Harga Jumlah
No URAIAN PEKERJAAN Volume satuan
Satuan Harga
I PEKERJAAN PONDASI
1 Direlasi keet/gudang/los kerja 1.00 unit 500,000 Rp. 500,000
2 Uitzet/pasang bouwplank 18.00 m' 30,000 Rp. 540,000
3 Mobilisasi / Demobilisasi Ls 2,250,000 Rp. 2,250,000
1 Galian tanah 78.71 m3 30,000 Rp. 2,361,150
2 Urugan tanah kembali 53.27 m3 20,000 Rp. 1,065,300
3 Pasir urug tebal 5 cm 2.65 m3 125,000 Rp. 331,250
4 Lt. kerja (beton mutu Bo) t=5 cm 0.72 m3 600,000 Rp. 432,000
5 Pasangan batu kali (di bwh sloof) 25.44 m3 450,000 Rp. 11,448,000
Total Pekerjaan Fondasi 160.78 m3 - Rp. 18,927,700
II PEKERJAAN BETON
1 Pondasi tapak (1,2x1,2m) 3.60 m3 3,350,000 Rp. 12,060,000
2 Pekerjaan Sloof 20/40 4.24 m3 3,350,000 Rp. 14,204,000
3 Pekerjaan Sloof 15/30 0.45 m3 3,350,000 Rp. 1,507,500
4 Balok B1 25/40 5.30 m3 3,450,000 Rp. 18,285,000
5 Balok B2 20/40 0.36 m3 3,450,000 Rp. 1,242,000
6 Balok B5 15/15 (Ringbalk) 1.14 m3 2,250,000 Rp. 2,565,000
7 Kolom K2 (30/30) 3.83 m3 3,800,000 Rp. 14,535,000
8 Kolom K3 15/30 0.28 m3 3,600,000 Rp. 1,004,400
9 Kolom KP 15/15 0.98 m3 2,250,000 Rp. 2,197,125
10 Plat t=12cm 7.80 m3 3,225,000 Rp. 25,155,000
11 Tangga Beton 1.19 m3 4,200,000 Rp. 5,003,460
Total Pekerjaan Beton 29.16 m3 Rp. 97,758,485
III PEKERJAAN DINDING
1 Pasangan bata (1pc:5 ps) 249.60 m2 68,000 Rp. 16,972,800
2 Sopi sopi bata (1 pc :5 ps) 11.00 m2 72,000 Rp. 792,000
3 Plester dinding bata (1pc:5ps)+acian 268.80 m2 32,500 Rp. 8,736,000
Total Pekerjaan Dinding 529.40 m3 Rp. 26,500,800
IV PEKERJAAN LANTAI
1 Pasangan keramik lantai 30x30 140.00 m2 72,000 Rp. 10,080,000
2 Pasangan keramik lt kamar mandi 20x20 6.00 m2 74,000 Rp. 444,000
Pasangan keramik dinding kamar mandi 20x20 26.00 m2 76,000 Rp. 1,976,000
3 Border keramik 10x20 (KM) 1.30 m2 148,000 Rp. 192,400
4 Border keramik teras 10x20 1.22 m2 148,000 Rp. 180,560
5 Urugan Pasir padat t.5 cm 3.50 m3 125,000 Rp. 437,500
Harga Jumlah
No URAIAN PEKERJAAN Volume satuan
Satuan Harga
I PEKERJAAN PONDASI
1 Direlasi keet/gudang/los kerja 1.00 unit 600,000 Rp. 600,000
2 Uitzet/pasang bouwplank 16.00 m' 30,000 Rp. 480,000
3 Mobilisasi / Demobilisasi ls 2,500,000 Rp. 2,500,000
4 Galian Tanah 128.78 m3 30,000 Rp. 3,863,400
5 Urugan tanah kembali 104.54 m3 20,000 Rp. 2,090,800
6 Pasir Urug tebal 5 cm 2.53 m3 125,000 Rp. 316,250
6 Lantai kerja (beton mutu Bo) t=5 cm 1.13 m3 600,000 Rp. 675,000
7 Pasangan batu kali (di bwh sloof) 24.24 m3 450,000 Rp. 10,908,000
Total Pekerjaan Fondasi 278.22 m3 Rp. 21,433,450
II PEKERJAAN BETON
1 Pondasi tapak (1,5x1,5m) 3.38 m3 3,350,000 Rp. 11,306,250
2 Pondasi tapak (1,5x2,3m) 1.13 m3 3,350,000 Rp. 3,768,750
3 Pekerjaan Sloof 20/40 4.04 m3 3,350,000 Rp. 13,534,000
4 Pekerjaan Sloof 15/30 0.20 m3 3,350,000 Rp. 678,375
5 Balok B1 25/40 10.10 m3 3,450,000 Rp. 34,845,000
6 Balok B2 20/40 0.72 m3 3,450,000 Rp. 2,484,000
7 Balok B4 15/30 0.14 m3 3,350,000 Rp. 452,250
