A. PEKERJAAN PERSIAPAN
Luas = P x L
1. Pembersihan Lahan = 21,5 m x 31,35 m
= 674,025 m²
Luas = P x L
2. Pembuatan Direksi Keet = 6,5 m x 8 m
= 52 m²
Panjang = P
3. Pembuatan Pagar Keliling
= 2150 m²
Luas = P x L
4. Gudang Bahan / Peralatan
= 5m x 5m = 25 m²
5. Pas. Bowplank Keliling = 94,3 m²
6. Listrik Penerangan 1 Ls
7. Air Kerja 1 Ls
B. PEKERJAAN TANAH
1. Pekerjaan galian tanah
Pondasi Footplat K1 Pondasi Footplat K1
Perhitungan Galian Pondasi Footplat
Jumlah (n) = 12 buah
Volume 1 = p x L x h x n
= 1,2 m x 1 m x 1,54 m x 12
= 22,176 m³
(1+1,6)
= 𝑥 1,1 𝑥 261,65
2
= 374,16 m³
(1+1,6)
= x 0,7 x 1,8
2
= 1,638 m³
= 3,507 m3
Volume galian total = V1 + V2 + V3 + V4 + V5
= (22,176 + 9,24 + 374,16 + 0,33 +
3,507) m³
= 409,41 m³
Keterangan :
P = Panjang pondasi (m)
L = Lebar pondasi (m)
h = Tinggi pondasi (m)
n = Jumlah titik
= 109,89 m3
VU1 = VG3 – Vp1 – VPS – VA
= (374,16 – 109,89 – 26,165 – 21,648) m³
= 216,4565 m³
(0,8+0,25)
VP = x 0,6 x 1,8
2
= 0,567 m3
VU2 = VG4 – VP – VPS2
= (1,738 – 0,567 – 0,18) m³
= 0,991 m³
Pondasi Footplat K1 Pondasi Footplat K1
VP = ((1 x 1,2 x 0,25) + (0,15 x 0,4 x 0,862)) x 12 titik
= 4,22 m3
VU3 = VG – VP
= 22,176 – 4,22
= 17,96 m3
= 1,61 m3
VU4 = VG – VP
= 9,24 – 1,61
= 7,63 m3
= 243,03 m3
Keterangan :
- VU = Volume urugan, m3
- VG = Volume galian, m3
- VP = Volume pondasi, m3
- VPS = Volume pasir, m3
- VA = Volume anstamping, m3
= 26,345 m3
= (p x l x t) x jumlah footplat K1
= 0,72 m3
= (p x l x t) x jumlah footplat K2
= (1 m x 1 m x 0,05 m) x 6 titik
= 0,3 m3
= 105,937 m2 x 0,2 m
= 21,187 m3
= 105,937 m2 x 0,07 m
= 7,41559 m3
Lantai 2
Volume Urugan Pasir di bawah lantai 2
V2 = Lb lt.2 x t
= 155,03 m2 x 0,05 m
= 7,7515 m3
Volume = V1 + V2
= (7,41559 + 7,7515 ) m3
= 15,1671 m3
Keterangan :
- Lb = Luas Bangunan, m2
- P = panjang,m
- l = Lebar,m
- h = Kedalaman, m
- t = tinggi, m
=8
Horizontal (Ø10 – 15)
Lebrar rencana
= jarak antar tulangan
100
= 15
=7
= 10
Horizontal (Ø16 – 12)
Lebrar rencana
= jarak antar tulangan
100
= 12
=9
Total Penulangan
= 11,78 kg + 38,22 kg
= 50 kg
Volume Penulangan K1
= Total Penulangan x jumlah K1
b. Footplat K2
= 50 kg x 12 unit
= 600 kg
=7
Horizontal (Ø12 – 15)
Lebrar rencana
= jarak antar tulangan
100
= 15
=7
=7
Horizontal (Ø12 – 15)
Lebrar rencana
= jarak antar tulangan
100
= 15
=7
Total Penulangan
= 10,19 kg + 14,67 kg
= 24,86 kg
Volume Penulangan K2
= Total Penulangan x jumlah K1
= 25,86 kg x 6 unit
= 149,18 kg
2. Pekerjaan Tulangan Sloof 15/20
2. Volume Sloof 1
V = Lp x P
Pekerjaan Sloof 1 = (0,25 m x 0,4 m) x 120,45 m
= 12,045 m³
3.
Volume Kolom (13x40)
V = Lp x b x n
Pekerjaan Kolom (13 x 40)
= (0,13 x 0,4) m² x 3,5 m x 5
= 0,91 m³