00
300,000.00 - - 300,000.00
2,333.33 - - 2,333.33
40,000.00 - - 40,000.00
1,000.00 - - 1,000.00
4,000.00 - - 4,000.00
10,000.00 - - 10,000.00
2,000.00 - - 2,000.00
359,333.33 160,000.00 519,333.33
- - 100,000.00 100,000.00
- - 60,000.00 60,000.00
400,000.00 - - 400,000.00
30,000.00 - - 30,000.00
20,000.00 - - 20,000.00
10,000.00 - - 10,000.00
93.33 - - 93.33
150,000.00 - - 150,000.00
610,093.33 160,000.00 770,093.33
DAFTAR HARGA
UPAH KERJA - BAHAN / MATERIAL
NO. URAIAN / JENIS SAT. HARGA ( RP )
A. UPAH KERJA
1 Pekerja O/H 120,000.00
2 Tukang O/H 200,000.00
3 Tukan Las O/H 200,000.00
4 Tukan Cat O/H 200,000.00
5 Kepala Tukang O/H 160,000.00
6 Mandor O/H 180,000.00
7 Satpam O/H 200,000.00
B. BAHAN / MATERIAL
1 Semen PC 50 Zak 297,587.92
2 Batu Bata Merah Bj 3,800.00
2 Semen Warna Zak 1,100,000.00
3 Batako Bj 26,543.44
4 Batu Gunung / Kali (import) M³ 2,037,974.98
5 Tanah Timbunan (import) M³ 2,269,704.98
6 Abu Batu (import) M³ 2,672,109.98
7 Pasir Pasangan / Beton (import) M³ 1,922,109.98
8 Pasir Urug (import) M³ 1,922,109.98
9 Paving - Block M² 375,000.00
10 Batu Kerikil / Split 1 - 2 cm (import) M³ 2,037,974.98
11 Besi Beton Polos Ø 8 mm Kg 20,393.88
12 Besi Beton Polos Ø 10 mm Btg 118,333.00
13 Besi Beton Polos Ø 12 mm Kg 14,174.49
14 Besi Beton Ulir Ø 16 mm Btg 305,000.00
15 Besi Beton Polos Ø 19 mm Btg 777,000.00
16 Kawat Beton Kg 50,000.00
17 Minyak Bekesting / Oli Kotor Kg 29,450.00
18 Paku Kg 30,000.00
19 Paku Tripleks Kg 42,500.00
20 Cat Menie Kg 50,000.00
21 Cat Besi Kg 75,000.00
22 Cat Dasar Kg 45,000.00
23 Cat Tembok Kg 70,000.00
24 Cat Anti Lumut Kg 75,000.00
25 Tenner / Minyak Cat Ltr 50,000.00
26 Kertas Amplas Lbr 37,500.00
27 Kuas Cat Bh 28,750.00
28 Plamur Kg 17,500.00
29 Atap Alumunium M 85,000.00
30 Nok Standar alumunium M 70,000.00
31 Paku Sekrup Dos 152,700.00
32 Piva GLP 2" Btg 2,400,000.00
33 Kayu Kls l Balok M³ 5,234,852.49
34 Kayu Kls l Papan M³ 5,234,852.49
35 Kayu Kls II Balok M³ 3,984,852.49
36 Kayu Kls II Papan M³ 3,984,852.49
37 Kayu Kls lll Balok M³ 2,184,852.49
38 Kayu Kls lll Papan M³ 2,184,852.49
39 Dolken Kayu Ø 8-10 cm -Panjang 4 m Btg 30,000.00
40 Lem Kayu Kg 90,000.00
41 Sheet Pile L = 12 M Btg 7,801,200.00
42 Tiang Ø500 mm Bottom K-600 kg/cm2 L= 6 Btg 4,666,200.00
43 Tiang Ø500 mm Bottom K-600 kg/cm2 L= 8 Btg 6,476,800.00
44 Besi Siku Btg 600,000.00
45 Baut Bh 19,500.00
46 Angkur 25 mm Bh 216,750.00
47 Tempat Penambat Tali Kapal (Bitt Bollard) 25 Ton Bh 29,215,000.00
48 Baja Ringan Canai Dingin C75 Btg 225,000.00
49 Kawat Las Dos 400,000.00
50 Wire Rope Clip Bh 142,500.00
