RENCANA ANGGARAN BIAYA

(RAB)

Kegiatan : Peningkatan Sarana Dan Prasarana UPT Pelatihan Perikanan Dan Kelautan

Pekerjaan : Betonisasi Kolam Pembesaran

Lokasi : Instalasi Pelatihan Budidaya Air Tawar - Rumbai

NO URAIAN PEKERJAAN

A PERSIAPAN
B PEKERJAAN GALIAN KOLAM

C PEKERJAAN KOLAM

D PEKERJAAN JALAN SEMENISASI

E PEKERJAAN LAIN-LAIN

JUMLAH

PPN 10%

JUMLAH TOTAL

DIBULATKAN

Terbilang :

Empat Ratus Delapan Belas Juta Dua Ratus Empat Puluh Empat Ribu Rupiah

Pekanbaru, 05 September 2012


CV. DANI ANUGRAH

LAMTIUR FEBRIOS
Direktur
RENCANA ANGGARAN BIAYA

(RAB)

Sarana Dan Prasarana UPT Pelatihan Perikanan Dan Kelautan

JUMLAH HARGA

7,250,000.00
113,059,710.62

228,473,409.33

21,938,832.00

9,500,000.00

380,221,951.94

38,022,195.19

418,244,147.13

418,244,000.00

Delapan Belas Juta Dua Ratus Empat Puluh Empat Ribu Rupiah

Pekanbaru, 05 September 2012


CV. DANI ANUGRAH

LAMTIUR FEBRIOS
Direktur
RENCANA ANGGARAN BIAYA

Kegiatan : Peningkatan Sarana Dan Prasarana UPT Pelatihan Perikanan Dan Kelautan
Pekerjaan : Betonisasi Kolam Pembesaran
Lokasi : Instalasi Pelatihan Budidaya Air Tawar - Rumbai

NO URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH HARGA

I II III IV V

A PERSIAPAN 7,250,000.00
1 Pembersihan Lokasi 1.000 Ls 2,500,000.00 2,500,000.00
2 Pas. Papan nama proyek 1.000 LS 750,000.00 750,000.00
3 Pengurasan air kolam 1.000 Ls 4,000,000.00 4,000,000.00

B PEKERJAAN GALIAN KOLAM 113,059,710.62


1 Moblisasi alat berat 1.000 Ls 6,500,000.00 6,500,000.00
2 Pek. Galian tanah kolam dengan alat berat 580.791 M3 133,598.33 77,592,709.62
3 Timbunan tanah bekas galian 290.396 M3 99,750.00 28,967,001.00

C PEKERJAAN KOLAM 228,473,409.33


1 Pengukuran dan pasangan bouwplank 144.000 M1 59,025.00 8,499,600.00
2 Penggalian Tanah Pondasi 8.875 M3 31,800.00 282,225.00
3 Pas. Pondasi cerocok 355.000 Btg 99,750.00 35,411,250.00
4 Pek. Pasir Urug Bawah Pondasi 1.420 M3 165,950.00 235,649.00
5 Pek. Cor Pondasi Setapak 1:2:3 5.325 M3 5,106,025.00 27,189,583.13
6 Pek. Cor sloof 15/20 ad. 1:2:3 4.320 M3 4,362,190.00 18,844,660.80
7 Pek. Urugan Tanah Kembali 6.656 M3 99,750.00 663,936.00
8 Pek. Cor kolom 15/15 ad. 1 : 2 : 3 3.911 M3 5,744,200.00 22,465,566.20
9 Pek. Dinding T.12cm ad. 1:2:3 25.920 M3 4,432,135.00 114,880,939.20

D PEKERJAAN JALAN SEMENISASI 21,938,832.00


1 Pas. Bouwplank 144.000 M1 59,025.00 8,499,600.00
2 Pas. Pasir urug t. 5cm 11.520 M3 165,950.00 1,911,744.00
3 Pek. Cor jalan beton 1:3:5 T.12cm 17.280 M3 667,100.00 11,527,488.00

E PEKERJAAN LAIN-LAIN 9,500,000.00


1 Instalasi inlet & outlet PVC 6" 1.000 Ls 5,500,000.00 5,500,000.00
2 Pembersihan akhir 1.000 Ls 4,000,000.00 4,000,000.00
I II III IV V

J U M LA H T O T A L 380,221,951.94
DAFTAR ANALISA HARGA SATUAN

Kegiatan : Peningkatan Sarana Dan Prasarana UPT Pelatihan Perikanan Dan Kelautan
Pekerjaan : Betonisasi Kolam Pembesaran
Lokasi : Instalasi Pelatihan Budidaya Air Tawar - Rumbai

