NO JENIS PEKERJAAN SATUAN VOLUME


I PEKERJAAN PERSIAPAN
1 Pembersihan Lahan m² 38.50
2 Pemasangan Bouwplank buah 28.00
SUB TOTAL I
II PEKERJAAN TANAH
1 Galian Tanah m³ 5.00
2 Urugan Pasir m³ 4.00
SUB TOTAL II
III PEKERJAAN PASANGAN
1 Pondasi Batu Kali Kosong m³ 1.35
2 Pondasi Batu Kali 1 Pc: 3 Ps m³ 7.60
3 Pek.Lantai Terjunan (Pas. Batu Kali 1Pc:3Ps) m³ 1.65
SUB TOTAL III
IV PEKERJAAN PRASARANA
1 Pengalihan Aliran m³ 50.00
SUB TOTAL IV
V PEKERJAAN STRIPING
1 Striping I m³ 28.60
SUB TOTAL V
TOTAL
MARANG

RAB)

HARGA SATUAN JUMLAH BOBOT (%) DURASI MINGGU 1 MINGGU 2

13,900.000 535,150.000 3.787 1.000 3.787


138,440.500 3,876,334.000 27.428 2.000 13.714
4,411,484.000 31.215

29,500.000 147,500.000 1.044 3.000 0.348


152,900.000 611,600.000 4.328 2.000
759,100.000 5.371

282,900.000 381,915.000 2.702 3.000 0.901


706,300.000 5,367,880.000 37.982 1.000 37.982
706,300.000 1,165,395.000 8.246 3.000 2.749
6,915,190.000 48.930

29,500.000 1,475,000.000 10.437 1.000 10.437


1,475,000.000 10.437

20,000.000 572,000.000 4.047 1.000 4.047


572,000.000 4.047
14,132,774.000
MINGGU 3 MINGGU 4 MINGGU 5

13.714

0.348 0.348
2.164 2.164

0.901 0.901
SMK NEGERI

Pekerjaan : Pembuatan Rumah Tinggal Type 36


Lokasi : Gunung Pati
T.A : 2018/2019

NO JENIS PEKERJAAN JUMLAH BOBOT (%)


I PEKERJAAN PERSIAPAN 4411484.00 28.265
II PEKERJAAN TANAH 759100.00 4.864
III PEKERJAAN PONDASI 6915190.00 44.306
IV PEKERJAAN BETON 2950000.00 18.901
V PEKERJAAN PASANGAN DINDING 572000.00 3.665
PROGRES MINGGU INI 100.000.000
15607774.00
PROGRES SD MINGGU INI
SMK NEGERI 7 (STM PEMBANGUNAN) SEMARANG
XI TKJIJ 2

DURASI MINGGU 1 MINGGU 2 MINGGU 3 MINGGU 4 MINGGU 5


1 28.26
2 2.43 2.43
3 14.77 14.77 14.77
2 9.45 9.45
3 1.22 1.22
SMK N 7 (STM PEMBANGUNAN) SEMARANG
XI TKJIJ 2
REKAPITULASI

Pekerjaan : Bangunan Terjunan


Lokasi : Gunung Pati
T.A : 2018/2019

NO JENIS PEKERJAAN JUMLAH


I PEKERJAAN PERSIAPAN 4411484.00
II PEKERJAAN TANAH 759100.00
III PEKERJAAN PASANGAN 6915190.00
IV PEKERJAAN PRASARANA 2950000.00
V PEKERJAAN STRIPING 572000.00
TOTAL 15607774.00
SMK N 7 (STM PEMBANGUNAN) SEMARANG
XI TKJIJ 2
RENCANA ANGGARAN BIAYA (RAB)

Pekerjaan : Bangunan Terjunan


Lokasi : Jl. Kauman II Mranggen Rt.03/05
T.A : 2018/2019

NO JENIS PEKERJAAN SATUAN VOLUME


I PEKERJAAN PERSIAPAN
1 Pembersihan Lahan m² 38.50
2 Pemasangan Bouwplank buah 28.00
SUB TOTAL I
II PEKERJAAN TANAH
1 Galian Tanah m³ 5.00
2 Urugan Pasir m³ 4.00
SUB TOTAL II
III PEKERJAAN PASANGAN
1 Pondasi Batu Kali Kosong m³ 1.35
2 Pondasi Batu Kali 1 Pc: 3 Ps m³ 7.60
3 Pek.Lantai Terjunan (Pas. Batu Kali 1Pc:3Ps) m³ 1.65
SUB TOTAL III
IV PEKERJAAN PRASARANA
1 Pengalihan Aliran m³ 50.00
SUB TOTAL IV
V PEKERJAAN STRIPING
1 Striping I m³ 28.60
SUB TOTAL V
TOTAL
AN) SEMARANG

IAYA (RAB)

HARGA SATUAN JUMLAH

13900.00 535150.00
138440.50 3876334.00
4411484.00

29500.00 147500.00
152900.00 611600.00
759100.00

282900.00 381915.00
706300.00 5367880.00
706300.00 1165395.00
6915190.00

29500.00 1475000.00
1475000.00
2950000.00
20000.00 572000.00
572000.00
15607774.00
TABEL -
RINGKASAN ANALISA HARGA SATUAN POKOK KEGIATAN (AHSPK)
BENDUNGAN LOGUNG KABUPATEN KUDUS

INDRA KARYA REVISI


No. Harga Satuan
Jenis Pekerjaan Satuan
Analisa (Rp)

A PEKERJAAN PERSIAPAN
A.00 Mobilisasi dan Demobilisasi LS 383,700,000.00
A.01 Barak Kerja (70 m2) LS 94,145,000.00
A.02 Kantor Lapangan (200 m2) LS 443,450,100.00
A.03 Penyediaan Air Bersih dan Sanitasi LS 106,205,000.00
A.04 Penyediaan Sarana Penerangan Kantor LS 404,800,000.00
A.05 Penyediaan Sarana Telekomunikasi LS 87,312,500.00
A.06 Penyediaan Sarana & Prasarana Laboratorium LS 408,479,500.00
A.07 Penyediaan Sarana Kesehatan LS 227,700,000.00
A.08 Jalan masuk ke lokasi ( Pemeliharaan,perbaikan , dll.) LS 5,889,015,000.00
A.09 Dokumentasi Foto dan film Kemajuan Pekerjaan LS 308,343,200.00
A.10 Pencegahan HIV AID LS 537,900,000.00
A.11 Pemantauan Lingkungan LS 419,760,000.00

B PEKERJAAN PENGELAKAN SUNGAI


B.01a Dewatering LS 310,961,700.00

C PEKERJAAN TANAH
C.01 Pembersihan lapangan m2 13,900.00
Pembersihan / Penebangan pohon m2 27,600.00
C.02 Pengupasan (minimum 0,15 m / tebal top soil) m2 21,200.00
C.03 Galian Tanah biasa m3 29,500.00
C.04 Penggalian Batu Lapuk (dengan alat berat) m3 63,900.00
C.05 Penggalian Batu Keras (dengan alat berat) m3 109,500.00
C.07 Timbunan inti (material kedap) m3 125,600.00
C.08 Timbunan Filter Halus (material pasir) m3 296,800.00
C.09 Timbunan Filter Kasar (material kerikil) m3 330,100.00
C.10 Timbunan Batu (dari stock pile) m3 293,800.00
C.11 Timbunan Riprap (material batu) m3 295,500.00
C.12 Timbunan tanah dipadatkan m3 20,200.00
C.13 Lapisan Kerikil m3 164,800.00
C.14 Urugan Pasir m3 152,900.00
C.15 Timbunan Random Tanah dari stockpile m3 48,600.00
C.16 Gebalan Rumput m2 14,000.00
C.17 Timbunan Sirtu m3 182,500.00
C.18 Timbunan Random (pengangkutan dari borrow area m3 79,100.00
ke stockpile, stockpile ke lokasi timbunan)
D PEKERJAAN BETON
D.01a Beton K-350 m3 1,228,400.00
D.01 Beton K-300 m3 1,162,100.00
D.02 Beton K-250 m3 1,117,400.00
D.03 Beton K-225 m3 1,090,900.00
D.04 Beton K-175 m3 1,033,000.00
D.05a Beton K-125 m3 958,100.00
D.05b Beton K100 / Lantai kerja m3 893,100.00
D.06 Tulangan Beton (pemotongan, pembengkokan dan pemasangan) Kg 15,378.00
D.07 Bekisting tipe non expose F1 (termasuk perancah dan pembongkaran) m2 155,300.00
D.08 Bekisting tipe expose F2 (termasuk perancah dan pembongkaran) m2 186,400.00
D.09 Bekisting tipe expose F4 (termasuk perancah dan pembongkaran) m2 192,600.00
TABEL -
RINGKASAN ANALISA HARGA SATUAN POKOK KEGIATAN (AHSPK)
BENDUNGAN LOGUNG KABUPATEN KUDUS

INDRA KARYA REVISI


No. Harga Satuan
Jenis Pekerjaan Satuan
Analisa (Rp)
TABEL -
RINGKASAN ANALISA HARGA SATUAN POKOK KEGIATAN (AHSPK)
BENDUNGAN LOGUNG KABUPATEN KUDUS

INDRA KARYA REVISI


No. Harga Satuan
Jenis Pekerjaan Satuan
Analisa (Rp)
E PEKERJAAN PASANGAN
E.01 Pasangan Batu Kali (1Pc : 3Ps) m3 706,300.00
E.02 Pasangan Batu Kali (1Pc : 4Ps) m3 670,200.00
E.03 Pasangan Batu Bata (1Pc : 4Ps) m3 216,000.00
E.04 Plesteran t=15 mm (1Pc : 3Ps) m2 42,000.00
E.05 Pasangan Batu Kali Kosong m3 282,900.00
E.06 Bronjong ukuran 1,00X2,00X0,50 m3 m3 588,431.25
E.07 Siaran (1PC : 2 Ps) m2 37,000.00
F PEKERJAAN JALAN
F.01 Lapisan Permukaan / Surface Course (penetrasi makadam aspal) m3 1,382,800.00
Lapisan penetrasi batu belah 10/15 m3 1,455,400.00
F.02 Lapis Pondasi / Base Course, Agregat Class A m3 274,800.00
F.03 Lapis Pondasi / Base Course, Agregat Class B m3 272,800.00
F.04 Lapis Pondasi / Base Course, Agregat Class C m3 301,900.00
F.02 Berm (Agregat Klas A) t = 30 Cm m2 274,800.00
F.05 Lapisan HRS m2 101,000.00
F.06 Lapisan ATB m3 2,955,600.00
G PEKERJAAN DRILLING DAN GROUTING
G.01 Pemboran Lubang Consolidation, Blanket dan Curtain Grouting m' 496,700.00
G.06 Pemboran Inti untuk Pilot & Check Hole m' 422,800.00
G.10 Material Grouting ( Semen ) ton 1,763,600.00
G.12 Water Pressure Test untuk Pilot & Check Hole test 272,200.00
G.14 Backfill Grouting m3 1,304,900.00
G.15 Shotcrete with Steel Wire Mesh 100 x 100 x 4 mm m2 397,200.00
G.16 Rock Bolt D=22, L=3 m m' 189,800.00
H INSTRUMENTASI
H.01 Hydraulic piezometer unit 35,097,500.00
H.01a Stand Pipe Piezometer unit 89,950,000.00
H.02 Seepage Water Measuring Device (V-notch weir) unit 51,894,200.00
H.03 Multilayer Settlement Gauges unit 80,978,000.00
H.05 Crest Settlement Survey Point unit 2,178,000.00
H.06 Observation Holes unit 16,879,500.00
H.07 Automatic Water Level Recorder (AWLR) unit 58,080,000.00
H.08 Papan Duga Air unit 315,700.00
H.09 Inklinometer unit 342,442,000.00
I HIDROMEKANIKAL
I.01 Intake Trashrack @((3 m x 0.750 m) x 2 bh) set 88,204,800.00
I.02 Fix Wheel Gate ( 1 x 1) set 786,555,000.00
I.03 Sleeve valve dia. 0.3 m set 27,582,500.00
I.04 Butterfly Valve, dia. 0,10 m set 5,500,000.00
I.05 Hollow Jet Valve, dia. 0,80 m set 113,025,000.00
I.05a Butterfly Valve, dia. 0,20 m Set 25,025,000.00
I.05b Butterfly Valve, dia. 0,15 m Set 12,512,500.00
I.06 Butterfly Valve, dia. 1.20 m set 117,425,000.00
I.06a Butterfly Valve, dia. 0,80 m set 100,925,000.00
I.06b Butterfly Valve, dia. 0.40 m set 50,050,000.00
I.07 Pipa Baja Saluran Utama, dia. 1,00 m tebal 10 mm set 23,302,700.00
I.09 Pipa Baja Saluran Utama, dia. 0,50 m tebal 10 mm set 18,941,100.00
I.11 Pintu 1,50 x 2,50 m set 359,105,000.00
I.11 Pintu 4,00 x 4,00 m lengkap dg giude frame set 2,066,530,000.00
TABEL -
RINGKASAN ANALISA HARGA SATUAN POKOK KEGIATAN (AHSPK)
BENDUNGAN LOGUNG KABUPATEN KUDUS

INDRA KARYA REVISI


No. Harga Satuan
Jenis Pekerjaan Satuan
Analisa (Rp)
TABEL -
RINGKASAN ANALISA HARGA SATUAN POKOK KEGIATAN (AHSPK)
BENDUNGAN LOGUNG KABUPATEN KUDUS

INDRA KARYA REVISI


No. Harga Satuan
Jenis Pekerjaan Satuan
Analisa (Rp)
J PEKERJAAN GEDUNG
J.01 Pemasangan Kuda-kuda Kayu Kruing m3 9,301,900.00
J.02 Pemasangan Reng Meranti / Usuk Kamper m2 104,800.00
J.03 Pemasangan Lisplank Kayu Kamper t=3 cm m' 110,000.00
J.04 Pemasangan Atap Asbes Gelombang Kecil m2 41,200.00
J.05 Pemasangan Wuwung Asbes Gelombang m' 74,300.00
J.06 Kusen Pintu / Jendela Kayu Meranti m3 10,035,500.00
J.07 Daun Pintu Teakwood m2 615,200.00
J.08 Daun Pintu Triplek m2 577,800.00
J.09 Pemasangan Kaca Mati t=5 mm m2 107,900.00
J.10 Gording / Nock m3 9,174,100.00
J.11 Pemasangan Kaca Mati Rayban t=5 mm m2 120,000.00
J.12 Pengecatan Tembok m2 52,300.00
J.13 Pemasangan Tegel Plin Abu-abu 15x20 cm campuran 1Pc : 2Ps m2 225,200.00
J.14 Pemasangan Tegel Teraso 30 x 30 cm m2 150,400.00
J.15 Pemasangan Tegel Keramik 30 x 30 cm m2 159,000.00
J.16 Pemasangan Kran Air bh 24,300.00
J.17 Kloset jongkok Porselin bh 412,600.00
J.18 Bak Mandi batu bata Volume 0,30m3 bh 1,088,000.00
J.19 Besi Baja Profil WF < 200 mm kg 40,300.00
J.20 Rangka Kuda-kuda L. 50.50.5 kg 46,800.00
J.21 List Plafon 15x15 cm m2 22,100.00
J.21a Plafon Eternit Rangka Kayu Meranti m2 242,000.00
J.22 Pemasangan Wastafel bh 522,000.00
J.24 Grendel bh 22,600.00
J.25 Engsel Kuningan bh 29,200.00
J.26 Kunci Tanam Besar 2x Putar bh 198,000.00
J.27 Gudang Lapangan ( 140 m2 ) LS 91,004,900.00
J.28 Tandon Air LS 27,175,077.49
J.29 Tangki Bahan Bakar LS 21,089,090.00
M.01 Kantor Utama Bendungan (420 m2) LS 827,476,100.00
J.34 Rumah Dinas Type 1 (60 m2) (1 Unit) LS 117,692,000.00
J.35 Rumah Dinas Type 2 (45 m2) (1 Unit) LS 92,882,000.00
J.37 Gardu Pandang (40 m2) LS 84,461,000.00
J.38 Pos Jaga (9 m2) LS 15,719,000.00
J.39 Mushola (60 m3) LS 117,411,000.00
J.40 Rumah Genset (16 m2) LS 31,169,000.00
J.41 Bengkel Peralatan (120 m2) LS 220,919,000.00
J.41a Rumah Instrumentasi (31.76 m2) LS 62,823,000.00
J.42 Rumah tangki Bahan Bakar (90 m³) LS 167,607,000.00

K PEKERJAAN LAIN-LAIN
K.01 PVC Water Stop, l=300 mm m' 169,800.00
K.02 Dowel Bar dia. 25, L=1 m bh 67,600.00
K.03 Anchor Bar D25 L=2,00 m m' 141,600.00
Anchor Bar D50 m' 233,500.00
K.04 Handrail, Galvanis Pipe dia. 3" (termasuk cat) m' 182,300.00
K.05 Pipa PVC Perforated dia. 6" m' 181,000.00
TABEL -
RINGKASAN ANALISA HARGA SATUAN POKOK KEGIATAN (AHSPK)
BENDUNGAN LOGUNG KABUPATEN KUDUS

INDRA KARYA REVISI


No. Harga Satuan
Jenis Pekerjaan Satuan
Analisa (Rp)
K.06 Besi Plat, 2,5 mm ton 15,814,800.00
K.07 Tiang Pancang (pengadaan tiang pancang) m' 114,100.00
K.08 Baja WF 150.150 kg 26,100.00
K.02 Dowel Bar dia. 25, L=2 m bh 67,600.00
K.10 Buis beton dia. 0,70 m (pengadaan dan pemasangan) m' 236,500.00
TABEL -
RINGKASAN ANALISA HARGA SATUAN POKOK KEGIATAN (AHSPK)
BENDUNGAN LOGUNG KABUPATEN KUDUS

INDRA KARYA REVISI


No. Harga Satuan
Jenis Pekerjaan Satuan
Analisa (Rp)
K.11 Tangga (pipa galvanis) dia. 16 mm m' 104,000.00
K.12 Pintu Plat besi t+C139=5 mm (0,8 x 2 m) bh 10,463,000.00
K.13 Buis beton dia. 1,20 m (pengadaan dan pemasangan) m' 230,200.00
K.14 Geotextile, t=2 mm m2 27,800.00
K.15 Weep Hole Pipa PVC dia. 2" m' 50,500.00
K.16 Pancang Dolken m' 114,100.00
K.18 Elastomerik bh 550,000.00
K.19 Pengadaan dan Pemasangan Fasilitas AC bh 4,537,500.00
K.20 Pengadaan dan Pemasangan Fasilitas Closet Duduk bh 1,444,000.00
K.21 Joint Filler t=1 cm bh 153,400.00
L PEKERJAAN LISTRIK
L.01 Instalasi Jaringan Tegangan Menengah 20 KV/220 V LS 246,477,700.00
L.03 Instalasi Penerangan Jalan dan Puncak Bendung LS 386,685,800.00
RENCANA ANGGARAN BIAYA ( R A B )
KEGIATAN : PEMBANGUNAN BENDUNGAN LOGUNG KABUPATEN KUDUS
TAHUN ANGGARAN : 2014

HARGA BIAYA
NO URAIAN SATUAN VOLUME SATUAN PEKERJAAN
(Rp.) (Rp.)
A. PEKERJAAN PERSIAPAN
a Mobilisasi dan Demobilisasi Ls 1.00 383,700,000.00 383,700,000.00
b Jalan masuk ke lokasi ( Pemeliharaan,perbaikan , dll.) Ls 1.00 5,889,015,000.00 5,889,015,000.00
c Kantor Direksi, Konsultan ( 200 m2 ) unit 1.00 443,450,100.00 443,450,100.00
Kantor Kontraktor ( 200 m2 ) unit 1.00 443,450,100.00 443,450,100.00
d Gudang Lapangan & Mushola ( 140 m2 ) unit 1.00 91,004,900.00 91,004,900.00
e Barak Kerja ( 70 m2 ) unit 1.00 94,145,000.00 94,145,000.00
f Gedung Poliklinik ( 31,75 m2 ) unit 1.00 62,823,000.00 62,823,000.00
g Bengkel Peralatan (120 m2 ) unit 1.00 220,919,000.00 220,919,000.00
h Penyedia Sarana & Prasarana Laboratorium unit 1.00 408,479,500.00 408,479,500.00
i Penyediaan Air Bersih dan Sanitasi Ls 1.00 106,205,000.00 106,205,000.00
j Penyediaan Sarana Penerangan Kantor Ls 1.00 404,800,000.00 404,800,000.00
k Penyediaan Sarana Telekomunikasi Ls 1.00 87,312,500.00 87,312,500.00
l Penyediaan Sarana Kesehatan Ls 1.00 227,700,000.00 227,700,000.00
m Dokumentasi Foto dan film Kemajuan Pekerjaan LS 1.00 308,343,200.00 308,343,200.00
n Program Pencegahan HIV AID LS 1.00 537,900,000.00 537,900,000.00
o Pemantauan Lingkungan LS 1.00 419,760,000.00 419,760,000.00
p Penyelenggaraan K3 Konstruksi LS 1.00 480,000,000.00 480,000,000.00
q Pembuatan laporan pelaksanaan pekerjaan LS 1.00 423,500,000.00 423,500,000.00
r Survey pengukuran, working drawing dan as build drawing LS 1.00 663,400,000.00 663,400,000.00
s Mebeler dan peralatan Kantor LS 1.00 300,000,000.00 300,000,000.00
11,995,907,300.00
B. PEKERJAAN JALAN

ACCES ROAD ( termasuki Houlling road )


1 Acces Road Panjang 3.590 m
a Pengupasan (minimum 0,15 m / tebal top soil) m2 43,075.00 21,200.00 913,190,000.00
b Galian tanah biasa m3 154,195.00 29,500.00 4,548,752,500.00
c Timbunan tanah dipadatkan ( random dari stockpile ) m3 7,773.00 48,600.00 377,767,800.00
d Beton K250 m3 216.00 1,117,400.00 241,358,400.00
e Beton K100 / Lantai kerja m3 17.00 893,100.00 15,182,700.00
f Baja tulangan ulir U 32 kg 31,545.00 15,378.00 485,099,010.00
g Begisting non Expose F1 m2 544.00 155,300.00 84,483,200.00
2 Drainase
a Galian tanah untuk selokan m3 4,629.00 29,500.00 136,555,500.00
b Pasangan Batu Kali (1Pc : 4Ps) m3 4,067.00 670,200.00 2,725,703,400.00
c Plesteran t=15 mm (1Pc : 3Ps) m2 8,112.00 42,000.00 340,704,000.00

3 Pekerjaan Pendukung
a Marka Jalan m2 177.00 158,200.00 28,001,400.00
b Rambu jalan bh 10.00 322,100.00 3,221,000.00
c Patok pengarah bh 120.00 94,708.00 11,364,960.00
d Patok kilometer bh 2.00 373,309.00 746,618.00
9,912,130,488.00
C PENGELAK SUNGAI
I Dewatering thn 4.00 319,995,500.00 1,279,982,000.00

II Primary Cofferdam. U/S


a Galian tanah biasa m3 18,514.00 29,500.00 546,162,918.88
b Timbunan tanah dipadatkan ( random dari stockpile) m3 123,429.00 48,600.00 5,998,649,400.00
6,544,812,318.88
III Primary Cofferdam. D/S
a Galian tanah biasa m3 9,288.00 29,500.00 273,995,859.88
b Timbunan tanah dipadatkan ( random dari stockpile) m3 45,034.00 48,600.00 2,188,652,400.00
2,462,648,259.88
IV Main Coffer Dam. ( MCD )
a Pembersihan Lapangan Inlet/Outlet Open Channel &MCD m2 25,867.00 13,900.00 359,551,300.00
b Galian tanah biasa, m3 13,901.00 29,500.00 410,079,536.88
c Penggalian Batu Lapuk (dengan alat berat) m3 11,120.00 63,900.00 710,568,063.90
d Penggalian Batu Keras (dengan alat berat) m3 4,170.00 109,500.00 456,615,041.06
Tmbunan :
a Core / Inti. Kedap air m3 28,273.00 125,600.00 3,551,088,800.00
b Filter / Saringan halus. m3 3,540.00 296,800.00 1,050,670,702.98
RENCANA ANGGARAN BIAYA ( R A B )
KEGIATAN : PEMBANGUNAN BENDUNGAN LOGUNG KABUPATEN KUDUS
TAHUN ANGGARAN : 2014

HARGA BIAYA
NO URAIAN SATUAN VOLUME SATUAN PEKERJAAN
(Rp.) (Rp.)
c Filter / Saringan kasar. m3 1,523.00 330,100.00 502,740,741.93
d Timbunan batu m3 4,705.00 293,800.00 1,382,327,531.00
e Riprap m3 5,624.00 295,500.00 1,661,891,704.50
f Timbunan Random ( Pengangkutan dr Borrow area ke - m3 176,179.00 79,100.00 13,935,759,164.19
stock pile - lokasi timbunan 24,021,292,586.44
V Saluran Pengelak
1 Inlet
a Galian tanah biasa. m3 12,248.00 29,500.00 361,316,000.00
b Penggalian Batu Lapuk (dengan alat berat) m3 12,861.00 63,900.00 821,818,151.73
C Penggalian Batu Keras (dengan alat berat) m3 11,023.00 109,500.00 1,207,018,087.61
d Beton K-225 m3 407.00 1,090,900.00 443,996,913.63
e Besi beton kg 8,469.00 15,378.00 130,236,300.99
f Bekisting expose type F2 m2 496.00 186,400.00 92,454,750.43
g Pasangan Batu Kali (1Pc : 4Ps) m3 41.00 670,200.00 27,474,849.00
h Siaran (1PC : 2 Ps) m2 80.00 37,000.00 2,960,000.00
2 Outlet
a Galian tanah biasa. m3 7,168.00 29,500.00 211,455,985.98
b Penggalian Batu Lapuk (dengan alat berat) m3 5,256.00 63,900.00 335,858,122.14
c Penggalian Batu Keras (dengan alat berat) m3 2,150.00 109,500.00 235,425,203.39
d Timbunan tanah dipadatkan ( random dari stockpile) m3 3,444.00 48,600.00 167,378,449.78
e Beton K-225 m3 1,202.00 1,090,900.00 1,311,261,800.00
f Besi beton kg 189,437.00 15,378.00 2,913,162,240.48
g Bekisting expose type F2 m2 8,198.00 186,400.00 1,528,107,131.03
3 Diversion Conduit .
a. Galian tanah biasa, m3 22,941.00 29,500.00 676,759,619.01
b. Penggalian Batu Lapuk (dengan alat berat) m3 16,059.00 63,900.00 1,026,170,344.36
c. Penggalian Batu Keras (dengan alat berat) m3 5,735.00 109,500.00 627,982,500.00
d Concrete Conduit ( K350 ) m3 6,889.00 1,228,400.00 8,462,447,600.00
e Besi beton kg 757,891.00 15,378.00 11,654,847,798.00
f Bekisting expose type F2 m2 17,756.00 186,400.00 3,309,718,400.00
g Filling Grouting ton 9,044.00 1,763,600.00 15,949,998,400.00
h Backfill Grouting m3 11.00 1,304,900.00 14,353,685.79
i Beton Plugging ( K225 ) m3 156.00 1,090,900.00 170,180,400.00
j Bekisting expose type F4 m2 47.00 192,600.00 9,052,200.00
51,691,434,933.35
VI Rumah kontrol / Control Room
a Galian tanah biasa m3 900.00 29,500.00 26,550,103.25
b Timbunan tanah dipadatkan ( random dari stockpile) m3 555.00 48,600.00 26,972,829.90
c Beton lantai dasar Besement EL. 91.00 ( K225 ) m3 1,837.00 1,090,900.00 2,003,980,027.30
d Beton lantai 1 EL. 94.20 ( K225 ) m3 1,870.00 1,090,900.00 2,039,983,000.00
e Besi beton kg 398,169.00 15,378.00 6,123,042,882.00
f Bekisting expose type F2 m2 1,646.00 186,400.00 306,814,400.00
10,527,343,242.45
D SPILLWAY / BANGUNAN PELIMPAH
I Pekerjaan Tanah
a Pembersihan Lapangan areal spillway. m2 24,845.00 13,900.00 345,345,500.00
b Galian tanah biasa. m3 215,392.00 29,500.00 6,354,063,941.04
c Penggalian Batu Lapuk (dengan alat berat) m3 117,486.00 63,900.00 7,507,355,388.43
d Penggalian Batu Keras (dengan alat berat) m3 78,323.00 109,500.00 8,576,368,500.00
e Timbunan tanah dipadatkan ( random dari stockpile) m3 44,868.00 48,600.00 2,180,584,814.77
24,963,718,144.25
II Ambang Pelimpah.
a Beton K-225 m3 38,918.00 1,090,900.00 42,455,640,955.41
b Bekisting expose type F4 m3 27,297.00 195,900.00 5,347,483,275.58
c Besi beton kg 1,660,744.00 15,378.00 25,538,921,268.14
d Beton plat lantai plunge pool ( K225 ) m3 2,403.00 1,090,900.00 2,621,427,649.13
e Beton / Lantai kerja(1Pc : 3Ps : 5Kr) m3 1,729.00 916,500.00 1,584,624,834.00
77,548,097,982.26
III Jembatan (2 unit)
a Beton Lantai Kerja (1pc : 3ps 5:kr) m3 12.00 916,500.00 10,998,000.00
b Beton K-225 m3 125.00 1,090,900.00 136,362,500.00
c Besi Tulangan Ulir kg 25174.00 15,378.00 387,125,772.00
d Lapisan penetrasi/laston m2 218.00 147,780.00 32,216,040.00
e Bekisting expose type F2 m2 249.00 189,500.00 47,185,026.25
f Elastomeric bearing pad bh 8.00 550,000.00 4,400,000.00
g Pipa sandaran 3" galvanis termasuk cat m' 194.00 182,300.00 35,366,200.00
RENCANA ANGGARAN BIAYA ( R A B )
KEGIATAN : PEMBANGUNAN BENDUNGAN LOGUNG KABUPATEN KUDUS
TAHUN ANGGARAN : 2014

HARGA BIAYA
NO URAIAN SATUAN VOLUME SATUAN PEKERJAAN
(Rp.) (Rp.)
653,653,538.25
RENCANA ANGGARAN BIAYA ( R A B )
KEGIATAN : PEMBANGUNAN BENDUNGAN LOGUNG KABUPATEN KUDUS
TAHUN ANGGARAN : 2014

HARGA BIAYA
NO URAIAN SATUAN VOLUME SATUAN PEKERJAAN
(Rp.) (Rp.)
IV Lain-lain
a Water stop m' 22,745.00 169,800.00 3,862,101,000.00
b Pipa PVC dia. 6" ( drainase spillway ) m' 1,265.00 181,000.00 228,965,000.00
c Gebalan rumput m2 12,032.00 14,000.00 168,448,000.00
d Angkur dia 25 - 200 panjang 2.50 m kg 15,419.00 141,600.00 2,183,330,400.00
e Shotcrete tebal 6 cm m2 27,604.00 397,200.00 10,964,307,462.76
f Dowel Bar dia. 25, L=1 m bh 4,548.00 67,600.00 307,444,800.00
g Joint Filler t=1 cm m' 34,117.00 153,400.00 5,233,547,800.00
22,948,144,462.76
E MAIN DAM
I Large Scale Sample 2.00 150,000,000.00 300,000,000.00

II Galian tanah
a Galian tanah biasa, m3 48,571.00 29,500.00 1,432,844,389.38
b Penggalian Batu Lapuk (dengan alat berat) m3 34,000.00 63,900.00 2,172,600,215.66
c Penggalian Batu Keras (dengan alat berat) m3 14,571.00 109,500.00 1,595,524,814.81
5,200,969,419.85
III Timbunan
a Core / Inti. Kedap air m3 189,827.00 125,600.00 23,842,271,514.00
b Filter / Saringan halus. m3 69,564.00 296,800.00 20,646,596,007.30
c Filter / Saringan kasar. m3 21,852.00 330,100.00 7,213,345,596.12
d Timbunan batu m3 13,611.00 293,800.00 3,998,911,033.69
e Riprap m3 41,258.00 295,500.00 12,191,739,000.00
f Timbunan Random ( Pengangkutan dari Borrow area ke - m3 1,122,605.00 79,100.00 88,798,055,500.00
stock pile, stockpile - kelokasi timbunan
g Pemboran Lubang Curtain Grouting m' 94,560.00 496,700.00 46,967,952,000.00
h Pemboran Lubang Blanket Grouting m' 9,456.00 496,700.00 4,696,795,200.00
i Pemboran Inti untuk Pilot & Check Hole m' 6,304.00 422,800.00 2,665,331,200.00
j Material Grouting ( Semen ) ton 15,602.00 1,763,600.00 27,515,687,200.00
k Water Pressure Test untuk Pilot & Check Hole test 1,260.00 272,200.00 342,972,000.00
l Backfill Grouting m3 1,300.00 1,304,900.00 1,696,370,000.00
m Gebalan rumput m2 29,100.00 14,000.00 407,400,000.00
240,983,426,251.11
IV Perkerasan puncak bendungan
a Lapis penetrasi Makadam 5 cm m2 2,992.00 82,968.00 248,240,256.00
b Lapis penetrasi batu belah 10/15 m2 2,992.00 181,924.50 544,318,104.00
c Urugan Pasir m3 299.00 330,100.00 98,699,900.00
d Kanstin buah 2,152.00 18,777.00 40,408,104.00
e Patok pengaman buah 220.00 195,400.00 42,988,000.00
974,654,364.00
V Jalan inspeksi di lereng hilir Bendungan
a Timbunan tanah dipadatkan ( random dari stockpile) m3 13,200.00 48,600.00 641,520,000.00
b Lapis penetrasi Makadam 50 mm m2 1,200.00 82,968.00 99,561,600.00
c Lapis penetrasi batu belah 10/15 m2 1,200.00 181,924.50 218,309,400.00
d Urugan Pasir m3 120.00 330,100.00 39,612,000.00
e Pasangan Batu Kali (1Pc : 4Ps) m3 206.80 670,200.00 138,597,360.00
f Siaran (1PC : 2 Ps) m2 1,800.00 37,000.00 66,600,000.00
g Lubang pengering PVC 50 mm ( 2" ) m 300.00 50,500.00 15,150,000.00
1,219,350,360.00
VI Drainase Kaki Bendungan
1 Drainase Rembesan
a Galian tanah biasa, m3 586.00 29,500.00 17,287,000.00
b Beton K225 m3 189.00 1,090,900.00 206,180,100.00
c Besi beton kg 8,316.00 15,378.00 127,883,448.00
d Pipa PVC dia 50 mm ( 2 " ) m' 20.00 50,500.00 1,010,000.00
e Pipa beton U R = 25 cm bh 150.00 58,344.00 8,751,600.00
f Begisting non Expose F1 m2 702.00 155,300.00 109,020,600.00
2 Drainase air hujan
a Galian tanah biasa, m3 2,624.00 29,500.00 77,407,893.18
b Timbunan tanah dipadatkan ( random dari stockpile) m3 186.00 48,600.00 9,039,794.40
c Beton K225 m3 216.00 1,090,900.00 235,634,400.00
d Besi beton kg 9,073.00 15,378.00 139,524,594.00
e Pipa beton U R = 25 CM bh 243.00 58,344.00 14,177,592.00
f Begisting non Expose F1 m2 1,386.00 155,300.00 215,245,644.70
g Pipa PVC dia 50 mm ( 2 " ) m 33.00 50,500.00 1,666,500.00
h Timbunan batu m3 43,638.00 293,800.00 12,820,844,400.00
RENCANA ANGGARAN BIAYA ( R A B )
KEGIATAN : PEMBANGUNAN BENDUNGAN LOGUNG KABUPATEN KUDUS
TAHUN ANGGARAN : 2014

