JADWAL PERENCANAAN PEMBANGUNAN RUMAH 1 LANTAI TIPE 45

Durasi Free Float Total Float Waktu


No Kegiatan Simbol Predesesor Ei Ej Li Lj
(hari) FF TF Kritis
1 Pek. Persiapan A 8 - 0 8 0 8 0 0 kritis
2 Pek. Galian tanah + urugan B 3 A 8 11 8 11 0 0 kritis
3 Pek. Septictank + pondasi + sloof C 10 B 11 21 11 21 0 0 kritis
4 Pek. Kolom struktrur D 12 C 21 33 21 33 0 0 kritis
5 Pek. Pasangan bata + kolom praktis E 15 C 21 36 21 54 0 18
6 Pek. Balok srtuktur F 10 D 33 43 33 43 0 0 kritis
7 Pek. Kusen pintu & jendela G 4 E,F 36 58 54 58 18 18
8 Pek. Rangka/ Penutup atap H 15 E,F 43 58 43 58 0 0 kritis
9 Pek. Instalasi listrik I 4 G,H 33 37 33 42 0 5
10 Pek. Instalasi air bangunan J 8 I 37 45 42 50 0 5
11 Pek. Plester & Acian K 8 G,H 45 58 50 58 5 5
12 Pek. Plafond L 3 J,K 58 61 58 61 0 0 kritis
13 Pek. Sanitair & Fixture M 4 L 61 65 61 65 0 0 kritis
14 Pek. Lantai N 10 J 65 75 65 75 0 0 kritis
15 Pek. Finishing O 10 M 75 85 75 85 0 0 kritis
Total 124
CRITICAL PATH METHOD (CPM)

PEMBANGUNAN RUMAH 1 LANTAI TIPE 45

37 45
J
8 hr
42 50

I 4 hr
8 hr K

0 8 11 21 33 43 58 61 65 75 85
A B C D F H L M N O
8 hr 3 hr 10 hr 12 hr 10 hr 15 hr 3 hr 4 hr 10 hr 10 hr
0 8 11 21 33 43 58 61 65 75 85

4 hr
G
15 hr 36
E
54