- 21 -
A. UPAH KERJA
1 Pekerja O/H 120,000.00
2 Tukang O/H 200,000.00
3 Tukan Las O/H 200,000.00
4 Tukan Cat O/H 200,000.00
5 Kepala Tukang O/H 160,000.00
6 Mandor O/H 180,000.00
7 Satpam O/H 200,000.00
51 Solar Ltr 25,000.00
52 Genset 1,5 kVA Unit 17,689,000.00
53 Perlengkapan Keselamatan Ls 90,000.00
54 Perlengkapan Keamaanan Ls 100,000.00
55 Besi Strip t=5 mm Kg 58,000.00
56 Jendela Nako (rangka + Kaca 5 mm) M2 611,800.00
57 Kaca Polos 3 mm M2 687,500.00
58 Sealant M2 100,000.00
59 Polywood Tebal 9 mm M2 250,000.00
60 Tripleks Tebal 4 mm Lbr 97,500.00
61 Kunci Tanam Biasa Bh 185,000.00
62 Engsel Pintu Set 60,000.00
63 Engsel Jendela Set 45,000.00
64 Grendel Jendela Bh 20,000.00
65 Grendel Pintu Bh 40,000.00
66 Kait Angin Bh 45,000.00
67 Besi Plat Baja 20 mm x 400 mm x 800 mm Lbr 10,437,000.00
68 Manual Winch 2 Ton Bh 7,500,000.00
69 Besi Baja H Beam L 300 x 300 x 10 x 15 (1128 Kg)/Btg Kg 52,500.00
70 Besi Baja WF 150 x 75 x 5 x 7 (168 Kg)/ Btg Kg 46,500.00
71 Tali Sling 16 MM 6x37 IWRC x 500 M M 125,000.00
72 Roda Rell Bh 1,350,000.00
73 Tegel Keramik 40x40 Dos 145,000.00
74 Tegel Keramik 30x30 Dos 155,000.00
75 Besi hollow 40x40x2 Btg 425,000.00
76 Pipa PVC 5/8" Btg 40,000.00
77 Pipa PVC 3/4" Btg 50,000.00
78 Pipa PVC 3" Btg 145,000.00
79 Keran air 3/4" Bh 50,000.00
80 Floor Drain Bh 25,000.00
81 Seal tape Bh 7,500.00
82 Closet Duduk Bh 1,425,000.00
83 Closet Jongkok Bh 300,000.00
84 Urinoir Bh 2,700,000.00
85 Wastafel Bh 1,200,000.00
86 Kabel NYM 3x2,5 m' 30,000.00
87 isolasi listrik Bh 25,000.00
88 MCB Bh 150,000.00
89 Klem plastik isi 45 Bks 10,500.00
90 Fitting Bh 25,000.00
91 Sakelar Tunggal Bh 30,000.00
92 Sakelar Ganda Bh 30,000.00
93 Stop Kontak Bh 25,000.00
94 Lampu XL 18 Watt Bh 73,800.00
95 Lampu TL 1x20 Watt Bh 127,500.00
- 22 -
A. UPAH KERJA
1 Pekerja O/H 120,000.00
2 Tukang O/H 200,000.00
3 Tukan Las O/H 200,000.00
4 Tukan Cat O/H 200,000.00
5 Kepala Tukang O/H 160,000.00
6 Mandor O/H 180,000.00
7 Satpam O/H 200,000.00
………………………………………..
DIPERIKSA/DISETUJUI DIBUAT
- 23 -
REKAPITULASI ESTIMASI ANGGARAN
PEKERJAAN:
DETAIL ENGINEERING DESIGN (DED)
SEPTIC TANK KOMUNAL
TERBILANG :
Mengetahui,
DINAS PERHUBUNGAN KAB.YAHUKIMO
PT.Koridor A
Konsultan Per
MENYETUJUI :
BAPPEDA KAB.YAHUKIMO
PEKERJAAN:
NGINEERING DESIGN (DED)
PTIC TANK KOMUNAL
KETERANGAN
DIBUAT
PT.Koridor Adicita
Konsultan Perencana
MENYETUJUI :
BAPPEDA KAB.YAHUKIMO
JUMLAH TOTAL
- 26 -
RENCANA ANGGARAN BIAYA (RAB)
NO URAIAN PEKERJAAN VOL. SAT. HARGA SAT
………………………
DIPERIKSA/DISETUJUI
- 27 -
ANA ANGGARAN BIAYA (RAB)
JML. HARGA KET.