HARGA JUMLAH
HRG. SATUAN
NO. URAIAN UPAH BAHAN HARGA
( Rp )
( Rp ) ( Rp ) ( Rp )
I II III IV V VI

1 Pembersihan Lapangan tiap 10 m2

0.750 Pekerja 70,000.00 52,500.00

0.020 Mandor 95,000.00 1,900.00

Jumlah 54,400.00 54,400.00

Untuk 1 M2 5,440.00

Dibulatkan 5,440.00

2 Pasangan Bowplank tiap 1 M'

0.100 Tukang kayu 85,000.00 8,500.00

0.010 Kepala tukang kayu 90,000.00 900.00

0.100 Pekerja 70,000.00 7,000.00

0.005 Mandor 95,000.00 475.00

0.007 M3 papan meranti klas IIII 2,100,000.00 14,700.00

0.012 M3 Kayu meranti 5/7 2,100,000.00 25,200.00

0.150 Kg Paku 15,000.00 2,250.00

Jumlah 16,875.00 42,150.00 59,025.00

Dibulatkan 59,025.00

3 Galian Tanah Biasa Pondasi/ M3

0.400 Pekerja 70,000.00 28,000.00

0.040 Mandor 95,000.00 3,800.00

Jumlah 31,800.00 31,800.00

Dibulatkan 31,800.00

4 1 m3 Pek. Galian Tanah Biasa dengan alat berat

0.625 Oh Perkerja 70,000.00 43,750.00

0.313 Oh Tukang Gali 85,000.00 26,562.50

0.156 Oh Kepala Tukang 90,000.00 14,062.50

0.062 Oh Mandor 95,000.00 5,890.00

0.067 jam alat bantu excavator 650,000.00 43,333.33

Jumlah 133,598.33 133,598.33

Dibulatkan 133,598.33
I II III IV V VI

5 Urugan Tanah Dipadatkan / M3

0.5000 Pekerja 70,000.00 35,000.00

0.0500 Mandor 95,000.00 4,750.00

1.000 M3 Tanah urug 60,000.00 60,000.00

Jumlah 39,750.00 60,000.00 99,750.00

Dibulatkan 99,750.00
I II III IV V VI
6 Urugan Pasir Bawah Lantai / M3

0.300 Pekerja 70,000.00 21,000.00

0.010 Mandor 95,000.00 950.00

1.200 M3 Pasir Urug 120,000.00 144,000.00

Jumlah 21,950.00 144,000.00 165,950.00

Dibulatkan 165,950.00

7 Stamp Beton Spesi 1 : 2 : 3 / M3

1.6500 Pekerja 70,000.00 115,500.00

0.0800 Mandor 95,000.00 7,600.00

0.2500 Tukang Batu 85,000.00 21,250.00

0.0250 Kepala Tukang batu 90,000.00 2,250.00

4.6400 Zak Semen ( 50 Kg ) 60,000.00 278,400.00

0.5200 M3 Pasir Beton 180,000.00 93,600.00

0.7800 M3 Kerikil Cor 190,000.00 148,200.00

Jumlah 146,600.00 520,200.00 666,800.00

Dibulatkan 666,800.00

8 Stamp Beton Spesi 1 : 3 : 5 / M3

1.6500 Pekerja 70,000.00 115,500.00

0.0800 Mandor 95,000.00 7,600.00

0.2500 Tukang Batu 85,000.00 21,250.00

0.0250 Kepala Tukang batu 90,000.00 2,250.00

4.3600 Zak Semen ( 50 Kg ) 60,000.00 261,600.00

0.5200 M3 Pasir Beton 180,000.00 93,600.00

0.8700 M3 Kerikil Cor 190,000.00 165,300.00

Jumlah 146,600.00 520,500.00 667,100.00

Dibulatkan 667,100.00

9 1 m³ Membuat Dinding Beton Bertulang ad. 1:2:3( 110 Kg + bekisting )

0.240 m3 Kayu Terentang 2,100,000.00 504,000.00

3.200 Kg Paku Biasa 2" - 5" 15,000.00 48,000.00

1.600 Lt Minyak Bekisting 15,000.00 24,000.00

110.000 Kg Besi Beton Polos 10,000.00 1,100,000.00

2.250 Kg Kawat Beton 20,000.00 45,000.00

6.460 Zak Semen Portland 60,000.00 387,600.00

0.520 m3 Pasir Beton 180,000.00 93,600.00

0.780 m3 Kerikil 190,000.00 148,200.00

0.160 m3 Kayu Balok 2,100,000.00 336,000.00

2.800 lbr Plywood 9 mm 170,000.00 476,000.00

24.000 btg Dolken Ø 8 / 4 m 20,000.00 480,000.00

5.600 Oh Perkerja 70,000.00 392,000.00

0.350 Oh Tukang Batu 85,000.00 29,750.00


I II III IV V VI
2.640 Oh Tukang Kayu 85,000.00 224,400.00

1.050 Oh Tukang Besi 85,000.00 89,250.00

0.400 Oh Kepala Tukang 90,000.00 36,000.00

0.193 Oh Mandor 95,000.00 18,335.00

Jumlah 789,735.00 3,642,400.00 4,432,135.00

Dibulatkan 4,432,135.00

10 1 m³ Membuat Sloof 15/20 Beton Bertulang ad. 1:2:3 ( 140 Kg + bekisting )