HARGA BIAYA
NO URAIAN SATUAN VOLUME SATUAN PEKERJAAN
(Rp.) (Rp.)
13,983,673,566.28
RENCANA ANGGARAN BIAYA ( R A B )
KEGIATAN : PEMBANGUNAN BENDUNGAN LOGUNG KABUPATEN KUDUS
TAHUN ANGGARAN : 2014

HARGA BIAYA
NO URAIAN SATUAN VOLUME SATUAN PEKERJAAN
(Rp.) (Rp.)
F BANGUNAN PENGAMBILAN / INTAKE
I Inlet Work
a Pembersihan Lapangan area Intake m2 1,322.00 13,900.00 18,375,800.00
b Galian tanah biasa m3 1,286.00 29,500.00 37,937,041.30
c Penggalian Batu Lapuk (dengan alat berat) m3 898.00 63,900.00 57,382,404.48
d Penggalian Batu Keras (dengan alat berat) m3 299.00 109,500.00 32,740,981.80
e Beton apron K225 ( Pot. E - E dan F - F ) m3 194.00 1,090,900.00 211,631,327.30
f Buis beton dia 0.70 m bh 12.00 236,500.00 2,838,000.00
g Angkur dia 25 mm m 24.00 141,600.00 3,398,400.00
h Pipa udara dia 0.50 m tebal 10 mm m 53.00 18,941,100.00 1,003,878,300.00
i Beton K225 ( Pot. A - A dan Pot B - B ) m3 1,018.00 1,090,900.00 1,110,536,200.00
j Besi beton kg 137,417.00 15,378.00 2,113,198,626.00
4,591,917,080.88
II Pipa Intake dia 1.00 m
a Galian tanah biasa m3 76.00 29,500.00 2,242,000.00
b Penggalian Batu Lapuk (dengan alat berat) m3 53.00 63,900.00 3,386,789.46
c Penggalian Batu Keras (dengan alat berat) m3 17.00 109,500.00 1,861,186.10
d Beton pembungkus pipa dia 1.00 m ( K225 ) m3 107.00 1,090,900.00 116,726,300.00
e Besi beton kg 6,619.00 15,378.00 101,786,982.00
f Pipa baja dia 1.00 m tebal 10 mm m 25.00 23,302,700.00 582,567,500.00
g Bekisting expose type F2 m2 124.00 186,400.00 23,113,600.00
h Grouting ( filling Grouting ) ton 640.00 1,763,600.00 1,128,698,356.48
i Backfill Grouting m3 8.00 1,304,900.00 10,434,155.78
1,970,816,869.82
III Valve House.
1 Struktur Bawah
a Galian tanah biasa m3 2,580.00 29,500.00 76,110,000.00
b. Timbunan tanah dipadatkan ( random dari stockpile) m3 244.00 48,600.00 11,858,400.00
c. Beton K-225 m3 1,582.00 1,090,900.00 1,725,805,436.35
d. Besi beton kg 174,038.00 15,378.00 2,676,356,287.11
2 Struktur Atas
a Beton K 225 kolom , plat atap , lisplank dll m3 151.00 1,090,900.00 164,720,445.50
b. Besi beton kg 15,895.00 15,378.00 244,433,310.00
4,899,283,878.96
IV Jembatan Penghubung
1 Struktur Bawah
Abutment
a Beton K225 m3 688.00 1,090,900.00 750,539,200.00
b Beton Plat injak K225 m3 8.00 1,090,900.00 8,727,200.00
c Besi beton. kg 1,480.00 15,378.00 22,759,440.00
d Beton / Lantai kerja(1Pc : 3Ps : 5Kr) m3 6.00 893,100.00 5,358,600.00
2 Struktur Atas
a Beton plat lantai K225 m3 31.00 1,090,900.00 33,817,900.00
b Trotoar K225 m3 18.00 1,090,900.00 19,636,200.00
c Besi beton. kg 5,405.00 15,378.00 83,118,090.00
d Bekisting expose type F2 m2 125.00 186,400.00 23,300,000.00
e Elastomeric bearing Pad. 65x400x16 Buah 8.00 550,000.00 4,400,000.00
f Anchor rod , D = 50 mm, L = 75 Cm. Buah 16.00 233,500.00 3,736,000.00
g Handrail, Galvanis Pipe dia. 3" (termasuk cat) m 104.00 182,300.00 18,959,200.00
h Expantion Joint. m 2.00 607,753.00 1,215,506.00
i Steel Drain pipe 75 mm. m 20.00 129,861.00 2,597,220.00
j Besi L 75 X 75 x 7 kg 333.00 40,300.00 13,419,900.00
k Besi U 120 x55x7 kg 563.00 40,300.00 22,688,900.00
l Pengaspalan Jembatan (ATB) m2 156.00 177,336.00 27,664,416.00
m Shear connector canal ( 125 x 65 x 6 x 8) kg 657.00 40,300.00 26,477,100.00

3 Intermediate Stiffener
Plat bawah
a Plat PL. 16 x 400 kg 1,397.00 15,814.80 22,093,275.60
b Plat PL. 25 x 400 kg 2,669.00 15,814.80 42,209,701.20
c Plat PL. 30 x 400 kg 3,846.00 15,814.80 60,823,720.80
Plat atas
a Plat PL. 16 x 300 kg 2,276.00 15,814.80 35,994,484.80
b Plat PL. 20 x 300 kg 1,954.00 15,814.80 30,902,119.20
c Plat PL. 10 x 1700 kg 13,659.00 15,814.80 216,014,353.20
RENCANA ANGGARAN BIAYA ( R A B )
KEGIATAN : PEMBANGUNAN BENDUNGAN LOGUNG KABUPATEN KUDUS
TAHUN ANGGARAN : 2014

HARGA BIAYA
NO URAIAN SATUAN VOLUME SATUAN PEKERJAAN
(Rp.) (Rp.)
Stiffener diafragma
a Plat PL. 140 x 8 x 1650 kg 4,003.00 15,814.80 63,306,644.40
b Plat PL. 120 x 8 x 1650 kg 3,611.00 15,814.80 57,107,242.80
4 Batang diagonal L. 70 X 70 X 7 kg 697.00 16,722.30 11,655,446.24
5 Batang horisontal L. 70 X 70 X 7 kg 573.00 16,722.30 9,581,880.48
6 Plat strip kg 20.00 15,814.80 316,296.00
1,618,420,036.72
VII Pembersihan Lapangan area genangan termasuk tebang pohon m2 160,840.00 27,600.00 4,439,184,000.00
4,439,184,000.00
VIII Penataan Greenbelt Ha 32.00 15,000,000.00 480,000,000.00

G PEKERJAAN ELEKTRIKAL & MEKANIKAL


I Saringan sampah pengambilan 2 @ 2.1 m x 28m unit 1.00 1,107,248,000.00 1,107,248,000.00
II Pintu pengambilan dan alat angkat
a Daun pintu 1.5 m x 2.5 m T unit 1.00 359,105,000.00 359,105,000.00
b Kerangka pengarah unit 1.00 302,308,000.00 302,308,000.00
c Alat angkat , kontrol dan sistem storage lifting equipment unit 1.00 1,047,851,000.00 1,047,851,000.00
1,709,264,000.00
III Pipa conduit keluaran dia 1.0 m - dia 0.4 m
a Pipa conduit pengambilan dia 1.0 m unit 1.00 890,954,000.00 890,954,000.00
b Conduit transsition of dia 1.0 m to 1.1 m 4 m L unit 1.00 608,538,000.00 608,538,000.00
c Pipa conduit pengeluaran dia 1.0 m unit 1.00 2,266,048,800.00 2,266,048,800.00
d Pipa conduit transisi dia 1.0 m - 1.0 m x 1.0 m square unit 1.00 127,759,400.00 127,759,400.00
e Gorong - gorong baja 1.0 m x 1.0 m 4 m L unit 1.00 295,863,900.00 295,863,900.00
f Pipa conduit irigasi dia 1.0 m unit 1.00 114,311,000.00 114,311,000.00
g Pipa conduit PDAM DIA 0.4 m unit 1.00 22,862,200.00 22,862,200.00
4,326,337,300.00
IV Pintu sorong bonet ( Bonette slide gate )
a Daun pintu , selinder dan batang torak . unit 1.00 43,707,100.00 43,707,100.00
b Bonnet 1.0 m x 1.0 m unit 1.00 66,681,400.00 66,681,400.00
c Alat angkat hidrolis & kontrol unit 1.00 268,967,200.00 268,967,200.00
d Katup pengaman dia 1000 mm unit 1.00 448,278,700.00 448,278,700.00
e Hollo Jet Valve dia 900 mm unit 1.00 1,064,661,900.00 1,064,661,900.00
f Alat angkat rantai jalan ( manually travelling chain hoist ) unit 1.00 123,276,600.00 123,276,600.00
g Katup Sluice dia 400 mm ( 2 sets ) unit 1.00 282,415,500.00 282,415,500.00
2,297,988,400.00
V Pintu Conduit pengelak
a Daun pintu 4 m x 4 m set 1.00 2,066,530,000.00 2,066,530,000.00
b Kerangka pengarah unit 1.00 225,820,400.00 225,820,400.00
c Spare parts and tools unit 1.00 210,130,600.00 210,130,600.00
2,502,481,000.00
H INSTRUMENTASI
a Hydraulic piezometer unit 12.00 35,097,500.00 421,170,000.00
b Stand pipe piezometer unit 18.00 89,950,000.00 1,619,100,000.00
c Seepage Water Measuring Device (V-notch weir) unit 2.00 51,894,200.00 103,788,400.00
d Inclinometer/Settlement Gauge (ISG) unit 2.00 342,442,000.00 684,884,000.00
e Crest Settlement Point unit 11.00 1,815,000.00 19,965,000.00
f Surface Settlement Point Down Stream unit 16.00 1,815,000.00 29,040,000.00
g Bench Mark ( BM ) bh 2.00 195,400.00 390,800.00
h Patok geser bh 5.00 710,200.00 3,551,000.00
i Alat ukur hujan otomatis (ARR), Alat ukur tinggi muka air unit 1.00 300,912,000.00 300,912,000.00
Otomatis (AWLR) dan Klimatologi
j Total Stress Cell unit 9.00 137,750,000.00 1,239,750,000.00
k Observation Whell unit 5.00 16,879,500.00 84,397,500.00
l Papan Duga Air bh 2.00 316,500.00 633,000.00
4,507,581,700.00
I PEMBANGKIT LISTRIK
Pekerjaan Sipil
a Galian tanah biasa, m3 1,539.00 29,500.00 45,400,500.00
b Penggalian Batu Lapuk (dengan alat berat) m3 660.00 63,900.00 42,174,000.00
c Beton K-125 m3 26.00 980,500.00 25,493,000.00
d Beton K-225 m3 559.00 1,090,900.00 609,813,100.00
e Besi Tulangan Ulir kg 25.00 15,378.00 384,450.00
f Bekisting expose type F2 m2 1,478.00 189,500.00 280,081,000.00
g Pintu Harmonika m2 21.00 24,750,000.00 519,750,000.00
h Pintu Aluminium set 2.00 4,950,000.00 9,900,000.00
RENCANA ANGGARAN BIAYA ( R A B )
KEGIATAN : PEMBANGUNAN BENDUNGAN LOGUNG KABUPATEN KUDUS
TAHUN ANGGARAN : 2014

HARGA BIAYA
NO URAIAN SATUAN VOLUME SATUAN PEKERJAAN
(Rp.) (Rp.)
i Jendela Aluminium set 12.00 825,000.00 9,900,000.00
1,542,896,050.00
RENCANA ANGGARAN BIAYA ( R A B )
KEGIATAN : PEMBANGUNAN BENDUNGAN LOGUNG KABUPATEN KUDUS
TAHUN ANGGARAN : 2014

HARGA BIAYA
NO URAIAN SATUAN VOLUME SATUAN PEKERJAAN
(Rp.) (Rp.)
J PEMBANGUNAN FASILITAS
a Gudang Lapangan ( 140 m2 ) unit 1.00 91,004,900.00 91,004,900.00
b Tandon Air unit 1.00 27,175,077.49 27,175,077.49
c Tangki Bahan Bakar unit 1.00 21,089,090.00 21,089,090.00
d Kantor Utama Bendungan (420 m2) unit 1.00 827,476,100.00 827,476,100.00
e Rumah Dinas Type 1 (60 m2) (1 Unit) unit 1.00 117,692,000.00 117,692,000.00
f Rumah Dinas Type 2 (45 m2) (1 Unit) unit 1.00 92,882,000.00 92,882,000.00
g Gardu Pandang (40 m2) unit 1.00 84,461,000.00 84,461,000.00
h Pos Jaga (9 m2) 2 unit unit 1.00 15,719,000.00 15,719,000.00
i Mushola (60 m3) unit 1.00 117,411,000.00 117,411,000.00
j Rumah Genset (16 m2) unit 1.00 31,169,000.00 31,169,000.00
k Bengkel Peralatan (120 m2) unit 1.00 220,919,000.00 220,919,000.00
l Rumah Instrumen (31.76 m2) unit 1.00 62,823,000.00 62,823,000.00
m Instalasi Jaringan Tegangan Menengah 20 KV/220 V Ls 1.00 246,477,700.00 246,477,700.00
n Instalasi Penerangan Jalan dan Puncak Bendung Titik 70.00 5,550,000.00 388,500,000.00
o Patok Batas aset Tanah Bendungan ( beton K 175 ) bh 30.00 959,000.00 28,770,000.00
p Landscape m2 50,000.00 12,500.00 625,000,000.00
2,998,568,867.49
K PEMBANGUNAN JALAN
a Lapis pondasi agregat klas C m3 1,458.00 301,900.00 440,170,200.00
b Lapis pondasi agregat klas A m3 3,280.00 274,800.00 901,344,000.00
c Lapis pondasi agregat klas B m3 6,560.00 272,800.00 1,789,568,000.00
d Lapis resap pengikat ltr 26,921.00 11,313.00 304,557,273.00
e Asphalt Treated ( ATB ) m3 1,094.00 2,955,600.00 3,233,426,400.00
6,669,065,873.00

Biaya konstruksi 552,872,292,274.61


Pajak (10%) 55,287,229,227
Total biaya 608,159,521,502.07
Dibulatkan 608,159,000,000.00
Perincian Harga Operasi per Jam
Model, Kapasitas, Flywheel Usia Nilai Sisa
Operasi Harga beli Nilai Susut Bunga, Biaya
Berat atau Power Guna (10%) Nilai Biaya Bahan Gaji Harga Total
Diameter Pajak & Penyu Spare Part Bahan Bakar
No. Jenis Alat Depre siasi Perbaikan Pelumas Pegawai
Asuransi sutan
(HP) (Tahun) (Jam) US$ (Rp.) (Rp.) (Rp.) (Rp.) (Rp.) (Rp.) (Rp.) (Rp.) (Rp.) (Rp.) (Rp.) (Rp.)
(1) (2) (3) (4) (5) (6) (7) (8) (9)=3%x(8) (10)=10%x(8)-(9)
(11)=((8)-(9)-(10))/((5)x(6))
(12) (13)=(9)/(6) (!4) (15) (16) (17) (18) (19 )

1. Agitator Truck, 3.2 m


3
3,2 m 3
110 5 2,000 38,329 571,725,000 17,151,750 55,457,325 49,912 20,582 8,576 16,637 11,091 157,740 11,220 14,688 290,500
2. Air compressor, 250 CFM 250 CFM 260 5 2,000 9,361 139,630,000 4,188,900 13,544,110 12,190 5,027 2,094 4,063 2,709 372,840 26,520 9,375 434,900
3. Air compressor, 365 CFM 365 CFM 365 5 2,000 18,282 272,706,000 8,181,180 26,452,482 23,807 9,817 4,091 7,936 5,290 523,410 37,230 9,375 621,000
4. Air compressor, 60 CFM 60 CFM 60 5 2,000 7,740 115,450,000 3,463,500 11,198,650 10,079 4,156 1,732 3,360 2,240 86,040 6,120 9,375 123,200
5. ARC Welder, 250 A 250 Ampere 0 5 2,000 4,941 73,702,860 2,211,086 7,149,177 6,434 2,653 1,106 2,145 1,430 - - 9,375 23,200
6. Asphalt Sprayer, 200 liter 200 liter 35 5 2,000 10,559 157,500,000 4,725,000 15,277,500 13,750 5,670 2,363 4,583 3,056 50,190 3,570 9,375 92,600
7. Asphalt Sprayer, 800 liter 800 liter 70 5 2,000 21,118 315,000,000 9,450,000 30,555,000 27,500 11,340 4,725 9,167 6,111 100,380 7,140 9,375 175,800
8. Batching Plant, 30 m3/jam 20 m3/jam 0 6 2,000 240,322 3,584,750,000 107,542,500 347,720,750 260,791 125,466 53,771 104,316 69,544 - - 20,000 633,900
9. Buldozer, 15 ton 15 ton 110 5 2,000 225,000 2,587,500,000 77,625,000 250,987,500 225,889 93,150 38,813 75,296 50,198 157,740 11,220 14,688 667,000
10. Buldozer, 21 ton 21 ton 220 5 2,000 235,000 2,702,500,000 81,075,000 262,142,500 235,928 97,290 40,538 78,643 52,429 315,480 22,440 14,688 857,500
11. Car Mix, 5 m3/jam 5 m3/jam 110 8 2,000 50,351 751,052,063 22,531,562 72,852,050 40,979 25,348 11,266 21,856 14,570 157,740 11,220 14,688 297,700
12. Concrete Mixer, 0,25 m3 0,25 m3 7 4 2,000 1,647 24,568,390 737,052 2,383,134 2,681 921 369 715 477 10,038 714 9,375 25,300
13. Concrete Mixer, 0,5 m3 0,5 m3 10 4 2,000 31,677 472,500,000 14,175,000 45,832,500 51,562 17,719 7,088 13,750 9,167 14,340 1,020 9,375 124,100
14. Concrete Pump Truck, 30 m3/jam 30 m3/jam 105 4 2,000 28,889 430,916,122 12,927,484 41,798,864 47,024 16,159 6,464 12,540 8,360 150,570 10,710 14,688 266,600
15. Concrete Vibrator, 45 mm 45 mm 5 1 2,000 890 13,272,000 398,160 1,287,384 5,793 796 199 386 257 7,170 510 9,375 24,500
16. Crane Truck Hydraulic, 20 ton 20 ton 230 5 2,000 105,512 1,573,854,600 47,215,638 152,663,896 137,398 56,659 23,608 45,799 30,533 329,820 23,460 14,688 662,000
17. Diesel Generator, 100 kVA 100 kVA 133 4 2,000 16,938 252,659,400 7,579,782 24,507,962 27,571 9,475 3,790 7,352 4,902 190,722 13,566 9,375 266,800
18. Diesel Generator, 45 kVA 45 kVA 60 5 2,000 12,713 189,630,000 5,688,900 18,394,110 16,555 6,827 2,844 5,518 3,679 85,825 6,105 9,375 136,800
19. Diesel generator, 60 kVA 60 kVA 80 5 2,000 13,560 202,272,000 6,068,160 19,620,384 17,658 7,282 3,034 5,886 3,924 114,433 8,140 14,688 175,100
20. Drill Pneumatic Crawler, 5 ton 353 CFM & 65 mm 0 5 2,000 31,129 464,340,660 13,930,220 45,041,044 40,537 16,716 6,965 13,512 9,008 - - 9,375 96,200
21. Drill Leg Air, 22 kg 88 CFM & 86 mm 0 3 2,000 1,779 26,530,140 795,904 2,573,424 3,860 1,061 398 772 515 - - 9,375 16,000
22. Dump Truck, 6 ton 6 ton 100 4 2,000 11,062 165,000,000 4,950,000 16,005,000 18,006 6,188 2,475 4,802 3,201 155,350 10,200 14,688 215,000
23. Dump Truck, 10 ton 10 ton 125 6 2,000 43,576 650,000,000 19,500,000 63,050,000 47,288 22,750 9,750 18,915 12,610 179,250 12,750 14,688 318,000
24. Giant breaker 0,7 m3 135 4 2,000 95,000 1,092,500,000 32,775,000 105,972,500 119,219 40,969 16,388 31,792 21,195 193,590 13,770 14,688 451,700
25. Excavator/Backhoe, 0.9 m3 0,7 m3 135 5 2,000 95,000 1,092,500,000 32,775,000 105,972,500 95,375 39,330 16,388 31,792 21,195 193,590 13,770 14,688 426,200
26. Excavator/Backhoe, 1.2 m3 1,2 m3 178 5 2,000 116,000 1,334,000,000 40,020,000 129,398,000 116,458 48,024 20,010 38,819 25,880 255,252 18,156 14,688 537,300
27. Excavator/Tracktor Shovel, 1.2 m3 1,2 m3 178 5 2,000 81,280 1,212,400,000 36,372,000 117,602,800 105,843 43,646 18,186 35,281 23,521 255,252 18,156 14,688 514,600
28. Hand Tamper 80 kg 6 4 1,000 1,140 17,010,000 510,300 1,649,970 3,712 1,276 510 990 660 8,604 612 9,375 25,800
29. Jack Hammer 25 kg 0 4 1,000 2,676 39,921,630 1,197,649 3,872,398 8,713 2,994.12 1,198 2,323 1,549 - - 14,688 31,500
30. Mesin pembengkok besi Maksimum 45 mm 0 5 2,000 5,796 86,449,222 2,593,477 8,385,575 7,547 3,112 1,297 2,516 1,677 - - 9,375 25,600
31. Mesin pemotong besi Maksimum 45 mm 0 5 2,000 5,029 75,011,325 2,250,340 7,276,099 6,548 2,700 1,125 2,183 1,455 - - 9,375 23,400
32. Motor Grader, 3.1 m 3,1 m 103 5 2,000 155,000 1,782,500,000 53,475,000 172,902,500 155,612 64,170 26,738 51,871 34,581 147,702 10,506 14,688 505,900
33. Tandem Roller 8 - 10 ton 80 7 2,000 85,677 1,278,000,000 38,340,000 123,966,000 79,692 43,817 19,170 37,190 24,793 114,720 8,160 14,688 342,300
34. Three Wheel Roller, 10 ton 10 - 12 ton 66 5 2,000 24,134 360,000,000 10,800,000 34,920,000 31,428 12,960 5,400 10,476 6,984 157,740 6,732 14,688 246,500
35. Truck Flat Bed, 4 ton 4 ton 180 5 2,000 16,471 245,688,240 7,370,647 23,831,759 21,449 8,845 3,685 7,150 4,766 258,120 18,360 14,688 337,100
36. Vibrator Roller, 10 ton 10 ton 109 4 2,000 72,000 828,000,000 24,840,000 80,316,000 90,356 31,050 12,420 24,095 16,063 195,383 25,942 14,688 410,000
37. Water tank truck & pump, 5000 liter 5000 liter 180 5 2,000 8,485 126,565,600 3,796,968 12,276,863 11,049 4,556 1,898 3,683 2,455 258,120 18,360 14,688 314,900
38. Wheel Loader, 1.5 m3 1,5 m3 108 5 2,000 77,637 1,158,060,000 34,741,800 112,331,820 101,099 41,690 17,371 33,700 22,466 154,872 11,016 14,688 397,000

Catatan:
1. Data of April 2012 8. Susut = Harga Susut / Usia Guna
2. Susut = 3% x Harga Beli 9. Harga BBM (Solar) = Rp 11,950 /liter
3. Spare Part = 6% x (Harga Beli - Nilai Susut) / Lama Operasi 10. Harga Pelumas = Rp 34,000 /liter
4. Biaya Perbaikan = 4% x (Harga Beli - Nilai Susut) / Lama Operasi 11. Operator = Rp 75,000 /org-hari 100,000
5. Suku Bunga Bank = 12% 12. Ass. Operator = Rp 42,500 /org-hari 66,667
6. Bahan bakar = 0.12 x HP x Harga bahan bakar (Solar)
7. Bahan bakar = 0.22 x HP x Harga bahan bakar (Premium)
8. Pelumas, dll = 0.003 x HP x Harga Pelumas
9. Kurs Dollar 1US$ = Rp. 11,500
STANDAR HARGA SATUAN DASAR (SHSD)
SEWA ALAT

Harga Sewa
No. Jenis Alat Satuan
(Rp)

1. Agitator Truck, 3.2 m3 Rp/jam 290,500.00


2. Air compressor, 250 CFM Rp/jam 434,900.00
3. Air compressor, 365 CFM Rp/jam 621,000.00
4. Air Compressor, 60 CFM Rp/jam 123,200.00
5. ARC Welder, 250 A Rp/jam 23,200.00
6. Asphalt Sprayer, 200 liter Rp/jam 92,600.00
7. Asphalt Sprayer, 800 liter Rp/jam 175,800.00
8. Concrete batching plant 30 m3 Rp/jam 633,900.00
9. Buldozer, 15 ton Rp/jam 667,000.00
10. Buldozer, 21 ton Rp/jam 857,500.00
11. Car Mix, 5 m3/jam Rp/jam 297,700.00
12. Concrete Mixer, 0,25 m3 Rp/jam 25,300.00
13. Concrete Mixer, 0,5 m3 Rp/jam 124,100.00
14. Concrete Pump Truck, 30 m3/jam Rp/jam 266,600.00
15. Concrete Vibrator, 45 mm Rp/jam 24,500.00
16. Crane Truck Hydroulik, 20 ton Rp/jam 662,000.00
17. Diesel Generator, 100 kVA Rp/jam 266,800.00
18. Diesel Generator, 45 kVA Rp/jam 136,800.00
19. Diesel generator, 60 kVA Rp/jam 175,100.00
20. Drill Pneumatic Crawler, 5 ton Rp/jam 96,200.00
21. Drill Leg Air, 22 kg Rp/jam 16,000.00
22. Dump Truck, 6 ton Rp/jam 215,000.00
23. Dump Truck, 10 ton Rp/jam 318,000.00
24. Excavator/Backhoe, 0.9 m3 Rp/jam 451,700.00
25. Excavator/Backhoe, 1,2 m3 Rp/jam 537,300.00
26. Excavator/Tracktor Shovel, 1.2 m3 Rp/jam 514,600.00
27. Giant breaker Rp/jam 451,700.00
28. Hand Tamper 80 kg Rp/jam 25,800.00
29. Jack Hammer 25Kg Rp/jam 31,500.00
30. Mesin pembengkok besi Rp/jam 25,600.00
31. Mesin pemotong besi Rp/jam 23,400.00
32. Motor Grader, 3,1 m Rp/jam 505,900.00
33. Tandem roller 10 ton Rp/jam 342,300.00
34. Three Wheel Roller, 10 ton Rp/jam 246,500.00
35. Truck Flat Bed, 4 ton Rp/jam 337,100.00
36. Vibrator Roller, 10 ton Rp/jam 410,000.00
37. Water Tank Truck, 5000 liter Rp/jam 314,900.00
38. Wheel Loader, 1.5 m3 Rp/jam 397,000.00
39. Pompa, 3" - H=5 m Rp/jam 12,500.00
40. Pompa, 4" - H=5 m Rp/jam 15,500.00
41. Aspalt Mixing Plant Rp/jam 3,471,705.00
42. Aspalt Finisher Rp/jam 490,200.00
43. Penomatic Tyre Roller Rp/jam 336,240.00
44. Chain saw Rp/jam 17,500.00
STANDAR HARGA SATUAN
UPAH KERJA, BAHAN DAN PERALATAN
BALAI BESAR WILAYAH SUNGAI PEMALI JUANA
TAHUN ANGGARAN 2014
DI KABUPATEN KUDUS

No Jenis Upah Kerja / Bahan / Peralatan Satuan Daftar Harga KETERANGAN


( Rp )
I UPAH KERJA
1 Mandor Oh 57,500
2 Pekerja Oh 42,500
3 Kepala tukang Oh 57,500 45,000
4 Tukang batu Oh 57,500 40,000
5 Tukang kayu Oh 57,500 42,500
6 Tukang besi Oh 57,500
7 Tukang cat Oh 57,500
8 Tukang listrik Oh 57,500
9 Tukang las Oh 57,500
10 Penganyam besi Oh
11 Tukang aspal Oh 42,500
12 Penjaga api Oh 42,500
13 Operator Oh 75,000
14 Asisten operator Oh 42,500
15 Mekanik terampil Oh 75,000
16 Driver Oh 75,000
17 Juru ukur Oh 75,000
18 Site Engineer Ob 4,500,000
19 Foreman Ob 3,500,000
20 Legdrill operator Ob 3,000,000
21 Mechanic Ob 3,000,000
22 Bore Master Ob 3,000,000
23 Asisten Bore Master Ob 2,500,000
24 Grouting Skill Ob 3,000,000
25 Nozzleman Ob 3,000,000
26 Shotmachine operator Ob 3,000,000
27 Air compresor operator Ob 3,000,000
28 Concrete technician Ob 2,500,000
29 Pekerja Khusus Ob 1,750,000

II BAHAN
1 Pasir urug m3 100,000
2 Pasir beton / cor ( hitam ) m3 300,000 190,000
3 Pasir pasang m3 147,500
4 Sirtu m3 115,000
5 Tanah urug m3
6 Batu belah ( kali / gunung ) m3 140,000
7 Batu bata merah bh 625
8 Batu pecah 5/7 m3 162,500
9 Batu pecah 3/5 m3 177,500
10 Batu pecah 2/3 m3 200,000
11 Semen portland 40 kg zak 53,000
12 Semen portland 50 kg zak 66,000 63,750
13 Semen warna kg 12,000
14 Keramik 30X30cm M2 50,000
15 Keramik 20X20cm M2 50,000
16 Besi tulangan beton ( polos ) kg 10,500
17 Besi tulangan beton ( ulir ) kg 12,500
18 Besi plat kg 13,000
19 Besi profil kg 13,750
20 Kawat ikat beton kg 16,750
20 Kayu jati balok m3 23,500,000
21 Kayu jati papan m3 28,000,000
22 Kayu kamper balok m3 6,800,000
23 Kayu kamper papan m3 7,450,000
24 Kayu kruing balok m3 6,400,000
25 Kayu kruing papan m3 6,900,000
No Jenis Upah Kerja / Bahan / Peralatan Satuan Daftar Harga KETERANGAN
( Rp )
26 Kayu tahun / balau balok m3 6,600,000
27 Kayu meranti balok m3 4,150,000
28 Kayu meranti papan m3 4,750,000
29 Kayu bekisting m3 2,200,000
No Jenis Upah Kerja / Bahan / Peralatan Satuan Daftar Harga KETERANGAN
( Rp )
30 Triplek 120 x 240 cm tebal 3mm lbr 55,000
31 Triplek 120 x 240 cm tebal 4 mm lbr 68,000
32 Kayu dolken/gelam Ø 10 cm panj. 4 m btg 31,000
33 Paku reng / usuk / triplek / seng kg 18,000
34 Paku asbes gelombang kg 21,000
35 Paku payung kg 21,000
36 Geotextile non Woven t=2mm m 17,500
37 Klosed Jongkok Keramik bh 140,000
38 Klosed Duduk Keramik bh 1,100,000
39 Teer / aspal kg 10,625
40 Buis Beton dia. 100, L=50 cm bh 150,000
41 Buis Beton dia. 50, L=50 cm bh 90,000
42 Pipa PVC Ø 1" m 8,000
43 Pipa PVC Ø 2" m 25,000
44 Pipa PVC Ø 4" m 75,833
45 Pipa PVC Ø 6" m 160,833
46 Cat kayu kg 56,500
47 Cat besi kg 45,000
49 Cat meni kg 16,500
50 Cat tembok kg 19,500
51 Cross bit, dia. 50 mm Pcs 278,300
52 Concrete Additive kg 17,500
53 Aspal Curah kg 10,469
54 Agregat Klas A m3 154,400
55 Agregat Klas B m3 137,900
56 Agregat Kasar m3 247,500
57 Agregat Halus m3 220,000
58 Filler kg 950
59 Dolken Jati lokal dia 15 - 20 cm L = 2 m btg 75,000
60 Rumput m2 5,000
61 Batu pecah mesin 1 - 2 cm ( beton ) m3 200,000
62 Multipleks 1,20x2,40m/12 mm lbr 160,000
63 Minyak Begisting Ltr 10,000
64 Mur baut Kuda -kuda Kg 15,000
65 Asbes gelombang 3,00 m x 1,05 m x 4 mm lbr 69,250
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : A.00
Jenis Pekerjaan : MOBILISASI DAN DEMOBILISASI
Harga Satuan : Rp. 383,700,000.0
Satuan : Ls

HARGA SATUAN JUMLAH


NO URAIAN SATUAN KUANTITAS
Rp. Rp.

