F.
ANALISA HARGA SATUAN PEKERJAAN PLESTERAN
Analisa Harga Satuan Pekerjaan Plesteran
Sesuai SNI 2837:2008
HARGA
NO URAIAN SATUAN VOLUME HARGA (Rp)
SATUAN (Rp)
F-01 Membuat 1 m2 plesteran 1 PC : 1 PP, tebal 15 cm
Semen Portland kg 15.5040 1,269.98 19,689.69
Pasir pasang m3 0.0160 240,600.00 3,849.60
Pekerja Oh 0.3000 60,000.00 18,000.00
Tukang batu Oh 0.1500 75,000.00 11,250.00
Kepala tukang Oh 0.0150 100,000.00 1,500.00
Mandor Oh 0.0150 65,000.00 975.00
Jumlah 55,264.29
Overhead/Keuntungan Perusahaan (10%) 5,526.43
Jumlah Total 60,790.72
F-02 Membuat 1 m2 Plesteran 1 PC : 2 PS, tebal 15 mm
Semen Portland kg 10.2240 1,269.98 12,984.22
Pasir pasang m3 0.0200 240,600.00 4,812.00
Pekerja Oh 0.3000 60,000.00 18,000.00
Tukang Batu Oh 0.1500 75,000.00 11,250.00
Kepala Tukang Oh 0.0150 100,000.00 1,500.00
Mandor Oh 0.0150 65,000.00 975.00
Jumlah 49,521.22
Overhead/Keuntungan Perusahaan (10%) 4,952.12
Jumlah Total 54,473.35
e
F-03 Membuat 1 m2 Plesteran 1 PC : 3 PS, tebal 15 mm
Semen Portland kg 7.7760 1,269.98 9,875.33
Pasir Pasang m3 0.0230 240,600.00 5,533.80
Pekerja Oh 0.3000 60,000.00 18,000.00
Tukang Batu Oh 0.1500 75,000.00 11,250.00
Kepala Tukang Oh 0.0150 100,000.00 1,500.00
Mandor Oh 0.0150 65,000.00 975.00
Jumlah 47,134.13
Overhead/Keuntungan Perusahaan (10%) 4,713.41
Jumlah Total 51,847.54
F-04 Membuat 1 m2 Plesteran 1 PC : 4 PS, tebal 15 mm
Semen Portland kg 6.2400 1,269.98 7,924.64
Pasir Pasang m3 0.0240 240,600.00 5,774.40
Pekerja Oh 0.3000 60,000.00 18,000.00
Tukang Batu Oh 0.1500 75,000.00 11,250.00
Kepala Tukang Oh 0.0150 100,000.00 1,500.00
Mandor Oh 0.0150 65,000.00 975.00
Jumlah 45,424.04
Overhead/Keuntungan Perusahaan (10%) 4,542.40
Jumlah Total 49,966.45
F-05 Membuat 1 m2 Plesteran 1 PC : 5 PP, tebal 15 mm
Semen Portland kg 5.1840 1,269.98 6,583.55
Pasir Pasang m3 0.0260 240,600.00 6,255.60
Pekerja Oh 0.3000 60,000.00 18,000.00
Tukang Batu Oh 0.1500 75,000.00 11,250.00
Kepala Tukang Oh 0.0150 100,000.00 1,500.00
Mandor Oh 0.0150 65,000.00 975.00
Jumlah 44,564.15
Overhead/Keuntungan Perusahaan (10%) 4,456.42
Jumlah Total 49,020.57
Plesteran - Hal 1
F-06 Membuat 1 m2 Plesteran 1PC : 6 PP, tebal 15 mm
Semen Portland kg 4.4160 1,269.98 5,608.21
Pasir Pasang m3 0.0270 240,600.00 6,496.20
Pekerja Oh 0.3000 60,000.00 18,000.00
Tukang Batu Oh 0.1500 75,000.00 11,250.00
Kepala Tukang Oh 0.0150 100,000.00 1,500.00
Mandor Oh 0.0150 65,000.00 975.00
Jumlah 43,829.41
Overhead/Keuntungan Perusahaan (10%) 4,382.94
Jumlah Total 48,212.35
F-07 Membuat 1 m2 Plesteran 1 PC : 7 PP, tebal 15 mm
Semen Portland kg 3.9360 1,269.98 4,998.62
Pasir Pasang m3 0.0280 240,600.00 6,736.80
Pekerja Oh 0.3000 60,000.00 18,000.00
Tukang Batu Oh 0.1500 75,000.00 11,250.00
Kepala Tukang Oh 0.0150 100,000.00 1,500.00
Mandor Oh 0.0150 65,000.00 975.00
Jumlah 43,460.42
Overhead/Keuntungan Perusahaan (10%) 4,346.04
Jumlah Total 47,806.46
