MINGGU K
KEGIATAN : Peningkatan Jalan Dan Jembatan
LOKASI : SAMARINDA
TAHUN
: 2018
ANGGARAN
KONSULTAN PERENCANAAN : CV RISMA NUGRAHA
NO URAIAN PEKERJAAN
1 2
I DIVISI 1 UMUM
a. JUMLAH Rp.
b.
DIKETAHUI OLEH : TOTAL DI PERIK
c KORDINATOR LAPANGAN KONSULTAN
d
DINAS PEKERJAAN UMUM DAN CV. BINA CIPTA
e.
PENATAAN RUANG
ARDIAN
M. ALI WARDANA Insp
PENATAAN RUANG
ARDIAN
M. ALI WARDANA Insp
REKAP MINGGUAN
MINGGU KE 1 ( SATU )
PERIODE : Tanggal, 29 Agustus 2018 s/d 2 September
RENCANA ( % ) : 0.71
REALISASI ( % ) : -
DEVIASI ( % ) : (0.71)
H PERKASA
PRESENTASE PRO
BOBOT
Rp 120,460,000.00 2.865 - -
Rp 238,010,805.57 5.660 - -
Rp 109,385,148.92 2.601
Rp 3,737,029,435.82 88.874
4,204,885,390.31
ARDIANSYAH, ST
Inspector AGUNG IRFANDY AZIES, ST
Site Engineer
PERKASA
ARDIANSYAH, ST
Inspector AGUNG IRFANDY AZIES, ST
Site Engineer
Tanggal, 29 Agustus 2018 s/d 2 September 2018
NO. 20/K-15.52.006/100.07/2018
PRESENTASE PROGRES
BOBOT BOBOT
7 8
- 2.865
- 5.660
- 2.601
- 88.874
- 100.00
RENCANA
0.71
REALISASI
-
DEVIASI TERHADAP RENCANA : + ( - )
(0.71)
LAPOR
MIN
KEGIATAN : Peningkatan Jalan Dan Jembatan
LOKASI : SAMARINDA
TAHUN
: 2018
ANGGARAN
HARGA SATUAN
NO URAIAN PEKERJAAN SATUAN VOLUME
( Rp )
1 2 3 4 6
I. DIVISI 1 UMUM
HARGA SATUAN
NO URAIAN PEKERJAAN SATUAN VOLUME
( Rp )
1 2 3 4 6
1.2 Mobilisasi Ls 1.00 118,560,000.00
1.8 Manajemen Dan Keselamatan Lalulintas Ls 1.00 1,900,000.00
TOTAL
II. DIVISI 3 PEKERJAAN TANAH
3.1.1 Galian Biasa M3 1,927.64 104,970.38
3.3.1 Penyiapan Badan Jalan M2 300.00 3,770.59
3.5.2a Geotextile Non Woven M2 1,023.10 33,754.79
TOTAL
III. DIVISI 5 PEKERJAAN PERKERASAN BERBUTIR
5.1.2 Lapis Pondasi Agregat Kelas B M3 171.84 636,552.31
TOTAL
DIKETAHUI OLEH :
HARGA SATUAN
NO URAIAN PEKERJAAN SATUAN VOLUME
( Rp )
1 2 3 4 6
DIKETAHUI OLEH :
KORDINATOR LAPANGAN
DINAS PEKERJAAN UMUM DAN
PENATAAN RUANG
M. ALI WARDANA
APORAN MINGGUAN
MINGGU KE 1 ( SATU )
PERIODE : Tanggal, 29 Agustus 2018 s/d 2 September 2018
RENCANA ( % ) : 0.71 %
REALISASI ( % ) : - %
DEVIASI ( % ) : (0.71) %
SA
PRESENTASE PROGRES
JUMLAH HARGA BOBOT
MINGGU LALU MINGGU INI S/D MINGGU INI
( Rp ) (%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT
7 8 9 10 11 12 13 14
PRESENTASE PROGRES
JUMLAH HARGA BOBOT
MINGGU LALU MINGGU INI S/D MINGGU INI
( Rp ) (%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT
7 8 9 10 11 12 13 14
118,560,000.00 2.820 - - - - -
1,900,000.00 0.045 - - - -
120,460,000.00 2.865 - - -
202,345,103.32 4.812 - - - -
1,131,176.39 0.027 - - - -
34,534,525.86 0.821 - - - -
238,010,805.57 5.660 - - -
109,385,148.92 2.601 - - - -
109,385,148.92 2.601 - - -
1,308,942,245.84 31.129 - - - -
589,891,573.70 14.029 - - - -
480,009,892.93 11.416 - - - -
10,528,580.97 0.250 - - - -
104,193,457.02 2.478 - - - -
173,213,617.50 4.119 - - - -
859,517,725.00 20.441 - - - -
210,732,342.86 5.012 - - - -
3,737,029,435.82 88.874 - - -
4,204,885,390.308 100.000 - - -
PRESENTASE PROGRES
JUMLAH HARGA BOBOT
MINGGU LALU MINGGU INI S/D MINGGU INI
( Rp ) (%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT
7 8 9 10 11 12 13 14
ARDIANSYAH, ST
Inspekctor AGUNG IRFANDY A
Site Engginee
Tanggal, 29 Agustus 2018 s/d 2 September 2018
NO. 20/K-15.52.006/100.07/2018
29 Agustus 2018
PRESENTASE PROGRES
1,927.640 4.812
300.000 0.027
1,023.100 0.821
5.660
171.840 2.601
2.601
545.000 31.129
283.400 14.029
21,461.380 11.416
545.000 0.250
92.070 2.478
277.200 4.119
716.000 20.441
768.000 5.012
88.874
100.000
PRESENTASE PROGRES
DI BUAT OLEH :
KONTRAKTOR PELAKSANA
PT.DITA ANUGRAH
PERKASA
JUMLAH Rp.
RENCANA 4,204,885,390.31 100.00 0.71
TOTAL RENCANA KOMULATIF 0.71
REALISASI -
TOTAL REALISASI
DEVIASI TERHADAP RENCANA ( + / - )
TIME SCHEDULE
: Tanggal, 29 Agustus 2018 s/d 2 September 2018
NCANA ( % ) : 0.71 %
ALISASI ( % ) : - %
: (0.71) %
5.19
2.34 2.34
2.28 2.28 2.28 2.28 2.28
0.71 0.71 2.17 4.39 6.67 6.66 6.66 5.21 7.54 11.27
1.42 2.13 4.30 8.69 15.36 22.02 28.69 33.89 41.43 52.71
LENDER
3 BULAN 4 KET
12 13 14 15 16
100%
0.00 0.00 0.00 0.00 0.00
0.09 0.09
1.30 1.30
50%
LAPORAN MINGGUAN
MINGGU KE 1 ( SATU )
KONTRAKTOR PELAKSANA