A MOBILISASI ALAT & PERSONIL


1 Excavator bh 12 4,000,000.0 48,000,000.0
2 Wheel Loader bh 6 3,000,000.0 18,000,000.0
3 Dump truck bh 35 900,000.0 31,500,000.0
4 Buldozer bh 2 4,000,000.0 8,000,000.0
5 Motor Grader bh 2 3,000,000.0 6,000,000.0
6 Vibro roller bh 2 4,000,000.0 8,000,000.0
7 Water tanker bh 2 900,000.0 1,800,000.0
8 Concrete Mixer bh 4 1,000,000.0 4,000,000.0
9 Vibrator Roller bh 3 4,000,000.0 12,000,000.0
10 Concrete pump bh 6 1,000,000.0 6,000,000.0
11 Water Pump 70-100 Mm bh 2 1,500,000.0 3,000,000.0
12 Compressor 4000-6500 L\M bh 2 3,000,000.0 6,000,000.0
13 Boring Machine Unit 2 1,000,000.0 2,000,000.0
14 Grouting Machine Unit 4 1,000,000.0 4,000,000.0
15 Crawler Crane cap. 22 ton Unit 1 4,000,000.0 4,000,000.0
16 Batching Plant Unit 1 12,000,000.0 12,000,000.0
17 Stone Crusher Unit 1 12,000,000.0 12,000,000.0
18 Bar Bender Unit 2 300,000.0 600,000.0
19 Bar Bender Unit 2 300,000.0 600,000.0
20 Tamper bh 6 75,000.0 450,000.0
21 Emergency Genset 150 kVA bh 1 450,000.0 450,000.0
22 Engine Pump bh 6 75,000.0 450,000.0
23 Concrete Pump Truck bh 2 1,500,000.0 3,000,000.0

B DEMOBILISASI ALAT & PERSONIL


1 Excavator bh 12 4,000,000.0 48,000,000.0
2 Wheel Loader bh 6 3,000,000.0 18,000,000.0
3 Dump truck bh 35 900,000.0 31,500,000.0
4 Buldozer bh 2 4,000,000.0 8,000,000.0
5 Motor Grader bh 2 3,000,000.0 6,000,000.0
6 Vibro roller bh 2 4,000,000.0 8,000,000.0
7 Water tanker bh 2 900,000.0 1,800,000.0
8 Concrete Mixer bh 4 1,000,000.0 4,000,000.0
9 Vibrator Roller bh 3 4,000,000.0 12,000,000.0
10 Concrete pump bh 6 1,000,000.0 6,000,000.0
11 Water Pump 70-100 Mm bh 2 1,500,000.0 3,000,000.0
12 Compressor 4000-6500 L\M bh 2 3,000,000.0 6,000,000.0
13 Boring Machine Unit 2 1,000,000.0 2,000,000.0
14 Grouting Machine Unit 4 1,000,000.0 4,000,000.0
15 Crawler Crane cap. 22 ton Unit 1 4,000,000.0 4,000,000.0
16 Batching Plant Unit 1 12,000,000.0 12,000,000.0
17 Stone Crusher Unit 1 12,000,000.0 12,000,000.0
18 Bar Bender Unit 2 300,000.0 600,000.0
19 Bar Bender Unit 2 300,000.0 600,000.0
20 Tamper bh 6 75,000.0 450,000.0
21 Emergency Genset 150 kVA bh 1 450,000.0 450,000.0
22 Engine Pump bh 6 75,000.0 450,000.0
23 Concrete Pump Truck bh 2 1,500,000.0 3,000,000.0

Jumlah 383,700,000.0
Biaya umum dan keuntungan 10 %
Jumlah (termasuk biaya umum dan keuntungan) sebelum PPN 383,700,000.0
Jumlah dibulatkan 383,700,000.0

An. Har. Sat Pek. Persiapan A - 33/195


ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. :
Jenis Pekerjaan : Patok geser
Harga Satuan : Rp. 710,200
Satuan : bh

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA
1. Tukang Batu org/hr 0.09 57,500 5,031
2. Mandor org/hr 0.04 57,500 2,396
3. Pekerja org/hr 0.10 42,500 4,427

Sub Total I 11,854

II BAHAN
1 Beton K175 m3 0.375 1,033,000.00 387,375
2 Besi Tulangan Kg 9.900 15,378.00 152,242
3 Bekisting m2 0.480 192,600.00 92,448
4 Cat Kg 0.050 19,500.00 975
Sub Total II 632,065

III PERALATAN
1 Concrete mixer jam 0.020 25,300 506
2 Concrete Vibrator Jam 0.020 24,500 490
3 Alat bantu ls 1.000 750 750

Sub Total III 1,746

Biaya Langsung (Sub Total I s/d III) 645,665


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 64,567
V JUMLAH 710,232
VI HARGA SATUAN PEKERJAAN (Rp/bh) 710,200
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. :
Jenis Pekerjaan : Patok Batas aset Tanah Bendungan
Harga Satuan : Rp. 959,000
Satuan : bh

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA
1. Tukang Batu org/hr 0.09 10,500 919
2. Mandor org/hr 0.04 177,500 7,396
3. Pekerja org/hr 0.10 200,000 20,833

Sub Total I 29,148

II BAHAN
1 Beton K175 m3 0.500 1,033,000.00 516,500
2 Besi Tulangan Kg 13.200 15,378.00 202,990
3 Bekisting m2 0.640 192,600.00 123,264

Sub Total II 842,754

III PERALATAN
1 Concrete mixer jam 0.020 0 0
2 Concrete Vibrator Jam 0.020 0 0
3 Alat bantu ls 1.000 0 0

Sub Total III 0

Biaya Langsung (Sub Total I s/d III) 871,902


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 87,190
V JUMLAH 959,092
VI HARGA SATUAN PEKERJAAN (Rp/bh) 959,000
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. :
Jenis Pekerjaan : Bench Mark ( BM )
Harga Satuan : Rp. 195,499
Satuan : bh

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA
1. Tukang Batu org/hr 0.221 57,500 12,728
2. Mandor org/hr 0.055 57,500 3,182
3. Pekerja org/hr 0.63 42,500 26,563

Sub Total I 42,472

II BAHAN
1 Beton K175 m3 0.012 1,033,000.00 12,783
2 Besi Tulangan Kg 1.238 15,378.00 19,030
3 Bekisting m2 0.060 192,600.00 11,556
4 Mur Kuningan bh 1.00 25,000.00 25,000
Sub Total II 68,370

III PERALATAN
1 Concrete mixer jam 1.328 25,300 33,598
2 Concrete Vibrator Jam 1.328 24,500 32,536
3 Alat bantu ls 1.000 750 750

Sub Total III 66,884

Biaya Langsung (Sub Total I s/d III) 177,726


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 17,773
V JUMLAH 195,499
VI HARGA SATUAN PEKERJAAN (Rp/bh) 195,400
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : A.02
Jenis Pekerjaan : Kantor Lapangan (200 m²)
Harga Satuan : Rp. 443,450,100
Satuan : LS

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

1. Pembersihan Lahan (ref.C.01) m2 220.000 13,900 3,058,000


2. Pengupasan (ref.C.02) m2 220.000 21,200 4,664,000
3. Pekerjaan Pondasi :
- Pasangan Batu Kali (1PC : 3Ps) (ref. E01) m3 6.640 706,300 4,689,832
- Beton K-175 (ref.D.04) m3 2.760 1,033,000 2,851,080
- Bekisting (ref.D.07) m2 1.440 155,300 223,632
- Timbunan Tanah (ref.C.15) m3 149.870 20,200 3,027,374
4. Pekerjan Dinding :
- Pasangan Batu Bata (1PC : 4Ps) (ref. E03) m3 40.000 216,000 8,640,000
- Beton K-175 (ref.D.04) m3 2.100 1,033,000 2,169,300
- Bekisting (ref.D.07) m2 1.092 155,300 169,588
- Plesteran (1PC : 3 PS) (ref.E.04) m2 938.000 42,000 39,396,000
- Pengecatan Tembok (ref.J.12) m2 938.000 52,300 49,057,400
- Keramik 30 x 30 cm (ref.J.15) m2 200.000 159,000 31,800,000
5. Pekerjaan Atap :
- Kuda-kuda WF 150.150 (ref.J.19) kg 2,657.210 40,300 107,085,563
- Gording 8/12 (ref.J.10) m3 1.212 9,174,100 11,119,009
- Rangka Kuda-kuda L. 50.50.5 (ref.J.20) kg 76.885 46,800 3,598,218
- Nock 8/12 (ref.J.10) m3 0.211 9,174,100 1,935,735
- Atap Asbes Gelombang Kecil (ref.J.04) m2 122.470 41,200 5,045,764
5. Plafon Eternit (ref.J.21a) m2 264.000 242,000 63,888,000
6. Pekerjaan Pintu dan Jendela :
- Kusen Pintu 1 (ref.J.06) m3 0.555 10,035,500 5,569,703
- Kusen Pintu 2 (ref.J.06) m3 0.042 10,035,500 421,491
- Kusen Pintu 3 (ref.J.06) m3 0.116 10,035,500 1,164,118
- Kusen Jendela 1 (ref.J.06) m3 1.050 10,035,500 10,537,275
- Kusen Jendela 2 (ref.J.06) m3 0.022 10,035,500 220,781
- Daun Pintu Teakwood (Pintu 1) (ref. J.07) m2 18.900 615,200 11,627,280
- Kaca Rayban Polos Tebal 5 mm (ref. J.11) m2 2.520 120,000 302,400
- Daun Pintu Teakwood (Pintu 3) (ref .J.07) m2 4.320 615,200 2,657,664
- Kaca Rayban Polos Tebal 5 mm (ref .J.11) m2 23.520 120,000 2,822,400
- Kaca Rayban Polos Tebal 5 mm (ref .J.11) m2 0.360 120,000 43,200
7. Pekerjaan Lain-lain :
- Wastafel (ref.J.22) bh 2.000 522,000 1,044,000
- Kloset Jongkok (ref.J17) bh 2.000 412,600 825,200
- Kran Air (ref.J.16) bh 4.000 24,300 97,200
- Bak Mandi batu bata Vol. 0,30m3 (ref.J.23) bh 1.000 1,088,000 1,088,000
- Grendel (ref.J.24) bh 6.000 22,600 135,600
- Engsel (ref.J.25) stel 21.000 29,200 613,200
- Kunci Tanam Besar Kuda Terbang 2 (J.26) bh 14.000 198,000 2,772,000
-Pemasangan Air Conditioner 1 PK bh 5.000 3,755,300 18,776,500

I Biaya Langsung (Sub Total ) 403,136,506


II OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 40,313,651
III JUMLAH 443,450,157
IV HARGA SATUAN PEKERJAAN (Rp/m³) 443,450,100
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : A.01
Jenis Pekerjaan : Barak Kerja (70 m2)
Harga Satuan : Rp. 94,145,000
Satuan : LS
BBWS
Harga Satuan Jumlah Harga
No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

1. Pengupasan (ref.C.02) m2 77.000 21,200 1,632,400


2. Pekerjaan Pondasi :
- Galian Tanah (ref.C.03) m3 63.000 29,500 1,858,500
-Pasangan Batu Kosong (ref.E.05) m2 10.500 282,900 2,970,450
- Beton K-175 (ref.D.04) m3 0.950 1,033,000 981,350
- Bekisting (ref.D.07) m2 0.490 155,300 76,097
-Besi Beton Polos (ref.D.06) ton 0.200 15,378 3,076
3. Pekerjan Dinding :
- Pasangan Batu Bata (1PC : 4Ps) (re f. E.03) m3 13.620 216,000 2,941,920
- Beton K-175 (ref.D.04) m3 1.330 1,033,000 1,373,890
- Bekisting (ref.D.07) m2 0.690 155,300 107,157
-Besi Beton Polos (ref.D.06) ton 0.270 15,378 4,152
- Plesteran (1PC : 3 Ps) (ref.E.04) m2 2.710 42,000 113,820
- Pengecatan Tembok (ref.J.12) m2 2.710 52,300 141,733
4. Pekerjaan Atap :
- Kuda-kuda Kayu Meranti (ref.J01) m3 1.740 9,301,900 16,185,306
- Kayu Usuk Kamper/Reng Meranti (ref. J02) m3 1.400 104,800 146,720
- Listplank Kayu Kamper (ref.J.03) m3 0.340 110,000 37,400
- Wuwung Asbes Gelombang Kecil (ref. J05) m' 31.000 74,300 2,303,300
- Atap Asbes Gelombang Kecil (ref.J.04) m2 108.400 41,200 4,466,080
5. Pekerjaan Pintu dan Jendela
Pintu Tipe PJ. 1
- Pintu (ref.J.07) m2 2.120 615,200 1,304,224
- Jendela (ref.J.09) m2 3.980 107,900 429,442
Pintu Tipe PJ. 2
- Pintu (ref.J.07) m2 2.120 615,200 1,304,224
- Jendela (ref.J.09) m2 2.850 107,900 307,515
Pintu Tipe P. 1
- Pintu (ref.J.07) m2 1.650 615,200 1,015,080
Pintu Tipe P. 2
- Pintu (ref.J.07) m2 1.400 615,200 861,280
Jendela Tipe J. 2
- Jendela (ref.J.09) m2 4.280 107,900 461,812
Jendela Tipe J. 1
- Jendela (ref.J.09) m2 1.490 107,900 160,771
Jendela Tipe B. 1
- Jendela (ref.J.09) m2 0.660 107,900 71,214
6. Pekerjaan Lantai
- Timbunan Tanah (ref.C15) m3 10.700 48,600 520,020
- Tegel Plain Abu-abu (ref.J.13) m2 55.000 225,200 12,386,000
- Tegel Porselin (ref.J.15) m2 15.740 159,000 2,502,660
- Tegel Traso (ref.J14) m2 9.700 150,400 1,458,880
7. Pekerjaan Plafon (ref.J.21) m2 107.270 242,000 25,959,340
8. Pekerjaan Lain-lain
- Bak Mandi (1,00 x 0,60 x 0,80) (ref J.18) buah 1.000 1,088,000 1,088,000
- Kloset Jongkok (ref.J.17) buah 1.000 412,600 412,600

I Biaya Langsung (Sub Total ) 85,586,413


II OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 8,558,641
III JUMLAH 94,145,054
IV HARGA SATUAN PEKERJAAN (Rp/m³) 94,145,000
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : A.03
Jenis Pekerjaan : Penyedia Air Bersih dan Sanitasi
Harga Satuan : Rp. 106,205,000
Satuan : LS
IKA
Harga Satuan Jumlah Harga
No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I PERALATAN DAN PEMASANG

1. Pemboran dia 10" m 60.000 750,000 45,000,000


2. Pipa Galvanis dia. 4" + pemasangan m 60.000 162,500 9,750,000
3. Pipa Galvanis dia. 3" + pemasangan m 60.000 137,500 8,250,000
4. Pembuatan Saringan ls 1.000 300,000 300,000
5. Pompa Sentrifugal q = 50 liter/detik buah 2.000 6,000,000 12,000,000
6. Sistem penampungan/reservoir bawah 10 m3 ls 1.000 7,500,000 7,500,000
7. Sistem perpipaan dll ls 1.000 7,500,000 7,500,000
8. Sistem Sanitasi ls 1.000 6,250,000 6,250,000

II Biaya Langsung (Sub Total ) 96,550,000


III OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 9,655,000
IV JUMLAH 106,205,000
V HARGA SATUAN PEKERJAAN (Rp/m³) 106,205,000
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : A.05
Jenis Pekerjaan : Penyedia Sarana Telekomunikasi
Harga Satuan : Rp. 87,312,500
Satuan : LS

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I PERALATAN

1. Truseiver unit 20 675,000 13,500,000


2. Drycell bateray bh 50,000 1,000 50,000,000

Sub Total I 63,500,000

II PENYAMBUNGAN

1. Biaya Penyambungan % 25.000 63,500,000.00 15,875,000

Sub Total II 15,875,000

III LAIN-LAIN

Sub Total III 0

Biaya Langsung (Sub Total I s/d III) 79,375,000


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 7,937,500
V JUMLAH 87,312,500
VI HARGA SATUAN PEKERJAAN (Rp/Ls) 87,312,500
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : A.06
Jenis Pekerjaan : Penyedia Sarana & Prasarana Laboratorium ( Mektan & Concrete )
Harga Satuan : Rp. 408,479,500
Satuan : LS

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I KONSTRUKSI

1. Gedung m2 70.000 1,344,929 94,145,000.00

Sub Total I 94,145,000

II PERALATAN TEST

1. Embankment Test LS 1.000 0


2. Concreting Test LS 1.000 0

Sub Total II 0

III OPERASIONAL

1. Juru Laborat org/bln 36.000 3,500,000 126,000,000


2. Pembantu Juru Laborat org/bln 36.000 3,000,000 108,000,000
3. Pekerja khusus org/bln 36.000 1,200,000 43,200,000

Sub Total III 277,200,000

Biaya Langsung (Sub Total I s/d III) 371,345,000


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 37,134,500
V JUMLAH 408,479,500
VI HARGA SATUAN PEKERJAAN (Rp/m2) 408,479,500
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : A.04
Jenis Pekerjaan : Penyediaan Sarana Penerangan Kantor
Harga Satuan : Rp. 404,800,000
Satuan : LS

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I PERALATAN DAN PEMASANGAN

1. Pengadaan Generator, 15 kVA unit 1.000 300,000,000 300,000,000


2. Pengadaan Sistem Penerangan ls 1.000 3,000,000 3,000,000
3. Perlengkapan lainnya ls 1.000 60,000,000 60,000,000
4. Biaya penyambungan dan lain-lain ls 1.000 5,000,000 5,000,000

II Biaya Langsung (Sub Total ) 368,000,000


III OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 36,800,000
IV JUMLAH 404,800,000
V HARGA SATUAN PEKERJAAN (Rp/Ls) 404,800,000
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : A.07
Jenis Pekerjaan : Penyediaan Sarana Kesehatan
Harga Satuan : Rp. 227,700,000
Satuan : LS

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)
I TENAGA

1 Perawat org-bln 1.00 2,250,000.00 2,250,000.00


2 Dokter org-bln 0.05 5,000,000.00 250,000.00

Sub Total I 2,500,000.00

II BAHAN
1. Obat-obatan Ls 1.00 1,500,000.00 1,500,000.00

Sub Total II 1,500,000.00

III PERALATAN
Alat bantu medis ls 1.00 15,000,000.00 15,000,000.00

Sub Total III 15,000,000.00


Biaya Langsung (Sub Total I s/d III) 207,000,000.00
IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 20,700,000.00
V JUMLAH 227,700,000.00
VI HARGA SATUAN PEKERJAAN (Selama 4 Tahun) 227,700,000.00
ANALISA HARGA SATUAN POKOK KEGIATAN

(AHSPK)

No. : A.08
Jenis Pekerjaan : Jalan masuk ke lokasi ( Pemeliharaan,perbaikan , dll.)
Harga Satuan : Rp. 5,889,015,000
Satuan : LS

Harga Satuan Total Biaya


No. Jenis Pekerjaan Satuan Volume
(Rp) (Rp)

I Ruas Jalan menuju lokasi Bendungan ( 15 Km )


1 Pekerjaan Jalan
- Lapisan Penetrasi, t = 5 cm (ref. F.01) m3 1,125.00 1,382,800 1,555,650,000
- Lapis Pondasi Atas / Base Course, t = 20 cm (ref.F.02) m3 4,500.00 274,800 1,236,600,000
- Lapis Pondasi Bawah / Sub-Base Course, t = 30 (ref.F.03) m3 6,750.00 272,800 1,841,400,000

II Pemeliharaan Jalan Selama 4 Tahun Masa Pelaksanaan


1 - Pemeliharaan Tahunan Ls 1.00 720,000,000 720,000,000

III Biaya Langsung (Sub Total I s/d V) 5,353,650,000


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 535,365,000
V JUMLAH 5,889,015,000
VI HARGA SATUAN PEKERJAAN (Selama 4 Tahun) 5,889,015,000
VII HARGA SATUAN PEKERJAAN (Rp/LS) 5,889,015,000
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)
No. : A.09
Macam Pekerjaan : Dokumentasi Foto dan Film Kemajuan Pekerjaan
Harga Satuan : Rp. 308,343,200.00
Kuantitas Pekerjaan : LS

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA

1. Juru Foto/Editor org-bln 1.00 3,000,000.00 3,000,000.00

Sub Total I 3,000,000.00

II BAHAN
1. CD - RW Handy Cam buah 2.00 12,000.00 24,000.00
2. Kertas Foto lbr 20.00 6,000.00 120,000.00
3. Album bh 4.00 75,000.00 300,000.00

Sub Total II 444,000.00

III PERALATAN

1. Handy cam bh 1.00 5,000,000.00 5,000,000.00


2. Camera SLR bh 1.00 10,000,000.00 10,000,000.00
3 Foto udara kali 5.00 20,000,000.00 100,000,000.00

Sub Total III 115,000,000.00


Biaya Langsung (Sub Total I s/d III) 280,312,000.00
IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 28,031,200.00
V JUMLAH 308,343,200.00
VI HARGA SATUAN PEKERJAAN (Selama 4 Tahun) 308,343,200.00
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : A.10
Jenis Pekerjaan : Pencegahan HIV AID
Harga Satuan : Rp. 537,900,000
Satuan : LS
BBWS
Harga Satuan Jumlah Harga
No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA
1 Nara Sumber org-bln 12.000 2,000,000 24,000,000
2 Tenaga Penyuluh Medis org-bln 12.000 1,750,000 21,000,000
3 Operator Komputer org-bln 12.000 1,250,000 15,000,000
4 Evaluator dan Pembuatan Laporan org-bln 12.000 1,500,000 18,000,000

Sub Total I 78,000,000

II BAHAN
1 Leaflet Lbr 1,200.000 3,000 3,600,000
2 Sticker Lbr 200.000 2,000 400,000
3 Poster Lbr 75.000 10,000 750,000
4 Banner Spanduk Lbr 20.000 80,000 1,600,000
5 CD Keping 100.000 10,000 1,000,000
6 Snak 100 x 1 x 12bln Dus 1,200.000 10,000 12,000,000
7 Penggandaan Laporan Bulanan Set 180.000 75,000 13,500,000

Sub Total Ii 32,850,000

III PERALATAN
1 Sewa LCD/ End Focus Kali 12.000 200,000 2,400,000
2 Sewa Kendaraan Roda 4 Minibus Kali 12.000 750,000 9,000,000

Sub Total III 11,400,000

Biaya Langsung (Sub Total I s/d III) x 4 Tahun Anggaran 489,000,000


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 48,900,000
V JUMLAH 537,900,000
VI HARGA SATUAN PEKERJAAN (Selama 4 Tahun) 537,900,000
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : A.11
Jenis Pekerjaan : Pemantauan Lingkungan
Harga Satuan : Rp. 419,760,000
Satuan : LS
BBWS
Harga Satuan Jumlah Harga
No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA
1 Ahli Lingkungan org-bln 4.000 4,500,000 18,000,000
2 Tenaga Pemantau/Pengambilan Uji Sample :
- Kualitas Air org-bln 8.000 1,750,000 14,000,000
- Polusi Udara org-bln 8.000 1,750,000 14,000,000
- Kebisingan org-bln 8.000 1,750,000 14,000,000
- Pengujian Laboraturium sample 40.000 250,000 10,000,000
3 Evaluasi dan Pembuatan Laporan org-bln 4.000 1,500,000 6,000,000
3 Operator Komputer org-bln 4.000 1,250,000 5,000,000

Sub Total I 81,000,000

II BAHAN
1 Poster Lbr 40.000 10,000 400,000
2 Baner Lbr 40.000 80,000 3,200,000
3 CD Keping 20.000 10,000 200,000
4 Penggandaan Laporan Bulanan Set 40.000 75,000 3,000,000

Sub Total II 6,800,000

III PERALATAN
1 Sewa Peralatan Uji Kali 8.000 200,000 1,600,000
2 Sewa Kendaraan Kali 8.000 750,000 6,000,000

Sub Total III 7,600,000

Biaya Langsung (Sub Total I s/d III) X 4 Tahun Anggaran 95,400,000


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 9,540,000
V JUMLAH 104,940,000
VI HARGA SATUAN PEKERJAAN (Selama 4 Tahun) 419,760,000
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : B.01a
Jenis Pekerjaan : Dewatering
Harga Satuan : Rp. 310,961,750
Satuan : pertahun

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA
1. Mekanik Terampil org/hr 1.00 75,000 75,000
2. Tukang Listrik org/hr 1.00 57,500 57,500
3. Mandor org/hr 1.00 57,500 57,500
4. Pekerja org/hr 5.00 42,500 212,500

Sub Total I 402,500

II BAHAN

Sub Total II 0

III PERALATAN
1. Pompa, 4" - H=5 m jam 24.00 15,500 372,000

Sub Total III 372,000

Biaya Langsung (Sub Total I s/d III) x 365 hari 282,692,500


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 28,269,250
V JUMLAH 310,961,750
VI HARGA SATUAN PEKERJAAN (Rp/thn) 310,961,700
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : C.05
Jenis Pekerjaan : Galian Batu Keras ( dengan alat berat ) termasuk pembuangan jarak 0,00-3000m
Harga Satuan : Rp. 109,500
Satuan : m³
BBWS
Harga Satuan Jumlah Harga
No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA
1. Mandor org/hr 0.0834 57,500 4,796
2. Pekerja org/hr 0.1601 42,500 6,802

Sub Total I 11,598

II BAHAN

Sub Total II 0

III PERALATAN
1. Air Compressor, 250 CFM jam 0.0667 434,900 29,017
2 Jack Hammer 25Kg jam 0.0334 31,500 1,051
3 Giant breaker jam 0.0695 451,700 31,393
4 Excavator/Backhoe, 1,2 m3 jam 0.0259 537,300 13,934
5 Buldozer, 15 ton jam 0.0043 667,000 2,881
6 Dump Truck, 10 ton jam 0.0306 318,000 9,731

Sub Total III 88,007

Biaya Langsung (Sub Total I s/d III) 99,605


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 9,960
V JUMLAH 109,565
VI HARGA SATUAN PEKERJAAN (Rp/m³) 109,500
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : C.02
Jenis Pekerjaan : Pengupasan (minimum 0,15 m tebal top soil)
Harga Satuan : Rp. 21,200
Satuan : m²
BBWS
Harga Satuan Jumlah Harga
No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA
1. Mandor org/hr 0.0056 57,500 322
2. Pekerja org/hr 0.0133 42,500 565

Sub Total I 887

II BAHAN

Sub Total II 0

III PERALATAN
1. Buldozer, 15 ton jam 0.0083 667,000 5,558
2. Excavator/Backhoe, 1,2 m3 jam 0.0042 537,300 2,239
3. Dump Truck, 10 ton jam 0.0333 318,000 10,600

Sub Total III 18,397

Biaya Langsung (Sub Total I s/d III) 19,284


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 1,928
V JUMLAH 21,213
VI HARGA SATUAN PEKERJAAN (Rp/m²) 21,200
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : C.01
Jenis Pekerjaan : Pembersihan lapangan
Harga Satuan : Rp. 13,900
Satuan : m²
BBWS
Harga Satuan Jumlah Harga
No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA
1. Mandor org/hr 0.0500 57,500 2,875
2. Pekerja org/hr 0.1000 42,500 4,250

Sub Total I 7,125

II BAHAN

Sub Total II 0

III PERALATAN
1. Buldozer, 15 ton jam 0.0083 667,000 5,558

Sub Total III 5,558

Biaya Langsung (Sub Total I s/d III) 12,683


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 1,268
V JUMLAH 13,952
VI HARGA SATUAN PEKERJAAN (Rp/m²) 13,900

ANALISA HARGA SATUAN POKOK KEGIATAN


(AHSPK)

No. : C.01
Jenis Pekerjaan : Pembersihan Lapangan area genangan
( termasuk tebang pohon dan pembuangan )
Harga Satuan : Rp. 27,600
Satuan : m²
BBWS
Harga Satuan Jumlah Harga
No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA
1. Mandor org/hr 0.0500 57,500 2,875
2. Pekerja org/hr 0.1000 42,500 4,250

Sub Total I 7,125

II BAHAN

Sub Total II 0

III PERALATAN
1. Chain saw jam 0.1667 17,500 2,917
2. Excavator/Backhoe, 1,2 m3 jam 0.0083 537,300 4,478
3. Dump Truck, 10 ton jam 0.0333 318,000 10,600

Sub Total III 17,994

Biaya Langsung (Sub Total I s/d III) 25,119


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 2,512
V JUMLAH 27,631
VI HARGA SATUAN PEKERJAAN (Rp/m²) 27,600
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : C.03
Jenis Pekerjaan : Galian Tanah biasa termasuk pembuangan jarak 0,00-3,000m
Harga Satuan : Rp. 29,500
Satuan : m³
BBWS
Harga Satuan Jumlah Harga
No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA
1. Mandor org/hr 0.0213 57,500 1,225
2. Pekerja org/hr 0.0085 42,500 361

Sub Total I 1,586

II BAHAN

Sub Total II 0

III PERALATAN
1. Buldozer, 15 ton jam 0.0046 667,000 3,035
2. Excavator/Backhoe, 1,2 m3 jam 0.0216 537,300 11,612
3. Dump Truck, 10 ton jam 0.0333 318,000 10,589

Sub Total III 25,236

Biaya Langsung (Sub Total I s/d III) 26,822


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 2,682
V JUMLAH 29,504
VI HARGA SATUAN PEKERJAAN (Rp/m³) 29,500
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : C.04
Jenis Pekerjaan : Galian Batu Lapuk (dengan alat berat) termasuk pembuangan jarak 0,00-3,000m
Harga Satuan : Rp. 63,900
Satuan : m³
BBWS
Harga Satuan Jumlah Harga
No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA
1. Mandor org/hr 0.0298 57,500 1,711
2. Pekerja org/hr 0.0858 42,500 3,647

Sub Total I 5,357

II BAHAN

Sub Total II 0

III PERALATAN
1 Air Compressor, 250 CFM jam 0.0584 434,900 25,389
2 Jack Hammer 25Kg jam 0.0350 31,500 1,103
2 Buldozer, 15 ton jam 0.0022 667,000 1,441
3 Excavator/Backhoe, 1,2 m3 jam 0.0272 537,300 14,631
5 Dump Truck, 10 ton jam 0.0321 318,000 10,217

Sub Total III 52,782

Biaya Langsung (Sub Total I s/d III) 58,139


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 5,814
V JUMLAH 63,953
VI HARGA SATUAN PEKERJAAN (Rp/m³) 63,900
ANALISA HARGA SATUAN POKOK KEGIATAN ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK) (AHSPK)

No. : C.07
Jenis Pekerjaan : Timbunan Inti termasuk Slurr
Harga Satuan : Rp. 125,600
Satuan : m³

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA
1. Mandor org/hr 0.0600 57,500 3,450
2. Pekerja org/hr 0.6000 42,500 25,500

Sub Total I 28,950

II BAHAN

Sub Total II 0

III PERALATAN
a Borrow area :
1. Excavator/Backhoe, 1,2 m3 jam 0.0174 537,300 9,349
2. Dump Truck, 10 ton jam 0.0239 318,000 7,584
b Stock Pile :
1 Excavator/Backhoe, 1,2 m3 jam 0.0300 537,300 16,119
2 Dump Truck, 10 ton jam 0.0395 318,000 12,545
c Embankment area :
1 Buldozer, 15 ton jam 0.0113 667,000 7,504
2 Vibrator Roller, 10 ton jam 0.0400 410,000 16,400
3 Motor Grader, 3,1 m jam 0.0048 505,900 2,428
4 Water Tank Truck, 5000 liter jam 0.0375 314,900 11,809
5. Tamping rammer jam 0.0113 140,000 1,575

Sub Total III 85,313

Biaya Langsung (Sub Total I s/d III) 114,263


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsu 11,426
V JUMLAH 125,690
VI HARGA SATUAN PEKERJAAN (Rp/m³) 125,600
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : C.08
Jenis Pekerjaan : Timbunan Filter Halus ( material Pasir )
Harga Satuan : Rp. 296,800
Satuan : m³

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA
1. Mandor org/hr 0.0147 57,500 845
2. Pekerja org/hr 0.0353 42,500 1,500

Sub Total I 2,346

II BAHAN
1. Agregat halus m3 1.1000 220,000 242,000

Sub Total II 242,000

III PERALATAN
a. Stock Pile :
1. Excavator/Backhoe, 1,2 m3 jam 0.0139 537,300 7,468
2. Dump Truck, 10 ton jam 0.0263 318,000 8,363
b. Embankment area :
3. Buldozer, 15 ton jam 0.0043 667,000 2,868
4. Vibrator Roller, 10 ton jam 0.0152 410,000 6,232
5. Tamping rammer 80 kg jam 0.0238 25,800 614

Sub Total III 25,546

Biaya Langsung (Sub Total I s/d III) 269,892


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 26,989
V JUMLAH 296,881
VI HARGA SATUAN PEKERJAAN (Rp/m³) 296,800
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : C.09
Jenis Pekerjaan : Timbunan Filter Kasar ( material kerikil )
Harga Satuan : Rp. 330,100
Satuan : m³

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA
1. Mandor org/hr 0.0147 57,500 845
2. Pekerja org/hr 0.0353 42,500 1,500

Sub Total I 2,346

II BAHAN
1. Agregat Kasar m3 1.1000 247,500 272,250

Sub Total II 272,250

III PERALATAN
a Stock Pile :
1. Excavator/Backhoe, 1,2 m3 jam 0.0139 537,300 7,468
2. Dump Truck, 10 ton jam 0.0263 318,000 8,363
b Embankment area :
1 Buldozer, 15 ton jam 0.0043 667,000 2,868
2 Vibrator Roller, 10 ton jam 0.0152 410,000 6,232
3 Tamping rammer 80 kg jam 0.0238 25,800 614

Sub Total III 25,546

Biaya Langsung (Sub Total I s/d III) 300,142


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 30,014
V JUMLAH 330,156
VI HARGA SATUAN PEKERJAAN (Rp/m³) 330,100
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : C.12
Jenis Pekerjaan : Urugan Kembali (dipadatkan)
Harga Satuan : Rp. 20,200
Satuan : m³

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA
1. Mandor org/hr 0.0135 57,500 777
2 Pekerja org/hr 0.0270 42,500 1,149

Sub Total I 1,927

II BAHAN

Sub Total II 0

III PERALATAN
1. Excavator/Backhoe, 1,2 m3 jam 0.0104 537,300 5,588
2. Dump Truck, 10 ton jam 0.0071 318,000 2,258
3. Tamping rammer 80 kg jam 0.3333 25,800 8,600