F-08 Membuat 1 m2 Plesteran 1 PC : 8 PP, tebal 15 mm
Semen Portland kg 3.4560 1,269.98 4,389.03
Pasir Pasang m3 0.0290 240,600.00 6,977.40
Pekerja Oh 0.3000 60,000.00 18,000.00
Tukang Batu Oh 0.1500 75,000.00 11,250.00
Kepala Tukang Oh 0.0150 100,000.00 1,500.00
Mandor Oh 0.0150 65,000.00 975.00
Jumlah 43,091.43
Overhead/Keuntungan Perusahaan (10%) 4,309.14
Jumlah Total 47,400.58
F-09 Membuat 1 m2 Plesteran 1 PC : 1/2 KP : 3 PP, tebal 15 mm
Semen Portland kg 5.7600 1,269.98 7,315.06
Kapur padam m3 0.0030 40,000.00 120.00
Pasir Pasang m3 0.1300 240,600.00 31,278.00
Pekerja Oh 0.3600 60,000.00 21,600.00
Tukang Batu Oh 0.1200 75,000.00 9,000.00
Kepala Tukang Oh 0.0120 100,000.00 1,200.00
Mandor Oh 0.0180 65,000.00 1,170.00
Jumlah 71,683.06
Overhead/Keuntungan Perusahaan (10%) 7,168.31
Jumlah Total 78,851.36
F-10 Membuat 1 m2 Plesteran 1 PC : 2 KP : 8 PP, tebal 15 mm
Semen Portland kg 3.0000 1,269.98 3,809.93
Kapur padam m3 0.0050 40,000.00 200.00
Pasir Pasang m3 0.0200 240,600.00 4,812.00
Pekerja Oh 0.3600 60,000.00 21,600.00
Tukang Batu Oh 0.1200 75,000.00 9,000.00
Kepala Tukang Oh 0.0120 100,000.00 1,200.00
Mandor Oh 0.0180 65,000.00 1,170.00
Jumlah 41,791.93
Overhead/Keuntungan Perusahaan (10%) 4,179.19
Jumlah Total 45,971.12
Plesteran - Hal 2
F-11 Membuat 1 m2 Plesteran 1 SM : 1 KP : 1 PP, tebal 15 mm
Semen merah m3 0.0090 330,000.00 2,970.00
Kapur Padam m3 0.0090 40,000.00 360.00
Pasir Pasang m3 0.0090 240,600.00 2,165.40
Pekerja Oh 0.3600 60,000.00 21,600.00
Tukang Batu Oh 0.1200 75,000.00 9,000.00
Kepala Tukang Oh 0.0120 100,000.00 1,200.00
Mandor Oh 0.0180 65,000.00 1,170.00
Jumlah 38,465.40
Overhead/Keuntungan Perusahaan (10%) 3,846.54
Jumlah Total 42,311.94
F-12 Membuat 1 m2 Plesteran 1 SM : 1 KP : 2 PP, tebal 15 mm
Semen merah m3 0.0070 330,000.00 2,310.00
Kapur Padam m3 0.0070 40,000.00 280.00
Pasir Pasang m3 0.0150 240,600.00 3,609.00
Pekerja Oh 0.3600 60,000.00 21,600.00
Tukang batu Oh 0.1200 75,000.00 9,000.00
Kepala Tukang Oh 0.0120 100,000.00 1,200.00
Mandor Oh 0.0180 65,000.00 1,170.00
Jumlah 39,169.00
Overhead/Keuntungan Perusahaan (10%) 3,916.90
Jumlah Total 43,085.90
F-13 Membuat 1 m2 Plesteran 1 PC : 2 PP, tebal 20 mm
Semen Portland kg 13.6320 1,269.98 17,312.30
Pasir Pasang m3 0.0270 240,600.00 6,496.20
Pekerja Oh 0.4000 60,000.00 24,000.00
Tukang Batu Oh 0.2000 75,000.00 15,000.00
Kepala Tukang Oh 0.0200 100,000.00 2,000.00
Mandor Oh 0.0220 65,000.00 1,430.00
Jumlah 66,238.50
Overhead/Keuntungan Perusahaan (10%) 6,623.85
Jumlah Total 72,862.35
F-14 Membuat 1 m2 Plesteran 1 PC : 3 PP, tebal 20 mm
Semen Portland kg 10.3680 1,269.98 13,167.10
Pasir Pasang m3 0.0310 240,600.00 7,458.60
Pekerja Oh 0.2600 60,000.00 15,600.00
Tukang Batu Oh 0.2000 75,000.00 15,000.00
Kepala Tukang Oh 0.0200 100,000.00 2,000.00
Mandor Oh 0.0130 65,000.00 845.00
Jumlah 54,070.70
Overhead/Keuntungan Perusahaan (10%) 5,407.07
Jumlah Total 59,477.77