8 Balok B5 15/15 (Ringbalk) 0.83 m3 2,250,000 Rp. 1,873,125
9 Kolom K1 (35/35) 5.51 m3 3,800,000 Rp. 20,947,500
10 Kolom K2 (30/30) 1.80 m3 3,800,000 Rp. 6,840,000
11 Kolom K3 15/30 0.28 m3 3,600,000 Rp. 1,004,400
12 Kolom KP 15/15 0.42 m3 2,250,000 Rp. 941,625
13 Plat t=12cm 14.04 m3 3,225,000 Rp. 45,279,000
14 Tangga Beton 2.38 m3 4,200,000 Rp. 10,006,920
Total Pekerjaan Beton 44.96 m3 Rp. 153,961,195
III PEKERJAAN DINDING
1 Pasangan bata (1pc:5 ps) 362.70 m2 68,000 Rp. 24,663,600
2 Sopi sopi bata (1 pc :5 ps) 22.00 m2 72,000 Rp. 1,584,000
3 Plester dinding bata (1pc:5ps)+acian 362.70 m2 32,500 Rp. 11,787,750
Total Pekerjaan Dinding Rp. 38,035,350
IV PEKERJAAN LANTAI
1 Pasangan keramik lantai 30x30 189.00 m2 72,000 Rp. 13,608,000
2 Pasangan keramik lt kamar mandi 20x20 9.00 m2 74,000 Rp. 666,000
Pasangan keramik dinding kamar mandi 20x20 39.00 m2 76,000 Rp. 2,964,000
3 Border keramik 10x20 3.90 m2 148,000 Rp. 577,200
4 Border keramik teras 10x20 1.12 m2 148,000 Rp. 165,760
5 Urugan Pasir padat t.5 cm 3.15 m3 125,000 Rp. 393,750
Total Pekerjaan Lantai Rp. 18,374,710
V
V PEKERJAAN
PEKERJAAN KUSEN,PINTU,JENDELA,
KUSEN,PINTU,JENDELA, BOVENLICH,
BOVENLICH, KACA
KACA
1 Jendela Muka lt.2+kaca (kusen alu 4/10) 1.00 unit 9,000,000 Rp. 9,000,000
2 Jendela Muka lt.3+kaca (kusen alu 4/10) 1.00 unit 9,000,000 Rp. 9,000,000
3 Pintu toilet+daun 3.00 unit 400,000 Rp. 1,200,000
Total Pekerjaan Kusen, Pintu, Jendela, Bovenlich, Kaca Rp. 19,200,000
VI PEKERJAAN ATAP & PLAFOND
1 Balok kayu uk. 8/12 Meranti 0.22 m3 3,600,000 Rp. 777,600
2 Kaso 5/7 0.19 m3 3,700,000 Rp. 699,300
3 papan lisplank 3/20,kayu Meranti 9.00 m' 95,000 Rp. 855,000
4 Asbes 63.00 m2 65,000 Rp. 4,095,000
5 Asbes nok 4.50 m' 70,000 Rp. 315,000
6 Plafond Gypsum 162.00 m2 65,000 Rp. 10,530,000
7 Lis profil Plafond Gypsum 111.00 m' 24,000 Rp. 2,664,000
8 Tripleks 4 mm plafond (Toilet) 9.00 m2 67,000 Rp. 603,000
9 List Plafond Kayu (toilet) 21.00 m' 20,000 Rp. 420,000
Total Pekerjaan Atap & Plafond Rp. 20,958,900
VII PEKERJAAN PENGECATAN
1 Cat dinding 362.70 m2 18,000 Rp. 6,528,600
2 Cat plafond 171.00 m2 19,000 Rp. 3,249,000
3 Cat List plafond 132.00 m' 12,000 Rp. 1,584,000
Total Pekerjaan Pengecatan Rp. 11,361,600
VIII PEKERJAAN INSTALASI AIR BERSIH & AIR KOTOR
1 Pipa PVC diameter 1/2" 2.00 m' 7,000 Rp. 14,000
Pipa PVC diameter 3/4" 23.00 m' 10,000 Rp. 230,000
2 Pipa PVC diameter 3'(air bekas) 22.50 m' 30,000 Rp. 675,000
3 Pipa PVC diameter 4'(dari kloset) 23.00 m' 50,000 Rp. 1,150,000
4 Septik tank + rembesan 1.00 unit 1,750,000 Rp. 1,750,000
5 Sumur Pantek 1.00 Ls 2,000,000 Rp. 2,000,000
6 Pompa LG250W 1.00 bh 2,000,000 Rp. 2,000,000
7 Bak kontrol 1.00 bh 280,000 Rp. 280,000
8 Biaya Penyambungan PAM Ls 2,000,000 Rp. 2,000,000
Total Pekerjaan Instalasi Air Bersih & Air Kotor Rp. 10,099,000
IX PEKERJAAN SANITAIR
1 Kloset jongkok merek Ex. KIA 3.00 bh 150,000 Rp. 450,000