Sub Total III 16,446

Biaya Langsung (Sub Total I s/d III) 18,372


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 1,837
V JUMLAH 20,210
VI HARGA SATUAN PEKERJAAN (Rp/m³) 20,200
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : C.10
Jenis Pekerjaan : Timbunan Batu (dari stock pile)
Harga Satuan : Rp. 293,800
Satuan : m³

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA
1. Mandor org/hr 0.0159 57,500 914
2. Pekerja org/hr 0.0381 42,500 1,619

Sub Total I 2,534

II BAHAN
1 Batu riprap m3 1.100 200,000 220,000

Sub Total II 220,000


III PERALATAN

a Stock Pile :
1 Excavator/Backhoe, 1,2 m3 jam 0.0159 537,300 8,543
2 Dump Truck, 10 ton jam 0.0213 318,000 6,773
b Embankment area :
1 Excavator/Backhoe, 1,2 m3 jam 0.0345 537,300 18,537
2 Buldozer, 15 ton jam 0.0056 667,000 3,735
3 Vibrator Roller, 10 ton jam 0.0172 410,000 7,052

Sub Total III 44,641

Biaya Langsung (Sub Total I s/d III) 267,174


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 26,717
V JUMLAH 293,891
VI HARGA SATUAN PEKERJAAN (Rp/m³) 293,800
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : C.11
Jenis Pekerjaan : Timbunan riprap ( material batu )
Harga Satuan : Rp. 295,500
Satuan : m³

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA
1. Mandor org/hr 0.0159 57,500 914
2. Pekerja org/hr 0.0381 42,500 1,619

Sub Total I 2,534

II BAHAN
1 Batu riprap m3 1.100 200,000 220,000

Sub Total II 220,000


III PERALATAN

a Stock Pile :
1 Excavator/Backhoe, 1,2 m3 jam 0.0222 537,300 11,928
2 Dump Truck, 10 ton jam 0.0400 318,000 12,720
b Embankment area :
1 Excavator/Backhoe, 1,2 m3 jam 0.0400 537,300 21,492

Sub Total III 46,140

Biaya Langsung (Sub Total I s/d III) 268,674


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 26,867
V JUMLAH 295,541
VI HARGA SATUAN PEKERJAAN (Rp/m³) 295,500
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : C.13
Jenis Pekerjaan : Lapisan Kerikil / Sirtu
Harga Satuan : Rp. 164,800
Satuan : m³

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA
1. Mandor org/hr 0.0139 57,500 799
2 Pekerja org/hr 0.0278 42,500 1,182

Sub Total I 1,981

II BAHAN
1. Sirtu m3 1.1000 115,000 126,500

Sub Total II 126,500

III PERALATAN
a Stock Pile :
1. Excavator/Backhoe, 1,2 m3 jam 0.0139 537,300 7,468
2. Dump Truck, 10 ton jam 0.0222 318,000 7,060
b Embankment area :
1 Vibrator Roller, 10 ton jam 0.0152 410,000 6,232
2 Tamping rammer 80 kg jam 0.0238 25,800 614

Sub Total III 21,374

Biaya Langsung (Sub Total I s/d III) 149,855


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 14,985
V JUMLAH 164,840
VI HARGA SATUAN PEKERJAAN (Rp/m³) 164,800
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : C.14
Jenis Pekerjaan : Urugan Pasir
Harga Satuan : Rp. 152,900
Satuan : m²

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA
1. Mandor org/hr 0.0147 57,500 845
2. Pekerja org/hr 0.0294 42,500 1,250

Sub Total I 2,095

II BAHAN
1. Pasir Urug m3 1.1000 100,000 110,000

Sub Total II 110,000

III PERALATAN
a Stock Pile :
1. Excavator/Backhoe, 1,2 m3 jam 0.0147 537,300 7,898
2. Dump Truck, 10 ton jam 0.0250 318,000 7,950
b Embankment area :
1 Buldozer, 15 ton jam 0.0078 667,000 5,203
2 Vibrator Roller, 10 ton jam 0.0144 410,000 5,904

Sub Total III 26,955

Biaya Langsung (Sub Total I s/d III) 139,050


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 13,905
V JUMLAH 152,955
VI HARGA SATUAN PEKERJAAN (Rp/m³) 152,900
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : C.15
Jenis Pekerjaan : Timbunan Random dari Stock Pile
Harga Satuan : Rp. 48,600
Satuan : m³

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA
1. Mandor org/hr 0.0048 57,500 276
2 Pekerja org/hr 0.0600 42,500 2,550

Sub Total I 2,826

II BAHAN

Sub Total II 0

III PERALATAN

1. Excavator/Backhoe, 1,2 m3 jam 0.0127 537,300 6,824


2. Dump Truck, 10 ton jam 0.0303 318,000 9,635
3 Buldozer, 15 ton jam 0.0090 667,000 6,003
4 Vibrator Roller, 10 ton jam 0.0270 410,000 11,070
5 Water Tank Truck, 5000 liter jam 0.0250 314,900 7,873

Sub Total III 41,405

Biaya Langsung (Sub Total I s/d III) 44,231


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 4,423
V JUMLAH 48,654
VI HARGA SATUAN PEKERJAAN (Rp/m³) 48,600
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : C.16
Jenis Pekerjaan : Gebalan Rumput
Harga Satuan : Rp. 14,000
Satuan : m²

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA
1. Mandor org/hr 0.0038 57,500 216
2 Pekerja org/hr 0.0375 42,500 1,594

Sub Total I 1,809

II BAHAN
1. Gebalan Rumput m2 1.1000 10,000 11,000

Sub Total II 11,000

III PERALATAN

Sub Total III 0

Biaya Langsung (Sub Total I s/d III) 12,809


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 1,281
V JUMLAH 14,090
VI HARGA SATUAN PEKERJAAN (Rp/m²) 14,000
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : C.18
Jenis Pekerjaan : Timbunan Random (pengangkutan dari borrow area ke stock pile, stock pile ke lokasi
timbunan)
Harga Satuan : Rp. 79,100
Satuan : m³

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA

1. Mandor org/hr 0.0048 57,500 276


2. Pekerja org/hr 0.0600 42,500 2,550

Sub Total I 2,826

II BAHAN

Sub Total II 0

III PERALATAN
a Borrow area
1. Excavator/Backhoe, 1,2 m3 jam 0.0216 537,300 11,612
2. Dump Truck, 10 ton jam 0.0455 318,000 14,469
b Stock Pile :
1 Excavator/Backhoe, 1,2 m3 jam 0.0127 537,300 6,824
2 Dump Truck, 10 ton jam 0.0303 318,000 9,635
c Embankment area :
1 Buldozer, 15 ton jam 0.0090 667,000 6,003
2 Vibrator Roller, 10 ton jam 0.0270 410,000 11,070
3 Motor Grader, 3,1 m jam 0.0032 505,900 1,619
4 Water Tank Truck, 5000 liter jam 0.0250 314,900 7,873

Sub Total III 69,104

Biaya Langsung (Sub Total I s/d III) 71,930


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 7,193
V JUMLAH 79,123
V HARGA SATUAN PEKERJAAN (Rp/m³) 79,100
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : C.17
Jenis Pekerjaan : Timbunan Sirtu
Harga Satuan : Rp. 182,500
Satuan : m³

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA

1. Mandor org/hr 0.0139 57,500 799


2. Pekerja org/hr 0.0278 42,500 1,182

Sub Total I 1,981

II BAHAN
1 Sirtu m3 1.100 115,000 126,500

Sub Total II 126,500

III PERALATAN
a River Deposit :
1. Excavator/Backhoe, 1,2 m3 jam 0.0132 537,300 7,092
2. Dump Truck, 10 ton jam 0.0213 318,000 6,773
b Stock Pile :
1 Excavator/Backhoe, 1,2 m3 jam 0.0139 537,300 7,468
2 Dump Truck, 10 ton jam 0.0222 318,000 7,060
c Embankment area :
1 Buldozer, 15 ton jam 0.0043 667,000 2,868
2 Vibrator Roller, 10 ton jam 0.0152 410,000 6,232

Sub Total III 37,494

Biaya Langsung (Sub Total I s/d III) 165,975


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 16,597
V JUMLAH 182,572
VI HARGA SATUAN PEKERJAAN (Rp/m³) 182,500
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : D.01
Jenis Pekerjaan : Beton K-300
Harga Satuan : Rp. 1,162,100
Satuan : m³

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA
1. Mandor org/hr 0.0830 57,500 4,773
2. Kepala Tukang org/hr 0.0280 57,500 1,610
3. Tukang Batu org/hr 0.2750 57,500 15,813
4. Pekerja org/hr 1.6500 42,500 70,125

Sub Total I 92,320

II BAHAN
1. Batu Pecah 1-2 cm m³ 0.8000 200,000 160,000
2. Pasir Beton / Cor m³ 0.4813 300,000 144,390
3. Semen portland 50 kg zak 8.2600 69,300 572,418
4. Concrete Additive kg 0.8000 17,500 14,000

Sub Total II 890,808

III PERALATAN

1. Car Mix, 5 m3/jam jam 0.0625 297,700 18,606


2. Diesel Generator, 100 kVA jam 0.0625 266,800 16,675
3 Concrete Pump Truck, 30 m3/jam jam 0.0521 266,600 13,897
4 Concrete Vibrator, 45 mm jam 0.1779 24,500 4,358
5 Concrete batching plant 40 m3 jam 0.0313 633,900 19,809

Sub Total III 73,345

Biaya Langsung (Sub Total I s/d III) 1,056,473


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 105,647
V JUMLAH 1,162,120
VI HARGA SATUAN PEKERJAAN (Rp/m³) 1,162,100
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : D.01a
Jenis Pekerjaan : Beton K-350
Harga Satuan : Rp. 1,228,400
Satuan : m³

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA
1. Mandor org/hr 0.1050 57,500 6,038
2. Kepala Tukang org/hr 0.0350 57,500 2,013
3. Tukang Batu org/hr 0.3500 57,500 20,125
4. Pekerja org/hr 2.1000 42,500 89,250

Sub Total I 117,425

II BAHAN
1. Batu Pecah 1-2 cm m³ 0.7407 200,000 148,148
2. Pasir Beton / Cor m³ 0.4764 300,000 142,929
3. Semen portland 50 kg zak 8.9600 69,300 620,928
4. Concrete Additive kg 0.8000 17,500 14,000

Sub Total II 926,005

III PERALATAN

1. Car Mix, 5 m3/jam jam 0.0625 297,700 18,606


2. Diesel Generator, 100 kVA jam 0.0625 266,800 16,675
3 Concrete Pump Truck, 30 m3/jam jam 0.0521 266,600 13,897
4 Concrete Vibrator, 45 mm jam 0.1779 24,500 4,358
5 Concrete batching plant 40 m3 jam 0.0313 633,900 19,809

Sub Total III 73,345

Biaya Langsung (Sub Total I s/d III) 1,116,775


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 111,677
V JUMLAH 1,228,452
VI HARGA SATUAN PEKERJAAN (Rp/m³) 1,228,400
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : D.02
Jenis Pekerjaan : Beton K-250
Harga Satuan : Rp. 1,117,400
Satuan : m³

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA
1. Mandor org/hr 0.0830 57,500 4,773
2. Kepala Tukang org/hr 0.0280 57,500 1,610
3. Tukang Batu org/hr 0.2750 57,500 15,813
4. Pekerja org/hr 1.6500 42,500 70,125

Sub Total I 92,320

II BAHAN
1. Batu Pecah 1-2 cm m³ 0.8000 200,000 160,000
2. Pasir Beton / Cor m³ 0.4700 300,000 141,000
3. Semen portland 50 kg zak 7.6800 69,300 532,224
4. Concrete Additive kg 0.8000 17,500 14,000

Sub Total II 847,224

III PERALATAN

1 Car Mix, 5 m3/jam jam 0.0650 297,700 19,351


2 Diesel Generator, 100 kVA jam 0.0650 266,800 17,342
3 Concrete Pump Truck, 30 m3/jam jam 0.0542 266,600 14,452
4 Concrete Vibrator, 45 mm jam 0.1850 24,500 4,532
5 Concrete batching plant 40 m3 jam 0.0325 633,900 20,602

Sub Total III 76,279

Biaya Langsung (Sub Total I s/d III) 1,015,823


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 101,582
V JUMLAH 1,117,405
VI HARGA SATUAN PEKERJAAN (Rp/m³) 1,117,400
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : D.03
Jenis Pekerjaan : Beton K-225
Harga Satuan : Rp. 1,090,900
Satuan : m³

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA

1. Mandor org/hr 0.0830 57,500 4,773


2. Kepala Tukang org/hr 0.0280 57,500 1,610
3. Tukang Batu org/hr 0.2750 57,500 15,813
4. Pekerja org/hr 1.6500 42,500 70,125

Sub Total I 92,320

II BAHAN

1. Batu Pecah 2 - 3 cm m3 0.7700 200,000 154,000


2. Pasir Beton / Cor m3 0.4700 300,000 141,000
3. Semen portland 50 kg zak 7.4200 69,300 514,206
4. Concrete Additive kg 0.8000 17,500 14,000

Sub Total II 823,206

III PERALATAN
1 Car Mix, 5 m3/jam jam 0.0650 297,700 19,351
2 Diesel Generator, 100 kVA jam 0.0650 266,800 17,342
3 Concrete Pump Truck, 30 m3/jam jam 0.0542 266,600 14,452
4 Concrete Vibrator, 45 mm jam 0.1850 24,500 4,532
5 Concrete batching plant 40 m3 jam 0.0325 633,900 20,602

Sub Total III 76,279

Biaya Langsung (Sub Total I s/d III) 991,805


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 99,180
V JUMLAH 1,090,985
VI HARGA SATUAN PEKERJAAN (Rp/m³) 1,090,900
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : D.04
Jenis Pekerjaan : Beton K-175
Harga Satuan : Rp. 1,033,000
Satuan : m³

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA

1. Mandor org/hr 0.0830 57,500 4,773


2. Kepala Tukang org/hr 0.0280 57,500 1,610
3. Tukang Batu org/hr 0.2750 57,500 15,813
4. Pekerja org/hr 1.6500 42,500 70,125

Sub Total I 92,320

II BAHAN

1. Batu Pecah Mesin 2 - 3 cm m3 0.7700 200,000 154,000


2. Pasir Beton / Cor m3 0.5053 300,000 151,590
3. Semen portland 50 kg zak 6.5200 69,300 451,836
4. Concrete Additive kg 0.7500 17,500 13,125

Sub Total II 770,551

III PERALATAN

1 Car Mix, 5 m3/jam jam 0.0650 297,700 19,351


2 Diesel Generator, 100 kVA jam 0.0650 266,800 17,342
3 Concrete Pump Truck, 30 m3/jam jam 0.0542 266,600 14,452
4 Concrete Vibrator, 45 mm jam 0.1850 24,500 4,532
5 Concrete batching plant 40 m3 jam 0.0325 633,900 20,602

Sub Total III 76,279

Biaya Langsung (Sub Total I s/d III) 939,150


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 93,915
V JUMLAH 1,033,065
VI HARGA SATUAN PEKERJAAN (Rp/m³) 1,033,000
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : D.05b
Jenis Pekerjaan : Beton K100 / Lantai Kerja
Harga Satuan : Rp. 893,100
Satuan : m³

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA

1. Mandor org/hr 0.0060 57,500 345


2. Kepala Tukang org/hr 0.0200 57,500 1,150
3. Tukang Batu org/hr 0.2000 57,500 11,500
4. Pekerja org/hr 1.2000 42,500 51,000

Sub Total I 63,995

II BAHAN

1. Batu Pecah Mesin 2 - 3 cm m3 0.7610 200,000 152,200


2. Pasir Beton / Cor m3 0.6380 300,000 191,400
3. Semen portland 50 kg zak 4.6000 69,300 318,780
4. Concrete Additive kg 0.7000 17,500 12,250

Sub Total II 674,630

III PERALATAN

1 Car Mix, 5 m3/jam jam 0.0625 297,700 18,606


2 Diesel Generator, 100 kVA jam 0.0625 266,800 16,675
3 Concrete Pump Truck, 30 m3/jam jam 0.0521 266,600 13,897
4 Concrete Vibrator, 45 mm jam 0.1779 24,500 4,358
5 Concrete batching plant 40 m3 jam 0.0313 633,900 19,809

Sub Total III 73,345

Biaya Langsung (Sub Total I s/d III) 811,970


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 81,197
V HARGA SATUAN PEKERJAAN (Rp/m³) 893,167
VI HARGA SATUAN PEKERJAAN (Rp/m³) 893,100
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : D.06
Jenis Pekerjaan : Tulangan Beton (pemotongan, pembengkokan dan pemasangan)
Harga Satuan : Rp. 15,378
Satuan : ton

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA

1. Kepala Tukang org/hr 0.0004 57,500 22


2. Tukang Besi org/hr 0.0009 57,500 50
3. Pekerja org/hr 0.0088 42,500 372

Sub Total I 444

II BAHAN

1. Besi Beton kg 1,100.0000 12,500 13,750,000


2. Kawat Beton (bendrat) kg 10.0000 16,750 167,500

Sub Total II 13,917,500

III PERALATAN

1. Mesin pembengkok besi jam 0.0200 25,600 512


2. Mesin pemotong besi jam 0.0100 23,400 234
3. Truck Flat Bed, 4 ton jam 0.1500 337,100 50,565
4. Crane Truck Hydroulik, 15 ton jam 0.0165 662,000 10,923

Sub Total III 62,234

Biaya Langsung (Sub Total I s/d III) 13,980,178


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 1,398,018
V JUMLAH 15,378,196
VI HARGA SATUAN PEKERJAAN (Rp/kg) 15,378.0
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : D.07
JENIS PEKERJAAN : Bekisting Tipe Non Expose F1 (termasuk perancah dan pembongkarannya)
HARGA SATUAN : Rp. 155,300
SATUAN PEKERJAAN : M2

Harga Satuan Jumlah Harga


No. Item Pekerjaan Uraian Volume
(Rp) (Rp)

I TENAGA
1 Mandor org/hr 0.0220 57,500.00 1,265.00
2 Tukang org/hr 0.5200 57,500.00 29,900.00
3 Pekerja org/hr 0.2000 42,500.00 8,500.00
Sub Total I 39,665.00

II BAHAN
1 Paku 2" dan 3" kg 0.4000 18,000.00 7,200.00
2 Papan Kayu Kls.4 m3 0.0300 2,200,000.00 33,000.00
3 Kayu kruing balok 5/7cm m3 0.0180 6,600,000.00 59,400.00
Sub Total II 99,600.00

III PERALATAN
1 Alat bantu ( 5% dari sub Total I ) % 5.0000 39,665.00 1,983.25
Sub Total III 1,983.25

Biaya Langsung (Sub Total I s/d III) 141,248.25


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 14,124.83
V JUMLAH 155,373.08
VI HARGA SATUAN PEKERJAAN (Rp/ton) 155,300.00
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. ;
JENIS PEKERJAAN ; Bekisting Tipe Expose F2 (termasuk perancah dan pembongkarannya)
HARGA SATUAN ; Rp. 186,400
SATUAN PEKERJAAN ; M2

Harga Satuan Jumlah Harga


No. Item Pekerjaan Uraian Volume
(Rp) (Rp)

I TENAGA
1 Mandor org/hr 0.0220 57,500.00 1,265.00
2 Tukang org/hr 0.5200 57,500.00 29,900.00
3 Pekerja org/hr 0.2000 42,500.00 8,500.00
Sub Total I 39,665.00

II BAHAN
1 Paku 2" dan 3" kg 0.4000 18,000.00 7,200.00
2 Papan Kayu Kls.4 lembar 0.3500 160,000.00 28,000.00
3 Kayu kruing balok 5/7cm m3 0.0280 6,600,000.00 92,400.00
set 0.0280 10,000.00 280.00
Sub Total II 127,880.00
III PERALATAN
1 Alat bantu ( 5% dari sub Total I )
% 5.0000 39,665.00 1,983.25
Sub Total III 1,983.25

Biaya Langsung (Sub Total I s/d III) 169,528.25


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 16,952.83
V JUMLAH 186,481.08
VI HARGA SATUAN PEKERJAAN (Rp/ton) 186,400.00
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : D.09
JENIS PEKERJAAN : Bekisting Tipe Expose F4 (termasuk perancah dan pembongkarannya)
HARGA SATUAN : Rp. 192,600
SATUAN PEKERJAAN : M2

Harga Satuan Jumlah Harga


No. Item Pekerjaan Uraian Volume
(Rp) (Rp)

I TENAGA
1 Mandor org/hr 0.0220 57,500.00 1,265.00
2 Tukang org/hr 0.5200 57,500.00 29,900.00
3 Pekerja org/hr 0.2000 42,500.00 8,500.00
Sub Total I 39,665.00

II BAHAN
1 Paku 2" dan 3" kg 0.4000 18,000.00 7,200.00
2 Multipleks 12 mm dengan lapisan Polyfilm lembar 0.4200 160,000.00 33,600.00
3 Kayu kruing balok 5/7cm m3 0.0280 6,600,000.00 92,400.00
4 Minyak bekisting set 0.0280 10,000.00 280.00
Sub Total II 133,480.00

III PERALATAN
1 Alat bantu ( 5% dari sub Total I ) 5.0000 39,665.00 1,983.25
Sub Total III 1,983.25

Biaya Langsung (Sub Total I s/d III) 175,128.25


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 17,512.83
V JUMLAH 192,641.08
VI HARGA SATUAN PEKERJAAN (Rp/ton) 192,600.00
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : F 04
Jenis Pekerjaan : Lapis Pondasi Atas / Base Course, Agregat Class C
Harga Satuan : Rp. 301,900
Satuan : m2

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA

1. Mandor org/hari 0.0338 57,500 1,941


2. Pekerja org/hari 0.1014 42,500 4,308

Sub Total I 6,249

II BAHAN

1. Agregat Base Kelas C m3 1.2000 160,000 192,000

Sub Total II 192,000

III PERALATAN

1. Wheel Loader, 1.5 m3 jam 0.0338 397,000 13,399


2. Dump Truck, 10 ton jam 0.0481 318,000 15,304
3. Motor Grader, 3,1 m jam 0.0063 505,900 3,162
4. Vibrator Roller, 10 ton jam 0.0284 410,000 11,634
5. Water Tank Truck, 5000 liter jam 0.1041 314,900 32,789

Sub Total III 76,287

Biaya Langsung (Sub Total I s/d III) 274,536


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 27,454
V JUMLAH 301,990
VI HARGA SATUAN PEKERJAAN (Rp/m³) 301,900
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : E.01
Jenis Pekerjaan : Pasangan Batu Kali (1Pc : 3Ps)
Harga Satuan : Rp. 706,300
Satuan : m³

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA

1. Mandor org/hari 0.0750 57,500 4,313


2. Kepala Tukang org/hari 0.0750 57,500 4,313
3. Tukang Batu org/hari 0.7500 57,500 43,125
4. Pekerja org/hari 1.5000 42,500 63,750

Sub Total I 115,500

II BAHAN

1. Semen portland 50 kg zak 4.0400 69,300 279,972


2 Batu belah (Kali/Gunung) m3 1.1000 140,000 154,000
3 Pasir Pasang m3 0.4850 147,500 71,538

Sub Total II 505,510

III PERALATAN

1 Concrete Mixer, 0,25 m3 jam 0.8333 25,300 21,082

Sub Total III 21,082

Biaya Langsung (Sub Total I s/d III) 642,092


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 64,209
V JUMLAH 706,301
VI HARGA SATUAN PEKERJAAN (Rp/m³) 706,300
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : E.03
Jenis Pekerjaan : Pasangan Batu Bata (1Pc : 4Ps)
Harga Satuan : Rp. 216,000
Satuan : m2
2
Harga Satuan Jumlah Harga
No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA

1. Mandor org/hari 0.0300 57,500 1,725


2. Kepala Tukang org/hari 0.0200 57,500 1,150
3. Tukang Batu org/hari 0.2000 57,500 11,500
4. Pekerja org/hari 0.6000 42,500 25,500

Sub Total I 39,875

II BAHAN

1. Semen portland 50 kg zak 0.5310 69,300 36,798


2. Batu Bata Merah bh 140.000 625 87,500
3. Pasir Pasang m3 0.0930 147,500 13,718

Sub Total II 138,016

III PERALATAN

1. Concrete Mixer, 0,25 m3 jam 0.7334 25,300 18,554

Sub Total III 18,554

Biaya Langsung (Sub Total I s/d III) 196,445


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 19,645
V JUMLAH 216,090
VI HARGA SATUAN PEKERJAAN (Rp/m2) 216,000
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : E.02
Jenis Pekerjaan : Pasangan Batu Kali (1Pc : 4Ps)
Harga Satuan : Rp. 670,200
Satuan : m³

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA

1. Mandor org/hari 0.0750 57,500 4,313


2. Kepala Tukang org/hari 0.0750 57,500 4,313
3. Tukang Batu org/hari 0.7500 57,500 43,125
4. Pekerja org/hari 1.5000 42,500 63,750

Sub Total I 115,500

II BAHAN

1. Semen portland 50 kg zak 3.2600 69,300 225,918


2 Batu belah (Kali/Gunung) m3 1.2000 140,000 168,000
3 Pasir Pasang m3 0.5200 147,500 76,700

Sub Total II 470,618

III PERALATAN

1 Concrete Mixer, 0,25 m3 jam 0.917 25,300 23,191

Sub Total III 23,191

Biaya Langsung (Sub Total I s/d III) 609,309


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 60,931
V JUMLAH 670,240
VI HARGA SATUAN PEKERJAAN (Rp/m³) 670,200
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : E.04
Jenis Pekerjaan : Plesteran t=15 mm (1Pc : 3Ps)
Harga Satuan : Rp. 42,000
Satuan : m²

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA

1. Mandor org/hari 0.0150 57,500 863


2 Tukang Batu org/hari 0.0150 57,500 863
3. Tukang Batu org/hari 0.1500 57,500 8,625
4. Pekerja org/hari 0.3000 42,500 12,750

Sub Total I 23,100

II BAHAN

1. Semen portland 50 kg zak 0.1630 69,300 11,296


2 Pasir Pasang m3 0.0230 147,500 3,393

Sub Total II 14,688

III PERALATAN

1. Concrete Mixer, 0,25 m3 jam 0.0165 25,300 417

Sub Total III 417


Biaya Langsung (Sub Total I s/d III) 38,206
IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 3,821
V JUMLAH 42,026
VI HARGA SATUAN PEKERJAAN (Rp/m²) 42,000
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : E.05
Jenis Pekerjaan : Pasangan Batu Kali Kosong
Harga Satuan : Rp. 282,900
Satuan : m³

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA

1. Mandor org/hari 0.0390 57,500 2,243


2. Kepala Tukang org/hari 0.0390 57,500 2,243
3. Tukang Batu org/hari 0.3900 57,500 22,425
4. Pekerja org/hari 0.7800 42,500 33,150

Sub Total I 60,060

II BAHAN
1 Pasir urug m3 0.4320 100,000 43,200
2 Batu belah ( kali / gunung ) m3 1.1000 140,000 154,000
Sub Total II 197,200

III PERALATAN

Sub Total III 0

Biaya Langsung (Sub Total I s/d III) 257,260


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 25,726
V JUMLAH 282,986
VI HARGA SATUAN PEKERJAAN (Rp/m³) 282,900
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : E.06
Jenis Pekerjaan : Bronjong
Harga Satuan : Rp. 588,431
Satuan : m³

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA:

1. Mandor org/hari 0.025 57,500 1,438


2 Pekerja org/hari 2.000 42,500 85,000

Sub Total I 86,438

II BAHAN
1. Batu Belah m3 1.100 135,000 148,500
2. Kawat Bronjong Galvanis Ø2,70 mm unit 1.000 300,000.0 300,000
( 2x1x0,50 ) m', Pabrikasi
Sub Total III 448,500

Biaya Langsung (Sub Total I s/d III) 534,938

IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 53,494

V HARGA SATUAN PEKERJAAN (Rp/m³) 588,431


ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : E.07
Jenis Pekerjaan : Siaran (1PC : 2 Ps)
Harga Satuan : Rp. 37,000
Satuan : m2

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA

1. Mandor org/hari 0.0150 57,500 863


2. Kepala Tukang org/hari 0.0150 57,500 863
3. Tukang Batu org/hari 0.1500 57,500 8,625
4. Pekerja org/hari 0.3000 42,500 12,750

Sub Total I 23,100

II BAHAN
1 Semen portland 50 kg zak 0.1268 69,300 8,787
2 Pasir Pasang m3 0.0120 147,500 1,770

Sub Total II 10,557


III PERALATAN

Sub Total III 0


Biaya Langsung (Sub Total I s/d III) 33,657
IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 3,366
V JUMLAH 37,023
VI HARGA SATUAN PEKERJAAN (Rp/m³) 37,000
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : F.01
Jenis Pekerjaan : Lapisan penetrasi batu belah 10/15
Harga Satuan : Rp. 1,455,400
Satuan : m³

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA

1. Mandor org/hari 0.0270 57,500 1,553


2. Pekerja org/hari 0.0811 42,500 3,447

Sub Total I 4,999

II BAHAN

1. Batu belah 10/15 m3 1.7273 160,000 276,368


2. Asphalt Curah kg 90.2479 10,469 944,783

Sub Total II 1,221,151

III PERALATAN

1. Wheel Loader, 1.5 m3 jam 0.0385 397,000 15,285


2. Dump Truck, 10 ton jam 0.0270 318,000 8,586
3. Three Wheel Roller, 10 ton jam 0.0588 246,500 14,494
4. Asphalt Sprayer, 800 liter jam 0.3333 175,800 58,594

Sub Total III 96,959

Biaya Langsung (Sub Total I s/d III) 1,323,109


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 132,311
V JUMLAH 1,455,420
VI HARGA SATUAN PEKERJAAN (Rp/m2) 1,455,400
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : F.02
Jenis Pekerjaan : Lapis Pondasi Atas / Base Course, Agregat Class A
Harga Satuan : Rp. 274,800
Satuan : m³

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA

1. Mandor org/hari 0.0338 57,500 1,941


2. Pekerja org/hari 0.1014 42,500 4,308

Sub Total I 6,249

II BAHAN

1. Agregat Base Kelas A m3 1.2000 154,400 185,280

Sub Total II 185,280

III PERALATAN

1. Wheel Loader, 1.5 m3 jam 0.0338 397,000 13,399


2. Dump Truck, 10 ton jam 0.0481 318,000 15,304
3. Motor Grader, 3,1 m jam 0.0084 505,900 4,237
4. Vibrator Roller, 10 ton jam 0.0379 410,000 15,529
5. Water Tank Truck, 5000 liter jam 0.0313 314,900 9,841

Sub Total III 58,309

Biaya Langsung (Sub Total I s/d III) 249,838


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 24,984
V JUMLAH 274,822
VI HARGA SATUAN PEKERJAAN (Rp/m³) 274,800
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : F.03
Jenis Pekerjaan : Lapis Pondasi Bawah/Sub-Base Course, Agregat Class B
Harga Satuan : Rp. 272,800
Satuan : m³

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA

1. Mandor org/hari 0.0338 57,500 1,941


2. Pekerja org/hari 0.1014 42,500 4,308

Sub Total I 6,249

II BAHAN

1. Agregat Base Klas B m3 1.2000 137,900 165,480

Sub Total II 165,480

III PERALATAN

1. Wheel Loader, 1.5 m3 jam 0.0338 397,000 13,399


2. Dump Truck, 10 ton jam 0.0481 318,000 15,304
3. Motor Grader, 3,1 m jam 0.0063 505,900 3,162
4. Vibrator Roller, 10 ton jam 0.0284 410,000 11,634
5. Water Tank Truck, 5000 liter jam 0.1041 314,900 32,789

Sub Total III 76,287

Biaya Langsung (Sub Total I s/d III) 248,016


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 24,802
V JUMLAH 272,818
VI HARGA SATUAN PEKERJAAN (Rp/m³) 272,800
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
No. : F 05
Macam Pekerjaan : HRS, Surface course-a (4cm)
Kuantitas Pekerjaan : 1 m2
Satuan Pengukuran : m2
Harga Satuan : Rp 101,000
Analisa :

HARGA
NO. MACAM PEKERJAAN SAT. KUANTITAS SATUAN JML.HARGA
(Rp) (Rp)

I TENAGA
1. Mandor jam 0.0021 57,500 122
2. Pekerja jam 0.0145 42,500 616
Sub Total I 738
II BAHAN
1. Agregat Kasar m3 0.0189 247,500.00 4,678
2. Agregat Halus m 3
0.0272 220,000.00 5,984
3. Aspal kg 5.4823 10,468.75 57,393
4. Filler kg 5.2899 950.00 5,025
Sub Total II 73,080
III PERALATAN
1. Wheel Loader, 1.5 m3 jam 0.0019 397,000 744
2. Asphalt Mixing Plant jam 0.0021 3,471,705 7,377
3. Dump Truck, 4 ton jam 0.0233 318,000 7,394
4. Asphalt Finisher jam 0.0026 490,200 1,287
5. Tandem Roller jam 0.0021 342,300 727
6. P. Tyre Roller jam 0.0016 336,240 546

Sub Total III 18,076

Biaya Langsung (Sub Total I s/d III) 91,894


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 9,189
V JUMLAH 101,084
VI HARGA SATUAN PEKERJAAN (Rp/m2) 101,000
ANALISA HARGA SATUAN PEKERJAAN
(AHSP)
No. : F 06
Macam Pekerjaan : ATB, Surface course-b (6cm)
Satuan Pengukuran : m2
Harga Satuan : Rp 177,336
Analisa :

HARGA
NO. MACAM PEKERJAAN SAT. KUANTITAS SATUAN JML.HARGA
(Rp) (Rp)

I TENAGA
1. Mandor jam 0.0686 57,500 3,946
2. Pekerja jam 0.6868 42,500 29,187
Sub Total I 29,187
II BAHAN
1. Agregat Kasar m3 0.8957 247,500.00 221,686
2. Agregat Halus m3 0.7022 220,000.00 154,484
3. Aspal kg 150.8600 10,468.75 1,579,316
4. Filler kg 112.8600 950.00 107,217
Sub Total II 2,062,702
III PERALATAN
1. Wheel Loader, 1.5 m3 jam 0.0605 397,000 24,019
2. Asphalt Mixing Plant jam 0.0686 3,471,705 238,246
3. Dump Truck, 4 ton jam 0.7726 318,000 245,695
4. Asphalt Finisher jam 0.0859 490,200 42,096
5. Tandem Roller jam 0.0753 342,300 25,758
6. P. Tyre Roller jam 0.0574 336,240 19,292