F-15 Membuat 1 m2 Plesteran 1 PC : 4 PP, tebal 20 mm
Semen Portland kg 8.3200 1,269.98 10,566.19
Pasir Pasang m3 0.0320 240,600.00 7,699.20
Pekerja Oh 0.4000 60,000.00 24,000.00
Tukang Batu Oh 0.2000 75,000.00 15,000.00
Kepala Tukang Oh 0.0200 100,000.00 2,000.00
Mandor Oh 0.0220 65,000.00 1,430.00
Jumlah 60,695.39
Overhead/Keuntungan Perusahaan (10%) 6,069.54
Jumlah Total 66,764.93
Plesteran - Hal 3
F-16 Membuat 1 m2 Plesteran 1 PC : 5 PP, tebal 20 mm
Semen Portland kg 6.9120 1,269.98 8,778.07
Pasir Pasang m3 0.0350 240,600.00 8,421.00
Pekerja Oh 0.4000 60,000.00 24,000.00
Tukang Batu Oh 0.2000 75,000.00 15,000.00
Kepala Tukang Oh 0.0200 100,000.00 2,000.00
Mandor Oh 0.0220 65,000.00 1,430.00
Jumlah 59,629.07
Overhead/Keuntungan Perusahaan (10%) 5,962.91
Jumlah Total 65,591.97
F-17 Membuat 1 m2 Plesteran 1 PC : 6 PP, tebal 20 mm
Semen Portland kg 5.8880 1,269.98 7,477.61
Pasir Pasang m3 0.0360 240,600.00 8,661.60
Pekerja Oh 0.4000 60,000.00 24,000.00
Tukang Batu Oh 0.2000 75,000.00 15,000.00
Kepala Tukang Oh 0.0200 100,000.00 2,000.00
Mandor Oh 0.0220 65,000.00 1,430.00
Jumlah 58,569.21
Overhead/Keuntungan Perusahaan (10%) 5,856.92
Jumlah Total 64,426.13
F-18 Membuat 1 m2 Plesteran 1 SM : 1 KP : 2 PP, tebal 20 mm
Semen merah m3 0.0090 72,000.00 648.00
Kapur padam m3 0.0090 40,000.00 360.00
Pasir Pasang m3 0.0180 240,600.00 4,330.80
Pekerja Oh 0.4400 60,000.00 26,400.00
Tukang Batu Oh 0.2200 75,000.00 16,500.00
Kepala Tukang Oh 0.0220 100,000.00 2,200.00
Mandor Oh 0.0220 65,000.00 1,430.00
Jumlah 51,868.80
Overhead/Keuntungan Perusahaan (10%) 5,186.88
Jumlah Total 57,055.68
F-19 Membuat 1 m2 Berapen 1 PC : 5 PP, tebal 15 mm
Semen portland kg 5.1840 1,269.98 6,583.55
Pasir Pasang m3 0.0260 240,600.00 6,255.60
Pekerja Oh 0.1500 60,000.00 9,000.00
Tukang Batu Oh 0.0750 75,000.00 5,625.00
Kepala Tukang Oh 0.0080 100,000.00 800.00
Mandor Oh 0.0080 65,000.00 520.00
Jumlah 28,784.15
Overhead/Keuntungan Perusahaan (10%) 2,878.42
Jumlah Total 31,662.57
F-20 Membuat 1 m' Plesteran Skoning lebar 10 mm 1 PC : 2 PP
Semen portland kg 0.5000 1,269.98 634.99
Pasir Pasang m3 0.0130 240,600.00 3,127.80
Pekerja Oh 0.0800 60,000.00 4,800.00
Tukang Batu Oh 0.4000 75,000.00 30,000.00
Kepala Tukang Oh 0.0400 100,000.00 4,000.00
Mandor Oh 0.0040 65,000.00 260.00
Jumlah 42,822.79
Overhead/Keuntungan Perusahaan (10%) 4,282.28
Jumlah Total 47,105.07
Plesteran - Hal 4
F-21 Membuat 1 m2 Plesteran Granit, 1 PC : 2 Granit, tebal 10 mm
Semen portland kg 10.0000 1,269.98 12,699.75
Batu Granit kg 15.0000 4,290.00 64,350.00
Pekerja Oh 0.4500 60,000.00 27,000.00
Tukang Batu Oh 0.2250 75,000.00 16,875.00
Kepala Tukang Oh 0.0230 100,000.00 2,300.00
Mandor Oh 0.0230 65,000.00 1,495.00
Jumlah 124,719.75
Overhead/Keuntungan Perusahaan (10%) 12,471.98
Jumlah Total 137,191.73
F-22 Membuat 1 m2 Plesteran Teraso, 1 PC : 2 batu teraso, tebal 10 mm