5,000,000.00
5,000,000.00
1,094,451.75
266,374.50
8,483,913.65
3,311,734.57
900,000.00
1,478,567.15
1,478,567.15
689,233.60
1,847,335.31
19,550,177.68
4,382,581.35
3,254,189.12
1,084,533.39
3,901,382.90
12,622,686.75
238,258.80
238,258.80
37,411,123.23
- 28 -
ANA ANGGARAN BIAYA (RAB)
JML. HARGA KET.
………………………………………….
DIBUAT
- 29 -
JADWA
3 Pekerjaan Struktur
3.a Pek. Lantai Kerja K125
Cor Beton K125 11.71
3.b Pek. Plat Beton K300
Cor Beton K300 8.70
Tulangan ø8 2.90
Bekisting 10.43
100.00
RENCANA BOBOT / MINGGU - - - -
RENCANA BOBOT KOMULATIF - - - -
- 30 -
JADWAL WAKTU PELAKSANAAN
WAKTU PELAKSANAAN 150 HARI KALENDER
BULAN 2 BULAN 3 BULAN 4
31 - 37 38 - 44 45 - 51 52 - 60 61 - 67 68 - 74 75 -81 82 - 90 91 - 97 98 - 104105 -111 112-120
- - - - - - - - - - - -
- - - - - - - - - - - -
- 31 -
ALENDER
BULAN 5 KET.
121-127 128-134 135-141 142-150
100.00
90.00
80.00
70.00
60.00
50.00
40.00
30.00
20.00
10.00
-
- - - -
- - - -
DIBUAT
PT.Koridor Adicita
Konsultan Perencana
- 32 -
PERHITU
NO. SKETSA
SKETSA PERHITUNGAN
Sub Jumlah
9.45 M3
2.13 M3
Sub Jumlah : 11.58 M3
3.86 M3
15.30 M2
JUMLAH 15.30 M2
15.30 M2
JUMLAH 15.30 M2
0.59 M3
JUMLAH 0.59 M3
0.59 M3
JUMLAH 0.59 M3
0.29 M3
JUMLAH 0.29 M3
0.66 M3
JUMLAH 0.66 M3
PERHITUNGAN VOLUME
3. Vol. Tulangan ø8
Panjang + Panjang x Kg/m
= 55.50 + 57.60 x 0.39
Jumla
4 Vol. Bekisting
P (m) x L (m) x T (m)
= 3.60 x 1.50 x 0.12
AN VOLUME
,.
0.99 M3
0.65 M3
44.11 Kg
Jumlah 44.11 Kg
6.62 M2
PERHITUNGAN VOLUME
NO. SKETSA
100
40 X 40
KERAMIK =
300
40 X 40 KERAMIK
150
30 X 30
KERAMIK
40 X 40
2 Vol.
150
=
KERAMIK
300
40 X 40
120
3 Vol.
KERAMIK
40 X 40
180
100
KERAMIK
4 Vol.
40 X 40
=
300 250 150
TERAS
=
100
-0.02
Km / Wc
-0.05
300
R. TIDUR
±0.00
150
R. KELUARGA/R. MAKAN
±0.00 =
=
150
DAPUR
±0.00
2 Vol.
300
R. TIDUR
120
±0.00
TERAS
-0.02
180
=
100
TERAS
-0.02
=
=
300 250 150
3 Vol.
DENAH(RUMAH TYPE 45)
Skala 1:100
=
4 Vol.
=
C . Pek. Pemasangan Rangka Plafond 1. Vol.
Pek. Pemasangan Plafond 300 250 150
a
=
b
TERAS
100
-0.02
300
PLAFOND TRIPLEK t:4mm
100 x 100 cm
150
c
PLAFOND TRIPLEK t:4mm
100 x 100 cm
150
300
PLAFOND TRIPLEK t:4mm
120
100 x 100 cm
180
100
TERAS
-0.02 2 Vol.