Sub Total III 595,105

Biaya Langsung (Sub Total I s/d III) 2,686,994


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 268,699
V JUMLAH 2,955,693
VI HARGA SATUAN PEKERJAAN (Rp/m3) 2,955,600
Vii HARGA SATUAN PEKERJAAN (Rp/m2) 177,336
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : G.01
Jenis Pekerjaan : Pemboran untuk injeksi semen ( Grouting ) Hole dia 56mm
Harga Satuan : Rp. 496,700
Satuan : m

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA

1. Site Engineer org/bulan 0.0021 4,500,000 9,375


2. Bore Master org/bulan 0.0083 3,500,000 29,167
3. Assistant Bore Master org/bulan 0.0083 2,500,000 20,833
4. Mechanic org/bulan 0.0042 3,000,000 12,500
5. Driver org/bulan 0.0042 1,750,000 7,292
6. Pekerja khusus org/bulan 0.0083 1,750,000 14,583

Sub Total I 93,750

II BAHAN

1. Drilling rod 40.50 mm x 3.00 m bh 0.0001 3,550,000 355


2. Core tube Single dia 56mmx1,50m bh 0.0001 12,500,000 1,250
3. Metal core bit dia 56mm bh 0.0143 1,500,000 21,429
4. Chuck piece & chuck bolt set 0.0002 750,000 150
5. Hydraulic piston set 0.0002 500,000 100
6. Water pipe diameter 1 1/4" x 6 m bh 0.0044 225,000 990
7. Water hose & accessories 1 1/4" m 0.0050 500,000 2,500
8. Pipe wrench bh 0.0001 750,000 75
9. Water swivel bh 0.0001 12,500,000 1,250
10. Rubber piston for pump bh 0.0036 150,000 540
11. Diesel spareparts set 0.0013 1,500,000 1,950
12. Bahan bakar kendaraan crew lt 1.2500 10,700 13,375
13. Bahan bakar peralatan lt 1.5000 11,950 17,925
14. Pelumas lt 0.0067 34,000 227
15. Kayu meranti balok m3 0.0410 4,150,000 170,150

Sub Total II 232,265

III PERALATAN

1. Drilling machine jam 0.3125 198,000 61,875


2. Drilling pump jam 0.3125 165,000 51,563
3. Kendaraan crew bulan 0.0027 4,500,000 12,150

Sub Total III 125,588

Biaya Langsung (Sub Total I s/d III) 451,603


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 45,160
V JUMLAH 496,763
VI HARGA SATUAN PEKERJAAN (Rp/m) 496,700
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : G.06
Jenis Pekerjaan : Pemboran inti untuk pilot & check hole dia 65 mm
Harga Satuan : Rp. 422,800
Satuan : m

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA

1. Site Engineer org/bulan 0.0042 4,500,000 18,750


2. Bore Master org/bulan 0.0083 3,500,000 29,167
3. Assistant Bore Master org/bulan 0.0083 2,500,000 20,833
4. Mechanic org/bulan 0.0042 3,000,000 12,500
5. Driver org/bulan 0.0042 1,750,000 7,292
6. Pekerja khusus org/bulan 0.0125 1,750,000 21,875

Sub Total I 110,417

II BAHAN

1. Drilling rod 40.50 mm x 3.00 m bh 0.0001 3,550,000 355


2. Core tube barrel ( double ) dia 65mmx1,50m bh 0.0001 17,500,000 1,750
3. Metal core bit dia 65mm bh 0.0238 1,750,000 41,667
4. Chuck piece & chuck bolt set 0.0002 750,000 150
5. Hydraulic piston set 0.0002 500,000 100
6. Water pipe diameter 1 1/4" x 6 m bh 0.0044 225,000 990
7. Water hose & accessories 1 1/4" m 0.0110 500,000 5,500
8. Pipe wrench bh 0.0001 750,000 75
9. Water swivel bh 0.0001 12,500,000 1,250
10. Rubber piston for pump bh 0.0036 150,000 540
11. Diesel spareparts set 0.0013 1,500,000 1,950
12. Bahan bakar kendaraan crew lt 1.2500 10,700 13,375
13. Bahan bakar peralatan lt 1.5000 11,950 17,925
14. Pelumas lt 0.0067 34,000 227
15 Core box nos 0.2000 250,000 50,000

Sub Total II 135,853

III PERALATAN

1. Drilling machine jam 0.3438 198,000 68,063


2. Drilling pump jam 0.3438 165,000 56,719
3. Kendaraan crew bulan 0.0030 4,500,000 13,365

Sub Total III 138,146

Biaya Langsung (Sub Total I s/d III) 384,416


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 38,442
V JUMLAH 422,858
VI HARGA SATUAN PEKERJAAN (Rp/m) 422,800
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : G.10
Jenis Pekerjaan : Ijeksi semen ( Grouting )
Harga Satuan : Rp. 1,763,600
Satuan : ton

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA
1. Site Engineer org/bulan 0.0057 4,500,000 25,714
2 Grouting skill org/bulan 0.0067 3,000,000 20,000
3 Pekerja khusus org/bulan 0.0067 1,750,000 11,667
4 Mechanic org/bulan 0.0057 3,000,000 17,143
5. Driver org/bulan 0.0067 1,750,000 11,667

Sub Total I 86,190

II BAHAN

1. Semen portland ton 1.1000 1,320,000 1,452,000

Sub Total II 1,452,000

III PERALATAN
1 Grouting Pump Jam 0.0036 99,000 354
2 Grouting Mixer Jam 0.0036 80,000 286
3 Double injection pipe dia. 33 mmx1,5m Jam 0.0014 1,000,000 1,389
4 Mechanical packer & accessories Jam 0.0014 3,500,000 4,861
5 Packer rubber bh 0.1000 200,000 20,000
6 Pipe wrench set 0.0001 750,000 75
7 Water pipe diameter 1 1/4" x 6 m bh 0.0014 225,000 313
8 Water hose & accessories 1 1/4" m 0.0028 500,000 1,389
9 Rubber piston bh 0.0111 150,000 1,667
10 Diesel spareparts set 0.0019 1,500,000 2,778
11 Bahan bakar peralatan lt 1.5000 11,950 17,925
12 Bahan bakar kendaraan crew lt 1.2500 10,700 13,375
13 Pelumas lt 0.0167 34,000 567
14 Flow meter Jam 0.0007 150,000 104
15 Pressure gauge Jam 0.0005 75,000 35

Sub Total III 65,116

Biaya Langsung (Sub Total I s/d III) 1,603,306


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 160,331
V JUMLAH 1,763,637
VI HARGA SATUAN PEKERJAAN (Rp/ton) 1,763,600
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : G.11
Jenis Pekerjaan : Water Pressure Test
Harga Satuan : Rp. 272,200
Satuan : tes

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA
1. Site Engineer org/bulan 0.0143 4,500,000 64,286
2 Grouting skill org/bulan 0.0133 3,000,000 40,000
3 Pekerja khusus org/bulan 0.0167 1,750,000 29,167
4 Mechanic org/bulan 0.0114 3,000,000 34,286
5 Driver org/bulan 0.0067 1,750,000 11,667

Sub Total I 179,405


II BAHAN

Sub Total II -

III PERALATAN
1 Grouting Pump Jam 0.0036 99,000 354
2 Water supply pump Jam 0.0036 66,000 236
3 Double injection pipe dia. 33 mmx1,5m Jam 0.0007 41,667 29
4 Mechanical packer & accessories Jam 0.0007 145,833 101
5 Packer rubber bh 0.0667 200,000 13,333
6 Pipe wrench set 0.0001 750,000 75
7 Water pipe diameter 1 1/4" x 6 m bh 0.0014 225,000 313
8 Water hose & accessories 1 1/4" m 0.0028 500,000 1,389
9 Rubber piston bh 0.0111 150,000 1,667
10 Diesel spareparts set 0.0014 1,500,000 2,083
11 Bahan bakar peralatan lt 4.0000 11,950 47,800
12 Pelumas lt 0.0167 34,000 567
13 Flow meter Jam 0.0005 150,000 69
14 Pressure gauge Jam 0.0005 75,000 35

Sub Total III 68,050

Biaya Langsung (Sub Total I s/d III) 247,455


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 24,745
V JUMLAH 272,200
VI HARGA SATUAN PEKERJAAN (Rp/m') 272,200
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : G.14
Jenis Pekerjaan : Backfill Grouting
Harga Satuan : Rp. 1,304,900
Satuan : m3

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA

1. Site Engineer org/bulan 4,500,000 0


2. Grouting skill org/bulan 0.0133 3,000,000 40,000
3. Pekerja khusus org/bulan 0.0167 1,750,000 29,167
4. Mechanic org/bulan 3,000,000 0
5. Driver org/bulan 1,750,000 0

Sub Total I 69,167

II BAHAN

1. Backfill grout assembly set 0.0044 5,000,000 22,000


2. Mechanical packer & accessories set 0.0022 3,500,000 7,700
3. Packer rubber nos 0.0500 200,000 10,000
4. Water hose & accessories 1 1/4" nos 0.1111 500,000 55,550
5. Pipe wrench m 0.0044 750,000 3,300
7. Rubber piston for pump nos 0.0356 150,000 5,340
8. Diesel spareparts set 0.0133 1,500,000 19,950
9. Portland cement ton 0.4345 1,320,000 573,540
10 Sieve sand m3 0.8690 300,000 260,700
12. Bahan bakar peralatan lt 0.6250 11,950 7,469
13. Pelumas lt 0.5333 34,000 18,132

Sub Total II 983,681

III PERALATAN

1. Grouting pump bulan 0.0267 2,500,000 66,750


2. Water supply pump bulan 0.0267 2,500,000 66,750
3. Kendaraan crew bulan 0.0000 4,500,000 0
4. Flow meter bulan 0.0000 150,000 0
5. Pressure gauge bulan 0.0000 75,000 0

Sub Total III 133,500

Biaya Langsung (Sub Total I s/d III) 1,186,348


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 118,635
V JUMLAH 1,304,982
VI HARGA SATUAN PEKERJAAN (Rp/m3) 1,304,900
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : G.15
Jenis Pekerjaan : Shotcrete with steel wire mesh 100 x 100 x 4mm ( tebal 6 cm )
Harga Satuan : Rp. 397,200
Satuan : m2

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA

1. Site Engineer org/bulan 0.0011 4,500,000 5,156


2. Foreman org/bulan 0.0046 3,500,000 16,042
3. Nozzleman org/bulan 0.0046 3,000,000 13,750
4. Shotmachine operator org/bulan 0.0055 3,000,000 16,500
5. Air compresor operator org/bulan 0.0073 3,000,000 22,000
6. Concrete technician org/bulan 0.0046 2,500,000 11,458
7. Mechanic org/bulan 0.0023 3,000,000 6,875
8. Driver org/bulan 0.0023 1,750,000 4,010
9. Pekerja khusus org/bulan 0.0092 1,750,000 16,042

Sub Total I 111,833

II BAHAN

1. Portland cement ton 0.0242 1,320,000 31,878


2. Fine aggregrat (sand) m3 0.0607 225,000 13,662
3. Coarse aggregrat (gravel) m3 0.0369 200,000 7,383
4. Accelaterator ton 0.0014 10,000,000 13,800
5. Safety measures set 0.0002 500,000 115
6. Pressure hose 1 1/4" diameter m 0.0009 250,000 230
7. Steel bar 13 mm diameter m 0.3835 3,000 1,151
8. Mesh clip bh 4.6000 1,000 4,600
9. Air water jet with nozzle set 0.0001 5,000,000 575
10. PVC pipe dia. 2" m 0.2000 13,667 2,733
11. Steel wire mesh 100 x 100 x 4 mm m2 1.0000 100,000 100,000
12. Bahan bakar peralatan lt 2.5000 11,950 29,875
13. Bahan bakar truck pengangkut lt 1.6667 11,950 19,917
14 Pelumas lt 0.0383 34,000 1,303

Sub Total II 227,222

III PERALATAN

1. Plant, warehouse etc Jam 0.0140 633,900 8,889


2. Air compressor 17m3/min Jam 0.0140 123,200 1,728
3. Shotcrete machine Jam 0.0100 198,000 1,983
4. Generator set 30 kVA Jam 0.0140 136,800 1,918
5 Concrete mixer 0,25m3 Jam 0.0120 25,300 304
6 Dump Truck 6 ton Jam 0.0130 202,800 2,641
7 Water tank truck 5,000ltr Jam 0.0120 314,900 3,785
8 Water supply pump ( Submersible 2") Jam 0.0120 66,000 793

Sub Total III 22,041

Biaya Langsung (Sub Total I s/d III) 361,096


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 36,110
V JUMLAH 397,205
VI HARGA SATUAN PEKERJAAN (Rp/m2) 397,200
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : G.16
Jenis Pekerjaan : Rock Bolt D = 22, L = 3 m
Harga Satuan : Rp. 189,800
Satuan : m

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA

1. Site Engineer org/bulan 0.0042 4,500,000 18,750


2. Foreman org/bulan 0.0000 3,500,000 0
3. Legdrill operator org/bulan 0.0083 3,000,000 25,000
4. Mechanic org/bulan 0.0042 3,000,000 12,500
5. Driver org/bulan 0.0000 1,750,000 0
6. Pekerja khusus org/bulan 0.0125 1,750,000 21,875

Sub Total I 78,125

II BAHAN

1. Hexagon rod 46 x 3000 nos 0.0006 4,500,000 2,700


2. Cross bit 46 nos 0.0033 1,500,000 4,950
3. Anchorage steel bar 25 m 3.0000 50,000 150,000
4. Face plate 150 x 150 x 10 nos 1.0000 20,000 20,000
5. Locked nut nos 1.0000 20,000 20,000
6. Resin capsule tube 1.0000 150,000 150,000
7. Drilling accesoris set 0.0003 2,500,000 750
8 Bahan bakar peralatan lt 0.5600 11,950 6,692
9 Pelumas lt 0.2000 34,000 6,800

Sub Total II 361,892

III PERALATAN

1. Legdrill bulan 0.0067 3,000,000 20,100


2. Air compressor bulan 0.0033 15,000,000 49,500
3 Water supply pump bulan 0.0033 2,500,000 8,250

Sub Total III 77,850

Biaya Langsung (Sub Total I s/d III) 517,867


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 51,787
V JUMLAH 189,885
VI HARGA SATUAN PEKERJAAN (Rp/m) 189,800
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : H.01
Jenis Pekerjaan : Hydraulic piezometer
Harga Satuan : Rp. 35,097,500
Satuan : set

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I BAHAN

1. Pneumatic Piezometer Set 1 29,006,250 29,006,250


mata piezometer/ceramic
twin tubing,
quick release coupling,
switch terminal
steel terminal cabinet with switched teminal panel futted inside,
alat baca piezometer,
gas presure regulator,
spare nut and olive set 1/8"
straight coupling,
colour adhesive tapes,
tube cutter,
bentonit powder
Sub Total I 29,006,250

II PEMASANGAN

(10% dari Sub Total I) % 10.0000 29,006,250.00 2,900,625

Sub Total III 2,900,625

III PERALATAN

Sub Total III 0

Biaya Langsung (Sub Total I s/d III) 31,906,875


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 3,190,688
V JUMLAH 35,097,563
VI HARGA SATUAN PEKERJAAN (Rp/set) 35,097,500
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : H.01a
Jenis Pekerjaan : Stand Pipe Piezometer
Harga Satuan : Rp. 89,950,000
Satuan : set

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I BAHAN

1. Stand Pipe Piezometer Set 1 74,338,876 74,338,876

Sub Total I 74,338,876

II PEMASANGAN

(10% dari Sub Total I) % 10.0000 74,338,875.60 7,433,888

Sub Total III 7,433,888

III PERALATAN

Sub Total III 0

Biaya Langsung (Sub Total I s/d III) 81,772,763


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 8,177,276
V JUMLAH 89,950,039
VI HARGA SATUAN PEKERJAAN (Rp/set) 89,950,000
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : H.02
Jenis Pekerjaan : Seepage Water Measuring Device (V-Notch Weir)
Harga Satuan : Rp. 51,894,200
Satuan : set

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I BAHAN
1. V-Notch Weir, semua konstruksi stainless bh 1.0000 42,887,813 42,887,813
steel, tebal 5 mm, dilengkapi dengan plat
baffle, pengatur dan skala pengukuran. Range
0-50 liter/detik

Sub Total I 42,887,813

II PEMASANGAN

(10% dari Sub Total I) % 10.0000 42,887,812.80 4,288,781

Sub Total II 4,288,781

III PERALATAN

Sub Total III 0

Biaya Langsung (Sub Total I s/d III) 47,176,594


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 4,717,659
V JUMLAH 51,894,253
VI HARGA SATUAN PEKERJAAN (Rp/set) 51,894,200
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : H.03
Jenis Pekerjaan : Multilayer Settlement Gauges
Harga Satuan : Rp. 80,978,000
Satuan : set

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I BAHAN

1. Datum Magnet bh 2.0000 600,000 1,200,000


2. Telescope Access Tube through the fill supplied in m 69.0000 300,000 20,700,000
2 metre lenghts

3. End Cap bh 4.0000 186,000 744,000


4. Circular Plate Mounted Magnet placed at 5 metre bh 14.0000 1,320,000 18,480,000
intervals through the fill materials

5. Magnet Settlement Probe, with 50 metre long pcs 1.0000 25,800,000 25,800,000
tape graduated in metres, milimetres

Sub Total I 66,924,000

II PEMASANGAN
(10% dari Sub Total I) % 10.0000 66,924,000.00 6,692,400

Sub Total II 6,692,400

III PERALATAN

Sub Total III 0

Biaya Langsung (Sub Total I s/d III) 73,616,400


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 7,361,640
V JUMLAH 80,978,040
VI HARGA SATUAN PEKERJAAN (Rp/set) 80,978,000
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : H.05
Jenis Pekerjaan : Crest Settlement Survey Point
Harga Satuan : Rp. 2,178,000
Satuan : set

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I BAHAN

1. Crest Settlement Survey Point bh 1.0000 1,800,000 1,800,000

Sub Total I 1,800,000

II PEMASANGAN

(10% dari Sub Total I) % 10.0000 1,800,000 180,000

Sub Total II 180,000

III PERALATAN

Sub Total III 0

Biaya Langsung (Sub Total I s/d III) 1,980,000


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 198,000
V JUMLAH 2,178,000
VI HARGA SATUAN PEKERJAAN (Rp/Set) 2,178,000
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : H.06
Jenis Pekerjaan : Observation Holes
Harga Satuan : Rp. 16,879,500
Satuan : set

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I BAHAN

1. Porous Siotted Tube, 38 mm l.d. 48 mm o.d. slot ukuran bh 2.0000 650,000 1,300,000
1.5 mm, flush jointed , 3 meter panjang

2. PVC Tube, 38 mm l.d., 48 mm o.d., flush jointed 3 meter bh 12.0000 275,000 3,300,000

3. Push-on End Cap bh 4.0000 150,000 600,000


4. Water Level Meter 30 m flat tape graduated every day bh 1.0000 8,750,000 8,750,000

Sub Total I 13,950,000

II PEMASANGAN

(10% dari Sub Total I) % 10.0000 13,950,000 1,395,000

Sub Total II 1,395,000

III PERALATAN

Sub Total III 0

Biaya Langsung (Sub Total I s/d III) 15,345,000


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 1,534,500
V JUMLAH 16,879,500
VI HARGA SATUAN PEKERJAAN (Rp/Set) 16,879,500
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : H.07
Jenis Pekerjaan : Autometic Water Level recorder (AWLR)
Harga Satuan : Rp. 58,080,000
Satuan : set

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I BAHAN

1. Automatic Water Level Recorder (AWLR) buah 1.0000 48,000,000 48,000,000

Sub Total I 48,000,000

II PEMASANGAN

(10% dari Sub Total I) % 10.0000 48,000,000.00 4,800,000

Sub Total II 4,800,000

III PERALATAN

Sub Total III 0

Biaya Langsung (Sub Total I s/d III) 52,800,000


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 5,280,000
V JUMLAH 58,080,000
VI HARGA SATUAN PEKERJAAN (Rp/set) 58,080,000
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : H.08
Jenis Pekerjaan : Papan Duga Air
Harga Satuan : Rp. 315,700
Satuan : set

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA

1. Mandor org/hr 0.0200 57,500 1,150


2. Pekerja org/hr 0.2500 42,500 10,625

Sub Total I 11,775

II BAHAN

1. Steel Enamated, Staff Gauge, W=0,50 m m' 1.0000 274,550 274,550

Sub Total II 274,550

III PERALATAN
1 Alat Bantu % 6.0000 11,775 707
Sub Total III 707

Biaya Langsung (Sub Total I s/d III) 287,032


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 28,703
V HARGA SATUAN PEKERJAAN (Rp/set) 315,735
VI HARGA SATUAN PEKERJAAN (Rp/set) 315,700
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : H.09
Jenis Pekerjaan : Inklinometer
Harga Satuan : Rp. 342,442,375 219472
Satuan : set

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

A INCLINOMETER & CASSING


1 INCLINOMETER Set 1.0000
- Inclinometer data logger set 1.0000 55,770,000.00 55,770,000.00
- Digital Inclinometer probe ( Biaxial,Digital sensor ) set 1.0000 64,350,000.00 64,350,000.00
- Inclinometer cable 50 m roll 1.0000 21,450,000.00 21,450,000.00
- Inclinometer calibration frame set 1.0000 19,305,000.00 19,305,000.00
- Pully and cable stop set 1.0000 4,719,000.00 4,719,000.00
- Inclinometer software set 1.0000 17,160,000.00 17,160,000.00
2 CASSING ( ABS )
- Inclinometer cassing @ 16m x 1ttk per batang 3m btg 6.0000 1,140,000.00 6,840,000.00
- End Cap ( Bottom cap, Top cap ) , dll ls 1.0000 7,055,000.00 7,055,000.00
Sub Total I 196,649,000.00

II PEMASANGAN & TRAINING Ls 1.0000 60,500,000.00 60,500,000.00

Sub Total II 60,500,000.00

III INTERNATIONAL AND LOCAL SHIPPING ls 1.0000 54,162,250.00 54,162,250.00

Sub Total III 54,162,250.00

Biaya Langsung (Sub Total I s/d III) 311,311,250.00


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 31,131,125.00
V JUMLAH 342,442,375
VI HARGA SATUAN PEKERJAAN (Rp/Set) 342,442,000
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : I.01
Jenis Pekerjaan : Intake Trashrack (1 x 1 )
Harga Satuan : Rp. 88,204,875
Satuan : set

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

1 Balok Penyangga kg 403.0000 50,000 20,150,000


2 Balok dasar kg 63.7500 50,000 3,187,500
3 Plat kisi kg 129.5000 50,000 6,475,000
4 Batang pengikat kg 21.0000 50,000 1,050,000
5 Baut pengikat anti karat buah 8.0000 50,000 400,000
6 Mur-Baut penahan anti karat buah 8.0000 125,000 1,000,000
7 Pipa penyekat buah 106.0000 25,000 2,650,000
8 Pengecatan anti karat m2 18.7500 2,250,000 42,187,500
9 Transportasi kg 617.2500 5,000 3,086,250

Sub Total I 80,186,250

Biaya Langsung (Sub Total I) 80,186,250


II OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 8,018,625
III JUMLAH 88,204,875
IV HARGA SATUAN PEKERJAAN (Rp/Set) 88,204,900
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : I.02
Jenis Pekerjaan : Fix Whell Gate (1 x 1 )
Harga Satuan : Rp. 786,555,000
Satuan : set

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

1. Balok utama Kg 443 50,000 22,150,000


2. Balok atas dan bawah Kg 304 50,000 15,200,000
3. Balok samping Kg 365 50,000 18,250,000
4. Balok penunjang tengah Kg 221 50,000 11,050,000
5. Balok penunjang tengah Kg 265 50,000 13,250,000
6. Plat d.pintu (dm) Kg 424 50,000 21,200,000
7. Sheave + dudukannya Kg 53 150,000 7,950,000
8. Karet perapat (m) m 5 250,000 1,250,000
9. Mur baut (anti karat) pcs 24 125,000 3,000,000
10. Roda utama Kg 148 150,000 22,200,000
11. Poros roda (d.50) Kg 15 250,000 3,750,000
12. Roda samping (d.80) Kg 4 150,000 600,000
13. Rumah roda samping Kg 10 85,000 850,000
14. Sill beam (I 400x300) Kg 205 50,000 10,250,000
15. Plat pelapis sill beam (stainless steal) Kg 10 150,000 1,500,000
16. Track frame Kg 408 50,000 20,400,000
17. Balok peluncur Kg 327 50,000 16,350,000
18. Lintle beam Kg 205 50,000 10,250,000
19. Plat stainless steal perapat (dm) pd lintle b Kg 10 150,000 1,500,000
20. Plat stainless steal perapat (dm) samping Buah 21 150,000 3,150,000
21. Embedded part (LS) ls 1 15,000,000 15,000,000
22. Hoist deck :
Balok Kg 635 50,000 31,750,000
Balok penunjang Kg 570 50,000 28,500,000
Checker plate (dm) Kg 393 50,000 19,650,000
23. Drump (d 0,5 m x 1 m) Kg 154 75,000 11,550,000
24. Motor listrik (5 kW) Buah 1 25,000,000 25,000,000
25. Wire rope (d. 25 galvanis) m m 25 250,000 6,250,000
26. Hooke Buah 1 12,500,000 12,500,000
27. Gear box Buah 2 17,500,000 35,000,000
28. Transportasi Kg 65,150 5,000 325,750,000

Sub Total I 715,050,000

Biaya Langsung (Sub Total I) 715,050,000


II OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 71,505,000
III JUMLAH 786,555,000
IV HARGA SATUAN PEKERJAAN (Rp/Set) 786,555,000
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : I.03
Jenis Pekerjaan : Katup Pintas (Sluice Valve) dia. 200 mm
Harga Satuan : Rp. 80,575,000
Satuan : set

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

1. Sluice valve d. 200 Buah 1.00 50,000,000 50,000,000


2. Piping (LS) ls 1.00 10,000,000 10,000,000
3. Alat pengoperasian (LS) manual ls 1.00 12,500,000 12,500,000
4. Transportasi Kg 150.00 5,000 750,000

Sub Total I 73,250,000

Biaya Langsung (Sub Total I) 73,250,000


II OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 7,325,000
III JUMLAH 80,575,000
IV HARGA SATUAN PEKERJAAN (Rp/Set) 80,575,000
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : I.04
Jenis Pekerjaan : Butterfly valve, dia. 0,10 m
Harga Satuan : Rp. 5,500,000
Satuan : set

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

1. Butterfly valve (d. 0,10 m) Buah 1.00 5,000,000 5,000,000

Sub Total I 5,000,000

Biaya Langsung (Sub Total I) 5,000,000


II OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 500,000
III JUMLAH 5,500,000
IV HARGA SATUAN PEKERJAAN (Rp/Set) 5,500,000
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : I.04
Jenis Pekerjaan : Butterfly Valve, dia 0,10 m
Harga Satuan : Rp. 25,589,666
Satuan : set

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

1. Butterfly valve (d. 0,10 m) Buah 1.00 15,000,000 15,000,000


2. Pipa GSP (d. 0,10 m) Buah 1.00 7,513,333 7,513,333
3. Bypass valve d. 100 mm (butt.fly d.100) Buah 1.00 750,000 750,000

Sub Total I 23,263,333

Biaya Langsung (Sub Total I) 23,263,333


II OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 2,326,333
III JUMLAH 25,589,666
IV HARGA SATUAN PEKERJAAN (Rp/Set) 25,589,700
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : I.05
Jenis Pekerjaan : Hollow Jet Valve, dia. 0.80 m
Harga Satuan : Rp. 113,025,000
Satuan : set

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

1. Hollow Jet valve (d. 0,80 m) Buah 1.00 102,000,000 102,000,000


2. Bypass valve d. 0,8 Buah 1.00 750,000 750,000

Sub Total I 102,750,000

Biaya Langsung (Sub Total I) 102,750,000


II OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 10,275,000
III JUMLAH 113,025,000
IV HARGA SATUAN PEKERJAAN (Rp/Set) 113,025,000
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : I.05
Jenis Pekerjaan : Butterfly Valve, dia 0,30 m
Harga Satuan : Rp. 50,325,000
Satuan : set

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

1. Butterfly valve (d. 0,30 m) Buah 1.00 45,000,000 45,000,000


2. Bypass valve d. 0,3 Buah 1.00 750,000 750,000

Sub Total I 45,750,000

Biaya Langsung (Sub Total I) 45,750,000


II OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 4,575,000
III JUMLAH 50,325,000
IV HARGA SATUAN PEKERJAAN (Rp/Set) 50,325,000
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : I.05
Jenis Pekerjaan : Butterfly Valve, dia 0,30 m
Harga Satuan : Rp. 50,325,000
Satuan : set

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

1. Butterfly valve (d. 0,30 m) Buah 1.00 45,000,000 45,000,000


2. Bypass valve d. 0,3 Buah 1.00 750,000 750,000

Sub Total I 45,750,000

Biaya Langsung (Sub Total I) 45,750,000


II OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 4,575,000
III JUMLAH 50,325,000
IV HARGA SATUAN PEKERJAAN (Rp/Set) 50,325,000
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : I.05b
Jenis Pekerjaan : Butterfly Valve, dia 0,15 m
Harga Satuan : Rp. 12,512,500
Satuan : set

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

1. Butterfly valve (d. 0,15 m) Buah 1.00 11,375,000 11,375,000

Sub Total I 11,375,000

Biaya Langsung (Sub Total I) 11,375,000


II OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 1,137,500
III JUMLAH 12,512,500
IV HARGA SATUAN PEKERJAAN (Rp/Set) 12,512,500
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : I.05
Jenis Pekerjaan : Butterfly Valve, dia 0,30 m
Harga Satuan : Rp. 50,325,000
Satuan : set

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

1. Butterfly valve (d. 0,30 m) Buah 1.00 45,000,000 45,000,000


2. Bypass valve d. 0,3 Buah 1.00 750,000 750,000

Sub Total I 45,750,000

Biaya Langsung (Sub Total I) 45,750,000


II OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 4,575,000
III JUMLAH 50,325,000
IV HARGA SATUAN PEKERJAAN (Rp/Set) 50,325,000
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : I.06
Jenis Pekerjaan : Butterfly Valve, dia. 0,70 m
Harga Satuan : Rp. 100,925,000
Satuan : set

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

1 Butterfly Valve (Ø 0,70 m) buah 1.0000 91,000,000 91,000,000


2 Bypass Valve Ø 100 mm buah 1.0000 750,000 750,000

Sub Total I 91,750,000

Biaya Langsung (Sub Total I) 91,750,000


II OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 9,175,000
III JUMLAH 100,925,000
IV HARGA SATUAN PEKERJAAN (Rp/Set) 100,925,000
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : I.06
Jenis Pekerjaan : Butterfly Valve, dia. 0,70 m
Harga Satuan : Rp. 100,925,000
Satuan : set

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

1 Butterfly Valve (Ø 0,70 m) buah 1.0000 91,000,000 91,000,000


2 Bypass Valve Ø 100 mm buah 1.0000 750,000 750,000

Sub Total I 91,750,000

Biaya Langsung (Sub Total I) 91,750,000


II OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 9,175,000
III JUMLAH 100,925,000
IV HARGA SATUAN PEKERJAAN (Rp/Set) 100,925,000
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : I.06
Jenis Pekerjaan : Butterfly Valve, dia. 0,70 m
Harga Satuan : Rp. 100,925,000
Satuan : set

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

1 Butterfly Valve (Ø 0,70 m) buah 1.0000 91,000,000 91,000,000


2 Bypass Valve Ø 100 mm buah 1.0000 750,000 750,000

Sub Total I 91,750,000

Biaya Langsung (Sub Total I) 91,750,000


II OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 9,175,000
III JUMLAH 100,925,000
IV HARGA SATUAN PEKERJAAN (Rp/Set) 100,925,000
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : I.07
Jenis Pekerjaan : Pipa Baja Saluran Utama, dia. 1,0 m tebal 10 mm
Harga Satuan : Rp. 23,302,700
Satuan : set

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I BAHAN :
1 Pipa baja (Ø 1,0 M) m 1.0000 10,500,000 10,500,000
2 Pekerjaan pengelasan m 0.6283 1,925,000 1,209,478
3 Ring penguat kg 4.9400 55,000 271,700
4 Bellmouth( Ø 1.0m) kg 5.3700 66,000 354,420
5 Sadel beton(1,5mx0,5mx0,5m) m3 0.0600 1,228,400 73,704
6 Expansion joint buah 1.0000 8,250,000 8,250,000
7 Biaya transportasi % 5.0000 10,500,000 525,000

Sub Total I 21,184,302

Biaya Langsung (Sub Total I) 21,184,302


II OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 2,118,430
III JUMLAH 23,302,732
IV HARGA SATUAN PEKERJAAN (Rp/Set) 23,302,700
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : I.08
Jenis Pekerjaan : Pipa Baja Saluran irigasi, dia. 0,8 m tebal 10 mm
Harga Satuan : Rp. 17,481,500
Satuan : set

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

1 Pipa baja (Ø 0,3 M) m 1.0000 5,572,000 5,572,000


2 Pekerjaan pengelasan m 1.0500 1,750,000 1,837,500
3 Ring penguat kg 4.9400 50,000 247,000
4 Bellmouth( Ø 1.0m) kg 5.3700 60,000 322,200
5 Sadel beton(1,5mx0,5mx0,5m) m3 0.0600 2,250,000 135,000
6 Expansion joint buah 1.0000 7,500,000 7,500,000
7 Biaya transportasi % 5.0000 5,572,000 278,600

Sub Total I 15,892,300

Biaya Langsung (Sub Total I) 15,892,300


II OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 1,589,230
III JUMLAH 17,481,530
IV HARGA SATUAN PEKERJAAN (Rp/Set) 17,481,500
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : I.09
Jenis Pekerjaan : Pipa Baja dia. 0,5 m tebal 10 mm
Harga Satuan : Rp. 18,941,100
Satuan : set