0.270 m3 Kayu Terentang 2,100,000.00 567,000.00

2.000 Kg Paku Biasa 2" - 5" 15,000.00 30,000.00


I II III IV V VI
0.600 Lt Minyak Bekisting 15,000.00 9,000.00

240.000 Kg Besi Beton Polos 10,000.00 2,400,000.00

3.000 Kg Kawat Beton 20,000.00 60,000.00

6.460 Kg Semen Portland 60,000.00 387,600.00

0.520 m3 Pasir Beton 180,000.00 93,600.00

0.780 m3 Kerikil 190,000.00 148,200.00

4.850 Oh Perkerja 70,000.00 339,500.00

0.350 Oh Tukang Batu 85,000.00 29,750.00

1.560 Oh Tukang Kayu 85,000.00 132,600.00

1.400 Oh Tukang Besi 85,000.00 119,000.00

0.331 Oh Kepala Tukang 90,000.00 29,790.00

0.170 Oh Mandor 95,000.00 16,150.00

Jumlah 666,790.00 3,695,400.00 4,362,190.00

Dibulatkan 4,362,190.00

11 1 m³ Membuat Kolom 15/15 Beton Bertulang ad. 1:2:3 ( 175 Kg + bekisting )

0.400 m3 Kayu Terentang 2,100,000.00 840,000.00

4.000 Kg Paku Biasa 2" - 5" 15,000.00 60,000.00

2.000 Lt Minyak Bekisting 15,000.00 30,000.00

175.000 Kg Besi Beton Polos 10,000.00 1,750,000.00

2.500 Kg Kawat Beton 20,000.00 50,000.00

6.460 Kg Semen Portland 60,000.00 387,600.00

0.520 m3 Pasir Beton 180,000.00 93,600.00

0.780 m3 Kerikil 190,000.00 148,200.00

0.150 m3 Kayu Balok 2,100,000.00 315,000.00

3.500 lbr Plywood 9 mm 170,000.00 595,000.00

20.000 btg Dolken Ø 8 / 4 m 20,000.00 400,000.00

7.300 Oh Perkerja 70,000.00 511,000.00

0.350 Oh Tukang Batu 85,000.00 29,750.00

3.300 Oh Tukang Kayu 85,000.00 280,500.00

2.100 Oh Tukang Besi 85,000.00 178,500.00

0.570 Oh Kepala Tukang 90,000.00 51,300.00

0.250 Oh Mandor 95,000.00 23,750.00

Jumlah 1,074,800.00 4,669,400.00 5,744,200.00

Dibulatkan 5,744,200.00

12 1 m³ Membuat Pondasi Beton Bertulang ( 340 Kg + bekisting )

