Anda di halaman 1dari 6

BILL OF QUANTITY ( BOQ )

PEKERJAAN : SISTEM MEKANIKAL, ELEKTRIKAL DAN PLUMBING ( MEP )


PROYEK : PERENCANAAN PEMBANGUNAN GEDUNG SUKSES ABADI SCHOOL
LOKASI : JAKARTA
TAHUN : 2023

NO ITEM PEKERJAAN VOLUME UNIT HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

PEKERJAAN SISTEM DENGAN PERALATAN UTAMA


Penawaran pekerjaan termasuk pengadaan dan pemasangan material di-site, lengkap dan
berfungsi dengan baik.

I PEKERJAAN LISTRIK
I.1 PERALATAN UTAMA
A Transformator Oil Immersed Type 400 kVA, 20 KV – 400 V, 50 Hz, Dyn 5 - AL/AL 1 Unit 263.000.000 263.000.000
B Medium Voltage Distribution Panel (MVDP) – 20 kV
- Arester LBS 20kV 3P 400A
- Cell Incoming CB 24 KV 630A 3P
- Cell Outgoing LBS 20KV 400A 3P
C Low Voltage Main Distribution Panel (LVMDP) 1 Unit 280.000.000 280.000.000
D Capacitor Bank 160 kVAR c/w Detuned Reactor 1 Unit 82.000.000 82.000.000
E Power Panel (PP) dan Lighting Panel (LP) :
- PP - POMPA 1 Unit 20.440.000 20.440.000
- PP - HYDRANT 1 Unit 20.440.000 20.440.000
- PP - LIFT 1 Unit 20.440.000 20.440.000
- PP - AC 1 Unit 20.440.000 20.440.000
- LP - LT. BS 1 Unit 12.142.000 12.142.000
- LP - LT. 1 1 Unit 12.142.000 12.142.000
- LP - LT. 2 1 Unit 12.142.000 12.142.000
- LP - LT. 3 1 Unit 12.142.000 12.142.000
- LP - LT. 4 1 Unit 12.142.000 12.142.000
- LP/PP - LT. ATAP 1 Unit 20.440.000 20.440.000
Pentanahan Netral pada Ruang Panel Utama, dll 1 lot 39.395.500 39.395.500
NO ITEM PEKERJAAN VOLUME UNIT HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

I.2 KABEL DISTRIBUSI UTAMA


KABEL DISTRIBUSI UTAMA TEGANGAN MENENGAH (TM)
Dari Medium Voltage Distribution Panel (MVDP), ke :
- Gardu PLN, NA2XSEFGbY 3 x 70 mm², termasuk Induksi kabel 50 m 815.000 40.750.000
- Transformator N2XSY 3 x 1c x 70 mm² 45 m 311.000 13.995.000
- Termination Kit 1 lot 10.949.000 10.949.000

KABEL DISTRIBUSI UTAMA TEGANGAN RENDAH (TR)


Dari Low Voltage Main Distribution Panel (LVMDP), ke :
- Transformator, NYY 4(2 x 1C x 185 mm²) 120 m 455.000 54.600.000
- Capasitor Bank, NYY 3 x 1C x 120 mm² 45 m 298.000 13.410.000
- GENSET SILENT TYPE, NYY 4 x 1C x 120 mm² 60 m 298.000 17.880.000
- PP-POMPA, NYY 4 x 6 mm² + BC 6 mm 29 m 68.000 1.972.000
- PP-HYDRANT, NYY 4 x 6 mm² + BC 6 mm 29 m 90.000 2.610.000
- PP-LIFT, NYY 4 x 25 mm² + BC 16 mm 38 m 339.000 12.882.000
- PP-AC, NYY 4 x 25 mm² + BC 16 mm 66 m 339.000 22.374.000
- LP-LT.BS, NYY 4 x 6 mm² + BC 6 mm 12 m 90.000 1.080.000
- LP-LT.1, NYY 4 x 6 mm² + BC 6 mm 17 m 90.000 1.530.000
- LP-LT.2, NYY 4 x 6 mm² + BC 6 mm 22 m 90.000 1.980.000
- LP-LT.3, NYY 4 x 6 mm² + BC 6 mm 27 m 90.000 2.430.000
- LP-LT.4, NYY 4 x 6 mm² + BC 6 mm 32 m 90.000 2.880.000
- LP/PP-LT.ATAP, NYY 4 x 6 mm² + BC 6 mm 37 m 90.000 3.330.000