300 250 150
RENCANA PLAFOND
Skala 1:100
b
=
100
c
76
d
218
=
766
293
180
100
238 365 85
RENCANA KAP
Skala 1:100
+186.2
+186.2
2 Vol.
a
=
b
=
c
=
3 Vol.
=
4 Vol.
=
+197.1
196 195 d J1
174 175
=
e v1
15 123 =
6 Unit
2 Vol.
62
a PJ1
82
=
5
15
15 15
6 60 6
6 80 6 b J1
=
DETAIL KUSEN P1(4 unit) DETAIL KUSEN P2 (1unit)
Skala 1:20 Skala 1:20
3 Vol.
a PJ1
15 15 =
4 5 5
10
b J1
78
=
196 10
195
15
5
c V1
=
15 4 Vol.
a PJ1
=
82
b P1
15
=
6 80 510 42 105
15
5
10
78
25
20 30
10
5
15 35
5
10
78
25
20 30
10
5
15 35
105 25 510
6 42 6 42 6
15 15 15 15
,.
Rabat Beon Mutu K125
T(m) x A(m2)
0.05 x 1.40 0.0700 M3
Spesi
A(m2)
1.40 1.4000 M2
Keramik 40x40
A(m2)
A Keramik
- 30x30- (m2)
Luas Dinding dan kolom
1.40 - 2.25 - Err:508 Err:508 M2
Keramik 30x30
A (m2)
2.25 2.2500 M2
,.
Dinding Batako 1/4
T(m) x P(m) - Luas Kus - Luas Kolom
3.00 x 44.70 - 14.63 - 7.65 111.8206 M2
A(m) x T(m) x J
6.15 x 1.86 x 2.00 11.4390 M2
6.15 x 1.97 x 2.00 12.1155 M2
Jumlah 135.3751
Plesteran 1:5
T(m) x P(m) - Luas Kus - Luas Kolom
3.00 x 38.70 14.63 - 5.85 95.6206 M2
A(m) x T(m) x J
6.15 x 1.86 x 2.00 11.4390 M2
6.15 x 1.97 x 2.00 12.1155 M2
2 Sisi 238.350
Plesteran 1 : 3
T(m) x P(m) - Luas Kolom
3.00 x 6.00 - 1.80 16.2000 M2
2 Sisi 32.40
Acian
A (m2)
135.38 135.3751 M2
2 Sisi 270.750
,.
Pek. Pemasangan Rangka Plafond
P(m) x L(m)
6.00 x 3.00 18.0000 M2
P(m) x L(m)
7.00 x 2.50 17.5000 M2
P(m) x L(m)
4.20 x 1.50 6.3000 M2
Jumlah 41.800
,.
Pek. Pemasangan Atap Alumunium
P(m) + L(m)
4.40 + 3.00 13.1850 M2
2 Sisi 26.37 M2
P(m) + L(m)
4.64 + 4.60 21.3440 M2
P(m) + L(m)
4.18 + 4.60 19.2188 M2
P(m) + L(m)
3.36 + 1.50 5.0340 M2
2 Sisi 10.068 M2
Jumlah 77.0008
Pek. Pemasangan Rangka Atap Jurai
P (m) x L(m)
7.36 x 3.00 22.07 M2
P (m) x L(m)
7.36 x 3.86 28.39 M2
P (m) x L(m)
5.56 x 1.50 8.34 M2
Jumlah 58.7982 M2
Pek. Pemasangan Nok Alumunium
P (m)
8.36 8.36 M'
Pek. Lisplank
P (m)
31.43 31.43 M'
,.
Pek. Kusen
A(m2) x P(m) x J(unit)
0.0075 x 4.82 x 4.00 19.28 0.1446 M3
Jumlah 3.19 M2
Pek. Pemasangan Kaca 3 mm
P(m) x L(m) x J(unit)
0.7800 x 0.42 x 1.00 0.3276 M2
,.
3.1200 M'
PERHITUNGAN VOLUME
A . Pek. Pengecetan Dinding Dan Kolom 1. Vol. Pek. Pengecetan Dinding Dan Kolom
Pek. Pengecetan Kusen (L(Acian)+L(kolom))(m2)
Pek. Pengecetan Plafond = 270.75 + 7.65
Pek. Daun Pintu 2 Vol. Pek. Pengecetan Kusen
Pek. Pengecetan Lisplank P(m) L(m)
= 48.28 x 0.40
3 Vol. Pek. Pengecetan Plafond
A(m2)
= 41.80
4 Vol. Pek. Daun Pintu
A(m2) x J.sisi
= 9.20 x 2.00
5 Vol. Pek. Pengecetan Lisplank
P(m) x T(m)
= 31.43 x 0.30
UNGAN VOLUME
278.4002 M2
19.312 M2
41.800 M2
18.408 M2
9.430 M2