0.200 m3 Kayu Terentang 2,100,000.00 420,000.00

1.500 Kg Paku Biasa 2" - 5" 15,000.00 22,500.00

0.400 Lt Minyak Bekisting 15,000.00 6,000.00

340.000 Kg Besi Beton Polos 10,000.00 3,400,000.00

5.500 Kg Kawat Beton 20,000.00 110,000.00

6.460 Kg Semen Portland 60,000.00 387,600.00


I II III IV V VI
0.520 m3 Pasir Beton 180,000.00 93,600.00

0.780 m3 Kerikil 190,000.00 148,200.00

3.900 Oh Perkerja 70,000.00 273,000.00

0.350 Oh Tukang Batu 85,000.00 29,750.00

1.040 Oh Tukang Kayu 85,000.00 88,400.00

1.050 Oh Tukang Besi 85,000.00 89,250.00

0.245 Oh Kepala Tukang 90,000.00 22,050.00

0.165 Oh Mandor 95,000.00 15,675.00

Jumlah 518,125.00 4,587,900.00 5,106,025.00

Dibulatkan 5,106,025.00
I II III IV V VI
13 Memasang Tiang Pancang Cerocok/Btg

0.200 Pekerja 70,000.00 14,000.00

0.200 Tukang Kayu 85,000.00 17,000.00

0.020 Kepala Tukang 90,000.00 1,800.00

0.010 Mandor 95,000.00 950.00

1.000 Btg Kayu cerocok 40,000.00 40,000.00

1.300 Alat bantu 20,000.00 26,000.00

Jumlah 33,750.00 66,000.00 99,750.00

Dibulatkan 99,750.00
DAFTAR HARGA SATUAN BAHAN DAN UPAH

Kegiatan : Peningkatan Sarana Dan Prasarana UPT Pelatihan Perikanan Dan Kelautan

Pekerjaan : Betonisasi Kolam Pembesaran


Lokasi : Instalasi Pelatihan Budidaya Air Tawar - Rumbai

SATUAN HARGA SATUAN


NO URAIAN KET
(Rp) (Rp)

1 2 3 4 5

I. UPAH
1 Kepala Tukang Hari 90,000.00
2 Tukang Hari 85,000.00
3 Pekerja Hari 70,000.00
4 Mandor Hari 95,000.00
5 Sewa Exscavator Jam 650,000.00

II. BAHAN BANGUNAN


A. BAHAN PASANGAN
1 Tanah Urug M3 60,000.00
2 Pasir Urug M3 120,000.00
3 Pasir Pasang M3 130,000.00
4 Pasir Cor/beton M3 180,000.00
5 Kerikil M3 190,000.00
6 Portland Cemen type I Zak/50 Kg 60,000.00

B. BAHAN KAYU
1 Kayu Klas I M3 4,000,000.00
2 Kayu Klas II M3 2,500,000.00
3 Kayu Klas III M3 2,100,000.00
4 Kayu Balok M3 2,100,000.00
5 Kayu dolken Btg 20,000.00
6 Kayu cerocok Btg 40,000.00
7 Plywood 9mm Lbr 170,000.00

C. BAHAN BESI/ BAJA, PAKU


1 Besi beton polos Kg 10,000.00
2 Kawat ikat beton Kg 20,000.00
3 Paku biasa Kg 15,000.00
4 Paku seri/triplek Kg 20,000.00
5 Minyak bekisting Ltr 15,000.00
1 2 3 4 5

15 Floordrain Buah .
JADWAL PELAKSANAAN PEKERJAAN

JANGKA WAKTU PELAKSANAAN 90 HK

NO. Bobot BULAN I BULAN II BULAN III PERSENTASE KET.

(%) 1 2 3 4 1 2 3 4 1 2 3 4

A PERSIAPAN

1 Pembersihan Lokasi 0.658 0.658


100.00
2 Pas. Papan nama proyek 0.197 0.197
RENCANA
3 Pengurasan air kolam 1.052 1.052

B PEKERJAAN GALIAN KOLAM


90.00

1 Moblisasi alat berat 1.710 1.710

2 Pek. Galian tanah kolam dengan alat berat 20.407 20.41

3 Timbunan tanah bekas galian 7.618 7.618 80.00

C PEKERJAAN KOLAM

1 Pengukuran dan pasangan bouwplank 2.235 2.235 70.00


2 Penggalian Tanah Pondasi 0.074 0.074

3 Pas. Pondasi cerocok 9.313 4.657 4.657

4 Pek. Pasir Urug Bawah Pondasi 0.062 0.062


60.00
5 Pek. Cor Pondasi Setapak 1:2:3 7.151 3.575 3.575

6 Pek. Cor sloof 15/20 ad. 1:2:3 4.956 2.478 2.478

7 Pek. Urugan Tanah Kembali 0.175 0.087 0.087


50.00
8 Pek. Cor kolom 15/15 ad. 1 : 2 : 3 5.909 2.954 2.954

9 Pek. Dinding T.12cm ad. 1:2:3 30.214 10.071 10.071 10.071

40.00
D PEKERJAAN JALAN SEMENISASI

1 Pas. Bouwplank 2.235 2.235

2 Pas. Pasir urug t. 5cm 0.503 0.503


30.00
3 Pek. Cor jalan beton 1:3:5 T.12cm 3.032 1.516 1.516

E PEKERJAAN LAIN-LAIN

1 Instalasi inlet & outlet PVC 6" 1.447 1.447 20.00


2 Pembersihan akhir 1.052 1.052

100.00 10.00
RENCANA PERMINGGU 26.33 12.28 8.29 6.14 5.52 13.03 10.07 11.52 2.74 1.52 1.52 1.05

KUMULATIF PERMINGGU 26.33 38.61 46.90 53.04 58.56 71.59 81.66 93.18 95.92 97.43 98.95 100.0

-
Pekanbaru, 05 September 2012
CV. DANI ANUGRAH

LAMTIUR FEBRIOS
Direktur