II PEKERJAAN INSTALASI PENERANGAN DAN FIXTURE


II.1 LANTAI BASEMENT
Pekerjaan instalasi Penerangan dan Stop Kontak lengkap
kabel NYM 3 x 2,5 mm, konduit, T-does, dan accessories :
- Instalasi Penerangan 100 ttk 185.000 18.500.000
- Instalasi Stop Kontak Dinding 13-16A/1Ph/220V-150W 16 ttk 185.000 2.960.000
Pengadaan dan pemasangan Fixtures dan Armatures :
- TL LED 2x36/220V/400-4500K Non Ballast TKI Type 11 unit 380.000 4.180.000
- TL LED 2x36/220V/400-4500K Non Ballast TKO Type 25 unit 380.000 9.500.000
- TL LED 2x18/220V/400-4500K Non Ballast TKO Type 17 unit 200.000 3.400.000
- Down Light Smart Bright 5", 1 x DLED /850/9W-600Lm 20 unit 255.000 5.100.000
- Baret Smart Bright, 1 x DLED /850/12W-1200Lm 6 unit 435.000 2.610.000
- Garden Lamp Outdoor 50 W 16 unit 255.000 4.080.000
NO ITEM PEKERJAAN VOLUME UNIT HARGA SATUAN (Rp) JUMLAH HARGA (Rp)
- Saklar Tunggal 1 Gang 6 unit 75.000 450.000
- Saklar Ganda 2 Gang 14 unit 85.000 1.190.000
- Stop Kontak Dinding 13-16A/1Ph/220V-150W 16 unit 85.000 1.360.000
- Kabel Tray Listrik 300 x 50 mm 100 m 365.000 36.500.000

II.2 LANTAI 1
Pekerjaan instalasi Penerangan dan Stop Kontak lengkap
kabel NYM 3 x 2,5 mm, konduit, T-does, dan accessories :
- Instalasi Penerangan 313 ttk 185.000 57.905.000
- Instalasi Stop Kontak Dinding 13-16A/1Ph/220V-150W 38 ttk 185.000 7.030.000
Pengadaan dan pemasangan Fixtures dan Armatures :
- TL LED 2x36/220V/400-4500K Non Ballast TKI Type 15 unit 380.000 5.700.000
- TL LED 2x18/220V/400-4500K Non Ballast TKI Type 63 unit 200.000 12.600.000
- Down Light Smart Bright 5", 1 x DLED /850/9W-600Lm 110 unit 255.000 28.050.000
- Baret Smart Bright, 1 x DLED /850/12W-1200Lm 4 unit 435.000 1.740.000
- Wall Lamp 12 W 4 unit 255.000 1.020.000
- Saklar Tunggal 1 Gang 15 unit 75.000 1.125.000
- Saklar Ganda 2 Gang 37 unit 85.000 3.145.000
- Saklar Hotel 1 unit 165.000 165.000
- Stop Kontak Dinding 13-16A/1Ph/220V-150W 38 unit 85.000 3.230.000
- Kabel Tray Listrik 300 x 50 mm 825 m 365.000 301.125.000

