Anda di halaman 1dari 7

: AREA PELAKSANAAN

PEKERJAAN PAVING

JALAN DESA

JALAN PASAR
JALAN DESA

JALAN RAYA

`
STA 0+255

STA 0+200

STA 0+150
: AREA PELAKSANAAN
PEKERJAAN PAVING

STA 0+100

STA 0+050

STA 0+000
TANAH EXISTING TANAH EXISTING

3000 2343

POTONGAN STA +000.00 EXISTING


SKALA 1 : 50

BATU GUNUNG
PAVING K.300 t.=6 cm
URUGAN PASIR
URUGAN TANAH
TANAH EXISTING

3000 2343

POTONGAN STA +000.00 RENCANA


SKALA 1 : 50
TANAH EXISTING
TANAH EXISTING

3000 1353

POTONGAN STA +050.00 EXISTING


SKALA 1 : 50

BATU GUNUNG
PAVING K.300 t.=6 cm
URUGAN PASIR
URUGAN TANAH TANAH EXISTING

3000 1353

POTONGAN STA +050.00 RENCANA


SKALA 1 : 50
TANAH EXISTING
TANAH EXISTING
TANAH EXISTING

2688 3000 1267

POTONGAN STA +100.00 EXISTING


SKALA 1 : 50

BATU GUNUNG
PAVING K.300 t.=6 cm
TANAH EXISTING URUGAN PASIR
TANAH EXISTING URUGAN TANAH TANAH EXISTING

2859 3000 1430

POTONGAN STA +100.00 RENCANA


SKALA 1 : 50
TANAH EXISTING TANAH EXISTING

2026 3000 2186

POTONGAN STA +150.00 EXISTING


SKALA 1 : 50

BATU GUNUNG
PAVING K.300 t.=6 cm
URUGAN PASIR
TANAH EXISTING URUGAN TANAH TANAH EXISTING

2026 3000 2186

POTONGAN STA +150.00 RENCANA


SKALA 1 : 50
BATU GUNUNG
PAVING K.300 t.=6 cm
URUGAN PASIR
URUGAN TANAH TANAH EXISTING

3000 1353

POTONGAN STA +200.00 EXISTING


SKALA 1 : 50

BATU GUNUNG
PAVING K.300 t.=6 cm
URUGAN PASIR
URUGAN TANAH TANAH EXISTING

3000 1353

POTONGAN STA +200.00 RENCANA


SKALA 1 : 50

Anda mungkin juga menyukai