KEMENTERIAN PEKERJAAN UMUM & PERUMAHAN RAKYAT

DIREKTORAT JENDERAL BINA MARGA


BALAI BESAR PELAKSANAAN JALAN NASIONAL VI MAKASSAR
SATKER PELAKSANAAN JALAN NASIONAL WILAYAH I PROP. SULAWESI TENGGARA ( BARAT )

LAPORAN MINGGUAN
SATUAN KERJA : PELAKSANAAN JALAN NASIONAL WILAYAH I PROVINSI SULAWESI TENGGARA (BARAT)
NAMA PAKET
N0./NAMA RUAS
:
:
PELEBARAN JALAN LASUSUA-BTS. KAB. KOLAKA-WOLO (MYC)
004 & 005 / LASUSUA-BTS. KAB. KOLAKA UTARA/KAB. KOLAKA-WOLO
WEEK 75
PROP/KAB/KODYA : PROVINSI SULAWESI TENGGARA January 16, 2017
PERIODE :
SUMBER DANA : APBN January 22, 2017
TAHUN ANGGARAN : 2015 - 2017

ADD - 01 MINGGU S/D


NO. MINGGU INI
URAIAN HARGA BOBOT (%) LALU MINGGU INI KETERANGAN
DIVISI (%)
PER DIVISI (%) (%)
1 Umum 2.330.110.000,00 2,057 1,485 - 1,485
2 Drainase 5.688.064.851,54 5,021 3,490 0,038 3,528
3 Pekerjaan Tanah 18.310.051.053,87 16,164 13,080 0,134 13,214
4 Pelebaran Perkerasan dan Bahu Jalan 2.780.052.334,09 2,454 - - -
5 Perkerasan Berbutir 26.336.235.434,58 23,250 14,638 0,246 14,884
6 Perkerasan Aspal 51.699.714.987,10 45,641 22,161 1,353 23,514
7 Struktur 3.561.287.824,68 3,144 1,121 - 1,121
8 Pengembalian Kondisi dan Pekerjaan Minor 2.409.970.568,68 2,128 - - -
9 Pekerjaan Harian - - - - -
10 Pekerjaan Pemeliharaan Rutin 159.000.000,00 0,140 0,084 - 0,084

(A) Sum of Division 1 to 10 (including overhead and profit) 113.274.487.054,55 100,000 56,059 1,771 57,830
(B) Value Added Tax ( PPn ) = 10% x (A) 11.327.448.705,45 REAL PROGRESS : 57,830
(C) TOTAL BID PRICE = (A) + (B) 124.601.935.760,00 SCHEDULE PROGRESS : 58,625
DEVIASI : -0,795

Dibuat,

Surya Firmansyah
Engineering