II.3 LANTAI 2
Pekerjaan instalasi Penerangan dan Stop Kontak lengkap
kabel NYM 3 x 2,5 mm, konduit, T-does, dan accessories :
- Instalasi Penerangan 313 ttk 185.000 57.905.000
- Instalasi Stop Kontak Dinding 13-16A/1Ph/220V-150W 38 ttk 185.000 7.030.000
Pengadaan dan pemasangan Fixtures dan Armatures :
- TL LED 2x36/220V/400-4500K Non Ballast TKI Type 15 unit 380.000 5.700.000
- TL LED 2x18/220V/400-4500K Non Ballast TKI Type 63 unit 200.000 12.600.000
- Down Light Smart Bright 5", 1 x DLED /850/9W-600Lm 110 unit 255.000 28.050.000
- Baret Smart Bright, 1 x DLED /850/12W-1200Lm 4 unit 435.000 1.740.000
- Saklar Tunggal 1 Gang 15 unit 75.000 1.125.000
- Saklar Ganda 2 Gang 37 unit 85.000 3.145.000
- Saklar Hotel 1 unit 165.000 165.000
- Stop Kontak Dinding 13-16A/1Ph/220V-150W 38 unit 85.000 3.230.000
NO ITEM PEKERJAAN VOLUME UNIT HARGA SATUAN (Rp) JUMLAH HARGA (Rp)
- Kabel Tray Listrik 300 x 50 mm 825 m 365.000 301.125.000

II.4 LANTAI 3
Pekerjaan instalasi Penerangan dan Stop Kontak lengkap
kabel NYM 3 x 2,5 mm, konduit, T-does, dan accessories :
- Instalasi Penerangan 313 ttk 185.000 57.905.000
- Instalasi Stop Kontak Dinding 13-16A/1Ph/220V-150W 38 ttk 185.000 7.030.000
Pengadaan dan pemasangan Fixtures dan Armatures :
- TL LED 2x36/220V/400-4500K Non Ballast TKI Type 15 unit 380.000 5.700.000
- TL LED 2x18/220V/400-4500K Non Ballast TKI Type 63 unit 200.000 12.600.000
- Down Light Smart Bright 5", 1 x DLED /850/9W-600Lm 110 unit 255.000 28.050.000
- Baret Smart Bright, 1 x DLED /850/12W-1200Lm 4 unit 435.000 1.740.000
- Wall Lamp 12 W 4 unit 255.000 1.020.000
- Saklar Tunggal 1 Gang 15 unit 75.000 1.125.000
- Saklar Ganda 2 Gang 37 unit 85.000 3.145.000
- Saklar Hotel 1 unit 165.000 165.000
- Stop Kontak Dinding 13-16A/1Ph/220V-150W 38 unit 85.000 3.230.000
- Kabel Tray Listrik 300 x 50 mm 825 m 365.000 301.125.000

II.5 LANTAI 4
Pekerjaan instalasi Penerangan dan Stop Kontak lengkap
kabel NYM 3 x 2,5 mm, konduit, T-does, dan accessories :
- Instalasi Penerangan 109 ttk 185.000 20.165.000
- Instalasi Stop Kontak Dinding 13-16A/1Ph/220V-150W 20 ttk 185.000 3.700.000
Pengadaan dan pemasangan Fixtures dan Armatures :
- TL LED 2x36/220V/400-4500K Non Ballast TKI Type 8 unit 380.000 3.040.000
- Down Light Smart Bright 5", 1 x DLED /850/9W-600Lm 76 unit 255.000 19.380.000
- Baret Smart Bright, 1 x DLED /850/12W-1200Lm 4 unit 435.000 1.740.000
- Spotlight Outdoor 50 W 21 unit 255.000 5.355.000
- Saklar Tunggal 1 Gang 4 unit 75.000 300.000
- Saklar Ganda 2 Gang 14 unit 85.000 1.190.000
- Stop Kontak Dinding 13-16A/1Ph/220V-150W 20 unit 85.000 1.700.000
- Kabel Tray Listrik 300 x 50 mm 150 m 365.000 54.750.000

