Anda di halaman 1dari 1

PERHITUNGAN BEBAN LP LANTAI 3

SPOT LED 5 W DOWN LED 12 RECE LED (600x600) 36RECE


W LED (1200x300) 36 W
TL LED BATTENS 18 W BED HEAD (2x9 WATT) TOTAL BEBAN TERPASANG (AMP) SAKLAR SAKLAR SAKLAR
KABEL FEEDER MCCB MCB KABEL ROL FUNGSI SAKLAR GANDA
BANYAK TOT. WATT BANYAK TOT. WATT BANYAK TOT. WATT BANYAK TOT. WATT BANYAK TOT. WATT BANYAK TOT. WATT WATT R S T TUNGGAL HOTEL HOTEL
MCB 1.P 6A / 4.5 kA NYM 3x2,5 mm2 1 LP.3-1 0 0 6 216 0 0 0 216 1,0 4
2 LP.3-2 0 0 5 180 0 0 0 180 0,9 5
3 LP.3-3 0 0 2 72 0 0 0 72 0,3 1 1
4 LP.3-4 0 0 8 288 0 0 0 288 1,4 8
5 LP.3-5 0 0 8 288 0 0 0 288 1,4 8
6 LP.3-6 0 0 5 180 0 0 0 180 0,9 1 1
7 LP.3-7 0 0 7 252 0 0 0 252 1,2 1 5
8 LP.3-8 0 0 3 108 0 0 0 108 0,5 1 1
9 LP.3-9 0 0 4 144 0 0 0 144 0,7 2
10 LP.3-10 0 0 7 252 0 0 0 252 1,2 2 2
11 LP.3-11 0 0 3 108 0 0 0 108 0,5 2
12 LP.3-12 0 0 4 144 0 0 0 144 0,7 2
13 LP.3-13 0 0 6 216 0 0 0 216 1,0 1 2
NYY 4 x 4mm2 MCCB 3P 15A / 7.5 kA 14 LP.3-14 0 0 5 180 0 0 0 180 0,9 4
15 LP.3-15 0 0 4 144 0 0 0 144 0,7 1
16 LP.3-16 0 0 4 144 0 0 0 144 0,7 1
17 LP.3-17 0 0 8 288 0 0 0 288 1,4 7
18 LP.3-18 0 0 3 108 0 0 0 108 0,5 2
19 LP.3-19 0 0 12 432 0 0 0 432 2,1 2 4
20 LP.3-20 0 0 6 216 0 0 0 216 1,0 2 2
21 LP.3-21 0 0 6 216 0 0 0 216 1,0 2 2
22 LP.3-22 0 0 9 324 0 0 0 324 1,6 1 3
23 LP.3-23 0 0 4 144 0 0 0 144 0,7 4
24 LP.3-24 0 0 4 144 0 0 0 144 0,7 1 1
SPARE 0 0 0 0 0 0 0 0,0
SPARE 0 0 0 0 0 0 0 0,0
SPARE 0 0 0 0 0 0 0 0,0
0 0 0 0 133 4788 0 0 0 0 0 0 4788 7,1 8,4 7,4

Total KW 4,8 KW
Total KVA 5,0 KVA