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I BAHAN :
1 Pipa baja (Ø 0,5 M) m 1.0000 5,950,560.00 5,950,560.00
2 Pekerjaan pengelasan m 1.0500 1,925,000.00 2,021,250.00
3 Ring penguat kg 4.9400 55,000.00 271,700.00
4 Bellmouth( Ø 0,50m) kg 5.3700 66,000.00 354,420.00
5 Sadel beton(1,5mx0,5mx0,5m) m3 0.0600 1,228,400.00 73,704.00
6 Expansion joint buah 1.0000 8,250,000.00 8,250,000.00
7 Biaya transportasi % 5.0000 5,950,560.00 297,528.00

Sub Total I 17,219,162

Biaya Langsung (Sub Total I) 17,219,162


II OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 1,721,916
III JUMLAH 18,941,078
IV HARGA SATUAN PEKERJAAN (Rp/Set) 18,941,100
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : I.11
Jenis Pekerjaan : Pintu (4,00 x 4,00) m
Harga Satuan : Rp. 220,243,000
Satuan : set

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

1 BAHAN

Besi siku kg 3,972.20 13,750 54,617,793


Besi plate kg 977.45 13,000 12,706,891
Besi plate strip kg 592.71 13,000 7,705,242
Besi beton kg 187.17 10,500 1,965,305
Pipa kg 10.40 9,900 102,945
Bahan bantu konstruksi % 18.91 4,372,000 826,581
Besi bulat st 60 kg 2,125.93 14,520 30,868,535
Bronze kg 239.16 50,820 12,154,318
Besi cor kg 374.34 14,960 5,600,183
Mur baut 1/2",5/8",7/8" kg 51.99 21,200 1,102,234
Paku keling 1/2",5/8",7/8" kg 155.98 16,000 2,495,625
Nipple buah 10.40 6,600 68,630
Split pen buah 20.80 68,860 1,432,073
Gembok buah 16.64 25,000 415,938
Druckager kecil/besar buah 10.40 931,700 9,688,224
Na f + ring buah 10.40 242,000 2,516,422

Sub Total I 144,266,937

2 ONGKOS KERJA

Kerja konstruksi kg 5,739.94 2,860 16,416,221


Kerja mesin kg 1,331.00 14,080 18,740,480
Sandblasting & cat m2 128.11 57,000 7,302,199

Sub Total II 42,458,900

3 PEMASANGAN kg 6,426.23 1,100 7,068,858

4 TRANSPORT kg 6,426.23 1,000 6,426,234

Sub Total III 13,495,092

Biaya Langsung (Sub Total I s/d III) 200,220,929


II OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 20,022,093
III JUMLAH 220,243,022
IV HARGA SATUAN PEKERJAAN (Rp/Set) 220,243,000
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : J.01
Jenis Pekerjaan : Pemasangan Kuda-kuda Kayu Kruing
Harga Satuan : Rp. 9,301,900
Satuan : m³

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA

1. Mandor org/hari 0.2000 57,500 11,500


2. Kepala Tukang org/hari 1.2000 57,500 69,000
3. Tukang Kayu org/hari 12.0000 57,500 690,000
4. Pekerja org/hari 4.0000 42,500 170,000

Sub Total I 940,500

II BAHAN

1. Kayu Kruing balok m³ 1.1000 6,400,000 7,040,000


2. Paku usuk kg 5.6000 18,000 100,800
3. Besi plat strip kg 15.0000 13,000 195,000
4. Baut mur Kuda-kuda kg 12.0000 15,000 180,000

Sub Total II 7,515,800

III PERALATAN

Sub Total III 0

Biaya Langsung (Sub Total I s/d III) 8,456,300


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 845,630
V JUMLAH 9,301,930
VI HARGA SATUAN PEKERJAAN (Rp/m³) 9,301,900
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : J.02
Jenis Pekerjaan : Pemasangan Reng Kruing / Usuk Kamper
Harga Satuan : Rp. 104,800
Satuan : m2

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA

1. Mandor org/hari 0.0060 57,500 345


2. Kepala Tukang org/hari 0.0120 57,500 690
3. Tukang Kayu org/hari 0.1200 57,500 6,900
4. Pekerja org/hari 0.1200 42,500 5,100

Sub Total I 13,035

II BAHAN

1. Kayu Kamper balok m³ 0.0070 6,800,000 47,600


2. Kayu Kruing balok m³ 0.0050 6,400,000 32,000
3. Paku usuk kg 0.1500 18,000 2,700

Sub Total II 82,300

III PERALATAN

Sub Total III 0

Biaya Langsung (Sub Total I s/d III) 95,335


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 9,534
V JUMLAH 104,869
VI HARGA SATUAN PEKERJAAN (Rp/m2) 104,800
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : J.03
Jenis Pekerjaan : Pemasangan Lisplank Kayu Kamper Tebal 3x30 cm
Harga Satuan : Rp. 110,000
Satuan : m

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA

1. Mandor org/hari 0.0050 57,500 288


2. Kepala Tukang org/hari 0.0200 57,500 1,150
3. Tukang Kayu org/hari 0.2000 57,500 11,500
4. Pekerja org/hari 0.1000 42,500 4,250

Sub Total I 17,188

II BAHAN

1. Kayu kamper papan m³ 0.0110 7,450,000 81,950


2. Paku 2"-5" kg 0.0500 18,000 900

Sub Total II 82,850

III PERALATAN

Sub Total III 0

Biaya Langsung (Sub Total I s/d III) 100,038


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 10,004
V JUMLAH 110,041
VI HARGA SATUAN PEKERJAAN (Rp/m) 110,000
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : J.04
Jenis Pekerjaan : Pemasangan Atap Asbes Gelombang 3,00 m x 1,05 m x 4 m
Harga Satuan : Rp. 41,200
Satuan : m2

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA

1. Mandor org/hari 0.0070 57,500 403


2. Kepala Tukang org/hari 0.0070 57,500 403
3. Tukang Kayu org/hari 0.0700 57,500 4,025
4. Pekerja org/hari 0.1400 42,500 5,950

Sub Total I 10,780

II BAHAN

1. Asbes gelombang 3,00 m x 1,05 m x 4 m m2 0.3500 69,250 24,238


2. Paku asbes gelombang kg 0.1200 21,000 2,520

Sub Total II 26,758

III PERALATAN

Sub Total III 0

Biaya Langsung (Sub Total I s/d III) 37,538


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 3,754
V JUMLAH 41,291
VI HARGA SATUAN PEKERJAAN (Rp/m2) 41,200
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : J.05
Jenis Pekerjaan : Pemasangan Bubung Asbes Gelombang
Harga Satuan : Rp. 74,300
Satuan : m

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA

1. Mandor org/hari 0.0020 57,500 115


2. Kepala Tukang org/hari 0.0200 57,500 1,150
3. Tukang Kayu org/hari 0.2000 57,500 11,500
4 Pekerja org/hari 0.4000 42,500 17,000

Sub Total I 12,765

II BAHAN

1. Bubugan psg 1.0000 50,000 50,000


2. Paku skrup 1/2" buah 2.0000 2,400 4,800

Sub Total II 54,800

III PERALATAN

Sub Total III 0

Biaya Langsung (Sub Total I s/d III) 67,565


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 6,757
V JUMLAH 74,322
VI HARGA SATUAN PEKERJAAN (Rp/m) 74,300
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : J.06
Jenis Pekerjaan : Kusen Pintu / Jendela Kayu Kruing
Harga Satuan : Rp. 10,035,500
Satuan : m³

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA

1. Mandor org/hari 0.300 57,500 17,250


2. Kepala Tukang org/hari 1.800 57,500 103,500
3. Tukang Kayu org/hari 18.000 57,500 1,035,000
4. Pekerja org/hari 6.000 42,500 255,000

Sub Total I 1,410,750

II BAHAN

1. Kayu Kruing balok m³ 1.2000 6,400,000 7,680,000


2 Paku 2'-5' kg 1.2500 18,000 22,500
3 Lem kayu kg 0.5000 20,000 10,000

Sub Total II 7,712,500

III PERALATAN

Sub Total III 0

Biaya Langsung (Sub Total I s/d III) 9,123,250


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 912,325
V JUMLAH 10,035,575
VI HARGA SATUAN PEKERJAAN (Rp/m³) 10,035,500
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : J.07
Jenis Pekerjaan : Daun Pintu Taekwood 3 mm
Harga Satuan : Rp. 615,200
Satuan : m2

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA

1. Mandor org/hari 0.0400 57,500 2,300


2. Kepala Tukang org/hari 0.2400 57,500 13,800
3. Tukang Kayu org/hari 2.4000 57,500 138,000
4. Pekerja org/hari 0.8000 42,500 34,000

Sub Total I 188,100

II BAHAN

1. Kayu kamper papan m2 0.0256 7,450,000 190,720


2. Teakwood 120 x 240cmx 3mm lbr 2.0000 85,000 170,000
3. Lem kayu kg 0.5000 20,000 10,000
4. Paku reng kg 0.0300 18,000 540

Sub Total II 371,260

III PERALATAN

Sub Total III 0

Biaya Langsung (Sub Total I s/d III) 559,360


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 55,936
V JUMLAH 615,296
VI HARGA SATUAN PEKERJAAN (Rp/m2) 615,200
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : J.08
Jenis Pekerjaan : Daun Pintu Triplek 4 mm
Harga Satuan : Rp. 577,800
Satuan : m2

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA

1. Mandor org/hari 0.0400 57,500 2,300


2. Kepala Tukang org/hari 0.2400 57,500 13,800
3. Tukang Kayu org/hari 2.4000 57,500 138,000
4. Pekerja org/hari 0.8000 42,500 34,000

Sub Total I 188,100

II BAHAN

1. Kayu kamper papan m3 0.0256 7,450,000 190,720


2. Tripleks 120 x 240 cmx4mm lbr 2.0000 68,000 136,000
3. Lem kayu kg 0.5000 20,000 10,000
4. Paku reng kg 0.0300 18,000 540

Sub Total II 337,260

III PERALATAN

Sub Total III 0

Biaya Langsung (Sub Total I s/d III) 525,360


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 52,536
V JUMLAH 577,896
VI HARGA SATUAN PEKERJAAN (Rp/m2) 577,800
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : J.09
Jenis Pekerjaan : Pemasangan Kaca Mati tebal 5 mm
Harga Satuan : Rp. 107,900
Satuan : m2

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA

1. Mandor org/hari 0.0008 57,500 46


2. Kepala Tukang org/hari 0.0150 57,500 863
3. Tukang Kayu org/hari 0.1500 57,500 8,625
4. Pekerja org/hari 0.0150 42,500 638

Sub Total I 10,171

II BAHAN

1. Kaca Bening Tebal 5mm m2 1.1000 80,000 88,000

Sub Total II 88,000

III PERALATAN

Sub Total III 0

Biaya Langsung (Sub Total I s/d III) 98,171


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 9,817
V JUMLAH 107,988
VI HARGA SATUAN PEKERJAAN (Rp/m2) 107,900
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : J.10
Jenis Pekerjaan : Gording/Nock
Harga Satuan : Rp. 9,174,100
Satuan : m3

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA

1. Mandor org/hari 0.1200 57,500 6,900


2. Kepala Tukang org/hari 0.7200 57,500 41,400
3. Tukang Kayu org/hari 7.2000 57,500 414,000
4. Pekerja org/hari 2.4000 42,500 102,000

Sub Total I 564,300

II BAHAN

1. Kayu Kamper Balok m3 1.100 6,800,000 7,480,000


2 Besi strip kg 15.000 13,000 195,000
3 Paku 2'-5' kg 5.600 18,000 100,800

Sub Total II 7,775,800

III PERALATAN

Sub Total III 0

Biaya Langsung (Sub Total I s/d III) 8,340,100


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 834,010
V JUMLAH 9,174,110
VI HARGA SATUAN PEKERJAAN (Rp/m3) 9,174,100
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : J.11
Jenis Pekerjaan : Pemasangan Kaca Mati Rayban tebal 5 mm
Harga Satuan : Rp. 120,000
Satuan : m2

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA

1. Mandor org/hari 0.0008 57,500 46


2. Kepala Tukang org/hari 0.0150 57,500 863
3. Tukang Kayu org/hari 0.1500 57,500 8,625
4. Pekerja org/hari 0.0150 42,500 638

Sub Total I 10,171

II BAHAN

1. Kaca Rayband Tebal 5 mm m2 1.1000 90,000 99,000

Sub Total II 99,000

III PERALATAN

Sub Total III 0

Biaya Langsung (Sub Total I s/d III) 109,171


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 10,917
V JUMLAH 120,088
VI HARGA SATUAN PEKERJAAN (Rp/m ) 2
120,000
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : J.12
Jenis Pekerjaan : Pengecatan Tembok
Harga Satuan : Rp. 52,300
Satuan : m2

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA

1. Mandor org/hari 0.0025 57,500 144


2. Kepala Tukang org/hari 0.0063 57,500 362
3. Tukang cat org/hari 0.0630 57,500 3,623
4. Pekerja org/hari 0.0200 42,500 850

Sub Total I 4,979

II BAHAN

1. Cat dinding/tembok kg 0.3600 110,000 39,600


2. Kertas Gosok lbr 0.2000 3,750 750
3. Plamur kg 0.1000 12,000 1,200
4. Kuas buah 0.1000 11,000 1,100

Sub Total II 42,650

III PERALATAN

Sub Total III 0

Biaya Langsung (Sub Total I s/d III) 47,629


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 4,763
V JUMLAH 52,391
VI HARGA SATUAN PEKERJAAN (Rp/m2) 52,300
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : J.13
Jenis Pekerjaan : Pemasangan Tegel Plint Abu-abu 15x20 cm campuran 1PC : 2Ps
Harga Satuan : Rp. 225,200
Satuan : m2

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA

1. Mandor org/hari 0.0140 57,500 805


2. Kepala Tukang org/hari 0.0140 57,500 805
3. Tukang batu org/hari 0.1350 57,500 7,763
4. Pekerja org/hari 0.2700 42,500 11,475

Sub Total I 20,848

II BAHAN

1. Pasir Pasang m3 0.0020 135,000 270


2. Semen PC (@50 kg) zak 0.0050 66,000 330
3. Plint polos 15/20 cm m 2 1.0000 183,333.33 183,333

Sub Total II 183,933

III PERALATAN

Sub Total III 0

Biaya Langsung (Sub Total I s/d III) 204,781


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 20,478
V JUMLAH 225,259
VI HARGA SATUAN PEKERJAAN (Rp/m2) 225,200
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : J.14
Jenis Pekerjaan : Pemasangan Tegel Teraso 30x30 cm
Harga Satuan : Rp. 150,400
Satuan : m2

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA

1. Mandor org/hari 0.0350 57,500 2,013


2. Kepala Tukang org/hari 0.0350 57,500 2,013
3. Tukang Batu org/hari 0.3500 57,500 20,125
4. Pekerja org/hari 0.7000 42,500 29,750

Sub Total I 53,900

II BAHAN

1. Pasir Pasang m3 0.0450 135,000 6,075


2. Kapur Pasangan m3 0.0160 350,000 5,600
3. Semen PC (@50 kg) zak 0.2000 66,000 13,200
4. Teraso 30x30 cm m2 1.0000 58,000 58,000

Sub Total II 82,875

III PERALATAN

Sub Total III 0

Biaya Langsung (Sub Total I s/d III) 136,775


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 13,678
V JUMLAH 150,453
VI HARGA SATUAN PEKERJAAN (Rp/m2) 150,400
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : J.15b No.


Jenis Pekerjaan : Pemasangan Keramik 20x20 cm Jenis Pekerjaan
Harga Satuan : Rp. 154,700 Harga Satuan
Satuan : m2 Satuan

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume No.
(Rp) (Rp)

I TENAGA I

1. Mandor org/hari 0.0350 57,500 2,013 1.


2. Kepala Tukang org/hari 0.0350 57,500 2,013 2.
3. Tukang batu org/hari 0.3500 57,500 20,125 3.
4. Pekerja org/hari 0.7000 42,500 29,750 4.

Sub Total I 53,900

II BAHAN II

1. Pasir Pasang m3 0.0045 135,000 608 1.


2. Semen Warna (@40 kg) kg 1.6200 12,000 19,440 2.
3. Semen PC (@50 kg) Zak 0.2080 66,000 13,728 3.
4. Keramik 20x20cm m2 1.0600 50,000 53,000 4.

Sub Total II 86,776

III PERALATAN III

Sub Total III 0

Biaya Langsung (Sub Total I s/d III) 140,676


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 14,068 IV
V JUMLAH 154,743 V
VI HARGA SATUAN PEKERJAAN (Rp/m2) 154,700 VI
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

: J.15
Jenis Pekerjaan : Pemasangan Tegel Keramik 30x30 cm
Harga Satuan : Rp. 159,000
Satuan : m2

Harga Satuan Jumlah Harga


Item Pekerjaan Satuan Volume
(Rp) (Rp)

TENAGA

Mandor org/hari 0.0350 57,500 2,013


Kepala Tukang org/hari 0.0350 57,500 2,013
Tukang batu org/hari 0.3500 57,500 20,125
Pekerja Biasa org/hari 0.7000 42,500 29,750

Sub Total I 53,900

MATERIAL

Pasir Pasang m3 0.0450 135,000 6,075


Semen Warna (@40 kg) kg 1.5000 12,000 18,000
Semen PC (@50 kg) Zak 0.2000 66,000 13,200
Tegel Keramik 30x30cm m2 1.0683 50,000 53,415

Sub Total II 90,690

PERALATAN

Sub Total III 0

Biaya Langsung (Sub Total I s/d III) 144,590


OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 14,459
JUMLAH 159,049
HARGA SATUAN PEKERJAAN (Rp/m2) 159,000
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : J.15c
Jenis Pekerjaan : Pemasangan List Keramik 5x20 cm
Harga Satuan : Rp. 69,400
Satuan : m2

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA

1. Mandor org/hari 0.0050 57,500 288


2. Kepala Tukang org/hari 0.0090 57,500 518
3. Tukang Batu org/hari 0.0900 57,500 5,175
4. Pekerja org/hari 0.0900 42,500 3,825

Sub Total I 9,805

II BAHAN

1. Pasir Pasang m3 0.0300 135,000 4,050


2. Semen Warna (@40 kg) kg 0.0250 12,000 300
3. Semen PC (@50 kg) Zak 0.0228 66,000 1,505
4. Keramik List bh 10.6000 5,400 57,240

Sub Total II 63,095

III PERALATAN

Sub Total III 0

Biaya Langsung (Sub Total I s/d III) 63,095


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 6,309
V JUMLAH 69,404
VI HARGA SATUAN PEKERJAAN (Rp/m2) 69,400
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : J.15d
Jenis Pekerjaan : Pemasangan Air Conditioner 2 PK
Harga Satuan : Rp. 4,580,300
Satuan : m2

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA

1. Mandor org/hari 0.0400 57,500 2,300


2. Kepala Tukang org/hari 0.3500 57,500 20,125
3. Tukang Listrik org/hari 1.5000 57,500 86,250
4. Pekerja org/hari 1.3000 42,500 55,250

Sub Total I 163,925

II BAHAN

1. AC dan perlengkapannya bh 1.0000 4,000,000 4,000,000

Sub Total II 4,000,000

III PERALATAN

Sub Total III 0

Biaya Langsung (Sub Total I s/d III) 4,163,925


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 416,393
V JUMLAH 4,580,318
VI HARGA SATUAN PEKERJAAN (Rp/m2) 4,580,300
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : J.15e
Jenis Pekerjaan : Pemasangan Air Conditioner 1 PK
Harga Satuan : Rp. 3,755,300
Satuan : m2

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA

1. Mandor org/hari 0.0400 57,500 2,300


2. Kepala Tukang org/hari 0.3500 57,500 20,125
3. Tukang Listrik org/hari 1.5000 57,500 86,250
4. Pekerja org/hari 1.3000 42,500 55,250

Sub Total I 163,925

II BAHAN

1. AC dan perlengkapannya bh 1.0000 3,250,000 3,250,000

Sub Total II 3,250,000

III PERALATAN

Sub Total III 0

Biaya Langsung (Sub Total I s/d III) 3,413,925


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 341,393
V JUMLAH 3,755,318
VI HARGA SATUAN PEKERJAAN (Rp/m2) 3,755,300
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : J.16
Jenis Pekerjaan : Pemasangan Kran Air dia 3/4"
Harga Satuan : Rp. 24,300
Satuan : buah

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA

1 Mandor org/hari 0.0050 57,500 288


2 Kepala Tukang org/hari 0.0100 57,500 575
3 Tukang ledeng org/hari 0.1000 57,500 5,750
4 Pekerja org/hari 0.0100 42,500 425

Sub Total I 7,038

II BAHAN

1. Kran Air dia 3/4" bh 1.0000 15,000 15,000


2. Rol TBA bh 0.0250 4,000 100

Sub Total II 15,100

III PERALATAN

Sub Total III 0

Biaya Langsung (Sub Total I s/d III) 22,138


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 2,214
V JUMLAH 24,351
VI HARGA SATUAN PEKERJAAN (Rp/buah) 24,300
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : J.17
Jenis Pekerjaan : Kloset Jongkok Porselin
Harga Satuan : Rp. 412,600
Satuan : buah

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA

1 Mandor org/hari 0.1600 57,500 9,200


2 Kepala Tukang org/hari 1.5000 57,500 86,250
3 Tukang batu org/hari 1.5000 57,500 86,250
4 Pekerja org/hari 1.0000 42,500 42,500

Sub Total I 224,200

II BAHAN

1. Kloset Jongkok Keramik bh 1.0000 140,000 140,000


2 Semen PC (@50 kg) zak 0.1200 66,000 7,920
3 Pasir Beton / Cor m3 0.0100 300,000 3,000

Sub Total II 150,920

III PERALATAN

Sub Total III 0

Biaya Langsung (Sub Total I s/d III) 375,120


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 37,512
V JUMLAH 412,632
VI HARGA SATUAN PEKERJAAN (Rp/buah) 412,600
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : J.18
Jenis Pekerjaan : Bak Mandi batu bata volume 0,30 m3
Harga Satuan : Rp. 1,088,000
Satuan : buah

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA
1 Mandor org/hari 0.0300 57,500 1,725
2 Kepala Tukang org/hari 0.3000 57,500 17,250
3 Tukang batu org/hari 3.0000 57,500 172,500
4 Pekerja org/hari 6.0000 42,500 255,000

Sub Total I 446,475

II BAHAN

1. Batu Bata bh 150.000 625 93,750


2. Semen PC (@50 kg) zak 2.4000 66,000 158,400
3. Porselin 11x11cm bh 360.000 484 174,240
4. Pasir pasang m 3 0.300 147,500 44,250
5 Semen nat kg 6.000 12,000 72,000

Sub Total II 542,640

III PERALATAN

Sub Total III 0

Biaya Langsung (Sub Total I s/d III) 989,115


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 98,912
V JUMLAH 1,088,027
VI HARGA SATUAN PEKERJAAN (Rp/buah) 1,088,000
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : J.19
Jenis Pekerjaan : Besi Baja Profil WF < 200 mm
Harga Satuan : Rp. 40,300
Satuan : kg
BBWS
Harga Satuan Jumlah Harga
No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA

1. Mandor org/hari 0.1400 57,500 8,050


2. Kepala Tukang org/hari 0.0006 57,500 35
3. Tukang besi org/hari 0.0770 57,500 4,428
4. Pekerja org/hari 0.1960 42,500 8,330

Sub Total I 20,842

II BAHAN

1. Baja Konstruksi/Profil WF kg 1.1000 13,750 15,125


2. Elektroda kg 0.0200 35,000 700

Sub Total II 15,825

III PERALATAN

Sub Total III 0

Biaya Langsung (Sub Total I s/d III) 36,667


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 3,667
V JUMLAH 40,334
VI HARGA SATUAN PEKERJAAN (Rp/kg) 40,300
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : J.20
Jenis Pekerjaan : Rangka Kuda-kuda L, 50/50 x 5
Harga Satuan : Rp. 46,800
Satuan : kg
BBWS
Harga Satuan Jumlah Harga
No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA

1. Mandor org/hari 0.1400 57,500 8,050


2. Kepala Tukang org/hari 0.0006 57,500 35
3. Tukang besi org/hari 0.0770 57,500 4,428
4. Pekerja org/hari 0.1960 42,500 8,330

Sub Total I 20,842

II BAHAN

1. Besi Siku 50/50 x 5 btg 0.0917 230,000 21,091


2. Elektroda kg 0.0200 35,000 700

Sub Total II 21,791

III PERALATAN

Sub Total III 0

Biaya Langsung (Sub Total I s/d III) 42,633


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 4,263
V JUMLAH 46,896
VI HARGA SATUAN PEKERJAAN (Rp/kg) 46,800
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : J.21
Jenis Pekerjaan : Plafon Gypsum
Harga Satuan : Rp. 338,300
Satuan : m2
BBWS
Harga Satuan Jumlah Harga
No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I PEKERJA

1. Mandor org/hari 0.0750 57,500 4,313


2. Kepala Tukang org/hari 0.0450 57,500 2,588
3. Tukang Kayu org/hari 0.2000 57,500 11,500
4. Pekerja org/hari 0.1500 42,500 6,375

Sub Total I 24,775

II MATERIAL

1 Metal Furing m' 3.6000 65,000 234,000


2 Kawat Seng polos Kg 0.1500 16,000 2,400
3 Ramset / Dina bolt Bh 1.0000 24,000 24,000
4 Gypsum Board 4"x8" tebal 9 mm lbr 0.3500 64,000 22,400

Sub Total II 282,800

III PERALATAN

Sub Total III 0

Biaya Langsung (Sub Total I s/d III) 307,575


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 30,758
V JUMLAH 338,333
VI HARGA SATUAN PEKERJAAN (Rp/m ) 2
338,300
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : J.21
Jenis Pekerjaan : List Plafon 15x15 cm
Harga Satuan : Rp. 22,100
Satuan : m2
BBWS
Harga Satuan Jumlah Harga
No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA

1. Mandor org/hari 0.0010 57,500 58


2. Kepala Tukang org/hari 0.0020 57,500 115
3. Tukang Kayu org/hari 0.0210 57,500 1,208
4. Pekerja org/hari 0.0210 42,500 893

Sub Total I 2,273

II BAHAN

1 List Gypsum 15/15 m 1.0000 12,500 12,500


2 Paku kg 0.3000 18,000 5,400

Sub Total II 17,900

III PERALATAN

Sub Total III 0

Biaya Langsung (Sub Total I s/d III) 20,173


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 2,017
V JUMLAH 22,190
VI HARGA SATUAN PEKERJAAN (Rp/m ) 2
22,100
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : J.21a
Jenis Pekerjaan : Plafon Eternit Rangka Kayu Meranti
Harga Satuan : Rp. 242,000
Satuan : m2
BBWS
Harga Satuan Jumlah Harga
No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA

1. Mandor org/hari 0.0100 57,500 575


2. Kepala Tukang org/hari 0.0300 57,500 1,725
3. Tukang Kayu org/hari 0.3000 57,500 17,250
4. Pekerja org/hari 0.2000 42,500 8,500

Sub Total I 28,050

II BAHAN

1. Eternit m2 1.0000 125,000 125,000


2. Kayu Meranti Balok m3 0.0155 4,150,000 64,325
3. Paku Reng kg 0.1500 18,000 2,700

Sub Total II 192,025

III PERALATAN

Sub Total III 0

Biaya Langsung (Sub Total I s/d III) 220,075


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 22,008
V JUMLAH 242,083
VI HARGA SATUAN PEKERJAAN (Rp/m2) 242,000
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : J.22
Jenis Pekerjaan : Pemasanngan Wastafel Gantung bulat
Harga Satuan : Rp. 522,000
Satuan : buah
BBWS
Harga Satuan Jumlah Harga
No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA

1. Mandor org/hari 0.1000 57,500 5,750


2. Tukang Batu org/hari 0.1450 57,500 8,338
3 Kepala Tukang org/hari 0.1500 57,500 8,625
4 Pekerja org/hari 1.2000 42,500 51,000

Sub Total I 73,713

II MATERIAL

1. Wastafel buah 1.0000 300,000 300,000


2. Perlengkapan (30% harga barang) % 30.0000 300,000 90,000
3. Semen PC (@50 kg) zak 0.1200 66,000 7,920
4. Pasir Beton / Cor m3 0.0100 300,000 3,000

Sub Total II 400,920

III PERALATAN

Sub Total III 0

Biaya Langsung (Sub Total I s/d III) 474,633


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 47,463
V JUMLAH 522,096
VI HARGA SATUAN PEKERJAAN (Rp/buah) 522,000
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : J.24
Jenis Pekerjaan : Grendel
Harga Satuan : Rp. 22,600
Satuan : buah
BBWS
Harga Satuan Jumlah Harga
No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA

1. Mandor org/hari 0.0075 57,500 431


2. Tukang Kayu org/hari 0.1500 57,500 8,625
3 Kepala Tukang org/hari 0.0150 57,500 863
4 Pekerja org/hari 0.0150 42,500 638

Sub Total I 10,556

II BAHAN

1. Grendel bh 1.0000 10,000 10,000

Sub Total II 10,000

III PERALATAN

Sub Total III 0

Biaya Langsung (Sub Total I s/d III) 20,556


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 2,056
V JUMLAH 22,612
VI HARGA SATUAN PEKERJAAN (Rp/bh) 22,600
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : J.25
Jenis Pekerjaan : Engsel Kuningan
Harga Satuan : Rp. 29,200
Satuan : buah
BBWS
Harga Satuan Jumlah Harga
No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA

1. Mandor org/hari 0.0075 57,500 431


2. Tukang Kayu org/hari 0.1500 57,500 8,625
3 Kepala Tukang org/hari 0.0150 57,500 863
4 Pekerja org/hari 0.0150 42,500 638

Sub Total I 10,556

II BAHAN

1. Engsel Nylon bh 1.0000 16,000 16,000

Sub Total II 16,000

III PERALATAN

Sub Total III 0

Biaya Langsung (Sub Total I s/d III) 26,556


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 2,656
V JUMLAH 29,212
VI HARGA SATUAN PEKERJAAN (Rp/bh) 29,200
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : J.26
Jenis Pekerjaan : Kunci Tanam 2x Putar
Harga Satuan : Rp. 198,000
Satuan : buah
BBWS
Harga Satuan Jumlah Harga
No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA

1. Mandor org/hari 0.0050 57,500 288


2. Tukang Kayu org/hari 0.5000 57,500 28,750
3 Kepala Tukang org/hari 0.0100 57,500 575
4 Pekerja org/hari 0.0100 42,500 425

Sub Total I 30,038

II BAHAN

1. Kunci Tanam 2x Putar bh 1.0000 150,000 150,000

Sub Total II 150,000

III PERALATAN

Sub Total III 0

Biaya Langsung (Sub Total I s/d III) 180,038


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 18,004
V JUMLAH 198,041
VI HARGA SATUAN PEKERJAAN (Rp/bh) 198,000
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : J.27
Jenis Pekerjaan : Gudang Lapangan (15 x 8 m2)
Harga Satuan : Rp. 91,004,900
Satuan : LS
BBWS
Harga Satuan Jumlah Harga
No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

1. Pembersihan Lahan (ref.C.01) m2 230.000 13,900 3,197,000


2. Pengupasan (ref.C.02) m2 230.000 21,200 4,876,000
3. Pekerjaan Pondasi :
- Pasangan Batu Kali (1PC : 3Ps) (ref.E.01) m3 6.640 706,300 4,689,832
- Beton K-175 (ref.D.04) m3 2.760 1,033,000 2,851,080
- Bekisting (ref.D.07) m2 1.440 155,300 223,632
- Gebalan Rumput (ref.C.16) m3 149.870 14,000 2,098,180
4. Pekerjan Dinding :
- Pasangan Batu Bata (1PC : 4Ps) (ref.E.03) m3 38.000 216,000 8,208,000
- Beton K-175 (ref.D.04) m3 2.100 1,033,000 2,169,300
- Bekisting (ref.D.07) m2 1.090 155,300 169,277
- Plesteran (1PC : 3 PS) (ref.E.04) m2 166.000 42,000 6,972,000
- Pengecatan Tembok (J.12) m2 166.000 52,300 8,681,800
5. Pekerjaan Atap :
- Pemasangan Kuda-kuda Kayu Kruing (ref.J.01) m3 0.700 9,301,900 6,511,330
- Gording 8/12 (ref.J.10) m3 1.210 9,174,100 11,100,661
- Nock 8/12 (ref.J.10) m3 0.210 9,174,100 1,926,561
- Atap Asbes Gelombang Kecil (ref.J.04) m2 122.470 41,200 5,045,764
6. Pekerjaan Pintu dan Jendela :
- Kusen Pintu (ref.J.06) m3 0.360 10,035,500 3,612,780
- Daun Pintu Triplek (ref.J.08) m2 10.000 577,800 5,778,000
- Kaca Rayban Polos Tebal 5 mm (jendela) (ref.J.12) m2 4.500 52,300 235,350
7. Pekerjaan Lain-lain :
- Grendel (ref.J.25) buah 1.000 29,200 29,200
- Engsel (ref.J.26) stel 22.000 198,000 4,356,000

Biaya Langsung (Sub Total I s/d III) 82,731,747


I OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 8,273,175
II JUMLAH 91,004,922
III HARGA SATUAN PEKERJAAN (Rp/bh) 91,004,900
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : J.28
Jenis Pekerjaan : Tandon air
Harga Satuan : Rp. 27,175,077
Satuan : LS

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA

1. Mandor org/hari 0.2000 57,500 11,500.00


2. Tukang Las org/hari 0.5000 57,500 28,750.00
3. Pekerja org/hari 1.5000 42,500 63,750.00

Sub Total I 104,000.00

II BAHAN

1. Beton K 175 (ref. D.04) m3 13.6185 1,033,000.00 14,067,910.50


2. Tulangan beton (ref.D.06) ton 2.7843 15,378.00 42,816.20
3. Tangga besi ton 0.0300 8,000,000.00 240,000.00
4. Bekisting (ref.D.07) m2 64.5000 155,300.00 10,016,850.00
5. Cat meni besi kg 5.6700 18,000.00 102,060.00
6. Elektroda kg 0.7051 35,000.00 24,679.20

Sub Total II 24,494,315.90

III PERALATAN

1. ARC. Welder, 300 A jam 0.2000 23,200.00 4,640.00


2. Electron Dryer, 100 kg jam 0.3000 135,300.00 40,590.00
3. Diesel Generator, 45 kVA jam 0.2000 136,800.00 27,360.00
4. Truck Flat Bed, 4 ton jam 0.1000 337,100.00 33,710.00