II.6 LANTAI ATAP


Pekerjaan instalasi Penerangan dan Stop Kontak lengkap
NO ITEM PEKERJAAN VOLUME UNIT HARGA SATUAN (Rp) JUMLAH HARGA (Rp)
kabel NYM 3 x 2,5 mm, konduit, T-does, dan accessories :
- Instalasi Penerangan 13 ttk 185.000 2.405.000
- Instalasi Stop Kontak Dinding 13-16A/1Ph/220V-150W 2 ttk 185.000 370.000
Pengadaan dan pemasangan Fixtures dan Armatures :
- TL LED 2x36/220V/400-4500K Non Ballast TKI Type 1 unit 380.000 380.000
- Down Light Smart Bright 5", 1 x DLED /850/9W-600Lm 12 unit 255.000 3.060.000
- Saklar Ganda 2 Gang 3 unit 85.000 255.000
- Stop Kontak Dinding 13-16A/1Ph/220V-150W 2 unit 85.000 170.000

III PENANGKAL PETIR


A Pekerjaan ini sudah termasuk Pengadaaan Material, Pemasangan/ Instalasi, Alat Bantu dll dan
berfungsi dengan baik
a Air Termination Network
Aluminium Air Terminal 15x500mm(L) 19 unit 340.000 6.460.000
Aluminium Base Air Terminal 19 unit 326.000 6.194.000
Aluminium Tape 25x3mm 197 m 48.000 9.456.000
Grey 25x3mm Non-metallic DC tape clip 197 unit 24.000 4.728.000
Aluminium Square Tape Clamp 9 unit 72.000 648.000
Bonding jumper from selected rebar column to façade by NYA cable 70mm2 supply with clamps,
9 set 687.150 6.184.350
supporting tools and accessories
Bimetallic Connector 10 unit 333.000 3.330.000

b Earthing System
Polymer Inspection Pit c/w 4 set 936.000 3.744.000
5/8" x 1800mm Extensible Copperbond Rod 4 unit 434.400 1.737.600
5/8" Rod Coupling 4 unit 434.400 1.737.600
Junction Box connected from natural down conductor to ring loop on Ground floor 4 set 1.443.840 5.775.360
Rod to cable clamp 4 unit 434.400 1.737.600
Grounding Test Box c/w earth dispatcher, nya cable and accesories (Roof Top) 1 lot 2.209.824 2.209.824
Driving stud 4 unit 434.400 1.737.600
Looping BC wire 70mm2 on selected floor c/w clamps and accessories 104 m 65.150 6.775.600

IV PEKERJAAN DIESEL GENSET 200 kVA TYPE SILENT, PRIME

Pekerjaan Termasuk Pemipaan, menginstal dan beroperasi secara normal baik lengkap Genset
Control Panel, Tangki Bahan Bakar, Grounding System, Sound Profing, Termination, Accessories
NO ITEM PEKERJAAN VOLUME UNIT HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Diesel generating set Prime power 200 Kva Type Silent, Prime 1 unit 257.888.000 257.888.000
PF = 0.8 ; 400/ 230 V, 3 Ph, 50 Hz, 1500 rpm. c/w Alternator Stamford, Panel Genset (PKG), AMF,
Knalpot, Accu, + Kabel, Tool Kits, Manual Book, Coo (tidak termasuk pekerjaan sipil dan finishing)
Tangki BBM capacity of 1.000 liters. 1 unit 11.500.000 11.500.000
Manual diesel pump 1 unit 1.500.000 1.500.000
Pemipaan supply dan distribusi bahan bakar, 1 lot 2.600.000 2.600.000
termasuk alat indikasi volume, alat pembatas, operasi pompa ( elektroda ), fine filter dan matrial
bantu lainnya.
Dari Unit Genset ke PKG, NYY 4x(1Cx120)mm² 40 m 298.000 11.920.000
Pipa knalpot dengan BSP medium class dia 150 mm, isolasi panas, 1 lot 4.768.000 4.768.000
jacketing, support dan spring hanger.
Grounding :
- Grounding body genset and panel with BC 70mm² 1 nos 13.800.000 13.800.000
- Grounding netral genset and panel with BC 70mm² 1 nos 13.800.000 13.800.000
Testing and Commissioning of Actual Expenses 1 lot 31.777.600 31.777.600

TOTAL PEKERJAAN LISTRIK : 2.919.241.634