2 Bak air fibre glass uk. 60x60x60 3.00 bh 200,000 Rp. 600,000
3 keran air merek SAN-EI 9.00 bh 100,000 Rp. 900,000
4 Roof Drain 2.00 bh 80,000 Rp. 160,000
5 Floor drain 3.00 bh 70,000 Rp. 210,000
Total Pekerjaan Sanitair Rp. 2,320,000
X PEKERJAAN LAIN-LAIN
1 Railing besi tangga+Void 10.70 m' 85,000 Rp. 909,500
2 Fin. Kolom depan 9.00 m2 175,000 Rp. 1,575,000
3 Folding Gate 1.00 ls 6,000,000 Rp. 6,000,000
4 Parkir, Koral sikat motif 27.00 m2 270,000 Rp. 7,290,000
Total Pekerjaan Lain-Lain Rp. 15,774,500
XI PEKERJAAN INSTALASI LISTRIK
1 Box MCB 2.00 bh 300,000 Rp. 600,000
2 Box meter 1.00 bh 500,000 Rp. 500,000
3 Titik lampu Termasuk Kabel NYM3x2.5 10.00 bh 170,000 Rp. 1,700,000
NYM 2x1.5 & Fitting+Inbow+Tee dus (Acessories)
4 Lampu tempel 2.00 bh 400,000 Rp. 800,000
5 Saklar dobel 4.00 bh 80,000 Rp. 320,000
6 Saklar Singel 4.00 bh 50,000 Rp. 200,000
7 Stop kontak 4.00 bh 50,000 Rp. 200,000
8 Biaya Penyambungan Daya Listrik Ls 2,500,000 Rp. 2,500,000
Total Pekerjaan Instalasi Listrik Rp. 6,820,000
Rekapitulasi RAB Ruko 3 Lantai :
I PEKERJAAN PERSIAPAN/ PONDASI Rp. 21,433,450
II PEKERJAAN BETON Rp. 153,961,195
III PEKERJAAN DINDING Rp. 38,035,350
IV PEKERJAAN LANTAI Rp. 18,374,710
V PEKERJAAN KUSEN,PINTU,JENDELA, BOVENLICH, KACA Rp. 19,200,000
VI PEKERJAAN ATAP & PLAFOND Rp. 20,958,900
VII PEKERJAAN PENGECATAN Rp. 11,361,600
VIII BIAYA PENYAMBUNGAN PAM ls Rp.2.000.000 Rp. 10,099,000
IX BIAYA PENYAMBUNGAN DAYA LISTRIK ls Rp.2.500.000 Rp. 2,320,000
X PEKERJAAN LAIN-LAIN Rp. 15,774,500
XI PEKERJAAN INSTALASI LISTRIK Rp. 6,820,000
TOTAL Rp. 318,338,705
TOTAL 16 UNIT Rp. 5,093,419,280
REKAPITULASI RENCANA ANGGARAN BIAYA (RAB)
16 Unit Blok N7 No. 6,7,8,9,10, 11, 12, 15, 16, 17, 18,19,20,21,22 & 23
I PEKERJAAN PERSIAPAN
1 Air Kerja Ls Rp. 1,000,000 Rp. 1,000,000
2 Mobilisasi / Demobilisasi Peralatan Ls Rp. 10,000,000 Rp. 10,000,000
3 Pengukuran / Bowplank 70.00 m3 Rp. 32,500 Rp. 2,275,000
4 Direksi Keet / Bedeng Ls Rp. 1,500,000 Rp. 1,500,000
II PEKERJAAN ROW 12
1 Galian tanah badan jalan / saluran 2,010.00 m3 Rp. 30,000 Rp. 60,300,000
2 Gelar Sirdam t=35cm 603.00 m3 Rp. 185,000 Rp. 111,555,000
3 Abu batu t=5cm 201.00 m3 Rp. 190,000 Rp. 38,190,000
4 Paving t=8cm 4,020.00 m2 Rp. 82,000 Rp. 329,640,000
5 Pemadatan 4,020.00 m2 Rp. 8,000 Rp. 32,160,000
6 Pasang saluran batu kali L=100cm 176.88 m3 Rp. 450,000 Rp. 79,596,000
7 Deuker Saluran Air 30.00 m' Rp. 650,000 Rp. 19,500,000
IV PEKERJAAN ROW 14
1 Galian tanah badan jalan / saluran 1,170.00 m3 Rp. 30,000 Rp. 35,100,000
2 Gelar Sirdam t=35cm 351.00 m3 Rp. 185,000 Rp. 64,935,000
3 Abu batu t=5cm 117.00 m3 Rp. 190,000 Rp. 22,230,000
4 Paving t=8cm 2,340.00 m2 Rp. 82,000 Rp. 191,880,000
5 Pemadatan 2,340.00 m2 Rp. 8,000 Rp. 18,720,000
6 Saluran batu kali L=100cm 79.20 m3 Rp. 450,000 Rp. 35,640,000
7 Deuker Saluran Air 24.00 m' Rp. 650,000 Rp. 15,600,000