Semen portland kg 10.0000 1,269.98 12,699.75
Batu Teraso kg 15.0000 2,640.00 39,600.00
Pekerja Oh 0.4500 60,000.00 27,000.00
Tukang Batu Oh 0.2250 75,000.00 16,875.00
Kepala Tukang Oh 0.0230 100,000.00 2,300.00
Mandor Oh 0.0230 65,000.00 1,495.00
Jumlah 99,969.75
Overhead/Keuntungan Perusahaan (10%) 9,996.98
Jumlah Total 109,966.73
F-23 Membuat 1 m2 Plesteran ciprat/kamprotan, 1 PC : 2 PP
Semen portland kg 4.3200 1,269.98 5,486.29
Pasir pasang m3 0.0060 240,600.00 1,443.60
Pekerja Oh 0.3000 60,000.00 18,000.00
Tukang Batu Oh 0.1000 75,000.00 7,500.00
Kepala Tukang Oh 0.0100 100,000.00 1,000.00
Mandor Oh 0.0150 65,000.00 975.00
Jumlah 34,404.89
Overhead/Keuntungan Perusahaan (10%) 3,440.49
Jumlah Total 37,845.38
F-24 Membuat 1 m2 Finishing siar pasangan dinding bata merah (=20 m')
Semen portland kg 3.1080 1,269.98 3,947.08
Pekerja Oh 0.1500 60,000.00 9,000.00
Tukang Batu Oh 0.0750 75,000.00 5,625.00
Kepala Tukang Oh 0.0080 100,000.00 800.00
Mandor Oh 0.0080 65,000.00 520.00
Jumlah 19,892.08
Overhead/Keuntungan Perusahaan (10%) 1,989.21
Jumlah Total 21,881.29
F-25 Membuat 1 m2 Finishing siar pasangan dinding conblock ekspos e (= 8 m')
Semen portland kg 1.6000 1,269.98 2,031.96
Pekerja Oh 0.0700 60,000.00 4,200.00
Tukang Batu Oh 0.0350 75,000.00 2,625.00
Kepala Tukang Oh 0.0040 100,000.00 400.00
Mandor Oh 0.0040 65,000.00 260.00
Jumlah 9,516.96
Overhead/Keuntungan Perusahaan (10%) 951.70
Jumlah Total 10,468.66
F-26 Membuat 1 m2 Finishing siar pasangan dinding batu kali adukan 1 PC : 2 PP
Semen portland kg 6.3400 1,269.98 8,051.64
Pasir pasang m3 0.0120 240,600.00 2,887.20
Pekerja Oh 0.3000 60,000.00 18,000.00
Tukang Batu Oh 0.1500 75,000.00 11,250.00
Kepala Tukang Oh 0.0150 100,000.00 1,500.00
Mandor Oh 0.0150 65,000.00 975.00
Jumlah 42,663.84
Overhead/Keuntungan Perusahaan (10%) 4,266.38
Jumlah Total 46,930.23
Plesteran - Hal 5
F-27 Membuat 1 m2 Acian
Semen portland kg 3.2500 1,269.98 4,127.42
Pekerja Oh 0.2000 60,000.00 12,000.00
Tukang Batu Oh 0.1000 75,000.00 7,500.00
Kepala Tukang Oh 0.0100 100,000.00 1,000.00
Mandor Oh 0.0100 65,000.00 650.00
Jumlah 25,277.42
Overhead/Keuntungan Perusahaan (10%) 2,527.74
Jumlah Total 27,805.16
F-28 Membuat 1 m2 Acian Semen Instan
Semen Instan kg 2.0000 2,328.15 4,656.30
Pekerja Oh 0.2000 60,000.00 12,000.00
Tukang Batu Oh 0.1000 75,000.00 7,500.00
Kepala Tukang Oh 0.0100 100,000.00 1,000.00
Mandor Oh 0.0100 65,000.00 650.00
Jumlah 25,806.30
Overhead/Keuntungan Perusahaan (10%) 2,580.63
Jumlah Total 28,386.93
F-24 Membuat 1 m Tali Air
Semen portland kg 0.4500 1,269.98 571.49
Pekerja Oh 0.1500 60,000.00 9,000.00
Tukang Batu Oh 0.0750 75,000.00 5,625.00
Kepala Tukang Oh 0.0080 100,000.00 800.00
Mandor Oh 0.0080 65,000.00 520.00
Jumlah 16,516.49
Overhead/Keuntungan Perusahaan (10%) 1,651.65
Jumlah Total 18,168.14
Manado, 31 Mei 2019
CV. DUA PUTRI NUSANTARA
BAMBANG KURNIADI BADERAN
Direktur
Plesteran - Hal 6