PROYEK SPAM UMBULAN

MINUTES OF MEETING Minutes No. : 39 Page : 1

Location of Meeting: Date of Meeting: Written by: Date of Report:


Ruang Meeting 04 November 2019 Fajry Widyanto 04 November 2019
Meta Surabaya Lt.2
Pekerjaan Pemasangan Pipa Transmisi SPAM Umbulan Fase 2 Paket 1 Sepanjang 26,9 Km
Distribution : All Attendances
Agenda of Meeting: KSO Pendayagunaan Air Umbulan (KSO – PAU)
Weekly Meeting-37

Attachment:
1. Attendance List

Signature: Jusman A. Rahim


Date: 04 November 2019

PT. Brantas Abipraya (Persero)

Signature: Fajry Widyanto, S.T.


Date: 04 November 2019

No. DISCUSSION ACTION BY STATUS


A GENERAL

A.1 KSO-PAU sudah melakukan kontrak dengan PT.Delameta KSO-PAU INFO

Pekerjaan perbaikan yang masih belum dikerjaan


1. Perbaikan Saluran di Rest area
A.2 BA OPEN
2. Jalan Aspal Sidogiri
3. Guardrill Toll Gempas
Proses Adminstrasi
1. Asbulid Drawing VGF 2 dan VGF 3
2. Data test beton RM Gempol
A.4 3. Data pekerjaan tambah kurang untuk proses final addendum BA OPEN

Proses Adminstrasi Adedendum data di submit pada tanggal 04 November 2019 oleh PT.BA, dan akan di koreksi selama 2 hari oleh tim teknis
A.5 BA OPEN
KSO-PAU

A.6