Sub Total III 106,300.00

Biaya Langsung (Sub Total I s/d III) 24,704,615.90


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 2,470,461.59
V HARGA SATUAN PEKERJAAN (Rp/LS) 27,175,077.49
VI HARGA SATUAN PEKERJAAN (Rp/LS) 27,175,000.00
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : J.29
Jenis Pekerjaan : Tangki Bahan Bakar
Harga Satuan : Rp. 21,089,090
Satuan : LS

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA

1. Mandor org/hari 4.0000 57,500 230,000


2. Tukang Las org/hari 10.0000 57,500 575,000
3. Pekerja org/hari 30.0000 42,500 1,275,000

Sub Total I 2,080,000

II BAHAN

1. Plat baja tebal 5 mm ton 0.4400 13,000,000 5,720,000


2. Tangga besi, dia. 16 mm ton 0.1000 8,000,000 800,000
3. Dudukan tangki ton 0.9200 8,000,000 7,360,000
4. Cat meni besi kg 4.0000 16,500 66,000
5. Elektroda kg 29.1400 35,000 1,019,900

Sub Total II 14,965,900

III PERALATAN

1. ARC. Welder, 300 A jam 4.0000 23,200 92,800


2. Electron Dryer, 100 kg jam 6.0000 135,300 811,800
3. Diesel Generator, 45 kVA jam 4.0000 136,800 547,200
4. Truck Flat Bed, 4 ton jam 2.0000 337,100 674,200

Sub Total III 2,126,000

Biaya Langsung (Sub Total I s/d III) 19,171,900


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 1,917,190
V HARGA SATUAN PEKERJAAN (Rp/LS) 21,089,090
VI HARGA SATUAN PEKERJAAN (Rp/LS) 21,089,000
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : J.30
Jenis Pekerjaan : Atap Baja Ringan + Genteng Penutup
Harga Satuan : Rp. 290,700
Satuan : m2

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA

1. Mandor org/hari 0.0095 57,500 546


2. Tukang Besi org/hari 0.2470 57,500 14,203
3 Kepala Tukang org/hari 0.1170 57,500 6,728
4 Pekerja org/hari 0.2500 42,500 10,625

Sub Total I 32,101

II BAHAN

1. Main Truss C-75-75 m 2.8000 14,870.00 41,636


2. Roof Bottom/Reng R 33-0.45 m 5.1000 8,500.00 43,350
3 Self Drilling Screw dia. 6x20 mm bh 25.0000 375.00 9,375
4 Self Drilling Screw dia. 4x16 mm bh 35.0000 350.00 12,250
5 Dinabolt dia. 12x120 mm bh 1.0000 1,500.00 1,500
6 Genteng Penutup Merk Multi m2 1.0000 124,070.00 124,070

Sub Total II 232,181

III PERALATAN

Sub Total III 0

Biaya Langsung (Sub Total I s/d III) 264,282


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 26,428
V HARGA SATUAN PEKERJAAN (Rp/m') 290,710
VI HARGA SATUAN PEKERJAAN (Rp/m') 290,700
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : J.31
Jenis Pekerjaan : Kusen Aluminium
Harga Satuan : Rp. 97,300
Satuan : m

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA

1. Mandor org/hari 0.0021 57,500 121


2. Tukang Besi org/hari 0.0430 57,500 2,473
3 Kepala Tukang org/hari 0.0043 57,500 247
4 Pekerja org/hari 0.0430 42,500 1,828

Sub Total I 4,668

II BAHAN

1. Kusen Aluminium 4" m 1.1000 70,000 77,000


2. Skrup bh 4.0000 800 3,200
3 Sealant tube 0.0600 60,000 3,600

Sub Total II 83,800

III PERALATAN

Sub Total III 0

Biaya Langsung (Sub Total I s/d III) 88,468


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 8,847
V HARGA SATUAN PEKERJAAN (Rp/m') 97,315
VI HARGA SATUAN PEKERJAAN (Rp/m') 97,300
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : J.32
Jenis Pekerjaan : Daun Pintu/Jendela Kaca
Harga Satuan : Rp. 292,900
Satuan : m2

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA

1. Mandor org/hari 0.0050 57,500 288


2. Tukang Besi org/hari 0.0850 57,500 4,888
3 Kepala Tukang org/hari 0.0090 57,500 518
4 Pekerja org/hari 0.0850 42,500 3,613

Sub Total I 9,305

II BAHAN

1 Kusen Aluminium 2" m 4.4000 35,000 154,000


2 Kaca Kabur 5 mm m2 1.1000 89,000 97,900
3 Sealant tube 0.2700 19,000 5,130
4 Skrup bh 4.0000 800 3,200

Sub Total II 257,030

III PERALATAN

Sub Total III 0

Biaya Langsung (Sub Total I s/d III) 266,335


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 26,634
V HARGA SATUAN PEKERJAAN (Rp/m') 292,969
VI HARGA SATUAN PEKERJAAN (Rp/m') 292,900
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : J.33
Jenis Pekerjaan : Kantor Proyek (420 m2)
Harga Satuan : Rp. 773,204,000
Satuan : Unit
BBWS
Harga Satuan Jumlah Harga
No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

1. Pembersihan Lahan (ref.C.01) m2 533.400 13,900 7,414,260


2. Pengupasan (ref.C.02) m2 533.400 21,200 11,308,080
3. Pekerjaan Pondasi :
- Pasangan Batu Kali (1PC : 3Ps) (ref.E.01) m3 76.800 706,300 54,243,840
- Beton K-175 (ref.D.04) m3 38.400 1,033,000 39,667,200
- Bekisting (ref.D.07) m2 30.720 155,300 4,770,816
- Gebalan Rumput (ref.C.16) m3 148.035 14,000 2,072,489
4. Pekerjan Dinding :
- Pasangan Batu Bata (1PC : 4Ps) (ref.E.03) m3 120.000 216,000 25,920,000
- Beton K-175 (ref.D.04) m3 19.200 1,033,000 19,833,600
- Bekisting (ref.D.07) m2 15.360 155,300 2,385,408
- Plesteran (1PC : 3 PS) (ref.E.04) m2 1,200.000 42,000 50,400,000
- Pengecatan Tembok (J.12) m2 1,200.000 52,300 62,760,000
5 Pekerjaan Penutup Lantai dan Dinding
- Lantai keramik 30/30 cm, merk Roman / setara m2 362 159,000 57,558,000
- Keramik dinding 20/25 cm, merk Roman / setara m2 40 154,700 6,188,000
- Keramik lantai 20/20 cm, merk Roman / setara m2 16 154,700 2,475,200
6 Pekerjaan Rangka, Penutup Dinding & Plafon
- Rangka metal furring + Penutup plafond gypsum 9 mm m2 462 338,300 156,294,600
- Pasang list plafond gypsum 15/15 m 480 22,100 10,608,000
7 Pekerjaan Atap
- Rangka Baja Ringan + Genteng Penutup (ref.J.30) m2 603.750 290,700 175,510,125
8 Pekerjaan Pintu dan Jendela :
- Kusen Pintu/Jendela Aluminium (ref.J.31) m 267.750 97,300 26,052,075
- Daun Pintu/Jendela Kaca (ref.J.32) m2 70.000 292,900 20,503,000
- Kaca Rayban Polos Tebal 5 mm (jendela) (ref.J.12) m2 122.500 120,000 14,700,000
9 Pekerjaan Lain-lain :
- Grendel (ref.J.24) buah 3.000 22,600 67,800
- Engsel (ref.J.25) stel 22.000 29,200 642,400
- Kunci Tanam (ref.J.26) stel 4.000 198,000 792,000
10 Pemasangan AC bh 4.000 4,537,500 18,150,000
11 Pemasangan Closet Duduk bh 2.000 1,444,000 2,888,000

I Biaya Langsung (Sub Total I s/d III) 773,204,893.26


II OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 0
III HARGA SATUAN PEKERJAAN (Rp/unit) 773,204,893
IV HARGA SATUAN PEKERJAAN (Rp/unit) 773,204,000
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : J.34
Jenis Pekerjaan : Rumah Dinas Type 1 (60 m2)
Harga Satuan : Rp. 117,692,000
Satuan : Unit
BBWS
Harga Satuan Jumlah Harga
No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

1. Pembersihan Lahan (ref.C.01) m2 76.200 13,900 1,059,180


2. Pengupasan (ref.C.02) m2 76.200 21,200 1,615,440
3. Pekerjaan Pondasi :
- Pasangan Batu Kali (1PC : 3Ps) (ref.E.01) m3 10.971 706,300 7,749,120
- Beton K-175 (ref.D.04) m3 5.486 1,033,000 5,666,743
- Bekisting (ref.D.07) m2 4.389 155,300 681,545
- Gebalan Rumput (ref.C.16) m3 74.935 14,000 1,049,090
4. Pekerjan Dinding :
- Pasangan Batu Bata (1PC : 4Ps) (ref.E.03) m3 17.143 216,000 3,702,857
- Beton K-175 (ref.D.04) m3 2.743 1,033,000 2,833,371
- Bekisting (ref.D.07) m2 2.194 155,300 340,773
- Plesteran (1PC : 3 PS) (ref.E.04) m2 171.429 42,000 7,200,000
- Pengecatan Tembok (J.12) m2 171.429 52,300 8,965,714
5 Pekerjaan Penutup Lantai dan Dinding
- Lantai keramik 30/30 cm, merk Roman / setara m2 52 159,000 8,222,571
- Keramik dinding 20/25 cm, merk Roman / setara m2 6 154,700 884,000
- Keramik lantai 20/20 cm, merk Roman / setara m2 2 154,700 353,600
6 Pekerjaan Rangka, Penutup Dinding & Plafon 0
- Rangka metal furring + Penutup plafond gypsum 9 mm m2 66 338,300 22,327,800
- Pasang list plafond gypsum 15/15 m 69 22,100 1,515,429
7 Pekerjaan Atap
- Rangka Baja Ringan + Genteng Penutup (ref.J.30) m2 86.250 290,700 25,072,875
8 Pekerjaan Pintu dan Jendela :
- Kusen Pintu/Jendela Aluminium (ref.J.31) m 38.250 97,300 3,721,725
- Daun Pintu/Jendela Kaca (ref.J.32) m2 10.000 292,900 2,929,000
- Kaca Rayban Polos Tebal 5 mm (jendela) (ref.J.12) m2 2.250 120,000 270,000
9 Pekerjaan Lain-lain :
- Grendel (ref.J.24) buah 3.000 22,600 67,800
- Engsel (ref.J.25) stel 12.000 29,200 350,400
- Kunci Tanam (ref.J.26) stel 3.000 198,000 594,000
10 Pemasangan AC bh 2.000 4,537,500 9,075,000
11 Pemasangan Closet Duduk bh 1.000 1,444,000 1,444,000

I Biaya Langsung (Sub Total I s/d III) 117,692,033.43


II OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 0
III HARGA SATUAN PEKERJAAN (Rp/unit) 117,692,033
IV HARGA SATUAN PEKERJAAN (Rp/unit) 117,692,000
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : J.35
Jenis Pekerjaan : Rumah Dinas Type 2 (45 m2)
Harga Satuan : Rp. 92,882,000
Satuan : Unit
BBWS
Harga Satuan Jumlah Harga
No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

1. Pembersihan Lahan (ref.C.01) m2 57.150 13,900 794,385


2. Pengupasan (ref.C.02) m2 57.150 21,200 1,211,580
3. Pekerjaan Pondasi :
- Pasangan Batu Kali (1PC : 3Ps) (ref.E.01) m3 8.229 706,300 5,811,840
- Beton K-175 (ref.D.04) m3 4.114 1,033,000 4,250,057
- Bekisting (ref.D.07) m2 3.291 155,300 511,159
- Gebalan Rumput (ref.C.16) m3 56.201 14,000 786,818
4. Pekerjan Dinding :
- Pasangan Batu Bata (1PC : 4Ps) (ref.E.03) m3 12.857 216,000 2,777,143
- Beton K-175 (ref.D.04) m3 2.057 1,033,000 2,125,029
- Bekisting (ref.D.07) m2 1.646 155,300 255,579
- Plesteran (1PC : 3 PS) (ref.E.04) m2 128.571 42,000 5,400,000
- Pengecatan Tembok (J.12) m2 128.571 52,300 6,724,286
5 Pekerjaan Penutup Lantai dan Dinding
- Lantai keramik 30/30 cm, merk Roman / setara m2 39 159,000 6,166,929
- Keramik dinding 20/25 cm, merk Roman / setara m2 4 154,700 663,000
- Keramik lantai 20/20 cm, merk Roman / setara m2 2 154,700 265,200
6 Pekerjaan Rangka, Penutup Dinding & Plafon
- Rangka metal furring + Penutup plafond gypsum 9 mm m2 50 338,300 16,745,850
- Pasang list plafond gypsum 15/15 m 51 22,100 1,136,571
7 Pekerjaan Atap
- Rangka Baja Ringan + Genteng Penutup (ref.J.30) m2 64.688 290,700 18,804,656
8 Pekerjaan Pintu dan Jendela :
- Kusen Pintu/Jendela Aluminium (ref.J.31) m 38.250 97,300 3,721,725
- Daun Pintu/Jendela Kaca (ref.J.32) m2 10.000 292,900 2,929,000
- Kaca Rayban Polos Tebal 5 mm (jendela) (ref.J.12) m2 2.250 120,000 270,000
9 Pekerjaan Lain-lain :
- Grendel (ref.J.24) buah 3.000 22,600 67,800
- Engsel (ref.J.25) stel 12.000 29,200 350,400
- Kunci Tanam (ref.J.26) stel 3.000 198,000 594,000
10 Pemasangan AC bh 2.000 4,537,500 9,075,000
11 Pemasangan Closet Duduk bh 1.000 1,444,000 1,444,000

I Biaya Langsung (Sub Total I s/d III) 92,882,006.32


II OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 0
III HARGA SATUAN PEKERJAAN (Rp/unit) 92,882,006
IV HARGA SATUAN PEKERJAAN (Rp/unit) 92,882,000
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : J.36
Jenis Pekerjaan : Klinik Umum (45,5 m2)
Harga Satuan : #REF!
Satuan : Unit
BBWS
Harga Satuan Jumlah Harga
No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

1. Pembersihan Lahan (ref.C.01) m2 57.785 13,900 803,212


2. Pengupasan (ref.C.02) m2 57.785 21,200 1,225,042
3. Pekerjaan Pondasi :
- Pasangan Batu Kali (1PC : 3Ps) (ref.E.01) m3 8.320 706,300 5,876,416
- Beton K-175 (ref.D.04) m3 4.160 1,033,000 4,297,280
- Bekisting (ref.D.07) m2 3.328 155,300 516,838
- Gebalan Rumput (ref.C.16) m3 56.826 14,000 795,560
4. Pekerjan Dinding :
- Pasangan Batu Bata (1PC : 4Ps) (ref.E.03) m3 13.000 216,000 2,808,000
- Beton K-175 (ref.D.04) m3 2.080 1,033,000 2,148,640
- Bekisting (ref.D.07) m2 1.664 155,300 258,419
- Plesteran (1PC : 3 PS) (ref.E.04) m2 130.000 42,000 5,460,000
- Pengecatan Tembok (J.12) m2 130.000 52,300 6,799,000
5 Pekerjaan Penutup Lantai dan Dinding 0
- Lantai keramik 40/40 cm, merk Roman / setara m2 39 159,000 6,235,450
- Keramik dinding 20/25 cm, merk Roman / seta m2 4 154,700 670,367
- Keramik lantai 20/20 cm, merk Roman / setara m2 2 154,700 268,147
- List keramik dinding 6/20 cm m 2 #REF! #REF!
6 Pekerjaan Rangka, Penutup Dinding & Plafon 0 0
- Rangka metal furring + Penutup plafond gyps m2 50 338,300 16,931,915
- Pasang list plafond gypsum 15/15 m 52 22,100 1,149,200
7 Pekerjaan Atap 0
- Rangka Baja Ringan + Genteng Penutup (ref.J.30) m2 65.406 290,700 19,013,597
8 Pekerjaan Pintu dan Jendela :
- Kusen Pintu/Jendela Aluminium (ref.J.31) m 38.250 97,300 3,721,725
- Daun Pintu/Jendela Kaca (ref.J.32) m2 10.000 292,900 2,929,000
- Kaca Rayban Polos Tebal 5 mm (jendela) (ref.J.12) m2 2.250 120,000 270,000
9 Pekerjaan Lain-lain :
- Grendel (ref.J.24) buah 3.000 22,600 67,800
- Engsel (ref.J.25) stel 12.000 29,200 350,400
- Kunci Tanam (ref.J.26) stel 3.000 198,000 594,000
10 Pemasangan AC bh 1.000 4,537,500 4,537,500
11 Pemasangan Closet Duduk bh 1.000 1,444,000 1,444,000

I Biaya Langsung (Sub Total I s/d III) #REF!


II OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 0
III HARGA SATUAN PEKERJAAN (Rp/unit) #REF!
IV HARGA SATUAN PEKERJAAN (Rp/unit) #REF!
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : J.37
Jenis Pekerjaan : Gardu Pandang (40 m2)
Harga Satuan : Rp. 84,461,000
Satuan : Unit
BBWS
Harga Satuan Jumlah Harga
No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

1. Pembersihan Lahan (ref.C.01) m2 51.364 13,900 713,966


2. Pengupasan (ref.C.02) m2 51.364 21,200 1,088,926
3. Pekerjaan Pondasi :
- Pasangan Batu Kali (1PC : 3Ps) (ref.E.01) m3 7.396 706,300 5,223,481
- Beton K-175 (ref.D.04) m3 3.698 1,033,000 3,819,804
- Bekisting (ref.D.07) m2 2.958 155,300 459,412
- Gebalan Rumput (ref.C.16) m3 50.512 14,000 707,164
4. Pekerjan Dinding :
- Pasangan Batu Bata (1PC : 4Ps) (ref.E.03) m3 11.556 216,000 2,496,000
- Beton K-175 (ref.D.04) m3 1.849 1,033,000 1,909,902
- Bekisting (ref.D.07) m2 1.479 155,300 229,706
- Plesteran (1PC : 3 PS) (ref.E.04) m2 115.556 42,000 4,853,333
- Pengecatan Tembok (J.12) m2 115.556 52,300 6,043,556
5 Pekerjaan Penutup Lantai dan Dinding
- Lantai keramik 30/30 cm, merk Roman / setara m2 35 159,000 5,542,622
- Keramik dinding 20/25 cm, merk Roman / setara m2 4 154,700 595,881
- Keramik lantai 20/20 cm, merk Roman / setara m2 2 154,700 238,353
6 Pekerjaan Rangka, Penutup Dinding & Plafon
- Rangka metal furring + Penutup plafond gypsum 9 mm m2 44 338,300 15,050,591
- Pasang list plafond gypsum 15/15 m 46 22,100 1,021,511
7 Pekerjaan Atap
- Rangka Baja Ringan + Genteng Penutup (ref.J.30) m2 58.139 290,700 16,900,975
8 Pekerjaan Pintu dan Jendela :
- Kusen Pintu/Jendela Aluminium (ref.J.31) m 34.000 97,300 3,308,200
- Daun Pintu/Jendela Kaca (ref.J.32) m2 8.889 292,900 2,603,556
- Kaca Rayban Polos Tebal 5 mm (jendela) (ref.J.12) m2 2.000 120,000 240,000
9 Pekerjaan Lain-lain :
- Grendel (ref.J.24) buah 3.000 22,600 67,800
- Engsel (ref.J.25) stel 8.000 29,200 233,600
- Kunci Tanam (ref.J.26) stel 3.000 198,000 594,000
10 Pemasangan AC bh 2.000 4,537,500 9,075,000
11 Pemasangan Closet Duduk bh 1.000 1,444,000 1,444,000

I Biaya Langsung (Sub Total I s/d III) 84,461,339.76


II OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 0
III HARGA SATUAN PEKERJAAN (Rp/unit) 84,461,340
IV HARGA SATUAN PEKERJAAN (Rp/unit) 84,461,000
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : J.38
Jenis Pekerjaan : Pos Jaga ( 9 m2 ) 2 Unit
Harga Satuan : Rp. 15,719,000
Satuan : Unit
BBWS
Harga Satuan Jumlah Harga
No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

1. Pembersihan Lahan (ref.C.01) m2 10.979 13,900 152,610


2. Pengupasan (ref.C.02) m2 10.979 21,200 232,758
3. Pekerjaan Pondasi :
- Pasangan Batu Kali (1PC : 3Ps) (ref.E.01) m3 1.581 706,300 1,116,519
- Beton K-175 (ref.D.04) m3 0.790 1,033,000 816,483
- Bekisting (ref.D.07) m2 0.632 155,300 98,199
- Gebalan Rumput (ref.C.16) m3 10.797 14,000 151,156
4. Pekerjan Dinding :
- Pasangan Batu Bata (1PC : 4Ps) (ref.E.03) m3 2.470 216,000 533,520
- Beton K-175 (ref.D.04) m3 0.395 1,033,000 408,242
- Bekisting (ref.D.07) m2 0.316 155,300 49,100
- Plesteran (1PC : 3 PS) (ref.E.04) m2 24.700 42,000 1,037,400
- Pengecatan Tembok (J.12) m2 24.700 52,300 1,291,810
5 Pekerjaan Penutup Lantai
- Pemasangan Tegel Teraso 30 x 30 cm m2 7 150,400 1,120,655
6 Pekerjaan Rangka, Penutup Dinding & Plafon
- Rangka metal furring + Penutup plafond gypsum 9 mm m2 10 338,300 3,217,064
- Pasang list plafond gypsum 15/15 m 10 22,100 218,348
7 Pekerjaan Atap
- Rangka Baja Ringan + Genteng Penutup (ref.J.30) m2 12.427 290,700 3,612,583
8 Pekerjaan Pintu dan Jendela :
- Kusen Pintu/Jendela Aluminium (ref.J.31) m 7.650 97,300 744,345
- Daun Pintu/Jendela Kaca (ref.J.32) m2 2.000 292,900 585,800
- Kaca Rayban Polos Tebal 5 mm (jendela) (ref.J.12) m2 0.450 120,000 54,000
9 Pekerjaan Lain-lain :
- Grendel (ref.J.24) buah 1.000 22,600 22,600
- Engsel (ref.J.25) stel 2.000 29,200 58,400
- Kunci Tanam (ref.J.26) stel 1.000 198,000 198,000

I Biaya Langsung (Sub Total I s/d III) 15,719,593.06


II OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 0
III HARGA SATUAN PEKERJAAN (Rp/unit) 15,719,593
IV HARGA SATUAN PEKERJAAN (Rp/unit) 15,719,000
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : J.39
Jenis Pekerjaan : Mushola (60 m3)
Harga Satuan : Rp. 117,411,000
Satuan : Unit
BBWS
Harga Satuan Jumlah Harga
No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

1. Pembersihan Lahan (ref.C.01) m2 73.194 13,900 1,017,401


2. Pengupasan (ref.C.02) m2 73.194 21,200 1,551,720
3. Pekerjaan Pondasi :
- Pasangan Batu Kali (1PC : 3Ps) (ref.E.01) m3 10.539 706,300 7,443,460
- Beton K-175 (ref.D.04) m3 5.269 1,033,000 5,443,221
- Bekisting (ref.D.07) m2 4.215 155,300 654,662
- Gebalan Rumput (ref.C.16) m3 71.979 14,000 1,007,709
4. Pekerjan Dinding :
- Pasangan Batu Bata (1PC : 4Ps) (ref.E.03) m3 16.467 216,000 3,556,800
- Beton K-175 (ref.D.04) m3 2.635 1,033,000 2,721,611
- Bekisting (ref.D.07) m2 2.108 155,300 327,331
- Plesteran (1PC : 3 PS) (ref.E.04) m2 164.667 42,000 6,916,000
- Pengecatan Tembok (J.12) m2 164.667 52,300 8,612,067
5 Pekerjaan Penutup Lantai dan Dinding
- Lantai keramik 30/30 cm, merk Roman / setara m2 50 159,000 7,898,237
- Keramik dinding 20/25 cm, merk Roman / setara m2 5 154,700 849,131
- Keramik lantai 20/20 cm, merk Roman / setara m2 2 154,700 339,652
6 Pekerjaan Rangka, Penutup Dinding & Plafon
- Rangka metal furring + Penutup plafond gypsum 9 mm m2 63 338,300 21,447,092
- Pasang list plafond gypsum 15/15 m 66 22,100 1,455,653
7 Pekerjaan Atap
- Rangka Baja Ringan + Genteng Penutup (ref.J.30) m2 82.848 290,700 24,083,889
8 Pekerjaan Pintu dan Jendela :
- Kusen Pintu/Jendela Aluminium (ref.J.31) m 51.000 97,300 4,962,300
- Daun Pintu/Jendela Kaca (ref.J.32) m2 13.333 292,900 3,905,333
- Kaca Rayban Polos Tebal 5 mm (jendela) (ref.J.12) m2 3.000 120,000 360,000
9 Pekerjaan Lain-lain :
- Grendel (ref.J.24) buah 3.000 22,600 67,800
- Engsel (ref.J.25) stel 8.000 29,200 233,600
- Kunci Tanam (ref.J.26) stel 3.000 198,000 594,000
10 Pemasangan AC bh 2.000 4,537,500 9,075,000
11 Pemasangan Closet Duduk bh 2.000 1,444,000 2,888,000

I Biaya Langsung (Sub Total I s/d III) 117,411,670.82


II OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 0
III HARGA SATUAN PEKERJAAN (Rp/unit) 117,411,671
IV HARGA SATUAN PEKERJAAN (Rp/unit) 117,411,000
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : J.40
Jenis Pekerjaan : Rumah Genset (16 m2)
Harga Satuan : Rp. 31,169,000
Satuan : Unit
BBWS
Harga Satuan Jumlah Harga
No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

1. Pembersihan Lahan (ref.C.01) m2 19.518 13,900 271,307


2. Pengupasan (ref.C.02) m2 19.518 21,200 413,792
3. Pekerjaan Pondasi :
- Pasangan Batu Kali (1PC : 3Ps) (ref.E.01) m3 2.810 706,300 1,984,923
- Beton K-175 (ref.D.04) m3 2.405 1,033,000 2,484,526
- Bekisting (ref.D.07) m2 1.124 155,300 174,577
- Gebalan Rumput (ref.C.16) m3 19.194 14,000 268,722
4. Pekerjan Dinding :
- Pasangan Batu Bata (1PC : 4Ps) (ref.E.03) m3 4.391 216,000 948,480
- Beton K-175 (ref.D.04) m3 0.703 1,033,000 725,763
- Bekisting (ref.D.07) m2 0.562 155,300 87,288
- Plesteran (1PC : 3 PS) (ref.E.04) m2 43.911 42,000 1,844,267
- Pengecatan Tembok (J.12) m2 43.911 52,300 2,296,551
5 Pekerjaan Penutup Lantai dan Dinding 0
- Pemasangan Tegel Teraso 30 x 30 cm m2 20.000 150,400 3,008,000
6 Pekerjaan Rangka, Penutup Dinding & Plafon 0
- Rangka metal furring + Penutup plafond gypsum 9 mm m2 16.906 338,300 5,719,225
- Pasang list plafond gypsum 15/15 m 17.564 22,100 388,174
7 Pekerjaan Atap 0
- Rangka Baja Ringan + Genteng Penutup (ref.J.30) m2 20.090 290,700 5,840,163
8 Pekerjaan Pintu dan Jendela :
- Kusen Pintu/Jendela Aluminium (ref.J.31) m 14.000 97,300 1,362,200
- Daun Pintu/Jendela Kaca (ref.J.32) m2 3.455 292,900 1,011,970
9 Pekerjaan Lain-lain :
- Grendel (ref.J.24) buah 3.000 22,600 67,800
- Engsel (ref.J.25) stel 8.000 29,200 233,600
- Kunci Tanam (ref.J.26) stel 3.000 198,000 594,000
10 Pemasangan Closet Duduk bh 1.000 1,444,000 1,444,000

I Biaya Langsung (Sub Total I s/d III) 31,169,326.60


II OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 0
III HARGA SATUAN PEKERJAAN (Rp/unit) 31,169,327
IV HARGA SATUAN PEKERJAAN (Rp/unit) 31,169,000
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : J.41
Jenis Pekerjaan : Bengkel Peralatan (120 m2)
Harga Satuan : Rp. 220,919,000
Satuan : Unit
BBWS
Harga Satuan Jumlah Harga
No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

1. Pembersihan Lahan (ref.C.01) m2 146.389 13,900 2,034,802


2. Pengupasan (ref.C.02) m2 146.389 21,200 3,103,440
3. Pekerjaan Pondasi :
- Pasangan Batu Kali (1PC : 3Ps) (ref.E.01) m3 21.077 706,300 14,886,921
- Beton K-175 (ref.D.04) m3 10.539 1,033,000 10,886,443
- Bekisting (ref.D.07) m2 8.431 155,300 1,309,324
- Gebalan Rumput (ref.C.16) m3 143.958 14,000 2,015,418
4. Pekerjan Dinding :
- Pasangan Batu Bata (1PC : 4Ps) (ref.E.03) m3 32.933 216,000 7,113,600
- Beton K-175 (ref.D.04) m3 5.269 1,033,000 5,443,221
- Bekisting (ref.D.07) m2 4.215 155,300 654,662
- Plesteran (1PC : 3 PS) (ref.E.04) m2 329.333 42,000 13,832,000
- Pengecatan Tembok (J.12) m2 329.333 52,300 17,224,133
5 Pekerjaan Penutup Lantai dan Dinding 0
- Pemasangan Tegel Teraso 30 x 30 cm m2 150 150,400 22,560,000
6 Pekerjaan Rangka, Penutup Dinding & Plafon 0
- Rangka metal furring + Penutup plafond gypsum 9 mm m2 127 338,300 42,894,185
- Pasang list plafond gypsum 15/15 m 132 22,100 2,911,307
7 Pekerjaan Atap 0
- Rangka Baja Ringan + Genteng Penutup (ref.J.30) m2 165.696 290,700 48,167,779
8 Pekerjaan Pintu dan Jendela :
- Kusen Pintu/Jendela Aluminium (ref.J.31) m 102.000 97,300 9,924,600
- Daun Pintu/Jendela Kaca (ref.J.32) m2 27.000 292,900 7,908,300
9 Pekerjaan Lain-lain :
- Grendel (ref.J.24) buah 22.000 22,600 497,200
- Engsel (ref.J.25) stel 60.000 29,200 1,752,000
- Kunci Tanam (ref.J.26) stel 22.000 198,000 4,356,000
10 Pemasangan Closet Duduk bh 1.000 1,444,000 1,444,000

I Biaya Langsung (Sub Total I s/d III) 220,919,334.53


II OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 0
III HARGA SATUAN PEKERJAAN (Rp/unit) 220,919,335
IV HARGA SATUAN PEKERJAAN (Rp/unit) 220,919,000
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : J.41a
Jenis Pekerjaan : Rumah Instrumen (31.76 m2)
Harga Satuan : Rp. 62,823,000
Satuan : Unit
BBWS
Harga Satuan Jumlah Harga
No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

1. Pembersihan Lahan (ref.C.01) m2 40.780 13,900 566,842


2. Pengupasan (ref.C.02) m2 40.780 21,200 864,536
3. Pekerjaan Pondasi :
- Pasangan Batu Kali (1PC : 3Ps) (ref.E.01) m3 5.870 706,300 4,145,981
- Beton K-175 (ref.D.04) m3 2.940 1,033,000 3,037,020
- Bekisting (ref.D.07) m2 2.350 155,300 364,955
- Gebalan Rumput (ref.C.16) m3 40.110 14,000 561,540
4. Pekerjan Dinding :
- Pasangan Batu Bata (1PC : 4Ps) (ref.E.03) m3 9.180 216,000 1,982,880
- Beton K-175 (ref.D.04) m3 1.470 1,033,000 1,518,510
- Bekisting (ref.D.07) m2 1.170 155,300 181,701
- Plesteran (1PC : 3 PS) (ref.E.04) m2 91.750 42,000 3,853,500
- Pengecatan Tembok (J.12) m2 91.750 52,300 4,798,525
5 Pekerjaan Penutup Lantai dan Dinding 0
- Pemasangan Tegel Keramik 30 x 30 cm m2 28 159,000 4,401,120
6 Pekerjaan Rangka, Penutup Dinding & Plafon 0
- Rangka metal furring + Penutup plafond gypsum 9 mm m2 35 338,300 11,948,756
- Pasang list plafond gypsum 15/15 m 37 22,100 811,070
7 Pekerjaan Atap 0
- Rangka Baja Ringan + Genteng Penutup (ref.J.30) m2 46.160 290,700 13,418,712
8 Pekerjaan Pintu dan Jendela :
- Kusen Pintu/Jendela Aluminium (ref.J.31) m 27.000 97,300 2,627,100
- Daun Pintu/Jendela Kaca (ref.J.32) m2 7.060 292,900 2,067,874
- Kaca Rayban Polos Tebal 5 mm (jendela) (ref.J.12) m2 2.000 120,000 240,000
9 Pekerjaan Lain-lain :
- Grendel (ref.J.24) buah 3.000 22,600 67,800
- Engsel (ref.J.25) stel 8.000 29,200 233,600
- Kunci Tanam (ref.J.26) stel 3.000 198,000 594,000
10 Pemasangan AC bh 1.000 4,537,500 4,537,500

I Biaya Langsung (Sub Total I s/d III) 62,823,522.00


II OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 0
III HARGA SATUAN PEKERJAAN (Rp/unit) 62,823,522
IV HARGA SATUAN PEKERJAAN (Rp/unit) 62,823,000
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : J.42
Jenis Pekerjaan : Rumah tangki Bahan Bakar ( 90 m³ )
Harga Satuan : Rp. 167,607,000
Satuan : Unit
BBWS
Harga Satuan Jumlah Harga
No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

1. Pembersihan Lahan (ref.C.01) m2 109.792 13,900 1,526,102


2. Pengupasan (ref.C.02) m2 109.792 21,200 2,327,580
3. Pekerjaan Pondasi :
- Pasangan Batu Kali (1PC : 3Ps) (ref.E.01) m3 15.808 706,300 11,165,190
- Beton K-175 (ref.D.04) m3 7.904 1,033,000 8,164,832
- Bekisting (ref.D.07) m2 6.323 155,300 981,993
- Gebalan Rumput (ref.C.16) m3 107.969 14,000 1,511,564
4. Pekerjan Dinding :
- Pasangan Batu Bata (1PC : 4Ps) (ref.E.03) m3 24.700 216,000 5,335,200
- Beton K-175 (ref.D.04) m3 3.952 1,033,000 4,082,416
- Bekisting (ref.D.07) m2 3.162 155,300 490,996
- Plesteran (1PC : 3 PS) (ref.E.04) m2 247.000 42,000 10,374,000
- Pengecatan Tembok (J.12) m2 247.000 52,300 12,918,100
5 Pekerjaan Penutup Lantai dan Dinding 0
- Pemasangan Tegel Teraso 30 x 30 cm m2 113 150,400 16,920,000
6 Pekerjaan Rangka, Penutup Dinding & Plafon 0
- Rangka metal furring + Penutup plafond gypsum 9 mm m2 95 338,300 32,170,639
- Pasang list plafond gypsum 15/15 m 99 22,100 2,183,480
7 Pekerjaan Atap 0
- Rangka Baja Ringan + Genteng Penutup (ref.J.30) m2 124.272 290,700 36,125,834
8 Pekerjaan Pintu dan Jendela :
- Kusen Pintu/Jendela Aluminium (ref.J.31) m 76.500 97,300 7,443,450
- Daun Pintu/Jendela Kaca (ref.J.32) m2 20.250 292,900 5,931,225
- Kaca Rayban Polos Tebal 5 mm (jendela) (ref.J.12) m2 11.250 120,000 1,350,000
9 Pekerjaan Lain-lain :
- Grendel (ref.J.24) buah 22.000 22,600 497,200
- Engsel (ref.J.25) stel 60.000 29,200 1,752,000
- Kunci Tanam (ref.J.26) stel 22.000 198,000 4,356,000

I Biaya Langsung (Sub Total I s/d III) 167,607,800.89


II OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 0
III HARGA SATUAN PEKERJAAN (Rp/unit) 167,607,801
IV HARGA SATUAN PEKERJAAN (Rp/unit) 167,607,000
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : K.01
Jenis Pekerjaan : PVC Water Stop, lebar 300 mm
Harga Satuan : Rp. 169,800
Satuan : m´

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA

1. Mandor org/hari 0.0075 57,500 431


2. Pekerja org/hari 0.0938 42,500 3,987

Sub Total I 4,418

II BAHAN

1. PVC Waterstop (b=300 mm) m' 1.0000 150,000 150,000

Sub Total II 150,000

III PERALATAN

Sub Total III 0

Biaya Langsung (Sub Total I s/d III) 154,418


IV OVER HEAD DAN KEUNTUNGAN ( 10 % dari Biaya Langsung ) 15,442
V HARGA SATUAN PEKERJAAN (Rp/m´) 169,860
VI HARGA SATUAN PEKERJAAN (Rp/m') 169,800
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : K.02
Jenis Pekerjaan : Dowel Bar dia. 25, L=1m
Harga Satuan : Rp. 67,600
Satuan : buah

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA

1. Mandor org/hari 0.0094 57,500 541


2. Tukang Besi org/hari 0.0188 57,500 1,081
3. Pekerja org/hari 0.0938 42,500 3,987

Sub Total I 5,608

II BAHAN

1. Besi Ulir dia. 25 mm kg 3.8304 12,500 47,879


2. Pipa PVC dia. 1" m 1.0000 8,000 8,000

Sub Total II 55,879

III PERALATAN

Sub Total III 0

Biaya Langsung (Sub Total I s/d III) 61,487


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 6,149
V HARGA SATUAN PEKERJAAN (Rp/m') 67,636
VI HARGA SATUAN PEKERJAAN (Rp/m') 67,600
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : K.03
Jenis Pekerjaan : Anchor rod D 25mm L-2,00m
Harga Satuan : Rp. 141,600
Satuan : m'

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA

1. Mandor org/hari 0.0156 57,500 897


2. Tukang Batu org/hari 0.0391 57,500 2,248
3. Pekerja org/hari 0.1563 42,500 6,643

Sub Total I 9,788

II BAHAN

1. Cross Bit dia. 30 mm buah 0.0029 13,400 39


2. Steel, Taper Rod, dia.25 mm buah 0.0020 4,700 9
3. Besi Beton kg 6.6880 12,500 83,600
4. Semen PC (@50 kg) zak 0.0052 66,000 343
5. Pasir Beton m3 0.0005 300,000 150

Sub Total II 84,141

III PERALATAN

1. Drill Leg Air, 22 kg jam 0.2500 16,000 4,000


2. Air Compressor, 60 CFM jam 0.2500 123,200 30,800

Sub Total III 34,800

Biaya Langsung (Sub Total I s/d III) 128,729


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 12,873
V HARGA SATUAN PEKERJAAN (Rp/buah) 141,602
VI HARGA SATUAN PEKERJAAN (Rp/m') 141,600
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : K.03
Jenis Pekerjaan : Anchor rod D 50mm
Harga Satuan : Rp. 233,500
Satuan : m'

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA

1. Mandor org/hari 0.0156 57,500 897


2. Tukang Batu org/hari 0.0391 57,500 2,248
3. Pekerja org/hari 0.1563 42,500 6,643

Sub Total I 9,788

II BAHAN

1. Cross Bit dia. 56 mm buah 0.0029 13,400 39


2. Steel, Taper Rod, dia.50 mm buah 0.0020 4,700 9
3. Besi Beton kg 13.3760 12,500 167,200
4. Semen PC (@50 kg) zak 0.0052 66,000 343
5. Pasir Beton m3 0.0005 300,000 150

Sub Total II 167,741

III PERALATAN

1. Drill Leg Air, 22 kg jam 0.2500 16,000 4,000


2. Air Compressor, 60 CFM jam 0.2500 123,200 30,800

Sub Total III 34,800

Biaya Langsung (Sub Total I s/d III) 212,329


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 21,233
V HARGA SATUAN PEKERJAAN (Rp/buah) 233,562
VI HARGA SATUAN PEKERJAAN (Rp/m') 233,500
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : K.04
Jenis Pekerjaan : Handrail, Galvanis Pipe dia. 3” (termasuk cat)
Harga Satuan : Rp. 182,300
Satuan : m´

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA

1. Mandor org/hari 0.0267 57,500 1,535


2. Tukang Besi org/hari 0.7333 57,500 42,165
3. Pekerja org/hari 0.6000 42,500 25,500

Sub Total I 69,200

II BAHAN

1. Pipa Galvanis 3" m 1.1000 73,333 80,667


2. Meni kg 0.0752 18,000 1,354
3. Cat kg 0.1504 34,000 5,114
4. Thinner A ltr 0.0200 15,000 300
5. Elektroda kg 0.0620 35,000 2,170

Sub Total II 89,604

III PERALATAN

1. ARC Welder,250 A jam 0.3000 23,200 6,960

Sub Total III 6,960.00

Biaya Langsung (Sub Total I s/d III) 165,764


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 16,576
V HARGA SATUAN PEKERJAAN (Rp/m´) 182,340
VI HARGA SATUAN PEKERJAAN (Rp/m') 182,300
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : K.05
Jenis Pekerjaan : Pipa PVC Perforated dia. 6”
Harga Satuan : Rp. 181,000
Satuan : m´

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA

1. Mandor org/hari 0.0050 57,500 288


2. Pekerja org/hari 0.0825 42,500 3,506

Sub Total I 3,794

II BAHAN

1. Pipa PVC dia 6 " m 1.0000 160,833 160,833

Sub Total II 160,833

III PERALATAN

Sub Total III 0

Biaya Langsung (Sub Total I s/d III) 164,627


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 16,463
V HARGA SATUAN PEKERJAAN (Rp/m´) 181,090
VI HARGA SATUAN PEKERJAAN (Rp/m') 181,000
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : K.06
Jenis Pekerjaan : Besi Plat
Harga Satuan : Rp. 15,814,800
Satuan : ton

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA

1. Mandor org/hari 0.0267 57,500 1,535


2. Tukang Besi org/hari 0.7333 57,500 42,165
3. Pekerja org/hari 0.6000 42,500 25,500

Sub Total I 69,200

II BAHAN

1. Besi Plat ton 1.1000 13,000,000 14,300,000


2. Elektroda kg 0.0930 35,000 3,255

Sub Total II 14,303,255

III PERALATAN

1. ARC Welder,250 A jam 0.2000 23,200 4,640

Sub Total III 4,640

Biaya Langsung (Sub Total I s/d III) 14,377,095


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 1,437,710
V HARGA SATUAN PEKERJAAN (Rp/ton) 15,814,805
VI HARGA SATUAN PEKERJAAN (Rp/ton) 15,814,800
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : K.06
Jenis Pekerjaan : Besi Profil
Harga Satuan : Rp. 16,722,300
Satuan : ton

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA

1. Mandor org/hari 0.0267 57,500 1,535


2. Tukang Besi org/hari 0.7333 57,500 42,165
3. Pekerja org/hari 0.6000 42,500 25,500

Sub Total I 69,200

II BAHAN

1. Besi Profil ton 1.1000 13,750,000 15,125,000


2. Elektroda kg 0.0930 35,000 3,255

Sub Total II 15,128,255

III PERALATAN

1. ARC Welder,250 A jam 0.2000 23,200 4,640

Sub Total III 4,640

Biaya Langsung (Sub Total I s/d III) 15,202,095


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 1,520,210
V HARGA SATUAN PEKERJAAN (Rp/ton) 16,722,305
VI HARGA SATUAN PEKERJAAN (Rp/ton) 16,722,300
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : K.08
Jenis Pekerjaan : Baja WF 150 x 150
Harga Satuan : Rp. 26,100
Satuan : kg

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA

1. Mandor org/hari 0.0016 57,500 92


2. Tukang Besi org/hari 0.0039 57,500 224
3. Pekerja org/hari 0.0171 42,500 727

Sub Total I 1,043

II BAHAN

1. Baja WF 150 x 150 kg 1.1000 14,500 15,950


2. Elektroda kg 0.0620 35,000 2,170

Sub Total II 18,120

III PERALATAN

1. ARC Welder,250 A jam 0.2000 23,200 4,640

Sub Total III 4,640

Biaya Langsung (Sub Total I s/d III) 23,803


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 2,380
V HARGA SATUAN PEKERJAAN (Rp/kg) 26,183
VI HARGA SATUAN PEKERJAAN (Rp/kg) 26,100
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : K.09
Jenis Pekerjaan : Dowel Bar dia. 25, L= 1 m
Harga Satuan : Rp. 52,100
Satuan : buah

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA

1. Mandor org/hari 0.0094 57,500 541


2. Tukang Besi org/hari 0.0188 57,500 1,081
3. Pekerja org/hari 0.0938 42,500 3,987

Sub Total I 5,608

II BAHAN

1. Besi Beton kg 3.9800 10,500 41,790

Sub Total II 41,790

III PERALATAN

Sub Total III 0

Biaya Langsung (Sub Total I s/d III) 47,398


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 4,740
V HARGA SATUAN PEKERJAAN (Rp/buah) 52,138
VI HARGA SATUAN PEKERJAAN (Rp/buah) 52,100
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : K.10
Jenis Pekerjaan : Buis Beton d 70 cm, pj. 1,00 m
Harga Satuan : Rp. 236,500
Satuan : buah

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA

1 Pekerja org/hr 0.380 42,500 16,150


2 Tukang batu org/hr 0.190 57,500 10,925
3 Kepala tukang batu org/hr 0.019 57,500 1,093
4 Mandor org/hr 0.019 57,500 1,093
Sub Total I 29,260

II BAHAN

1. Buis Beton d 70 cm, pj.0,5 m bh 1.000 150,000 150,000


2 Batu bata m3 0.550 11,400 6,270
3 Semen PC kg 10.300 1,320 13,596
4 Pasir Pasang m3 0.061 147,500 8,998
5 Pasir uruk m3 0.069 100,000 6,900

Sub Total II 185,764

III PERALATAN

Sub Total III 0

Biaya Langsung (Sub Total I s/d III) 215,024


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 21,502
V HARGA SATUAN PEKERJAAN (Rp/buah) 236,526
VI HARGA SATUAN PEKERJAAN (Rp/buah) 236,500
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : K.11
Jenis Pekerjaan : Tangga (Pipa Galvanis) dia. 16 mm
Harga Satuan : Rp. 104,000
Satuan : m'

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA

1. Mandor org/hari 0.0267 57,500 1,535


2. Tukang Besi org/hari 0.7333 57,500 42,165
3. Pekerja org/hari 0.6000 42,500 25,500

Sub Total I 69,200

II BAHAN

1. Tangga (Pipa Galvanis) dia. 16 mm m 1.1000 15,663 17,229


2. Cat Meni kg 0.0752 18,000 1,354
3. Elektroda kg 0.0620 35,000 2,170

Sub Total II 20,753

III PERALATAN

1. ARC Welder, 250 A jam 0.2000 23,200 4,640

Sub Total III 4,640

Biaya Langsung (Sub Total I s/d III) 94,593


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 9,459
V HARGA SATUAN PEKERJAAN (Rp/m') 104,052
VI HARGA SATUAN PEKERJAAN (Rp/m') 104,000
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : K.12
Jenis Pekerjaan : Pintu Plat Besi t = 5 mm (0,8 x 2 m)
Harga Satuan : Rp. 10,463,000
Satuan : buah

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA

1. Mandor org/hari 0.0267 57,500 1,535


2. Tukang Besi org/hari 0.7333 57,500 42,165
3. Pekerja org/hari 0.6000 42,500 25,500

Sub Total I 69,200

II BAHAN

1. Pintu Plat Besi t = 5 mm buah 10.0000 936,000 9,360,000


2. Meni kg 0.6840 18,000 12,312
3. Cat kg 1.3680 34,000 46,512
4. Elektroda kg 0.5638 35,000 19,733

Sub Total II 9,438,557

III PERALATAN

1. ARC Welder, 250 A jam 0.2000 23,200 4,640

Sub Total III 4,640

Biaya Langsung (Sub Total I s/d III) 9,512,397


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 951,240
V HARGA SATUAN PEKERJAAN (Rp/buah) 10,463,637
VI HARGA SATUAN PEKERJAAN (Rp/buah) 10,463,000
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : K.13
Jenis Pekerjaan : Buis Beton dia.100 L=1,00 m
Harga Satuan : Rp. 230,200
Satuan : buah

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA

1 Pekerja org/hr 0.3800 42,500 16,150


2 Tukang batu org/hr 0.1900 57,500 10,925
3 Kepala tukang batu org/hr 0.0190 57,500 1,093
4 Mandor org/hr 0.0190 57,500 1,093

Sub Total I 29,260

II BAHAN

1. Buis Beton dia.100 L=50 m bh 1.0000 150,000 150,000


2 Batu bata m3 0.550 11,400 6,270
3 Semen PC kg 10.300 1,320 13,596
4 Pasir Pasang m3 0.061 0 0
5 Pasir uruk m3 0.069 147,500 10,178

Sub Total II 180,044

III PERALATAN

Sub Total III 0

Biaya Langsung (Sub Total I s/d III) 209,304


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 20,930
V HARGA SATUAN PEKERJAAN (Rp/buah) 230,234
VI HARGA SATUAN PEKERJAAN (Rp/buah) 230,200
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : K.14
Jenis Pekerjaan : Geotextile, t=2 mm
Harga Satuan : Rp 27,800
Satuan : m2

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA

1. Mandor org/hari 0.0182 57,500 1,048


2. Pekerja org/hari 0.1003 42,500 4,263

Sub Total I 5,311

II BAHAN

1. Geotextile non Woven t=2mm m2 1.0000 20,000 20,000

Sub Total II 20,000

III PERALATAN

Sub Total III 0

Biaya Langsung (Sub Total I s/d III) 25,311


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 2,531
V HARGA SATUAN PEKERJAAN (Rp/buah) 27,842
VI HARGA SATUAN PEKERJAAN (Rp/m') 27,800
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : K.15
Jenis Pekerjaan : Weep Hole Pipa PVC dia. 2"
Harga Satuan : Rp 50,500
Satuan : m

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA

1 Pekerja org/hr 0.0540 42,500 2,295


2 Tukang batu org/hr 0.0900 57,500 5,175
3 Kepala tukang batu org/hr 0.0090 57,500 518
4 Mandor org/hr 0.0027 57,500 155
Sub Total I 8,143

II BAHAN

1 Pipa PVC Tipe C Dia 2" m' 1.2000 13,667 16,400


2 Ijuk kg 0.7704 7,000 5,393
3 Koral Beton Split m3 0.0800 200,000 16,000

Sub Total II 37,793

III PERALATAN

Sub Total III 0

Biaya Langsung (Sub Total I s/d III) 45,935


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 4,594
V JUMLAH 50,529
VI HARGA SATUAN PEKERJAAN (Rp/m') 50,500
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : K.16
Jenis Pekerjaan : Pancang Dolken
Harga Satuan : Rp 114,100
Satuan : m'

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA

1. Mandor org/hari 0.0430 57,500 2,473


2. Kepala Tukang org/hari 0.0040 57,500 230
3. Tukang Kayu org/hari 0.0400 57,500 2,300
4. Pekerja org/hari 1.5000 42,500 63,750

Sub Total I 68,753

II BAHAN

1 Dolken Kayu Gelam Dia 15-20 Cm/ 400c btg 1.0000 40,000 40,000
Sub Total II 40,000

III PERALATAN

Sub Total III 0

Biaya Langsung (Sub Total I s/d III) 103,750


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 10,375
V JUMLAH 114,125
VI HARGA SATUAN PEKERJAAN (Rp/m') 114,100
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : K.19
Jenis Pekerjaan : Pengadaan dan Pemasangan Fasilitas Air Conditioner
Harga Satuan : Rp 4,537,500
Satuan : bh

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA

Sub Total I 0

II BAHAN

1 Pengadaan Air Conditioner 3/4 PK bh 1.0000 3,750,000.00 3,750,000

Sub Total II 3,750,000

III PERALATAN

1. Biaya Instalasi dan Pemasangan % 10.0000 375,000

Sub Total III 375,000

Biaya Langsung (Sub Total I s/d III) 4,125,000


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 412,500
V JUMLAH 4,537,500
VI HARGA SATUAN PEKERJAAN (Rp/m') 4,537,500
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : K.20
Jenis Pekerjaan : Pengadaan dan Pemasangan Fasilitas Closet Duduk
Harga Satuan : Rp 1,444,000
Satuan : bh

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I TENAGA
1 Pekerja org/hr 3.3000 42,500 140,250
2 Tukang batu org/hr 1.1000 57,500 63,250
3 Kepala tukang batu org/hr 0.0010 57,500 58
4 Mandor org/hr 0.1600 57,500 9,200

Sub Total I 212,758

II BAHAN

1 Closet duduk bh 1.0000 1,100,000.00 1,100,000

Sub Total II 1,100,000

III PERALATAN

Sub Total III 0

Biaya Langsung (Sub Total I s/d III) 1,312,758


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 131,276
V JUMLAH 1,444,033
VI HARGA SATUAN PEKERJAAN (Rp/m') 1,444,000
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)
No. : K.21
Jenis Pekerjaan : Joint Filler t=1 cm
Harga Satuan : Rp 153,400
Satuan : m2

Harga Satuan Jumlah


No. Keterangan Satuan Volume
(Rp) (Rp)

I TENAGA

1. Mandor org/hari 0.0300 57,500 1,725


2. Pekerja Biasa org/hari 0.3000 42,500 12,750

Sub Total I 14,475

II BAHAN

1. Rubber Joint Filler (t=1 cm) m2 1.0000 125,000 125,000

Sub Total II 125,000

III PERALATAN
0

Sub Total III 0

Biaya Langsung (Sub Total I s/d III) 139,475.00


IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 13,947.50
V JUMLAH 153,422.50
VI HARGA SATUAN PEKERJAAN (Rp/m') 153,400.00
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : L.01
Jenis Pekerjaan : Instalasi Jaringan Tegangan Menengah 20 KV/220 V 3 phasa 4 Conductor ;
Transformator 50 KVA 3 Phasa 4 Conductor
Harga Satuan : Rp 246,477,700
Satuan : Ls

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

I Penarikan Jaringan 20 KV
1 Conductor AAA C 70 mm2 M 330.00 40,500.00 13,365,000
2 GSW 70 mm M 110.00 35,000.00 3,850,000
3 Concrete Pole 11 m/200daN termasuk Insulator dan Accessories Set 3.00 3,540,000 10,620,000

SUB TOTAL I 27,835,000


II Pemasasangan Transformator 50 KVA 3 phasa 20 KV/ 220 V
1 Transformator 50 KVA 3 phasa 50 KVA 20 KV/ 220 V Set 1.00 56,000,000 56,000,000
2 Concrete Pole 12 m/200 daN - E termasuk Accessories Bh 2.00 4,250,000 8,500,000
3 Fuse Cut out 20 KV, 100 A lengkap fuse link Bh 3.00 1,280,000 3,840,000
4 Lightning Arrester 20 KV, 10 KA Bh 3.00 890,000 2,670,000
5 Cross Arm UNP 100x50x6x2000mm Galvanis Bh 2.00 300,000 600,000
6 Kabel NYY 1 x 150 mm2 M 40.00 176,250 7,050,000
7 Kabel NYY 1 x 70 mm2 M 120.00 87,750 10,530,000
8 Kabel Schoen CU 70 mm2 Bh 16.00 9,000 144,000
9 Kabel Schoen CU 150 mm2 Bh 3.00 11,000 33,000
10 Rak Trafo (Breaket) 3 Pole Komplit Unit 1.00 550,000 550,000
11 Papan Jati/Kulim 50x200x220 u/dudukan pengaman Lbr 3.00 725,000 2,175,000
12 Pondasi Trafo Tiang Portal ( Cor Beton 1:2:3 Besi dia 12 mm Ls 1.00 2,859,700 2,859,700
13 Schoor untuk pengaman trafo Komplit Set 1.00 350,000 350,000
14 Grounding Arrester & Body dan Nol Trafo Set 3.00 900,000 2,700,000
15 Pipa Galvanis 3 " 6 m Bh 1.00 318,000 318,000
16 Bochten 3" Galvanis Bh 12.00 51,000 612,000
17 Flans u/pasang pipa ke Panel Bh 3.00 40,000 120,000
18 Klem/Band Pole ( u/ satu set trafo tiang portal ) Set 1.00 9,000 9,000
19 Copper Conductor 35 mm2 kg 3.00 15,000 45,000
20 Joint Sleeve 70 mm2 Bh 8.00 30,000 240,000
21 Connector CU AL 35-70 mm2 Bh 12.00 60,000 720,000
22 Plat tanda bahaya Bh 1.00 170,000 170,000
23 Box Lemari Bagi Moun Plat 1x1.25x0.35 M 3 phasa 4 Rute Komplit Set 1.00 14,500,000 14,500,000

SUB TOTAL II 114,735,700


III Beaya Penyambungan dan Pengetesan Comissioning sampai dengan Sertifikat
Layak Operasi (SLO)
1 Biaya Penyambungan LS 1.00 40,000,000 40,000,000
2 Langganan Bulanan selama Tahun Anggaran Berjalan dgn beban minima Bl 10.00 2,400,000 24,000,000
3 Biaya Pengetesan Commisioning sampai dengan Sertifikasi layak LS 1.00 17,500,000 17,500,000
operasional (SLO)

SUB TOTAL III 81,500,000

Biaya Langsung 224,070,700

IV OVER HEAD DAN KEUNTUNGAN (10 % dari Biaya Langsung) 22,407,070

V JUMLAH 246,477,770

VI HARGA SATUAN PEKERJAAN (Rp/m') 246,477,700


ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : L.02
Jenis Pekerjaan : Instalasi Penerangan Gedung
Harga Satuan : Rp 0
Satuan : Ls

Harga Satuan Jumlah


No. Keterangan Satuan Volume
(Rp) (Rp)

I Instalasi Penerangan Gedung

a. Kantor Proyek Ls 1.0000 0


b. Rumah Dinas 60 Ls 1.0000 0
c. Rumah Dinas 45 Ls 1.0000 0
d. Klinik Umum Ls 1.0000 0
e. Gardu Pandang Ls 1.0000 0
f. Pos Jaga Ls 1.0000 0
g. Mushola Ls 1.0000 0
h. Rumah Genset Ls 1.0000 0
i. Gudang Material Ls 1.0000 0
j. Bengkel Peralatan Ls 1.0000 0
k. Rumah Jaga Ls 1.0000 0

Sub Total III 0

Jumlah 0
Biaya umum dan keuntungan 10 % 0
Jumlah (termasuk biaya umum dan keuntungan) sebelum PPN 0
Jumlah Dibulatkan 0
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : L.03
Jenis Pekerjaan : Instalasi Penerangan Jalan dan Puncak Bendungan
Harga Satuan : Rp 386,685,800
Satuan : Ls

Harga Satuan Jumlah


No. Keterangan Satuan Volume
(Rp) (Rp)

I Instalasi Penerangan Jalan dan Puncak Bendungan

a. Panel Lighting set 3.000 12,000,000 36,000,000


b. Tiang Lampu PJU one lamp (Hexagon) ea 51.000 2,050,000 104,550,000
c. Mercury lamp, c/w Balast, capasitor, d ea 51.000 1,100,000 56,100,000
d. MCB 1P, 220V, 4 A, 6kA ea 51.000 50000 2,550,000
e. Terminal Blok 6pole set 51.000 125000 6,375,000
f. Kabel NYY 3x2.5 mm2 set 51.000 100000 5,100,000
g. Delivery Cost to Site Project lot 1.000 40000000 40,000,000
h. Kabel LVTC 2x16 mm2 m 2244.000 13200 29,620,800
i. Installasi kabel m 2244.000 2,200 4,936,800
j. Intallasi Tiang dan Lampu set 51.000 1,175,000 59,925,000

Sub Total III 345,157,600

Jumlah 351,532,600
Biaya umum dan keuntungan 10 % 35,153,260
Jumlah (termasuk biaya umum dan keuntungan) sebelum PPN 386,685,860
Jumlah Dibulatkan 386,685,800
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : M.01
Jenis Pekerjaan : Kantor Utama Bendungan (420 m²)
Harga Satuan : Rp. 827,476,100
Satuan : LS

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

1. Pembersihan Lahan (ref.C.01) m2 420.00 13,900 5,838,000


3. Pekerjaan Pondasi :
- Galian tanah pondasi (ref. C.03) m3 184.80 29,500 5,451,600
- Pasangan Batu kosong Stampeng (ref. E05) m3 58.21 282,900 16,467,609
- Pasangan Batu Kali (1PC : 3Ps) (ref. E01) m3 93.00 706,300 65,685,900
- Beton K-175 (ref.D.04) m3 17.60 1,033,000 18,180,800
- Pembesian (ref. D.06) Ton 1.936 15,378 29,772
- Bekisting (ref.D.07) m2 111.00 155,300 17,238,300
- Timbunan Tanah (ref.C.12) m3 105.00 20,200 2,121,000
4. Pekerjan Dinding :
- Pasangan Batu Bata 1PC : 4Ps (ref. E03) m3 91.26 216,000 19,712,160
- Beton K-175 (ref.D.04) m3 6.54 1,033,000 6,759,952
- Bekisting (ref.D.07) m2 91.22 155,300 14,166,466
- Pembesian (ref. D.06) Ton 0.564 15,378 8,673
- Plesteran (1PC : 3 PS) (ref.E.04) m2 1,035.00 42,000 43,470,000
- Pengecatan Tembok (ref.J.12) m2 1,967.00 52,300 102,874,100
- Keramik Lantai KW I 30 x 30 cm (ref. J15A) m2 436.00 159,000 69,324,000
- Keramik dinding Motif KW I Kamar Mandi dan Dapur (ref. J 15 B) m2 115.60 154,700 17,883,320
- Keramik Lantai Kamar mandi KW I 30 x 30 cm (ref. J15A) m2 52.00 159,000 8,268,000
5. Pekerjaan Atap :
- Kuda-kuda Kayu Kruing 8/15 (ref.J.01B) m3 2.494 9,301,900 23,198,939
- Pemasangan Gording dan jurai Kayu Kruing 8/15 (ref.J.01B) m3 1.354 9,174,100 12,421,731
- Pasang Usuk (ref.J.01C) m2 540.00 104,800 56,592,000
- Atap Asbes Gelombang Kecil (ref.J.04) m2 550.00 41,200 22,660,000
- Bubungan asbes gelombang (ref. J05) m' 58.80 74,300 4,368,840
- Lisplang kayu kamper m' 91.60 110,000 10,076,000
- Pengecatan Lisplang m2 27.48 32,000 879,360

5. Plafon Eternit Rangka Kayu Meranti m2 487.20 242,000 117,902,400


6. Pekerjaan Pintu dan Jendela :
- Kusen Pintu Almunium 4" Type 1 bh 6.00 1,647,200 9,883,200
- Kusen Pintu Almunium 4" Type 2 bh 5.00 1,277,600 6,388,000
- Kusen Jendela 4" bh 12.00 1,714,400 20,572,800
- Kusen Almunium 4" untuk KM bh 5.00 860,000 4,300,000
- Daun Pintu Type 1 Komplit Engsel Assessouris lain dan kunci Set 6.00 4,800,000 28,800,000
Kaca 6 mm dark blue termasuk bouven list
- Daun Pintu Type 2 Komplit Engsel Assessouris lain dan kunci Set 5.00 2,850,000 14,250,000
Kaca 6 mm dark blue termasuk bouven list
- Daun Jendela Almunium Komplit Engsel Assessouris lain Set 12.00 2,780,000 33,360,000
kaca 5 mm dark blue termasuk bouven list
- Daun Pintu Komplit untuk KM Set 5.00 780,000 3,900,000
7. Pekerjaan Lain-lain :
a. Wastafel (ref.J.22) buah 2.00 522,000 1,044,000
b. Kloset Duduk KW I (ref.K20) buah 3.00 1,444,000 4,332,000
c. Kran Air buah 9.00 24,300 218,700
d. Urinal buah 2.00 1,375,000 2,750,000
e. Kitchen Zink Komplit kran dan Dudukan Set 1.00 700,000 700,000
f. Affur Kamarmandi Bh 3.00 95,000 285,000
g. Affur Penguras Bak KM bh 3.00 55,000 165,000
h. Pipa saluran air bersih 3/4" m 46.00 8,500 391,000
i. Pipa Sanitasi 1.5" m 22.00 45,000 990,000
j. Pipa Sanitasi 3" m 20.00 92,000 1,840,000
k. Pipa Sanitasi 4" m 18.00 140,000 2,520,000
l. Septitank untuk 15 Personil komplit Peresapan Set 1.00 5,500,000 5,500,000
m. Pengadaan dan Pemasangan Fasilitas Air Conditioner Unit 5.00 4,537,500 22,687,500
n. Kaca Cermin/Miror 5 mm untuk kamar mandi termasuk assesouris m2 2.40 425,000 1,020,000

Biaya sudah termasuk Over Head Profit 10 % 827,476,122


Pembulatan 827,476,100
ANALISA HARGA SATUAN POKOK KEGIATAN
(AHSPK)

No. : A.02
Jenis Pekerjaan : Kantor Lapangan (200 m²)
Harga Satuan : Rp. 341,209,100
Satuan : LS

Harga Satuan Jumlah Harga


No. Item Pekerjaan Satuan Volume
(Rp) (Rp)

1. Pembersihan Lahan (ref.C.01) m2 220.000 13,900.00 3,058,000.00


3. Pekerjaan Pondasi :

- Pasangan Batu Kali (1PC : 3Ps) m3 6.640 706,300.00 4,689,832.00


- Beton K-175 (ref.D.04) m3 2.760 1,033,000.00 2,851,080.00

- Bekisting (ref.D.07) m2 1.440 155,300.00 223,632.00


- Timbunan Tanah (ref.C.15) m3 149.870 20,200.00 3,027,374.00
4. Pekerjan Dinding :
- Pasangan Batu Bata 1PC : 4Ps (ref.E03 ) m3 40.000 216,000.00 8,640,000.00
- Beton K-175 (ref.D.04) m3 2.100 1,033,000.00 2,169,300.00
- Bekisting (ref.D.07) m2 1.092 155,300.00 169,587.60

- Plesteran (1PC : 3 PS) (ref.E.04) m2 938.000 42,000.00 39,396,000.00


- Pengecatan Tembok (J.12) m2 938.000 52,300.00 49,057,400.00
- Keramik 30 x 30 cm (J.15) m2 200.000 159,000.00 31,800,000.00

5. Pekerjaan Atap :
- Kuda-kuda WF 150.150 (ref.J.19) kg 2,657.210 40,300.00 107,085,563.00
- Gording 8/12 (ref.J.10) m3 1.212 9,174,100.00 11,119,009.20
- Atap Asbes Gelombang Kecil (ref.J.04 ) m2 122.470 41,200.00 5,045,764.00
6 Plafon Eternit (ref.J.21) m2 264.000 138,100.00 36,458,400.00
7 Pekerjaan Pintu dan Jendela :
- Kusen Pintu 1 (ref.J.06) m3 0.555 10,035,500.00 5,569,702.50
- Kusen Pintu 2 (ref.J.06) m3 0.042 10,035,500.00 421,491.00
- Kusen Pintu 3 (ref.J.06) m3 0.116 10,035,500.00 1,164,118.00
- Kusen Jendela 1 (ref.J.06) m3 1.050 10,035,500.00 10,537,275.00
- Kusen Jendela 2 (ref.J.06) m3 0.022 10,035,500.00 220,781.00
- Daun Pintu Teakwood (Pintu 1) (ref.J.07) m2 18.900 615,200.00 11,627,280.00
- Kaca Rayban Polos Tebal 5 mm (ref.J.11) m2 2.520 120,000.00 302,400.00
8 Pekerjaan Lain-lain :
- Wastafel (ref.J.22) buah 2.000 522,000.00 1,044,000.00
- Kloset Jongkok (ref.J17) buah 2.000 412,600.00 825,200.00
- Kran Air (ref.J.16) buah 4.000 24,300.00 97,200.00
- Bak Mandi (0,60 x 0,60 x 0,80) (ref .J18 ) buah 1.000 1,088,000.00 1,088,000.00
- Grendel (ref.J.24) buah 6.000 22,600.00 135,600.00
- Engsel (ref.J.25) stel 21.000 29,200.00 613,200.00
'- Kunci Tanam Besar 2x Putar buah 14.000 198,000.00 2,772,000.00

Biaya sudah termasuk Over Head Profit 10 % 341,209,189


Pembulatan 341,209,100